JPH0978614A - Reverse striking method combined with leading cutting beam - Google Patents
Reverse striking method combined with leading cutting beamInfo
- Publication number
- JPH0978614A JPH0978614A JP7233991A JP23399195A JPH0978614A JP H0978614 A JPH0978614 A JP H0978614A JP 7233991 A JP7233991 A JP 7233991A JP 23399195 A JP23399195 A JP 23399195A JP H0978614 A JPH0978614 A JP H0978614A
- Authority
- JP
- Japan
- Prior art keywords
- wall
- constructed
- cutting
- pile
- retaining wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
(57)【要約】
【課題】 山留め壁として必要な壁厚は軟弱層が厚い場
合などの地盤の悪さには左右されることなく、壁杭の間
隔と側圧分布の大きさにより設計されるので非常に合理
的であり、経済的となり、壁杭の前面にソイルセメント
で改良された地盤をもって鉛直板状の地中先行切ばりを
施工するだけで、敷地全面を改良したと同じ効果が期待
でき、施工の容易性および合理化、さらに、工費の節
減、工期の短縮が得られる。
【解決手段】 壁杭5をある間隔で構築し、本設地下外
壁位置に根切りに必要な長さの山留め壁4を構築し、ま
た、構真柱6を構築し、壁杭5の前面に対面の壁杭にむ
けて鉛直板状の地中先行切ばり7をソイルセメントで改
良された地盤をもって施工し、1階スラブ2をかけてか
ら、躯体を根切りの進行にあわせて打ち下げていく逆打
ちを行い、根切り完了後地中先行切ばり7上に基礎梁ス
ラブを構築する。
(57) [Abstract] [Problem] Since the wall thickness required as a retaining wall is not affected by the badness of the ground such as when the soft layer is thick, it is designed by the interval between the wall piles and the size of the lateral pressure distribution. It is very rational and economical, and it is possible to expect the same effect as improving the entire site simply by constructing a vertical plate-like ground undercut with the soil improved in front of the wall pile. , The construction is easy and rationalized, and the construction cost and the construction period can be shortened. SOLUTION: The wall piles 5 are constructed at a certain interval, the mountain retaining wall 4 of a length necessary for root cutting is constructed at the position of the main underground outer wall, and the true pillars 6 are constructed, and the front surface of the wall pile 5 is constructed. To the facing wall piles, the vertical plate-like pre-cutting beam 7 is constructed with the soil improved with soil cement, the first floor slab 2 is applied, and then the skeleton is shot down according to the progress of root cutting. After the root cutting is completed, the foundation beam slab is constructed on the preceding cutting beam 7 in the ground.
Description
【0001】[0001]
【発明の属する技術分野】本発明は、地下構造物または
建築の地下部分を施工する逆打ち工法で、先行切ばりと
併用する工法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a reverse construction method for constructing an underground structure or an underground portion of a building, which is used in combination with a preceding cut beam.
【0002】[0002]
【従来の技術】逆打ち工法は周知のように本設スラブを
支保工としながら躯体を根切りの進行にあわせて打ち下
げていくものであるが、このような逆打ち工法における
山留め架構の設計法は、図13に示すように山留め壁1に
作用する側圧を上部は1階スラブ2で、下部は床付け以
深の支持層となる硬質層βに支持される梁としての鉛直
方向にワンウエイの解析方法が採用されている。これは
一般的な切ばりオープンカット工法採用時と同じであ
る。Aは根切り側、Bは背面側、αは軟弱層である。2. Description of the Related Art As is well known, the reverse striking method is one in which the main slab is used as a support work to strike down the skeleton according to the progress of root cutting. According to the method, as shown in FIG. 13, the lateral pressure acting on the mountain retaining wall 1 is a one-way vertical direction as a beam supported by the hard layer β that is the supporting layer at the upper part and the floor below the floor. The analysis method is adopted. This is the same as when using the general open-cut method. A is the root cutting side, B is the back side, and α is the soft layer.
【0003】[0003]
【発明が解決しようとする課題】軟弱地盤が深い場合に
は、組立鋼材による切ばりをかけながらオープンカット
を行うより、前記逆打ち工法の方が安全性が高いといわ
れている。When the soft ground is deep, it is said that the above-mentioned upside-down construction method is more safe than the open cutting while applying the burrs by the assembled steel material.
【0004】この逆打ち工法は軟弱層が厚い場合の工事
では、床付け以深には構真柱用場所打ちコンクリート杭
3の施工が必要となる。また、本設躯体のスラブコンク
リートの硬化収縮により本設地下外壁となる山留め壁1
にはM0 の曲げモーメントが発生する。M0 が非常に大
きくなることにより、本設地下外壁、あるいは外周柱を
兼用するには非常に大きな断面の地下連続壁が必要とな
り、工期、工費ともに大きな問題となっている。In this reverse construction method, when the soft layer is thick, it is necessary to construct the cast-in-place concrete pile 3 for the structure column in the depth below the floor. In addition, the earth retaining wall 1 that will become the outer wall of the main building by hardening and shrinking of the slab concrete of the main building
A bending moment of M 0 is generated at. Since M 0 becomes very large, an underground continuous wall with a very large cross section is required to double as the main underground outer wall or the outer peripheral column, which is a big problem in terms of construction period and construction cost.
【0005】本発明の目的は前記従来例の不都合を解消
し、山留め壁として必要な壁厚は軟弱層が厚い場合など
の地盤の悪さには左右されることなく、壁杭の間隔と側
圧分布の大きさにより設計されるので非常に合理的であ
り、経済的となり、壁杭の前面にソイルセメントで改良
された地盤をもって地中先行切ばりを施工するだけで、
敷地全面を改良したと同じ効果が期待でき、施工の容易
性および合理化、さらに、工費の節減、工期の短縮が得
られる先行切ばり併用逆打ち工法を提供することにあ
る。The object of the present invention is to eliminate the disadvantages of the above-mentioned conventional example, and the wall thickness required as a mountain retaining wall is not affected by the poor ground such as when the soft layer is thick, and the interval between the wall piles and the lateral pressure distribution. It is very reasonable and economical because it is designed according to the size of, and it is only necessary to construct the ground pre-cutting with the ground improved with soil cement on the front surface of the wall pile,
It is intended to provide a reverse striking method with a leading beam which can be expected to have the same effect as improving the entire site, simplifying and rationalizing construction, as well as saving construction costs and shortening the construction period.
【0006】[0006]
【課題を解決するための手段】本発明は前記目的を達成
するため、第1に、壁杭を柱心位置に構築し、本設地下
外壁位置に根切りに必要な長さの山留め壁を構築し、ま
た、構真柱を構築し、壁杭の前面に対面の壁杭にむけて
鉛直板状の地中先行切ばりをソイルセメントで改良され
た地盤をもって施工し、1階スラブをかけてから、躯体
を根切りの進行にあわせて打ち下げていく逆打ちを行
い、根切り完了後地中先行切ばり上に基礎梁スラブを構
築すること、第2に、山留め壁は本設地下外壁として利
用すること、または、壁杭はT字あるいは十字の左右に
山留め壁の係合部を突設し、山留め壁は根切り期間中は
仮設であり、耐震壁に利用の本設地下外壁は壁杭の係合
部を利用して後打ち壁として施工することを要旨とする
ものである。In order to achieve the above-mentioned object, the present invention firstly constructs a wall pile at a pillar center position, and installs a mountain retaining wall of a length required for root cutting at a permanent underground outer wall position. We also constructed a true pillar and constructed a vertical plate-like ground undercut with a soil cement-improved ground on the front side of the wall pile facing the facing wall pile. After that, perform the reverse striking down of the skeleton according to the progress of root cutting, and after the root cutting is completed, build the foundation beam slab on the preceding cutting beam in the ground. Second, the mountain retaining wall is the basement underground. It is used as an outer wall, or the wall pile has T-shaped or cross-shaped protrusions on the left and right engaging parts of the mountain retaining wall, and the mountain retaining wall is temporary during the root cutting period. Is to be constructed as a post-strike wall using the engaging portion of the wall pile.
【0007】根切りにより発生する山留め壁の応力は前
記図12に示すように、軟弱層が深い場合には非常に大き
な曲げモーメントが作用し、山留め壁の剛性も大きなも
のが必要となる。請求項1記載の本発明によれば、仮想
支点となる先行切ばりを床付け位置より僅かに下の位置
までソイルセメントにより改良しておくので、これが板
状の先行切ばりとなり、あたかも全体が硬質層であるが
ごとき挙動を示す。As shown in FIG. 12, when the soft layer is deep, a very large bending moment acts on the stress of the earth retaining wall caused by root cutting, and the earth retaining wall needs to have a high rigidity. According to the present invention as set forth in claim 1, since the preceding cutting beam serving as a virtual fulcrum is improved by soil cement to a position slightly below the floor mounting position, this becomes a plate-like preceding cutting beam, and it is as if the whole. It behaves like a hard layer.
【0008】図11、図12はこのような側圧分布と山留め
壁の曲げモーメントの分布を示すもので、太実線のよう
な曲げモーメント分布となり一般的な逆打ち工法による
曲げモーメント曲線である細点線と比べて、変形量も大
幅に減少する。FIG. 11 and FIG. 12 show such lateral pressure distribution and bending moment distribution of the mountain retaining wall. The bending moment distribution is as shown by the thick solid line, and the thin dotted line is the bending moment curve obtained by the general upsetting method. Compared with, the amount of deformation is also significantly reduced.
【0009】先行切ばりは構真柱工事により構真柱位置
で分断されることになり、先行切ばりとしての機能は十
分とはいかなくなる。このため、やや地盤強度が低下し
たと見做され、あるいは切ばりとしての剛性が低下する
もののその能力が全て失われるものでない。最終床付け
位置より下には場所打ちコンクリート杭が施工されてい
ることにより先行切ばりとしての強度、機能は十分あ
り、仮想支点が下がった不利な状態でも図11、図12の点
線のように最終床付け位置に仮想支点を仮定することに
より安全性は保たれる。The preceding cut beam is divided at the position of the true column by the construction of the true column, and the function as the preceding beam is not sufficient. Therefore, it is considered that the ground strength is slightly lowered, or the rigidity as the cut is reduced, but the ability is not lost. Since cast-in-place concrete piles are installed below the final flooring position, it has sufficient strength and function as a leading beam, and even in the disadvantageous state that the virtual fulcrum is lowered, as shown by the dotted lines in Figs. 11 and 12. Safety is maintained by assuming a virtual fulcrum at the final floor mounting position.
【0010】なお、構真柱埋戻しをソイルセメントなど
を用いて十分に行えば、先行切ばりは連続性を失うこと
はないので、さらに有効な曲げモーメント分布となる。If the structural column backfilling is sufficiently performed by using soil cement or the like, the preceding cut beam does not lose continuity, so that the bending moment distribution becomes more effective.
【0011】硬質層に定着していない壁杭の場合でも、
山留め壁に作用する側圧を受けることにより山留め壁に
発生する曲げモーメントは主に水平方向に平面的に壁杭
位置を支持点とする単純梁のようになる。従って、軟弱
層の深さやその地盤の強度にはあまり左右されることな
く単純に壁杭の間隔により設計することができる。この
ため、山留め壁の必要深さは最終根切り底より1〜2m
程度の位置に達していれば十分であり、経済的に優れた
ものとなる。Even in the case of wall piles not fixed to the hard layer,
The bending moment generated in the retaining wall due to the lateral pressure acting on the retaining wall becomes like a simple beam with the wall pile position as the supporting point mainly in the horizontal plane. Therefore, it is possible to simply design by the interval between the wall piles without being much influenced by the depth of the soft layer and the strength of the ground. Therefore, the required depth of the retaining wall is 1-2m from the final root cutting bottom.
It is enough to reach a certain level, and it will be economically superior.
【0012】請求項2記載の本発明は山留め壁は本設地
下外壁として利用する場合であり、請求項3記載の本発
明は本設地下外壁として利用しない場合であり、いずれ
も本発明は適用できるが、請求項3記載の本発明によれ
ば、壁杭のシヤーキーを利用して本設地下壁を後打ち壁
として施工することで耐震壁としての機能を持たせるこ
とができる。The present invention described in claim 2 is a case where the mountain retaining wall is used as a permanent underground outer wall, and the present invention described in claim 3 is a case where the mountain retaining wall is not used as a permanent underground outer wall. According to the present invention as set forth in claim 3, it is possible to provide a function as an earthquake-resistant wall by constructing the permanent underground wall as a post-strike wall by utilizing the shear key of the wall pile.
【0013】[0013]
【発明の実施の形態】以下、本発明の実施の形態を図面
について詳細に説明する。図5〜図8は本発明の先行切
ばり併用逆打ち工法の1実施形態を示す各工程の側面
図、図1は本発明の先行切ばり併用逆打ち工法の1実施
形態を示す縦断側面図、図2は同上平面図である。Embodiments of the present invention will be described below in detail with reference to the drawings. 5 to 8 are side views of respective steps showing an embodiment of the reverse cutting combined use reverse precasting method of the present invention, and FIG. 1 is a longitudinal side view showing one embodiment of the prior cut beam combined reverse reverse injection construction method of the present invention. 2 is a plan view of the same as above.
【0014】図5に示すように、本設柱兼用の壁杭5を
ある間隔で構築し、本設地下外壁位置に根切りに必要な
長さの山留め壁4を構築し、また、構真柱用場所打ちコ
ンクリート杭3および構真柱6を構築する。なお、この
壁杭5の下端は硬質層βに到達する長さである必要はな
い。As shown in FIG. 5, wall piles 5 which also serve as main installation pillars are constructed at a certain interval, and a mountain retaining wall 4 of a length required for root cutting is constructed at the main underground outer wall position. A cast-in-place concrete pile 3 for columns and a true column 6 are constructed. In addition, the lower end of the wall pile 5 does not need to have a length that reaches the hard layer β.
【0015】壁杭5はこれを十文字またはT字形状に構
築し、左右に係合部5aを張出し、山留め壁4に一体的
に構築するものとする。前記山留め壁4と該壁杭5とを
ともに連続壁で構成する場合は、山留め壁4と壁杭5と
は一体的に施工することになり、壁杭5の形状を十文字
またはT字形状のものとして、左右の係合部5aで山留
め壁4を接続させるため、水平筋のジョイント工法が必
要となる。また、山留め壁4と壁杭5とはこれらのいず
れか一方または両方をプレキャストコンクリート製や鋼
とすることも可能である。The wall pile 5 is constructed in a cross shape or a T-shape, and the engaging portions 5a are projected to the left and right to be integrally constructed on the mountain retaining wall 4. When both the mountain retaining wall 4 and the wall pile 5 are continuous walls, the mountain retaining wall 4 and the wall pile 5 are integrally constructed, and the wall pile 5 has a cross shape or a T-shape. As a matter of course, since the mountain retaining wall 4 is connected by the left and right engaging portions 5a, a joint method of horizontal lines is required. Further, either one or both of the mountain retaining wall 4 and the wall pile 5 may be made of precast concrete or steel.
【0016】他の実施形態として、壁杭5は図3に示す
ようにこの係合部に山留め壁4の端を重ね合わせてこの
山留め壁4を支持するようにした。このように接続を重
ね合わせで行うには例えば重ね合わせることにより十分
機能するために費用の安い工法、例えばプレキャストコ
ンクリートを自硬化性泥水中に埋め込むような工法でも
よい。As another embodiment, the wall pile 5 supports the mountain retaining wall 4 by overlapping the end of the mountain retaining wall 4 with the engaging portion as shown in FIG. In order to perform the connection in such a superposition manner, for example, a construction method which is inexpensive and sufficiently functions by superposition, for example, a construction method in which precast concrete is embedded in self-hardening mud water.
【0017】山留め壁4はこれを本設土圧壁兼用のもの
とする場合と仮設とする場合とがある。山留め壁4を仮
設のものとする場合には、H、I形鋼あるいはプレキャ
スト式の重ね合わせ式を採用した場合には、本設地下外
壁としての壁杭5の十文字(あるいはT字形)のシヤー
キーを利用して後打ち壁とすることで耐震壁としての機
能を持たせることもできる。The earth retaining wall 4 may be used also as a permanent earth pressure wall or may be temporary. When the mountain retaining wall 4 is a temporary one, and when H, I-shaped steel or a precast type of superposition type is adopted, a cross key (or T-shaped) shear key of the wall pile 5 as a permanent underground outer wall It can be made to have a function as an earthquake-resistant wall by making it a post-casting wall.
【0018】前記壁杭5間に構築する山留め壁4はこれ
を壁杭5と同じ地中連続壁工法として、横長掘削孔に鉄
筋カゴを配設し、コンクリートを打設してなるエレメン
トを先行、後行で接続していくことにより施工する。The mountain retaining wall 4 constructed between the wall piles 5 has the same underground continuous wall construction method as the wall piles 5, and an element made by placing a concrete basket in a horizontally long drilling hole and placing concrete is preceded. , Connect by connecting in the subsequent line.
【0019】また、他の実施形態として山留め壁4は、
ソイルセメント連続壁で施工するものとし、その一例と
しては掘削機を大型にした大型チェンソーでベントナイ
ト溶液とエヤレーションを併用して掘削し、完成後セメ
ントペースト(セメントミルク)を注入しながら攪拌混
合する、いわゆる、トレンダー工法で施工する。As another embodiment, the mountain retaining wall 4 is
Soil cement continuous wall shall be used. As an example, excavation is carried out using a large chain saw with a large excavator using bentonite solution and aeration, and after completion, cement paste (cement milk) is injected and mixed with stirring. , The so-called trender construction method is used.
【0020】なお、山留め壁4を構成するソイルセメン
ト壁の連続掘削工法としては、このようなトレーダー工
法の他にSMW工法の3軸杭打機を小型にしたソイルチ
ェンジャーと称する施工機を使用する3軸工法を採用し
てもよい。As a continuous excavation method for the soil cement wall constituting the mountain retaining wall 4, in addition to such a trader method, a construction machine called a soil changer which is a small-sized 3-axis pile driving machine of the SMW method is used. A triaxial method may be adopted.
【0021】また、山留め壁4は根切り壁面を崩壊させ
ないように支持できる最低限度の長さ、すなわち、最終
根切り底より1〜2m程度の位置に達するものとする。
なお、地下水の多い場合には山留め壁4の下部に止水性
の膜を設置する。The earth retaining wall 4 reaches a minimum length capable of supporting the root cutting wall surface without collapsing, that is, reaches a position of about 1 to 2 m from the final root cutting bottom.
If there is a lot of groundwater, a waterproof membrane is installed below the retaining wall 4.
【0022】このように山留め壁4をソイルセメント連
続壁で施工するのに必要な強度が不足となるおそれがあ
る場合は、図9、図10に示すように、掘削孔内に注入し
た自硬性の泥水(ベントナイト溶液)あるいはセメント
ミルクが混練して硬化する前に、その内部にウエブ10a
を水平向きとして水平方向を主応力とするHあるいはI
形鋼の形鋼10をワイヤー11等の吊り部材により上下方向
に間隔を存して並べてすだれ状に配置する。When there is a possibility that the strength required for constructing the earth retaining wall 4 with a soil cement continuous wall may be insufficient as described above, as shown in FIGS. 9 and 10, the self-hardening property injected into the excavation hole is shown. Before the muddy water (bentonite solution) or cement milk is kneaded and hardened, the web 10a
Is the horizontal direction and H or I is the main stress in the horizontal direction.
Shaped steels 10 of shaped steels are arranged in a comb-like shape by vertically arranging them with a hanging member such as a wire 11 at intervals.
【0023】この形鋼10はウエブ10aに円形または角形
の穴10bを適宜間隔であけるものとした。このように穴
10bを設けることで形鋼10の材料費を安価なものとし、
また、形鋼10を設置する際に自硬性の泥水(ベントナイ
ト溶液)あるいはセメントミルクがこの穴10bを通過す
ることで施工性のよいものとなる。なお、形鋼10の設置
は掘削孔を形成した段階で行い、その後で自硬性の泥水
やセメントミルクを注入し、攪拌することも可能であ
る。The shaped steel 10 has circular or square holes 10b formed in the web 10a at appropriate intervals. Hole like this
By providing 10b, the material cost of the shaped steel 10 can be made low,
Further, when the shaped steel 10 is installed, the self-hardening muddy water (bentonite solution) or cement milk passes through the hole 10b, which improves the workability. It is also possible to install the shaped steel 10 at the stage of forming the drilled hole, and then inject self-hardening mud or cement milk and stir it.
【0024】図6に示すように、壁杭5の前面に対面の
壁杭に到達する溝をセメントミルク・ベントナイト等の
注入材を注入しながら最終床付け位置より深い位置まで
削孔してソイルセメント壁の連続掘削工法による鉛直板
状の地中先行切ばり7を施工する。かかる鉛直板状の地
中先行切ばり7の施工は前記山留め壁4の施工と同じく
ソイルセメント連続壁で施工するものとし、掘削機を大
型にした大型チェンソーでのトレーダー工法や、SMW
工法の3軸杭打機を小型にしたソイルチェンジャーと称
する施工機を使用する3軸工法で施工する等の工法が採
用できる。As shown in FIG. 6, the groove that reaches the wall pile facing the front side of the wall pile 5 is drilled to a position deeper than the final flooring position while pouring an injection material such as cement milk and bentonite. A vertical plate-like ground undercut 7 is constructed by a continuous excavation method for cement walls. The construction of such a vertical plate-like undercut beam 7 shall be carried out with a continuous soil cement wall similar to the construction of the retaining wall 4, the trader construction method using a large chain saw with a large excavator, and the SMW.
It is possible to adopt a construction method in which a construction machine called a soil changer, which is a compact construction of the construction 3-axis pile driving machine, is used, and the construction is carried out by a triaxial construction method.
【0025】この鉛直板状の先行切ばり7は、強度が必
要な場合には掘削した溝底を、RCあるいはプレキャス
ト、H鋼などの強度部材で補強する。This vertical plate-shaped leading edge beam 7 reinforces the excavated groove bottom with a strength member such as RC, precast, or H steel when strength is required.
【0026】図4は前記図3に示すようにこの係合部に
山留め壁4の端を重ね合わせてこの山留め壁4を支持す
るようにした場合の全体の平面図で、先行切ばり7は構
真柱工事により構真柱6の位置で分断されることになる
が、先に述べたように切ばりとしての剛性が低下するも
ののその能力が全て失われるものでなく、最終床付け位
置より下には場所打ちコンクリート杭が施工されている
ことにより先行切ばりとしての強度、機能は十分ある。
なお、構真柱埋戻しをソイルセメントなどを用いて十分
に行えば、先行切ばりは連続性を失うことはないので、
さらに有効な曲げモーメント分布となる。FIG. 4 is an overall plan view of the case where the ends of the mountain retaining wall 4 are superposed on the engaging portion to support the mountain retaining wall 4 as shown in FIG. Although it will be divided at the position of the true pillar 6 due to the construction of the true pillar, as mentioned above, although the rigidity as the cut-off is reduced, all of its capacity is not lost, and Since the cast-in-place concrete pile is installed underneath, it has sufficient strength and function as the preceding beam.
It should be noted that if the structural column backfilling is sufficiently performed using soil cement, the preceding cutting will not lose continuity,
A more effective bending moment distribution is obtained.
【0027】図7に示すように、1階スラブ2の位置あ
るいはここにかからないような深さまで根切りを行い、
1階スラブ2をかけてから、第2次根切り、地下1階ス
ラブ12の構築(図12参照)、第3次根切り等躯体を根切
りの進行にあわせて打ち下げていく逆打ちを行う。な
お、途中の地下階の図示は省略する。As shown in FIG. 7, root cutting is performed to the position of the first-floor slab 2 or to a depth such that it does not reach here.
After the first floor slab 2 is applied, the second root cutting, the construction of the basement first floor slab 12 (see Fig. 12), the third root cutting, etc. To do. The illustration of the basement floor on the way is omitted.
【0028】図8に示すように、根切り完了後地中先行
切ばり7上に基礎梁スラブ9を構築する。As shown in FIG. 8, a foundation beam slab 9 is built on the preceding cutting beam 7 in the ground after the completion of root cutting.
【0029】壁杭5に作用する応力に対して反力となる
切ばり軸力と仮想支点反力については一般的な逆打ち工
法での計算と同じである。しかも、この壁杭5は大きな
曲げ剛性があることにより変形に対して大きな耐力があ
ることにより、切ばりがなくとも、また、本設躯体スラ
ブの間隔が比較的大きなものでも対抗できる。これは根
切り工事のスピードと安全施工に対して非常に有利とな
る。The cut-off axial force and the virtual fulcrum reaction force, which are reaction forces against the stress acting on the wall pile 5, are the same as those calculated by the general reverse striking method. In addition, since the wall pile 5 has a large bending rigidity and a large proof strength against deformation, it is possible to resist even if there is no burrs and the main body slab has a relatively large interval. This is very advantageous for speed of root cutting work and safe construction.
【0030】なお、山留め壁4は本設地下外壁として利
用する場合もあるが、これを仮設としてもよい。その場
合は、図4に示すように改めて耐震壁として利用する本
設地下外壁13を施工するが、壁杭5の係合部5aを利用
して後打ち壁として施工するようにしてもよい。Although the mountain retaining wall 4 may be used as a permanent underground outer wall in some cases, it may be temporary. In that case, as shown in FIG. 4, the permanent underground outer wall 13 to be used as an earthquake-resistant wall is constructed again, but it may be constructed to be a post-strike wall by utilizing the engaging portion 5a of the wall pile 5.
【0031】また、施工手順に関しては、壁杭の設置、
構真柱の施工、山留め壁の施工、地中先行切ばりの施工
は前記実施形態の記載にとらわれず、これらを同時進行
で行うことや、いずれかを先行施工させ、他は同時進行
またはいずれか一方を先行させる後行施工とすることな
ど、現場の状況によって適宜選択できるものとする。そ
の一例は壁杭設置のためのプレボーリングはこれをソイ
ルセメントで改良された地盤による地中先行切ばりや山
留め壁の施工で自硬性の泥水やセメントミルク等の注入
材を注入しながら削孔する際にともに行うことができる
などである。Regarding the construction procedure, installation of wall piles,
Construction of structural columns, construction of earth retaining wall, construction of pre-cutting burrs in the ground are not limited to the description of the embodiment, and these can be performed simultaneously or any of them can be performed in advance, and others can be performed simultaneously or Depending on the situation of the site, it is possible to select it appropriately, for example, by performing the subsequent construction in which one of them precedes. One example is pre-boring for the installation of wall piles by drilling holes while pouring injection material such as self-hardening muddy water and cement milk by constructing a predecessor burial ground and a retaining wall with soil improved by soil cement. And so on.
【0032】[0032]
【発明の効果】以上述べたように本発明の先行切ばり併
用逆打ち工法は、山留め壁として必要な壁厚は軟弱層が
厚い場合などの地盤の悪さには左右されることなく、壁
杭の間隔と側圧分布の大きさにより設計されるので非常
に合理的であり、経済的となり、壁杭の前面にソイルセ
メントで改良された地盤をもって鉛直板状の地中先行切
ばりを施工するだけで、敷地全面を改良したのと同じ効
果が期待でき、施工の容易性および合理化、さらに、工
費の節減、工期の短縮が得られるものである。As described above, according to the reverse striking method for combined use of preceding cutting beams according to the present invention, the wall thickness required for the retaining wall is not affected by the poor ground such as when the soft layer is thick, and the wall pile is not affected. It is very rational and economical because it is designed by the interval of the space and the size of lateral pressure distribution, and only the vertical plate-like ground precut beam is installed on the front surface of the wall pile with the soil improved by soil cement. Therefore, the same effect as improving the entire site can be expected, and the ease and rationalization of construction, reduction of construction cost, and shortening of construction period can be obtained.
【図1】本発明の先行切ばり併用逆打ち工法の1実施形
態を示す縦断側面図である。FIG. 1 is a vertical cross-sectional side view showing one embodiment of a reverse striking method with combined use of a leading flash of the present invention.
【図2】本発明の先行切ばり併用逆打ち工法の1実施形
態を示す平面図である。FIG. 2 is a plan view showing an embodiment of a reverse striking method with combined use of a leading flash according to the present invention.
【図3】本発明の先行切ばり併用逆打ち工法の他の実施
形態を示す平面図である。FIG. 3 is a plan view showing another embodiment of the reverse striking method with combined leading flash of the present invention.
【図4】本発明の先行切ばり併用逆打ち工法で図3の実
施形態における全体の平面図である。FIG. 4 is a plan view of the entire structure in the embodiment of FIG. 3 according to the reverse-cutting method with prior cutting flash of the present invention.
【図5】本発明の先行切ばり併用逆打ち工法の1実施形
態での第1工程を示す縦断側面図である。FIG. 5 is a vertical cross-sectional side view showing a first step in an embodiment of the reverse striking method with combined preceding flash of the present invention.
【図6】本発明の先行切ばり併用逆打ち工法の1実施形
態での第2工程を示す縦断側面図である。FIG. 6 is a vertical cross-sectional side view showing a second step in the first embodiment of the reverse striking combined reverse striking method of the present invention.
【図7】本発明の先行切ばり併用逆打ち工法の1実施形
態での第3工程を示す縦断側面図である。FIG. 7 is a vertical cross-sectional side view showing a third step in one embodiment of the method of reverse striking combined with reverse flashing according to the present invention.
【図8】本発明の先行切ばり併用逆打ち工法の1実施形
態での第4工程を示す縦断側面図である。FIG. 8 is a vertical cross-sectional side view showing a fourth step in one embodiment of the backward striking combined reverse-injection method of the present invention.
【図9】本発明の先行切ばり併用逆打ち工法の1実施形
態を示す要部の横断平面図である。FIG. 9 is a cross-sectional plan view of an essential part showing an embodiment of a reverse striking method with combined use of a leading flash of the present invention.
【図10】本発明の先行切ばり併用逆打ち工法の1実施
形態を示す要部の正面図である。FIG. 10 is a front view of the essential parts showing one embodiment of a reverse striking method with combined use of a leading flash according to the present invention.
【図11】本発明の先行切ばり併用逆打ち工法で、1階
スラブ架設時の側圧分布・曲げモーメント分布を示す説
明図である。FIG. 11 is an explanatory view showing a lateral pressure distribution and a bending moment distribution at the time of erection of the first floor slab by the reverse striking method with combined use of the preceding flash of the present invention.
【図12】本発明の先行切ばり併用逆打ち工法で、地下
1階スラブ架設時の側圧分布・曲げモーメント分布を示
す説明図である。FIG. 12 is an explanatory view showing a lateral pressure distribution and a bending moment distribution at the time of erection of a slab on the first basement floor by the reverse striking method with combined use of the preceding cut beam of the present invention.
【図13】従来例を示す説明図である。FIG. 13 is an explanatory diagram showing a conventional example.
1…山留め壁 2…1階スラブ 3…構真柱用場所打ちコンクリート杭 4…山留め壁 5…壁杭 5a…係合部 6…構真柱 7…地中先行切ばり 9…基礎梁スラ
ブ 10…形鋼 10a…ウエブ 10b…穴 11…ワイヤー 12…地下1階スラブ 13…本設地下外
壁1 ... Mountain retaining wall 2 ... First floor slab 3 ... Cast-in-place concrete pile for structure pillar 4 ... Mountain retaining wall 5 ... Wall pile 5a ... Engagement part 6 ... Structure pillar 7 ... Preceding ground undercut 9 ... Foundation beam slab 10 … Section steel 10a… Web 10b… Hole 11… Wire 12… Basement 1st floor slab 13… Main basement outer wall
─────────────────────────────────────────────────────
─────────────────────────────────────────────────── ───
【手続補正書】[Procedure amendment]
【提出日】平成8年10月14日[Submission date] October 14, 1996
【手続補正1】[Procedure amendment 1]
【補正対象書類名】明細書[Document name to be amended] Statement
【補正対象項目名】0019[Correction target item name] 0019
【補正方法】変更[Correction method] Change
【補正内容】[Correction contents]
【0019】また、他の実施形態として山留め壁4は、
ソイルセメント連続壁で施工するものとし、その一例と
しては掘削機を大型にした大型チェンソーでベントナイ
ト溶液とエヤレーションを併用して掘削し、完成後セメ
ントペースト(セメントミルク)を注入しながら攪拌混
合する工法で施工する。As another embodiment, the mountain retaining wall 4 is
Soil cement continuous wall construction shall be used. As an example, excavation is carried out using a large chain saw with a large excavator using bentonite solution and aeration. After completion, cement paste (cement milk) is poured and mixed with stirring. Use the construction method.
【手続補正2】[Procedure amendment 2]
【補正対象書類名】明細書[Document name to be amended] Statement
【補正対象項目名】0020[Correction target item name] 0020
【補正方法】変更[Correction method] Change
【補正内容】[Correction contents]
【0020】なお、山留め壁4を構成するソイルセメン
ト壁の連続掘削工法としては、このような大型チェーン
ソーによる工法の他に原位置土混合壁体(SMW)工法
の3軸杭打機を小型にしたソイルチェンジャーと称する
施工機を使用する3軸工法を採用してもよい。As a method for continuously excavating the soil cement wall which constitutes the mountain retaining wall 4, in addition to the method using such a large chainsaw, the in-situ soil mixing wall (SMW) method 3-axis pile driver can be made compact. A three-axis construction method using a construction machine called a soil changer may be adopted.
【手続補正3】[Procedure 3]
【補正対象書類名】明細書[Document name to be amended] Statement
【補正対象項目名】0024[Name of item to be corrected] 0024
【補正方法】変更[Correction method] Change
【補正内容】[Correction contents]
【0024】図6に示すように、壁杭5の前面に対面の
壁杭に到達する溝をセメントミルク・ベントナイト等の
注入材を注入しながら最終床付け位置より深い位置まで
削孔してソイルセメント壁の連続掘削工法による鉛直板
状の地中先行切ばり7を施工する。かかる鉛直板状の地
中先行切ばり7の施工は前記山留め壁4の施工と同じく
ソイルセメント連続壁で施工するものとし、掘削機を大
型にした大型チェンソーでの工法や、原位置土混合壁体
(SMW)工法の3軸杭打機を小型にしたソイルチェン
ジャーと称する施工機を使用する3軸工法で施工する等
の工法が採用できる。As shown in FIG. 6, the groove that reaches the wall pile facing the front side of the wall pile 5 is drilled to a position deeper than the final flooring position while pouring an injection material such as cement milk and bentonite. A vertical plate-like ground undercut 7 is constructed by a continuous excavation method for cement walls. The construction of such a vertical plate-like pre-cutting beam 7 is to be carried out with a soil cement continuous wall as in the construction of the earth retaining wall 4, and a construction method with a large chain saw with a large excavator and an in-situ soil mixing wall. It is possible to adopt a construction method such as a construction method using a construction machine called a soil changer which is a miniaturized 3-axis pile driving machine of the body (SMW) construction method.
Claims (3)
位置に根切りに必要な長さの山留め壁を構築し、また、
構真柱を構築し、壁杭の前面に対面の壁杭にむけて鉛直
板状の地中先行切ばりをソイルセメントで改良された地
盤をもって施工し、1階スラブをかけてから、躯体を根
切りの進行にあわせて打ち下げていく逆打ちを行い、根
切り完了後地中先行切ばり上に基礎梁スラブを構築する
ことを特徴とした先行切ばり併用逆打ち工法。1. A wall pile is constructed at a pillar center position, and a mountain retaining wall of a length necessary for root cutting is constructed at a main underground outer wall position, and
Constructing a true pillar, and constructing a vertical plate-like leading cut-out in the front of the wall pile with facing soil improved with soil cement, and applying the slab on the first floor, then constructing the skeleton A reverse striking method combined with pre-cutting, characterized by constructing a foundation beam slab on the pre-cutting undercut after completion of root cutting by performing reverse striking as the root cutting progresses.
請求項1記載の先行切ばり併用逆打ち工法。2. The reverse striking method with combined pre-cutting according to claim 1, wherein the mountain retaining wall is used as a permanent underground outer wall.
壁の係合部を突設し、山留め壁は根切り期間中は仮設で
あり、耐震壁に利用する本設地下外壁は壁杭の係合部を
利用して後打ち壁として施工する請求項1記載の先行切
ばり併用逆打ち工法。3. The wall pile has protrusions on the left and right sides of the T-shape or cross-shaped engaging portions of the retaining wall, and the retaining wall is temporary during the root cutting period, and the main underground outer wall used for the earthquake resistant wall is the wall pile. 2. The reverse striking method with combined front cut-off according to claim 1, wherein the construction is performed as a post-strike wall by utilizing the engaging portion of.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP7233991A JP3012896B2 (en) | 1995-09-12 | 1995-09-12 | Reverse cutting method combined with advance cutting |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP7233991A JP3012896B2 (en) | 1995-09-12 | 1995-09-12 | Reverse cutting method combined with advance cutting |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0978614A true JPH0978614A (en) | 1997-03-25 |
| JP3012896B2 JP3012896B2 (en) | 2000-02-28 |
Family
ID=16963838
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP7233991A Expired - Fee Related JP3012896B2 (en) | 1995-09-12 | 1995-09-12 | Reverse cutting method combined with advance cutting |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3012896B2 (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2007270461A (en) * | 2006-03-30 | 2007-10-18 | Takenaka Komuten Co Ltd | Earth retaining method |
| CN103015457A (en) * | 2012-12-03 | 2013-04-03 | 常州大学 | Method for building rural brick buried sewage treatment facility |
| CN113482021A (en) * | 2021-08-19 | 2021-10-08 | 中铁第六勘察设计院集团有限公司 | Half-pile supporting structure for excavating shallow foundation pit above underground structure floor and construction method |
-
1995
- 1995-09-12 JP JP7233991A patent/JP3012896B2/en not_active Expired - Fee Related
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2007270461A (en) * | 2006-03-30 | 2007-10-18 | Takenaka Komuten Co Ltd | Earth retaining method |
| CN103015457A (en) * | 2012-12-03 | 2013-04-03 | 常州大学 | Method for building rural brick buried sewage treatment facility |
| CN113482021A (en) * | 2021-08-19 | 2021-10-08 | 中铁第六勘察设计院集团有限公司 | Half-pile supporting structure for excavating shallow foundation pit above underground structure floor and construction method |
Also Published As
| Publication number | Publication date |
|---|---|
| JP3012896B2 (en) | 2000-02-28 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR20200029079A (en) | Construction method for Eearth self-retaining wall using reinforcing member and CIP construction method | |
| US20020071725A1 (en) | Earth support and permanent structural foundation wall | |
| JP2007051541A (en) | Retaining wall and construction method therefor | |
| JP2001303584A (en) | Connection structure between foundation pile head and footing | |
| JP2006291575A (en) | Retaining wall and method of constructing the same | |
| JPH11172710A (en) | Construction method of underground part of steel reinforced concrete building | |
| KR20200029080A (en) | Construction method for earth self-retaining wall using reinforcing member and PHC pile | |
| JPH0978614A (en) | Reverse striking method combined with leading cutting beam | |
| JP4675101B2 (en) | Semi-rigid joint structure between concrete pile and foundation slab or foundation beam and its construction method | |
| JP2899668B2 (en) | Simple underground construction | |
| KR20200029078A (en) | Construction method for earth self-retaining wall using reinforcing member and SCW construction method | |
| JP3012894B2 (en) | Simple underground construction method | |
| JPH0721196B2 (en) | Reverse construction method of underground structure | |
| JP3012895B2 (en) | Simple underground construction method | |
| JP2001207451A (en) | Retaining wall and its construction method | |
| JPH07119465B2 (en) | Underground excavation construction method | |
| JP3101762B2 (en) | Simple mountain retaining method | |
| JPH07138972A (en) | Construction method for underground skeleton | |
| JP4031284B2 (en) | Construction method for underground structures | |
| JPH09111754A (en) | Parent pile water stop wall construction method | |
| JPS6018769B2 (en) | Construction method of underground structure | |
| JPS6250516A (en) | Formation work of composite pile | |
| KR100273864B1 (en) | An improved top-down method using the retaining wall | |
| JPH108482A (en) | Joint structure between trussed columns and piles and post-construction method for trussed columns | |
| JPH0931986A (en) | Simple underground construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| LAPS | Cancellation because of no payment of annual fees |