JPH0921235A - Column erecting accuracy correction method in drive floor advance rise type building construction method - Google Patents

Column erecting accuracy correction method in drive floor advance rise type building construction method

Info

Publication number
JPH0921235A
JPH0921235A JP16907195A JP16907195A JPH0921235A JP H0921235 A JPH0921235 A JP H0921235A JP 16907195 A JP16907195 A JP 16907195A JP 16907195 A JP16907195 A JP 16907195A JP H0921235 A JPH0921235 A JP H0921235A
Authority
JP
Japan
Prior art keywords
floor
column
force
drive floor
accuracy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP16907195A
Other languages
Japanese (ja)
Other versions
JP3661041B2 (en
Inventor
Takumi Fujii
卓美 藤井
Tadaharu Hagiwara
忠治 萩原
Shinko Morita
真弘 森田
Masao Miyaguchi
正夫 宮口
Takao Nakamura
隆男 中村
Masanao Nishiyama
正直 西山
Kazuhiko Hashimura
一彦 橋村
Kunio Aoyama
邦男 青山
Kazuhiko Tanimura
和彦 谷村
Youzou Morimoto
楊三 森本
Takeshi Mitsui
健 三井
Tsutomu Fujita
務 藤田
Shiro Taniguchi
四郎 谷口
Kanta Miyaguchi
幹太 宮口
Minoru Suzuki
稔 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Takenaka Doboku Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Takenaka Doboku Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd, Takenaka Doboku Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP16907195A priority Critical patent/JP3661041B2/en
Publication of JPH0921235A publication Critical patent/JPH0921235A/en
Application granted granted Critical
Publication of JP3661041B2 publication Critical patent/JP3661041B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PROBLEM TO BE SOLVED: To correct the erection accuracy of a column (steel frame column) in a drive floor advance rise type building construction method. SOLUTION: One end of a tensile material 2 is fixed to a drive floor 1, the other end of it is fixed to an existing structural body 3 at an angle which produces a correction force roughly in the horizontal direction relative to the direction to correct column erection error, and the drive floor 1 is raised slightly in order to correct the erection error of a column 4 by using the resultant force of a proper tension generated in the tensile material 2 and the rising force of the drive floor 1 as a correction force. Then the column 4 is connected fixedly to a beam steel frame 5 of next upper floor. Because the vertical accuracy of multiple steel frame columns can be corrected at once through the drive floor, the number of cables used is not in proportion to the number of columns. It may be less, and also a lever block is not needed. Thus labor is less needed and, accordingly, the work period can be shortened.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】この発明は、建物の最上階と
して使用される屋根代用の駆動階を先行して上昇させ、
駆動階の直下階の床上で次上階の建築作業を進める駆動
階先行上昇型建築工法において実施される、施工時の柱
(鉄骨柱)の建て方精度を補正する方法に関するもので
ある。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention firstly raises a driving floor for a roof substitute used as a top floor of a building,
The present invention relates to a method of correcting the erection accuracy of a pillar (steel frame pillar) at the time of construction, which is carried out in a driving floor preceding ascending type construction method for advancing the construction work of the next upper floor on the floor immediately below the driving floor.

【0002】[0002]

【従来の技術】従来一般のタワークレーン等を用いて建
物を構築する工法においては、3層程度の鉄骨柱を本設
床の上方に仮組みした後、各鉄骨柱の頂部に複数本のワ
イヤを四方、八方に取付け、トランシット等を用いて各
鉄骨柱の建て方精度を測定し、誤差があると前記複数本
のワイヤのうち誤差を補正するのに適切なワイヤをレバ
ーブロック等で引っ張り、鉄骨柱の建て方精度を1本ず
つ補正する方法が行われている。
2. Description of the Related Art In a conventional method of constructing a building using a general tower crane or the like, after temporarily assembling about three layers of steel columns above the main floor, a plurality of wires are attached to the tops of the respective steel columns. Is attached to four sides, eight sides, the building accuracy of each steel column is measured using a transit, etc., and if there is an error, pull a wire suitable for correcting the error among the plurality of wires with a lever block or the like, A method of correcting the accuracy of building steel columns one by one is used.

【0003】しかし、上記方法は駆動階先行上昇型建築
工法にはそのまま適用できず、また、駆動階先行上昇型
建築工法特有の鉄骨柱の建て方精度を補正する方法につ
いての格別な実施例等はない。
However, the above method cannot be applied as it is to the driving floor preceding ascending type construction method, and a special embodiment of a method for correcting the accuracy of constructing a steel column peculiar to the driving floor preceding ascending type construction method, etc. There is no.

【0004】[0004]

【発明が解決しようとする課題】上記した従来一般の鉄
骨柱の建て方精度を補正する方法は、各鉄骨柱に複数の
ワイヤを取付ける他、1本のワイヤに1個ずつレバーブ
ロック等を使用するから、仮設資機材が多く必要にな
る。また、ワイヤを鉄骨柱の頂部に取り付ける作業は本
設床からおよそ12m程の高所で行われるため危険な場
所で手間の掛かる作業になっている。更に、鉄骨を粗い
精度で仮組みした後、鉄骨柱の建て方精度の補正作業を
行うので、最終的に精度が確保されるまで数日間は必要
となるから、それだけ工期も長びくことになる。
SUMMARY OF THE INVENTION The above-mentioned method for correcting the accuracy of the conventional general steel-framed columns uses a plurality of wires attached to each steel-framed column and a lever block or the like for each wire. Therefore, a lot of temporary equipment will be needed. Further, since the work of attaching the wire to the top of the steel column is performed at a height of about 12 m from the main floor, it is a troublesome work in a dangerous place. Furthermore, after temporarily assembling the steel frame with rough accuracy, the work of correcting the steel frame column construction accuracy is performed, and therefore several days are required until the accuracy is finally ensured, which leads to a longer construction period.

【0005】従って、本発明の目的は、駆動階先行上昇
型建築工法の特長を活かし、仮設資材類及び手間の削減
と工期の短縮を図れる鉄骨柱の建て方精度の補正方法を
提供することである。
Therefore, an object of the present invention is to provide a method of correcting the accuracy of erection of a steel column that can reduce the temporary materials and labor and the construction period by making the most of the features of the construction method of first ascending type drive floor. is there.

【0006】[0006]

【課題を解決するための手段】上述の課題を解決するた
めの手段として、本発明に係る駆動階先行上昇型建築工
法における柱の建て方精度の補正方法は、駆動階1に引
張材2の一端を固定し、前記引張材2の他端は柱の建て
方誤差を補正する向きに略水平方向に補正力を発生させ
る角度で既設の躯体3に固定し、前記駆動階1を若干上
昇させて、前記引張材2に発生する適度な張力と駆動階
1の上昇力との合力を補正力として柱4の建て方誤差を
補正し、しかる後、前記柱4と次上階床の梁鉄骨5を本
接合して固定することを特徴とする。
[Means for Solving the Problems] As a means for solving the above-mentioned problems, a method of correcting the erection accuracy of a pillar in a driving floor preceding ascending type construction method according to the present invention is such that a tension member 2 is attached to a driving floor 1. One end is fixed, and the other end of the tension member 2 is fixed to the existing frame 3 at an angle that generates a correction force in a substantially horizontal direction in a direction for correcting the pillar construction error, and the driving floor 1 is slightly raised. Then, the construction error of the pillar 4 is corrected using the resultant force of the appropriate tension generated in the tensile member 2 and the ascending force of the driving floor 1 as a correction force, and thereafter, the beam steel frame of the pillar 4 and the next upper floor. It is characterized in that 5 is permanently joined and fixed.

【0007】[0007]

【発明の実施の形態】以下、本発明の実施例の形態を図
面に基づいて説明する。図1は、建物のN階まで躯体3
の建築を完成した後、このN階の躯体3の床上で次上階
床(N+1階)の梁鉄骨5を組むなど躯体の建築を進め
る段階を示している。前記躯体3からは上方に略垂直に
複数層分の鉄骨柱4が建てられ、該鉄骨柱4に反力をと
り上昇するプッシュアップ装置6が駆動階1を先行上昇
させるように取り付けられている。次上階の梁鉄骨5等
の組立てをN階の本設床の上で完成した後は、駆動階1
に直接、吊具7によって吊り下げた形で駆動階1を上昇
させることにより前記梁鉄骨5等をN+1階位置へ持ち
上げ、前記鉄骨柱4と仮接合する。
Embodiments of the present invention will be described below with reference to the drawings. Figure 1 shows the building 3 up to the Nth floor of the building
After completion of the construction of No. 3, the stage of advancing the construction of the frame is shown, for example, the beam steel frame 5 of the next upper floor (N + 1 floor) is assembled on the floor of the frame 3 on the Nth floor. A plurality of layers of steel-framed columns 4 are erected substantially vertically upward from the frame 3, and a push-up device 6 that raises by taking a reaction force to the steel-framed columns 4 is attached so as to raise the drive floor 1 in advance. . After completing the assembly of the beam steel frame 5 etc. on the next upper floor on the N-th floor permanent floor, drive floor 1
Then, the beam floor 5 and the like are lifted to the N + 1th floor position by directly raising the drive floor 1 in the form of being suspended by the hanging tool 7, and temporarily joined to the steel column 4.

【0008】梁鉄骨5の本接合の前に、前記したよう
に、先行して建てられた鉄骨柱4の垂直精度をトランシ
ット等により確認する。そして、建て方誤差が発見され
たときは、まず駆動階1に予め取り付けてあるブラケッ
ト8に引張材2の一端を固定し、前記引張材2の他端は
鉄骨柱4の建て方誤差を補正する向きに略水平方向の補
正力を発生させる角度で既設の躯体3に用意したブラケ
ット8に固定する。前記引張材2にはワイヤ、鋼棒等が
使用され、建て方誤差の状況に応じて複数本使用する。
しかる後に、前記駆動階1を若干上昇させると、その上
昇力に伴ない前記引張材2に相応の引張力が発生する。
その結果、前記上昇力と引張力との合力が略水平方向に
発生し、前記合力が補正力となり駆動階1を介して建て
方誤差のある鉄骨柱4がその誤差を解消する方向へ押し
やられる。従って、前記トランシット等で監視しなが
ら、当該鉄骨柱4の建て方誤差が零になるまで駆動階1
の上昇をつづけることにより、鉄骨柱4の建て方精度の
補正が達成される。かくして建て方誤差を補正された鉄
骨柱4は、仮接合してある梁鉄骨5と本接合することに
より補正した状態をきっちり固定できる。補正作業の終
了後は、駆動階1を元の位置まで下降させ、引張材2を
撤去し、再び建築作業を進めることになる。以後、同様
な工程を繰り返すと、鉄骨柱4の建て方誤差を解消しつ
つ建物の建築が高精度に進むのである。
Before the main joining of the beam steel frame 5 is performed, as described above, the vertical accuracy of the steel frame column 4 built in advance is confirmed by a transit or the like. When an erection error is found, first, one end of the tension member 2 is fixed to the bracket 8 previously attached to the drive floor 1, and the other end of the tension member 2 corrects the erection error of the steel column 4. It is fixed to the bracket 8 prepared on the existing frame 3 at an angle that generates a correction force in a substantially horizontal direction. A wire, a steel rod, or the like is used as the tensile member 2, and a plurality of the tensile members 2 are used depending on the situation of the building error.
After that, when the driving floor 1 is slightly raised, a corresponding tensile force is generated in the tensile member 2 due to the ascending force.
As a result, a resultant force of the ascending force and the tensile force is generated in a substantially horizontal direction, and the resultant force serves as a correction force, and the steel frame column 4 having a building error is pushed through the driving floor 1 in a direction to eliminate the error. . Therefore, while monitoring with the transit, etc., the driving floor 1
By continuing to rise, the correction of the erection accuracy of the steel column 4 is achieved. In this way, the steel frame column 4 in which the construction error is corrected can be firmly fixed in the corrected state by the main connection with the beam steel frame 5 that is temporarily connected. After the completion of the correction work, the drive floor 1 is lowered to the original position, the tension member 2 is removed, and the construction work is started again. After that, by repeating the same process, the construction of the building progresses with high accuracy while eliminating the error in the method of constructing the steel column 4.

【0009】図1は全ての鉄骨柱4が駆動階1を介して
一気に補正される構成であるのに対し、図2は建て方誤
差の方向が共通しない右端の鉄骨柱4は駆動階1に届か
ない長さとし、もって補正作業の影響を受けない構成と
した実施例を示している。つまり、本発明の補正方法
は、複数本の鉄骨柱4の補正を駆動階1を介して一気に
行えるが、誤差の内容によっては、誤差が共通する鉄骨
柱4を選択して補正することを特徴とする。
In FIG. 1, all the steel columns 4 are corrected at once through the drive floor 1, whereas in FIG. 2, the rightmost steel column 4 in which the direction of the building error is not common is the drive floor 1. An example is shown in which the length is unreachable and the structure is not affected by the correction work. That is, according to the correction method of the present invention, the plurality of steel frame columns 4 can be corrected at once through the drive floor 1, but the steel frame columns 4 having a common error are selected and corrected depending on the content of the error. And

【0010】[0010]

【本発明が奏する効果】本発明に係る駆動階先行上昇型
建築工法における柱の建て方精度の補正方法は、複数の
鉄骨柱の垂直精度を駆動階を介して一気に補正できるか
ら、使用するワイヤの本数は柱の本数に比例せず、少数
でよく、またレバーブロックは必要ない。よって手間が
掛からず、それに伴い工期の短縮を図れる。また、レバ
ーブロック等の仮設資機材は不要でありコストの削減に
貢献する。
EFFECTS OF THE INVENTION The method for correcting the accuracy of the pillar construction in the driving-floor advance climbing construction method according to the present invention can correct the vertical accuracy of a plurality of steel columns at once through the driving floor, so that the wire to be used is used. The number of columns is not proportional to the number of columns and can be a small number, and a lever block is not required. Therefore, it does not take time and labor, and the construction period can be shortened accordingly. Moreover, temporary equipment such as lever blocks is not required, which contributes to cost reduction.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明のプッシュアップ装置の正面図FIG. 1 is a front view of a push-up device according to the present invention.

【図2】異なる実施例を示したプッシュアップ装置の正
面図
FIG. 2 is a front view of a push-up device showing a different embodiment.

【符号の説明】[Explanation of symbols]

1 駆動階 2 引張材 3 躯体 4 柱 5 梁鉄骨 1 Drive floor 2 Tensile material 3 Body 4 Pillar 5 Beam steel frame

───────────────────────────────────────────────────── フロントページの続き (72)発明者 森田 真弘 千葉県印旛郡印西町大塚一丁目5番 株式 会社竹中工務店技術研究所内 (72)発明者 宮口 正夫 東京都中央区銀座八丁目21番1号 株式会 社竹中工務店東京本店内 (72)発明者 中村 隆男 名古屋市中区錦一丁目18番22号 株式会社 竹中工務店名古屋支店内 (72)発明者 西山 正直 名古屋市中区錦一丁目18番22号 株式会社 竹中工務店名古屋支店内 (72)発明者 橋村 一彦 名古屋市中区錦一丁目18番22号 株式会社 竹中工務店名古屋支店内 (72)発明者 青山 邦男 名古屋市中区錦一丁目18番22号 株式会社 竹中工務店名古屋支店内 (72)発明者 谷村 和彦 名古屋市中区錦一丁目18番22号 株式会社 竹中工務店名古屋支店内 (72)発明者 森本 楊三 名古屋市中区錦一丁目18番22号 株式会社 竹中工務店名古屋支店内 (72)発明者 三井 健 名古屋市中区錦一丁目18番22号 株式会社 竹中工務店名古屋支店内 (72)発明者 藤田 務 名古屋市中区錦一丁目18番22号 株式会社 竹中工務店名古屋支店内 (72)発明者 谷口 四郎 名古屋市中区錦一丁目18番22号 株式会社 竹中工務店名古屋支店内 (72)発明者 宮口 幹太 名古屋市中区錦一丁目18番22号 株式会社 竹中工務店名古屋支店内 (72)発明者 鈴木 稔 東京都中央区銀座八丁目21番1号 株式会 社竹中土木内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Masahiro Morita 1-5-5 Otsuka, Inzai-cho, Inba-gun, Chiba Incorporated Takenaka Corporation Technical Research Institute (72) Masao Miyaguchi 8-21-1 Ginza, Chuo-ku, Tokyo No. 18 Incorporated Takenaka Corporation Tokyo Main Store (72) Inventor Takao Nakamura 1-18-22 Nishiki, Naka-ku, Nagoya-shi Incorporated Takenaka Corporation Nagoya Branch (72) Inventor Makoto Nishiyama 1- Nishiki, Naka-ku, Nagoya 18-22 No. 22 Takenaka Corporation Nagoya Branch (72) Inventor Kazuhiko Hashimura 1-chome Nishiki Naka-ku, Nagoya 18-22 Takenaka Corporation Nagoya Branch (72) Inventor Kunio Aoyama Nishiki Naka-ku, Nagoya 1-18-22 Takenaka Corporation Nagoya Branch (72) Inventor Kazuhiko Tanimura 1-18-22 Nishiki, Naka-ku, Nagoya Takenaka Corporation Nagoya Inside the branch (72) Inventor Yangzo Morimoto 1-18-22 Nishiki, Naka-ku, Nagoya-shi Takenaka Corporation Nagoya Branch (72) Inventor Ken Mitsui 18-22 Nishiki, Naka-ku, Nagoya Takenaka Corporation Nagoya Branch (72) Inventor Tsutomu Fujita 1-18-22 Nishiki, Naka-ku, Nagoya City Takenaka Corporation Nagoya Branch (72) Inventor Shiro Taniguchi 1-18-22 Nishiki, Naka-ku, Nagoya Takenaka Corporation Nagoya Branch (72) Inventor Shinta Miyaguchi 1-18-22 Nishiki, Naka-ku, Nagoya City Takenaka Corporation Nagoya Branch (72) Inventor Minoru Suzuki 21-21 Ginza, Chuo-ku, Tokyo Takenaka Civil Engineering Works No. 1 Stock Company

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 柱に反力をとるプッシュアップ装置によ
って駆動階を先行上昇させ、同駆動階の直下階の床上で
次上階の建築作業を進める駆動階先行上昇型建築工法に
おいて、 駆動階に引張材の一端を固定し、前記引張材の他端は柱
の建て方誤差を補正する向きに略水平方向の補正力を発
生させる角度で既設の躯体に固定し、前記駆動階を若干
上昇させて、前記引張材に発生する張力と駆動階の上昇
力との合力を補正力として柱の建て方誤差を補正し、し
かる後、前記柱と次上階梁を本接合して固定することを
特徴とする柱の建て方精度の補正方法。
1. A driving floor advance ascending type construction method in which a push-up device that applies a reaction force to a pillar raises the driving floor in advance and advances the construction work of the next upper floor on the floor immediately below the driving floor. One end of the tension material is fixed to the other end, and the other end of the tension material is fixed to the existing frame at an angle that generates a correction force in a substantially horizontal direction in the direction of correcting the building error of the column, and the driving floor is slightly raised. Then, the building error of the pillar is corrected by using the resultant force of the tension generated in the tensile member and the ascending force of the driving floor as a correction force, and thereafter, the pillar and the beam of the next upper floor are permanently joined and fixed. A method of correcting the accuracy of how to build a column.
JP16907195A 1995-07-04 1995-07-04 Correction method of column construction accuracy in driving floor advance type construction method Expired - Fee Related JP3661041B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16907195A JP3661041B2 (en) 1995-07-04 1995-07-04 Correction method of column construction accuracy in driving floor advance type construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16907195A JP3661041B2 (en) 1995-07-04 1995-07-04 Correction method of column construction accuracy in driving floor advance type construction method

Publications (2)

Publication Number Publication Date
JPH0921235A true JPH0921235A (en) 1997-01-21
JP3661041B2 JP3661041B2 (en) 2005-06-15

Family

ID=15879794

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16907195A Expired - Fee Related JP3661041B2 (en) 1995-07-04 1995-07-04 Correction method of column construction accuracy in driving floor advance type construction method

Country Status (1)

Country Link
JP (1) JP3661041B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103572837A (en) * 2012-07-30 2014-02-12 上海天演建筑物移位工程有限公司 Building jacking system and jacking method
CN104234439A (en) * 2014-09-03 2014-12-24 中铁十六局集团城市建设发展有限公司 Angle regulating device and angle regulating method in integrated frame lifting process

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103572837A (en) * 2012-07-30 2014-02-12 上海天演建筑物移位工程有限公司 Building jacking system and jacking method
CN103572837B (en) * 2012-07-30 2016-08-10 上海天演建筑物移位工程有限公司 A kind of building jacking method
CN104234439A (en) * 2014-09-03 2014-12-24 中铁十六局集团城市建设发展有限公司 Angle regulating device and angle regulating method in integrated frame lifting process

Also Published As

Publication number Publication date
JP3661041B2 (en) 2005-06-15

Similar Documents

Publication Publication Date Title
US7296349B2 (en) Method to assemble a steam generator
JPH0921235A (en) Column erecting accuracy correction method in drive floor advance rise type building construction method
CN107419907A (en) A kind of steel-making tower steel structure platform is staggered installation of welding method
CN107542163A (en) House frame
CN104153467A (en) Device for connecting shear wall and concrete floor in construction structure and arranging method thereof
JPH0673783A (en) Construction of steel framed reinforced concrete column and steel beam
JPH04153458A (en) Deflection controlling construction for beam, and deflection controlling method
JP3049571B2 (en) Joint method of steel tube concrete column and beam without diaphragm
JP3089348B2 (en) Beam-to-column connection of driving floor in roof push-up method
JP2791749B2 (en) Method and apparatus for lifting up top-level frame for structure construction
JP2793053B2 (en) Building construction method
JPH06248704A (en) Erecting method for steel frame roof using outcable string beam
JP2878571B2 (en) Building construction method using construction equipment
CN116289619A (en) Large-span curve steel box girder installation system and construction method
JPH1046838A (en) Method of demolition construction of building
CN114753652A (en) Steel structure roof jig frame sliding precision control method
JPS5934346A (en) Construction of film structure
CN118517071A (en) Reverse construction method for steel structure suspension structure of frame-first and barrel-last
JPS6213659A (en) Steel bar construction method of building
JP2622313B2 (en) How to build a building
JP2637358B2 (en) Chimney erection method and equipment
CN117188597A (en) Steel frame internal arch structure and flexible back-pull relay hoisting construction method thereof
JPH08120785A (en) Construction of portal frame assembly structure
JPH06146591A (en) Constructing method for building
JPS61158537A (en) Building of iron skeletal

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040817

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040831

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040909

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050207

A61 First payment of annual fees (during grant procedure)

Effective date: 20050307

Free format text: JAPANESE INTERMEDIATE CODE: A61

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 4

Free format text: PAYMENT UNTIL: 20090401

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 5

Free format text: PAYMENT UNTIL: 20100401

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 5

Free format text: PAYMENT UNTIL: 20100401

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110401

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees