JPH06109375A - Tower lifting mechanism for tower equipment - Google Patents

Tower lifting mechanism for tower equipment

Info

Publication number
JPH06109375A
JPH06109375A JP28057592A JP28057592A JPH06109375A JP H06109375 A JPH06109375 A JP H06109375A JP 28057592 A JP28057592 A JP 28057592A JP 28057592 A JP28057592 A JP 28057592A JP H06109375 A JPH06109375 A JP H06109375A
Authority
JP
Japan
Prior art keywords
tower
stage
furnace
work
elevating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP28057592A
Other languages
Japanese (ja)
Other versions
JP2645782B2 (en
Inventor
Yasuhiro Higashijima
靖紘 東島
Hirobumi Yamaguchi
博文 山口
Takeshi Kimoto
丈志 木元
Juichi Shibata
寿一 芝田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KUCHIKU KOGYO KK
Nippon Steel Corp
Original Assignee
KUCHIKU KOGYO KK
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KUCHIKU KOGYO KK, Nippon Steel Corp filed Critical KUCHIKU KOGYO KK
Priority to JP4280575A priority Critical patent/JP2645782B2/en
Publication of JPH06109375A publication Critical patent/JPH06109375A/en
Application granted granted Critical
Publication of JP2645782B2 publication Critical patent/JP2645782B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D1/00Casings; Linings; Walls; Roofs
    • F27D1/16Making or repairing linings ; Increasing the durability of linings; Breaking away linings
    • F27D1/1621Making linings by using shaped elements, e.g. bricks
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D3/00Charging; Discharging; Manipulation of charge
    • F27D2003/0034Means for moving, conveying, transporting the charge in the furnace or in the charging facilities
    • F27D2003/0065Lifts, e.g. containing the bucket elevators

Landscapes

  • Furnace Housings, Linings, Walls, And Ceilings (AREA)
  • Carbon Steel Or Casting Steel Manufacturing (AREA)
  • Movable Scaffolding (AREA)

Abstract

(57)【要約】 【目的】 伸縮性を有し、かつ荷上げ機構を備えたタワ
ーの伸縮作業の作業性の向上が図れ、またタワーを伸長
させた際には必ずタワーの被搬送物の搬送口を開口し
て、被搬送物をタワー内に出し入れできるタワー設備の
タワー昇降機構を提供する。 【構成】 タワー16は、被搬送物25の搬送口36、
37が開口された基台部31内に伸縮自在な筒形部材3
2〜34を有している。タワー16は空洞部35を昇降
して、基台部31の搬送口36、37から搬入された被
搬送物25をタワー16の上部に設けられた作業ステー
ジ17、18まで持ち上げる昇降台46と、昇降台46
を昇降させる昇降装置66とを備えている。タワー16
の昇降は、タワー16の各段の筒形部材32〜34と多
段チューブ型シリンダ38の各段のロッド39〜41と
を、それぞれ対応する段ごとに連結することにより可能
となる。
(57) [Summary] [Purpose] It is possible to improve the workability of the expansion and contraction work of a tower that is elastic and has a loading mechanism. (EN) Provided is a tower lifting mechanism for tower equipment, which is capable of opening and closing a transfer port and loading / unloading a transferred object into / from a tower. [Construction] The tower 16 includes a transfer port 36 for the transferred object 25,
A tubular member 3 which is expandable and contractable in a base 31 in which 37 is opened.
2 to 34. The tower 16 raises and lowers the hollow portion 35 and lifts the transported object 25 loaded from the transfer ports 36 and 37 of the base 31 to the work stages 17 and 18 provided on the upper part of the tower 16, and an elevator 46. Lift 46
And an elevating device 66 for elevating and lowering. Tower 16
Can be moved up and down by connecting the tubular members 32 to 34 of each stage of the tower 16 and the rods 39 to 41 of each stage of the multi-stage tube type cylinder 38 for each corresponding stage.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、タワー設備のタワー昇
降機構に係り、更に詳しくは、複数段の筒形部材を伸縮
自在に連結させた多段筒形のタワーを多段チューブ型シ
リンダにより昇降自在にしたタワー設備のタワー昇降機
構に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a tower raising / lowering mechanism for tower equipment, and more particularly, a multistage tubular tower in which a plurality of stages of tubular members are elastically connected to each other can be raised and lowered by a multistage tube cylinder. Related to the tower lifting mechanism of the tower equipment.

【0002】[0002]

【従来の技術】転炉や電気炉などの炉体の内壁には、溶
けた金属の熱から炉体を保護するために耐熱性の煉瓦が
敷設されている。この煉瓦は耐熱性を有しているもの
の、炉体内の温度が極めて高温になるため、炉使用によ
る煉瓦の溶損は激しく、通常、約1カ月に1回の割合で
新しい煉瓦に取り替えている。この煉瓦の取り替えは、
古い煉瓦を崩して撤去し、新しい煉瓦を炉体の内壁に敷
設(築炉)することにより行われる。
2. Description of the Related Art Heat-resistant bricks are laid on the inner wall of a furnace body such as a converter or an electric furnace in order to protect the furnace body from heat of molten metal. Although this brick has heat resistance, the temperature inside the furnace becomes extremely high, so the brick is severely melted and damaged due to use of the furnace, and it is normally replaced with new brick once a month. . The replacement of this brick is
This is done by breaking down and removing old bricks and laying new bricks on the inner wall of the furnace (building furnace).

【0003】この煉瓦を炉体内に敷設する築炉作業の1
つの方法として、炉上部に開口された炉口部を利用して
行なうものが知られている。この作業は、まず作業に先
駆けて、煉瓦を炉口部から炉体内に搬入する下降装置を
炉体内に持ち込み、次いで作業員が煉瓦を炉口部まで運
び上げ、それから運び上げた煉瓦を下降装置により炉体
内に順次降ろして所定の高さ位置で水平方向に搬出し、
そののちこれを作業員が手作業により炉体の内壁に敷設
するものである。
One of the furnace construction works for laying this brick in the furnace body
As one of the methods, there is known a method using a furnace opening part opened at the upper part of the furnace. In this work, first of all, prior to the work, a lowering device that carries bricks into the furnace body from the furnace mouth is brought into the furnace body, then the worker carries the bricks up to the furnace mouth, and then the bricks carried up are lowered. Then, it is sequentially lowered into the furnace body and carried out horizontally at a predetermined height position.
After that, the worker manually lays this on the inner wall of the furnace body.

【0004】ところで、炉口部の上方には例えば金属の
溶融などに必要な諸々の付帯設備が配設されており、こ
のため大型の下降装置を炉口部から炉体内に持ち込むの
は極めて困難である。そこで、下降装置は分解した状態
で炉口部から炉体内に持ち込まれて炉体内で組み立てる
手段がとられているが、この分解された下降装置を作業
員が炉口部上に運び上げて炉体内に持ち込むのには相当
な手間を要していた。また、築炉作業時においても、作
業員により煉瓦を炉口部まで運び上げなければならず、
この作業にも多大な労力が必要であった。
By the way, above the furnace opening, various incidental equipment necessary for melting metal, for example, is arranged. Therefore, it is extremely difficult to bring a large descending device into the furnace through the furnace opening. Is. Therefore, the lowering device is taken into the furnace body from the furnace mouth in a disassembled state and assembled in the furnace body.However, a worker carries the disassembled lowering device to the furnace mouth portion to raise the furnace. It took a lot of work to bring it into the body. In addition, even during the furnace construction work, the worker must carry the brick up to the furnace opening,
This work also required a lot of labor.

【0005】そこで、この対策として、炉体の炉底部に
開閉自在な開口部を設け、この開口部から炉体内に煉瓦
を持ち上げる持ち上げ装置を挿入し、この持ち上げ装置
により煉瓦を炉体の下方から炉体内に搬入するようにし
たものが知られている。従来、このような炉底部の開口
部から炉体内に煉瓦を搬入するものとして、例えば特公
平4−18003号公報の図7に開示されたものが知ら
れている。
Therefore, as a countermeasure against this, an opening / closing opening is provided at the bottom of the furnace body, and a lifting device for lifting bricks is inserted into the furnace body through this opening. The lifting device lifts the brick from below the furnace body. It is known that it is carried into the furnace body. Conventionally, for example, the one disclosed in FIG. 7 of Japanese Examined Patent Publication No. 4-18003 is known as a tool for carrying bricks into the furnace through such an opening at the bottom of the furnace.

【0006】このものは、炉底部に開口部が設けられた
炉体の下方に配置される移動台車と、この移動台車上に
順次積み上げられて、開口部より炉体内に挿入される多
数個のフレームユニットを備えており、フレームユニッ
トの内部には互いに所定間隔をあけて垂設された固定ビ
ームと称する固定梯子と、昇降ビームと称する昇降梯子
とを組み合わせた煉瓦の持ち上げ装置が配設され、この
昇降梯子を連続的に昇降させることにより、煉瓦を昇降
梯子、固定梯子、昇降梯子と順次飛び移らせて持ち上げ
る構造になっている。このようにすることで、煉瓦を炉
体内に搬入する装置を作業員が炉上部の炉口部まで持ち
上げたり、築炉作業時に多数個の煉瓦を炉口部まで運び
上げるという作業が不要になり、作業員の削減と作業性
の向上を図ることができる。
This is composed of a movable carriage arranged below a furnace body having an opening at the bottom of the furnace and a plurality of movable carriages which are sequentially stacked on the movable carriage and inserted into the furnace body through the opening. The frame unit is provided, and inside the frame unit, there is provided a brick lifting device that is a combination of a fixed ladder called a fixed beam vertically hung at a predetermined interval from each other, and a lifting ladder called a lifting beam. By continuously elevating and lowering the elevating ladder, the brick is sequentially lifted by the elevating ladder, the fixed ladder, and the elevating ladder. This eliminates the need for workers to lift the brick loading device into the furnace mouth to the furnace mouth at the top of the furnace or to carry many bricks to the furnace mouth during the furnace construction work. Therefore, it is possible to reduce the number of workers and improve workability.

【0007】[0007]

【発明が解決しようとする課題】しかしながら、前記従
来の築炉設備は、このように持ち上げ装置が組み立て式
になっているため、煉瓦の敷設作業の進行に合わせて作
業員が炉体内でフレームユニットを積み上げなければな
らず、前述した炉上部の炉口部から持ち込む場合ほどは
ないものの、やはりこの煉瓦を炉体内に搬入する装置の
組み立て作業が面倒であるという問題点があった。本発
明はこのような事情に鑑みてなされたもので、伸縮性を
有し、かつ荷上げ機構を備えたタワーの伸縮作業の作業
性の向上が図れるタワー設備のタワー昇降機構を提供す
ることを目的とする。
However, in the conventional furnace construction equipment, since the lifting device is thus of an assembly type, the worker can use the frame unit in the furnace body as the brick laying work progresses. However, the assembly work of the device for bringing the bricks into the furnace body is still troublesome, though it is not so much as when carrying it in through the furnace mouth portion above the furnace. The present invention has been made in view of such circumstances, and it is an object of the present invention to provide a tower elevating mechanism for tower equipment that has elasticity and can improve the workability of the expansion and contraction work of a tower equipped with a loading mechanism. To aim.

【0008】[0008]

【課題を解決するための手段】前記目的に沿うタワー設
備のタワー昇降機構は、被搬送物の搬送口が開口された
筒形の基台部内に複数段の筒形部材を伸縮自在に設けた
多段筒形のタワーと、該タワーの周囲に均等に配設され
て、多段チューブ形のロッドを有する複数個の多段チュ
ーブ型シリンダと、前記タワーの上部に設けられた作業
ステージと、前記タワー内の空洞部を昇降して、前記基
台部の搬送口よりタワー内に搬入された被搬送物を前記
作業ステージまで持ち上げる昇降台と、前記タワーに設
けられて、前記昇降台を昇降させる昇降装置とを備えた
タワー設備のタワー昇降機構であって、前記タワーの各
段の筒形部材と、前記多段チューブ型シリンダの各段の
ロッドとを、それぞれ対応する段ごとに連結させた構成
としている。
In a tower lifting mechanism for tower equipment in accordance with the above object, a plurality of stages of tubular members are extendably and retractably provided in a tubular base portion in which a transport port of a transported object is opened. A multi-stage tubular tower, a plurality of multi-stage tube type cylinders that are evenly arranged around the tower and have multi-stage tube rods, a work stage provided above the tower, and the inside of the tower. And an elevator for raising and lowering the hollow part of the base to raise the object to be conveyed carried into the tower from the transfer opening of the base to the working stage, and an elevator for raising and lowering the elevator provided on the tower. A tower elevating mechanism of tower equipment comprising: a tower member of each stage of the tower and a rod of each stage of the multi-stage tube type cylinder are connected to each corresponding stage. .

【0009】[0009]

【作用】本発明に係るタワー設備のタワー昇降機構にお
いては、多段チューブ型シリンダを駆動させると、各段
のロッドが突出してそれそれのロッドに連結された各段
の筒形部材が上昇する。この際、基台部に開口された搬
送口は、多段チューブ型シリンダにより最先に上昇され
た1段目の筒形部材の上昇時に開口される。これは、タ
ワー上部に重量のある作業ステージが設けられているた
め、ロッドにかかる負荷が大きい場合は断面積の大きい
ロッドから順次伸縮するというテレスコシリンダの特性
により、多段チューブ型シリンダを駆動した際に最先に
断面積の最も大きな1段目のロッドが突出し、この1段
目のロッドの突出により1段目の筒形部材が他の筒形部
材とともに上昇して基台部の搬送口が開口するためであ
る。
In the tower elevating mechanism for tower equipment according to the present invention, when the multi-stage tube type cylinder is driven, the rod of each stage projects and the tubular member of each stage connected to the rod rises. At this time, the transfer port opened in the base portion is opened when the first-stage tubular member which is first raised by the multistage tube cylinder is raised. This is because when a multi-stage tube type cylinder is driven, due to the characteristic of the telescopic cylinder that a heavy work stage is installed at the top of the tower, it expands and contracts in order from a rod with a large cross section when the load on the rod is large. The first-stage rod with the largest cross-sectional area projects first, and the first-stage rod protrudes to raise the first-stage tubular member together with the other tubular members, and This is for opening.

【0010】タワーを所定の高さまで上昇させたら、開
口された搬送口から被搬送物をタワー内の昇降台上に搬
入し、次いで、昇降装置により昇降台を上昇させて被搬
送物をタワーの上部の作業ステージまで持ち上げる。こ
のように、複数段の筒形部材を伸縮自在に連結させた多
段筒形のタワーを多段チューブ型シリンダにより昇降さ
せる構造としたので、伸縮性を有し、かつ荷上げ機構を
備えたタワーを伸縮させる作業の作業性の向上を図るこ
とができる。
When the tower is raised to a predetermined height, the object to be conveyed is carried into the elevator table in the tower through the opened transfer port, and then the elevator is raised by the elevating device to lift the object to be conveyed from the tower. Lift to upper working stage. As described above, since the multi-stage tubular tower in which a plurality of stages of tubular members are elastically connected is moved up and down by the multi-stage tube type cylinder, a tower having elasticity and a loading mechanism is provided. The workability of the work of expanding and contracting can be improved.

【0011】[0011]

【実施例】続いて、添付した図面を参照しつつ、本発明
を具体化した実施例につき説明し、本発明の理解に供す
る。ここに、図1は本発明の一実施例に係るタワー設備
のタワー昇降機構を適用した築炉設備の使用状態を説明
する断面図、図2は同移動台車の平面図、図3は同タワ
ー内への煉瓦の搬送中の要部断面図、図4は同作業ステ
ージの平面図、図5(a)は同作業ステージにおけるア
ウトリガの収納状態を説明する要部断面図、図5(b)
は同作業ステージにおける回動デッキの収納状態を説明
する要部断面図、図6は同使用状態を説明する断面図、
図7は同昇降装置の平面図、図8は同搭乗ステージおよ
び昇降装置の正面図、図9は同搭乗ステージおよび昇降
台の断面図、図10は同昇降台の正面図、図11は同昇
降台の要部側面図、図12は同タワーの要部拡大断面
図、図13は同タワーの伸長状態を説明する要部拡大側
面図、図14は同使用状態を説明する要部断面図であ
る。
Embodiments of the present invention will now be described with reference to the accompanying drawings to provide an understanding of the present invention. Here, FIG. 1 is a cross-sectional view for explaining a usage state of a furnace building facility to which a tower lifting mechanism of a tower facility according to an embodiment of the present invention is applied, FIG. 2 is a plan view of the mobile carriage, and FIG. 3 is the tower. 4 is a plan view of the work stage, FIG. 5 (a) is a cross-sectional view of the main part for explaining the storage state of the outriggers in the work stage, and FIG. 5 (b).
FIG. 6 is a sectional view of an essential part for explaining a storage state of the rotating deck in the work stage, FIG.
7 is a plan view of the elevator, FIG. 8 is a front view of the boarding stage and the elevator, FIG. 9 is a cross-sectional view of the boarding stage and the elevator, FIG. 10 is a front view of the elevator, and FIG. 11 is the same. FIG. 12 is an enlarged side view of an essential part of the elevator, FIG. 12 is an enlarged side view of an essential part of the tower, FIG. 13 is an enlarged side view of an essential part of the tower, and FIG. Is.

【0012】図1に示すように、本発明の一実施例に係
るタワー設備のタワー昇降機構を適用した築炉設備10
は、炉底部11に開口部12が設けられた転炉用の炉体
13の下方の床面に配設されたレール14上を摺動する
移動台車15と、この移動台車15の中央部上に設けら
れて、前記開口部12より炉体13内に伸縮自在に挿入
されるタワー16と、タワー16の上部に組み付け自在
に設けられた作業ステージ17と、タワー16の上部ま
たは作業ステージ17上に組み付け自在に設けられた同
じく作業ステージの一例としての乗員の搭乗ステージ1
8とを備えている。なお、作業ステージ17および搭乗
ステージ18は、同図鎖線に示すようにタワー16から
分離して移動台車15の両側部上に収納できるようにな
っている。
As shown in FIG. 1, a furnace construction facility 10 to which a tower lifting mechanism of a tower facility according to an embodiment of the present invention is applied.
Is a moving carriage 15 that slides on a rail 14 arranged on a floor surface below a furnace body 13 for a converter having an opening 12 in a furnace bottom 11, and a central portion of the moving carriage 15. And a work stage 17 provided on the upper part of the tower 16 so as to be freely assembled, and on the work stage 17 or on the upper part of the tower 16. An occupant's boarding stage 1 as an example of a work stage that is freely installed in the vehicle
8 and. The work stage 17 and the boarding stage 18 can be separated from the tower 16 and housed on both sides of the moving carriage 15 as shown by the chain line in the figure.

【0013】図1、2に示すように、前記移動台車15
は、台車本体19の中央部から後部上にかけて2階部2
0が設けられており、これらの台車本体19と2階部2
0には、昇降用の階段21が架け渡されている。また、
作業ステージ17は台車本体19の前部上に載置され、
搭乗ステージ18は2階部20の後部に載置される。台
車本体19の前部には運転室22が設けられており、運
転室22の前部にはこの移動台車15を図外の他の移動
台車と連結させるための連結部23が突設され、また台
車本体19の下部にはレール14上を摺動させる車輪2
4が配設されている。
As shown in FIG. 1 and FIG.
Is the second floor 2 from the center to the upper rear of the carriage body 19.
0 is provided, and these trolley body 19 and the second floor 2
At 0, a staircase 21 for raising and lowering is bridged. Also,
The work stage 17 is mounted on the front part of the carriage body 19,
The boarding stage 18 is placed at the rear of the second floor 20. A driver's cab 22 is provided in the front part of the carriage main body 19, and a connecting part 23 for connecting this moving carriage 15 to another moving carriage (not shown) is projectingly provided in the front of the driver's compartment 22. In addition, the wheel 2 that slides on the rail 14 is provided at the bottom of the carriage body 19.
4 are provided.

【0014】台車本体19の前部付近上には、被搬送物
の一例としての煉瓦25が運び出されたパレット26の
回収装置である回収リフタ27が設けられている。台車
本体19上のタワー16より後部側には、煉瓦25を載
置したパレット26をタワー16へ搬入する搬入コンベ
ア28が設けられ、台車本体19上のタワー16と回収
リフタ27の間には、パレット26を搬出する第1の搬
出コンベア29が設けられている。また、回収リフタ2
7の一側部には、パレット26を回収リフタ27から横
方向へ外部排出するための第2の排出コンベア30が設
けられている。
A recovery lifter 27, which is a recovery device for a pallet 26 to which a brick 25, which is an example of an object to be conveyed, is carried is provided near the front of the carriage main body 19. A carry-in conveyor 28 that carries the pallet 26 on which the bricks 25 are placed into the tower 16 is provided on the rear side of the tower 16 on the carriage body 19, and between the tower 16 on the carriage body 19 and the recovery lifter 27. A first carry-out conveyor 29 that carries out the pallet 26 is provided. In addition, the recovery lifter 2
A second discharge conveyor 30 for laterally discharging the pallet 26 from the recovery lifter 27 to the outside is provided on one side of the device 7.

【0015】図1、2に示すように、前記タワー16
は、各々平面視して正方形の箱筒状のタワーで、移動台
車15に固定された基台部31と、この基台部31内に
各々伸縮自在に挿入された筒形部材の一例としての下段
タワー部32、中段タワー部33および上段タワー部3
4から構成されている。各タワー部32〜34は上段に
なるに従って断面形状が小さくなっている。また、図3
に示すようにタワー16内には空洞部35が設けられ、
基台部31の下部の背面にはパレット26をタワー16
内に搬入するための搬送口の一例としての入口36が開
口され、基台部31の下部の前面にはタワー16内から
パレット26を搬出するための搬送口の他の例としての
出口37が開口されている。なお、これらの入口36お
よび出口37は、基台部31の内側にある下段タワー部
32の昇降時に開閉される。
As shown in FIGS. 1 and 2, the tower 16 is
Each of them is a tower having a square box-cylindrical shape in a plan view, and is an example of a base portion 31 fixed to the moving carriage 15 and a tubular member that is elastically inserted into the base portion 31. Lower tower part 32, middle tower part 33 and upper tower part 3
It is composed of 4. Each of the tower parts 32 to 34 has a cross-sectional shape that becomes smaller as it goes up. Also, FIG.
As shown in, a cavity 35 is provided in the tower 16,
A pallet 26 is installed on the bottom of the base 31 on the back of the tower 16
An inlet 36, which is an example of a transfer port for carrying in the inside, is opened, and an outlet 37, which is another example of the transfer port for carrying out the pallet 26 from the inside of the tower 16, is opened on the front surface of the lower portion of the base 31. It is open. The inlet 36 and the outlet 37 are opened and closed when the lower tower unit 32 inside the base unit 31 is moved up and down.

【0016】図1および図2に示すように、タワー16
の両側部の移動台車15上には、タワー16を伸縮させ
る多段チューブ型シリンダとしての一対のテレスコシリ
ンダ38が立設されている。テレスコシリンダ38は、
チューブ形の下段ロッド39、中段ロッド40、上段ロ
ッド41を備えた3段ロッド式のシリンダであり、下段
ロッド39の先端部は下段タワー部32の先端部に連結
され、中段ロッド40の先端部は中段タワー部33の先
端部に連結され、上段ロッド41の先端部は上段タワー
部34の先端部にそれぞれ連結部42を介して連結され
ている。前記作業ステージ17は、下板43と上板44
を備えており、下板43はタワー16に組み付け自在に
取り付けられ、また上板44は4本の支柱45により下
板43上に固定状態で支持されている。上下板43、4
4の中央部には、タワー16内の空洞部35を昇降する
昇降台46の昇降口47、48が設けられており、下板
43上の昇降口47の回りには、煉瓦25が載置された
パレット26を昇降台46から水平方向に搬出する4個
の払出し装置49が前後左右に放射状に配設されてい
る。
As shown in FIGS. 1 and 2, the tower 16
A pair of telescopic cylinders 38, which are multi-stage tube cylinders for expanding and contracting the tower 16, are erected on the movable carriages 15 on both sides. The telescopic cylinder 38
It is a three-stage rod type cylinder provided with a tube-shaped lower rod 39, middle rod 40, and upper rod 41. The tip end of the lower rod 39 is connected to the tip end of the lower tower part 32, and the tip end of the middle rod 40. Is connected to the tip of the middle tower part 33, and the tip of the upper rod 41 is connected to the tip of the upper tower 34 via a connecting part 42, respectively. The work stage 17 includes a lower plate 43 and an upper plate 44.
The lower plate 43 is attached to the tower 16 so as to be freely assembled, and the upper plate 44 is fixedly supported on the lower plate 43 by four columns 45. Upper and lower plates 43, 4
In the central part of 4, the elevating ports 47 and 48 of the elevating table 46 for elevating the cavity 35 in the tower 16 are provided, and the brick 25 is placed around the elevating port 47 on the lower plate 43. Four pay-out devices 49 for horizontally discharging the pallet 26 thus produced from the elevating table 46 are radially arranged in the front, rear, left and right directions.

【0017】図4、5に示すように、払出し装置49
は、下板43の外縁部に上方回動自在な回動デッキ50
が枢着され、回動デッキ50上にローラコンベア51が
設けられたものである。この回動デッキ50内には、シ
リンダ50aのロッド50bを出し入れすることにより
このデッキ50の先端部から出入りするスライドデッキ
50cが収納されている。また、同じく図4、5に示す
ように、下板43の外縁部の各払出し装置49間には、
築炉作業時に作業ステージ17を炉体13内に固定する
4本のアウトリガ52が、前記各支柱45の元部にそれ
ぞれ上方回動自在に枢着されている。アウトリガ52
は、筒状の本体53内に、炉体13の内壁に当接される
脚部54が摺動自在に挿入されており、この脚部54
は、その内部に収納されたシリンダ54aのロッド54
bを出し入れさせることにより摺動する。各払出し装置
49とアウトリガ52の間には、扇形の足場板55が着
脱自在に敷設されている。なお、この足場板55は、ス
ライドデッキ50cおよび脚部54を伸長させた際にも
その伸長部分に継ぎ足される。
As shown in FIGS. 4 and 5, the dispensing device 49
Is a rotating deck 50 that is rotatable upward on the outer edge of the lower plate 43.
And a roller conveyor 51 is provided on the rotating deck 50. A slide deck 50c, which moves in and out from the tip of the deck 50 by moving the rod 50b of the cylinder 50a in and out, is housed in the rotating deck 50. Similarly, as shown in FIGS. 4 and 5, between the dispensing devices 49 on the outer edge of the lower plate 43,
Four outriggers 52 for fixing the work stage 17 in the furnace body 13 at the time of furnace construction work are pivotally attached to the bases of the columns 45 so as to be rotatable upward. Outrigger 52
In a cylindrical main body 53, a leg portion 54 abutting against the inner wall of the furnace body 13 is slidably inserted.
Is the rod 54 of the cylinder 54a housed inside.
Sliding by inserting and removing b. A fan-shaped scaffolding plate 55 is removably laid between each dispensing device 49 and the outriggers 52. The scaffolding plate 55 is added to the extended portion when the slide deck 50c and the leg portion 54 are extended.

【0018】払出し装置49とアウトリガ52は、炉底
部11の開口部12から作業ステージ17を炉体13内
に出し入れするときに、この出し入れの邪魔にならない
ように上方回動される。このとき、アウトリガ52は支
柱45の外側面に設けられた縦長の溝部56内に収納で
きるようになっている。すなわち、図5(a)に示すよ
うにこの支柱45の溝部56内に設けられたシリンダ4
5aのロッド45bを突出させることにより、アウトリ
ガ52を上方回動させて溝部56内に収納する。このよ
うにしたため、アウトリガ52の収納性が良好になり、
作業ステージ17の炉体13内への出し入れがさらに円
滑になる。図6に示すように、前記作業ステージ17の
上板44の対向位置には、払出し装置49により搬出さ
れた煉瓦25を炉体13の内壁に敷設する煉瓦積み装置
の一例としての一対の築炉装置57が配設されている。
築炉装置57はアーム58の先端部に設けられたクラン
プ部59により払出し装置94上の煉瓦25をクランプ
してピックアップし、アーム58を移動させてこれを炉
体13の内壁に順次積み上げる。
The payout device 49 and the outrigger 52 are rotated upward so that the work stage 17 can be put in and taken out of the furnace body 13 through the opening 12 of the furnace bottom 11 so as not to interfere with the putting in and out. At this time, the outrigger 52 can be housed in a vertically long groove portion 56 provided on the outer surface of the column 45. That is, as shown in FIG. 5A, the cylinder 4 provided in the groove portion 56 of the support column 45.
By projecting the rod 45b of 5a, the outrigger 52 is rotated upward and is housed in the groove 56. Because of this, the outrigger 52 can be easily stored.
The work stage 17 can be further smoothly taken in and out of the furnace body 13. As shown in FIG. 6, at a position opposite to the upper plate 44 of the work stage 17, a pair of building furnaces as an example of a brick stacking device that lays the bricks 25 discharged by the discharging device 49 on the inner wall of the furnace body 13. A device 57 is provided.
The furnace building device 57 clamps and picks up the bricks 25 on the dispensing device 94 by the clamp portion 59 provided at the tip of the arm 58, and moves the arm 58 to sequentially stack the bricks on the inner wall of the furnace body 13.

【0019】図1に戻って、前記搭乗ステージ18は、
上板44に立設された4本の支柱60に組み付け自在に
支持された台板61と、この台板61上に支柱62によ
り支持された作業デッキ63を備えている。台板61お
よび作業デッキ63の中央部には、昇降台46の昇降口
64、65が設けられており、台板61の対向位置に
は、前記昇降台46を昇降させる左右一対の昇降装置6
6が設けられている。作業デッキ63は台部63a上に
作業用の手すり63bが周設されたものであり、台部6
3a上には作業員による築炉作業を補助するために煉瓦
積み装置の他の例としてのバランサ63cが設けられて
いる。次に、昇降装置66を図7〜9を参照して詳細に
説明する。図7、8に示すように、台板61上にはモー
タ67が設けられ、モータ67のシャフト軸68にはギ
ヤ69が固着され、このギヤ69に噛合するギヤ70が
ドラム71の回転軸72に固着されている。この回転軸
72は一対の軸受73により支持されており、ドラム7
1はこの回転軸72の両端部にそれぞれ設けられてい
る。また、ドラム71の周面には先端部が昇降台46の
4隅に接続されたワイヤ74が巻回されている。
Returning to FIG. 1, the boarding stage 18 is
A base plate 61 supported so as to be freely assembled to four columns 60 erected on the upper plate 44, and a work deck 63 supported by the columns 62 on the platform plate 61 are provided. Elevating ports 64 and 65 of the elevating table 46 are provided in the central portions of the table 61 and the work deck 63, and a pair of left and right elevating devices 6 for elevating the elevating table 46 are provided at opposing positions of the table 61.
6 is provided. The work deck 63 is one in which a work handrail 63b is provided around a base 63a.
A balancer 63c, which is another example of the brick-laying device, is provided on 3a to assist the worker in the furnace construction work. Next, the elevating device 66 will be described in detail with reference to FIGS. As shown in FIGS. 7 and 8, a motor 67 is provided on the base plate 61, a gear 69 is fixed to a shaft shaft 68 of the motor 67, and a gear 70 meshing with the gear 69 is a rotary shaft 72 of a drum 71. Is stuck to. The rotary shaft 72 is supported by a pair of bearings 73, and the drum 7
1 is provided at both ends of the rotary shaft 72. Further, on the peripheral surface of the drum 71, wires 74 whose front ends are connected to the four corners of the elevating table 46 are wound.

【0020】図右側の昇降装置66において、一方の軸
受73から延出した回転軸72の一端部にはギヤ75が
固着され、このギヤ75に噛合するギヤ76は軸受77
に片持ち支持された短尺な回転軸78の先端部に固着さ
れている。回転軸78の元部付近には一方のスプロケッ
ト79が固着されており、これに対する他方のスプロケ
ット80が、図左側の昇降装置66における一方の軸受
73から延出した回転軸72の一端部に固着されてい
る。これらのスプロケット79、80間には左右のモー
タ67を同期させるチェーン81が調帯されており、チ
ェーン81の中間部にはチェーン81の弛みを防止する
スナップアイドル82が介在されている。モータ67を
回転させると、ギヤ69、70を介して回転軸72が回
転し、これによりドラム71からワイヤ74が導出さ
れ、またはドラム71にワイヤ74が巻回されることに
より昇降台46が昇降する。
In the lifting device 66 on the right side of the drawing, a gear 75 is fixed to one end of a rotary shaft 72 extending from one bearing 73, and a gear 76 meshing with the gear 75 is a bearing 77.
It is fixed to the tip of a short rotary shaft 78 that is cantilevered. One sprocket 79 is fixed near the base of the rotary shaft 78, while the other sprocket 80 is fixed to one end of the rotary shaft 72 extending from one bearing 73 in the lifting device 66 on the left side of the drawing. Has been done. A chain 81 for synchronizing the left and right motors 67 is arranged between these sprockets 79, 80, and a snap idle 82 for preventing the chain 81 from slackening is interposed in the middle of the chain 81. When the motor 67 is rotated, the rotating shaft 72 is rotated via the gears 69 and 70, whereby the wire 74 is drawn out from the drum 71, or the wire 74 is wound around the drum 71, so that the elevating table 46 moves up and down. To do.

【0021】また、台板61の各支柱62の近傍上に
は、上昇した昇降台46を保持するための4個のシリン
ダ式のストッパ83が立設されており、図9に示すよう
にストッパ83のロッド84を突出させることにより上
昇した昇降台46を下方から支持する。次に、昇降台4
6を図9〜11を参照して詳細に説明する。
Further, four cylinder-type stoppers 83 for holding the lift table 46 that has been lifted are provided upright in the vicinity of the columns 62 of the base plate 61. As shown in FIG. The elevating table 46 raised by projecting the rod 84 of 83 is supported from below. Next, lift 4
6 will be described in detail with reference to FIGS.

【0022】図9に示すように、昇降台46は枠体から
なる下段部85と、この下段部85上に支柱86を介し
て支持された同じく枠体からなる上段部87と、上段部
87に回転自在に設けられたターンテーブル88と、下
段部85上に設けられて、ターンテーブル88を回転さ
せるモータ89とを備えている。ターンテーブル88上
には、パレット26の搬送に用いられるローラコンベア
90が設けられており、ターンテーブル88の回転軸9
1は軸受92を介して上段部87に支持されている。タ
ーンテーブル88の下面と上段部87の上面の間には、
ターンテーブル88の回転スラストを受けるドーナツ形
の旋回スラスト軸受93が介在されている。ターンテー
ブル88の回転軸91の先端部には傘歯車94が固着さ
れ、この傘歯車94に噛合する傘歯車95がモータ89
のシャフト軸に固着されている。モータ89を回転させ
ると、傘歯車94、95を介して回転軸91が回転して
ターンテーブル88が回転する。下段部85の中央部に
は、モータ89、ローラコンベア90および図外のリミ
ットスイッチに給電するためのスリップリング96が設
けられている。
As shown in FIG. 9, the elevating table 46 has a lower step portion 85 made of a frame body, an upper step portion 87 made of the same frame body supported on the lower step portion 85 via a support 86, and an upper step portion 87. The turntable 88 is rotatably provided on the lower stage 85, and the motor 89 is provided on the lower stage 85 to rotate the turntable 88. A roller conveyor 90 used to convey the pallet 26 is provided on the turntable 88, and the rotary shaft 9 of the turntable 88 is provided.
1 is supported by the upper step portion 87 via a bearing 92. Between the lower surface of the turntable 88 and the upper surface of the upper step portion 87,
A donut-shaped orbiting thrust bearing 93 that receives the rotating thrust of the turntable 88 is interposed. A bevel gear 94 is fixed to the tip of a rotary shaft 91 of the turntable 88, and a bevel gear 95 meshing with the bevel gear 94 is a motor 89.
Is fixed to the shaft axis of. When the motor 89 is rotated, the rotating shaft 91 is rotated via the bevel gears 94 and 95, and the turntable 88 is rotated. A motor 89, a roller conveyor 90, and a slip ring 96 for supplying electric power to a limit switch (not shown) are provided at the center of the lower portion 85.

【0023】また、図10に示すように、下段部85は
短尺な前後フレーム98と左右フレーム99を有してお
り、左右フレーム99の両端部には4個の滑車100が
昇降台46の角部方向へ向かって斜めに取り付けられて
いる。また、図10および図11に示すように、上段部
87の左右フレーム101の両端部上には、先端部が対
峙方向に反った長尺なガイド板102が立設されてい
る。このガイド板102は、昇降台46が伸長されたタ
ワー16の空洞部35内を上昇する際に、基台部31か
ら下段タワー部32への通過時、下段タワー部32から
中段タワー部33への通過時および中段タワー部33か
ら上段タワー部34への通過時において、昇降台46の
左右側が中段タワー部33の下端部や上段タワー部34
の下端部の左右内壁に接触して、昇降台46の円滑な上
昇を妨げるのを解消するものである。また、昇降台46
の前後側が、これらの各タワー部32〜34の下端部の
左右内壁に接触するのを防止するために、図12に示す
ように各タワー部32〜34の下端部の角部近傍の左右
内壁にそれぞれ切欠部103を形成し、この切欠部10
3内にガイドローラ104を設けている。
Further, as shown in FIG. 10, the lower step portion 85 has a short front and rear frame 98 and a left and right frame 99, and four pulleys 100 are provided at both ends of the left and right frame 99 and the corners of the lift table 46. It is attached diagonally toward the direction of the part. Further, as shown in FIGS. 10 and 11, on both ends of the left and right frames 101 of the upper step portion 87, long guide plates 102 whose tip portions are warped in the confronting direction are provided upright. The guide plate 102 moves from the lower tower section 32 to the middle tower section 33 when passing from the base section 31 to the lower tower section 32 when the elevator board 46 moves up in the hollow section 35 of the tower 16. The left and right sides of the lifting platform 46 are located at the lower end of the middle tower part 33 and the upper tower part 34 when the middle tower part 33 and the upper tower part 34 pass.
This prevents contact with the left and right inner walls of the lower end of the hose and hinders the smooth lifting of the lift table 46. In addition, the lift 46
In order to prevent the front and rear sides of the towers 32 to 34 from contacting the left and right inner walls of the lower ends of the towers 32 to 34, the left and right inner walls near the corners of the lower ends of the towers 32 to 34 as shown in FIG. The notch 103 is formed in each of the
A guide roller 104 is provided in the unit 3.

【0024】なお、図1において、105は煉瓦25の
受け筒、106はケーブルベア、107は炉上部(傾斜
部)、108は炉上部107に開口された炉口部、10
9は炉中央部(直胴部)、110はクレーン、111は
フォークリフト車である。
In FIG. 1, 105 is a receiving tube for the brick 25, 106 is a cable bear, 107 is a furnace upper part (inclined part), 108 is a furnace opening part opened in the furnace upper part 107, 10
Reference numeral 9 is a central portion of the furnace (straight body portion), 110 is a crane, and 111 is a forklift truck.

【0025】続いて、本発明の一実施例に係るタワー設
備のタワー昇降機構が適用された築炉設備10の動作に
ついて説明する。予め、図1の鎖線に示すように、作業
ステージ17と搭乗ステージ18はタワー16から分離
して、移動台車15のタワー16の両側部上に収納させ
ておく。炉体13の炉底部11の築炉作業時は、まず開
口部12内に煉瓦25の受け筒105を装着し、搭乗ス
テージ18が炉底部11の開口部12の直下に位置する
ように、移動台車15を炉体13の下方に移動させ、炉
上部107の炉口部108の上方からクレーン110に
より搭乗ステージ18を吊り上げ、移動台車15を移動
してタワー16を炉底部11の開口部12の直下に位置
させ、吊り上げた搭乗ステージ18を下降させて搭乗ス
テージ18をタワー16の上部にボルトにより組み付け
る。
Next, the operation of the furnace construction equipment 10 to which the tower lifting mechanism of the tower equipment according to the embodiment of the present invention is applied will be described. In advance, as shown by the chain line in FIG. 1, the work stage 17 and the boarding stage 18 are separated from the tower 16 and stored on both sides of the tower 16 of the moving carriage 15. When constructing the furnace bottom 11 of the furnace body 13, first, the receiving cylinder 105 of the brick 25 is mounted in the opening 12, and the boarding stage 18 is moved so as to be located immediately below the opening 12 of the furnace bottom 11. The carriage 15 is moved below the furnace body 13, the boarding stage 18 is lifted by a crane 110 from above the furnace opening 108 of the furnace upper part 107, and the moving carriage 15 is moved to move the tower 16 to the opening 12 of the furnace bottom 11. The boarding stage 18 positioned directly below is lowered to mount the boarding stage 18 on the upper portion of the tower 16 with bolts.

【0026】次いで、図13に示すように、テレスコシ
リンダ38を駆動させると下段ロッド39が突出し、タ
ワー16の下段タワー部32が他のタワー部33、34
とともに上昇して、搭乗ステージ18が開口部12を通
過して炉底部11内まで上昇する。このとき、図3に示
すように下段タワー部32の上昇によりタワー16の下
部に設けられた出入口36、37が開口する。このよう
に、テレスコシリンダ38の駆動により中段タワー部3
3や上段タワー部34が上昇せずに下段タワー部32が
上昇するのは、ロッド39〜41にかかる負荷が大きい
場合には断面積の大きいロッドから順次伸縮するという
テレスコシリンダ38の特性を利用しているためであ
る。すなわち、再び図13に示すようにタワー16上に
は大重量の搭乗ステージ18が組み付けられ、しかも各
タワー部32〜34は各ロッド39〜41にそれぞれ連
結されているので、テレスコシリンダ38を駆動させる
と、まず最先に最も断面積の大きな下段ロッド39が他
のロッド40、41を押し上げながら突出し、この突出
に伴って下段ロッド39に連結された下段タワー部32
が他のタワー部33、34とともに上昇するのである。
Next, as shown in FIG. 13, when the telescopic cylinder 38 is driven, the lower stage rod 39 is projected, and the lower stage tower portion 32 of the tower 16 is replaced with the other tower portions 33, 34.
Along with this, the boarding stage 18 passes through the opening 12 and rises into the furnace bottom 11. At this time, as shown in FIG. 3, as the lower tower section 32 rises, the entrances and exits 36 and 37 provided in the lower portion of the tower 16 open. In this way, by driving the telescopic cylinder 38, the middle tower unit 3
The reason why the lower tower part 32 ascends while the upper tower part 34 and the upper tower part 34 do not ascend is that the characteristics of the telescopic cylinder 38 are expanded and contracted in order from a rod having a large cross-sectional area when the load applied to the rods 39 to 41 is large. This is because That is, as shown in FIG. 13 again, since the heavy loading stage 18 is mounted on the tower 16 and the tower portions 32 to 34 are connected to the rods 39 to 41, respectively, the telescopic cylinder 38 is driven. Then, first, the lower stage rod 39 having the largest cross-sectional area protrudes while pushing up the other rods 40 and 41, and the lower stage tower portion 32 connected to the lower stage rod 39 is accompanied by this protrusion.
Rises with the other tower parts 33, 34.

【0027】このように、基台部31に開口された出入
口36、37は、テレスコシリンダ38により最先に上
昇された下段タワー部32の上昇時に必ず開口されるの
で、炉底部11、炉中央部109、炉上部107という
炉体13の部位に関係なく、タワー16を伸長させて築
炉作業を行う際には必ず出入口36、37を開口させ
て、煉瓦25を入口36からタワー16内の昇降台46
上に搬入して搭乗ステージ18上に持ち上げたり、煉瓦
25がなくなったパレット26を出口37から運び出す
ことができる。
As described above, the inlets and outlets 36, 37 opened in the base 31 are always opened when the lower tower 32 raised by the telescopic cylinder 38 is raised. Regardless of the portion of the furnace body 13 such as the section 109 and the furnace upper part 107, when the tower 16 is extended and the furnace construction work is performed, the inlets and outlets 36 and 37 are always opened, and the brick 25 is inserted from the inlet 36 to the inside of the tower 16. Lift 46
It is possible to carry it up and lift it onto the boarding stage 18, or carry out the pallet 26 from which the bricks 25 have disappeared from the exit 37.

【0028】そののち、煉瓦25が載置されたパレット
26はフォークリフト車111により搬入コンベア28
に搬入され、図3に示すように、入口36からタワー1
6の下部に下降した昇降台46のローラコンベア90上
に搬送される。次いで、図7に示すように昇降装置66
のモータ67の回転により、ワイヤ74がドラム71に
巻回されて昇降台46がタワー16内の空洞部35を上
昇し、作業デッキ63の昇降口65まで上昇する。この
とき、昇降台46が基台部31から下段タワー部32へ
通過する際に昇降台46が横揺れしても、図10、11
に示す昇降台46上に突設されたガイド板102や図1
2に示す下段タワー部32の下端部に設けられたガイド
ローラ104により昇降台46が下段タワー部32の内
壁に接触することはない。図9に示すように、昇降台4
6が昇降口65まで上昇したらストッパ83を駆動して
ロッド84を突出させ、昇降台46を下方から支持す
る。
After that, the pallet 26 on which the bricks 25 are placed is transferred by the forklift truck 111 to the carry-in conveyor 28.
It is carried into the tower 1, and as shown in FIG.
It is conveyed onto the roller conveyor 90 of the elevating table 46 that has descended to the lower part of 6. Then, as shown in FIG.
The rotation of the motor 67 causes the wire 74 to be wound around the drum 71, and the lift table 46 to move up the cavity 35 in the tower 16 to the lift opening 65 of the work deck 63. At this time, even if the lift table 46 sways when the lift table 46 passes from the base section 31 to the lower tower section 32, as shown in FIGS.
1 and the guide plate 102 protrudingly provided on the lift table 46 shown in FIG.
The guide roller 104 provided at the lower end of the lower tower section 32 shown in FIG. 2 prevents the elevating table 46 from contacting the inner wall of the lower tower section 32. As shown in FIG.
When 6 rises up to the elevating port 65, the stopper 83 is driven to cause the rod 84 to project, and the elevating table 46 is supported from below.

【0029】次いで、図14に示すように、作業デッキ
63上に搭乗した作業員がバランサ63cを手動操作し
てパレット26上の煉瓦25をピックアップし、炉底部
11の内壁に順次敷設する。このとき、炉底部11の開
口部12には受け筒105が装着されているので、煉瓦
25が炉底部11の下傾斜する内壁を滑り落ちて開口部
12から落下するのを防止できる。なお、開口部12に
装着された受け筒105は、炉底部11に煉瓦25を敷
設した後に適時撤去される。図1に示すように、炉中央
部109の築炉作業時は、まずタワー16から搭乗ステ
ージ18を一旦取り外してクレーン110により炉上部
107の炉口部108から炉体13の上方まで吊り上
げ、これを炉体13の上方側部に仮置しておく。次い
で、移動台車15を移動して炉底部11の開口部12の
直下に作業ステージ17を位置させ、クレーン110に
よりこの作業ステージ17を吊り上げてこれを開口部1
2から炉体13内に吊り上げる。このとき、作業ステー
ジ17が開口部12を通過する際の邪魔にならないよう
に、払出し装置49は手動または電動により、またアウ
トリガ52はシリンダ54aにより上方へ回動される
(図5参照)。
Next, as shown in FIG. 14, a worker on the work deck 63 manually operates the balancer 63c to pick up the bricks 25 on the pallet 26 and sequentially lay them on the inner wall of the furnace bottom 11. At this time, since the receiving cylinder 105 is attached to the opening 12 of the furnace bottom 11, it is possible to prevent the brick 25 from sliding down the inner wall of the furnace bottom 11 which is inclined downward and dropping from the opening 12. The receiving tube 105 mounted in the opening 12 is removed at a proper time after the brick 25 is laid on the furnace bottom 11. As shown in FIG. 1, during the furnace construction work of the furnace central part 109, first, the loading stage 18 is temporarily removed from the tower 16 and the crane 110 lifts it from the furnace opening 108 of the furnace upper part 107 to a position above the furnace body 13. Is temporarily placed on the upper side of the furnace body 13. Then, the movable carriage 15 is moved to position the work stage 17 just below the opening 12 of the furnace bottom 11, and the work stage 17 is lifted by the crane 110 to open it.
Lift from 2 into the furnace body 13. At this time, the payout device 49 is rotated manually or electrically and the outrigger 52 is rotated upward by the cylinder 54a so that the work stage 17 does not interfere with the passage of the opening 12 (see FIG. 5).

【0030】次いで、移動台車15を移動させてタワー
16を炉底部11の開口部12の直下に位置させ、それ
から吊り上げた作業ステージ17を下降させてこれをタ
ワー16の上部に組み付ける。続いて、仮置き状態の搭
乗ステージ18をクレーン110により炉口部108か
ら炉体13内に下降し、これを作業ステージ17上に組
み付ける。そののち、図4、5に示すように払出し装置
49およびアウトリガ52を下方回動させてから、シリ
ンダ54aによりロッド54bを突出させて各アウトリ
ガ52の脚部54を延ばし、これを炉体13の内壁に押
接して作業ステージ17を炉体13内に支持する。ま
た、払出し装置49のシリンダ50aのロッド50bを
突出させてスライドデッキ50cを押し出し、そののち
各払出し装置49およびアウトリガ52間に足場板55
を取り付ける。
Next, the moving carriage 15 is moved to position the tower 16 directly below the opening 12 of the furnace bottom 11, and the work stage 17 that has been lifted is then lowered to assemble it on the upper part of the tower 16. Subsequently, the boarding stage 18 in the temporarily placed state is lowered by the crane 110 from the furnace opening 108 into the furnace body 13, and is mounted on the work stage 17. After that, as shown in FIGS. 4 and 5, the dispensing device 49 and the outrigger 52 are rotated downward, and then the rod 54b is projected by the cylinder 54a to extend the leg portion 54 of each outrigger 52. The work stage 17 is supported in the furnace body 13 by being pressed against the inner wall. Further, the rod 50b of the cylinder 50a of the dispensing device 49 is projected to push out the slide deck 50c, and then the scaffold plate 55 is provided between each dispensing device 49 and the outrigger 52.
Attach.

【0031】次いで、図1、6に示すように、テレスコ
シリンダ38により中段ロッド40および上段ロッド4
1を突出させて中段タワー部33や上段タワー部34を
上昇させ、作業ステージ17を炉中央部109の所定位
置まで上昇させる。そののち、昇降装置66のモータ6
7を回転させて、昇降台46を作業ステージ17の下板
43の昇降口47まで上昇させ、次いで昇降台46のモ
ータ89によりターンテーブル88を回転させ、パレッ
ト26の搬出方向を選択された払出し装置49の搬送方
向に合わせる。そして、ローラコンベア90によりパレ
ット26を昇降台46から選択された払出し装置49へ
水平方向に搬出する。このようにしたので、ターンテー
ブル88を回転させるという小さな動力で、煉瓦25の
搬出方向を一方向だけでなく、払出し装置49の個数だ
け多方向に向けることができる。なお、昇降台46の上
昇時において、昇降台46が基台部31、下段タワー部
32、中段タワー部33、上段タワー部34の各間を通
過する際には、炉底部11の築炉作業時の場合と同様
に、昇降台46上のガイド板102や各タワー部32〜
34の下端部に設けられたガイドローラ104により、
昇降台46が上昇中に各タワー部32〜34の内壁に接
触するのを防止できる。
Then, as shown in FIGS. 1 and 6, the intermediate rod 40 and the upper rod 4 are moved by the telescopic cylinder 38.
1 is projected to raise the middle tower part 33 and the upper tower part 34, and the work stage 17 is raised to a predetermined position in the furnace central part 109. After that, the motor 6 of the lifting device 66
7 to rotate the lift table 46 up to the lift opening 47 of the lower plate 43 of the work stage 17, and then rotate the turntable 88 by the motor 89 of the lift table 46 to discharge the pallet 26 in the selected delivery direction. Align with the transport direction of the device 49. Then, the roller conveyor 90 horizontally conveys the pallet 26 from the elevating table 46 to the selected dispensing device 49. Since it did in this way, the small motive power of rotating the turntable 88 can direct not only one direction of carrying out the bricks 25 but many directions by the number of the dispensing devices 49. It should be noted that, when the elevating table 46 passes between the base part 31, the lower tower part 32, the middle tower part 33, and the upper tower part 34 when the elevating table 46 is raised, a furnace construction work for the furnace bottom part 11 is performed. As in the case of the time, the guide plate 102 on the elevating table 46 and each of the tower parts 32 to
By the guide roller 104 provided at the lower end of 34,
It is possible to prevent the elevating table 46 from coming into contact with the inner walls of the tower sections 32 to 34 during the ascent.

【0032】次いで、図14に示すように、築炉装置5
7の駆動によりパレット26上の煉瓦25をクランプし
てピックアップし、これを炉中央部109の内壁に下方
位置から順次積み上げる。この際、パレット26上の煉
瓦25がなくなったら、パレット26を昇降台46上に
戻して空洞部35内を下降させ、タワー16の下部に到
達したら、図3に示すように、煉瓦25がなくなったパ
レット26をローラコンベア90によりタワー16の出
口37から第1の搬出コンベア29上に搬出し、それか
ら図1に示すように回収リフタ27、第2の搬出コンベ
ア30を介して外部搬出する一方、煉瓦25が載置され
た新たなパレット26を搬入コンベア28により入口3
6から昇降台46上に載置し、そののち昇降台46を上
昇させてこれを下板43上まで持ち上げる。そこで、タ
ーンテーブル88を回転させて、パレット26の搬出方
向を次に選択された払出し装置49の搬送方向に合わ
せ、パレット26を水平方向に搬出して、同様に築炉装
置57による煉瓦25の敷設作業を行う。これらの作業
は、炉中央部109の内壁の全域に煉瓦25が敷設され
るまで繰り返して行われる。
Next, as shown in FIG.
The bricks 25 on the pallet 26 are clamped and picked up by the drive of No. 7, and they are sequentially stacked on the inner wall of the furnace central portion 109 from the lower position. At this time, when the bricks 25 on the pallet 26 are gone, the pallet 26 is returned to the lift table 46 to lower the inside of the cavity 35, and when it reaches the lower part of the tower 16, as shown in FIG. The pallet 26 is carried out by the roller conveyor 90 from the exit 37 of the tower 16 onto the first carry-out conveyor 29, and then is carried out to the outside via the recovery lifter 27 and the second carry-out conveyor 30 as shown in FIG. A new pallet 26 on which the bricks 25 are placed is transferred to the entrance 3 by the carry-in conveyor 28.
6 is placed on the lift table 46, and then the lift table 46 is raised to lift it onto the lower plate 43. Therefore, the turntable 88 is rotated so that the carrying-out direction of the pallet 26 is aligned with the carrying direction of the next selected dispensing device 49, and the pallet 26 is carried out in the horizontal direction. Perform laying work. These operations are repeated until the bricks 25 are laid on the entire inner wall of the furnace central portion 109.

【0033】なお、煉瓦25の積み上げの進行に応じ
て、作業ステージ17を炉体13の上方位置に固定し直
す場合には、シリンダ54aによりアウトリガ52の脚
部54を一旦引き込ませ、次いでテレスコシリンダ38
により中段ロッド40や上段ロッド41を突出させて作
業ステージ17を所定位置まで上昇させ、そののち再び
アウトリガ52の脚部54を突出させて、これを炉体1
3の内壁に押接させる。炉上部107の築炉作業時は、
テレスコシリンダ38により上段ロッド41をさらに突
出させて、搭乗ステージ18が炉上部107に達するま
で上段タワー部34を上昇させる。次いで、昇降装置6
6のモータ67を回転させて、昇降台46を作業デッキ
63の昇降口65まで上昇させ、そののち前述した炉底
部11の築炉作業時の場合と同様に、作業員がバランサ
63cを手動操作してパレット26上の煉瓦25を炉上
部107の内壁に順次敷設する。
When the work stage 17 is re-fixed to the upper position of the furnace body 13 as the bricks 25 are piled up, the legs 54 of the outriggers 52 are once retracted by the cylinder 54a, and then the telesco cylinder. 38
The middle stage rod 40 and the upper stage rod 41 are thereby projected to raise the work stage 17 to a predetermined position, and then the leg portions 54 of the outriggers 52 are projected again, and this is set in the furnace body 1.
Press it against the inner wall of 3. When constructing the furnace top 107,
The upper rod 41 is further projected by the telescopic cylinder 38, and the upper tower part 34 is raised until the boarding stage 18 reaches the furnace upper part 107. Next, the lifting device 6
The motor 67 of No. 6 is rotated to raise the elevating table 46 to the elevating port 65 of the working deck 63, and then the worker manually operates the balancer 63c in the same manner as in the above-described furnace construction work of the furnace bottom 11. Then, the bricks 25 on the pallet 26 are sequentially laid on the inner wall of the furnace upper part 107.

【0034】このように、複数段のタワー部32〜34
を伸縮自在に連結させた多段筒形のタワー16をテレス
コシリンダ38により昇降させる構造としたので、伸縮
性を有し、かつ荷上げ機構を備えたタワー16を伸縮さ
せる作業の作業性の向上を図ることができる。また、テ
レスコシリンダ38によりタワー16を伸長させて、昇
降装置66により煉瓦25を開口部12より炉体13内
に搬入しながら築炉作業を行うので、炉体13内に収め
られる築炉設備10の部分や煉瓦25の炉体13内への
持ち込みが容易になって築炉作業の作業性の向上が図れ
る。しかも、この煉瓦25の炉体13内への搬入は、タ
ワー16の空洞部35内を昇降する昇降台46により行
われるので、煉瓦25の持ち上げ中に荷崩れを起こして
も煉瓦25はタワー16内を落下するだけでタワー16
の外に落ちることはなく、このため周囲の装置を破損さ
せたり、作業員が怪我をするなどの事故を防止できる。
また、炉体13内に挿入される築炉設備10の部分を分
割式にしたので、床面から炉底部11までの高さが十分
とれない炉体13であっても、この築炉設備10の炉体
13内への挿入部分を簡単に炉体13内に挿入すること
ができる。さらに、タワー16の上部に作業ステージ1
7と搭乗ステージ18を選択的に組み付けるようにした
ので、炉体13の部位に応じて、作業員による作業と築
炉装置57による作業を選択して築炉作業を行うことが
できる。
As described above, a plurality of tower sections 32 to 34 are provided.
Since the multi-stage cylindrical tower 16 in which the towers are elastically connected is moved up and down by the telescopic cylinder 38, the workability of the work of expanding and contracting the tower 16 having elasticity and having a loading mechanism is improved. Can be planned. Further, since the tower 16 is extended by the telescopic cylinder 38 and the brick 25 is carried into the furnace body 13 through the opening 12 by the elevating device 66, the furnace building work is performed while the furnace 25 is installed in the furnace body 13. It is easy to bring the part and the bricks 25 into the furnace body 13, and the workability of the furnace construction work can be improved. Moreover, since the bricks 25 are carried into the furnace body 13 by the elevating table 46 that ascends and descends in the cavity 35 of the tower 16, even if a load collapse occurs while the bricks 25 are being lifted, the bricks 25 are not removed. Tower 16 just by falling inside
Therefore, it is possible to prevent accidents such as damage to surrounding devices and injury of workers.
Further, since the portion of the furnace building equipment 10 to be inserted into the furnace body 13 is of a split type, even if the furnace body 13 does not have a sufficient height from the floor surface to the furnace bottom portion 11, this furnace building equipment 10 It is possible to easily insert the insertion part of the above into the furnace body 13. In addition, the work stage 1 is installed on the upper part of the tower 16.
Since 7 and the boarding stage 18 are selectively assembled, it is possible to perform the furnace building work by selecting the work by the worker and the work by the furnace building device 57 according to the site of the furnace body 13.

【0035】本発明は前記実施例に限定されるのもので
はなく、例えば実施例では本発明のタワー設備を築炉設
備に採用したが、その他タワーを備えて高所において作
業を行うどのような設備にも適用できる。また、実施例
では、築炉される炉体として転炉を例示したが、例えば
電気炉のような内壁に煉瓦が敷設される炉体であれば炉
の種類は限定されない。さらに、実施例では、作業ステ
ージと搭乗ステージはタワーから分離できる構造にして
いるが、床面から炉底部までの高さが十分にとれる炉体
であれば、作業ステージと搭乗ステージはタワーに固定
されていてもよい。
The present invention is not limited to the above-mentioned embodiment. For example, in the embodiment, the tower equipment of the present invention is adopted for the furnace construction equipment. It can also be applied to equipment. Further, in the embodiment, the converter is illustrated as the furnace body to be constructed, but the type of furnace is not limited as long as it is a furnace body in which bricks are laid on the inner wall such as an electric furnace. Further, in the embodiment, the work stage and the boarding stage are structured so that they can be separated from the tower, but if the furnace body has a sufficient height from the floor to the furnace bottom, the work stage and the boarding stage are fixed to the tower. It may have been done.

【0036】[0036]

【発明の効果】本発明に係るタワー設備のタワー昇降機
構は、複数段の筒形部材を伸縮自在に連結させた多段筒
形のタワーを多段チューブ型シリンダにより昇降させる
構造にしたので、伸縮性を有し、かつ荷上げ機構を備え
たタワーを伸縮させる作業の作業性の向上を図ることが
できる。しかも、この被搬送物の炉体内への搬入は、タ
ワーの空洞部内を昇降する昇降台により行われるので、
被搬送物の持ち上げ中に荷崩れを起こしても被搬送物は
タワー内を落下するだけでタワーの外に落ちることはな
く、このため周囲の装置を破損させたり、作業員が怪我
をするなどの事故を防止できる。また、基台部に開口さ
れた搬送口は、必ずテレスコシリンダにより最先に上昇
された下段タワー部の上昇時に開口されるので、タワー
を伸長させて作業を行う際には必ず被搬送物をこの搬送
口からタワーの上部の作業ステージまで持ち上げること
ができる。
The tower lifting mechanism for tower equipment according to the present invention has a structure in which a multi-stage tubular tower in which a plurality of stages of tubular members are elastically connected is moved up and down by a multi-stage tube cylinder. It is possible to improve the workability of the work of expanding and contracting the tower having the above and having the loading mechanism. Moreover, since the carried object is carried into the furnace, it is carried out by the elevating table which ascends and descends in the cavity of the tower.
Even if a load collapse occurs during lifting of the transported object, the transported object only falls inside the tower and does not fall out of the tower, which damages the surrounding devices and injures workers. Can prevent accidents. In addition, the transfer port opened on the base is always opened when the lower tower part, which was raised first by the telescopic cylinder, is lifted. It can be lifted from this transfer port to the work stage above the tower.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施例に係るタワー設備のタワー昇
降機構を適用した築炉設備の使用状態を説明する断面図
である。
FIG. 1 is a cross-sectional view illustrating a usage state of furnace construction equipment to which a tower lifting mechanism for tower equipment according to an embodiment of the present invention is applied.

【図2】同移動台の平面図である。FIG. 2 is a plan view of the mobile table.

【図3】同タワー内への煉瓦の搬送中の要部断面図であ
る。
FIG. 3 is a cross-sectional view of an essential part during the transfer of bricks into the tower.

【図4】同作業ステージの平面図である。FIG. 4 is a plan view of the work stage.

【図5】(a) 同作業ステージにおけるアウトリガの
収納状態を説明する要部断面図である。 (b) 同作業ステージにおける回動デッキの収納状態
を説明する要部断面図である。
FIG. 5 (a) is a cross-sectional view of relevant parts for explaining the stored state of the outriggers on the work stage. (B) It is an important section sectional view explaining the storing state of the rotation deck in the work stage.

【図6】同使用状態を説明する断面図である。FIG. 6 is a cross-sectional view illustrating the same usage state.

【図7】同昇降装置の平面図である。FIG. 7 is a plan view of the lifting device.

【図8】同搭乗ステージおよび昇降装置の正面図であ
る。
FIG. 8 is a front view of the boarding stage and the lifting device.

【図9】同搭乗ステージおよび昇降台の断面図である。FIG. 9 is a cross-sectional view of the boarding stage and the lift.

【図10】同昇降台の正面図である。FIG. 10 is a front view of the lifting table.

【図11】同昇降台の要部側面図である。FIG. 11 is a side view of a main part of the elevator.

【図12】同タワーの要部拡大断面図である。FIG. 12 is an enlarged sectional view of a main part of the tower.

【図13】同タワーの伸長状態を説明する要部拡大側面
図である。
FIG. 13 is an enlarged side view of an essential part for explaining the extension state of the tower.

【図14】同使用状態を説明する要部断面図である。FIG. 14 is a cross-sectional view of an essential part for explaining the same usage state.

【符号の説明】[Explanation of symbols]

10 築炉設備(タワー設備) 11 炉底部 12 開口部 13 炉体 14 レール 15 移動台車 16 タワー 17 作業ステージ 18 搭乗ステージ(作業ステージ) 19 台車本体 20 2階部 21 階段 22 運転室 23 連結部 24 車輪 25 煉瓦(被搬送物) 26 パレット 27 回収リフタ 28 搬入コンベア 29 第1の搬出コンベア 30 第2の搬出コンベア 31 基台部 32 下段タワー部(筒形部材) 33 中段ワター部(筒形部材) 34 上段タワー部(筒形部材) 35 空洞部 36 入口(搬送口) 37 出口(搬送口) 38 テレスコシリンダ(多段チューブ型シリンダ) 39 下段ロッド 40 中段ロッド 41 上段ロッド 42 連結部 43 下板 44 上板 45 支柱 45a シリンダ 45b ロッド 46 昇降台 47 昇降口 48 昇降口 49 払出し装置 50 回動デッキ 50a シリンダ 50b ロッド 50c スライドデッキ 51 ローラコンベア 52 アウトリガ 53 本体 54 脚部 54a シリンダ 54b ロッド 55 足場板 56 溝部 57 築炉装置 58 アーム 59 クランプ部 60 支柱 61 台板 62 支柱 63 作業デッキ 63a 台部 63b 手すり 63c バランサ 64 昇降口 65 昇降口 66 昇降装置 67 モータ 68 シャフト軸 69 ギヤ 70 ギヤ 71 ドラム 72 回転軸 73 軸受 74 ワイヤ 75 ギヤ 76 ギヤ 77 軸受 78 回転軸 79 スプロケット 80 スプロケット 81 チェーン 82 スナップアイドル 83 ストッパ 84 ロッド 85 下段部 86 支柱 87 上段部 88 ターンテーブル 89 モータ 90 ローラコンベア 91 回転軸 92 軸受 93 旋回スラスト軸受 94 傘歯車 95 傘歯車 96 スリップリング 98 前後フレーム 99 左右フレーム 100 滑車 101 左右フレーム 102 ガイド板 103 切欠部 104 ガイドローラ 105 受け筒 106 ケーブルベア 107 炉上部 108 炉口部 109 炉中央部 110 クレーン 111 フォークリフト車 10 Furnace Construction Equipment (Tower Equipment) 11 Furnace Bottom 12 Opening 13 Furnace Body 14 Rail 15 Mobile Truck 16 Tower 17 Working Stage 18 Boarding Stage (Working Stage) 19 Truck Main Body 20 Second Floor 21 Stairs 22 Operator's Room 23 Connection 24 Wheels 25 Brick (conveyed object) 26 Pallet 27 Recovery lifter 28 Carry-in conveyor 29 First carry-out conveyor 30 Second carry-out conveyor 31 Base part 32 Lower tower part (cylindrical member) 33 Middle watter part (cylindrical member) 34 Upper Tower Part (Cylindrical Member) 35 Cavity Part 36 Inlet (Conveyor Port) 37 Outlet (Conveyor Port) 38 Telesco Cylinder (Multistage Tube Type Cylinder) 39 Lower Rod 40 Middle Rod 41 Upper Rod 42 Connecting Part 43 Lower Plate 44 Upper Plate 45 Strut 45a Cylinder 45b Rod 46 Lifting platform 47 Lifting port 48 Ascending Mouth 49 Discharge device 50 Rotating deck 50a Cylinder 50b Rod 50c Sliding deck 51 Roller conveyor 52 Outrigger 53 Main body 54 Leg 54a Cylinder 54b Rod 55 Scaffolding board 56 Groove 57 Construction furnace 58 Arm 59 Clamping section 60 Strut 61 Stand board 62 Strut 63 Working Deck 63a Platform 63b Handrail 63c Balancer 64 Elevating Port 65 Elevating Port 66 Elevating Device 67 Motor 68 Shaft Shaft 69 Gear 70 Gear 71 Drum 72 Rotating Shaft 73 Bearing 74 Wire 75 Gear 76 76 Gear 77 Bearing 78 Rotating Shaft 79 Sprocket 80 Sprocket 81 Chain 82 Snap Idle 83 Stopper 84 Rod 85 Lower Stage 86 Strut 87 Upper Stage 88 Turntable 89 Motor 90 Roller Conveyor 91 Rotating Shaft 92 Bearings 93 Swiveling thrust bearings 94 Bevel gears 95 Bevel gears 96 Slip rings 98 Front / rear frames 99 Left / right frames 100 Pulleys 101 Left / right frames 102 Guide plates 103 Notches 104 Guide rollers 105 Receptacles 106 Cable bears 107 Tops of furnaces 108 Furnace mouths 109 Center of furnaces Department 110 Crane 111 Forklift truck

───────────────────────────────────────────────────── フロントページの続き (72)発明者 山口 博文 福岡県北九州市八幡東区山王1丁目9番10 号 九築工業株式会社内 (72)発明者 木元 丈志 福岡県北九州市戸畑区大字中原46−59 新 日本製鐵株式会社機械プラント事業部内 (72)発明者 芝田 寿一 愛知県東海市東海町5−3 新日本製鐵株 式会社名古屋製鐵所内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Hirofumi Yamaguchi 1-9-10 Sanno, Yawatahigashi-ku, Kitakyushu City, Fukuoka Prefecture, Kuki Construction Co., Ltd. (72) Takeshi Kimoto, Nakahara, Tobata-ku, Kitakyushu, Fukuoka 46-59 Nippon Steel Co., Ltd. Machinery Plant Division (72) Inventor Juichi Shibata 5-3 Tokai-cho, Tokai City, Aichi Prefecture Nippon Steel Co., Ltd. Nagoya Steel Works

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 被搬送物の搬送口が開口された筒形の基
台部内に複数段の筒形部材を伸縮自在に設けた多段筒形
のタワーと、該タワーの周囲に均等に配設されて、多段
チューブ形のロッドを有する複数個の多段チューブ型シ
リンダと、前記タワーの上部に設けられた作業ステージ
と、前記タワー内の空洞部を昇降して、前記基台部の搬
送口よりタワー内に搬入された被搬送物を前記作業ステ
ージまで持ち上げる昇降台と、前記タワーに設けられ
て、前記昇降台を昇降させる昇降装置とを備えたタワー
設備のタワー昇降機構であって、前記タワーの各段の筒
形部材と、前記多段チューブ型シリンダの各段のロッド
とを、それぞれ対応する段ごとに連結させたことを特徴
とするタワー設備のタワー昇降機構。
1. A multi-stage tubular tower in which a plurality of stages of tubular members are extendably and retractably provided in a tubular base portion having an opening for transporting an object to be transported, and the towers are evenly arranged around the tower. Then, a plurality of multi-stage tube type cylinders having multi-stage tube type rods, a work stage provided in the upper part of the tower, and a cavity part in the tower are moved up and down, from a transfer port of the base part. A tower lifting mechanism for tower equipment, comprising: a lifting platform that lifts an object carried into a tower to the work stage; and a lifting device that is provided in the tower and that lifts the lifting platform. The tower elevating mechanism of tower equipment, characterized in that the tubular member of each stage and the rod of each stage of the multi-stage tube type cylinder are connected for each corresponding stage.
JP4280575A 1992-09-24 1992-09-24 Tower lifting mechanism for tower equipment Expired - Lifetime JP2645782B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4280575A JP2645782B2 (en) 1992-09-24 1992-09-24 Tower lifting mechanism for tower equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4280575A JP2645782B2 (en) 1992-09-24 1992-09-24 Tower lifting mechanism for tower equipment

Publications (2)

Publication Number Publication Date
JPH06109375A true JPH06109375A (en) 1994-04-19
JP2645782B2 JP2645782B2 (en) 1997-08-25

Family

ID=17626947

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4280575A Expired - Lifetime JP2645782B2 (en) 1992-09-24 1992-09-24 Tower lifting mechanism for tower equipment

Country Status (1)

Country Link
JP (1) JP2645782B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114458065A (en) * 2022-01-10 2022-05-10 广东省气象探测数据中心 Integrated liftable meteorological tower platform

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114458065A (en) * 2022-01-10 2022-05-10 广东省气象探测数据中心 Integrated liftable meteorological tower platform

Also Published As

Publication number Publication date
JP2645782B2 (en) 1997-08-25

Similar Documents

Publication Publication Date Title
US5018923A (en) Automated bricklaying apparatus
US5419669A (en) Installation for lining an internal wall of an enclosure with brickwork
US3679071A (en) Apparatus for use in lining vessels
JP2691834B2 (en) Furnace construction equipment
US2933918A (en) Method of lining furnaces
JP2645782B2 (en) Tower lifting mechanism for tower equipment
JP3100522B2 (en) Furnace tower equipment
JP2558181Y2 (en) Mounting structure of tower elevating mechanism of tower equipment
JP2645784B2 (en) Connection structure between tower of tower equipment and tower elevating mechanism
JP2645783B2 (en) Assembly structure of work deck of tower equipment
JP2558180Y2 (en) Furnace tower equipment with outriggers on top
JP3841242B2 (en) Elevator parking elevating work table and construction method using it
JP2545756Y2 (en) Slide structure of the slide deck of tower equipment
JPH0140086B2 (en)
JPH05113026A (en) Temporary scaffold structure
JP2558182Y2 (en) Tower equipment height maintenance device
JP2558183Y2 (en) Automatic connection device of power transmission system of elevator platform of tower equipment
JPH079156B2 (en) Segment transfer device
JP4518982B2 (en) Brick arranging apparatus and method for converter
JP3046552B2 (en) Blast furnace furnace construction method
JP3216400B2 (en) Multi-level parking device
JP2691836B2 (en) Power transmission structure for stage installation equipment of tower equipment
CN118495301B (en) A construction cargo elevator convenient for transporting materials
JPH11292483A (en) Swivel work platform
JP3786385B2 (en) Elevating work table and assembly method of parking equipment using it

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19970304

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080509

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080509

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090509

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100509

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100509

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110509

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120509

Year of fee payment: 15

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130509

Year of fee payment: 16

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130509

Year of fee payment: 16

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

EXPY Cancellation because of completion of term
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130509

Year of fee payment: 16

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130509

Year of fee payment: 16