JPH0650084A - Method for constructing multistage pipe beam - Google Patents

Method for constructing multistage pipe beam

Info

Publication number
JPH0650084A
JPH0650084A JP19128292A JP19128292A JPH0650084A JP H0650084 A JPH0650084 A JP H0650084A JP 19128292 A JP19128292 A JP 19128292A JP 19128292 A JP19128292 A JP 19128292A JP H0650084 A JPH0650084 A JP H0650084A
Authority
JP
Japan
Prior art keywords
pipe beam
work
stage
excavated
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP19128292A
Other languages
Japanese (ja)
Inventor
Yoshio Kusakabe
好男 日下部
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP19128292A priority Critical patent/JPH0650084A/en
Publication of JPH0650084A publication Critical patent/JPH0650084A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To enable excavation of even a long tunnel extending several hundred meters. CONSTITUTION:A first-stage pipe beam is constructed 1 and, as timbering is built into the pipe beam, excavation is carried out in the forward direction. A second-stage pipe beam 2 is constructed in front of the inside of the pipe beam 1 with an overlap at their end portions, and the inside of the pipe beam 2 is similarly excavated. Similar work is repeated as needed. Therefore, even such a long tunnel that cannot be constructed by pipe-beam construction method can safely, promptly and economically be excavated.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、多段にパイプビーム工
を施して長いトンネルを掘削する工法に関するものであ
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of drilling a long tunnel by performing multi-stage pipe beam work.

【0002】[0002]

【従来技術】地上に住居や道路等が存在する場所で土か
ぶりが薄いトンネルを掘削する場合の工法として従来知
られているパイプビーム工法は、掘削すべきトンネルの
断面の外縁に沿って鋼管を並らべて押し込んで形成した
パイプビーム工の内部を、支保工を建て込みながら順次
前方に向かって掘削してゆくものであるが、大口径の鋼
管を正確に所定の位置に押し込むことができる長さの限
度は数十メートル程度であるため、従来は数百メートル
の長さのトンネルをパイプビーム工法で施工することは
できないものとされていた。
2. Description of the Related Art The pipe beam method, which is conventionally known as a method for excavating a tunnel with a thin soil cover in a place where there are houses, roads, etc. on the ground, uses a steel pipe along the outer edge of the cross section of the tunnel to be excavated. The inside of the pipe beam work that is formed by pushing them side by side is sequentially excavated forward while building the support work, but it is possible to push a large-diameter steel pipe into a predetermined position accurately. Since the limit of length is about several tens of meters, it was conventionally considered that a tunnel with a length of several hundred meters could not be constructed by the pipe beam method.

【0003】[0003]

【発明の目的】本発明の目的は、数百メートル程度の長
いトンネルでも掘削が可能な多段式のパイプビーム工法
を提供することにある。
SUMMARY OF THE INVENTION It is an object of the present invention to provide a multi-stage pipe beam construction method capable of excavating a long tunnel of several hundred meters.

【0004】[0004]

【発明の構成】本発明の多段式パイプビーム工法の構成
上の特徴は、トンネルの端となる所から第1段のパイプ
ビーム工を施して、その内部を、支保工を建て込みなが
ら順次前方に向かって掘削し、次いで第1段のパイプビ
ーム工の内側前方に、端部が重なるようにして第2段の
パイプビーム工を施して、同様にその内部を掘削し、更
に必要に応じて順次同様の作業を繰り返す点にある。
The multi-stage pipe beam construction method of the present invention is characterized in that the first stage pipe beam construction is performed from the end of the tunnel, and the inside of the pipe beam construction is carried forward in sequence while the support work is being built. To the inside of the first-stage pipe beam work, and then the second-stage pipe beam work is performed with the ends overlapping, and the inside is similarly drilled. The point is to repeat the same work in sequence.

【0005】[0005]

【図面による発明の説明】図面は、トンネルの両端の地
点A,Bからそれぞれ本発明の工法により掘削を進め
て、地点A,B間の中間部で連通させ、このようにして
掘削した長いトンネル内に地下道Wを構築する施工例を
示しており、図中、Fは地表面である。
[Explanation of the Invention According to the Drawing] The drawing shows a long tunnel excavated from points A and B at both ends of the tunnel by the construction method of the present invention so as to communicate with each other at an intermediate portion between points A and B, and thus excavated. An example of construction for constructing an underpass W is shown inside, and in the figure, F is the ground surface.

【0006】先ず、地点A,Bに立て坑を掘り、この立
て坑からトンネルを掘削する方向に水平に鋼管を順次接
続しながら押し込んで、第1段のパイプビーム工1を形
成し、その内部を、支保工Sを建て込みながら順次、前
方に向かって掘削するが、掘削の方式は任意であり、例
えば、トンネルの上部を先行して掘削するようにしても
よい。
First, vertical shafts are dug at points A and B, and steel pipes are sequentially connected horizontally in the vertical direction in which tunnels are to be excavated from the vertical shafts to form the first-stage pipe beam work 1, and the inside thereof is formed. Are sequentially excavated forward while building the support S, but the excavation method is arbitrary, and for example, the upper part of the tunnel may be excavated first.

【0007】掘削がパイプビーム工1の先端近くまで進
んだ段階で、パイプビーム工1の内側前方に第2段のパ
イプビーム工2を、その後端部がパイプビーム工1の前
端部と或る程度重なるようにして形成する。
At the stage where the excavation has proceeded to near the tip of the pipe beam work 1, a second stage pipe beam work 2 is provided inside the pipe beam work 1, and its rear end is the front end of the pipe beam work 1. They are formed so that they overlap each other.

【0008】そして、パイプビーム工2の内部もパイプ
ビーム工1の内部と同様に掘削してトンネルを前進さ
せ、次いで、パイプビーム工2の内側前方に第3段のパ
イプビーム工3を施し、その内部も同様に掘削し、最後
に、両側のパイプビーム工3の内側にそれぞれ端部が重
なるようにして第4段のパイプビーム工4を施し、その
内部を掘削して、両側から掘削してきたトンネルを連通
させる。
Then, the inside of the pipe beam work 2 is excavated in the same manner as the inside of the pipe beam work 1 to advance the tunnel, and then the pipe beam work 3 of the third stage is performed in front of the inside of the pipe beam work 2, The inside is also excavated in the same way, and finally, the pipe beam work 4 of the fourth stage is performed so that the ends overlap with the insides of the pipe beam work 3 on both sides. Open the tunnel.

【0009】なお、本発明の工法で掘削されるトンネル
の断面は施されるパイプビーム工の段数に応じて次第に
小さくなるから、トンネルの長さが特に長い場合は、図
示の施工例のようにトンネルの両端から掘削するのが有
利である。
Since the cross section of the tunnel excavated by the method of the present invention becomes gradually smaller depending on the number of steps of the pipe beam construction to be performed, when the length of the tunnel is particularly long, as in the illustrated construction example. It is advantageous to drill from both ends of the tunnel.

【0010】[0010]

【発明の効果】本発明の工法は以上のようなものである
から、従来、パイプビーム工法では施工が不可能とされ
ていた長いトンネルでも、パイプビーム工を何段も重ね
ることにより、比較的安全かつ迅速に、しかも経済的に
施工することができる。
EFFECTS OF THE INVENTION Since the method of the present invention is as described above, even in a long tunnel which was conventionally impossible to be constructed by the pipe beam method, it is possible to obtain a comparative It can be constructed safely, quickly, and economically.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明による施工例の全体的説明図である。FIG. 1 is an overall explanatory view of a construction example according to the present invention.

【図2】図1のX−X線断面図である。FIG. 2 is a sectional view taken along line XX of FIG.

【図3】図1のY−Y線断面図である。3 is a cross-sectional view taken along line YY of FIG.

【符号の説明】[Explanation of symbols]

A,B:地点、W:地下道、F:地表面、S:支保工、
1,2,3,4:パイプビーム工。
A, B: Point, W: Underpass, F: Ground surface, S: Support work,
1, 2, 3, 4: Pipe beam work.

─────────────────────────────────────────────────────
─────────────────────────────────────────────────── ───

【手続補正書】[Procedure amendment]

【提出日】平成5年6月21日[Submission date] June 21, 1993

【手続補正1】[Procedure Amendment 1]

【補正対象書類名】図面[Document name to be corrected] Drawing

【補正対象項目名】図1[Name of item to be corrected] Figure 1

【補正方法】変更[Correction method] Change

【補正内容】[Correction content]

【図1】 [Figure 1]

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 トンネルの端となる所から第1段のパイ
プビーム工を施して、その内部を、支保工を建て込みな
がら順次前方に向かって掘削し、次いで第1段のパイプ
ビーム工の内側前方に、端部が重なるようにして第2段
のパイプビーム工を施して、同様にその内部を掘削し、
更に必要に応じて順次同様の作業を繰り返すことを特徴
とする多段式パイプビーム工法。
1. A first stage pipe beam work is performed from the end of the tunnel, and the inside is sequentially excavated forward while building a support work, and then the first stage pipe beam work is performed. The pipe beam work of the second stage is applied to the inside front so that the ends overlap, and the inside is similarly excavated,
Furthermore, the multi-stage pipe beam construction method is characterized in that the same work is repeated as needed.
JP19128292A 1992-06-09 1992-06-09 Method for constructing multistage pipe beam Pending JPH0650084A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP19128292A JPH0650084A (en) 1992-06-09 1992-06-09 Method for constructing multistage pipe beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP19128292A JPH0650084A (en) 1992-06-09 1992-06-09 Method for constructing multistage pipe beam

Publications (1)

Publication Number Publication Date
JPH0650084A true JPH0650084A (en) 1994-02-22

Family

ID=16271970

Family Applications (1)

Application Number Title Priority Date Filing Date
JP19128292A Pending JPH0650084A (en) 1992-06-09 1992-06-09 Method for constructing multistage pipe beam

Country Status (1)

Country Link
JP (1) JPH0650084A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004278102A (en) * 2003-03-14 2004-10-07 Taisei Corp Structure of underground passage and its construction method
JP2006249735A (en) * 2005-03-09 2006-09-21 Nishimatsu Constr Co Ltd Construction method of crossing underground structure and crossing underground structure

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62284892A (en) * 1986-05-31 1987-12-10 佐藤工業株式会社 Method of reinforcing circular pipe
JPH02112595A (en) * 1988-10-21 1990-04-25 Fujita Corp Execution device for reinforcing tunnel working-face-front bedrock

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62284892A (en) * 1986-05-31 1987-12-10 佐藤工業株式会社 Method of reinforcing circular pipe
JPH02112595A (en) * 1988-10-21 1990-04-25 Fujita Corp Execution device for reinforcing tunnel working-face-front bedrock

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004278102A (en) * 2003-03-14 2004-10-07 Taisei Corp Structure of underground passage and its construction method
JP2006249735A (en) * 2005-03-09 2006-09-21 Nishimatsu Constr Co Ltd Construction method of crossing underground structure and crossing underground structure

Similar Documents

Publication Publication Date Title
JP2008121356A (en) Boring machine and boring device using the same
JPH0650084A (en) Method for constructing multistage pipe beam
KR100781357B1 (en) It establishes the tunnel formation tunnel structure the maine pipe construction method
JP2587312B2 (en) Underground structure installation method
JPH08170485A (en) Blasting construction method
JP3450172B2 (en) Tunnel support structure
JP2019190031A (en) Advancing method of open shield machine
JP5158631B2 (en) Construction method of tunnel junction
JP3447116B2 (en) Double-body shield excavator and its simultaneous excavation method.
JPS5988598A (en) Widening of underground construction
JP6620122B2 (en) Direction correction mechanism used for blade edge propulsion method
JPH06313396A (en) Constructing method for large-diameter tunnel
JPH0462299A (en) Larger section tunnel and construction method thereof
JPH04327694A (en) Curve propulsive timbering method and curve propulsive machine
KR20230067921A (en) Construction method for large-section slab formation using lead pipe propulsion set and press-fit steel pipe set and construction method for non-interlaced large-section underground space structure
JPH04194295A (en) Method for building underground structure with movable timbering
JP3253909B2 (en) Tunnel support structure and tunnel support method
JPS6131594A (en) Bypass tunnel construction method
JP2005042546A (en) Branch type propulsive excavator
KR20070045459A (en) It establishes the tunnel formation tunnel structure the maine pipe construction method
JPH08284437A (en) Method for demolishing land slide protection wall
JPS6362637B2 (en)
JPS58120995A (en) Method of construction of curve propulsion
JPH01284694A (en) Open blade drilling machine and its reaction supporting device
JPS6145038B2 (en)