JPH03132520A - Construction method of basement and column and beam joining body used therefor - Google Patents
Construction method of basement and column and beam joining body used thereforInfo
- Publication number
- JPH03132520A JPH03132520A JP1269969A JP26996989A JPH03132520A JP H03132520 A JPH03132520 A JP H03132520A JP 1269969 A JP1269969 A JP 1269969A JP 26996989 A JP26996989 A JP 26996989A JP H03132520 A JPH03132520 A JP H03132520A
- Authority
- JP
- Japan
- Prior art keywords
- columns
- beams
- tops
- column
- piles
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title 1
- 229910000831 Steel Inorganic materials 0.000 abstract 1
- 238000009412 basement excavation Methods 0.000 abstract 1
- 238000000034 method Methods 0.000 abstract 1
- 238000009417 prefabrication Methods 0.000 abstract 1
- 239000010959 steel Substances 0.000 abstract 1
Abstract
PURPOSE: To rationalize the joining of piles, columns and struts by connecting the lower ends of core columns to the tops of concrete piles, and connecting beams to a prefabricated column and beam joining body which is fitted and inserted from the tops of the core columns to arrange.
CONSTITUTION: Concrete piles 4 are driven up to a specific depth from the surface of the ground, and the lower ends 62 of steel core columns 61 are inserted in the tops 41 of them to connect before they are solidified. After that, a column and beam joining body 10, etc. formed separately of a prefabrication, etc. are fitted and inserted from the tops 63 of the core columns 61 to support them on brackets 64, and concrete 65 work for columns 6 under the brackets can be carried out, while concrete for a connection of floor beams 7 and floor slabs 8 is placed. Then, beams 7A are constructed to the insides of external walls 3, PC beams 71 are arranged to complete the floor beams 7, and excavation work for the next work is carried out. According to the constitution, the joining of piles, columns and struts can be rationalized and, at the same time, the process of work can be reduced.
COPYRIGHT: (C)1991,JPO&Japio
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1269969A JPH07109098B2 (en) | 1989-10-17 | 1989-10-17 | Construction method of basement floor and beam-column joint used for the construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1269969A JPH07109098B2 (en) | 1989-10-17 | 1989-10-17 | Construction method of basement floor and beam-column joint used for the construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH03132520A true JPH03132520A (en) | 1991-06-05 |
JPH07109098B2 JPH07109098B2 (en) | 1995-11-22 |
Family
ID=17479749
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP1269969A Expired - Fee Related JPH07109098B2 (en) | 1989-10-17 | 1989-10-17 | Construction method of basement floor and beam-column joint used for the construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH07109098B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20010097524A (en) * | 2000-04-24 | 2001-11-08 | 배종렬 | Hybrid precast concrete structure and the method of the same |
CN104196032A (en) * | 2014-08-12 | 2014-12-10 | 上海隧道工程有限公司 | Subway station supporting plate and inversed operation combined construction method |
CN113550349A (en) * | 2021-07-24 | 2021-10-26 | 中铁广州工程局集团深圳工程有限公司 | Assembly type subway station and construction method thereof |
-
1989
- 1989-10-17 JP JP1269969A patent/JPH07109098B2/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20010097524A (en) * | 2000-04-24 | 2001-11-08 | 배종렬 | Hybrid precast concrete structure and the method of the same |
CN104196032A (en) * | 2014-08-12 | 2014-12-10 | 上海隧道工程有限公司 | Subway station supporting plate and inversed operation combined construction method |
CN113550349A (en) * | 2021-07-24 | 2021-10-26 | 中铁广州工程局集团深圳工程有限公司 | Assembly type subway station and construction method thereof |
CN113550349B (en) * | 2021-07-24 | 2022-06-28 | 中铁广州工程局集团深圳工程有限公司 | Assembly type subway station and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
JPH07109098B2 (en) | 1995-11-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH02136444A (en) | Construction of composite structure consisting of precast reinforced concrete column and steel structural beam | |
JPH03132520A (en) | Construction method of basement and column and beam joining body used therefor | |
JPH0431573A (en) | Reinforced concrete anti-seismic wall construction | |
JPH04131428A (en) | Construction of underground structure | |
JPH03132521A (en) | Strut construction method of basement floor excavation work | |
JPH02266014A (en) | Constructing underground structure eliminating use of temporary material | |
JPS61266732A (en) | Reverse driving work | |
JPS62137324A (en) | Foundation structure for high building | |
JPH0366852A (en) | Construction method for complex structure of precast reinforced concrete column and steel beam | |
JPH0376929A (en) | Steel-framed foundation | |
JPH04185816A (en) | Construction of beam in underground wall | |
JPS62280414A (en) | Construction work of underground continuous wall | |
JPH03233058A (en) | Precast beam member and execution method of jointing section of columns and beams | |
JPH032435A (en) | Construction method for jointing column and steel frame reinforced-concrete beam to each other | |
JPS6217233A (en) | Foundation base column | |
JPS62273327A (en) | Set caisson work | |
JPS62111028A (en) | Construction of underground structure | |
JPH02236325A (en) | Construction method for super-highrise building | |
JPH04209211A (en) | Construction method of underground structure | |
JPH04149365A (en) | Construction method of beam | |
JPH0381500A (en) | Method for constructing big space for building in great depth underground | |
JPS6245832A (en) | Slope frame work | |
JPH0359223A (en) | Foundation constructing method for reinforced concrete building | |
JPS6347427A (en) | Construction of structure under groundwater | |
JPH02167939A (en) | Construction work of precast steel framed, reinforced concrete structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |