JPH04194295A - Method for building underground structure with movable timbering - Google Patents

Method for building underground structure with movable timbering

Info

Publication number
JPH04194295A
JPH04194295A JP32727890A JP32727890A JPH04194295A JP H04194295 A JPH04194295 A JP H04194295A JP 32727890 A JP32727890 A JP 32727890A JP 32727890 A JP32727890 A JP 32727890A JP H04194295 A JPH04194295 A JP H04194295A
Authority
JP
Japan
Prior art keywords
movable
shoring
pipe roof
support
underground structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP32727890A
Other languages
Japanese (ja)
Inventor
Shigeki Kitagawa
北川 滋樹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP32727890A priority Critical patent/JPH04194295A/en
Publication of JPH04194295A publication Critical patent/JPH04194295A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To stabilize support and to shorten a work executing time by erecting first - third moving timbering each, formed in a state that a support beam is elevated, in a pipe roof, and excavating a bedrock simultaneously with building of an underground structure. CONSTITUTION:First moving timbering 20A formed such that a support beam 33 is elevatable by means of a jack 30 is erected on the frontmost part of a part where a bedrock 1 inside a pipe roof 2 is excavated. Second moving timbering 20B is erected in the vicinity of the first moving timbering, and a third moving timbering 20C is erected with a distance therebetween to support the pipe roof 2. Simultaneously with excavation of the bedrock 1 in front of the moving timbering 20A, an underground structure 10 is built in the rear of the third moving timbering 20C. Through movement of each of the moving timbering 20A-20C, the pipe roof 2 is supported and excavation and building are repeated. This method carries out safe and easy execution of a work.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、パイプルーフにより、地山の変形を防止して
、 トンネルなどの地下構造物を構築する方法に関する
DETAILED DESCRIPTION OF THE INVENTION [Industrial Application Field] The present invention relates to a method of constructing underground structures such as tunnels by using a pipe roof to prevent deformation of the ground.

〔従来の技術〕[Conventional technology]

従東 トンネルなどの地下構造物を構築するのに、構築
のため掘削すべき部分の外周に沿って、鋼管で形成され
た多数のパイプを地山内に挿入二そして、前記挿入した
多数のパイプにより、地下構造物の外形に合ったパイプ
ルーフを形成し そして、パイプルーフの内側の地山を
掘削して、地下構造物を構築する方法がある。
To construct an underground structure such as a tunnel, a large number of steel pipes are inserted into the ground along the outer periphery of the part to be excavated for construction. There is a method of constructing an underground structure by forming a pipe roof that matches the external shape of the underground structure, and then excavating the ground inside the pipe roof.

前記方法は、前記パイプルーフを、支保工で支承しなが
ら、パイプルーフの内側の地山を掘削する。この繰り返
しによりこのパイプルーフ内の掘削を完了した部分に、
地下構造物を構築する。
The method involves excavating the ground inside the pipe roof while supporting the pipe roof with shoring. By repeating this process, the part of the pipe roof that has been excavated will be
Build underground structures.

そして、パイプルーフを支承していた支保工1戯その部
分の地下構造物を構築するか、或は、支保工を撤去しな
がら、支保工の一部を地下構造物中に埋め込んでいる。
Then, an underground structure is built in that part of the shoring that supported the pipe roof, or a part of the shoring is buried in the underground structure while the shoring is removed.

また、地下構造物を、前記の掘削、支保工架設、構乳 
及び、支保工撤去を履行しながら構築して、施工を行っ
ている。
In addition, underground structures can be constructed through the above-mentioned excavation, shoring erection, and embankment construction.
Furthermore, construction is being carried out by constructing and removing the shoring.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

前記従来のパイプルーフによる地下構造物の構築物の構
築方法のうち、坑内支保工架設は、困難な作業で、さら
に、支保工を撤去する方法は、構築を早くしようとして
、支保工を撤去しながら地下構造物の構築を行うように
すると、撤去作業が難しくなる。
Among the conventional methods for constructing underground structures using pipe roofs, the erection of underground supports is a difficult task, and the method of removing the supports involves removing the supports while trying to speed up construction. If underground structures are constructed, removal work becomes difficult.

また、支保工を地下構造物中に埋め込む方法は、地下構
造物中に埋設される鉄筋と、支保工との関連もあり、構
成が複雑となりコストも高くなる。
Furthermore, in the method of embedding shoring in an underground structure, there is a relationship between the reinforcing bars buried in the underground structure and the shoring, resulting in a complicated structure and high cost.

さらに、前記のようにして実施しても、なお地山の掘削
後に、地下構造物の構築を行うものであるので、施工に
長時間を要するものであり九本発明は、前記事項に鑑み
なされたものであり、パイプルーフによる地下構造物の
構築を、簡単で安全に、かつ、施工時間が短縮できるよ
うにすることを技術的課題とする。
Furthermore, even if carried out as described above, since the underground structure is constructed after excavating the ground, the construction takes a long time. The technical challenge is to make the construction of an underground structure using a pipe roof simple, safe, and shorten the construction time.

〔課題を解決するための手段〕[Means to solve the problem]

本発明は、掘削すべき地山1の外周に沿ってパイプ3を
挿入して、構築すべき地下構造物10の外形に合ったパ
イプルーフ2を形成し、このパイプルーフ2を支保工で
支承して、パイプルーフ2の内側の地山1を掘削する地
下構造物10の構築方法において、 パイプルーフ2の内側の地山1を掘削した部分の最前部
に、枠製に形成すると共に、受桁33をジヤツキ30に
より昇降可能に構成した第1の可動支保工20Aを立設
し この第1の可動支保工20Aに接近して、同様の構
成の第2の可動支保工20Bを立設し、第2の可動支保
工20Bと間隔を置いて、同様の構成の第3の可動支保
工20Cを立設して、前記のパイプルーフ2を支障させ
、前記第1の可動支保工20Aの前方で、地山1を掘削
すると共に、第3の可動支保工20Cの後方で、地下構
造物10を構築し 次に、第1の可動支保工20Aを、
地山1を掘削した部分の前方に移動させて、パイプルー
フ2を支承させ、次へ第2の可動支保工20Bを、第1
の可動支保工20Aに接近した位置に移動させて、前記
パイプルーフ2を支承させると共に、第3の可動支保工
20Cを、第2の可動支保工20Bと間隔を置いた位置
に移動させて、前記パイプルーフ2を支承させ、第1の
可動支保工20Aの前方の地山1を掘削すると共に、第
3の可動支保工20Cの後方で地下構造物10を構築す
る可動支保工による地下構造物の構築方法として。
The present invention involves inserting a pipe 3 along the outer periphery of a ground 1 to be excavated, forming a pipe roof 2 that matches the external shape of an underground structure 10 to be constructed, and supporting this pipe roof 2 with shoring. In the method for constructing an underground structure 10 in which the ground 1 inside the pipe roof 2 is excavated, the ground 1 inside the pipe roof 2 is formed of a frame at the forefront of the excavated part, and a receiving plate is formed. A first movable support 20A with a girder 33 that can be raised and lowered by a jack 30 is erected, and a second movable support 20B with a similar configuration is erected close to the first movable support 20A. , a third movable support 20C having a similar configuration is erected at a distance from the second movable support 20B, and obstructs the pipe roof 2, so that the structure is placed in front of the first movable support 20A. Then, the ground 1 is excavated, and the underground structure 10 is constructed behind the third movable support 20C. Next, the first movable support 20A is
The earth 1 is moved to the front of the excavated part to support the pipe roof 2, and then the second movable support 20B is moved to the front of the excavated part.
moving the third movable shoring 20C to a position close to the movable shoring 20A to support the pipe roof 2, and moving the third movable shoring 20C to a position spaced apart from the second movable shoring 20B, An underground structure using movable shoring that supports the pipe roof 2, excavates the ground 1 in front of the first movable shoring 20A, and constructs the underground structure 10 behind the third movable shoring 20C. As a construction method.

〔イ乍用〕[For use]

本発明は、第1の可動支保工20Aの前方の地山1を掘
削しながら、同時に第3の可動支保工20Cの後方で、
地下構造物の構築が行われて、施工の時間が短縮される
In the present invention, while excavating the ground 1 in front of the first movable support 20A, at the same time behind the third movable support 20C,
Underground structures are constructed, reducing construction time.

また、可動支保工20の移動は、前方に順次送り込まれ
るので安全に短時間で移動される。
Furthermore, the movable support 20 is moved forward in sequence, so it can be moved safely in a short time.

〔実施例〕〔Example〕

第1図ないし第6図は、本発明の一実施例の可動支保工
による地下構造物の構築方法の説明用の図である。
1 to 6 are diagrams for explaining a method of constructing an underground structure using a movable support according to an embodiment of the present invention.

この実施例は、図示してない立坑の側壁から鋼管製のパ
イプ3を多数、地山の掘削すべき部分の外周に沿って角
形に挿入する。
In this embodiment, a large number of steel pipes 3 are inserted from the side wall of a shaft (not shown) in a rectangular shape along the outer periphery of a portion of the earth to be excavated.

そして、この挿入した多数のパイプ3で、パイプルーフ
2を形成する。そして、前記パイプ3は、前記立坑の側
壁からパイプ3の端部を突出させて置くか、又は、挿入
したパイプ3の端の内側の地山1を少し掘削する。
Then, a pipe roof 2 is formed by a large number of inserted pipes 3. Then, the pipe 3 is placed so that the end of the pipe 3 protrudes from the side wall of the shaft, or the ground 1 inside the inserted end of the pipe 3 is slightly excavated.

次を気 前記パイプ3の範 すなわち、パイプルーフ2
の端の内側に第1の可動支保工20A1 及び、第2の
可動支保工20Bを接近して挿入立設して、前記パイプ
ルーフ2を支承させる。
Take care of the following: the area of the pipe 3, that is, the pipe roof 2
A first movable support 20A1 and a second movable support 20B are inserted and erected close to each other inside the end of the pipe roof 2 to support the pipe roof 2.

そして、前記第1の可動支保工20Aと第2の可動支保
工20B、及び、後記する第3の可動支保工20Cは、
第5図に示すようへ 対向して設けた2本の支柱24の
上部と下部&へ 上部連結材22と下部連結材23を連
結して4角形の枠体21を形成している。
The first movable support 20A, the second movable support 20B, and the third movable support 20C to be described later are:
As shown in FIG. 5, an upper connecting member 22 and a lower connecting member 23 are connected to form a rectangular frame 21.

そして、前記枠体21の角部に1 第1補強材25を取
り付け、枠体21の上部連結材22の上部には、2個の
ジヤツキ30を介して受桁33が設けである。
A first reinforcing member 25 is attached to the corner of the frame 21, and a support girder 33 is provided on the upper part of the upper connecting member 22 of the frame 21 via two jacks 30.

そして、バイブルーフ2内に立設される各可動支保工2
0間に番戴  第2補強材26が平行状態を保つように
設けである。
Each movable support 2 erected inside the vibe roof 2
The second reinforcing member 26 is provided between the two and the second reinforcing member 26 is provided so as to maintain a parallel state.

前記のようにして、パイプルーフ2の端&へ 第1の可
動支保工20Aと第2の可動支保工20Bを挿入し ジ
ヤツキ30を伸長させて支承した、パイプルーフ2の端
部の内側の地山1を、所定の間隔で掘削する。
As described above, the first movable support 20A and the second movable support 20B are inserted into the end of the pipe roof 2, and the ground inside the end of the pipe roof 2, which is supported by extending the jack 30, is inserted into the end of the pipe roof 2. Mountain 1 is excavated at predetermined intervals.

次に、前記第1の可動支保工20Aのジヤツキ30を縮
小させて、第1の可動支保工20Aを、所定の間隔だけ
前方に移動させて、ジヤツキ30を伸長させ、パイプル
ーフ2を支承させ、続いて第2の可動支保工20Bを同
様にて、第1の可動支保工20Aに接近してた位置に移
動させて、パイプルーフ2を支承させる。
Next, the jacks 30 of the first movable shoring 20A are reduced, the first movable shoring 20A is moved forward by a predetermined distance, the jacks 30 are extended, and the pipe roof 2 is supported. Then, the second movable shoring 20B is similarly moved to a position close to the first movable shoring 20A to support the pipe roof 2.

次に、パイプルーフ2の端へ 第3の可動支保工20C
を挿入して立設し  バイブルーフ2を支承させて、第
1の可動支保工20Aの前方の他山1を掘削する。
Next, move the third movable support 20C to the end of the pipe roof 2.
is inserted and erected to support the vibration roof 2, and the other mountain 1 in front of the first movable support 20A is excavated.

そして、第1の可動支保工20Aを、前記と同様にして
、所定間隔前方に移動させて、バイブルーフ2を支承さ
せ、続いて同様にして第2の可動支保工ZOBを、前記
第1の可動支保工20Aに接近した位置に移動させて、
パイプルーフ2を支承させ、次に、第3の可動支保工2
0Cを、前記第2の可動支保工20Bと間隔を置いた位
置に移動させて、パイプルーフ2を支承させる。
Then, in the same manner as described above, the first movable shoring 20A is moved forward by a predetermined distance to support the vibe roof 2, and then in the same manner, the second movable shoring ZOB is moved forward by a predetermined distance. Move it to a position close to the movable support 20A,
The pipe roof 2 is supported, and then the third movable support 2
0C is moved to a position spaced apart from the second movable support 20B to support the pipe roof 2.

以上のようにして、地下構造物10の構築の準備が完了
する。前記の準備完了状態が、第1図から鉄筋11を除
いた状態である。
In the manner described above, preparations for constructing the underground structure 10 are completed. The above-mentioned ready state is the state in which the reinforcing bars 11 are removed from FIG.

そして、地下構造物10の構築は、次のようにして行う
The underground structure 10 is constructed as follows.

すなわち、第1図に示す第1の可動支保工20Aの前方
で、パイプルーフ2内の地山lを、第2図に示すように
掘削すると共に、第1図に示すよう&ミ 第3図の可動
支保工20Cの後方で、バイブルーフ2内に鉄筋11を
配置し 第2図に示すように型板12を配置して、第3
図に示すようへ地下構造物10を構築する。
That is, in front of the first movable support 20A shown in FIG. 1, the ground l inside the pipe roof 2 is excavated as shown in FIG. Behind the movable support 20C, the reinforcing bars 11 are placed inside the vibe roof 2, and the template 12 is placed as shown in Fig. 2.
An underground structure 10 is constructed as shown in the figure.

次&ミ 第1の可動支保工20Aのジヤツキ30を縮小
して、第3図に示すように、バイブルーフ2内の地山1
を掘削した部分の前方にに移動させ、ジヤツキ30を伸
長して、第1の可動支保工20Aで、前記パイプルーフ
2を支承させる。
Next & Mi The jack 30 of the first movable support 20A is reduced and the ground 1 in the vibe roof 2 is
is moved to the front of the excavated part, the jack 30 is extended, and the pipe roof 2 is supported by the first movable support 20A.

次へ 第4図に示すように、−第2の可動支保工ZOB
を、第1の可動支保工20Aに接近した位置に、同様に
して移動させて、パイプルーフ2を支承させると共に、
第3の可動支保工20Cを、前記第2の可動支保工20
Bから間隔を置いた位置に、同様にして移動させて、パ
イプルーフ2を支承させる。
Next As shown in Figure 4, - the second movable support ZOB
is similarly moved to a position close to the first movable shoring 20A to support the pipe roof 2, and
The third movable support 20C is replaced by the second movable support 20C.
Similarly, it is moved to a position spaced apart from B to support the pipe roof 2.

そして、前記第2の可動支保工20Bと第3の可動支保
工20Cの移動+1  第2の可動支保工20Bを移動
させて、パイプルーフ2を支承させた後、第3の可動支
保工20Cを移動させる方法のほかに、地山1の状態に
より、第2の可動支保工20Bと第3の可動支保工20
Cを同時に移動させることも可能である。
Then, after moving the second movable shoring 20B and the third movable shoring 20C +1 to support the pipe roof 2, the third movable shoring 20C is moved. In addition to the method of moving, depending on the state of the ground 1, the second movable support 20B and the third movable support 20
It is also possible to move C at the same time.

さらに、第3の可動支保工20Cを先に移動させて、パ
イプルーフ2を支承させた後&ミ 第2の可動支保工2
0Bを移動させる方法もある。
Furthermore, after moving the third movable support 20C first and supporting the pipe roof 2, the second movable support 20C is moved.
There is also a method of moving 0B.

前記第4図に示す状態で、さらに、第1の可動支保工2
0Aの前方の地山1を掘削すると共シミ第3の可動支保
工20Cの後方で、地下構造物10を構築し、以下前記
施工を繰り返して行う。
In the state shown in FIG. 4, the first movable support 2
When the ground 1 in front of 0A is excavated, an underground structure 10 is constructed behind the third movable support 20C, and the above construction is repeated.

〔発明の効果〕〔Effect of the invention〕

本発明は、パイプルーフ2内!、  枠型に形成すると
共&ミ 受桁33をジヤツキ30により昇降状態に構成
した、第1の可動支保工20A、第2の可動支保工20
B、及び、第3の可動支保工20Cを立設してパイプル
ーフ2を支承獣 パイプルーフ2内の他山lの掘削は、
第1の可動支保工20Aの前方で行い、地下構造物10
の構築は、第3の可動支保工20Cの後方で行うように
したものである。
This invention is inside the pipe roof 2! The first movable support 20A and the second movable support 20 are formed into a frame shape and have a receiving girder 33 raised and lowered by a jack 30.
B, and the third movable support 20C is erected to support the pipe roof 2. Excavation of the other mountain l inside the pipe roof 2 is as follows:
Performed in front of the first movable support 20A, underground structure 10
The construction is carried out behind the third movable support 20C.

したがって、他出1の掘削と、地下構造物10の構築を
同時に行うことができ施工時間を短縮できるものである
Therefore, the excavation and construction of the underground structure 10 can be performed at the same time, and the construction time can be shortened.

また、可動支保工zOのうち、少なくとも1つの可動支
保工20頃 常にパイプルーフ2を支承して、他の可動
支保工20を、順に前方に移動させるものである。
Furthermore, among the movable supports zO, at least one movable support 20 always supports the pipe roof 2, and the other movable supports 20 are sequentially moved forward.

したがって、パイプルーフ2を、安定して支承できると
共に、支保工の装着及び取り除きがきわめて簡単である
Therefore, the pipe roof 2 can be supported stably, and the shoring can be installed and removed very easily.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図ないし第6図は、本発明の一実施例の可動支保工
による地下構造物の構築方法の説明用の図で、第1図な
いし第4図は地山の掘削と地下構造物の構築状態を示す
云 第5図は可動支保工の正面A 第6図はパイプルー
フと地下構造物の断面図である。 1 地山、 2 パイプルーフ、 3−パイプ、10・
地下構造物、2o・可動支保工、20A・・第1の可動
支保工、 20B・第2の可動支保工、 20C・第3の可動支保工、 30 ・ジヤツキ、 33 受桁。
Figures 1 to 6 are explanatory diagrams of a method for constructing an underground structure using a movable support according to an embodiment of the present invention. Figure 5 shows the construction state. Figure 5 is a front view of the movable support. Figure 6 is a sectional view of the pipe roof and underground structure. 1. Earth, 2. Pipe roof, 3. Pipe, 10.
Underground structure, 2o, movable shoring, 20A...first movable shoring, 20B, second movable shoring, 20C, third movable shoring, 30, jack, 33 support girder.

Claims (1)

【特許請求の範囲】[Claims] (1)掘削すべき地山1の外周に沿ってパイプ3を挿入
して、構築すべき地下構造物10の外形に合ったパイプ
ルーフ2を形成し、このパイプルーフ2を支保工で支承
して、パイプルーフ2の内側の地山1を掘削する地下構
造物10の構築方法において、 パイプルーフ2の内側の地山1を掘削した部分の最前部
に、枠型に形成すると共に、受桁33をジャッキ30に
より昇降可能に構成した第1の可動支保工20Aを立設
し、この第1の可動支保工20Aに接近して、同様の構
成の第2の可動支保工20Bを立設し、第2の可動支保
工20Bと間隔を置いて、同様の構成の第3の可動支保
工20Cを立設して、前記のパイプルーフ2を支承させ
、前記第1の可動支保工20Aの前方で、地山1を掘削
すると共に、第3の可動支保工20Cの後方で、地下構
造物10を構築し、次に、第1の可動支保工20Aを、
地山1を掘削した部分の前方に移動させて、パイプルー
フ2を支承させ、次に、第2の可動支保工20Bを、第
1の可動支保工20Aに接近した位置に移動させて、前
記パイプルーフ2を支承させると共に、第3の可動支保
工20Cを、第2の可動支保工20Bと間隔を置いた位
置に移動させて、前記パイプルーフ2を支承させ、第1
の可動支保工20Aの前方の地山1を掘削すると共に、
第3の可動支保工20Cの後方で地下構造物10を構築
する可動支保工による地下構造物の構築方法。
(1) Insert the pipe 3 along the outer circumference of the ground 1 to be excavated to form a pipe roof 2 that matches the external shape of the underground structure 10 to be constructed, and support this pipe roof 2 with shoring. In the method for constructing an underground structure 10 in which the ground 1 inside the pipe roof 2 is excavated, the ground 1 inside the pipe roof 2 is formed into a frame shape at the forefront of the excavated part, and a receiving girder is A first movable shoring structure 20A, in which the movable supporting structure 33 can be raised and lowered by a jack 30, is erected, and a second movable shoring structure 20B, which has a similar structure, is erected close to this first movable shoring structure 20A. , a third movable shoring 20C having a similar configuration is erected at a distance from the second movable shoring 20B to support the pipe roof 2, and is placed in front of the first movable shoring 20A. Then, while excavating the ground 1, the underground structure 10 is constructed behind the third movable shoring 20C, and then the first movable shoring 20A is
The earth 1 is moved to the front of the excavated part to support the pipe roof 2, and then the second movable support 20B is moved to a position close to the first movable support 20A. While supporting the pipe roof 2, the third movable shoring 20C is moved to a position spaced apart from the second movable shoring 20B to support the pipe roof 2, and the first
While excavating the ground 1 in front of the movable support 20A,
A method for constructing an underground structure using a movable support, in which the underground structure 10 is constructed behind the third movable support 20C.
JP32727890A 1990-11-28 1990-11-28 Method for building underground structure with movable timbering Pending JPH04194295A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP32727890A JPH04194295A (en) 1990-11-28 1990-11-28 Method for building underground structure with movable timbering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP32727890A JPH04194295A (en) 1990-11-28 1990-11-28 Method for building underground structure with movable timbering

Publications (1)

Publication Number Publication Date
JPH04194295A true JPH04194295A (en) 1992-07-14

Family

ID=18197342

Family Applications (1)

Application Number Title Priority Date Filing Date
JP32727890A Pending JPH04194295A (en) 1990-11-28 1990-11-28 Method for building underground structure with movable timbering

Country Status (1)

Country Link
JP (1) JPH04194295A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012026106A (en) * 2010-07-21 2012-02-09 Kajima Corp Execution method of underground structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012026106A (en) * 2010-07-21 2012-02-09 Kajima Corp Execution method of underground structure

Similar Documents

Publication Publication Date Title
CN111188629B (en) Construction method for sudden change of tunnel bifurcation section and expanding excavation
WO2015007133A1 (en) Temporary supporting and permanent supporting parallel operation excavating technology for crawler-type hydraulic combination bracket and equipment using same
CN208885287U (en) Circumferential direction digs shield mechanism
JPH035600A (en) Method and device for constructing branch and connection part of shield tunnel and its segment
JPH04194295A (en) Method for building underground structure with movable timbering
JP2762133B2 (en) How to build a large architectural space underground
JPH0464697A (en) Construction of tunneling space
KR101967167B1 (en) The Method of Constructing Non-excavation Type Tunnel
JPH0460019A (en) Master pile horizontal sheet-pile method
JPH112095A (en) Method for tunnel constructing work
JPS61186623A (en) Method of building foundation of building
CN113882429B (en) Construction method and construction structure of underground structure
JPS62220616A (en) Construction work for underground space
JPH0726877A (en) Construction method of underground structure
JPH0396600A (en) Constructing method for building large space in large-depth underground section
JPS60226917A (en) Underground excavation work
JPH03279598A (en) Construction method of large section or superlarge section of tunnel
JPH0216291A (en) Constructing of shield tunnel requiring no shaft
JP2003278160A (en) Simplified landslide protection wall construction method
JPS6322916A (en) Construction of continuous underground wall in artificial islet
JP2005194764A (en) Tunnel connecting method
JPH04194224A (en) Advancing method for open shield machine and device thereof
CN113550753A (en) Construction method of crossing middle partition wall with through upper step in advance
JPH06346698A (en) Construction method of underground space
JP2799343B2 (en) Replacement method of middle pillar in lining of multiple tunnels