JPH0699939B2 - Equipment foundation construction method - Google Patents

Equipment foundation construction method

Info

Publication number
JPH0699939B2
JPH0699939B2 JP60261697A JP26169785A JPH0699939B2 JP H0699939 B2 JPH0699939 B2 JP H0699939B2 JP 60261697 A JP60261697 A JP 60261697A JP 26169785 A JP26169785 A JP 26169785A JP H0699939 B2 JPH0699939 B2 JP H0699939B2
Authority
JP
Japan
Prior art keywords
floor
equipment
foundation
work
setting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP60261697A
Other languages
Japanese (ja)
Other versions
JPS62121237A (en
Inventor
利幸 高橋
忠彦 仁科
Original Assignee
株式会社日立製作所
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社日立製作所 filed Critical 株式会社日立製作所
Priority to JP60261697A priority Critical patent/JPH0699939B2/en
Publication of JPS62121237A publication Critical patent/JPS62121237A/en
Publication of JPH0699939B2 publication Critical patent/JPH0699939B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】 〔発明の利用分野〕 本発明は、機器基礎建設方法に係り、特にモータや発電
機のような回転機の土台または制御室のように、床ピッ
ト(凹み)を設けてその中にケーブルを布設配線する盤
土台などのコンクリート基礎建設方法に関する。
Description: BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an equipment foundation, and more particularly, to provide a floor pit (recess) such as a base of a rotating machine such as a motor or a generator or a control room. The present invention relates to a concrete foundation construction method such as a board foundation for laying and wiring a cable therein.

〔発明の背景」 原子力発電所の中央制御室は、近年、建屋容積縮小化,
プラント全体配置の適性化のために、従来の制御建屋内
に設置する方式から、原子炉建屋内に設置する方式に変
わりつつある。さらに、原子炉建屋内に設置する場合の
中央制御室は、適正配置の観点から、上階に設置される
ことになる。従来は、中央制御室の建設工事を原子炉建
屋とは別に先行してできたのに対し、建設工事は、通
常、下階から始めるので、中央制御室が原子炉建屋内に
設置される場合、原子炉建屋の建設工事がある程度進捗
してからでないと、中央制御室関係の工事が開始できな
い。一方、据付を完了した設備はテストに入るが、この
時点で中央制御室は完成していなければならない。すな
わち、中央制御室工事は、全体工事工程のクリティカル
パスになってきている。
[Background of the Invention] In recent years, the central control room of a nuclear power plant has been reduced in building volume,
In order to optimize the layout of the entire plant, the conventional method of installing in the control building is changing to the method of installing in the reactor building. Further, the central control room when installed in the reactor building will be installed on the upper floor from the viewpoint of proper layout. In the past, the construction work of the main control room was done separately from the reactor building, whereas the construction work usually starts from the lower floor, so when the main control room is installed inside the reactor building , The work related to the main control room cannot be started until the construction of the reactor building has progressed to some extent. On the other hand, the equipment that has been installed will be tested, but the central control room must be completed at this point. That is, the main control room construction is becoming a critical path for the entire construction process.

同様な理由により、中央制御室から現場機器までのケー
ブル工事もクリティカルパスになってきているが、これ
に対しては、例えば、特開技報81−3228号にあるよう
に、集合端子盤を設置し、中央制御室内の配線を現場機
器と集合端子盤間のケーブル工事から分離して、後者の
先行工事を可能にしている。
For the same reason, the cable work from the central control room to the field equipment is becoming a critical path, but for this, for example, as described in JP-A-81-3228, It is installed and the wiring inside the central control room is separated from the cable work between the field equipment and the collective terminal board, enabling the latter precedent work.

一方、集合端子盤と中央制御室制御盤間の配線について
は、第6図に示すように、例えば集合端子盤11の基礎ブ
ロック4を配置し、床コンクリート面上でそれら基礎ブ
ロック4の間に形成された凹みを機器間の配線等のため
の床ピットとして利用し、この中にケーブルトレイ9を
設け、プレハブケーブル12を集合端子盤11の下部から立
ち上げ、ケーブル布設を合理化している。
On the other hand, regarding the wiring between the collective terminal board and the control panel of the central control room, as shown in FIG. 6, for example, the basic block 4 of the collective terminal board 11 is arranged, and between the basic blocks 4 on the floor concrete surface. The formed recess is used as a floor pit for wiring between devices, a cable tray 9 is provided therein, and a prefabricated cable 12 is raised from the lower part of the collective terminal board 11 to rationalize cable laying.

中央制御室の基礎工事に関しては、さらに例えば、特開
昭52−21592号にあるように、コンクリート柱とI字鋼
を組み合わせて行う方法がある。この方法では、制御盤
の基礎となるコンクリート柱の設定は、床コンクリート
打設後に、一つ一つ型枠を組んでなされていた。コンク
リート柱は中央制御室全体で約100個にものぼるため、
制御盤の基礎の位置および高さの調整やケーブルトレイ
の布設を含め、中央制御室基礎工事が、工程上のクリテ
ィカルパスになってきており、その工数低減および工期
短縮が重要な課題となってきている。
As for the foundation work of the main control room, there is a method of combining concrete columns and I-shaped steel, as disclosed in JP-A-52-21592. In this method, the setting of the concrete columns that form the basis of the control panel was done by assembling the formwork one by one after placing the floor concrete. Since there are approximately 100 concrete columns in the central control room,
Central control room foundation work, including adjusting the position and height of the control panel foundation and laying cable trays, is becoming a critical path in the process, and reducing the number of man-hours and shortening the construction period are important issues. ing.

また、モータや発電機等の回転機器の基礎土台は、耐震
動性および強度の点から、コンクリート土台が用いられ
ているが、従来の床コンクリート打設後に土台を作成す
る方法では、基礎ブロックを一つ一つ形成するため手間
がかかり、養生と仕上げを含め、コンクリート床引き渡
し後、基礎完成まで約2ヶ月を要し、機器に接続される
配管の工事を遅らせる原因になっている。
In addition, concrete foundations are used for the foundations of rotating equipment such as motors and generators in terms of earthquake resistance and strength, but in the conventional method of creating foundations after placing concrete, the foundation blocks are It takes time to form each one, and it takes about two months from completion of the concrete floor, including curing and finishing, to the completion of the foundation, which is a cause of delaying the construction of the piping connected to the equipment.

〔発明の目的〕[Object of the Invention]

本発明の目的は、機器を設置する複数の基礎を床面から
突出させて配置し、床面上で前記複数の基礎間に形成さ
れた凹みを機器間の配線等のための床ピットとして利用
する機器基礎を建設する方法において、機器基礎のコン
クリート工事を短期間で完了できる機器基礎建設方法を
提供することである。
An object of the present invention is to arrange a plurality of foundations on which equipment is installed so as to project from a floor surface, and use a recess formed between the plurality of foundations on the floor surface as a floor pit for wiring between equipments. In the method of constructing an equipment base, the concrete foundation of the equipment foundation is provided in a short time.

〔発明の概要〕[Outline of Invention]

本発明は、上記目的を達成するために、機器を設置する
複数の基礎を床面から突出させて配置し床面上で前記複
数の基礎間に形成された凹みを機器間の配線等のための
床ピットとして利用する機器基礎を建設する方法におい
て、 A.床下部の上に基礎設定用架台を配置する作業と、 B.床配筋をする作業と、 C.予め作成した複数の機器基礎ブロックを前記床ピット
に必要な凹みを確保しながら前記架台上に設定する作業
と、 D.前記A,B,Cの作業終了後に床コンクリートを打設する
作業と からなる機器基礎建設方法を提案するものである。
In order to achieve the above object, the present invention arranges a plurality of foundations on which equipment is installed so as to project from a floor surface, and forms a recess formed between the plurality of foundations on the floor surface for wiring between equipments or the like. In the method of constructing the equipment foundation to be used as the floor pit of A, the work of arranging the foundation setting frame on the lower floor of the floor, B. the work of arranging the floor, and C. the plurality of equipment foundations created in advance Proposal of equipment foundation construction method consisting of work of setting blocks on the pedestal while securing necessary recesses in the floor pit, and D. work of placing floor concrete after completion of the work of A, B, C To do.

前記複数の機器基礎ブロックのうちでいくつかの機器基
礎ブロックと設定用架台とを予め一体化し、上記A作業
とC作業とを同時に実行し、次に上記B作業を実行する
ことができる。
It is possible to preliminarily integrate some of the plurality of device basic blocks with the setting gantry, perform the work A and the work C at the same time, and then perform the work B.

また、上記C作業時に、前記複数の機器基礎ブロックの
うちでいくつかの機器基礎ブロックをビームにより予め
一体化し、同時に搬入し設定することも可能である。
Further, at the time of the above-mentioned C work, it is possible to preliminarily integrate some equipment basic blocks among the plurality of equipment basic blocks by a beam and carry in and set them at the same time.

本発明の機器基礎建設方法においては、現場工事と並行
して複数の機器基礎ブロックを作成しておき、床コンク
リート打設前に、設定用架台に前記複数の機器基礎ブロ
ックを載せて位置を設定し、その後に、床コンクリート
を打ち、それら複数の機器基礎ブロック間に機器間の配
線等のための床ピットの凹みを形成するので、現場での
コンクリート打設が1回で済み、床ピットの凹みを含め
た基礎工事の工期が大幅に短縮される。
In the equipment foundation construction method of the present invention, a plurality of equipment foundation blocks are created in parallel with the on-site construction, and the plurality of equipment foundation blocks are placed on the setting frame before the floor concrete is placed to set the position. After that, the floor concrete is struck and the recess of the floor pit for wiring between the equipment is formed between the plurality of equipment foundation blocks, so it is only necessary to place the concrete on site once. The construction period for foundation work, including dents, will be greatly shortened.

〔実施例〕〔Example〕

以下、実施例に基づき、本発明を詳細に説明する。 Hereinafter, the present invention will be described in detail based on examples.

第1図は、本発明による機器基礎建設方法の一実施例を
示すフロー図である。
FIG. 1 is a flow chart showing an embodiment of the equipment foundation construction method according to the present invention.

ステップAにおいて、床下部1が建設された時点で、基
礎設定用架台あるいは枠2を搬入し、設置する。本架台
は、機器基礎の高さおよび位置を設定するためのもので
ある。
In step A, when the lower floor 1 is constructed, the foundation setting frame or the frame 2 is loaded and installed. This mount is for setting the height and position of the equipment foundation.

ステップBにおいては、床配筋3a,3bを施工する。In step B, floor reinforcement 3a, 3b is constructed.

ステップCでは、予め作成した機器基礎ブロック4を搬
入し、設定用架台上に設置する。
In Step C, the device basic block 4 created in advance is loaded and installed on the setting stand.

最後にステップDにおいて、床コンクリートを打設し、
基礎工事を完了させる。
Finally, in step D, floor concrete is poured,
Complete the foundation work.

なお、ステップBとCとを逆にしても、本発明の利点が
変わらないのは、明らかである。
Obviously, reversing steps B and C does not change the advantages of the present invention.

第2図は機器基礎ブロック4の一例を示すものである。
第2図(a)はブロック外観図、(b)はブロックの断
面図である。基礎ブロック4は、配筋22が下部にはみ出
しており、床コンクリート5と結合する構造となってい
る。ここでは、直線状のものを例示してあるが、アング
ル状であってもよいことはもちろんである。また、機器
を固定するためのボルト21が埋め込まれており、その一
部がブロック上部につき出ている。図示しない機器とブ
ロック4とはボルト21により結合される。
FIG. 2 shows an example of the device basic block 4.
FIG. 2A is an external view of the block, and FIG. 2B is a sectional view of the block. The base block 4 has a structure in which the reinforcing bars 22 project to the lower part and are connected to the floor concrete 5. Although the linear shape is illustrated here, it is needless to say that the shape may be an angle. Further, a bolt 21 for fixing the device is embedded, and a part of the bolt 21 sticks out to the upper part of the block. A device (not shown) and the block 4 are connected by a bolt 21.

第3図は機器基礎ブロック4の他の例である。第3図に
おいて、ブロック上部には埋込金物31があり、機器とは
溶接により結合される。
FIG. 3 shows another example of the device basic block 4. In FIG. 3, there is an embedded metal item 31 at the upper part of the block, which is connected to the equipment by welding.

第1図の例は、1つの基礎ブロック4について示したも
のであるが、基礎が複数である場合は、複数の基礎ブロ
ック4を一体化して搬入し設定することもできる。第4
図は、一体化した基礎ブロックの外観を示す一例であ
る。図において、基礎ブロック4a,4b,4c,4d,4e,4fは、
埋込金物31a,31b,31c,31d,31e,31fにおいてビーム41と
溶接で結合されている。
The example of FIG. 1 shows one basic block 4, but when there are a plurality of basic blocks, a plurality of basic blocks 4 can be integrally carried in and set. Fourth
The figure is an example showing the appearance of the integrated basic block. In the figure, basic blocks 4a, 4b, 4c, 4d, 4e, 4f are
The embedded hardware 31a, 31b, 31c, 31d, 31e, 31f is welded to the beam 41.

基礎ブロック搬入時には、これらを一体化したままクレ
ーン42で吊り下げて搬入し、設定用架台2の上に設定す
る。この場合には、床コンクリート打設後ビーム41を取
りはずし、基礎工事を完成させる。
When the basic block is carried in, they are suspended and carried in by the crane 42 while being integrated, and set on the setting base 2. In this case, the beam 41 is removed after placing the floor concrete, and the foundation work is completed.

このようにすると、基礎ブロック間の寸法を高精度に維
持できる。第4図の例は、6個のブロックを一体化して
いるが、ブロックの数はいくつであっても、同様に搬入
し、設定できる。
By doing so, the dimension between the basic blocks can be maintained with high accuracy. In the example of FIG. 4, six blocks are integrated, but any number of blocks can be similarly loaded and set.

なお、第3図の埋込金物を備えた基礎ブロックではな
く、第2図のボルトを用いる基礎ブロックについて、第
4図のようにビームで一体化し、搬入し設定する場合、
ボルト21をビームへの取り付けにも兼用できることはい
うまでもない。
When the basic block using the bolts of FIG. 2 is integrated with the beam as shown in FIG. 4 and is carried in and set, instead of the basic block having the embedded metal of FIG. 3,
It goes without saying that the bolt 21 can also be used for attaching to the beam.

以上は、設定用架台設定後、基礎ブロックを搬入し設定
する例であるが、第5図のように、基礎ブロック4a,4b
を設定用架台2と一体化させておき、クレーン42で搬入
し設定する方法もある。この場合には、搬入も一回で済
む利点がある。
The above is an example of loading and setting the basic block after setting the setting base. As shown in FIG. 5, the basic blocks 4a and 4b are set.
Alternatively, there is also a method in which is integrated with the setting base 2 and carried in by the crane 42 and set. In this case, there is an advantage that loading can be done only once.

〔発明の効果〕 本発明の方法によれば、次の効果が得られる。[Effects of the Invention] According to the method of the present invention, the following effects can be obtained.

1.機器基礎建設現場における機器基礎土台の配筋施工、
型枠施工および成形や表面仕上げ等の作業が不要とな
り、これらに替わる基礎ブロック作成を現場建設工事と
並行して行うことが可能となるため、現場作成工数を大
幅に低減し、工期を短縮できる。特に、ブロック位置お
よびその高さの設定および調整は、従来最も工数を必要
としていた部分であるが、本発明の基礎ブロック一体化
設定方法によれば、建設現場でのこうした調整作業を大
幅に減らすことができる。
1. Equipment foundation construction of the equipment foundation foundation at the construction site,
It eliminates the need for work such as formwork construction, molding, and surface finishing, and it is possible to create basic blocks to replace them in parallel with on-site construction work, thus significantly reducing the number of on-site production steps and shortening the construction period. . In particular, the setting and adjustment of the block position and its height are the parts that required the most man-hours in the past, but the basic block integrated setting method of the present invention greatly reduces such adjustment work at the construction site. be able to.

2.基礎ブロックやトレイブロックおよび基礎設定用架台
の作成あるいはそれらの一体化製作は、工場で実施でき
るため、加工や溶接が容易になり、これらの製作コスト
低減および品質向上が可能となる。特に、その数が多い
基礎ブロックは標準化することにより、大量生産が可能
となり、大幅なコストダウンが図れる。
2. Since the basic blocks, tray blocks, and the foundation setting cradle can be created or integrally manufactured in the factory, processing and welding are facilitated, and the manufacturing cost and quality of these can be reduced. In particular, standardization of a large number of basic blocks enables mass production, resulting in a significant cost reduction.

【図面の簡単な説明】[Brief description of drawings]

第1図は本発明による機器基礎建設方法の施工手順の一
例を示すフロー図、第2図は機器を基礎土台にボルトで
固定する方式のプレキャスト基礎ブロックを示す図、第
3図は同じく埋込金物で固定する方式の基礎ブロックを
示す図、第4図は複数のプレキャスト基礎ブロックをビ
ームで一体化し、クレーンで吊り下げて設定用架台に載
せる作業状況を示す図、第5図は基礎ブロックと設定用
架台とを一体化し、クレーンで搬入する作業状況を示す
図、第6図は集合端子盤周りの配線の様子を示す図であ
る。 1…床下部、2…基礎設定用架台、3…床配筋、 4…プレキャスト基礎ブロック、5…床コンクリート、 9…ケーブルトレイ、11…集合端子盤、 12…プレハブケーブル、21…機器固定用ボルト、 22…基礎ブロック配筋、31…埋込金物、 41…ビーム、42…クレーン。
FIG. 1 is a flow chart showing an example of a construction procedure of an equipment foundation construction method according to the present invention, FIG. 2 is a diagram showing a precast foundation block of a method of fixing equipment to a foundation base with bolts, and FIG. 3 is also embedded. Fig. 4 is a diagram showing the basic block of the method of fixing with hardware, Fig. 4 is a diagram showing the work situation in which a plurality of precast basic blocks are integrated with a beam, suspended by a crane and placed on a setting stand, Fig. 5 shows the basic block FIG. 6 is a diagram showing a work situation in which the setting platform is integrated and carried in by a crane, and FIG. 6 is a diagram showing a state of wiring around the collective terminal board. 1 ... bottom floor, 2 ... base setting frame, 3 ... floor bar arrangement, 4 ... precast foundation block, 5 ... floor concrete, 9 ... cable tray, 11 ... collection terminal board, 12 ... prefab cable, 21 ... for fixing equipment Bolts, 22 ... Foundation block reinforcement, 31 ... Embedded parts, 41 ... Beams, 42 ... Cranes.

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】機器を設置する複数の基礎を床面から突出
させて配置し前記床面上で前記複数の基礎間に形成され
た凹みを前記機器間の配線等のための床ピットとして利
用する機器基礎を建設する方法において、 A.床下部の上に基礎設定用架台を配置する作業と、 B.床配筋をする作業と、 C.予め作成した複数の機器基礎ブロックを前記床ピット
に必要な凹みを確保しながら前記架台上に設定する作業
と、 D.前記A,B,Cの作業終了後に床コンクリートを打設する
作業と からなることを特徴とする機器基礎建設方法。
1. A plurality of foundations on which equipment is installed are arranged so as to project from a floor surface, and a recess formed between the plurality of foundations on the floor surface is used as a floor pit for wiring between the equipments. In the method of constructing the equipment foundation, the steps of A. placing the foundation setting pedestal on the lower floor, B. arranging the floor, and C. placing a plurality of prefabricated equipment foundation blocks in the floor pit A method for constructing a foundation for equipment, comprising the steps of setting on the pedestal while ensuring the necessary recesses in D. and D. the work of placing floor concrete after the work of A, B, and C.
【請求項2】特許請求の範囲第1項において、 前記複数の機器基礎ブロックのうちでいくつかの機器基
礎ブロックと設定用架台とを予め一体化し、上記A作業
とC作業とを同時に実行し、次に上記B作業を実行する
ことを特徴とする機器基礎建設方法。
2. The device according to claim 1, wherein some of the plurality of device basic blocks are integrated with a setting base in advance, and the work A and the work C are simultaneously performed. Then, a method for constructing an equipment foundation, which is characterized in that the work B is then performed.
【請求項3】特許請求の範囲第1項において、 上記C作業時に、前記複数の機器基礎ブロックのうちで
いくつかの機器基礎ブロックをビームにより予め一体化
し、同時に搬入し設定することを特徴とする機器基礎建
設方法。
3. The apparatus according to claim 1, wherein during the C work, some of the plurality of equipment basic blocks are preliminarily integrated by a beam and are simultaneously loaded and set. Equipment foundation construction method.
JP60261697A 1985-11-21 1985-11-21 Equipment foundation construction method Expired - Lifetime JPH0699939B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP60261697A JPH0699939B2 (en) 1985-11-21 1985-11-21 Equipment foundation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP60261697A JPH0699939B2 (en) 1985-11-21 1985-11-21 Equipment foundation construction method

Publications (2)

Publication Number Publication Date
JPS62121237A JPS62121237A (en) 1987-06-02
JPH0699939B2 true JPH0699939B2 (en) 1994-12-12

Family

ID=17365454

Family Applications (1)

Application Number Title Priority Date Filing Date
JP60261697A Expired - Lifetime JPH0699939B2 (en) 1985-11-21 1985-11-21 Equipment foundation construction method

Country Status (1)

Country Link
JP (1) JPH0699939B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5960520B2 (en) * 2012-06-22 2016-08-02 鹿島建設株式会社 Multifunctional rooftop foundation
JP2016199957A (en) * 2015-04-14 2016-12-01 戸田建設株式会社 Floor preceding method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0336967B2 (en) * 1985-09-20 1991-06-04 Kajima Corp

Also Published As

Publication number Publication date
JPS62121237A (en) 1987-06-02

Similar Documents

Publication Publication Date Title
US4023315A (en) Prefabricated buildings
US4434600A (en) Method for fixing the ends of concrete columns in concrete bases and device for carrying out said method
JPH0699939B2 (en) Equipment foundation construction method
CN206599919U (en) A kind of integral prefabricated reinforcing bar web frame of shear wall
JPH10311049A (en) Work executing method for turbine frame of steel plate concrete and locating jig for burying metal piece
JP3015415B2 (en) Nuclear power plant construction method
JP4358408B2 (en) Power generation facility mount and method for manufacturing power generation facility mount
JPH0784763B2 (en) Squirrel-framed formwork for the steel column support in the building
US5748690A (en) Construction method of nuclear reactor reinforced concrete containment vessel and diaphragm floor structure of nuclear reactor reinforced concrete containment vessel
JP3187618B2 (en) How to assemble beam reinforcement
JPH09296565A (en) Precast concrete column, its manufacture, and execution method
JP2002295203A (en) Foundation pedestal for turbine generator and the construction method
JP2614000B2 (en) Basics of steel frame
JPH0743490A (en) Constructing method for reactor container
JP2990216B2 (en) Construction method of reinforced concrete building
JPH108725A (en) Constructing method for building frame
JP2002194892A (en) Construction method of building
JP2513376B2 (en) How to build a building
CN112282063A (en) Site intelligent construction process of complex space grid structure
JP2000273946A (en) Method for constructing reinforced concrete structure
WO1983002298A1 (en) Improved method for erecting reinforced concrete building structures
JP2000192664A (en) Method for construction of building
JP3205467B2 (en) Translational construction of the building and the equipment stand, and advance loading of equipment into the building
JP2520037B2 (en) How to build a seismic isolated building
JPH05179694A (en) Construction method of building