JPH08210090A - Method and device for lining excavated wall surface of tunnel - Google Patents

Method and device for lining excavated wall surface of tunnel

Info

Publication number
JPH08210090A
JPH08210090A JP7043483A JP4348395A JPH08210090A JP H08210090 A JPH08210090 A JP H08210090A JP 7043483 A JP7043483 A JP 7043483A JP 4348395 A JP4348395 A JP 4348395A JP H08210090 A JPH08210090 A JP H08210090A
Authority
JP
Japan
Prior art keywords
wall surface
tunnel
cylindrical
cylindrical form
tunnel excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP7043483A
Other languages
Japanese (ja)
Other versions
JP3507173B2 (en
Inventor
Shingo Nagashima
伸吾 長島
Takeshi Daikuhara
毅 大工原
Minoru Kurashina
稔 蔵品
Mikio Takeuchi
幹雄 竹内
Kiyousuke Mishima
亨介 三島
Hiroshi Wada
洋 和田
Takeshi Hayashi
威 林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyo Gas Co Ltd
Okumura Corp
Original Assignee
Tokyo Gas Co Ltd
Okumura Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Gas Co Ltd, Okumura Corp filed Critical Tokyo Gas Co Ltd
Priority to JP04348395A priority Critical patent/JP3507173B2/en
Publication of JPH08210090A publication Critical patent/JPH08210090A/en
Application granted granted Critical
Publication of JP3507173B2 publication Critical patent/JP3507173B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PURPOSE: To efficiently and continuously form a set layer having the desired strength while preventing the set layer from adhering to a cylindrical form, in a method for forming the set layer made of a setting material on the excavated wall surface of a small-diameter tunnel using the cylindrical form. CONSTITUTION: A cylindrical form 5 that is smaller in diameter than a temporary pipe 1 laid inside a tunnel T is connected to the temporary pipe 1 in such a way that it can advance integral with the pipe 1. After a setting material 6 is injected into a cavity 9 between the cylindrical form 4 and the excavated wall surface 8 of the tunnel, the cylindrical form 5 is moved back and forth by means of a jack 7 so as to form a cylindrical set layer integrated with the tunnel excavated wall surface 8, while preventing the setting material 6 from adhering to the cylindrical form 5.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明はトンネル内に敷設された
仮管の前進に従って、トンネル掘削壁面に硬化性材料か
らなる覆工を形成する方法とその方法を実施するための
装置に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for forming a lining made of a hardenable material on a tunnel excavation wall as a temporary pipe laid in a tunnel advances, and an apparatus for carrying out the method. .

【0002】[0002]

【従来の技術】シールド機によって掘削されたトンネル
掘削壁面に覆工を施す場合、大口径のトンネルにおいて
は一定長のトンネルの掘進毎にトンネル内で型枠を組み
立てたのち、該型枠とトンネル掘削壁面との間にコンク
リートを打設することによって施工することが行われて
いるが、作業員が出入りできない小口径のトンネルの場
合には覆工作業ができない。
2. Description of the Related Art When lining a tunnel excavation wall surface excavated by a shield machine, in a large-diameter tunnel, a formwork is assembled in the tunnel every time a tunnel of a certain length is advanced, and then the formwork and the tunnel are assembled. Construction is performed by placing concrete between the excavated wall surface, but lining work cannot be performed in the case of a tunnel with a small diameter where workers cannot enter or leave.

【0003】このため、小口径シールド機によって発進
立坑から到達立坑に向かってトンネルを掘進すると共に
その掘進に従って仮管を該シールド機に後続させて順次
継ぎ足しながら推進し、両立坑間に複数本の仮管を直列
状に埋設したのち、最後部の仮管に該仮管よりも小径の
円筒形型枠を連結し、到達立坑側から仮管を順次引き抜
く一方、仮管が適宜長さ前進する毎に円筒形型枠とトン
ネル掘削壁面との間の空隙部にモルタル等の硬化性材料
を注入して硬化層を形成するトンネル掘削壁面の覆工方
法が提案されている。
Therefore, a small-diameter shield machine excavates a tunnel from the starting shaft to the reaching shaft, and in accordance with the excavation, a temporary pipe is followed by the shield machine and sequentially added and propelled, and a plurality of tunnels are provided between the compatible shafts. After burying the temporary pipe in series, connect a cylindrical formwork having a smaller diameter than the temporary pipe to the temporary pipe at the rearmost part, and pull out the temporary pipe from the reaching shaft side one by one, while the temporary pipe advances by an appropriate length. A method of lining a tunnel excavation wall surface is proposed in which a curable material such as mortar is injected into a gap between the cylindrical formwork and the tunnel excavation wall surface to form a hardened layer.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、上記の
ようなトンネル覆工方法では、硬化層を形成するに際し
て、仮管の引抜きを停止してトンネル掘削壁面と円筒形
型枠との間の空隙部に硬化性材料を注入すると、該硬化
性材料が硬化するにつれて円筒形型枠の外周面に付着
し、そのため、トンネル掘削壁面に一体的に固着した一
定強度の硬化層にまで硬化させたのち仮管と共に円筒形
型枠を次の覆工施工位置まで前進させようとすると、該
円筒形型枠の外周面に硬化性材料が一体的に付着してい
るので、仮管と共に円筒形型枠を前進させることができ
なくなる。
However, in the tunnel lining method as described above, when forming the hardened layer, the withdrawal of the temporary pipe is stopped and the void portion between the tunnel excavation wall surface and the cylindrical form is formed. When the curable material is injected into the, it adheres to the outer peripheral surface of the cylindrical form as the curable material hardens, so that after hardening to a hardened layer of constant strength integrally fixed to the tunnel excavation wall surface, When attempting to advance the cylindrical formwork to the next lining construction position together with the pipe, the curable material is integrally attached to the outer peripheral surface of the cylindrical formwork, so the cylindrical formwork is installed together with the temporary pipe. You will not be able to move forward.

【0005】また、硬化性材料の付着力に抗して付着部
分を破断させる牽引力でもって仮管を前進させると、硬
化層自体が張力を受けてクラックが生じ、該クラックを
通じて地下水がトンネル内に浸入することになる。この
ため、円筒形型枠の外周面にシリコン等の離型層を設け
ておけば、硬化性材料の付着力を減少させることができ
るが、このような離型層を設けておいても円筒形型枠を
停止させた状態で硬化性材料を硬化させるものであるか
ら、円筒形型枠に対する硬化性材料の完全な付着防止が
不可能であり、硬化性材料の硬化が進行するに従って離
型層に対する付着力も増大して次の覆工位置まで前進さ
せる際に大きな抵抗力が発生し、作業能率が低下するば
かりでなく前進時には上述したように硬化層にクラック
が生じる虞れがある。
Further, when the temporary pipe is advanced by a traction force that breaks the adhered portion against the adhesive force of the curable material, the cured layer itself receives tension and cracks occur, and groundwater passes through the cracks into the tunnel. It will infiltrate. Therefore, if a release layer such as silicon is provided on the outer peripheral surface of the cylindrical mold, the adhesive force of the curable material can be reduced. Since the curable material is cured while the formwork is stopped, it is impossible to completely prevent the curable material from adhering to the cylindrical formwork. The adhesive force to the layer also increases, and a large resistance force is generated when advancing to the next lining position, which not only lowers work efficiency but also may cause cracks in the hardened layer during advancing as described above.

【0006】本発明はこのような問題点に鑑みてなされ
たもので、その目的とするところは円筒形型枠に対する
硬化性材料の付着を防止しながら、小口径のトンネル掘
削壁面に均一な強度を有する硬化層を能率よく覆工、形
成し得るトンネル掘削壁面の覆工方法とその方法を実施
するための装置を提供するにある。
The present invention has been made in view of the above problems, and an object thereof is to prevent the hardening material from adhering to the cylindrical form while maintaining a uniform strength on the wall surface of the tunnel excavation having a small diameter. The present invention provides a method for lining a tunnel excavation wall surface that enables efficient lining and formation of a hardened layer having the above, and an apparatus for performing the method.

【0007】[0007]

【課題を解決するための手段】上記目的を達成するため
に、本発明のトンネル掘削壁面の覆工方法は、トンネル
内に敷設している仮管の後端に内筒を一体に連結し、こ
の内筒の外周面に外径が上記仮管よりも小径の円筒形型
枠を摺動自在に被嵌し、該円筒形型枠とトンネル掘削壁
面との間の空隙部に硬化性材料を注入したのち、円筒形
型枠を前後又は周方向に往復動させながら該硬化性材料
を硬化させて円筒状硬化層を形成し、この硬化層を仮管
の前進に従ってトンネル掘削壁面に連続的に施工するこ
とを特徴とするものである。
In order to achieve the above object, a method of lining a tunnel excavation wall surface of the present invention is to integrally connect an inner cylinder to a rear end of a temporary pipe laid in a tunnel, A cylindrical formwork having an outer diameter smaller than that of the temporary pipe is slidably fitted on the outer peripheral surface of the inner cylinder, and a curable material is placed in a space between the cylindrical formwork and the tunnel excavation wall surface. After the injection, the curable material is cured while reciprocating the cylindrical form in the front-rear direction or in the circumferential direction to form a cylindrical hardened layer, and the hardened layer is continuously applied to the tunnel excavation wall surface as the temporary pipe advances. It is characterized by being constructed.

【0008】上記方法において、請求項2に記載した発
明は、円筒形型枠とトンネル掘削壁面との間の空隙部に
注入した硬化性材料の硬化完了毎に仮管を円筒形型枠と
共にトンネル方向に一定長、前進させることを特徴とす
るものであり、請求項3に記載した発明は、円筒形型枠
とトンネル掘削壁面との間の空隙部に注入した硬化性材
料の硬化速度に同調した速度で仮管を円筒形型枠と共に
前進させることを特徴とするものである。
In the above method, in the invention described in claim 2, the temporary pipe is tunneled together with the cylindrical form every time the hardening of the curable material injected into the gap between the cylindrical form and the tunnel excavation wall is completed. The invention described in claim 3 is characterized by advancing a predetermined length in the direction, and is synchronized with the curing speed of the curable material injected into the gap between the cylindrical formwork and the tunnel excavation wall surface. It is characterized in that the temporary tube is advanced together with the cylindrical form at the above speed.

【0009】また、上記方法を実施するための装置とし
ては、請求項4に記載したように、トンネル内に敷設し
ている仮管の後端に一定長さを有する内筒の前端を一体
的に連結すると共にこの内筒に上記仮管よりも小径の円
筒形型枠を摺動自在に被嵌させ、さらに、トンネル掘削
壁面と円筒形型枠との間の空隙部に硬化性材料を注入す
る配管を配設すると共に仮管の後端部内に上記円筒形型
枠を前後又は周方向に摺動させるジャッキを配設してな
るものである。
As a device for carrying out the above method, as described in claim 4, a front end of an inner cylinder having a certain length is integrally formed at a rear end of a temporary pipe laid in a tunnel. A cylindrical formwork having a diameter smaller than that of the temporary pipe is slidably fitted into the inner cylinder, and a curable material is injected into the space between the tunnel excavation wall surface and the cylindrical formwork. And a jack for sliding the cylindrical form in the front and rear or in the circumferential direction in the rear end of the temporary pipe.

【0010】[0010]

【作用】仮管を一定長、前進させる毎に、トンネル掘削
壁面と円筒形型枠との間の空隙部に硬化性材料を注入し
てトンネル掘削壁面に硬化層を順次、連続覆工していく
ものであるが、覆工位置において、仮管の前進を停止さ
せた状態でトンネル掘削壁面と円筒形型枠との間の空隙
部に硬化性材料を注入、硬化させる際に、円筒形型枠を
前後動又は周方向に往復動させるものである。このよう
に、円筒形型枠を往復動させると、硬化性材料と円筒形
型枠との接触部が常に縁切り状態となって硬化性材料の
硬化が進行しても円筒形型枠の外周面に付着するのを防
止されると共にその振動作用によって硬化性材料が空隙
内に密に且つ均一に充満するものである。
[Operation] Each time the temporary pipe is moved forward for a certain length, a curable material is injected into the gap between the tunnel excavation wall surface and the cylindrical form, and the tunnel excavation wall surface is successively covered with a hardened layer. At the lining position, when the curable material is injected and cured in the gap between the tunnel excavation wall surface and the cylindrical form at the lining position, the cylindrical form The frame is moved back and forth or reciprocally in the circumferential direction. In this way, when the cylindrical formwork is reciprocated, the contact portion between the curable material and the cylindrical formwork is always in an edge-cutting state, and even if the hardening of the curable material progresses, the outer peripheral surface of the cylindrical formwork The curable material is densely and uniformly filled in the voids due to its vibration effect.

【0011】そして、この状態で硬化性材料の硬化が進
行してトンネル掘削壁面に一体に固着した一定厚みの均
質な円筒形状硬化層が形成され、この硬化層が一定の強
度に達すると仮管を一定長、前進させて該仮管と共に円
筒形型枠を次の覆工位置まで移動させ、その位置で停止
させて再び上記同様にトンネル掘削壁面と円筒形型枠と
の間の空隙部に硬化性材料を注入、充満させ、円筒形型
枠を往復動させながら先に設けた硬化層と連続する硬化
層を形成するものである。
Then, in this state, the hardening of the hardening material progresses to form a uniform cylindrical hardened layer having a constant thickness and integrally fixed to the wall surface of the tunnel excavation. When the hardened layer reaches a certain strength, the temporary pipe is formed. Is moved forward by a certain length to move the cylindrical formwork together with the temporary pipe to the next lining position, stopped at that position, and again in the space between the tunnel excavation wall surface and the cylindrical formwork as described above. The curable material is injected and filled, and the cylindrical form is reciprocated to form a cured layer continuous with the previously provided cured layer.

【0012】仮管の前進動作は、円筒形型枠とトンネル
掘削壁面との間の空隙部に注入した硬化性材料の硬化が
完了したのち、トンネルの長さ方向に一定長さ距離だけ
前進させて円筒形型枠を次の覆工位置まで一体移動させ
てもよく、また、円筒形型枠とトンネル掘削壁面との間
の空隙部に注入した硬化性材料が一定の強度にまで硬化
した状態からさらに硬化が進行する速度に応じて円筒形
型枠と共に徐々に前進させてもよい。
The advancing operation of the temporary pipe is performed by advancing a predetermined length distance in the length direction of the tunnel after the hardening of the hardenable material injected into the gap between the cylindrical formwork and the tunnel excavation wall surface is completed. The cylindrical formwork may be integrally moved to the next lining position, and the curable material injected into the gap between the cylindrical formwork and the tunnel excavation wall has hardened to a certain strength. It is also possible to gradually move forward together with the cylindrical form according to the speed at which the curing further progresses.

【0013】[0013]

【実施例】本発明の実施例を図面について説明すると、
図1〜図5において、発進立坑Aから到達立坑B間に亘
って掘削形成されたトンネルT内に直列状態に接続した
仮管1が敷設されている。仮管1の外周面はトンネル掘
削壁面8に摺接し、地盤の崩壊を防止している。直列状
態に接続した仮管列の最後部の仮管1の後端には、図2
に示すように、該仮管1と同一外径を有する短筒体2を
一体的に連結してあり、この短筒体2の内周面数カ所に
リブ2aを固着し、該リブ2aの後端面に一定長さを有する
内筒3の前端を一体的に固着している。内筒3の前後端
部は外径に向かって肉厚の円形摺接面3a、3bに形成さ
れ、これらの円形摺接面3a、3bにシール4を介して円筒
形型枠5の前後端部の内周面を摺動自在に密接させてい
る。なお、円筒形型枠5の前端部外周面は短筒体2の後
端に一体に設けているリング状妻板2cの内周面に摺動自
在に密接させている。
Embodiments of the present invention will now be described with reference to the drawings.
1 to 5, a temporary pipe 1 connected in series is laid in a tunnel T formed by excavation from a starting shaft A to a reaching shaft B. The outer peripheral surface of the temporary pipe 1 is in sliding contact with the tunnel excavation wall surface 8 to prevent the ground from collapsing. The rear end of the temporary pipe 1 at the end of the temporary pipe row connected in series is shown in FIG.
As shown in FIG. 2, a short tube body 2 having the same outer diameter as the temporary tube 1 is integrally connected, and ribs 2a are fixed to several places on the inner peripheral surface of the short tube body 2 and the ribs 2a The front end of the inner cylinder 3 having a fixed length is integrally fixed to the end surface. The front and rear ends of the inner cylinder 3 are formed in thick circular slidable contact surfaces 3a and 3b toward the outer diameter, and the circular slidable contact surfaces 3a and 3b are provided with seals 4 on the front and rear ends of the cylindrical formwork 5. The inner peripheral surface of the part is slidably in close contact. The outer peripheral surface of the front end of the cylindrical form 5 is slidably brought into close contact with the inner peripheral surface of the ring-shaped end plate 2c integrally provided at the rear end of the short tubular body 2.

【0014】この円筒形型枠5は仮管1の外径よりもそ
の外径が小径で且つ内筒3と同長またはやゝ長く形成さ
れていると共にその外周面にセラミックとフッ素樹脂と
の複合コーティング等からなる離型層5aを層着してあ
り、この離型層5aによって後述する硬化性材料6の硬化
層6aと円筒形型枠5との剥離性を良好にしている。又、
上記リブ2aの後端部外面側には円筒形型枠5の前端部が
一定長、出入り可能な切込部2bが設けられていると共に
短筒体2の内周面数カ所にジャッキ7を装着し、このジ
ャッキ7のロッド後端を円筒形型枠5の前端面に一体的
に連結し、これらのジャッキ7のロッドを伸縮させるこ
とにより円筒形型枠5を内筒3上で前後摺動させるよう
に構成している。なお、これらのジャッキ7を円周方向
に向けてそのロッド端を円筒形型枠5の前端面に一体的
に連結し、円筒形型枠5を内筒3上で周方向に往復摺動
させるように構成しておいてもよい。
The cylindrical form 5 has an outer diameter smaller than the outer diameter of the temporary pipe 1 and is formed to have the same length as or a little longer than the inner cylinder 3, and its outer peripheral surface is made of ceramic and fluororesin. A mold release layer 5a made of a composite coating or the like is layered, and the mold release layer 5a improves the releasability between the cured layer 6a of the curable material 6 described later and the cylindrical mold 5. or,
On the outer surface side of the rear end of the rib 2a, the front end of the cylindrical formwork 5 is provided with a fixed length, and a cut-in portion 2b capable of entering and exiting is provided, and jacks 7 are attached to the inner surface of the short tubular body 2 at several places. Then, the rod rear end of the jack 7 is integrally connected to the front end face of the cylindrical form 5, and the rods of these jacks 7 are expanded and contracted to slide the cylindrical form 5 back and forth on the inner cylinder 3. It is configured to let. It should be noted that these jacks 7 are oriented in the circumferential direction and their rod ends are integrally connected to the front end surface of the cylindrical form 5, so that the cylindrical form 5 reciprocally slides on the inner cylinder 3 in the circumferential direction. It may be configured as follows.

【0015】さらに、上記短筒体2の適所には該短筒体
2の一部に内周面からトンネル掘削壁面8と円筒形型枠
5との間の空隙部9に連通する硬化性材料注入孔10を穿
設してなる注入部材10a を一体に設けていると共に、こ
の注入孔10に短筒体2内側から注入管11とバルブ21を有
する洗浄水供給管12とを連結、連通させている。注入管
11の先端部にはバルブ22を有する戻り管13と急結材供給
管14とが注入管11に設けたバルブ23を介して順次、分岐
状態で接続している。
Further, at a suitable position of the short tubular body 2, a curable material which communicates with a part of the short tubular body 2 from an inner peripheral surface to a void portion 9 between the tunnel excavation wall surface 8 and the cylindrical formwork 5. An injection member 10a having an injection hole 10 is integrally provided, and an injection pipe 11 and a cleaning water supply pipe 12 having a valve 21 are connected to and communicate with the injection hole 10 from the inside of the short cylinder 2. ing. Injection tube
A return pipe 13 having a valve 22 and a quick-connecting material supply pipe 14 are sequentially connected in a branched state via a valve 23 provided in the injection pipe 11 to the tip of the pipe 11.

【0016】なお、上記注入孔10を円筒形型枠5の前端
部適所に設け、この注入孔10に可撓性注入短管の外端開
口部を接続し、該可撓性注入短管の内端開口部を内筒3
の内周面に臨ませてその開口部に上記注入管11等を連
結、連通させた構造としておいてもよい。また、注入管
11や洗浄水供給管12、戻り管13、急結材供給管14等は図
1に示すように仮管列の内部を通じて到達立坑B側から
地上に設置した夫々の供給設備Cに連結、連通させてい
るが、トンネルT内を通じて発進立坑A側に配設してお
いてもよい。
The injection hole 10 is provided at a proper position in the front end portion of the cylindrical form 5, and the outer end opening of the flexible injection short pipe is connected to the injection hole 10 to form the flexible injection short pipe. Inner tube 3 with inner end opening
The structure may be such that the injection pipe 11 and the like are connected and communicated with the opening facing the inner peripheral surface. Also the injection tube
11, the washing water supply pipe 12, the return pipe 13, the quick connection material supply pipe 14, etc. are connected and communicated with the respective supply facilities C installed on the ground from the reaching shaft B side through the inside of the temporary pipe row as shown in FIG. However, it may be arranged on the side of the starting shaft A through the tunnel T.

【0017】次に、上記のように構成した装置によって
トンネル掘削壁面8に硬化性材料6の硬化による硬化層
6aよりなる覆工を施す方法について説明する。まず、発
進立坑Aと到達立坑Bとの間にトンネルTを掘削しなが
ら多数本の仮管1を直列状に敷設しておくが、この仮管
1の敷設作業は、図6に示すように発進立坑Aから到達
立坑Bに向かってシールド機SによりトンネルTを掘削
しながらその掘進に従って該シールド機Sに仮管1を順
次継ぎ足して発進立坑A内に設置した推進ジャッキGに
より推進し、到達立坑Bに達したシールド機Sを撤去し
て両縦坑A、B間に多数本の直列状に埋設するものであ
る。
Next, a hardened layer formed by hardening the hardenable material 6 on the tunnel excavation wall surface 8 by the apparatus configured as described above.
A method of applying a lining consisting of 6a will be described. First, a large number of temporary pipes 1 are laid in series while excavating a tunnel T between the starting shaft A and the reaching shaft B. The laying work of the temporary pipe 1 is as shown in FIG. While the tunnel T is being excavated by the shield machine S from the starting shaft A to the reaching shaft B, the temporary pipe 1 is sequentially added to the shielding device S in accordance with the excavation, and is propelled by the propulsion jack G installed in the starting shaft A to reach the shaft. The shield machine S that has reached the vertical shaft B is removed and buried in a large number of series between the vertical shafts A and B.

【0018】この仮管列の最後部の仮管1の後端に上述
したように、短筒体2を連結すると共に該短筒体2に円
筒形型枠5を摺動自在に被嵌させている内筒3を連結し
たのち、覆工作業を開始する。まず、到達立坑B側から
最前部の仮管1をウインチ等の適宜な牽引手段(図示せ
ず)によって牽引し、仮管列と共に円筒形型枠5を一定
長(円筒形型枠5の長さ以下)前進させると、円筒形型
枠5はトンネル掘削壁面8よりも小径に形成されている
ので、円筒形型枠5とトンネル掘削壁面8との間に断面
円環状の空隙部9が設けられる。この空隙部9に仮管1
の前進を停止させた状態で注入管11、注入孔10を通じて
硬化性材料6を注入し、該空隙部9内に充満させる。な
お、空隙部9への硬化性材料6の注入は、仮管1が前進
して空隙部9が生じると同時に注入するようにしてもよ
い。
As described above, the short cylinder 2 is connected to the rear end of the temporary pipe 1 at the rearmost portion of the temporary pipe row, and the cylindrical form 5 is slidably fitted on the short cylinder 2. After connecting the inner cylinders 3, the lining work is started. First, the foremost temporary pipe 1 is pulled from the reaching shaft B side by an appropriate pulling means (not shown) such as a winch, and the cylindrical formwork 5 is fixed length (the length of the cylindrical formwork 5) together with the temporary pipe row. When moving forward, the cylindrical form 5 is formed with a diameter smaller than that of the tunnel excavation wall surface 8. Therefore, a space 9 having an annular cross section is provided between the cylindrical form frame 5 and the tunnel excavation wall surface 8. To be The temporary pipe 1 is placed in this void portion 9.
The curable material 6 is injected through the injection pipe 11 and the injection hole 10 in a state where the advance is stopped, and the void 9 is filled with the curable material 6. The curable material 6 may be injected into the void 9 at the same time as the provisional tube 1 is moved forward to form the void 9.

【0019】硬化性材料6としてはセメントと砂とを混
練したモルタル、あるいはこのモルタルにベントナイト
を添加した材料や水ガラスと砂との混合物等のように、
注入時には液状体で注入後、一定時間経過すれば硬化し
て所定の強度を有する硬化層6aを形成するものであれば
よい。この硬化性材料6を空隙部9に注入する直前に供
給管14を通じて硬化性材料6の硬化を促進させる急結材
を注入管11に供給し、硬化性材料6に混入させた状態で
空隙部9内に注入する。
As the curable material 6, for example, a mortar in which cement and sand are kneaded, a material in which bentonite is added to this mortar, or a mixture of water glass and sand,
At the time of injection, any material may be used as long as it is a liquid material and is cured after a certain period of time to form a cured layer 6a having a predetermined strength. Immediately before injecting the curable material 6 into the cavity 9, a quick-setting material that accelerates the curing of the curable material 6 is supplied to the injection tube 11 through the supply tube 14, and the cavity is mixed in the curable material 6. Inject into 9.

【0020】空隙部9内に硬化性材料6を注入したの
ち、仮管1の後端に連結した短筒体2内に装着している
ジャッキ7のロッドを伸縮させて円筒形型枠5を前後方
向に往復動させると、硬化性材料6がその振動によって
全体的に均一な密度で空隙部9内に充満すると共に硬化
性材料6と円筒形型枠5との接触面が縁切りされて硬化
性材料6が円筒形型枠5の外周面に付着するのを防止さ
れる。この硬化性材料6の付着防止は、円筒形型枠5の
外周面に層着している離型層5aによって一層確実に行わ
れると共に硬化性材料6の硬化が進行するに従って離型
層5aと摺接する該硬化性材料6の内周面が平滑化されて
完全な剥離状態となる。
After injecting the curable material 6 into the void portion 9, the rod of the jack 7 mounted in the short tubular body 2 connected to the rear end of the temporary pipe 1 is expanded and contracted to form the cylindrical form 5. When it is reciprocated in the front-rear direction, the curable material 6 fills the voids 9 with a uniform density as a whole due to the vibration, and the contact surface between the curable material 6 and the cylindrical mold 5 is cut off and cured. The conductive material 6 is prevented from adhering to the outer peripheral surface of the cylindrical form 5. The prevention of adhesion of the curable material 6 is more surely performed by the release layer 5a layered on the outer peripheral surface of the cylindrical mold 5, and as the curing of the curable material 6 proceeds, The inner peripheral surface of the curable material 6 that is in sliding contact is smoothed to be in a completely peeled state.

【0021】一方、トンネル掘削壁面8に対しては硬化
性材料6が完全に付着し、この状態で硬化性材料6の硬
化が進行してトンネル掘削壁面8に一体的に固着した円
筒形状の硬化層6aが徐々に形成される。この硬化層6aの
形状が内径方向に変形しない程度の一定の強度まで該硬
化層6aが硬化したのち、再び、仮管1を一定長、牽引し
て円筒形型枠5を被嵌させている内管3を一体的に前進
させ、その前進によって次の覆工部位である空隙部9を
設け、該空隙部9に硬化性材料6を注入して円筒形型枠
5を往復動させながら硬化させ、上記硬化層6aに連続し
た硬化層6aを形成する。なお、発進立坑A側から最初の
硬化層6aを形成する際には、トンネル掘削壁面8の開口
端と円筒形型枠5の外周面間を適宜なシール材(図示せ
ず)によって密閉しておく。
On the other hand, the curable material 6 is completely adhered to the tunnel excavation wall surface 8, and in this state, the curable material 6 is cured and the cylindrical excavation wall surface 8 is integrally fixed to the tunnel excavation wall surface 8. Layer 6a is gradually formed. After the hardened layer 6a has hardened to a certain strength such that the shape of the hardened layer 6a is not deformed in the inner diameter direction, the temporary tube 1 is pulled again by a certain length to fit the cylindrical form 5 thereon. The inner tube 3 is integrally advanced, and by the advancement, a void portion 9 which is the next lining portion is provided, and the curable material 6 is injected into the void portion 9 and cured while reciprocating the cylindrical formwork 5. Then, a hardened layer 6a continuous with the hardened layer 6a is formed. When forming the first hardened layer 6a from the side of the starting shaft A, the space between the opening end of the tunnel excavation wall surface 8 and the outer peripheral surface of the cylindrical form 5 is sealed with an appropriate sealing material (not shown). deep.

【0022】このように、円筒形型枠5を仮管列と共に
一定長、前進させる毎に、トンネル掘削壁面8と円筒形
型枠5との間の空隙部9に硬化性材料6の注入と円筒形
型枠5の前後動の作動下における硬化の進行を行わせ、
一定強度まで硬化した硬化層6aを形成していくものであ
るが、硬化層6aが完全に硬化したのち、円筒形型枠5を
一定長、前進させてもよく、硬化層6aが一定強度まで達
したのち完全に硬化するまでの間、その硬化速度に同調
して円筒形型枠5を仮管1の牽引によって一定長、徐々
に掘進させてもよい。
As described above, every time the cylindrical form 5 is moved forward together with the temporary pipe row by a certain length, the curable material 6 is injected into the space 9 between the tunnel excavation wall surface 8 and the cylindrical form 5. The hardening is performed under the operation of the back and forth movement of the cylindrical form 5,
The hardened layer 6a is formed to be hardened to a certain strength, but after the hardened layer 6a is completely hardened, the cylindrical form 5 may be moved forward for a certain length. After reaching the temperature, the cylindrical form 5 may be gradually excavated by a certain length by pulling the temporary pipe 1 in synchronization with the curing speed until it is completely cured.

【0023】なお、硬化性材料6がトンネル掘削壁面8
と円筒形型枠5との空隙部9に注入、充満させる毎に、
直ちに硬化性材料注入管11のバルブ23を閉止する一方、
戻り管13のバルブ22を開放した状態にして洗浄水供給管
14から洗浄水を注入孔10を通じて注入管11の先端部を流
動させ、該注入孔10と注入管11に充填されている硬化性
材料6を戻り管13を通じて排除し、次の注入に支障を生
じないようにする。また、空隙部9に臨んでいる注入孔
10の開口端には硬化性材料6が注入孔10内に逆流するの
を阻止するようにしている。
The hardenable material 6 is the tunnel excavation wall surface 8.
Every time it is filled and filled in the space 9 between the cylindrical formwork 5 and
While immediately closing the valve 23 of the curable material injection pipe 11,
Wash water supply pipe with the valve 22 of the return pipe 13 opened
Cleaning water is made to flow from 14 through the injection hole 10 through the tip of the injection pipe 11, and the curable material 6 filled in the injection hole 10 and the injection pipe 11 is removed through the return pipe 13 to prevent the next injection. Try not to occur. In addition, the injection hole facing the space 9
At the open end of the curable material 6, the curable material 6 is prevented from flowing back into the injection hole 10.

【0024】トンネル掘削壁面8に対する上記硬化層6a
の覆工作業が進むに従って、到達立坑B側においては仮
管1が順次引抜き、撤去される。こうして、両立坑A、
B間に亘ってトンネル掘削壁面8に覆工を施すものであ
る。
The hardened layer 6a for the tunnel excavation wall surface 8
As the lining work proceeds, the temporary pipe 1 is sequentially pulled out and removed on the side of the reaching shaft B. Thus, compatibility pit A,
The tunnel excavation wall surface 8 is covered with a lining.

【0025】[0025]

【発明の効果】以上のように本発明によれば、トンネル
内に敷設している仮管の後端に内筒を一体に連結し、こ
の内筒の外周面に外径が上記仮管よりも小径の円筒形型
枠を摺動自在に被嵌し、該円筒形型枠とトンネル掘削壁
面との間の空隙部に硬化性材料を注入したのち、円筒形
型枠を前後又は周方向に往復動させながら該硬化性材料
を硬化させて円筒状硬化層を形成し、この硬化層を仮管
の前進に従ってトンネル掘削壁面に連続的に施工するも
のであるから、仮管の後端に連結した内筒の外周面をガ
イドとして円筒形型枠を正確に往復動させることができ
るばかりでなく、該円筒形型枠の往復動によって硬化性
材料が該円筒形型枠の外周面に付着、硬化するのを防止
することができると共に硬化性材料を空隙部内に密に充
満させることができ、この状態で硬化させてトンネル掘
削壁面に一体的に固着した均一で優れた強度を有する一
定厚みの硬化層を形成することができる。
As described above, according to the present invention, the inner cylinder is integrally connected to the rear end of the temporary pipe laid in the tunnel, and the outer diameter of the inner cylinder is larger than that of the temporary pipe. Also, a cylindrical formwork having a small diameter is slidably fitted, and a curable material is injected into the gap between the cylindrical formwork and the tunnel excavation wall surface. Since the curable material is cured while reciprocating to form a cylindrical hardened layer, and the hardened layer is continuously applied to the tunnel excavation wall surface as the temporary pipe advances, it is connected to the rear end of the temporary pipe. Not only can the cylindrical formwork be accurately reciprocated by using the outer peripheral surface of the inner cylinder as a guide, but the curable material adheres to the outer peripheral surface of the cylindrical formwork by the reciprocating motion of the cylindrical formwork, It is possible to prevent the resin from hardening and to fill the voids with a hardenable material. , It is possible to form a cured layer of a predetermined thickness having excellent strength at uniform and fixed integrally cured in this state to the tunnel excavation wall.

【0026】さらに、硬化性材料の硬化が進行して一定
の強度にまで硬化した硬化層が形成されると、該硬化層
が上述したように円筒形型枠の往復動によって該円筒形
型枠に付着することなく縁切り状態となっているので、
円筒形型枠を次の覆工部位まで前進させる際には硬化層
にクラックを発生させる虞れもなく、仮管と伴に円筒形
型枠の前進が円滑に行われて作業能率の向上を図ること
ができるものである。
Further, when the curable material is further cured to form a cured layer which is cured to a certain strength, the cured layer is reciprocated as described above to reciprocally move the cylindrical form. Since it is in a rim cutting state without adhering to,
When advancing the cylindrical formwork to the next lining site, there is no risk of cracking in the hardened layer, and the advancement of the cylindrical formwork along with the temporary pipe is performed smoothly to improve work efficiency. It can be achieved.

【図面の簡単な説明】[Brief description of drawings]

【図1】施工状態を示す簡略縦断側面図、FIG. 1 is a simplified vertical sectional side view showing a construction state,

【図2】仮管に連結した円筒形型枠部分の縦断側面図、FIG. 2 is a vertical sectional side view of a cylindrical formwork portion connected to a temporary pipe,

【図3】図2におけるAーA線断面図、3 is a sectional view taken along line AA in FIG.

【図4】図2におけるBーB線断面図、FIG. 4 is a sectional view taken along line BB in FIG.

【図5】図2におけるCーC線断面図、5 is a sectional view taken along line CC in FIG.

【図6】仮管を埋設している状態の縦断側面図。FIG. 6 is a vertical cross-sectional side view showing a state in which a temporary pipe is buried.

【符号の説明】[Explanation of symbols]

1 仮管 3 内筒 5 円筒形型枠 6 硬化性材料 6a 硬化層 7 ジャッキ 8 トンネル掘削壁面 9 空隙部 10 注入孔 1 Temporary pipe 3 Inner cylinder 5 Cylindrical form 6 Curable material 6a Hardened layer 7 Jack 8 Tunnel excavation wall surface 9 Void portion 10 Injection hole

フロントページの続き (72)発明者 蔵品 稔 東京都杉並区和泉2ー10ー9 (72)発明者 竹内 幹雄 大阪市阿倍野区松崎町2丁目2番2号 株 式会社奥村組内 (72)発明者 三島 亨介 大阪市阿倍野区松崎町2丁目2番2号 株 式会社奥村組内 (72)発明者 和田 洋 大阪市阿倍野区松崎町2丁目2番2号 株 式会社奥村組内 (72)発明者 林 威 大阪市阿倍野区松崎町2丁目2番2号 株 式会社奥村組内Front page continued (72) Inventor Minoru Minoru 2-10-9 Izumi, Suginami-ku, Tokyo (72) Inventor Mikio Takeuchi 2-2-2 Matsuzaki-cho, Abeno-ku, Osaka City Okumura Gumi (72) Invention Reisuke Mishima 2-2-2 Matsuzaki-cho, Abeno-ku, Osaka-shi Okumura-gumi, a stock company (72) Inventor Hiroshi Wada 2--2 Matsuzaki-cho, Abeno-ku, Osaka-shi Okumura-gumi (72) Inventor Hayashi We are located in Okumura group, 2-2-2, Matsuzaki-cho, Abeno-ku, Osaka

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 トンネル内に敷設している仮管の後端に
内筒を一体に連結し、この内筒の外周面に外径が上記仮
管よりも小径の円筒形型枠を摺動自在に被嵌し、該円筒
形型枠とトンネル掘削壁面との間の空隙部に硬化性材料
を注入したのち、円筒形型枠を前後又は周方向に往復動
させながら該硬化性材料を硬化させて円筒状硬化層を形
成し、この硬化層を仮管の前進に従ってトンネル掘削壁
面に連続的に施工することを特徴とするトンネル掘削壁
面の覆工方法。
1. An inner cylinder is integrally connected to a rear end of a temporary pipe laid in a tunnel, and a cylindrical form having an outer diameter smaller than that of the temporary pipe is slid on an outer peripheral surface of the inner cylinder. Freely fit and inject a curable material into the gap between the cylindrical form and the tunnel excavation wall surface, then cure the curable material while reciprocating the cylindrical form in the front-back or circumferential direction. A method for lining a tunnel excavation wall surface, characterized in that a cylindrical hardened layer is formed thereby, and the hardened layer is continuously applied to the tunnel excavation wall surface as the temporary pipe advances.
【請求項2】 円筒形型枠とトンネル掘削壁面との間の
空隙部に注入した硬化性材料の硬化完了毎に仮管を円筒
形型枠と共にトンネル方向に一定長、前進させることを
特徴とする請求項1記載のトンネル掘削壁面の覆工方
法。
2. A temporary tube is advanced together with the cylindrical formwork for a certain length in the tunnel direction each time the hardening of the curable material injected into the gap between the cylindrical formwork and the tunnel excavation wall surface is completed. The method for lining a tunnel excavation wall surface according to claim 1.
【請求項3】 円筒形型枠とトンネル掘削壁面との間の
空隙部に注入した硬化性材料の硬化速度に同調した速度
で仮管を円筒形型枠と一体的に前進させることを特徴と
する請求項1記載のトンネル掘削壁面の覆工方法。
3. The temporary tube is integrally advanced with the cylindrical form at a speed that is synchronized with the curing speed of the curable material injected into the space between the cylindrical form and the wall surface of the tunnel excavation. The method for lining a tunnel excavation wall surface according to claim 1.
【請求項4】 トンネル内に敷設している仮管の後端に
一定長さを有する内筒の前端を一体的に連結すると共に
この内筒に上記仮管よりも小径の円筒形型枠を摺動自在
に被嵌させ、さらに、トンネル掘削壁面と円筒形型枠と
の間の空隙部に硬化性材料を注入する配管を配設すると
共に仮管の後端部内に上記円筒形型枠を前後又は周方向
に摺動させるジャッキを配設してなることを特徴とする
トンネル掘削壁面の覆工装置。
4. A front end of an inner cylinder having a constant length is integrally connected to a rear end of a temporary pipe laid in a tunnel, and a cylindrical form having a diameter smaller than that of the temporary pipe is connected to the inner cylinder. It is slidably fitted, and furthermore, a pipe for injecting a curable material is arranged in the gap between the tunnel excavation wall surface and the cylindrical form, and the cylindrical form is placed in the rear end of the temporary pipe. A lining device for a tunnel excavation wall surface, comprising a jack that slides in the front-rear direction or the circumferential direction.
JP04348395A 1995-02-07 1995-02-07 Tunnel excavation wall lining method and apparatus Expired - Fee Related JP3507173B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP04348395A JP3507173B2 (en) 1995-02-07 1995-02-07 Tunnel excavation wall lining method and apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP04348395A JP3507173B2 (en) 1995-02-07 1995-02-07 Tunnel excavation wall lining method and apparatus

Publications (2)

Publication Number Publication Date
JPH08210090A true JPH08210090A (en) 1996-08-13
JP3507173B2 JP3507173B2 (en) 2004-03-15

Family

ID=12664979

Family Applications (1)

Application Number Title Priority Date Filing Date
JP04348395A Expired - Fee Related JP3507173B2 (en) 1995-02-07 1995-02-07 Tunnel excavation wall lining method and apparatus

Country Status (1)

Country Link
JP (1) JP3507173B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104612696A (en) * 2014-11-28 2015-05-13 中铁四局集团有限公司 Construction method for underground excavated large-section subway station to pass through viaduct in fine sand layer based on pioneer heading-column method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104612696A (en) * 2014-11-28 2015-05-13 中铁四局集团有限公司 Construction method for underground excavated large-section subway station to pass through viaduct in fine sand layer based on pioneer heading-column method

Also Published As

Publication number Publication date
JP3507173B2 (en) 2004-03-15

Similar Documents

Publication Publication Date Title
JP3507173B2 (en) Tunnel excavation wall lining method and apparatus
JP4847881B2 (en) Existing pipe repair method and existing pipe repair system used for the method
JP3507174B2 (en) Tunnel excavation wall lining method and apparatus
JP2000027172A (en) Bearing ground improvement method for existing structure
JP2525847B2 (en) Old pipe rehabilitation method
CN212744003U (en) Hydraulic mould and automatic molding system for traction connection of cement pipeline
JP3542657B2 (en) Lining equipment used for tunnel lining method
JPH05287726A (en) Installation method for line for drainage
JP2910797B2 (en) Tunnel lining device and lining method
JP3942656B2 (en) Lubricant and tubular body propulsion burying method using the lubricant
JP3247788B2 (en) Construction method of underground piping
US20240052743A1 (en) Automated method and processing train for lining tunnels
JP4249873B2 (en) Removal method of existing pipeline
JPH02132295A (en) Constructing method for tunnel lining work
CN111637278A (en) Hydraulic mould and automatic molding system for traction connection of cement pipeline
JP3299903B2 (en) Tunnel lining structure and tunnel construction method
JPH041367A (en) Crack impregnation method
JP2001303888A (en) Leading pipe used for pipe jacking method and molding method therefor
JP2676691B2 (en) Construction method of shield and lining using shield
JPH1181294A (en) Ground improvement method
JPH10184285A (en) End form in shield machine
JPH07247790A (en) Method of molding concrete pipe underground
JP2001200696A (en) Placing method for back-filling material
JPH05263586A (en) Injection method for lubricant and back-filler in a double pipe shield technique
JPH06257389A (en) Pouring method for back-filling material in propulsive construction method for double tube

Legal Events

Date Code Title Description
A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20031218

LAPS Cancellation because of no payment of annual fees