JPS5850232A - Construction of concrete beam in building structure - Google Patents

Construction of concrete beam in building structure

Info

Publication number
JPS5850232A
JPS5850232A JP15013581A JP15013581A JPS5850232A JP S5850232 A JPS5850232 A JP S5850232A JP 15013581 A JP15013581 A JP 15013581A JP 15013581 A JP15013581 A JP 15013581A JP S5850232 A JPS5850232 A JP S5850232A
Authority
JP
Japan
Prior art keywords
formwork
column
concrete
construction
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP15013581A
Other languages
Japanese (ja)
Inventor
明 落合
下村 英男
竹内 洋一郎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP15013581A priority Critical patent/JPS5850232A/en
Publication of JPS5850232A publication Critical patent/JPS5850232A/en
Pending legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】[Detailed description of the invention]

この発明は建築構造物におけるコンクリート梁の構築法
に関Tるものである。 一般に、llIl図に示すような、柱lの上部に梁8を
業は渡しtなる鉄筋コンクリ−F造の建築構造4!Fを
構築Tる場合、まず型枠((2)示せず)をセットし1
次いでこの型枠内にコンクリート
This invention relates to a method of constructing concrete beams in building structures. In general, a reinforced concrete F building structure 4 where a beam 8 is connected to the top of a column t is shown in Figure llIl. When constructing F, first set the formwork ((2) not shown) and
Concrete is then poured into this formwork.

【打設して柱lおよび
梁Brt同時に構築している。ここで、梁2a分−ro
 m粋については、1本の柱lによる1点支持になるた
め、柱1m分の他に途中複数箇所に型枠および打設コン
クリートの重みに耐え得るようサポートを設ける必要が
ある。特に、大型のJP−参票角程度の梁を構築しよう
とする際には、大量の乗用打設コンクリートIざだえる
ために、かなり強固に型枠を保持Tる必要かあり、途中
のサポートは不可欠のものといえる・ところで、火力発
1所のタービン架台のように超大型架mt−構築Tる場
合、工程的な要求から、タービンの下階つまりタービン
架台の下&−復水器等の機器【、タービン架台の梁W:
s簗する前に、設置しなけれはならない場合がある。そ
のような場合、前記の梁の型枠については1そのサポー
トな柱間にとることかできないという問題かある。 この発明は上記事情に鑑みてなされたもので、コ不の柱
間に梁な架は渡してなる建築−遺物の梁を構築するにあ
たり、先にある程度構築した1柱以外に梁の型枠のサポ
ー)1W記1柱の間にとる必斐がなく1梁【後から構築
するという工程1つまり先に梁す分の下に機器を設置し
後から梁【構築Tるという工程を選択できる建築構造物
におけるコンクリ−塾梁の構築法【IM供Tること憂目
的とTるものである。 この発明の特徴は、まず柱e構築し、一方梁の型枠を所
定の強度をもつよう鋼板塾により製作して、梁型枠t−
1本の柱の間に架は渡して梁型枠の両1lalTt柱上
部に固定し、これら2本の柱によって梁型枠12点支持
しながら梁のコンクリート【打設し、その後梁型枠【梁
−造の一部として残すようにした点にある〇 以下、この発明を図面な参照して説明Tる〇第一図はこ
の発明の一実施例な示Tもので1柱11の上部図面に、
後述する梁型枠IBを取り付けるための梁型枠接合&1
8rt形成して、各柱11t−檎築Tる。この場合、梁
型枠接合1>18は、鉄板【巻き付けた構造のもので、
鉄板の内面にジベルを取り付けて、柱11のコンクリー
トを打設Tることにより、柱と一体的になるようにした
ものである。こうして、柱11を梁の下端位置まで構築
しておく。 一方、梁型枠12については1これrt第3図に示Tよ
うに鉄板14および補強材15により、所定の強度をも
つように瓢作Tる。こQ」場合、型枠の形状は梁の形状
に対応させて断面略U字状4I:Tる。また、補強材1
5は梁型枠1Bの内部に設ける。そして、この梁型枠1
salJ本の柱11(他の1本は図示せず)の上部に架
は渡して梁型枠1Bの両1s−を、それぞれの柱1.1
に設けた梁型枠接合ff118c接合する。接合の方決
としては、両者が#I411であることから、溶接で行
なったり、あるいはアングル部材等を用いてボルトによ
って接合したりする。このようにして型枠1m’、一本
の柱11によって一点支持するわけであるから、梁型枠
1sには自身の荷重に加えてコンクリ−)な打設した時
の全荷重に耐え得るだけの所定の強度をもたせる。 ここで182図に示Tものは1梁の十字交叉1分であり
、この場合、各#型枠12をそれぞれセットした後、柱
11の頭部eも梁と同時に構築するよう&:梁創枠18
同士の該間な二点鎖麹に示T型枠16により埋める。 そして、梁型枠ta内に鉄筋(図示せず)をセットし、
次いで梁型枠12内にコンクリ−)を打設して梁t−榊
築する。これらの作業をTるに際しては、梁梨枠Is内
に補強材15を設けであるため、これら補強材15t−
足場として利用することができる。このことは、本案か
特に超大型構造物の梁(たとえば3〜亭票角の梁)を構
築Tるのに適用多であることから、施工な大巾に簡略化
でき有効である。なお、鉄筋の組み付けについて番は、
梁型枠l5art製作Tる際に同時に先細みTることも
でき、現地施工手間【軽減Tることもできる。 このようにして、コンクリート梁【構築した後、梁型枠
138はそのtまl#構造の−bとして残T。 従って1梁の設計段階において、型枠の強度を梁の強度
の一部としてあらかじめ組み入れておくこともでき、梁
寸法の小形化、およびそれによるコンクリートおよび鉄
筋の減量化を図れるものである◎ なお1上記−実施例においては、梁型枠として鋼製のも
の【用いた場合について述べたか、梁型枠の材質として
、コンクリートあるいはプラスチック等管用いてもよい
。 また1上記実施例においては、柱11の上部に鉄板を看
いて梁型枠接合部18t1111成したか−これに限ら
れず、たとえば島参図に示Tよう&:llI4材17を
柱11の側面部に単数あるいはIII数理設して前記接
合部18を構成してもよい・この場合、鋼材17として
図のようにT字形#AあるいはH形鋼等各種のものか利
用できるか、要は、型枠12を接合Tるための鋼製部材
【柱11の上部に取り付ければよく、こうTることによ
り型枠2の接合【容易にしかも強固に行なえるようにす
ることである。tた、この支持&1Bの鉄板巻き管柱1
.1の上部に限らず、柱11の全長に亘って行なうよう
にし、これで柱11の型枠を兼用TるようにTれ4f、
この型枠自体を柱11の一島とすることも゛でき1鋤度
設計にも組み込み、柱11を鉄骨鉄筋コンクリート造(
充填角形鋼管コンクリート造)&:Tることもできる。 また、上記実施例においては、柱11として角形のもの
について述べたが、丸形等の形状としてもよい。 以上説明したように、この発明によれば−まず柱rt構
築し、一方所定の強度をもつように製゛作された梁型枠
eJ本の柱の間に架は渡して梁型枠の両端を柱上乱に固
定し、これらコ本の柱によって梁型枠を1点支持して、
コンクリート【打設し1梁型枠自体【梁構造の−りとし
て残留せしめるというものであるから、前記コ柱以外&
:@型枠のサポートなこれらコ柱の間に設ける必要がな
く、梁【後から構築Tるという工程、つまり先&:梁i
分の下に機器を設置して後から梁な構築するという工程
がとれるものである。また、型枠を架構造Q】−mとし
て残すことにより、梁強度をアップさせることかでき、
従って梁自体の寸法を小8〈でき、コンクリートおよび
鉄筋の量を減らTこともできるO
[Column L and beam Brt are constructed at the same time by pouring. Here, beam 2a - ro
As for M-I, it is supported at one point by one column L, so in addition to the 1-meter column, it is necessary to provide supports at multiple locations along the way to withstand the weight of the formwork and poured concrete. In particular, when trying to construct a large beam with the same size as a JP standard, it is necessary to hold the formwork quite firmly in order to handle a large amount of poured concrete. By the way, when constructing an extremely large frame such as a turbine frame for a single thermal power plant, due to process requirements, the lower floor of the turbine, that is, the bottom of the turbine frame and the condenser etc. equipment [, beam W of turbine mount:
It may be necessary to install it before using it. In such a case, there is a problem in that the formwork for the beam mentioned above cannot be used except for the spaces between the supporting pillars. This invention was made in view of the above-mentioned circumstances, and when constructing the beam of an architectural relic in which a beam frame is passed between the pillars of the pillars, the formwork of the beam is placed in addition to the one pillar that has been constructed to some extent. Support) 1W Note: 1 beam is not required to be installed between the pillars, and the process of building it later (1) is the process of installing equipment under the beam first, and building the beam later. Method of constructing concrete beams in structures. The feature of this invention is that the column e is first constructed, and then the beam formwork is manufactured by a steel plate school to have a predetermined strength.
The frame is passed between one pillar and fixed to the top of both 1lalTt pillars of the beam formwork, and while supporting the beam formwork at 12 points with these two pillars, the beam concrete is poured, and then the beam formwork is poured. Hereinafter, this invention will be explained with reference to the drawings. Figure 1 shows an embodiment of this invention, and shows the upper part of one column 11. To,
Beam formwork connection &1 for installing beam formwork IB described later
8rt is formed, and each pillar is 11t-shaped. In this case, the beam formwork joint 1>18 is a steel plate [wrapped structure]
By attaching a dowel to the inner surface of the iron plate and pouring concrete for the column 11, it becomes integral with the column. In this way, the pillar 11 is constructed up to the lower end position of the beam. On the other hand, the beam form 12 is made of iron plate 14 and reinforcing material 15 as shown in FIG. 3 so as to have a predetermined strength. In this case, the shape of the formwork corresponds to the shape of the beam and has a substantially U-shaped cross section (4I:T). In addition, reinforcement material 1
5 is provided inside the beam formwork 1B. And this beam formwork 1
The frame is passed over the top of the columns 11 (the other one is not shown), and both 1s- of the beam formwork 1B are attached to each column 1.1.
Beam formwork joint ff118c provided at. As for the method of joining, since both are #I411, they may be joined by welding or by bolts using angle members or the like. In this way, the formwork 1m' is supported at one point by one pillar 11, so the beam formwork 1s has enough capacity to withstand its own load as well as the full load when concrete is poured. to have a predetermined strength. Here, the T shown in Fig. 182 is one cross-section of one beam, and in this case, after each # formwork 12 is set, the head e of the column 11 is also constructed at the same time as the beam. frame 18
The two-point chain koji between the two is filled with the T-form frame 16. Then, reinforcing bars (not shown) are set inside the beam formwork ta,
Next, concrete is poured into the beam formwork 12 to construct a beam T-sakaki. When carrying out these operations, since the reinforcing material 15 is provided within the beam frame Is, these reinforcing materials 15t-
It can be used as a scaffold. This is particularly applicable to the construction of beams for very large structures (for example, beams with angles of 3 to 10 mm), and is therefore effective because it can be simplified to a large width during construction. Regarding the assembly of reinforcing bars, the number is as follows:
When the beam formwork is manufactured, it can also be tapered at the same time, reducing the labor required for on-site construction. In this way, after constructing the concrete beam, the beam formwork 138 remains as the -b of the structure. Therefore, at the design stage of a single beam, the strength of the formwork can be incorporated in advance as part of the strength of the beam, making it possible to reduce the size of the beam and thereby reduce the amount of concrete and reinforcing bars.◎ 1. In the above-mentioned embodiments, the beam formwork is made of steel.In addition, concrete or plastic pipes may also be used as the material of the beam formwork. In addition, in the above embodiment, the beam formwork joint 18t1111 was formed with a steel plate on the upper part of the column 11.It is not limited to this. The joint part 18 may be constructed by having a single or III-shaped steel in the part. In this case, it is important to determine whether various types of steel material 17, such as T-shaped #A or H-shaped steel, can be used as shown in the figure. A steel member for joining the formwork 12 can be attached to the upper part of the pillar 11, and by doing so, the formwork 2 can be joined easily and firmly. This support & 1B iron plate wrapped tube column 1
.. This is done not only on the upper part of column 1, but also over the entire length of column 11.
This formwork itself can be used as an island for the column 11, and it can also be incorporated into the one-way design, so that the column 11 can be made of steel-framed reinforced concrete (
Filled square steel pipe concrete construction)&:T can also be used. Furthermore, in the above embodiments, the pillars 11 are rectangular, but they may have a round shape or the like. As explained above, according to the present invention, the columns rt are first constructed, and the frame is passed between the beam formwork eJ columns manufactured to have a predetermined strength, and the frame is passed between both ends of the beam formwork. are fixed on the columns, and the beam formwork is supported at one point by these columns.
Concrete [1 beam formwork itself] is poured and remains as a beam structure, so other than the above-mentioned columns &
: @ It is not necessary to install between these columns that support the formwork, and the process of constructing the beam later, that is, the beam
It is possible to install the equipment under the beam and then construct the beam later. Also, by leaving the formwork as a frame structure Q]-m, the beam strength can be increased,
Therefore, the dimensions of the beam itself can be reduced to 8, and the amount of concrete and reinforcing bars can be reduced to 8.

【図面の簡単な説明】[Brief explanation of drawings]

第1V:Jは−゛般の建築構造物の一例艙示T斜視図、
第J図はこの発明の一実旅例を示T斜視図、第3図は梁
型枠12の詳細を示T図、第参図は柱上b&:設けた梁
型枠接合部18の変形例を示T斜包図である。 11・・・・・・柱、1g・・・・・・梁型枠、18・
・・・・・梁型枠接合部、15・・・・・・補強材。 出願人清水il!設株式会社 第2図 2 乎: /l 「′1 7
1st V: J is a perspective view of an example of a general building structure;
Fig. J is a perspective view showing an example of this invention; Fig. 3 is a T drawing showing details of the beam formwork 12; and Fig. 3 is a deformation of the beam formwork joint 18 provided on the column. An example is shown in a T-diagonal envelope diagram. 11...Column, 1g...Beam formwork, 18.
...Beam formwork joint, 15...Reinforcement material. Applicant Shimizu IL! Setup Co., Ltd. Figure 2 2 乎: /l ``'1 7

Claims (1)

【特許請求の範囲】 一本の柱の上部にコンクリート梁を架は波してなる建築
Il構造物構築Tるにあたり、少なくとも上部側面に梁
型枠接合部を形成して柱【構築し1断面略U字状で内部
に補強材を有して前記2柱によって1点支持可能な強度
をもつよう1作された梁型枠【前記a柱間に架は波して
その両端mrt前記梁型枠接合部に接合し、次いでこの
梁蓋枠内にコンクリートを打設するとともに梁型枠を梁
1111mの一部として残留せしめるようにしたことを
特徴とTる難桑徘造物におけるコンクリート梁の構築法
[Claims] When constructing an architectural structure in which a concrete beam is corrugated at the top of one column, a beam formwork joint is formed at least on the upper side surface of the column. The beam form is approximately U-shaped and has a reinforcing material inside and is strong enough to be supported at one point by the two pillars. Construction of a concrete beam in a difficult-to-reach building characterized by joining to the frame joint, then pouring concrete within the beam cover frame, and leaving the beam formwork as a part of the 1111m beam. Law 0
JP15013581A 1981-09-22 1981-09-22 Construction of concrete beam in building structure Pending JPS5850232A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15013581A JPS5850232A (en) 1981-09-22 1981-09-22 Construction of concrete beam in building structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15013581A JPS5850232A (en) 1981-09-22 1981-09-22 Construction of concrete beam in building structure

Publications (1)

Publication Number Publication Date
JPS5850232A true JPS5850232A (en) 1983-03-24

Family

ID=15490245

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15013581A Pending JPS5850232A (en) 1981-09-22 1981-09-22 Construction of concrete beam in building structure

Country Status (1)

Country Link
JP (1) JPS5850232A (en)

Similar Documents

Publication Publication Date Title
JP2000170285A (en) Connecting method for steel sheet concrete structural wall and junction structure
JP2928942B2 (en) Column beam connection and construction method
RU2107789C1 (en) Shuttering for walls
JPS5850232A (en) Construction of concrete beam in building structure
WO2002018725A1 (en) Crux-bar concrete structure
JPS5883751A (en) Construction of beam in building
JP2004052276A (en) Joining structure of column and beam
JP2002332691A (en) Joint construction between column and beam
JP3319709B2 (en) Construction method of prestressed concrete steel beam
JPS61179947A (en) Steel pipe concrete composite pillar
JPH0332586Y2 (en)
JP2023149165A (en) Reinforcement connection part structure for existing frame member
JP2619323B2 (en) Assembling method of steel columns and beams in steel reinforced buildings
JP3125165B2 (en) Warehouse frame
JPH06299718A (en) Construction of wall, floor in atomic power plant and wall slab thereof
JPS6128801Y2 (en)
JPH08239807A (en) Composite column base structure
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JPH0434147A (en) Connecting structure for precast concrete column and beam
JPH02167937A (en) Connecting work of steel plate-concrete structure
JPS61254734A (en) Connection of precast steel panel concrete wall
JPH0762740A (en) Joint method for precast steel framed reinforced concrete construction pillar and beam
JP3312945B2 (en) Construction method of concrete structure
JPS6175118A (en) Pc pile and method of building steel skeleton building employing said pc pile
JPS58204246A (en) Construction of reinforced concrete structure