JPH10121573A - Half-precast concrete member and construction method of structure - Google Patents

Half-precast concrete member and construction method of structure

Info

Publication number
JPH10121573A
JPH10121573A JP27953396A JP27953396A JPH10121573A JP H10121573 A JPH10121573 A JP H10121573A JP 27953396 A JP27953396 A JP 27953396A JP 27953396 A JP27953396 A JP 27953396A JP H10121573 A JPH10121573 A JP H10121573A
Authority
JP
Japan
Prior art keywords
column
floor
precast concrete
concrete
slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP27953396A
Other languages
Japanese (ja)
Inventor
Takeo Seguchi
健夫 瀬口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP27953396A priority Critical patent/JPH10121573A/en
Publication of JPH10121573A publication Critical patent/JPH10121573A/en
Pending legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a construction method of a structure, reducing the number of PCa members applied and using PCa members which can be constructed without use of outside scaffolds or the like and half-PC members used for the construction. SOLUTION: Half-PC members H composed of gate-shaped thin plate members in which the reinforcement part positioned at the outer peripheral side in the column reinforcements and the beam reinforcements is embedded so that a pair of column reinforcements 4, 5 oppositely arranged with a specifeid distance are integrally formed with beam reinforcements 7, 9 arranged astride over the column reinforcements 4, 5, are erected so as to paralelly arrange. And reinforcements connecting mutual column parts adjacent to each other of the adjacent half-precast concrete members, are arranged. Subsequently, concrete for the columns is placed up to the height of the end of the underfloor. Floor slabs are supported on the upper ends of columns constructed by placing concrete to construct slabs or the like.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、ハーフプレキャス
トコンクリート(以下、ハーフPCと呼ぶ)部材の構
造、及びそのハーフPC部材によるプレキャストコンク
リートを使用した構造物の構築方法に関するものであ
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a structure of a half precast concrete (hereinafter referred to as "half PC") member and a method of constructing a structure using the precast concrete using the half PC member.

【0002】[0002]

【従来の技術】構造物外周を鉄筋コンクリート造りの柱
梁構造で構成し、内部に梁を設けずに床のみで構成して
大空間を確保する構造物を、プレキャストコンクリート
(以下、PCaと呼ぶ)部材の組み立てによって構築す
る場合、従来にあっては、PCa柱部材、PCa梁部
材、PCa床部材のように、予め各部位単位にPCa化
を行う。
2. Description of the Related Art Precast concrete (hereinafter, referred to as PCa) is a structure in which the outer periphery of a structure is made of a reinforced concrete column-beam structure, and a large space is secured by using only a floor without a beam inside. In the case of building by assembling members, conventionally, PCa is formed in advance for each part, such as a PCa column member, a PCa beam member, and a PCa floor member.

【0003】そして、立設させたPCa柱部材間にPC
a梁部材を横架し、その柱梁接合部に、現場で、柱フー
プ筋等を配筋した後、柱梁接合部の外周全周を囲うよう
に型枠を配置しコンクリートを打設してPCa柱部材と
PCa梁部材とを接合する。また、梁間にPCa床部材
を敷き並べてスラブを構築する。
[0003] Then, the PC is provided between the PCa columns which are erected.
a After arranging a beam member horizontally, arranging a column hoop, etc. at the column-beam joint at the site, placing a formwork around the entire outer periphery of the column-beam joint and placing concrete. To join the PCa column member and the PCa beam member. A slab is constructed by laying PCa floor members between the beams.

【0004】これを順次行って構造物の上部を順次,構
築する。
[0004] This is sequentially performed to sequentially build the upper part of the structure.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、一般
に、PCa柱部材の長さは、床上面から上階の梁下端面
までの長さであり、また、PCa梁部材は、その端部を
PCa柱部材の上端面に数センチメートル載せる程度の
長さの部材構成であるので、上述のように、現場におい
て、柱梁接合部に配筋を行いコンクリートの打設作業が
行われるが、その際に外周部の目地が揃わないおそれが
ある。
However, in general, the length of the PCa column member is the length from the upper surface of the floor to the lower end surface of the beam on the upper floor, and the end of the PCa beam member has a PCa column. Because it is a member configuration with a length of about several centimeters placed on the upper end surface of the member, as described above, at the site, reinforcement is arranged at the beam-column joint and concrete placing work is performed. The joints at the outer peripheral portion may not be aligned.

【0006】またこのとき、構造物の外周側の側面型枠
が必要になるなど、この作業のために構造物の外周側に
も足場を必要とする。つまり、外部足場を必要とするの
で、施工する階が高層となるほど作業の安全性が低くな
る。
At this time, a scaffold is also required on the outer peripheral side of the structure for this operation, such as the need for a side formwork on the outer peripheral side of the structure. That is, since an external scaffold is required, the higher the floor to be constructed, the lower the work safety.

【0007】また、構造物の外壁の仕上げをタイルや石
貼りとする場合を想定すると、PCa柱部材やPCa梁
部材として、構造物外面を構成する面にタイル等の仕上
材を打ち込んだPCa部材を使用したとしても、柱梁接
合部においては目地が多く、後からタイル等を貼るか、
又はこれらの材料等を予め打ち込んだ打ち込み型枠を使
用する必要がある。
Further, assuming that the exterior wall of the structure is to be finished with tiles or stones, a PCa member having a PCa column member or a PCa beam member in which a finishing material such as a tile is driven into the surface constituting the outer surface of the structure. Even if is used, there are many joints at the beam-column joint,
Alternatively, it is necessary to use a driving form in which these materials are driven in advance.

【0008】このとき、現場でタイル等を貼る場合に
は、PCa柱部材の仕上面より内側に型枠を設置し、タ
イルや石の貼り代を残す必要があり、また、打ち込み型
枠を使用した場合には、打ち込み型枠の厚さだけ予めP
Ca柱の断面を大きくする必要があるなどの問題点を有
している。
[0008] At this time, when the tiles and the like are stuck on the site, it is necessary to install a formwork inside the finishing surface of the PCa column member and leave a margin for the tiles and stones. In this case, P
There are problems such as the necessity of increasing the cross section of the Ca column.

【0009】また、上記従来の構築では、PCa柱部材
の形状は、全柱断面をPCa化しているため、PCa柱
部材の1ピース当たりの重量が大きくなる。この結果、
PCa部材の建方に大型の揚重機が必要になるなどの問
題もある。
Further, in the above-mentioned conventional construction, since the shape of the PCa column member is such that the entire column cross section is made into PCa, the weight per piece of the PCa column member increases. As a result,
There is also a problem that a large lifting machine is required to build the PCa member.

【0010】さらに、上述のように各部位を個々にPC
a部材で構成すると、使用するPCa部材の個数が多く
なる。この結果、PCa部材の組み立てに要する時間や
工数が多くなり、工期短縮などの面で不利である。
Furthermore, as described above, each part is individually
When it is composed of the member a, the number of PCa members used increases. As a result, the time and man-hours required for assembling the PCa member are increased, which is disadvantageous in terms of shortening the construction period.

【0011】なお、PCa部材を使用しないで、現場で
型枠の組み立て、配筋、コンクリートの打設を行って柱
や梁を構築する方法も考えられるが、この場合には、多
くの熟練技能を有する作業員や仮設資機材を必要とし、
作業環境面・安全性・工期・品質などの各面で問題を有
し、これらの問題解消が要求される。
In addition, a method of assembling a formwork, arranging reinforcement, and placing concrete on site to construct a column or a beam without using a PCa member can be considered. In this case, however, many skilled skills are required. Need temporary workers and temporary equipment
There are problems in various aspects such as working environment, safety, construction period, quality, etc., and it is required to solve these problems.

【0012】本発明は、上記のような問題点に着目して
なされたもので、使用するPCa部材の個数を減らすと
共に外部足場等を使用することなく構築可能なPCa部
材を使用した構造物の構築方法及びその構築に使用され
るハーフPC部材を提供することを課題としている。
SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned problems, and is intended to reduce the number of PCa members to be used and to provide a structure using a PCa member that can be constructed without using an external scaffold or the like. It is an object to provide a construction method and a half PC member used for the construction.

【0013】[0013]

【課題を解決するための手段】上記課題を解決するため
に、本発明のうち請求項1に記載のハーフプレキャスト
コンクリート部材は、所定間隔をあけて対向配置した一
対の柱鉄筋及びその柱鉄筋間に跨がる梁鉄筋と一体に成
形されるように、当該柱鉄筋及び梁鉄筋のうち構造物の
外周側に位置する鉄筋部分を埋め込んだ門型形状の薄肉
板状部材からなることを特徴としている。
In order to solve the above-mentioned problems, a half precast concrete member according to the first aspect of the present invention comprises a pair of column reinforcing bars opposed to each other at a predetermined interval and a pair of column reinforcing bars. It is composed of a gate-shaped thin plate-shaped member in which a reinforcing bar portion of the column reinforcing bar and the beam reinforcing bar located on the outer peripheral side of the structure is embedded so as to be integrally formed with the beam reinforcing bar straddling. I have.

【0014】本発明によれば、薄肉板状とすることで、
PCa部材の軽量化が図られる。また、構造物の外周側
では柱梁接合部が一体的となっているので、構造物の外
周側からの柱梁接合のための作業、例えば建物外周側の
型枠設置作業等の施工が不要になる。
[0014] According to the present invention, by forming a thin plate,
The weight reduction of the PCa member is achieved. In addition, since the beam-to-column joints are integrated on the outer peripheral side of the structure, there is no need to perform work for beam-to-column joints from the outer peripheral side of the structure, such as installation of formwork on the outer peripheral side of the building. become.

【0015】次に、請求項2に記載の発明は請求項1に
記載の構成に対し、梁部のプレキャストコンクリート
は、その下部が構造物の内周側に張り出して断面L形と
なっていることを特徴としている。
Next, according to a second aspect of the present invention, in contrast to the first aspect, the precast concrete of the beam portion has an L-shaped cross section with its lower portion projecting toward the inner peripheral side of the structure. It is characterized by:

【0016】本発明によれば、梁構築のための底部の型
枠が不要となると共に、床版の支持部を増加させること
ができる。次に、請求項3に記載の発明は、請求項1又
は請求項2に記載された構成に対し、コンクリートに埋
め込まれた柱主筋の上端部及び下端部の少なくも一方
に、上層又は下層の柱鉄筋との接続を行う接続金物を備
えることを特徴としている。
According to the present invention, a bottom formwork for beam construction is not required, and the number of support portions of the floor slab can be increased. Next, the invention according to claim 3 is different from the structure according to claim 1 or claim 2 in that at least one of the upper end and the lower end of the pillar main bar embedded in concrete has an upper layer or a lower layer. It is characterized by having a connection hardware for connection with the column reinforcing bar.

【0017】この発明においては、接続金物を備えるこ
とで、上下のハーフプレキャストコンクリート部材の柱
主筋同士の接続が容易となる。次に、請求項4に記載の
発明である構造物の構築方法は、上記請求項1から請求
項3のいずれかに記載されたハーフプレキャストコンク
リート部材を並べるように建方を行い、隣合うハーフプ
レキャストコンクリート部材の隣接する柱部分同士を接
続する補強鉄筋を配置した後、床下端部の高さまで柱用
コンクリートを打設し、その打設して構築した柱上端部
に床版を支持させることを特徴としている。
In the present invention, the provision of the connecting hardware facilitates the connection between the column main reinforcements of the upper and lower half precast concrete members. Next, in the construction method of a structure according to the invention described in claim 4, the half precast concrete members according to any one of claims 1 to 3 are constructed so that the half precast concrete members are arranged side by side. After arranging reinforcing bars that connect adjacent column parts of the precast concrete member, cast concrete for the column up to the height of the floor bottom, and support the floor slab at the column top constructed by casting. It is characterized by.

【0018】本発明においては、並べて建方をした、隣
合うハーフプレキャストコンクリート部材の柱部同士が
補強鉄筋で所定の強度をもって一体化し、また、打設し
た柱部のコンクリートの天端で床版が支持される。
In the present invention, the columns of adjacent half precast concrete members, which are arranged side by side, are integrated with a predetermined strength by reinforcing steel, and the concrete slabs of the cast column are joined by the floor slab. Is supported.

【0019】次に、請求項5に記載の発明は、請求項4
の構成に対し、上記床版はプレキャストコンクリート板
であって、その板の上に中空部材が設置され、コンクリ
ートを打設することでスラブが構築されることを特徴と
している。
Next, the invention according to claim 5 is directed to claim 4
In contrast to the above configuration, the floor slab is a precast concrete plate, a hollow member is installed on the plate, and a slab is constructed by casting concrete.

【0020】本発明においては、中空部材が設置される
ことで、スラブが軽量化し、その分だけスラブを大きく
とれる。次に、請求項6に記載の発明は、請求項4の構
成に対し、上記床版は、逆梁床版であって、その床版の
上に2重床を構築することを特徴としている。
In the present invention, the provision of the hollow member reduces the weight of the slab, and the slab can be made larger by that amount. Next, according to a sixth aspect of the present invention, in addition to the configuration of the fourth aspect, the floor slab is a reverse beam slab, and a double floor is constructed on the floor slab. .

【0021】本発明においては、床版に逆梁を備えた逆
梁床版を使用することで、床版の曲げ剛性が大きくなる
と共に、上部に大きな突出部を設けることがないので、
OAフロア等の2重床構造を採用可能となる。
In the present invention, by using a reverse beam slab having a reverse beam on the floor slab, the flexural rigidity of the floor slab is increased, and a large protrusion is not provided at the upper portion.
A double floor structure such as an OA floor can be adopted.

【0022】[0022]

【発明の実施の形態】次に、本発明の実施の形態を図面
に基づいて説明する。まず、ハーフPC部材Hの構成に
ついて、図1及び図3を参照しつつ説明する。
Next, an embodiment of the present invention will be described with reference to the drawings. First, the configuration of the half PC member H will be described with reference to FIGS.

【0023】ハーフPC本体は、図1に示すように、所
定間隔をあけて対向する一対の柱部1と、その柱部1の
上部間を連結する梁部2とからなる薄肉の門型形状をし
たPCa部材であって、その横方向の長さL1は、構造
物の壁柱中心軸間の1スパン分の長さに設計されてい
る。
As shown in FIG. 1, the half PC main body has a thin, gate-like shape comprising a pair of pillars 1 facing each other at a predetermined interval and a beam 2 connecting the upper portions of the pillars 1 to each other. The length L1 in the lateral direction is designed to be one span between the center axes of the wall columns of the structure.

【0024】また、各柱部1の幅L2は、構造物の外周
面側の壁柱を壁柱断面の中心軸で2分割した幅であり、
また、柱部1の高さ方向の長さL3は、当該階の梁天端
から上階の梁天端までの1層分と同じ長さに設定されて
いる。
The width L2 of each pillar 1 is a width obtained by dividing the wall pillar on the outer peripheral surface side of the structure into two by the center axis of the wall pillar cross section.
The length L3 of the column 1 in the height direction is set to the same length as one layer from the beam top end of the floor to the beam top end of the upper floor.

【0025】その柱部1の厚さL4は、図2に示すよう
に、構造物の最外周側の柱主筋4を埋設するだけの薄肉
厚に設計され、また、柱部1に柱鉄筋の一部である柱フ
ープ筋5の一部(構造物外周側部分)が埋設されて当該
柱フープ筋5も柱部1と一体に成形されている。
As shown in FIG. 2, the thickness L4 of the column portion 1 is designed to be thin enough to bury the column main bar 4 on the outermost peripheral side of the structure. A part of the column hoop 5 (the outer peripheral portion of the structure), which is a part, is buried, and the column hoop 5 is also formed integrally with the column 1.

【0026】上記柱部1に埋設されている柱主筋4は、
その脚部4aには鉄筋接合金物6を取り付けた状態で埋
設され、下側ある柱鉄筋の柱頭部との接合が容易となっ
ている。また、当該埋設された柱主筋4の柱頭部4b
は、柱部1の天端から所定長だけ突出して、上階の柱主
筋4に対し鉄筋接合金物等によって接合可能となってい
る。
The column main reinforcement 4 buried in the column 1 is
The leg 4a is buried with the reinforcing metal fitting 6 attached thereto, so that it can be easily connected to the column head of the lower column reinforcing bar. Also, the column cap 4b of the buried column main bar 4
Protrudes from the top end of the column portion 1 by a predetermined length, and can be joined to the column main reinforcing bar 4 on the upper floor by a reinforcing metal joint or the like.

【0027】また、上記柱部1間を繋いでいる梁部2
も、上記図1及び図3に示すように、本体が構造物の最
外周側の梁主筋7だけを埋設する程度の厚さL5の薄肉
に設計されている。但し、その下部に構造物の内側に張
り出す張出部2aを備えることで、梁部2は、全体とし
て梁断面L字形状となっている。
Further, a beam 2 connecting the pillars 1 is provided.
Also, as shown in FIGS. 1 and 3, the main body is designed to be thin with a thickness L5 such that only the main beam 7 on the outermost peripheral side of the structure is embedded. However, by providing a projecting portion 2a projecting inside the structure below the beam portion 2, the beam portion 2 has an L-shaped beam cross section as a whole.

【0028】即ち、梁部2の下部は、梁断面の全梁幅を
有して下端梁主筋7,8の全部を埋設し、その張出部2
aの高さ方向の厚さL6は、この梁部2で支持される床
版の下端部までが張り出すようにPCa化している。な
お、この張出部2aは、両柱部1の梁部2と接する面ま
で形成されている。
That is, the lower part of the beam portion 2 has the entire beam width of the beam cross section and embeds all the lower end beam main reinforcements 7 and 8, and the overhang portion 2
The thickness L6 in the height direction of a is made into PCa so that the lower end of the floor slab supported by the beam portion 2 protrudes. In addition, the overhang portion 2a is formed up to the surface of both pillars 1 that is in contact with the beam 2.

【0029】また、梁用スターラップ筋9の一部(構造
物の外周側部分)も梁部2に埋設されて当該梁部2と一
体に成形されている。ここで、上記梁部2に埋設されて
いる構造物の最外周側の梁主筋7の両端部は柱部1の上
部(柱梁接合部)に埋設されている。その他の梁部2に
埋設された梁主筋8の両端部8aは露出した状態となっ
ている。
Further, a part of the beam stirrup 9 (the outer peripheral portion of the structure) is also buried in the beam 2 and is formed integrally with the beam 2. Here, both ends of the beam main reinforcement 7 on the outermost periphery side of the structure embedded in the beam portion 2 are embedded in the upper portion of the column portion 1 (column-beam joint portion). Both end portions 8a of the beam main reinforcement 8 buried in the other beam portions 2 are exposed.

【0030】次に、上記構成のハーフPC部材Hからな
るPCa部材を使用した構造物の構築について説明す
る。先行して構築された下階部分の柱部1の天端から突
出する下階の柱鉄筋の柱頭部と、対象階に設置するハー
フPC部材Hの柱主筋4の脚部4aとを、鉄筋接合金物
6で接合するようにして立設させる。これを構造物の外
周面に沿って順次隣合わせるように組み立ることで建方
を行い(図8若しくは図9を参照)、これらハーフPC
部材Hによって対象とする階の構造物の外周面を構成す
る。
Next, the construction of a structure using the PCa member composed of the half PC member H having the above configuration will be described. The column heads of the column reinforcing bars of the lower floor projecting from the top end of the column portion 1 of the lower floor portion constructed in advance, and the legs 4a of the column main reinforcing bars 4 of the half PC member H installed on the target floor are reinforced. It is erected so as to be joined with the joint hardware 6. By assembling them so as to be adjacent to each other sequentially along the outer peripheral surface of the structure (see FIG. 8 or FIG. 9), the half PC
The member H forms the outer peripheral surface of the structure on the target floor.

【0031】このとき、隣合うハーフPC部材Hの隣接
する2つ柱部1によって一つの壁柱を構成するように、
図4に示すように、その隣接する柱部1のそれぞれと一
体になっている柱フープ筋5の露出部分同士をフープ筋
からなる補強鉄筋10で連結するように当該補強鉄筋1
0を配筋する。
At this time, one wall column is constituted by two adjacent column portions 1 of the adjacent half PC member H.
As shown in FIG. 4, the exposed portions of the column hoops 5 integrated with each of the adjacent column portions 1 are connected to each other by a reinforcing bar 10 made of a hoop.
Arrange 0 bars.

【0032】また、柱部1に埋設した柱主筋4以外の柱
主筋11、つまり上記補強鉄筋10で囲まれた部分の柱
主筋11の配筋を行う。この柱主筋11の脚部も、下階
の柱主筋4と接合させる。
Further, the bar main bars 11 other than the column main bars 4 embedded in the column portion 1, that is, the column main bars 11 in the portion surrounded by the reinforcing steel bars 10 are arranged. The leg of the column main bar 11 is also joined to the column main bar 4 on the lower floor.

【0033】さらに、図5に示すように、隣合うハーフ
PC部材Hから露出して対向する各梁下端主筋8の両端
部8a同士を柱梁接合部でエンクローズ溶接等により接
合する。ここで、12は主筋8巻の接合部である。
Further, as shown in FIG. 5, both end portions 8a of the main beams 8 at the lower ends of the beams, which are exposed from the adjacent half PC members H and are opposed to each other, are joined to each other at column-beam joint portions by enclosure welding or the like. Here, reference numeral 12 denotes a joint portion of eight main bars.

【0034】次に、柱部1の構造物内部側面型枠13
を、上記図4、図5、及び柱部1での断面図である図6
に示すように、上階の床下端(張出部2aと同じ高さ)
まで組み立て、この高さまでコンクリート14を打設し
て、柱中心軸で分割された柱を一体化する。ここで、上
記型枠について、構造物外周部位置は、柱部1自身が型
枠の役割をするため、構造物外周側の型枠は不要とな
る。
Next, the frame 13 inside the structure of the pillar 1
4 and FIG. 5 and FIG.
As shown in the figure, the floor bottom of the upper floor (the same height as the overhang 2a)
And the concrete 14 is poured to this height to integrate the columns divided by the column center axis. Here, regarding the above-mentioned formwork, since the pillar portion 1 itself functions as a formwork at the position of the structure outer peripheral portion, the formwork on the structure outer peripheral side becomes unnecessary.

【0035】次に、上記図6及び梁部2での断面図であ
る図7、及び図8に示すように、上記打設して構築した
柱の上端面及び梁部2の張出部2aに載せるようにして
床版を構成するハーフPC床版16を敷き並べ、その
後、梁上端主筋17、床配筋18を行うと共に、梁用及
び柱梁接合部用の型枠19を取付けた後に、床及び梁用
のコンクリート20を打設して構造物の対象とする階層
部分を構築する。
Next, as shown in FIG. 6 and FIGS. 7 and 8, which are cross-sectional views of the beam portion 2, the upper end surface of the column constructed by casting and the projecting portion 2a of the beam portion 2 are formed. The half PC floor slabs 16 constituting the floor slab are laid out so as to be placed on the floor, and thereafter, the beam upper main reinforcement 17 and the floor reinforcement 18 are performed, and after the formwork 19 for the beam and the beam-column joint is attached. Then, concrete 20 for floors and beams is cast to construct a layer portion to be a target of the structure.

【0036】このとき、柱部1及び梁部2が構造物外周
側の型枠の役割を有するので、構造物外周側に型枠を設
置する必要はない。ここで、上記実施の形態のスラブの
構築は、ハーフPC床版16を敷き並べ後にコンクリー
ト20を打設して構築しているが、ハーフPC床版の上
に中空型枠(中空部材)を設置した後にコンクリートを
打設して、スラブ内に中空部を設けることで、スラブの
軽量化を図り、これによって、小梁を設けなくても大き
なスラブを構築可能としてもよい。なお、このときに
は、ハーフPC床版から突設するトラス筋の成を高くし
てスラブの曲げ耐力を大きく設定するとよい。
At this time, since the pillar portion 1 and the beam portion 2 have a role of a formwork on the outer peripheral side of the structure, there is no need to install a formwork on the outer peripheral side of the structure. Here, the slab of the above embodiment is constructed by laying half PC floor slabs 16 and then casting concrete 20 therein. However, a hollow mold (hollow member) is placed on the half PC floor slab. By placing concrete after installation and providing a hollow portion in the slab, the weight of the slab may be reduced, thereby making it possible to construct a large slab without providing small beams. At this time, it is preferable to increase the bending strength of the slab by increasing the strength of the truss bars projecting from the half PC slab.

【0037】又は、床版自体に空洞をもつプレストレス
コンクリート板を床版として採用してスラブの軽量化を
図ってもよい。また、上記床版として逆梁床版を使用し
て要求されるスラブの曲げ剛性を確保すると共に、その
逆梁床版の上に、OAフロア等の2重床を構築してもよ
い。
Alternatively, a prestressed concrete plate having a cavity in the floor slab itself may be employed as the floor slab to reduce the weight of the slab. Moreover, while using a reverse beam slab as the floor slab, the required bending rigidity of the slab may be ensured, and a double floor such as an OA floor may be constructed on the reverse beam slab.

【0038】以上のような施工を順次行って所定の階層
の構造物を構築する。なお、柱部1に直交する方向に梁
を設ける場合には、図9に示すように、柱部1に直交す
る方向に接続用の梁鉄筋20を突設させたハーフPC部
材Hを使用すればよい。
The above construction is sequentially performed to construct a structure of a predetermined hierarchy. When a beam is provided in a direction orthogonal to the column 1, as shown in FIG. 9, a half PC member H in which a beam reinforcing bar 20 for connection protrudes in a direction orthogonal to the column 1 may be used. I just need.

【0039】このように、本実施形態のハーフPC部材
Hを使用して上述のように構造物を構築する場合には、
ハーフPC部材Hの外面が構造物の外壁部を構成し、し
かも、その構造物の外周側部分では、ハーフPC部材H
の柱部1と梁部2の接合部は一体化しているので、従来
のように、現場施工である柱梁接合部分の外壁部にタイ
ル等の仕上部材を貼り付ける必要が必ずもない。従っ
て、従来の打ち込みPCa型枠で行う場合のように打ち
込み型枠分の厚さを必要としないため、構造物は、構造
上必要な断面のみで構成される。この結果、躯体重量の
面で合理的な設計が可能となる。
As described above, when the structure is constructed as described above using the half PC member H of the present embodiment,
The outer surface of the half PC member H constitutes the outer wall of the structure, and the half PC member H
Since the joint portion between the column portion 1 and the beam portion 2 is integrated, it is not always necessary to attach a finishing member such as a tile to the outer wall portion of the column-beam joint portion that is constructed on site, unlike the related art. Accordingly, the structure does not need the thickness of the driving formwork as in the case of the conventional driving PCa formwork, so that the structure is composed only of a structurally necessary cross section. As a result, a rational design is possible in terms of the frame weight.

【0040】また、従来のように構造物外部側の型枠作
業が不要となるので、外部足場を必要としない。このた
め、その分だけ作業の安全源が確保されう。また、従来
の方法では、各PCa部材の接合を柱梁接合部で行って
いるので、構造物外部側の仕上がタイルや石貼り等の場
合、目地が複雑となって揃わないおそれがあったが、本
実施形態では、PCa部材の接合は、壁柱の芯のみで行
われるため、目地が一本の線上となり、目地が確実に揃
う。
In addition, since there is no need to perform a mold work on the outside of the structure as in the related art, an external scaffold is not required. Therefore, a safe source of work can be ensured by that much. In addition, in the conventional method, since the joints of the PCa members are performed at the beam-column joints, when the finish on the outer side of the structure is tile or stone, the joints may be complicated and may not be aligned. However, in this embodiment, since the joining of the PCa members is performed only at the core of the wall pillar, the joints are on one line, and the joints are surely aligned.

【0041】また、PCa部材として、上述のようなハ
ーフPC部材Hを使用することで、柱梁部2が一体のP
Ca部材となっているため、PCa部材間の組み立てに
要する時間及び工程数が低減する。従って、施工が簡略
化すると共に、構造物を構築する工期の短縮に繋がる。
Further, by using the half PC member H as described above as the PCa member, the column and beam portion 2 can be integrated with the P member.
Since it is a Ca member, the time and the number of steps required for assembling the PCa members are reduced. Therefore, the construction is simplified and the construction period for constructing the structure is shortened.

【0042】また、PCa部材も、構造物の最外周側の
鉄筋だけが埋設される程度の薄肉のハーフPCa部材で
あるので、1ピース当たりのPCa部材の重量も軽くな
り、当該PCa部材を吊り上げ組み立てる際に使用され
るクレーン等の揚重機も小型のものが使用可能となる。
The PCa member is also a thin half PCa member in which only the outermost reinforcing bar of the structure is buried, so that the weight of the PCa member per piece is reduced, and the PCa member is lifted. A small lifting machine such as a crane used for assembling can be used.

【0043】また、上記説明では、隣接する柱部1を連
結する補強鉄筋10としてフープ筋を例示して説明した
が、フープ筋に限定されない。要は、柱部1相互の柱フ
ープ筋5等が連結できればよいので、スターラップ筋状
の鉄筋やU字状の鉄筋を使用してもよい。
Further, in the above description, the hoop rebar has been described as an example of the reinforcing bar 10 for connecting the adjacent column portions 1, but the present invention is not limited to the hoop rebar. In short, it is only necessary that the column hoop bars 5 and the like of the column portions 1 can be connected to each other. Therefore, a stirrup-shaped reinforcing bar or a U-shaped reinforcing bar may be used.

【0044】また、上記実施の形態では、ハーフPC部
材Hの梁部2の断面をL字形状として床版16を載置可
能としているが、必ずしも張出部2aを設けてL字形状
とする必要はない。但し、断面L字形状とした方が、床
版16の支持部が大きくなり、その分だけスラブを大き
くとることができる。
In the above-described embodiment, the cross section of the beam portion 2 of the half PC member H is L-shaped so that the floor slab 16 can be placed thereon. No need. However, when the section is L-shaped, the supporting portion of the floor slab 16 becomes larger, and the slab can be made larger by that amount.

【0045】また、上記実施の形態では、柱主筋4の脚
部4aに接続金物を設けた例で説明しているが、柱主筋
4の上端部に接続金物を設けるようにしてもよい。
Further, in the above-described embodiment, an example is described in which the connecting hardware is provided on the leg 4a of the column main reinforcing bar 4. However, the connecting hardware may be provided on the upper end of the column main reinforcing bar 4.

【0046】[0046]

【発明の効果】以上説明してきたように、本発明のハー
フプレキャストコンクリート部材、及び、構造物の構築
方法を採用すると、各PCa部材の重量が軽量化すると
共に、使用するPCa部材数も少なくて済む。この結
果、組み立て時間が早くなり、構造物の構築の工期の短
縮化に繋がるという効果がある。
As described above, when the half precast concrete member and the method of constructing a structure according to the present invention are employed, the weight of each PCa member is reduced and the number of PCa members used is reduced. I'm done. As a result, there is an effect that the assembling time is shortened and the construction period of the structure is shortened.

【0047】また、構造物外周部の接合のための目地が
少なくなると共に、外壁にタイル等の仕上材を貼り付け
る場合であっても当該仕上際のダメが無くなるという効
果がある。
Further, joints for joining the outer peripheral portion of the structure are reduced, and even when a finishing material such as a tile is stuck on the outer wall, there is an effect that the finishing is eliminated.

【0048】また、構造物外周側の柱梁接合部の構築の
ために構造物外周側の側面型枠が不要となるので、外部
足場が不要となり施工上の安全性が向上するという効果
がある。
Further, since the side formwork on the outer peripheral side of the structure is not required for constructing the beam-to-column joint on the outer peripheral side of the structure, there is no need for an external scaffold, and the construction safety is improved. .

【0049】さらに、請求項2記載の発明を採用する
と、梁構築の際の底部の型枠が不要となると共に、床版
の支持部が増加して、その分だけ床版を大きくとること
が可能となるという効果がある。
Further, when the invention according to the second aspect is adopted, the formwork at the bottom at the time of constructing the beam becomes unnecessary, and the number of support portions of the floor slab is increased. There is an effect that it becomes possible.

【0050】また、請求項3に記載した発明を採用する
と、上下のハーフPC部材の接続が容易に実施可能とな
るという効果がある。また、請求項5に記載の発明を採
用すると、床スラブの軽量化が図られ、小梁のないスラ
ブを大きくとることが可能となるという効果がある。
Further, when the invention described in claim 3 is adopted, there is an effect that the connection of the upper and lower half PC members can be easily performed. Further, when the invention described in claim 5 is employed, the weight of the floor slab can be reduced, and there is an effect that a slab without small beams can be made large.

【0051】また、請求項6に記載の発明を採用する
と、逆梁によって床版に所定の曲げ剛性が確保されて、
床スラブを大きくしつつ、その上部を2重床構造とする
ことができるという効果がある。
Further, when the invention according to claim 6 is adopted, a predetermined bending rigidity is secured to the floor slab by the inverted beam,
There is an effect that the floor slab can have a double floor structure while the size of the floor slab is large.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施の形態に係るハーフPC部材を示
す全体図である。
FIG. 1 is an overall view showing a half PC member according to an embodiment of the present invention.

【図2】本発明の実施の形態に係るハーフPC部材の柱
部を示す縦断面図である。
FIG. 2 is a longitudinal sectional view showing a pillar portion of a half PC member according to the embodiment of the present invention.

【図3】本発明の実施の形態に係るハーフPC部材の梁
部を示す縦断面図である。
FIG. 3 is a longitudinal sectional view showing a beam portion of the half PC member according to the embodiment of the present invention.

【図4】隣合うハーフPC部材の柱部間の接合を説明す
るための横断面図である。
FIG. 4 is a cross-sectional view for explaining joining between pillar portions of adjacent half PC members.

【図5】隣合うハーフPC部材の柱主筋間の接続を説明
するための横断面図である。
FIG. 5 is a cross-sectional view for explaining connection between column main bars of adjacent half PC members.

【図6】柱と床との接合を説明するための縦断面図であ
る。
FIG. 6 is a vertical cross-sectional view for explaining joining between a pillar and a floor.

【図7】梁部と床との接合を説明するための縦断面図で
ある。
FIG. 7 is a vertical cross-sectional view for explaining joining between a beam portion and a floor.

【図8】ハーフPC部材と床材との接合を示す全体図で
ある。
FIG. 8 is an overall view showing the joining between a half PC member and a floor material.

【図9】ハーフPC部材と床材との接合を示す全体図で
ある。
FIG. 9 is an overall view showing a connection between a half PC member and a floor material.

【符号の説明】[Explanation of symbols]

H ハーフPC部材 1 柱部 2 梁部 2a 張出部 4 柱主筋(柱鉄筋) 5 柱フープ筋(柱鉄筋) 6 接続金物 7 梁主筋(梁鉄筋) 9 スターラップ筋(梁鉄筋) 16 床版 H Half PC member 1 Column 2 Beam 2a Overhang 4 Column main reinforcement (column reinforcement) 5 Column hoop reinforcement (column reinforcement) 6 Connection hardware 7 Beam main reinforcement (beam reinforcement) 9 Stirrup reinforcement (beam reinforcement) 16 Floor slab

───────────────────────────────────────────────────── フロントページの続き (51)Int.Cl.6 識別記号 FI E04C 3/44 E04B 2/86 601M 601T 601C 611D 611H ──────────────────────────────────────────────────の Continued on the front page (51) Int.Cl. 6 Identification code FI E04C 3/44 E04B 2/86 601M 601T 601C 611D 611H

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 所定間隔をあけて対向配置した一対の柱
鉄筋及びその柱鉄筋間に跨がる梁鉄筋と一体に成形され
るように、当該柱鉄筋及び梁鉄筋のうち構造物の外周側
に位置する鉄筋部分を埋め込んだ門型形状の薄肉板状部
材からなることを特徴とするハーフプレキャストコンク
リート部材。
1. An outer peripheral side of a structure of a column reinforcing bar and a beam reinforcing bar so as to be integrally formed with a pair of column reinforcing bars and a beam reinforcing bar extending between the column reinforcing bars at a predetermined interval. A half precast concrete member comprising a gate-shaped thin plate-like member having a reinforcing bar portion embedded therein.
【請求項2】 梁部のプレキャストコンクリートは、そ
の下部が構造物の内周側に張り出して断面L形となって
いることを特徴とする請求項1に記載されたハーフプレ
キャストコンクリート部材。
2. The half precast concrete member according to claim 1, wherein a lower portion of the precast concrete of the beam portion projects toward the inner peripheral side of the structure and has an L-shaped cross section.
【請求項3】 コンクリートに埋め込まれた柱主筋の上
端部及び下端部の少なくも一方に、上層又は下層の柱主
筋との接続を行う接続金物を備えることを特徴とする請
求項1又は請求項2に記載されたハーフプレキャストコ
ンクリート部材。
3. A connection metal fitting for connecting with an upper or lower layer column main reinforcement at least at one of an upper end and a lower end of the column main reinforcement embedded in concrete. 2. The half precast concrete member according to 2.
【請求項4】 上記請求項1から請求項3のいずれかに
記載されたハーフプレキャストコンクリート部材を並べ
るように建方を行い、隣合うハーフプレキャストコンク
リート部材の隣接する柱部分同士を接続する補強鉄筋を
配置した後、床下端部の高さまで柱用コンクリートを打
設し、その打設して構築した柱上端部に床版を支持させ
ることを特徴とする構造物の構築方法。
4. A reinforcing reinforcing bar for constructing a half precast concrete member according to any one of claims 1 to 3 so as to be arranged, and connecting adjacent column portions of adjacent half precast concrete members. A method for constructing a structure, comprising: placing concrete for a column to the height of the lower end of the floor after placing the concrete, and supporting the floor slab at the upper end of the column constructed by the casting.
【請求項5】 上記床版はプレキャストコンクリート板
であって、その板の上に中空部材が設置され、コンクリ
ートを打設することでスラブが構築されることを特徴と
する請求項4に記載した構造物の構築方法。
5. The floor slab is a precast concrete plate, a hollow member is installed on the plate, and a slab is constructed by casting concrete. How to build the structure.
【請求項6】 上記床版は、逆梁床版であって、その床
版の上に2重床を構築することを特徴とする請求項4に
記載した構造物の構築方法。
6. The method according to claim 4, wherein the floor slab is a reverse beam slab, and a double floor is built on the floor slab.
JP27953396A 1996-10-22 1996-10-22 Half-precast concrete member and construction method of structure Pending JPH10121573A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP27953396A JPH10121573A (en) 1996-10-22 1996-10-22 Half-precast concrete member and construction method of structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP27953396A JPH10121573A (en) 1996-10-22 1996-10-22 Half-precast concrete member and construction method of structure

Publications (1)

Publication Number Publication Date
JPH10121573A true JPH10121573A (en) 1998-05-12

Family

ID=17612339

Family Applications (1)

Application Number Title Priority Date Filing Date
JP27953396A Pending JPH10121573A (en) 1996-10-22 1996-10-22 Half-precast concrete member and construction method of structure

Country Status (1)

Country Link
JP (1) JPH10121573A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007051420A (en) * 2005-08-15 2007-03-01 Shimizu Corp Building structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007051420A (en) * 2005-08-15 2007-03-01 Shimizu Corp Building structure

Similar Documents

Publication Publication Date Title
JP3069753B2 (en) Construction method of framed reinforced concrete structure
JPH10121573A (en) Half-precast concrete member and construction method of structure
KR20010090294A (en) Precast concrete structure for variable plan of apartment house
JP2884440B2 (en) Formwork for construction of concrete prism and construction method of column using it
JP3586121B2 (en) Mixed structure of reinforced concrete column and steel beam and its construction method
JP2959325B2 (en) Construction method of steel frame reinforced concrete structure
JP3711322B2 (en) Construction method of precast concrete beams, precast concrete floor boards and reinforced concrete structures
JPH0657710A (en) Construction of concrete main tower
JPH08144425A (en) Prefabricated member of mixed structure and construction method of mixed structure
JP2928002B2 (en) Column formwork structure
JPH1150538A (en) Building and method for constructing the same
JP2757032B2 (en) Construction method of underground building with pillars with capital by reverse hitting method
JP2643641B2 (en) Building method using PC members
JP3207276B2 (en) How to build a unit building
JPH06104993B2 (en) Construction method of steel pipe precast concrete columns
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JPH02236325A (en) Construction method for super-highrise building
JP3045839B2 (en) Method and apparatus for installing floor slab in unit building
JP2004197400A (en) Construction method of earthquake-resistant wall
CN114607041A (en) Construction method of building structure
JPH02120441A (en) Precast concrete wall panel and constructing wall therewith
JPS5858503B2 (en) Construction method of reinforced concrete composite wall
JP2804219B2 (en) Reinforced steel pipe unit and building construction method using the same
JPH0874381A (en) Reinforcement unit and construction method of reinforced concrete-made building using the same
JPH0692669B2 (en) Frame method using shaped steel for beam with rebar concrete structure