JPH06173339A - Constructing method for joining section for column/beam - Google Patents
Constructing method for joining section for column/beamInfo
- Publication number
- JPH06173339A JPH06173339A JP33063192A JP33063192A JPH06173339A JP H06173339 A JPH06173339 A JP H06173339A JP 33063192 A JP33063192 A JP 33063192A JP 33063192 A JP33063192 A JP 33063192A JP H06173339 A JPH06173339 A JP H06173339A
- Authority
- JP
- Japan
- Prior art keywords
- joint
- concrete
- column
- supported
- pillar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000004567 concrete Substances 0.000 claims abstract description 23
- 239000011178 precast concrete Substances 0.000 claims abstract description 16
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 15
- 239000010959 steel Substances 0.000 claims abstract description 15
- 238000009415 formwork Methods 0.000 claims description 5
- 238000010276 construction Methods 0.000 abstract description 12
- 230000002787 reinforcement Effects 0.000 abstract description 4
- 210000001503 Joints Anatomy 0.000 description 3
- 230000003014 reinforcing Effects 0.000 description 3
- 239000007787 solid Substances 0.000 description 3
- 229920001875 Ebonite Polymers 0.000 description 2
- 239000003351 stiffener Substances 0.000 description 2
- 210000003205 Muscles Anatomy 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
Abstract
Description
【0001】[0001]
【産業上の利用分野】この発明はプレキャストコンクリ
ート製,もしくは鋼管コンクリート造の柱部材とプレキ
ャストコンクリート製の梁部材から接合部を構成する、
柱・梁接合部の施工方法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention forms a joint from a column member made of precast concrete or a steel tube concrete structure and a beam member made of precast concrete.
It relates to a method of constructing a pillar / beam joint.
【0002】[0002]
【従来技術及び発明が解決しようとする課題】プレキャ
ストコンクリート製,もしくは鋼管コンクリート造の柱
部材とプレキャストコンクリート製の梁部材とから架構
を構築する方法では柱部材をまず立設した後に梁部材を
吊り込み、接合部への配筋とコンクリートの打設によっ
て接合部が構成されるが、従来は梁部材を吊り込み後も
これを養生し、安定化するまでクレーンによって吊り下
げた状態で支持することになるため、この施工時の安定
性を確保することが難しく、また梁部材が不安定な状態
に長時間置かれるため接合部での作業に危険が伴うこと
に加え、クレーンの有効稼働率が低下することから、施
工の進捗の低下を招いている。2. Description of the Related Art In a method of constructing a frame from a column member made of precast concrete or steel pipe concrete and a beam member made of precast concrete, the column member is first erected and then the beam member is suspended. The joints are constructed by placing reinforcements and placing concrete into the joints, but in the past, the beam members were supported after being hung up and stabilized by a crane until they stabilize after being suspended. Therefore, it is difficult to secure the stability during this construction, and the beam members are placed in an unstable state for a long time, which poses a risk of work at the joints and the effective operating rate of the crane. Since it will decrease, the progress of construction will decrease.
【0003】この発明はクレーンを用いて梁部材を支持
する施工方法の実情を踏まえてなされたもので、上記問
題を解消する施工方法を新たに提案しようとするもので
ある。The present invention has been made in view of the actual situation of a construction method for supporting a beam member by using a crane, and is intended to newly propose a construction method for solving the above problems.
【0004】[0004]
【課題を解決するための手段】本発明では柱部材の外周
に架台を着脱自在に突設し、この架台に梁部材を仮支持
させることによりクレーンによる支持を不要にし、クレ
ーンを用いることによる不安定化とそれに伴う危険を回
避し、施工の進捗を図る。In the present invention, a pedestal is detachably provided on the outer periphery of a column member, and a beam member is temporarily supported on this pedestal to eliminate the need for support by a crane. Stabilize and avoid the risks associated with it, and work on the construction progress.
【0005】梁部材は柱部材の立設後に吊り込まれて架
台上に載置され、クレーンから切り離される。梁部材の
載置後、その主筋が接合部を貫通して配筋され、架台上
に接合部の梁型枠が組み立てられ、コンクリートの打設
によって接合部が構成される。The beam member is suspended after being erected on the column member, placed on the pedestal, and separated from the crane. After the beam member is placed, its main bar is pierced through the joint part, the beam form of the joint part is assembled on the frame, and the joint part is formed by placing concrete.
【0006】梁部材が架台上に載置され、これにそのま
ま支持されることによりクレーンから吊り下げられたま
ま支持されることによる安定性の確保が不要となり、不
安定化に伴う危険が回避される。またクレーンが梁部材
の載置後に切り離されることによりその稼働率が上昇
し、施工の進捗が図られる。Since the beam member is placed on the pedestal and is supported by the beam member as it is, it is not necessary to ensure the stability by being supported while being suspended from the crane, and the risk associated with instability is avoided. It In addition, since the crane is separated after the beam member is placed, the operating rate of the crane is increased, and the progress of construction is achieved.
【0007】[0007]
【実施例】以下本発明を一実施例を示す図面に基づいて
説明する。DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below with reference to the drawings showing an embodiment.
【0008】この発明は図1に示すようにプレキャスト
コンクリート製,もしくは鋼管コンクリート造の柱部材
1とプレキャストコンクリート製の梁部材2,2から、
梁部材2,2を柱部材1に突設される架台3に支持させ
た状態で柱・梁の接合部を施工する方法である。As shown in FIG. 1, the present invention comprises a pillar member 1 made of precast concrete or a steel pipe concrete structure and beam members 2 made of precast concrete.
This is a method of constructing a joint between a pillar and a beam while the beam members 2 and 2 are supported by a pedestal 3 projecting from the pillar member 1.
【0009】柱部材1はプレキャストコンクリート製の
場合は図4に示すように主筋11とフープ12を埋設した中
実,または中空断面形状に製作され、鋼管コンクリート
造の場合は図8に示すように鋼管13と予め充填される,
または後から充填されるコンクリート14とから構成され
る。図1〜図4に示すように接合部を柱部材1が貫通す
る場合、柱部材1,1は接合部を外した位置で互いに接
続され、梁部材2が貫通する場合は図5に示すように梁
部材2,2を挟んで設置され、接合部へのコンクリート
の打設によって接続される。When the pillar member 1 is made of precast concrete, as shown in FIG. 4, the pillar member 1 is made to have a solid or hollow cross section in which the main bar 11 and the hoop 12 are embedded, and in the case of a steel pipe concrete structure, as shown in FIG. Pre-filled with steel pipe 13,
Alternatively, it is composed of concrete 14 to be filled later. When the pillar member 1 penetrates the joint as shown in FIGS. 1 to 4, the pillar members 1 and 1 are connected to each other at the position where the joint is removed, and when the beam member 2 penetrates as shown in FIG. It is installed by sandwiching the beam members 2 and 2, and is connected by pouring concrete to the joint.
【0010】また接合部を柱部材1が貫通する場合、そ
の接合部位置の内部には図2〜図4に示すように梁部材
2の下端主筋21と上端主筋22と継手される連結鉄筋4が
貫通して配筋される。When the column member 1 penetrates the joint, the connecting rebar 4 which is joined to the lower end main bar 21 and the upper end main bar 22 of the beam member 2 is provided inside the position of the joint, as shown in FIGS. Is pierced and arranged.
【0011】梁部材2は下端主筋21とスターラップが埋
設されてU形や中実断面形状の、もしくは図示するよう
に更に上端主筋22が埋設されて中実断面形状のプレキャ
ストコンクリートで製作される。The beam member 2 is made of precast concrete having a U-shape or a solid cross-section with a lower end main bar 21 and a stirrup embedded therein, or a solid cross-section with a top main bar 22 further buried as shown in the figure. .
【0012】柱部材1が接合部を貫通する場合、下端主
筋21と上端主筋22はプレキャストコンクリートの端面か
ら柱部材1側へ突出し、梁部材2は図1,図2に示すよ
うに端面が柱部材1から距離を隔てて架設され、下端主
筋21と上端主筋22が柱部材1を貫通して配筋される連結
鉄筋4とカプラー5を用いたねじ継手によって互いに接
続される。カプラー5は図2に示すように下端主筋21と
上端主筋22の端部に予め取り付けられ、図3に示すよう
に梁部材2の設置後に回転させられて連結鉄筋4に接続
される。When the pillar member 1 penetrates the joint, the lower end main bar 21 and the upper end main bar 22 project from the end face of the precast concrete to the side of the pillar member 1, and the beam member 2 has the end face as shown in FIGS. 1 and 2. A lower end main bar 21 and an upper end main bar 22 are erected at a distance from the member 1 and are connected to each other by a threaded joint using a connecting reinforcing bar 4 and a coupler 5 which are arranged through the column member 1. The coupler 5 is attached in advance to the ends of the lower end main bar 21 and the upper end bar 22 as shown in FIG. 2, and is rotated after the beam member 2 is installed and connected to the connecting reinforcing bar 4 as shown in FIG.
【0013】梁部材2が接合部を貫通する場合は図5に
示すように接合部位置の下端主筋21と上端主筋22が露出
し、架台3上への設置によってそのまま接合部を貫通し
て配筋される。図6は梁部材2が貫通する場合の梁部材
2とその吊り込みの様子を示している。柱部材1が鋼管
コンクリート造の場合には梁部材2を下端主筋21とスタ
ーラップのみを埋設して製作しておくことにより上端主
筋22は梁部材2の設置後にスライドさせられて鋼管13を
貫通することによっても配筋される。When the beam member 2 penetrates the joint portion, the lower end main bar 21 and the upper end main bar 22 at the joint part are exposed as shown in FIG. Be streaked. FIG. 6 shows the beam member 2 and its suspended state when the beam member 2 penetrates. When the column member 1 is made of steel pipe concrete, the beam member 2 is manufactured by embedding only the lower end main bar 21 and the stirrup so that the upper main bar 22 is slid after the beam member 2 is installed and penetrates the steel pipe 13. It is also arranged by doing.
【0014】架台3は図1に示すように柱部材1の外周
の、梁部材2の下端面位置から着脱自在に突設され、梁
部材2の吊り込みから接合部の施工完了まで梁部材2を
仮支持する。架台3は図4に示すように2方向の梁部材
2と接合部のコンクリートを支持するに十分な面積を持
ち、適当な数の、L形や六角形状のユニット30に分割さ
れる。As shown in FIG. 1, the pedestal 3 is detachably provided on the outer periphery of the pillar member 1 from the lower end surface position of the beam member 2, and the beam member 2 is hung from the suspension of the beam member 2 to the completion of construction of the joint. Temporary support. As shown in FIG. 4, the pedestal 3 has an area sufficient to support the beam member 2 in two directions and the concrete of the joint, and is divided into an appropriate number of L-shaped or hexagonal units 30.
【0015】各ユニット30は柱部材1に外接する取付片
31が図3に示すように柱部材1に埋め込まれたナットに
ボルト6により接合される、または図5に示すように隣
接するユニット30,30の取付片31,31の両端にフランジ
32,32が形成され、フランジ32,32が互いにボルト6に
より接続されることにより、もしくは図7に示すように
鋼管13の外周にそのフランジの補強用に突設されたリン
グスチフナ7に直接ボルト6により接合されることによ
り柱部材1に対して着脱自在に突設される。柱部材1が
プレキャストコンクリート製の場合、取付片31の柱部材
1に接触する面には柱部材1の保護のために図5に示す
ように必要により硬質ゴム8が貼着される。架台3は接
合部へのコンクリート打設時の下型枠を兼ね、着脱自在
に柱部材1に突設されることにより接合部の施工後に取
り外され、転用される。Each unit 30 is a mounting piece circumscribing the pillar member 1.
31 is joined to the nut embedded in the pillar member 1 by the bolt 6 as shown in FIG. 3, or as shown in FIG. 5, flanges are provided at both ends of the attachment pieces 31, 31 of the adjacent units 30, 30.
32, 32 are formed, and the flanges 32, 32 are connected to each other by bolts 6, or as shown in FIG. 7, bolts are directly attached to the ring stiffener 7 projecting on the outer circumference of the steel pipe 13 for reinforcement of the flanges. By being joined by 6, the pillar member 1 is detachably provided on the pillar member 1. When the pillar member 1 is made of precast concrete, a hard rubber 8 is attached to the surface of the mounting piece 31 that contacts the pillar member 1 as shown in FIG. The gantry 3 also serves as a lower formwork when pouring concrete into the joint, and is detachably provided on the pillar member 1 to be removed after the construction of the joint and diverted.
【0016】接合部の施工は架台3が接続した柱部材1
をスラブ上の所定位置に立設した後、梁部材2,2を吊
り込んで架台3に支持させ、下端主筋21と上端主筋22を
連結鉄筋4に接続し、図4に示すように架台3上に接合
部の梁型枠9を組み立て、接合部にコンクリートを打設
する、という要領で行われる。下端主筋21と上端主筋22
の接続後、梁部材2の端部から突出する下端主筋21と上
端主筋22回りにはスターラップが配筋され、梁型枠9の
組み立てと並行して梁部材2上ではスラブ型枠の組み立
てとスラブ筋の配筋が行われ、接合部とスラブのコンク
リートが打設される。柱部材1が鋼管コンクリート造の
場合は鋼管13の内部には必要な柱の耐力に応じて強度の
異なるコンクリート14が別途打設される。The construction of the joint is carried out by the pillar member 1 to which the pedestal 3 is connected.
After standing up at a predetermined position on the slab, the beam members 2 and 2 are suspended and supported by the gantry 3, the lower end main bar 21 and the upper end main bar 22 are connected to the connecting rebar 4, and the gantry 3 is connected as shown in FIG. The beam form 9 of the joint is assembled on the top, and concrete is placed in the joint. Lower main bar 21 and upper main bar 22
After connecting, the stirrup is arranged around the lower end main bar 21 and the upper end main bar 22 projecting from the end of the beam member 2, and the slab formwork is assembled on the beam member 2 in parallel with the assembly of the beam formwork 9. And the slab reinforcement is arranged and the joint and slab concrete are placed. When the column member 1 is made of steel pipe concrete, concrete 14 having different strength depending on the required proof strength of the column is separately placed inside the steel pipe 13.
【0017】図1〜図5は柱部材1がプレキャストコン
クリート製の場合の、図7,図8は鋼管コンクリート造
の場合の実施例であり、図5は梁部材2が接合部を貫通
する場合の、その他は柱部材1が貫通する場合の実施例
を示している。1 to 5 show an embodiment in which the pillar member 1 is made of precast concrete, and FIGS. 7 and 8 show an embodiment in the case of a steel pipe concrete structure. FIG. 5 shows a case where the beam member 2 penetrates the joint. Others show examples in which the column member 1 penetrates.
【0018】[0018]
【発明の効果】この発明は以上の通りであり、柱部材の
外周に架台を着脱自在に突設し、この架台に梁部材を仮
支持させた状態で梁主筋を接合部を貫通させて配筋し、
コンクリートの打設によって接合部を構成するものであ
るため梁部材をクレーンから吊り下げることによる安定
性の確保が不要になると同時に、不安定化に伴う危険を
回避することができる。As described above, the present invention is as described above. A frame is detachably provided on the outer periphery of a column member, and a beam main bar is pierced through a joint portion while the beam member is temporarily supported by the frame. Muscle and
Since the joint is formed by pouring concrete, it is not necessary to secure stability by suspending the beam member from the crane, and at the same time, the risk associated with instability can be avoided.
【0019】またクレーンが梁部材の載置後に切り離さ
れることによりその稼働率が上昇するため施工の進捗を
図ることができる。Further, since the operating rate of the crane is increased by separating the crane after the beam member is placed, the progress of construction can be promoted.
【図1】梁部材の架設状態を示した立面図である。FIG. 1 is an elevational view showing a erected state of a beam member.
【図2】図1の接合部の拡大図である。FIG. 2 is an enlarged view of a joint portion in FIG.
【図3】梁主筋を連結鉄筋に接続したときの様子を示し
た立面図である。FIG. 3 is an elevational view showing a state where the main beam bars are connected to the connecting reinforcing bars.
【図4】図3の平面図である。FIG. 4 is a plan view of FIG.
【図5】接合部を梁部材が貫通する場合の実施例を示し
た立面図である。FIG. 5 is an elevational view showing an embodiment in which a beam member penetrates a joint portion.
【図6】図5に示す梁部材の吊り込みの様子を示した立
面図である。FIG. 6 is an elevational view showing how the beam member shown in FIG. 5 is suspended.
【図7】柱部材が鋼管コンクリート造の場合の実施例を
示した立面図である。FIG. 7 is an elevational view showing an embodiment in which the column member is made of steel pipe concrete.
【図8】図7の平面図である。FIG. 8 is a plan view of FIG.
1……柱部材、11……主筋、12……フープ、13……鋼
管、14……コンクリート、2……梁部材、21……下端主
筋、22……上端主筋、3……架台、30……ユニット、31
……取付片、32……フランジ、4……連結鉄筋、5……
カプラー、6……ボルト、7……リングスチフナ、8…
…硬質ゴム、9……梁型枠。1 ... Column member, 11 ... Main bar, 12 ... Hoop, 13 ... Steel tube, 14 ... Concrete, 2 ... Beam member, 21 ... Lower end bar, 22 ... Upper bar, 3 ... Stand, 30 ...... Unit, 31
...... Mounting piece, 32 ...... Flange, 4 ...... Connecting rebar, 5 ......
Coupler, 6 ... Bolt, 7 ... Ring stiffener, 8 ...
… Hard rubber, 9… Beam formwork.
Claims (1)
鋼管コンクリート造の柱部材とプレキャストコンクリー
ト製の梁部材からなる接合部の施工方法であり、柱部材
の外周の、梁部材の下端面位置からは梁部材を仮支持す
る架台が着脱自在に張り出しており、柱部材を立設した
後、その架台上に梁部材を載置して支持させ、梁部材の
主筋を接合部を貫通させて配筋し、架台上に接合部の梁
型枠を組み立て、接合部にコンクリートを打設して接合
部を構成する柱・梁接合部の施工方法。1. A method for constructing a joint comprising a beam member made of precast concrete or a steel pipe concrete structure and a beam member made of precast concrete, wherein the beam member is attached from the lower end surface position of the beam member on the outer periphery of the column member. The pedestal for temporary support is detachably overhanging, and after the pillar member is erected, the beam member is placed and supported on the pedestal, and the main bar of the beam member is pierced through the joint to arrange the bar member. A method of constructing a column-beam joint in which the beam formwork of the joint is assembled on top and concrete is placed in the joint to form the joint.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4330631A JP2677144B2 (en) | 1992-12-10 | 1992-12-10 | Construction method for column-beam joints |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4330631A JP2677144B2 (en) | 1992-12-10 | 1992-12-10 | Construction method for column-beam joints |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH06173339A true JPH06173339A (en) | 1994-06-21 |
JP2677144B2 JP2677144B2 (en) | 1997-11-17 |
Family
ID=18234832
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP4330631A Expired - Lifetime JP2677144B2 (en) | 1992-12-10 | 1992-12-10 | Construction method for column-beam joints |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2677144B2 (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08135015A (en) * | 1994-11-08 | 1996-05-28 | Tokyu Constr Co Ltd | Connection structure of column and beam and connection method thereof |
JP2006169837A (en) * | 2004-12-16 | 2006-06-29 | Taisei Corp | Column-beam joint structure of reinforced concrete construction |
JP2008115539A (en) * | 2006-10-31 | 2008-05-22 | Okumura Corp | Flat plate construction method |
JP2012207414A (en) * | 2011-03-29 | 2012-10-25 | Takenaka Komuten Co Ltd | Joint structure for reinforced concrete beam |
CN103088915A (en) * | 2012-08-16 | 2013-05-08 | 杨众 | Cast-in-site column with column cap and construction method |
JP2014214460A (en) * | 2013-04-24 | 2014-11-17 | 株式会社竹中工務店 | Connection member and beam connection method |
CN104631705A (en) * | 2015-02-12 | 2015-05-20 | 广西壮族自治区冶金建设公司 | Integral type beam-column node area column hoop and constructing method thereof |
CN104895196A (en) * | 2015-05-27 | 2015-09-09 | 常州市规划设计院 | Hidden steel corbel type beam column hinged node and construction method thereof |
CZ305454B6 (en) * | 2013-06-17 | 2015-09-23 | ÄŚeskĂ© vysokĂ© uÄŤenĂ technickĂ© v Praze, Fakulta stavebnĂ, Katedra konstrukcĂ pozemnĂch staveb | Building structure connecting module |
JP6030274B1 (en) * | 2015-07-17 | 2016-11-24 | 三井住友建設株式会社 | Frame structure and its construction method |
WO2017013694A1 (en) * | 2015-07-17 | 2017-01-26 | 三井住友建設株式会社 | Framework structure and construction method for same |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111764509A (en) * | 2020-06-17 | 2020-10-13 | 江苏华源建筑设计研究院股份有限公司 | Reinforced concrete connecting joint with steel pipe core for prefabricated beam column and connecting method |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS63289141A (en) * | 1987-05-19 | 1988-11-25 | Fujita Corp | Construction method for bonding pc pillar and beam |
-
1992
- 1992-12-10 JP JP4330631A patent/JP2677144B2/en not_active Expired - Lifetime
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS63289141A (en) * | 1987-05-19 | 1988-11-25 | Fujita Corp | Construction method for bonding pc pillar and beam |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08135015A (en) * | 1994-11-08 | 1996-05-28 | Tokyu Constr Co Ltd | Connection structure of column and beam and connection method thereof |
JP2006169837A (en) * | 2004-12-16 | 2006-06-29 | Taisei Corp | Column-beam joint structure of reinforced concrete construction |
JP2008115539A (en) * | 2006-10-31 | 2008-05-22 | Okumura Corp | Flat plate construction method |
JP2012207414A (en) * | 2011-03-29 | 2012-10-25 | Takenaka Komuten Co Ltd | Joint structure for reinforced concrete beam |
CN103088915A (en) * | 2012-08-16 | 2013-05-08 | 杨众 | Cast-in-site column with column cap and construction method |
JP2014214460A (en) * | 2013-04-24 | 2014-11-17 | 株式会社竹中工務店 | Connection member and beam connection method |
CZ305454B6 (en) * | 2013-06-17 | 2015-09-23 | ÄŚeskĂ© vysokĂ© uÄŤenĂ technickĂ© v Praze, Fakulta stavebnĂ, Katedra konstrukcĂ pozemnĂch staveb | Building structure connecting module |
CN104631705A (en) * | 2015-02-12 | 2015-05-20 | 广西壮族自治区冶金建设公司 | Integral type beam-column node area column hoop and constructing method thereof |
CN104895196A (en) * | 2015-05-27 | 2015-09-09 | 常州市规划设计院 | Hidden steel corbel type beam column hinged node and construction method thereof |
JP6030274B1 (en) * | 2015-07-17 | 2016-11-24 | 三井住友建設株式会社 | Frame structure and its construction method |
WO2017013694A1 (en) * | 2015-07-17 | 2017-01-26 | 三井住友建設株式会社 | Framework structure and construction method for same |
US10465374B2 (en) | 2015-07-17 | 2019-11-05 | Sumitomo Mitsui Construction Co., Ltd. | Frame structure and method of constructing frame structure |
Also Published As
Publication number | Publication date |
---|---|
JP2677144B2 (en) | 1997-11-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH06173339A (en) | Constructing method for joining section for column/beam | |
JP2750368B2 (en) | Construction method of reactor containment top slab | |
JP3700102B2 (en) | Building basic structure | |
CN107227814B (en) | A kind of large cantilever concrete structure section construction method | |
CN210529735U (en) | Building steel structure platform base | |
CN109812001A (en) | A kind of construction method of Super High bilayer I-steel overhanging support system | |
JP3087195B2 (en) | How to build stairs | |
JPH05311617A (en) | Construction method for elevated structure | |
JP3281421B2 (en) | Construction method of horizontal beam erected on tower | |
CN213806581U (en) | Super high-rise high-altitude large-span cantilever concrete structure formwork support system | |
KR102296982B1 (en) | Transfer Structure Construction Method Using U-shaped Steel Girder | |
JPH11247288A (en) | Column-beam main bar pre-assembled hollow precast concrete column unit and column constructing method using this column unit | |
JPH1113141A (en) | Constructing method of composite structure | |
JP2759361B2 (en) | Pillar support members for building reinforced concrete buildings | |
CN113403936A (en) | Bracket-free rapid construction method for hollow pier partition plate of bridge | |
JPH1150653A (en) | Supporting frame of scaffold plate and fitting and removing method therefor and construction for reinforced concrete wall by use thereof | |
JP2669305B2 (en) | Structure using covered steel tube concrete columns | |
JP2904752B2 (en) | Construction method of reinforced steel frame of reinforced concrete building | |
JPH06299718A (en) | Construction of wall, floor in atomic power plant and wall slab thereof | |
JPH0988348A (en) | Method for constructing foundation beam | |
CN114033111A (en) | Assembled cornice inclined roof and installation and construction method thereof | |
JP3039665U (en) | Steel reinforced concrete | |
JP2629496B2 (en) | Construction method of structure | |
JPH0711736A (en) | Precast reinforced concrete pillar | |
JP2967530B2 (en) | Basement building construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 19970624 |