JPH1037221A - Construction of facility embedding underground storage tank and its working method - Google Patents

Construction of facility embedding underground storage tank and its working method

Info

Publication number
JPH1037221A
JPH1037221A JP8215988A JP21598896A JPH1037221A JP H1037221 A JPH1037221 A JP H1037221A JP 8215988 A JP8215988 A JP 8215988A JP 21598896 A JP21598896 A JP 21598896A JP H1037221 A JPH1037221 A JP H1037221A
Authority
JP
Japan
Prior art keywords
concrete
layer
block
foam
underground pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP8215988A
Other languages
Japanese (ja)
Inventor
Kiyotaka Wakuishi
清孝 和久石
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BAU HOUSE KK
Original Assignee
BAU HOUSE KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BAU HOUSE KK filed Critical BAU HOUSE KK
Priority to JP8215988A priority Critical patent/JPH1037221A/en
Publication of JPH1037221A publication Critical patent/JPH1037221A/en
Pending legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To obtain a required bearing power without driving piles even to soft ground, to prevent cracking and to shorten the period of construction work. SOLUTION: Floor portion for an underground pit 13, on which a storage tank is to be installed, should be formed by laying foamed blocks 24 on a leveling layer 23 with unevenness corrected and pouring concrete over the blocks, thereby forming a paved floor surface lever 26. And the pavement near the blocked top surface of the underground pit 13 should be formed by laying formed blocks 24 over a leveling layer 41 with the irregularity corrected, laying a protection concrete layer 42 to the top surface of which an inorganic crystal- growing agent with water-soluble silicate and magnesium fluoride compound as principal components added, and then concrete is placed on the protection layer 42 for forming the surface paving layer 43.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、ガソリンスタンド
など、貯留タンクを地下に埋設した施設の構造およびそ
の施工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a structure of a facility, such as a gas station, in which a storage tank is buried underground, and a method of constructing the facility.

【0002】[0002]

【従来の技術】貯留タンクを地下に埋設した施設の代表
的なものとしてはガソリンスタンドが挙げられる。ガソ
リンスタンドは、ガソリンや灯油を貯留するタンクを地
下に埋設し、また、給油するための車が頻繁に往来する
ので、地盤の支持力が重要である。この地盤の支持力
は、地域によって大きく差が有る。このため、強固な支
持力のある土地の場合には土壌改良剤を混ぜることによ
り所定の支持力を得ることができるが、軟弱な地盤の場
合には、図 に示すように、所定の支持力を確保するた
めに、地下タンクのピット1の床下は勿論のこと、走路
2にも多数の摩擦基礎杭3…を打ち込むことが一般に行
われている。
2. Description of the Related Art A typical example of a facility in which a storage tank is buried underground is a gas station. In a gas station, a tank for storing gasoline and kerosene is buried underground, and vehicles for refueling frequently come and go, so that the ground support is important. The bearing capacity of this ground varies greatly from region to region. For this reason, in the case of land with strong bearing capacity, a predetermined bearing capacity can be obtained by mixing a soil conditioner, but in the case of soft ground, as shown in the figure, the predetermined bearing capacity can be obtained. It is common practice to drive a large number of friction foundation piles 3... Not only under the floor of the pit 1 of the underground tank but also on the runway 2 in order to secure the ground.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、摩擦基
礎杭3…を打ち込む作業は、振動や騒音の問題が発生す
るばかりでなく、作業工程が増すので工期が長くなって
しまうし、経費も増大してしまう。また、摩擦基礎杭3
…を打ち込んで支持力を高めたとしても、図 に示すよ
うに、杭3は表面の舗装4を点でしか支えられないの
で、杭3と杭3との間の舗装4を均一に支えることは困
難である。このため、大型トラックなどの重量車両が走
行すると、舗装4が僅かに波打ったり沈下したりして、
これを繰り返すとひび割れが発生する。
However, the operation of driving the friction foundation piles 3... Not only raises the problem of vibration and noise, but also increases the number of work steps, so that the construction period becomes longer and the cost increases. Would. In addition, friction foundation pile 3
Even if the supporting force is increased by driving…, as shown in the figure, the pile 3 can only support the surface pavement 4 at points, so the pavement 4 between the piles 3 should be uniformly supported. It is difficult. For this reason, when a heavy vehicle such as a large truck runs, the pavement 4 slightly undulates or sinks,
Repeating this causes cracks.

【0004】また、コンクリート舗装面は寒暖による収
縮が繰り返されてひび割れが発生することがあり、特に
寒冷地においては、ひび割れ隙間に浸入した水が凍結し
てさらに割れを成長させてたり、凍害によりコンクリー
トが脆くなって強度が低下してしまう問題がある。ま
た、コンクリートは時間の経過に伴って僅かずつ収縮す
るので、この収縮に起因する割れも発生する。これらの
ひび割れを防止するために目地切りする場合もあるが、
従来の目地切りでは不充分であり、ひび割れを確実に防
止することができず、実際には、発生した割れ目にエポ
キシ樹脂を充填するなどの補修作業を度々行っている。
そして、この補修に要する費用と手間も問題である。さ
らに、ガソリンスタンドにあっては、こぼれたガソリン
等がひび割れに浸入すると危険であり、自然環境保護の
観点からも問題になる。
[0004] In addition, the concrete pavement surface may be repeatedly shrunk by cold and warm, and cracks may be generated. There is a problem that the concrete becomes brittle and the strength is reduced. Moreover, concrete shrinks little by little with the passage of time, and cracks due to this shrinkage also occur. Sometimes joints are cut to prevent these cracks,
Conventional joint cutting is insufficient and cracks cannot be reliably prevented. In practice, repairs such as filling the cracks with epoxy resin are frequently performed.
And the cost and labor required for this repair are also problems. Further, in a gas station, if spilled gasoline or the like enters the cracks, it is dangerous, and this is a problem from the viewpoint of protecting the natural environment.

【0005】そこで、本発明は、軟弱な地盤であっても
杭を打ち込むことなく所定の支持力を得ることができ、
ひび割れを防止でき、工期を短縮することができる、貯
留タンクを地下に埋設した施設の構造およびその施工法
を提供することを目的とする。
Therefore, the present invention can obtain a predetermined supporting force without driving a pile even on soft ground,
An object of the present invention is to provide a structure of a facility in which a storage tank is buried underground and a construction method thereof, which can prevent cracks and shorten a construction period.

【0006】[0006]

【課題を解決するための手段】本発明は上記目的を達成
するために提案されたもので、請求項1に記載の構造
は、タンクが埋設できる深さまで排土した穴の少なくと
も底部にコンクリートを打設して地下ピットを形成し、
この地下ピット内に貯留タンクを設置し、地下ピットの
上面開口部分を塞ぐとともに、塞いだ地下ピット上面を
その周辺と同じ高さにコンクリートで舗装した施設にお
いて、地下ピットの床部分は、不陸整正したレベリング
層上に発泡材ブロックを敷設し、これら発泡材ブロック
上にコンクリートを打設した床面舗装層を形成すること
により構成し、地下ピットの閉塞上面の周辺の舗装は、
不陸整正したレベリング層上に発泡材ブロックを敷設
し、これら発泡材ブロックの上面に、水溶性シリケート
とマグネシウムフッ化化合物を主成分とする無機質系結
晶増殖材をコンクリートに添加した保護層を形成し、こ
の保護層上にコンクリートを打設した表面舗装層を形成
することにより構成したことを特徴とする貯留タンクを
地下に埋設した施設の構造である。
SUMMARY OF THE INVENTION The present invention has been proposed to achieve the above-mentioned object, and the structure according to claim 1 has a structure in which concrete is formed at least at the bottom of a hole which has been drained to a depth where a tank can be buried. Casting to form an underground pit,
A storage tank is installed in this underground pit, and the top opening of the underground pit is closed, and the underground pit is covered with concrete at the same height as the surrounding area. It is constructed by laying foam blocks on the leveling layer that has been adjusted and forming a floor pavement layer in which concrete is cast on these foam blocks, and the pavement around the closed upper surface of the underground pit,
A foam material block is laid on the uneven leveling layer, and a protective layer made by adding an inorganic crystal breeding material containing water-soluble silicate and a magnesium fluoride compound as a main component to concrete is provided on the upper surface of the foam material block. It is a structure of a facility in which a storage tank is buried underground, characterized in that it is formed by forming a surface pavement layer in which concrete is cast on the protective layer.

【0007】請求項2に記載の構造は、請求項1の構造
に加えて、地下ピットの床部分は、不陸整正した基礎層
上に発泡材ブロックを敷設し、これら発泡材ブロックの
上面に、水溶性シリケートとマグネシウムフッ化化合物
を主成分とする無機質系結晶増殖材をコンクリートに添
加した保護層を形成し、この保護層上にコンクリートを
打設した床面舗装層を形成することにより構成したこと
を特徴とする貯留タンクを地下に埋設した施設の構造で
ある。
According to a second aspect of the present invention, in addition to the first aspect, the floor portion of the underground pit is provided with a foam material block laid on an uneven ground foundation layer, and an upper surface of the foam material block is provided. By forming a protective layer in which an inorganic crystal breeding material containing water-soluble silicate and magnesium fluoride compound as main components is added to concrete, and forming a floor pavement layer in which concrete is cast on the protective layer. It is a structure of a facility where a storage tank characterized by being constructed is buried underground.

【0008】請求項3に記載の構造は、前記発泡材ブロ
ックが、発泡ポリスチレン製ブロックである。
According to a third aspect of the present invention, the foam block is a block made of expanded polystyrene.

【0009】請求項4に記載の構造は、前記発泡材ブロ
ックが、発泡コンクリート製ブロックである。
According to a fourth aspect of the present invention, the foam material block is a foam concrete block.

【0010】請求項5に記載の施工法は、タンクが埋設
できる深さまで排土した穴の少なくとも底部にコンクリ
ートを打設して地下ピットを形成し、この地下ピット内
に貯留タンクを設置し、地下ピットの上面開口部分を塞
ぐとともに、塞いだ地下ピット上面をその周辺と同じ高
さにコンクリートで舗装した施設を施工するにあたり、
地下ピットの床部分は、穴の底部を不陸整正してレベリ
ング層を形成するレベリング層形成工程と、このレベリ
ング層上に発泡材ブロックを敷設する発泡材ブロック敷
設工程と、発泡材ブロック上にコンクリートを打設する
コンクリート打設工程とを経て構築し、地下ピットの閉
塞上面の周辺の舗装は、不陸整正してレベリング層を形
成するレベリング層形成工程と、このレベリング層上に
発泡材ブロックを敷設する発泡ブロック敷設工程と、発
泡材ブロックの上面に、水溶性シリケートとマグネシウ
ムフッ化化合物を主成分とする無機質系結晶増殖材をコ
ンクリートに添加した保護層を形成する保護層形成工程
と、この保護層上にコンクリートを打設するコンクリー
ト打設工程とを経て構築することを特徴とする貯留タン
クを地下に埋設した施設の施工法である。
[0010] In the construction method according to the fifth aspect, concrete is poured into at least the bottom of the hole that has been excavated to a depth where the tank can be buried to form an underground pit, and a storage tank is installed in the underground pit. In closing the opening of the upper surface of the underground pit and constructing a facility where the closed upper surface of the underground pit is paved with concrete at the same height as the surrounding area,
The floor portion of the underground pit has a leveling layer forming step of forming a leveling layer by irregularly adjusting the bottom of the hole, a foaming material block laying step of laying a foaming material block on the leveling layer, and a foaming material block laying step. Pavement around the closed top surface of the underground pit is leveled by unevenness to form a leveling layer, and foaming is performed on this leveling layer. Layer laying step of laying a material block, and a protective layer forming step of forming a protective layer on the upper surface of the foam material block by adding an inorganic crystal breeding material mainly composed of a water-soluble silicate and a magnesium fluoride compound to concrete And a concrete pouring step of pouring concrete on this protective layer. Facility is a construction method.

【0011】[0011]

【発明の実施の形態】以下、本発明の実施の形態を図面
に基づいて説明する。なお、本実施形態は、貯留タンク
を地下に埋設した施設の代表的なものとしてガソリンス
タンドを例に挙げて説明する。
Embodiments of the present invention will be described below with reference to the drawings. In the present embodiment, a gas station will be described as an example of a typical facility in which a storage tank is buried underground.

【0012】ガソリンスタンド11は、図1の平面図に
示すように、ガソリン貯留タンクや灯油貯留タンクなど
の貯留タンク12を地下に埋設するために地下にピット
13を形成し、この地下ピット13内にまとめて設置
し、また、道路側を除く境界に防火壁14を設け、敷地
内の一側には事務棟15を建て、この事務棟15からキ
ャノピー16を延設し、このキャノピー16の下方に給
油機を設置したり吊り下げ式給油機を設ける。そして、
上記地下ピット13の上面開口部分は閉塞するととも
に、塞いだ地下ピット13上面をその周辺と同じ高さに
コンクリートで舗装して車両走行路17とする。なお、
図1中に示す20は自動洗車場、21は洗車場である。
As shown in the plan view of FIG. 1, the gas station 11 has a pit 13 formed underground for burying a storage tank 12 such as a gasoline storage tank or a kerosene storage tank underground. In addition, a fire wall 14 is provided on the boundary excluding the road side, an office building 15 is built on one side of the site, a canopy 16 is extended from the office building 15, and a lower part of the canopy 16 is A refueling machine will be installed in the plant and a suspended refueling machine will be installed. And
The upper surface opening portion of the underground pit 13 is closed, and the closed upper surface of the underground pit 13 is paved with concrete at the same height as the periphery of the underground pit 13 to form a vehicle traveling path 17. In addition,
In FIG. 1, reference numeral 20 denotes an automatic car wash, and 21 denotes a car wash.

【0013】地下ピット13を構築するには、まず、タ
ンク12が埋設できる深さまで充分に排土する(排土工
程)。そして、この穴の底部に砕石等を敷いて転圧する
ことにより基礎層22を形成し(基礎層形成工程)、こ
の基礎層22の上に砂や緩い軽量骨材を水平に敷き均し
て、即ち不陸整正してレベリング層23を形成する(レ
ベリング層形成工程)。このレベリング層23は、後述
する発泡材ブロック24を安定した状態で整列して水平
に敷設できるようにするとともに、敷設した発泡材ブロ
ック24の不陸現象を防止するための層である。そし
て、レベリング層23を形成したならば、このレベリン
グ層23の上に発泡材ブロック24を敷設する(発泡材
ブロック敷設工程)。
In order to construct the underground pit 13, first, the soil is sufficiently discharged to a depth where the tank 12 can be buried (a discharging step). Then, crushed stones or the like are laid at the bottom of the hole and rolled to form a base layer 22 (base layer forming step), and sand or a loose lightweight aggregate is laid horizontally on the base layer 22, That is, leveling is performed to form the leveling layer 23 (leveling layer forming step). The leveling layer 23 is a layer for arranging the foam blocks 24 to be described later in a stable state so that they can be laid horizontally in a stable state, and for preventing the laid foam blocks 24 from becoming uneven. When the leveling layer 23 is formed, a foam material block 24 is laid on the leveling layer 23 (foam material block laying step).

【0014】発泡材ブロック24は地盤安定材として機
能するもので、本実施形態では幅2m、長さ1m、厚さ
50cmの発泡ポリスチレン製のブロック(発泡スチロ
ールブロック24)である。そして、この発泡スチロー
ルブロック24を敷設する場合には、隣りのもの離脱し
ないように緊結金具(図示せず)を使用して接続しなが
ら敷設する。緊結金具は、両側に爪を有し、この爪を隣
り合う発泡スチロールブロック24にそれぞれ突き刺し
て両ブロックを緊結する。
The foam material block 24 functions as a ground stabilizing material. In this embodiment, the foam material block 24 is a block made of expanded polystyrene having a width of 2 m, a length of 1 m, and a thickness of 50 cm (styrene foam block 24). When the styrofoam block 24 is laid, the styrofoam block 24 is laid while being connected using a tie (not shown) so as not to be separated from an adjacent one. The binding metal has claws on both sides, and the nails are pierced into adjacent styrofoam blocks 24 to bind the two blocks together.

【0015】発泡スチロールブロック24は、軽量で、
断熱性、遮音性に優れるばかりでなく、充分な圧縮強さ
を備えている。そして、本実施形態のようにガソリンス
タンド11の場合には、難燃性のものを使用することが
好ましい。また、発泡スチロールは、ガソリンや灯油な
どの溶剤によって融けるので、上面に保護層25を形成
する(保護層形成工程)。
The styrofoam block 24 is lightweight,
Not only is it excellent in heat insulation and sound insulation, but it also has sufficient compressive strength. In the case of the gas station 11 as in the present embodiment, it is preferable to use a gas-resistant one. Further, since the polystyrene foam is melted by a solvent such as gasoline or kerosene, the protective layer 25 is formed on the upper surface (protective layer forming step).

【0016】保護層25は、コンクリートに無機質系結
晶増殖材を添加したものを塗布することにより形成す
る。この無機質系結晶増殖材は、水溶性シリケートとマ
グネシウムフッ化化合物を主成分とする。なお、この無
機質系結晶増殖材の作用については後述する。
The protective layer 25 is formed by applying a material obtained by adding an inorganic crystal growth material to concrete. This inorganic crystal breeding material contains a water-soluble silicate and a magnesium fluoride compound as main components. The function of the inorganic crystal breeder will be described later.

【0017】保護層25を形成したならば、次には、こ
の保護層25上にコンクリートを打設して床面舗装層2
6を形成する(コンクリート打設工程)。この床面舗装
層26を形成する場合、鉄筋27を配してからコンクリ
ートを打設する。
After the protective layer 25 is formed, the concrete is cast on the protective layer 25 to form the floor pavement layer 2.
6 is formed (concrete casting step). When the floor pavement layer 26 is formed, concrete is poured after the reinforcing bars 27 are arranged.

【0018】この様にして地下ピット13の床部を構築
したならば、各タンク12の架台28をコンクリート等
により構築し、また、地下ピット13の側壁29を構築
するとともに、各タンク12の間に仕切り壁を兼ねた支
持壁30を構築する。
When the floor of the underground pit 13 is constructed in this way, the gantry 28 of each tank 12 is constructed of concrete or the like, and the side wall 29 of the underground pit 13 is constructed. The support wall 30 which also functions as a partition wall is constructed.

【0019】側壁29は、断面L字状のコンクリート製
基礎ブロック31を床面舗装層26上に設置し、この基
礎ブロック31上にコンクリート製の壁を構築すること
により構成する。そして、本実施形態では、コンクリー
ト製の壁を構築するに際して、図7に示すように、発泡
スチロール製の型枠32を組み上げて押え金具33等に
より両側の型枠32相互を固定し、型枠32内に鉄筋3
4を配し、コンクリートを打設して型枠32…と一体化
させることにより壁を構築する。
The side wall 29 is constructed by installing a concrete base block 31 having an L-shaped cross section on the floor pavement layer 26, and constructing a concrete wall on the base block 31. In this embodiment, when constructing a concrete wall, as shown in FIG. 7, a styrofoam mold 32 is assembled, and the molds 32 on both sides are fixed to each other by holding metal fittings 33 and the like. Reinforcing bar 3 inside
4 and the concrete is cast and integrated with the formwork 32 to build a wall.

【0020】この様に、発泡スチロール製の型枠32を
使用すると、コンクリートが養生した後に型枠32を取
り外す必要がないので省力化を図ることができるととも
に、工期の短縮化を図ることができる。なお、発泡スチ
ロール製の型枠32は、コンクリートとの接触面に、泡
による小さな凹部が無数に存在するので、打設コンクリ
ートとの接合力が強い。また、この様にして構築した側
壁29の表面、特にタンク側の面には、前記した様に、
コンクリートに無機質系結晶増殖材を添加したものを塗
布することにより保護層を形成することが望ましい。側
壁29の表面に保護層を形成しておくと、ガソリン等の
油脂が付着しても、発泡スチロールを保護することがで
きる。前記防火壁14も同様にして構築することができ
る。
As described above, when the styrofoam form 32 is used, it is not necessary to remove the form 32 after the concrete is cured, so that labor can be saved and the construction period can be shortened. In addition, the mold 32 made of Styrofoam has a large number of small concave portions due to foam on the contact surface with concrete, and therefore has a strong bonding force with cast concrete. As described above, the surface of the side wall 29 thus constructed, particularly the surface on the tank side,
It is desirable to form a protective layer by applying a material obtained by adding an inorganic crystal breeder to concrete. If a protective layer is formed on the surface of the side wall 29, it is possible to protect the styrofoam even if fats such as gasoline adhere. The fire wall 14 can be similarly constructed.

【0021】支持壁30は、本実施形態では発泡スチロ
ール製ブロックを積み上げることにより構築してある。
そして、この発泡スチロール製ブロックの表面にも、側
壁29と同様に、コンクリートに無機質系結晶増殖材を
添加したものを塗布することにより保護層を形成してお
くことが望ましい。また、発泡スチロール製のブロック
を積み上げる場合、接着剤としてセメントミルクを使用
すると、前記したように、発泡スチロールの小さな凹部
の存在により強力な接合力を得ることができる。
In this embodiment, the support wall 30 is constructed by stacking styrofoam blocks.
Then, it is desirable to form a protective layer on the surface of the styrofoam block by applying a material obtained by adding an inorganic crystal breeding material to concrete, similarly to the side wall 29. When a block made of Styrofoam is stacked, when cement milk is used as an adhesive, a strong bonding force can be obtained due to the presence of the small recesses of Styrofoam, as described above.

【0022】なお、上記した側壁29及び支持壁30
は、コンクリートブロックを積み重ねて構築したり、或
は金属製或は木製の型枠を組んでコンクリートを打設
し、養生後に型枠を取り外して構築してもよい。また、
型枠32を発泡コンクリート製としてもよく、この方が
耐火性に優れる。
The side wall 29 and the support wall 30
May be constructed by stacking concrete blocks, or constructing a metal or wooden formwork, casting concrete, and removing the formwork after curing. Also,
The formwork 32 may be made of foamed concrete, which has better fire resistance.

【0023】この様にして地下ピット13を構築したな
らば、架台28上に貯留タンク12を設置して固定する
とともに貯留タンク12の設置に伴う配管等の作業を行
う。そして、側壁29の外側を埋め戻すとともに、地下
ピット13の上面開口部分に床版コンクリート35を被
せて塞ぐ。なお、貯留タンク12の周りの地下ピット1
3内に砂等を充填してもよい。
After the underground pit 13 is constructed in this manner, the storage tank 12 is installed and fixed on the gantry 28, and work such as piping for installing the storage tank 12 is performed. Then, the outside of the side wall 29 is backfilled, and the upper surface opening of the underground pit 13 is covered with the floor slab concrete 35 and closed. The underground pit 1 around the storage tank 12
3 may be filled with sand or the like.

【0024】次に、塞いだ地下ピット13の上面及びそ
の周辺の舗装(車両走行路17)について説明する。ま
ず、地下ピット13の上面を除く舗装施工域の土砂を所
定の深さまで排土したり(排土工程)、或は埋め戻して
深さを一定にする。そして、この穴の底部に砕石等を敷
いて転圧することにより基礎層40を形成し(基礎層形
成工程)、この基礎層40の上に砂や緩い軽量骨材を水
平に敷き均して、即ち不陸整正してレベリング層41を
形成する(レベリング層形成工程)。このレベリング層
41は、地下ピット13の場合と同様に、発泡材ブロッ
ク24を安定した状態で整列して水平に敷設できるよう
にするとともに、敷設した発泡材ブロック24の不陸現
象を防止するための層である。そして、レベリング層4
1を形成したならば、このレベリング層41の上に発泡
材ブロック24を敷設する(発泡材ブロック敷設工
程)。
Next, the upper surface of the closed underground pit 13 and the pavement around it (vehicle running path 17) will be described. First, the earth and sand in the pavement construction area except the upper surface of the underground pit 13 is discharged to a predetermined depth (a discharging process) or backfilled to make the depth constant. Then, a crushed stone or the like is laid on the bottom of the hole and rolled to form a base layer 40 (a base layer forming step), and sand or a loose lightweight aggregate is laid horizontally on the base layer 40, That is, leveling is performed to form the leveling layer 41 (leveling layer forming step). Like the underground pit 13, the leveling layer 41 enables the foam blocks 24 to be lined up in a stable state and laid horizontally, and to prevent the laid foam blocks 24 from becoming uneven. Layer. And the leveling layer 4
When 1 is formed, the foam material block 24 is laid on the leveling layer 41 (foam material block laying step).

【0025】発泡材ブロック24は地盤安定材として機
能するもので、地下ピット13の場合と同様に、本実施
形態では幅2m、長さ1m、厚さ50cmの発泡ポリス
チレン製のブロック(発泡スチロールブロック24)を
使用する。そして、この発泡スチロールブロック24を
敷設する場合には、隣りのもの離脱しないように緊結金
具を使用して接続しながら敷設する。
The foam material block 24 functions as a ground stabilizing material. As in the case of the underground pit 13, in this embodiment, a block made of expanded polystyrene having a width of 2 m, a length of 1 m, and a thickness of 50 cm (a styrofoam block 24) is used. ). When the styrofoam block 24 is laid, the styrofoam block 24 is laid while being connected using a tie-down fitting so as not to be separated from the adjacent one.

【0026】発泡スチロールブロック24は、本実施形
態のようにガソリンスタンド11の場合には、難燃性の
ものを使用する。また、発泡スチロールは、ガソリンや
灯油などの溶剤によって融けるので、上面に保護層42
を形成する(保護層形成工程)。
As the styrofoam block 24, in the case of the gas station 11 as in this embodiment, a flame-retardant one is used. In addition, since styrene foam is melted by a solvent such as gasoline or kerosene, a protective layer 42 is formed on the upper surface.
Is formed (protective layer forming step).

【0027】保護層42は、コンクリートに無機質系結
晶増殖材を添加したものを塗布することにより形成す
る。この無機質系結晶増殖材は、水溶性シリケートとマ
グネシウムフッ化化合物を主成分とする。なお、この無
機質系結晶増殖材の添加割合は約1割乃至1割弱でよ
い。
The protective layer 42 is formed by applying a material obtained by adding an inorganic crystal growth material to concrete. This inorganic crystal breeding material contains a water-soluble silicate and a magnesium fluoride compound as main components. The proportion of the inorganic crystal breeding material added may be about 10% to less than 10%.

【0028】無機質系結晶増殖材は、その成分を示す
と、例えば、SiO2が20重量%,CaOが30重量
%,NaOが5重量%,不溶成分が2〜3重量%であ
る。この無機質系結晶増殖材の反応は、水溶性シリケ
ート+Ca(OH)2→C−S−H系結晶となり、マ
グネシアを含むフッ化化合物+Ca(OH)2→CaF2
+MgSiO2+αH2Oとなる。の反応で水溶性シリ
ケートを再生産し、の反応で余分にH2Oを生成し、
反応に利用し、即ち、,の反応が連鎖反応として継
続する。そして、C−S−H系結晶(針状)とCaF
2,MgO・nSiO2(等軸、斜方)が絡みあって強固
になる。したがって、コンクリートの強度は、4週養生
後測定して無塗布のものと比較して約10〜15%圧縮
強度が向上する。そして、さらなる時間経過に伴い反応
が進行して28〜30%の強度アップを図ることができ
る。
The components of the inorganic crystal breeding material are, for example, 20% by weight of SiO2, 30% by weight of CaO, 5% by weight of NaO, and 2-3% by weight of insoluble components. The reaction of the inorganic crystal breeding material is a water-soluble silicate + Ca (OH) 2 → C—S—H type crystal, and a fluoride compound containing magnesia + Ca (OH) 2 → CaF2
+ MgSiO2 + αH2O. Reproduce the water-soluble silicate in the reaction, and generate extra H2O in the reaction,
The reaction is utilized in the reaction, that is, the reaction continues as a chain reaction. Then, C—S—H based crystal (needle-shaped) and CaF
2. MgO.nSiO2 (equiaxial, oblique) is entangled and becomes strong. Therefore, the strength of the concrete is improved by about 10 to 15% as compared with the non-coated one as measured after curing for 4 weeks. Then, as the time elapses, the reaction proceeds, and the strength can be increased by 28 to 30%.

【0029】さらに、この無機質系結晶増殖材は極く微
細なので、毛細管現象や浸透圧作用によりコンクリート
内部に30cm以上浸透することができ、またコンクリー
トの毛細孔や空隙等の小さな隙間に入り込んで密封する
ことにより緻密組織化を図ることができる。したがっ
て、図9に示すように、保護層42上に打設したコンク
リート内部に浸透していく特性を有し、防水性(止水
性)を発揮してガソリンや水等の浸透を確実に防止する
ことができる。このため、後述する表面舗装に万一クラ
ックが発生しても、このクラックにガソリンや水が入っ
ても、ガソリン等の油分は水と分離して上昇して蒸発す
るので、ガソリン等の油分が発泡スチロールまで到達す
ることは殆どない。万一、クラックに入ったガソリン等
の油分が下降したとしても、保護層42が止水性を有す
るので、発泡スチロールブロック24に到達或は接触す
ることを確実に防止する。
Further, since this inorganic crystal breeding material is extremely fine, it can penetrate more than 30 cm into the concrete by capillary action and osmotic pressure action, and enters into small gaps such as pores and voids of the concrete to seal. By doing so, a dense organization can be achieved. Therefore, as shown in FIG. 9, it has a property of penetrating into the concrete cast on the protective layer 42, exhibits waterproofness (water stoppage), and reliably prevents penetration of gasoline, water, and the like. be able to. For this reason, even if cracks occur on the surface pavement described later, even if gasoline or water enters the cracks, oil such as gasoline separates from water and rises and evaporates. It hardly reaches the styrofoam. Even if the cracked oil such as gasoline falls, the protective layer 42 has the water-stopping property, so that it can be surely prevented from reaching or contacting the styrofoam block 24.

【0030】また、前記した緻密組織化が前記強度向上
に寄与し、ひび割れ防止にも役立つし、万一、クラック
が発生した場合には無機質系結晶増殖材の結晶増殖によ
り自己修復し、再度一体化する。
In addition, the above-mentioned dense structure contributes to the improvement of the strength, and also helps to prevent cracks. In the event that a crack occurs, it is self-repaired by the crystal growth of the inorganic crystal growth material, and is integrated again. Become

【0031】また、上記無機質形結晶増殖材のその他の
特性としては、凍害抑止性,塩害抑止性,中性化抑止
性,アルカリ骨材反応抑止性,硬化収縮抑止性,化学抵
抗性がある。
Other characteristics of the above-mentioned inorganic type crystal breeding material include deterrence against frost damage, deterrence against salt damage, deterrence against neutralization, deterrence against alkali-aggregate reaction, deterrence from hardening shrinkage, and chemical resistance.

【0032】なお、上記した保護層42は、敷設した発
泡スチロールブロック24の上面の全域に形成するばか
りでなく、地下ピット13の上面開口部を塞いだ床版コ
ンクリート35の上面にも形成する。すなわち、表面舗
装のコンクリートを打設するエリアの前面に保護層42
を形成し、コンクリートのひび割れを防止するとともに
発泡スチロールブロック24の保護を確実ならしめる。
The above-mentioned protective layer 42 is formed not only on the entire upper surface of the styrofoam block 24 laid but also on the upper surface of the slab concrete 35 which covers the opening of the upper surface of the underground pit 13. That is, the protective layer 42 is provided in front of the area where the surface pavement concrete is cast.
Is formed to prevent cracking of the concrete and to ensure protection of the Styrofoam block 24.

【0033】保護層42を形成したならば、次には、こ
の保護層42上にコンクリートを打設して表面舗装層4
3を形成する(コンクリート打設工程)。この表面舗装
層43を形成する場合、鉄筋44を縦横に配してからコ
ンクリートを打設する。
After the protection layer 42 is formed, next, concrete is cast on the protection layer 42 to form a surface pavement layer 4.
3 is formed (concrete casting step). When the surface pavement layer 43 is formed, concrete is cast after the reinforcing bars 44 are arranged vertically and horizontally.

【0034】鉄筋44を配置する場合、本実施形態にお
いては、図11に示す、鉄筋支持金具45を使用する。
この鉄筋支持金具45は、左右に下向きの脚部46を有
する倒コ字状の部材47を、それぞれ水平部分中央で略
直角に交叉した状態で溶接等によって固定し、一方の部
材47の水平部分には、上方が開いて向きが異なる略S
字状の巻き付け線部48を一対設け、他方の部材の水平
部分には、下方が開いて向きが異なる略S字状の巻き付
け線部49を一対設け、上記交叉部分には上方に柱状の
打設面指標部50を、下方に差し込み深さ規制部51を
それぞれ延設してある。
In the case of arranging the reinforcing bar 44, in this embodiment, a reinforcing bar support 45 shown in FIG. 11 is used.
The rebar supporting bracket 45 is fixed by welding or the like in a state where the inverted members 47 having left and right downwardly directed legs 46 are respectively crossed substantially at a right angle at the center of the horizontal portion. Has a substantially S
And a pair of substantially S-shaped winding wires 49 which are open downward and have different directions in the horizontal portion of the other member. The installation surface index portion 50 is inserted downward, and a depth regulating portion 51 is extended.

【0035】上記した構成から成る鉄筋支持金具45を
使用して鉄筋44を止めるには、規制部51よりも長い
脚部46を発泡スチロールブロック24の上面の所定位
置に突き刺し、差し込み深さ規制部51の下端が発泡ス
チロールブロック24の上面に当接するまで充分に突き
刺す。差し込み深さ規制部51は、鉄筋44を最適な高
さに保持し得る所定の長さに設定されているので、下端
を発泡スチロールブロック24の上面に当接させるだけ
で、鉄筋44の高さを最適高さに位置させることができ
る。なお、差し込み深さ規制部51は、発泡スチロール
ブロック24に刺さらないように、下端を、例えばL字
状に屈折するなどして、当接面積をできるだけ大きくし
ておくことが望ましい。
In order to stop the reinforcing bar 44 by using the reinforcing bar support fitting 45 having the above-described configuration, a leg 46 longer than the restricting portion 51 is pierced into a predetermined position on the upper surface of the Styrofoam block 24 and inserted. Is sufficiently pierced until the lower end thereof contacts the upper surface of the Styrofoam block 24. Since the insertion depth regulating portion 51 is set to a predetermined length capable of holding the reinforcing bar 44 at an optimum height, the height of the reinforcing bar 44 can be reduced only by bringing the lower end into contact with the upper surface of the Styrofoam block 24. It can be located at the optimum height. It is desirable that the insertion depth regulating portion 51 has a contact area as large as possible by, for example, bending the lower end into an L shape so as not to pierce the styrofoam block 24.

【0036】この様にして、鉄筋支持金具45を発泡ス
チロールブロック24上に配設したならば、次に、S字
状の巻き付け線部48,49内に鉄筋44を挿通し、巻
き付け線部48,49の先端部分を打設面指標部50や
差し込み深さ規制部51に巻き付けることにより当該鉄
筋44を止める。この場合、鉄筋44は長さに限界があ
るので、実際には途中で繋ぎ合わせることが行われてお
り、同じ方向の鉄筋44は隣り合う巻き付け線部48,
49内にそれぞれの鉄筋44を挿通して止める。そし
て、縦横の鉄筋44が交叉する部分に、この鉄筋支持金
具45を配置して各鉄筋44を支持するので、図12に
示すように、合計4本の鉄筋44が交叉する場合
(a)、3本が交叉する場合(b)、2本が交叉する場
合(c)などがあるが、上側に一対、下側に一対の巻き
付け線部48,49を設けてあるので、これらのすべて
の場合に対処してそれぞれの鉄筋44を無理無く確実に
支持することができる。
After the reinforcing bar support 45 is disposed on the styrofoam block 24 in this manner, the reinforcing bar 44 is then inserted into the S-shaped winding wires 48, 49, and the winding wires 48, 49 are inserted. The reinforcing bar 44 is stopped by winding the tip portion of 49 around the driving surface indicator 50 and the insertion depth regulating portion 51. In this case, since the reinforcing bar 44 has a limit in length, the reinforcing bar 44 is actually joined in the middle, and the reinforcing bar 44 in the same direction is adjacent to the winding wire portion 48,
The respective rebars 44 are inserted into 49 and stopped. Then, the reinforcing bars 45 are arranged at the portions where the vertical and horizontal reinforcing bars 44 intersect, and each reinforcing bar 44 is supported. Therefore, as shown in FIG. 12, when a total of four reinforcing bars 44 cross (a), There are a case where three wires cross (b) and a case where two wires cross (c). However, since a pair of winding wires 48 and 49 are provided on the upper side and a pair of winding wires 48 and 49 on the lower side, all of these cases are used. Accordingly, each reinforcing bar 44 can be supported without difficulty.

【0037】この様にして鉄筋44の配置作業が終了し
たならば、コンクリートを打設する。この時、図12
(d)に示すように、前記した鉄筋支持金具45に設け
た打設面指標部50の上端を目安にすると、所定の厚さ
に正確に打設することができる。なお、打設面指標部5
0の上端の高さは、当該現場に適合したコンクリートの
厚さに合わせて、予め調整してある。
When the work of arranging the reinforcing bar 44 is completed in this way, concrete is poured. At this time, FIG.
As shown in (d), when the upper end of the casting surface index portion 50 provided on the reinforcing steel support bracket 45 is used as a guide, the casting can be accurately performed to a predetermined thickness. Note that the casting surface indicator 5
The height of the upper end of 0 is adjusted in advance according to the thickness of the concrete suitable for the site.

【0038】ガソリンスタンド11の場合、キャノピー
16を支える柱52を設けることが多いが、この柱52
の基礎部分は、一般に、その周囲よりも一段高く形成す
る。本実施形態では、この基礎部分を形成する際に、図
13に示すように、予め所定高さに成型したコンクリー
ト製枠体55を保護層42上に載置し、この状態で枠体
55の内外にコンクリートを打設する。なお、コンクリ
ート製枠体55の底部は外方に突出した形状に成型され
ており、打設したコンクリートによって押えつけられる
ように構成されている。また、枠体55の側壁29の内
面上部には鉄筋44を支える非貫通孔56が、打設コン
クリートに埋まる側壁29の下部には鉄筋44を貫通さ
せる貫通孔57を形成してある。
In the case of the gas station 11, a column 52 for supporting the canopy 16 is often provided.
Is generally one step higher than its surroundings. In the present embodiment, when forming this base portion, as shown in FIG. 13, a concrete frame 55 molded in advance to a predetermined height is placed on the protective layer 42, and in this state, the frame 55 Cast concrete inside and outside. The bottom of the concrete frame 55 is formed in a shape protruding outward, and is configured to be pressed down by the poured concrete. A non-through hole 56 for supporting the reinforcing bar 44 is formed in an upper portion of an inner surface of the side wall 29 of the frame 55, and a through hole 57 for penetrating the reinforcing bar 44 is formed in a lower portion of the side wall 29 buried in the cast concrete.

【0039】上記した枠体55を載置してコンクリート
を打設すると、一段高くなった基礎部分を簡単に構築す
ることができる。そして、この基礎部分に柱52を立設
することができる。
When the above-described frame 55 is placed and concrete is cast, a raised base portion can be easily constructed. Then, the pillar 52 can be erected on the base portion.

【0040】この様にして、保護層42上にコンクリー
トを打設して表面舗装層43を形成すると、保護層42
の無機質形結晶増殖材が時間の経過に伴って表面舗装層
43のコンクリート内部に浸透していく。したがって、
表面舗装層43のコンクリートが緻密組織化して強度が
向上し、ひび割れや微細なヘヤークラックの発生を抑制
することができる。そして、万一、表面舗装にクラック
が発生したとしても、このクラックは、連鎖反応し続け
る無機質系結晶増殖材が浸透してくるので、そのまま放
置していても閉塞されてしまうし、閉塞される前にガソ
リンや水がクラック内に流入したとしても、これらのガ
ソリンや水は、止水性を有する保護層42によってそれ
以上の浸透が阻止される。したがって、表面舗装層43
にクラックが発生したとしても、こぼれらガソリンが発
泡スチロールブロック24まで到達することを確実に防
止することができ、油脂類の付着による発泡スチロール
ブロック24の損傷を確実に防止することができる。
In this way, when the surface pavement layer 43 is formed by placing concrete on the protective layer 42, the protective layer 42
The inorganic form crystal breeding material permeates into the concrete of the surface pavement layer 43 with the passage of time. Therefore,
The concrete of the surface pavement layer 43 is densely structured and the strength is improved, and the occurrence of cracks and fine hair cracks can be suppressed. Even if cracks occur on the surface pavement, the cracks are blocked because the inorganic crystal breeding material that continues to undergo a chain reaction penetrates. Even if gasoline or water previously flows into the crack, the gasoline or water is prevented from further penetrating by the protective layer 42 having the water blocking property. Therefore, the surface pavement layer 43
Even if cracks occur, the spilled gasoline can be reliably prevented from reaching the styrofoam block 24, and damage to the styrofoam block 24 due to adhesion of oils and fats can be reliably prevented.

【0041】また、地盤安定材として難燃性の発泡スチ
ロールブロック24を埋設したが、この発泡スチロール
ブロック24の上面は保護層42により被覆され、さら
に保護層42上にコンクリートを打設してあるので、万
一、表面舗装上で火災が発生したとしても、地中の発泡
スチロールブロック24が燃えることはなく、防火上の
危険もない。なお、難燃性発泡スチロールブロック24
に代わって、不燃性発泡材、例えば発泡セメントブロッ
クを使用すると、一層防火上の危険性はなくなる。
A flame-retardant styrofoam block 24 is buried as a ground stabilizing material. However, since the upper surface of this styrofoam block 24 is covered with a protective layer 42 and concrete is cast on the protective layer 42, Even if a fire occurs on the surface pavement, the underground Styrofoam block 24 does not burn and there is no danger in fire prevention. The flame-retardant styrofoam block 24
Alternatively, the use of a non-combustible foam, such as a foam cement block, further reduces the fire hazard.

【0042】図14に示す表面舗装層43の他の実施形
態は、発泡スチロールブロックなどの発泡材ブロック2
4上に融雪機構を設けたものである。この融雪機構は、
例えば発泡スチロールブロック24の上面に溝を形成す
るとともに、この溝内に融雪管60を配管し、融雪管6
0内に通した温水等の熱媒体により運搬された熱により
表面舗装層43上の積雪を溶かすものである。
Another embodiment of the surface pavement layer 43 shown in FIG. 14 is a foam material block 2 such as a styrofoam block.
4 is provided with a snow melting mechanism. This snow melting mechanism
For example, a groove is formed on the upper surface of the Styrofoam block 24, and a snow-melting pipe 60 is provided in the groove.
The snow carried on the surface pavement layer 43 is melted by heat carried by a heat medium such as hot water passed through the inside of the pavement.

【0043】この様に、融雪機構を発泡スチロールブロ
ック24上に設けると、発泡スチロールの断熱性により
熱が地盤に逃げることを効率良く防止することができ、
放熱された熱量を融雪のために有効に利用することがで
きる。したがって、熱効率に優れた融雪機構とすること
ができる。なお、融雪機構は、温水を通すものに限ら
ず、例えば電熱線を設けたものでも良い。
As described above, when the snow melting mechanism is provided on the styrofoam block 24, the heat can be efficiently prevented from escaping to the ground due to the heat insulating property of the styrofoam.
The heat radiated can be effectively used for melting snow. Therefore, a snow melting mechanism excellent in thermal efficiency can be provided. Note that the snow melting mechanism is not limited to a mechanism through which warm water is passed, but may be a mechanism provided with a heating wire, for example.

【0044】なお、前記した実施形態においては、ガソ
リンスタンド11を例に挙げて説明したが、本発明はこ
れに限定されるものでなく、ガソリン以外の物質を貯留
するためのタンクを地下に埋設した施設であってもよ
い。
In the above embodiment, the gas station 11 has been described as an example. However, the present invention is not limited to this, and a tank for storing substances other than gasoline is buried underground. It may be a facility that did.

【0045】[0045]

【発明の効果】以上説明したように本発明によれば、以
下の効果を奏する。請求項1,5の発明によれば、地下
ピットの床部分は、不陸整正した基礎層上に発泡材ブロ
ックを敷設し、これら発泡材ブロック上にコンクリート
を打設した床面舗装層を形成することにより構成し、地
下ピットの閉塞上面の周辺の舗装は、不陸整正したレベ
リング層上に発泡材ブロックを敷設し、これら発泡材ブ
ロックの上面に、水溶性シリケートとマグネシウムフッ
化化合物を主成分とする無機質系結晶増殖材をコンクリ
ートに添加した保護層を形成し、この保護層上にコンク
リートを打設した表面舗装層を形成することにより構成
したので、軟弱地盤であっても基礎杭を打ち込むことな
く、敷設した発泡材ブロックによって必要な支持力を確
保することができる。したがって、軟弱地盤であっても
基礎杭を打ち込む作業が不要となり、このため杭打ち作
業に伴う振動や騒音の問題が解消されるばかりでなく、
作業者が人力で敷設できる発泡材ブロックの使用により
工期を、杭打ちの場合に比較して短縮することができ、
また、工事費用を節約することができる。
According to the present invention as described above, the following effects can be obtained. According to the first and fifth aspects of the present invention, the floor portion of the underground pit is constructed by laying a foam material block on an uneven ground foundation layer, and placing a floor pavement layer in which concrete is cast on the foam material block. The pavement around the closed upper surface of the underground pit is laid with foam blocks on the uneven leveling layer, and water-soluble silicate and magnesium fluoride compound are placed on the upper surfaces of these foam blocks. Is formed by forming a protective layer by adding an inorganic crystal breeding material whose main component is concrete to concrete, and by forming a surface pavement layer on which concrete is cast on this protective layer. The necessary supporting force can be secured by the laid foam block without driving the pile. Therefore, even if the ground is soft, it is not necessary to drive the foundation pile, which not only eliminates the problems of vibration and noise associated with the pile driving work,
The construction period can be shortened by using a foam block that can be laid by workers manually, compared to the case of pile driving.
Also, construction costs can be saved.

【0046】また、発泡材ブロックによって必要な支持
力を確保するので、換言すると、杭による点の支持とは
異なる面による支持力なので、表面舗装に掛かる荷重を
分散して担うことができ、撓み量の減少化を図ることが
できる。したがって、集中荷重に起因する表面舗装のク
ラック乃至ひび割れの発生を確実に防止することができ
る。
Further, since the necessary supporting force is secured by the foam material block, in other words, since the supporting force is provided by a surface different from that of the point supported by the pile, the load applied to the surface pavement can be dispersed and carried. The amount can be reduced. Therefore, it is possible to reliably prevent the surface pavement from being cracked or cracked due to the concentrated load.

【0047】さらにまた、発泡材ブロックの上面に、水
溶性シリケートとマグネシウムフッ化化合物を主成分と
する無機質系結晶増殖材をコンクリートに添加した保護
層を形成し、この保護層上にコンクリートを打設した表
面舗装層を形成するので、表面舗装層のコンクリートを
無機質系結晶増殖材により緻密化を図ると共に強度の向
上を図ることができる。したがって、コンクリート舗装
面は寒暖による収縮が繰り返されても、ひび割れやクラ
ックの発生を抑制することができ、特に寒冷地における
凍害も防止することができる。
Further, on the upper surface of the foam material block, a protective layer is formed by adding an inorganic crystal breeding material containing a water-soluble silicate and a magnesium fluoride compound as main components to concrete, and concrete is cast on the protective layer. Since the provided surface pavement layer is formed, the concrete of the surface pavement layer can be densified by the inorganic crystal breeding material and the strength can be improved. Therefore, even if the concrete pavement surface is repeatedly shrunk due to cold and warm, generation of cracks and cracks can be suppressed, and frost damage in a cold region can be prevented.

【0048】そして、無機質系結晶増殖材は、保護層上
に打設したコンクリート内部に浸透していく特性を有
し、防水性(止水性)を発揮してガソリンや水等の浸透
を確実に防止することができる。このため、表面舗装に
万一クラックが発生しても、このクラックに入ったガソ
リンや水が発泡材ブロックまで到達することを確実に防
止することができ、発泡材ブロックとして発泡スチロー
ルを使用した場合に特に有益である。
The inorganic crystal breeding material has the property of penetrating into the concrete cast on the protective layer, and exhibits waterproofness (water-stopping property) to ensure penetration of gasoline, water and the like. Can be prevented. For this reason, even if a crack occurs on the surface pavement, it is possible to reliably prevent gasoline and water entering the crack from reaching the foam material block, and when styrofoam is used as the foam material block. Particularly useful.

【0049】また、表面舗装面のひび割れやクラックの
発生を有効に抑制することができるので、補修の手間や
経費を大幅に節約することができ、メンテナンスの簡略
化、簡素化を図ることができる。
Further, since the occurrence of cracks and cracks on the pavement surface can be effectively suppressed, the labor and cost for repair can be greatly reduced, and the maintenance can be simplified and simplified. .

【0050】請求項2の発明によれば、地下ピットの床
部分を構築するために敷設した発泡材ブロックの上面
に、水溶性シリケートとマグネシウムフッ化化合物を主
成分とする無機質系結晶増殖材をコンクリートに添加し
た保護層を形成し、この保護層上にコンクリートを打設
するので、床面舗装層が、車両走行路の表面舗装層と同
様に、ひび割れし難くなると共に、止水性を発揮する。
したがって、床面舗装層が万一ひび割れしたりクラック
が発生しても、タンクから漏れたガソリン等が発泡材ブ
ロックへの到達することを確実に防止することができ
る。
According to the second aspect of the present invention, an inorganic crystal breeding material containing water-soluble silicate and a magnesium fluoride compound as main components is provided on the upper surface of the foam material block laid for constructing the floor of the underground pit. Since a protective layer added to concrete is formed and concrete is poured on this protective layer, the floor pavement layer is less likely to crack and exhibits water stoppage, similarly to the surface pavement layer of a vehicle traveling road. .
Therefore, even if the floor pavement layer is cracked or cracked, it is possible to reliably prevent gasoline and the like leaking from the tank from reaching the foam material block.

【0051】請求項3の発明によれば、発泡ポリスチレ
ン製ブロックを使用するので、軽量であるがために敷設
作業が容易であり、工期の短縮化に大きく寄与する。ま
た、発泡ポリスチレン製ブロックは、断熱性に優れてい
るので、融雪機構を設置した場合に熱効率を高めること
ができ、ランニングコストを低減することができる。
According to the third aspect of the present invention, since the block made of expanded polystyrene is used, the laying work is easy because of its light weight, which greatly contributes to shortening the construction period. In addition, since the expanded polystyrene block is excellent in heat insulation, when a snow melting mechanism is installed, thermal efficiency can be increased, and running costs can be reduced.

【0052】請求項4の発明によれば、不燃物である発
泡コンクリート製ブロックを敷設するので、防火上の安
全性を一層高めることができる。
According to the fourth aspect of the invention, since the non-combustible foam concrete block is laid, the fire safety can be further enhanced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】ガソリンスタンドの平面図である。FIG. 1 is a plan view of a gas station.

【図2】地下ピットの断面図である。FIG. 2 is a sectional view of an underground pit.

【図3】地下ピットの断面図である。FIG. 3 is a sectional view of an underground pit.

【図4】床版コンクリートを一部欠截した地下ピットの
平面図である。
FIG. 4 is a plan view of an underground pit in which floor slab concrete is partially removed.

【図5】地下ピットの斜視図である。FIG. 5 is a perspective view of an underground pit.

【図6】(a)は側壁の断面図、(b)は側壁の斜視図
である。
6A is a sectional view of a side wall, and FIG. 6B is a perspective view of the side wall.

【図7】車両走行路の断面図である。FIG. 7 is a sectional view of a vehicle traveling path.

【図8】車両走行路の一部欠截斜視図である。FIG. 8 is a partially cutaway perspective view of a vehicle traveling path.

【図9】車両走行路の断面図である。FIG. 9 is a sectional view of a vehicle traveling path.

【図10】車両走行路の一部欠截斜視図である。FIG. 10 is a partially cutaway perspective view of a vehicle traveling path.

【図11】(a)は鉄筋支持金具の斜視図、(b)はそ
の正面図である。
FIG. 11A is a perspective view of a reinforcing bar support, and FIG. 11B is a front view thereof.

【図12】鉄筋を支持した状態を示す説明図であり、
(a)は交差した4本の鉄筋を、(b)は交差した3本
の鉄筋を、(c)は交差した2本の鉄筋を支持した状態
を示す説明図、(d)は交差した鉄筋を支持した状態を
示す正面図である。
FIG. 12 is an explanatory diagram showing a state where a reinforcing bar is supported,
(A) is an explanatory view showing a state in which four intersecting rebars are supported, (b) is an explanatory view showing three intersecting rebars, (c) is an explanatory view showing a state in which two intersecting rebars are supported, and (d) is an intersecting rebar. It is a front view which shows the state which supported.

【図13】(a)は枠体の斜視図、(b)は枠体の平面
図、(c)は枠体の断面図である。
13A is a perspective view of a frame, FIG. 13B is a plan view of the frame, and FIG. 13C is a cross-sectional view of the frame.

【図14】融雪機構を設けた車両走行路の一部欠截斜視
図である。
FIG. 14 is a partially cutaway perspective view of a vehicle running path provided with a snow melting mechanism.

【図15】摩擦基礎杭で支持した舗装層の断面図であ
る。
FIG. 15 is a sectional view of a pavement layer supported by a friction foundation pile.

【図16】従来のガソリンスタンドの平面図である。FIG. 16 is a plan view of a conventional gas station.

【符号の説明】[Explanation of symbols]

11 ガソリンスタンド 12 貯留タンク 13 地下ピット 14 防火壁 15 事務棟 16 キャノピー 17 車両走行路 20 自動洗車場 21 洗車場 22 基礎層 23 レベリング層 24 発泡材ブロック(発泡スチロールブロック) 25 保護層 26 床面舗装層 27 鉄筋 28 架台 29 側壁 30 支持壁 31 基礎ブロック 32 型枠 33 押え金具 34 鉄筋 35 床版コンクリート 40 基礎層 41 レベリング層 42 保護層 43 表面舗装層 44 鉄筋 45 鉄筋支持金具 46 脚部 47 脚部を形成した部材 48,49 巻き付け線部 50 打設面指標部 51 差し込み深さ規制部 52 柱 55 枠体 56 非貫通孔 57 貫通孔 60 融雪管 DESCRIPTION OF SYMBOLS 11 Gas station 12 Storage tank 13 Underground pit 14 Fire wall 15 Office building 16 Canopy 17 Vehicle running path 20 Automatic car wash 21 Car wash 22 Base layer 23 Leveling layer 24 Foam block (Styrofoam block) 25 Protective layer 26 Floor pavement layer 27 Reinforcing Bar 28 Stand 29 Side Wall 30 Supporting Wall 31 Foundation Block 32 Formwork 33 Holder 34 Reinforcing Bar 35 Floor Slab 40 Base Layer 41 Leveling Layer 42 Protective Layer 43 Surface Pavement Layer 44 Reinforcing Bar 45 Reinforcing Bar Support 46 Leg 47 Formed members 48, 49 Winding wire portion 50 Placing surface index portion 51 Insertion depth regulating portion 52 Column 55 Frame body 56 Non-through hole 57 Through hole 60 Snow melting tube

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 タンクが埋設できる深さまで排土した穴
の少なくとも底部にコンクリートを打設して地下ピット
を形成し、この地下ピット内に貯留タンクを設置し、地
下ピットの上面開口部分を塞ぐとともに、塞いだ地下ピ
ット上面をその周辺と同じ高さにコンクリートで舗装し
た施設において、 地下ピットの床部分は、不陸整正したレベリング層上に
発泡材ブロックを敷設し、これら発泡材ブロック上にコ
ンクリートを打設した床面舗装層を形成することにより
構成し、 地下ピットの閉塞上面の周辺の舗装は、不陸整正したレ
ベリング層上に発泡材ブロックを敷設し、これら発泡材
ブロックの上面に、水溶性シリケートとマグネシウムフ
ッ化化合物を主成分とする無機質系結晶増殖材をコンク
リートに添加した保護層を形成し、この保護層上にコン
クリートを打設した表面舗装層を形成することにより構
成したことを特徴とする貯留タンクを地下に埋設した施
設の構造。
1. An underground pit is formed by casting concrete at least at the bottom of a hole that has been excavated to a depth where a tank can be buried, a storage tank is installed in the underground pit, and a top opening of the underground pit is closed. At the same time, in a facility where the top surface of the closed underground pit is paved with concrete at the same height as the surrounding area, the floor of the underground pit is laid with foam blocks on uneven leveling layers, and these foam blocks are The pavement around the closed upper surface of the underground pit is laid with a foam block on the uneven leveling layer. On the upper surface, a protective layer formed by adding an inorganic crystal breeding material mainly composed of a water-soluble silicate and a magnesium fluoride compound to concrete is formed. Structure of the facility the storage tank, characterized by being configured by forming a surface pavement layer was Da設 concrete and buried underground to.
【請求項2】 地下ピットの床部分は、不陸整正した基
礎層上に発泡材ブロックを敷設し、これら発泡材ブロッ
クの上面に、水溶性シリケートとマグネシウムフッ化化
合物を主成分とする無機質系結晶増殖材をコンクリート
に添加した保護層を形成し、この保護層上にコンクリー
トを打設した床面舗装層を形成することにより構成した
ことを特徴とする請求項1に記載の貯留タンクを地下に
埋設した施設の構造。
2. The floor of an underground pit is constructed by laying a foam material block on an uneven foundation layer, and an inorganic material mainly composed of a water-soluble silicate and a magnesium fluoride compound on the foam material block. The storage tank according to claim 1, wherein a protective layer is formed by adding a system crystal breeding agent to concrete, and a floor pavement layer in which concrete is cast is formed on the protective layer. The structure of the facility buried underground.
【請求項3】 前記発泡材ブロックが、発泡ポリスチレ
ン製ブロックである請求項1または2に記載の貯留タン
クを地下に埋設した施設の構造。
3. The structure of a facility having a storage tank buried underground according to claim 1, wherein the foam material block is a block made of expanded polystyrene.
【請求項4】 前記発泡材ブロックが、発泡コンクリー
ト製ブロックである請求項1または2に記載の貯留タン
クを地下に埋設した施設の構造。
4. The structure of a facility having a storage tank buried underground according to claim 1, wherein the foam material block is a foam concrete block.
【請求項5】 タンクが埋設できる深さまで排土した穴
の少なくとも底部にコンクリートを打設して地下ピット
を形成し、この地下ピット内に貯留タンクを設置し、地
下ピットの上面開口部分を塞ぐとともに、塞いだ地下ピ
ット上面をその周辺と同じ高さにコンクリートで舗装し
た施設を施工するにあたり、 地下ピットの床部分は、穴の底部を不陸整正してレベリ
ング層を形成するレベリング層形成工程と、このレベリ
ング層上に発泡材ブロックを敷設する発泡材ブロック敷
設工程と、発泡材ブロック上にコンクリートを打設する
コンクリート打設工程とを経て構築し、 地下ピットの閉塞上面の周辺の舗装は、不陸整正してレ
ベリング層を形成するレベリング層形成工程と、このレ
ベリング層上に発泡材ブロックを敷設する発泡ブロック
敷設工程と、発泡材ブロックの上面に、水溶性シリケー
トとマグネシウムフッ化化合物を主成分とする無機質系
結晶増殖材をコンクリートに添加した保護層を形成する
保護層形成工程と、この保護層上にコンクリートを打設
するコンクリート打設工程とを経て構築することを特徴
とする貯留タンクを地下に埋設した施設の施工法。
5. An underground pit is formed by casting concrete at least at the bottom of a hole that has been excavated to a depth at which the tank can be buried, a storage tank is installed in the underground pit, and an upper opening of the underground pit is closed. At the same time, when constructing a facility in which the top surface of the closed underground pit is paved with concrete at the same height as the surrounding area, the floor of the underground pit will have a leveling layer to form a leveling layer by leveling the bottom of the hole. Pavement around the closed upper surface of the underground pit by constructing through a process, a foam block laying process of laying a foam block on the leveling layer, and a concrete casting process of casting concrete on the foam block. A leveling layer forming step of forming a leveling layer by adjusting unevenness, and laying a foam block on the leveling layer to lay a foam material block A protective layer forming step of forming a protective layer by adding an inorganic crystal breeding material containing water-soluble silicate and magnesium fluoride compound as main components to concrete on the upper surface of the foam material block; A method of constructing a facility in which a storage tank is buried underground, which is constructed through a concrete placing step of placing concrete.
JP8215988A 1996-07-30 1996-07-30 Construction of facility embedding underground storage tank and its working method Pending JPH1037221A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8215988A JPH1037221A (en) 1996-07-30 1996-07-30 Construction of facility embedding underground storage tank and its working method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8215988A JPH1037221A (en) 1996-07-30 1996-07-30 Construction of facility embedding underground storage tank and its working method

Publications (1)

Publication Number Publication Date
JPH1037221A true JPH1037221A (en) 1998-02-10

Family

ID=16681556

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8215988A Pending JPH1037221A (en) 1996-07-30 1996-07-30 Construction of facility embedding underground storage tank and its working method

Country Status (1)

Country Link
JP (1) JPH1037221A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002235369A (en) * 2001-02-09 2002-08-23 Hitachi Chem Co Ltd Underground tank embedding method and concrete pit for embedding underground tank
CN106760707A (en) * 2016-11-21 2017-05-31 常州第建筑集团有限公司 Trench abnormity branch mouthful embedded iron construction method
JP2019085759A (en) * 2017-11-06 2019-06-06 鹿島建設株式会社 Concrete structure
CN114045873A (en) * 2021-11-29 2022-02-15 中建五局土木工程有限公司 Backfilling and waterproof green construction method for station structure top pit slot

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002235369A (en) * 2001-02-09 2002-08-23 Hitachi Chem Co Ltd Underground tank embedding method and concrete pit for embedding underground tank
CN106760707A (en) * 2016-11-21 2017-05-31 常州第建筑集团有限公司 Trench abnormity branch mouthful embedded iron construction method
CN106760707B (en) * 2016-11-21 2019-01-29 常州第一建筑集团有限公司 Trench abnormity branch mouth embedded iron construction method
JP2019085759A (en) * 2017-11-06 2019-06-06 鹿島建設株式会社 Concrete structure
CN114045873A (en) * 2021-11-29 2022-02-15 中建五局土木工程有限公司 Backfilling and waterproof green construction method for station structure top pit slot
CN114045873B (en) * 2021-11-29 2023-04-28 中建五局土木工程有限公司 Backfilling and waterproof green construction method for pit slot at top of station structure

Similar Documents

Publication Publication Date Title
CN111042185B (en) Construction method of basement raft foundation with tower crane foundation
JP2002506942A (en) Method of forming a load transfer performance by connecting concrete members
US10267011B2 (en) Pre-cast decorative retaining wall system
CN107747261A (en) A kind of new Soft Clay seasonal frozen soil region highway subgrade structure and construction method
US10053833B2 (en) Pre-cast decorative retaining wall system
JPH1037221A (en) Construction of facility embedding underground storage tank and its working method
CN113026461A (en) Reinforced foam concrete roadbed structure and roadbed filling method
US1707391A (en) Method of repairing cuts in pavements
CN108193706A (en) A kind of downward construction concrete pouring procedure of part contrary sequence method vertical structure
CN110331740B (en) Waterproof construction method for underground engineering
Meyer et al. Precast repair of CRC Pavements
KR100332085B1 (en) method for laying of pipe and structure for layind the same
EP2356287B1 (en) Monolithic foundation system
WO2007073570A1 (en) Building block
RU2345191C2 (en) Unstable ground thermostructural foundation
WO2005042854A1 (en) Foundations and bases for buildings
RU2802766C1 (en) Multilayer mat for device of road embanking and method for its manufacture
CN109667278A (en) Tower crane anti-cracking and seepage control construction method is set under underground garage isolated footing
US1953920A (en) Protected concrete structure
JPH07310329A (en) Foundation structure of building and construction method thereof
CN114318991B (en) Highway bench back structure in plain area, highway structure and construction method
CN111074933B (en) Construction method of plate rib type cast-in-place anchor rod high retaining wall
CN107882021B (en) Concrete filled steel tube reference stake and construction method
JP2876452B2 (en) Retaining wall construction method
JP2604380Y2 (en) Construction member for railway station platform and structure using the same