JPH0355612B2 - - Google Patents

Info

Publication number
JPH0355612B2
JPH0355612B2 JP11202486A JP11202486A JPH0355612B2 JP H0355612 B2 JPH0355612 B2 JP H0355612B2 JP 11202486 A JP11202486 A JP 11202486A JP 11202486 A JP11202486 A JP 11202486A JP H0355612 B2 JPH0355612 B2 JP H0355612B2
Authority
JP
Japan
Prior art keywords
hollow
pile
hole
concrete
mortar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP11202486A
Other languages
Japanese (ja)
Other versions
JPS62268423A (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP11202486A priority Critical patent/JPS62268423A/en
Publication of JPS62268423A publication Critical patent/JPS62268423A/en
Publication of JPH0355612B2 publication Critical patent/JPH0355612B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、アースアンカー兼用地中杭の施工
法に関するものである。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a method of constructing an underground pile that also serves as an earth anchor.

〔従来技術とその問題点〕[Prior art and its problems]

地中杭によつて建造物を支える場合、地中杭B
は建造物の正の荷重を支持するものである。
When supporting a structure with underground piles, underground piles B
supports the positive loads of the structure.

しかし、最近では、地下構造物の有効利用が非
常に多くなつて来ており、負の荷重である浮力に
対する対応が問題になつている。従来、一般的な
浮力対策としては、建造物の荷重が浮力を上まわ
る正の荷重にすることにより対応している。また
浮力は、常に一定ではなく水位差により変化す
る。そこで杭を設計する時は、浮力が最小の時を
想定して行われているのが現状であり、第1図a
のように基礎Aなどの地下駆体を大きくしたり、
またスパンを小さくすることにより対応していた
が、地下構造物が巨大化してコストアツプとなつ
ていた。
However, in recent years, effective use of underground structures has become very common, and how to deal with buoyancy, which is a negative load, has become an issue. Conventionally, a common measure against buoyancy has been to make the load of the building a positive load that exceeds the buoyancy. Also, buoyancy is not always constant and changes depending on the water level difference. Therefore, when designing piles, the current situation is to assume that the buoyancy is at its minimum, as shown in Figure 1a.
Increasing the size of underground structures such as foundation A,
In addition, the problem was solved by reducing the span, but the underground structure became huge and the cost increased.

また地震時の震動によつて建造物が揺れた場
合、傾いた側の地中杭Bには、正の荷重が作用
し、反応側の地中杭Bには、負の荷重が作用する
ことになる。(第2図参照) このような場合にも負の荷重への対応が重要で
あつた。
In addition, when a building shakes due to vibrations during an earthquake, a positive load acts on the underground pile B on the tilted side, and a negative load acts on the underground pile B on the reactive side. become. (See Figure 2) In such cases, it was also important to deal with negative loads.

以上のような場合の地中杭Bは、正の荷重を支
えるだけでなく、負の荷重に抵抗するアースアン
カーが必要となる。そこで単なるアースアンカー
としのてものではなく、アースアンカー兼用の地
中杭が非常に都合が良いが、施工が難しい。
The underground pile B in the above case requires an earth anchor that not only supports positive loads but also resists negative loads. Therefore, it is very convenient to use underground piles that also serve as earth anchors, rather than simply using them as earth anchors, but they are difficult to construct.

〔問題点を解決するための手段〕[Means for solving problems]

この発明にかかるアースアンカー兼用地中杭
は、地中に先端部を拡底した削孔を形成して、該
削孔内の先端部にモルタル若しくはコンクリート
を打設して、その孔内に中空パイルを降下し、該
中空パイルの中空部を通つてPC鋼材の下部に取
り付けたアンカー部をまだ固まらない削孔先端部
のモルタル若しくは、コンクリートに埋設し、一
方中空パイル上部にコンクリート基礎の受圧部を
構築した後、PC鋼材を緊張してプレストレス力
を導入し、中空パイルの中空部にモルタル若しく
はコンクリートを注入するものである。
The underground pile that also serves as an earth anchor according to the present invention is provided by forming a hole in the ground with an enlarged tip, pouring mortar or concrete into the tip of the hole, and installing a hollow pile in the hole. The anchor part attached to the lower part of the prestressing steel material through the hollow part of the hollow pile is buried in the mortar or concrete at the tip of the drilled hole that has not hardened yet, while the pressure receiving part of the concrete foundation is placed in the upper part of the hollow pile. After construction, the prestressing force is applied by tensioning the prestressing steel, and mortar or concrete is injected into the hollow part of the hollow pile.

既成中空パイルを使用するための施工が容易で
ある。
Construction is easy because it uses prefabricated hollow piles.

中空パイルの中空部を利用してPC鋼材を降下
するため、削孔内壁の崩壊が生じず確実に削孔底
部まで降下が可能である。
Since the prestressing steel material is lowered using the hollow part of the hollow pile, it is possible to reliably descend to the bottom of the borehole without collapsing the inner wall of the borehole.

複数本の中空パイルを使用してもプレストレス
力によつて一体化し、また中実断面になるので、
長期的にも且つ強固な地中杭となる。
Even if multiple hollow piles are used, they will be integrated by prestressing force and will have a solid cross section, so
It becomes a long-lasting and strong underground pile.

〔実施例〕〔Example〕

以下、図に示す一実施例に基づきこの発明を詳
細に説明する。
Hereinafter, the present invention will be explained in detail based on an embodiment shown in the drawings.

〈1〉 削孔の形成(第3図、a,b) 地中に削孔機1によつて削孔2を形成する。
削孔2は、支持層3まで至るようにし、支持層
3に削孔した先端部4は、上部よりも径を拡大
する。削孔機1の注入パイプを使用して削孔2
の先端部4にモルタル若しくは、コンクリート
5を打設する。
<1> Formation of a drilled hole (FIG. 3, a, b) A drilled hole 2 is formed underground using a driller 1.
The hole 2 is made to reach the support layer 3, and the diameter of the tip 4 drilled in the support layer 3 is larger than that of the upper part. Drilling hole 2 using injection pipe of hole drilling machine 1
Mortar or concrete 5 is placed on the tip 4 of the holder.

〈2〉 中空パイルの降下(第3図、c,d) 削孔2内に既成の中空パイル6を降下する。
中空パイル6は、中心に中空部7が貫通された
円筒形状である。中空パイル6は、単数でも複
数でもよく、最下端となる部分は底部4に至ら
せる。
<2> Lowering the hollow pile (Fig. 3, c, d) The ready-made hollow pile 6 is lowered into the drilled hole 2.
The hollow pile 6 has a cylindrical shape with a hollow portion 7 passing through the center. The hollow pile 6 may be singular or plural, and the lowermost portion thereof reaches the bottom portion 4.

〈3〉 PC鋼材の降下(第3図、e,f) 下端にアンカー部8であるアンカー金物が取
付けられたPC鋼材9を押し下げパイプ11に
保護させながら中空部7を通つて削孔最下端の
まだ固まらないモルタル若しくはコンクリート
5内の所定の位置に埋設する。(第4図、a,
b) PC鋼材9としては、PC鋼線、PC鋼より線、
PC鋼棒または、アンポントPC鋼線等が使用で
きる。アンカー部8上には、定着部の支圧補強
用のスパイラル筋10が取り付けられている。
削孔2内壁は、中空パイル6によつて崩壊が防
げられるため押し下げパイプ11に保護された
PC鋼線9の降下は容易である。
<3> Lowering of the PC steel material (Fig. 3, e, f) The PC steel material 9, to which the anchor hardware that is the anchor part 8 is attached to the lower end, is pushed down and protected by the pipe 11, passing through the hollow part 7 and lowering it to the bottom of the drilling hole. It is buried at a predetermined position in mortar or concrete 5 that has not yet hardened. (Figure 4, a,
b) As the PC steel material 9, PC steel wire, PC steel stranded wire,
PC steel rods or ampont PC steel wires can be used. A spiral reinforcement 10 for reinforcing the bearing pressure of the fixing part is attached to the anchor part 8.
The inner wall of the drilled hole 2 was protected by the push-down pipe 11 because the hollow pile 6 prevented it from collapsing.
Lowering the PC steel wire 9 is easy.

なお、押し下げパイプ11とともにグラウト
注入パイプ12を中空部7内を降下させ、注入
パイプ12下端は、削孔口の底部4近くまで降
下させる。
In addition, the grout injection pipe 12 is lowered in the hollow part 7 together with the push-down pipe 11, and the lower end of the injection pipe 12 is lowered to near the bottom 4 of the drilling hole.

〈4〉 プレストレス力導入(第3図、g,h) 第5図に示すように、中空パイル6上端にキ
ヤツプ13を被せ、PC鋼材9とグラウト注入
パイプ12を突出させる。PC鋼材9の上端に
は、シース14を被せ、シース14の中間部か
ら泥水排出パイプ15を連続させる。中空パイ
ル6上には、受圧部16である、マツトスラ
プ、あるいは基礎Aを構築する。その後PC鋼
材9を緊張してプレストレス力を導入し、くさ
び等の端部金物によつて定着する。PC鋼材9
によつてマツトスラブ、あるいは基礎を支持層
3に固定するとともに、プレストレス力によつ
て複数本の中空パイル6,6を一体化する。
<4> Introduction of prestress force (Fig. 3, g, h) As shown in Fig. 5, the cap 13 is placed on the upper end of the hollow pile 6, and the PC steel material 9 and the grout injection pipe 12 are made to protrude. The upper end of the PC steel material 9 is covered with a sheath 14, and a muddy water discharge pipe 15 is connected to the middle part of the sheath 14. On the hollow pile 6, a pine slab or foundation A, which is a pressure receiving part 16, is constructed. Thereafter, the PC steel material 9 is tensioned to introduce a prestress force, and is fixed using end metal fittings such as wedges. PC steel material 9
The pine slab or the foundation is fixed to the support layer 3 by the pine slab, and the plurality of hollow piles 6, 6 are integrated by the prestressing force.

グラウト注入パイプ12からモルタル等18
を中空内に充填するとともに注入することによ
り、削孔時の泥水を底部から押し上げ、泥水パ
イプ15から泥水を排水する。
From grout injection pipe 12 to mortar etc. 18
By filling and injecting into the hollow, muddy water during drilling is pushed up from the bottom and drained from the muddy water pipe 15.

〔発明の効果〕〔Effect of the invention〕

この発明は、以上のような構成を有し、以下の
ような効果を得ることができる。
The present invention has the above configuration and can obtain the following effects.

(イ) この発明により施工したアースアンカー兼用
地中杭によれば、正の荷重とともに、負の荷重
も支え、地下水による浮力や地震時の杭の引抜
き力に対しても建造物を安定させることができ
る。(第1図b参照) (ロ) 既成の中空パイルを使用するため施工が容易
である。
(a) According to the underground pile that doubles as an earth anchor constructed according to the present invention, it can support not only positive loads but also negative loads, and stabilize buildings against the buoyancy of groundwater and the pull-out force of the piles during earthquakes. I can do it. (See Figure 1b) (b) Construction is easy because ready-made hollow piles are used.

(ハ) 削孔内壁の崩れを中空パイルによつて防げる
ため削孔内へPC鋼材を容易に降下できる。
(c) Since the hollow pile prevents the inner wall of the borehole from collapsing, the PC steel material can be easily lowered into the borehole.

(ニ) プレストレス力を導入して複数本の中空パイ
ルを一体化し、またモルタル等の充填によつて
中実断面となり、強固な地中杭とすることがで
きる。
(d) By introducing prestressing force, multiple hollow piles can be integrated, and by filling with mortar, etc., a solid cross-section can be obtained, making it possible to create a strong underground pile.

【図面の簡単な説明】[Brief explanation of drawings]

第1図a,bは従来例と本発明の一実施例の浮
力を受けた状態を比較した概略図、第2図は本発
明の一実施例の地震時の概略図、第3図a.〜hは
本発明の一実施例のの施工順序縦断面図、第4図
a,bはアンカー部の削孔底部への埋設状態の縦
断面図、第5図はPC鋼材の定着部の縦断面図で
ある。 1……削孔機、2……削孔、3……支持層、4
……底部、5……モルタル若しくはコンクリー
ト、6……中空パイル、7……中空部、8……ア
ンカー部、9……PC鋼材、10……スパイラル
筋、11……押し下げパイプ、12……グラウト
注入パイプ、13……キヤツプ、14……シー
ス、15……泥水排出パイプ、16……受圧部、
17……端部金物、18……モルタル。
Figures 1a and b are schematic diagrams comparing the conventional example and an embodiment of the present invention under buoyancy, Figure 2 is a schematic diagram of an embodiment of the present invention during an earthquake, and Figure 3a. -h are longitudinal cross-sectional views of the construction sequence according to an embodiment of the present invention, Fig. 4 a and b are longitudinal cross-sectional views of the anchor part buried in the bottom of the drilled hole, and Fig. 5 is a longitudinal cross-sectional view of the anchoring part of the prestressing steel material. It is a front view. 1... Hole drilling machine, 2... Hole drilling, 3... Support layer, 4
... Bottom, 5 ... Mortar or concrete, 6 ... Hollow pile, 7 ... Hollow part, 8 ... Anchor part, 9 ... PC steel, 10 ... Spiral reinforcement, 11 ... Push down pipe, 12 ... Grout injection pipe, 13... Cap, 14... Sheath, 15... Mud water discharge pipe, 16... Pressure receiving part,
17... End hardware, 18... Mortar.

Claims (1)

【特許請求の範囲】[Claims] 1 地中に先端部を拡底し、該拡底部分にモルタ
ル若しくはコンクリートを打設した削孔を形成し
て該削孔内に中空パイルを降下し、該中空パイル
の中空部を通つてPC鋼材下部に取り付けたアン
カーをまだ固まらない削孔先端部のモルタル若し
くはコンクリートに埋設し、一方、中空パイルの
上部にコンクリート基礎の受圧部を構築した後、
PC鋼材を緊張して、プレストレス力を導入し、
中空パイルの中空部にモルタル若しくはコンクリ
ートを注入することを特徴とするアースアンカー
兼用地中杭の施工法。
1. The bottom of the tip is widened in the ground, a hole is formed by pouring mortar or concrete into the bottom part, and a hollow pile is lowered into the hole, and the lower part of the PC steel material is passed through the hollow part of the hollow pile. bury the anchor attached to the hole in the mortar or concrete at the tip of the drilled hole that has not hardened yet, and on the other hand, after constructing the pressure receiving part of the concrete foundation on the top of the hollow pile,
Tension the PC steel material, introduce prestress force,
A method of constructing an underground pile that also serves as an earth anchor, characterized by injecting mortar or concrete into the hollow part of the hollow pile.
JP11202486A 1986-05-16 1986-05-16 Construction work of underground pile used in common for earth anchor Granted JPS62268423A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11202486A JPS62268423A (en) 1986-05-16 1986-05-16 Construction work of underground pile used in common for earth anchor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11202486A JPS62268423A (en) 1986-05-16 1986-05-16 Construction work of underground pile used in common for earth anchor

Publications (2)

Publication Number Publication Date
JPS62268423A JPS62268423A (en) 1987-11-21
JPH0355612B2 true JPH0355612B2 (en) 1991-08-23

Family

ID=14576083

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11202486A Granted JPS62268423A (en) 1986-05-16 1986-05-16 Construction work of underground pile used in common for earth anchor

Country Status (1)

Country Link
JP (1) JPS62268423A (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07103559B2 (en) * 1990-02-05 1995-11-08 株式会社大林組 Construction method for steel pipe piles
US7070362B2 (en) * 2002-01-22 2006-07-04 Henning Baltzer Rasmussen Reinforcement unit for a reinforcing a footing element when laying pile foundations with a pile, and method for placing a foundation pile and reinforcement of a footing element
JP5207047B2 (en) * 2008-07-30 2013-06-12 清水建設株式会社 Seismic reinforcement method for existing foundation and seismic reinforcement structure for existing foundation
JP5684069B2 (en) * 2011-08-05 2015-03-11 大成建設株式会社 Pile structure
TWI634249B (en) * 2017-05-24 2018-09-01 潤弘精密工程事業股份有限公司 Method for forming underground construction and underground construction formed thereby

Also Published As

Publication number Publication date
JPS62268423A (en) 1987-11-21

Similar Documents

Publication Publication Date Title
CA2623014A1 (en) Method and apparatus for increasing the force needed to move a pile axially
US5050356A (en) Immured foundation
US4293242A (en) Piles
CN110777836A (en) Reinforced concrete plate-anchor rod composite foundation and using method thereof
CA2551712C (en) Void form for constructing post-tensioned foundation piles
US20080008539A1 (en) Void form for constructing post-tensioned foundation piles
JPH0355612B2 (en)
US4588327A (en) Precast concrete pile and method of placing it in the ground
US5429455A (en) Integrated column and pile
RU2089706C1 (en) Pile frozen into permafrost and method of erection of pile frozen into permafrost
GB2085950A (en) Driven composite piles
US20050019104A1 (en) Soil stabilization and pile formation method
JPH1082057A (en) Method of earthquake-resisting pile foundation construction
JPS62268424A (en) Underground pile used in common for earth anchor
KR100441966B1 (en) Applying Method of Casing as the Concrete Filled Tube
RU219607U1 (en) Concrete screw pile
JPS6311715A (en) Construction of earth anchor-concrete pile
JP2508563B2 (en) Support pile structure for large span structures
RU2760287C1 (en) Method for erecting a mooring structure on a rock base and an element of a mooring structure on a rock base obtained by this method
JP2002146780A (en) Steel pipe for concrete composite pile and method of building steel-pipe concrete composite pile
JPH05171638A (en) Construction method of pile used as drawing yield strength
KR100627691B1 (en) Foundation for Steel tower and method thereof
JP3519375B2 (en) Cast-in-place pile construction method just below the existing foundation
KR200255715Y1 (en) Anchorage of earth anchor in steel pipe pile for pull-out resistance in the water
US20060115333A1 (en) Soil stabilization and pile formation method