JPH0333320A - Landslide protection wall technique - Google Patents
Landslide protection wall techniqueInfo
- Publication number
- JPH0333320A JPH0333320A JP16581489A JP16581489A JPH0333320A JP H0333320 A JPH0333320 A JP H0333320A JP 16581489 A JP16581489 A JP 16581489A JP 16581489 A JP16581489 A JP 16581489A JP H0333320 A JPH0333320 A JP H0333320A
- Authority
- JP
- Japan
- Prior art keywords
- bedrock
- excavated
- ground
- anchors
- face
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims description 9
- 238000009412 basement excavation Methods 0.000 claims abstract description 15
- 239000004575 stone Substances 0.000 abstract description 5
- 238000010276 construction Methods 0.000 description 7
- 230000000694 effects Effects 0.000 description 3
- 230000000087 stabilizing effect Effects 0.000 description 3
- 238000009415 formwork Methods 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Retaining Walls (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
【発明の詳細な説明】
〔産業上の利用分野〕
この発明は掘削した地山面の安定化を図る山留工法に関
するもので、特に長大な掘削地山の安定化を図るための
山留工法に関するものである。[Detailed Description of the Invention] [Field of Industrial Application] This invention relates to a retaining method for stabilizing the surface of an excavated ground, and in particular, a retaining method for stabilizing a long excavated ground. It is related to.
高さが高く長大な地山の山留を行う場合、上方から下方
まで一気に掘削してしまい、その後山留構造物を掘削地
山面に沿って設置する方法が採用されている。When retaining a long and high ground, the method used is to excavate from the top to the bottom all at once, and then install retaining structures along the surface of the excavated ground.
しかし大きな掘削面を掘削した後、土留構造物の固定を
完了するまで掘削地山は不安定な状態であり、この地山
面の下で作業をするのは極めて大きな危険を伴っていた
。However, after excavating a large excavation surface, the excavated ground remains unstable until the earth retaining structure is fixed, and it is extremely dangerous to work under this ground surface.
また掘削地山が崩壊しようとするとき構造物の背面にか
かる圧力を全て構造物によって支えようとすると、構造
物に大きな強度を要求しなければならなかった。In addition, if the structure is to support all the pressure exerted on the back of the structure when the excavated ground is about to collapse, the structure must have great strength.
この発明は以上のような課題を解決するためになされた
もので、安全な施工が可能であり、また土留構造物に大
きな強度を必ずしも要求することがない山留工法を提供
することを目的とする。This invention was made in order to solve the above-mentioned problems, and the purpose is to provide a mountain retaining method that allows safe construction and does not necessarily require large strength of the earth retaining structure. do.
この発明にかかる山留工法は、地山を掘削するのに伴っ
て順次仮留めするものである。The mountain retaining method according to the present invention is one in which temporary retaining is performed sequentially as the ground is excavated.
長大な掘削面を山留めする場合、上方から下方に向って
複数段階に分けて掘削する。つまり所定高さづつ順次掘
削していくもので、その掘削ごとに仮留めする。When retaining a long excavated surface, the excavation is done in multiple stages from the top to the bottom. In other words, the tunnel is excavated one after another to a predetermined height, and temporary fixing is performed after each excavation.
まず各段階ごとに地山面からアンカーを打設する。この
アンカーに、地山面に沿って配設した縦梁を固定し、縦
梁によって地山面の崩壊を防ぐ。縦梁としてはコンクリ
ート製の柱状体が考えられ、既製のものを使用してもよ
いし、また現場にて型枠を組んでコンクリートを打設し
て構築してもよい。First, anchors are driven from the ground surface at each stage. A vertical beam placed along the ground surface is fixed to this anchor, and the vertical beam prevents the ground surface from collapsing. Concrete columnar bodies can be considered as the vertical beams, and ready-made ones may be used, or they may be constructed by assembling formwork and pouring concrete on site.
この縦梁による仮留めの状態で、順次下方へ掘削、仮留
めを繰り返して長大地山面を掘削する。With this vertical beam temporarily secured, a long mountain face is excavated by repeatedly excavating downward and temporarily securing.
掘削完了後、既設のコンクリートパネルなどの土留構造
物を掘削面に沿って起立する。この土留構造物を前記し
たアンカーに固定する。土留構造物と地山との間には隙
間を設けておき、土砂や砕石を詰めてもよい。After excavation is complete, earth retaining structures such as existing concrete panels will be erected along the excavation surface. This earth retaining structure is fixed to the above-mentioned anchor. A gap may be provided between the earth retaining structure and the ground and filled with earth and sand or crushed stone.
土留構造物上に更に土留構造物を積み上げてアンカーに
固定し、掘削地山全面の山留めを完了する。Further earth retaining structures are stacked on top of the earth retaining structures and fixed to anchors to complete the retaining of the entire excavated ground.
以下、図に示す一実施例に基づき、この発明の詳細な説
明する。Hereinafter, the present invention will be described in detail based on an embodiment shown in the drawings.
まず、地山を計画線に沿って上方から所定高さづつ複数
段階に分けて掘削する。この掘削ごとに掘削地山面lか
らアンカー2を地山に向って打設する。アンカー2は様
々な構成のものが採用できるが、鋼より線を削札内に挿
入し硬化材によって固定する地山アンカーを使用する。First, the ground is excavated from above along a planned line in multiple stages at predetermined heights. For each excavation, the anchor 2 is driven toward the ground from the excavated ground surface l. Although various configurations can be adopted for the anchor 2, a ground anchor is used in which a steel strand is inserted into the tag and fixed with a hardened material.
このアンカー2に′#1梁3を固定する。縦梁3は地山
面に沿って配筋して型枠を組み、吹付はコンクリートを
打設して構築する。縦梁3は実施例では柱状体に形成し
ている。前記したアンカー2の地山からの突出部分はこ
の縦梁3を貫通させて、ナ・/ト4などによって固定す
る。(第2図)アンカー2の地山からの突出部分は充分
長くとっておく。The '#1 beam 3 is fixed to this anchor 2. The vertical beams 3 are constructed by arranging reinforcement along the ground surface, constructing a formwork, and pouring concrete. In the embodiment, the vertical beam 3 is formed into a columnar body. The protruding portion of the anchor 2 from the ground passes through the vertical beam 3 and is fixed with a nut 4 or the like. (Figure 2) The part of the anchor 2 that protrudes from the ground should be long enough.
このように上方の掘削地山面を縦梁3で仮留めして崩壊
を防ぎ、更に下方を掘削する。(第3図)この掘削した
地山も前記したと同様に縦梁3にて仮留めする。(第4
図)
その後掘削、仮留めを繰り返して地山全面を計画通り掘
削する。(第5.6図)
掘削地山面1に沿って土留構造物である既製の土留めパ
ネル5を起立する。この土留めパネル5に前記したアン
カー2の地山からの突出部分を通して、ナツト6等によ
って固定する。土留パネル5としては、実施例では円弧
状のアーチ部7と、この前面に棚状の補強部8を有する
土留パネル5を使用する。アンカー2は土留パネル5の
両端に通して固定する。In this way, the upper excavated ground surface is temporarily fixed with the vertical beams 3 to prevent collapse, and the lower part is further excavated. (Fig. 3) This excavated ground is also temporarily secured with vertical beams 3 in the same manner as described above. (4th
Figure) After that, excavation and temporary fixing are repeated to excavate the entire surface of the ground as planned. (Fig. 5.6) A ready-made earth retaining panel 5, which is an earth retaining structure, is erected along the excavated earth surface 1. The protruding portion of the anchor 2 from the ground is passed through the soil retaining panel 5 and fixed with a nut 6 or the like. As the retaining panel 5, in the embodiment, a retaining panel 5 having an arcuate arch portion 7 and a shelf-like reinforcing portion 8 on the front surface thereof is used. The anchors 2 are passed through both ends of the retaining panel 5 and fixed.
土留パネル5と掘削地山面lとの間に地山からの水を排
水するための砕石9を詰める。(第7図)
この土留パネル5上に順次土留パネル5を積み上げてア
ンカー2に固定し、砕石9を詰める。Crushed stone 9 for draining water from the earth is packed between the earth retaining panel 5 and the excavated earth surface l. (FIG. 7) The earth retaining panels 5 are stacked one after another on top of the earth retaining panels 5, fixed to the anchors 2, and crushed stones 9 are filled.
(第8図)
以上のような作業を繰り返して掘削地山1全面を土留パ
ネル5によって覆う。(Fig. 8) By repeating the above operations, the entire surface of the excavated ground 1 is covered with the retaining panels 5.
土留構造物としては上記のような形状の土留パネル5に
限らず、平板状のパネル等様々なものが使用できる。The earth retaining structure is not limited to the earth retaining panel 5 having the shape described above, but various types such as flat panels can be used.
この発明は以上のような構成によって以下の効果を得る
ことができる。With the above configuration, the present invention can obtain the following effects.
■ 地山を上方から下方に向って複数段階に分けて掘削
し、この各段階ごとに縦梁によって掘削地山面の仮留め
をすることができ、施工中に地山の崩壊の危険が小さく
、安全な作業ができる。■ The ground can be excavated in multiple stages from top to bottom, and the surface of the excavated ground can be temporarily secured using vertical beams at each stage, reducing the risk of the ground collapsing during construction. , can work safely.
@ 縦梁を永久構造物として設計すれば、それだけ土留
構造物に作用する背圧は小さく、土留構造物自体の強度
を余り大なものにする必要なく、軽量な構造物が使用で
きそれだけ安価に作用できる。また縦梁に土留荷重の全
てに近い荷重を分担させることもでき、設計上の対応幅
があり、土留工法としては現場の条件に応じた最適の設
計ができ、理想的である。@ If the vertical beam is designed as a permanent structure, the back pressure acting on the earth retaining structure will be smaller, and there will be no need to increase the strength of the earth retaining structure itself, allowing the use of lighter structures and lower costs. It can work. In addition, it is possible to have the longitudinal beams share almost all of the earth retaining load, and there is a wide range of design flexibility, making it ideal as an earth retaining method as it allows for optimal design according to site conditions.
■ 縦梁を設置することによって、地山掘削面の凹凸を
均し、この縦梁を土留構造物設置のための枕である基礎
梁として使用することができる。そのため土留構造物の
設置が正確かつ容易に可能となる。■ By installing vertical beams, unevenness on the ground excavation surface can be smoothed out, and these vertical beams can be used as foundation beams that serve as pillows for installing earth retaining structures. Therefore, the earth retaining structure can be installed accurately and easily.
■ 以上のような効果により、従来極めて困難とされた
鉛直地山の山留めも極めて安全かつ容易に行えるように
なる。■ Due to the above-mentioned effects, it is now possible to secure vertical ground, which was previously considered extremely difficult, extremely safely and easily.
■ この工法により従来確立されていなかった長大な地
山を山留めする出留め工事で、上方から順に堀削して安
定化させながら下方まで堀削し、その後下方から順に土
留構造物を積み上げる逆打ち工法的な施工が可能となる
。■ This construction method is used to hold back a long ground that has not been previously established, and involves excavating from the top to the bottom while stabilizing it, and then stacking earth retaining structures from the bottom. Construction method-based construction becomes possible.
第1図〜第8図はこの発明の一実施例の施工順序断面図
、第9図は山留め完了時の横断面図、第1O図は施工状
態の斜視図である。
1・・・掘削地山面、2・・・アンカー、3・・・縦梁
、4・・・ナツト、5・・・土留めパネル、6・・・ナ
ツト、7・・・アーチ部、
8・・・補強部、
9・・・砕石。1 to 8 are sectional views in the construction sequence of an embodiment of the present invention, FIG. 9 is a cross sectional view when the heaping is completed, and FIG. 1O is a perspective view of the construction state. 1... Excavation ground surface, 2... Anchor, 3... Vertical beam, 4... Nut, 5... Earth retaining panel, 6... Nut, 7... Arch part, 8 ... Reinforcement part, 9... Crushed stone.
Claims (2)
削し、各段階ごとに地山掘削面からアンカーを打設し、
掘削面に沿って配設した縦梁をこのアンカーに固定して
地山の崩壊を防止し、下端まで掘削した後下方から順次
土留構造物を掘削面に沿って起立して前記アンカーに固
定し、掘削面に沿って土留構造物を積み上げてなる山留
工法。(1) Excavate the ground in multiple stages from above to below, and drive anchors from the ground excavation surface at each stage.
Vertical beams placed along the excavation surface are fixed to these anchors to prevent the ground from collapsing, and after excavation to the bottom end, earth retaining structures are erected sequentially from below along the excavation surface and fixed to the anchors. , a mountain retaining method in which earth retaining structures are piled up along the excavation surface.
とする請求項(1)記載の山留工法。(2) The mountain retaining method according to claim (1), wherein the vertical beam is a columnar body made of concrete.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP16581489A JPH0663233B2 (en) | 1989-06-28 | 1989-06-28 | Yamadome method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP16581489A JPH0663233B2 (en) | 1989-06-28 | 1989-06-28 | Yamadome method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0333320A true JPH0333320A (en) | 1991-02-13 |
JPH0663233B2 JPH0663233B2 (en) | 1994-08-22 |
Family
ID=15819506
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP16581489A Expired - Lifetime JPH0663233B2 (en) | 1989-06-28 | 1989-06-28 | Yamadome method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0663233B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0641994A (en) * | 1991-08-21 | 1994-02-15 | Oyo Kikaku:Kk | Surface forming method of step gradient banking |
US9295888B2 (en) | 2012-08-09 | 2016-03-29 | Nhk Spring Co., Ltd. | Shaft for golf club having rigidity improved at intermediate part |
-
1989
- 1989-06-28 JP JP16581489A patent/JPH0663233B2/en not_active Expired - Lifetime
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0641994A (en) * | 1991-08-21 | 1994-02-15 | Oyo Kikaku:Kk | Surface forming method of step gradient banking |
US9295888B2 (en) | 2012-08-09 | 2016-03-29 | Nhk Spring Co., Ltd. | Shaft for golf club having rigidity improved at intermediate part |
Also Published As
Publication number | Publication date |
---|---|
JPH0663233B2 (en) | 1994-08-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3226933A (en) | Sheeting wall system and method of constructing same | |
JP3491243B2 (en) | Underground hollow lining structure and lining method | |
JP2000352296A (en) | Method o constructing passage just under underground structure | |
KR20000003270A (en) | Tunnel construction method at area of thin soil surface | |
KR20000058239A (en) | Multi-phased underground construction method for wide excavation using permanent structural members as temporary struts | |
KR20040031451A (en) | Prestressed scaffolding method | |
JP2787806B2 (en) | Earth retaining wall | |
JPH0333320A (en) | Landslide protection wall technique | |
KR102482690B1 (en) | Bridge foundation construction method using formwork integrated PC panels | |
JPH0684690B2 (en) | Building basement extension method | |
KR200308716Y1 (en) | Prestressed scaffolding method | |
JPS63280153A (en) | Underground inverted lining method | |
JPH0336318A (en) | Method of construction for stopping natural ground | |
KR20040051182A (en) | Temporary soil sheathing using prestress and pile thereof | |
JPH0559728A (en) | Sheathing work above underground structure | |
JP7510328B2 (en) | Construction Method | |
JPH04368519A (en) | Anchor retaining wall | |
JPH04115024A (en) | Sheathing method | |
JPH0781274B2 (en) | How to build a beam on an underground wall | |
JPH0325196A (en) | Timbering for excavation | |
KR200308105Y1 (en) | Pile for temporary soil sheathing method using prestress | |
JP2881001B1 (en) | Earth retaining wall construction method for cutting land mountain | |
JPH08302689A (en) | Construction method for skeleton of underground exterior wall | |
JPS63312437A (en) | Construction of underground structure | |
JPH0663235B2 (en) | Soil retaining method |