JPH0254067A - Mass concrete construction method - Google Patents

Mass concrete construction method

Info

Publication number
JPH0254067A
JPH0254067A JP20341588A JP20341588A JPH0254067A JP H0254067 A JPH0254067 A JP H0254067A JP 20341588 A JP20341588 A JP 20341588A JP 20341588 A JP20341588 A JP 20341588A JP H0254067 A JPH0254067 A JP H0254067A
Authority
JP
Japan
Prior art keywords
concrete
rubber tube
formwork
mass
mass concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP20341588A
Other languages
Japanese (ja)
Inventor
Shigeru Usami
宇佐美 滋
Hisatoshi Yamazaki
山崎 敞敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP20341588A priority Critical patent/JPH0254067A/en
Publication of JPH0254067A publication Critical patent/JPH0254067A/en
Pending legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、ダム、大規模建物のマツトスラブ。[Detailed description of the invention] [Industrial application field] This invention is a pine slab for dams and large buildings.

厚壁等のように一個所に大量に大塊として打設するマス
コンクリートの施工方法に関するものである。
This relates to a construction method for mass concrete, which is cast in large quantities in one place, such as on thick walls.

〔従来技術およびこの発明が解決すべき課題〕従来この
種のマスコンクリートの施工に際しては、−度に非常に
長く厚(大量のコンクリートを打設して、長大な一体の
大塊状態にすると、所謂マスコンひびわれが発生してし
まい、この対策に苦慮していた。
[Prior Art and Problems to be Solved by the Invention] Conventionally, when constructing this type of mass concrete, it was extremely long and thick (if a large amount of concrete was poured to form a large, long lump, So-called mascon cracks had occurred, and they were struggling to find a solution.

なおここでマスコンひびわれについて説明する。Here, we will explain about the cracks in the mask.

コンクリートの水和熱により、凝固時のマスコンクリー
トは熱膨張する。しかしこれらのマスコンクリートは、
約7日位で外気温程度の温度まで低下、かつ熱収縮する
。マスコンが岩盤上や既設コンクリートに打設されてい
ると、この境界部分は強固に付着し収縮しないが、拘束
の弱い部分が収縮してひびわれが発生する。これが所謂
マスコンひびわれである。
Due to the heat of hydration of concrete, mass concrete thermally expands during solidification. However, these mass concrete
In about 7 days, the temperature drops to about the outside temperature and heat shrinks. When mascon is placed on bedrock or in existing concrete, the boundary portions are firmly attached and do not shrink, but the weakly constrained portions contract and cracks occur. This is the so-called mascon crack.

この発明は前述した事情に鑑みて創案されたもので、そ
の目的はマスコンひびわれが発生することのないマスコ
ンクリートの施工方法を提供することにある。
This invention was devised in view of the above-mentioned circumstances, and its purpose is to provide a method for constructing mass concrete in which cracks in mass concrete do not occur.

〔課題の解決するための手段〕[Means for solving problems]

この発明方法によれば、まずマスコンクリート用の型枠
内の長手方向複数箇所に、前記マスコンクリートの厚み
方向全長へ延びるゴムチューブが前記マスコンクリート
の幅方向に多数本並設してなるゴムチューブ型枠群を配
置する。
According to the method of the present invention, first, a large number of rubber tubes are arranged in parallel in the width direction of the mass concrete, and the rubber tubes extend along the entire length in the thickness direction of the mass concrete at a plurality of locations in the longitudinal direction within a formwork for mass concrete. Place the formwork group.

次にこのゴムチューブ型枠群における各ゴムチューブ内
に空気または水を充填し、各ゴムチューブ間の間隙を塞
いで前記マスコンクリート用の型枠内を前記各ゴムチュ
ーブ型枠群で複数個に分割した後、この型枠内へコンク
リートを打設する。
Next, each rubber tube in this rubber tube form group is filled with air or water, and the gap between each rubber tube is closed, so that the mass concrete form is divided into multiple pieces using each rubber tube form group. After dividing, concrete is poured into the formwork.

その後コンクリート凝固後、前記各ゴムチューブ型枠群
の内部空気または水を抜いて取り外し、その後の空間へ
新たにコンクリートを打設することとする。
After the concrete solidifies, the air or water inside each rubber tube form group is removed and removed, and new concrete is placed in the space provided.

そして−度に大量のコンクリートを打設しても、各ゴム
チューブ型枠群で複数に分割された状態になっており、
一体の長大な大塊状態とならないようにして、所謂マス
コンひびわれが発生しないようにしたものである。
Even when a large amount of concrete is placed at a time, it is divided into multiple pieces by each rubber tube form group.
This is to prevent so-called mascon cracks from occurring by preventing it from becoming one long lump.

〔実施例〕〔Example〕

以下この発明のマスコンクリートの施工方法を図示する
実施例で説明する。
The mass concrete construction method of the present invention will be explained below with reference to illustrated examples.

先ず最初に第1図に示す如く、厚く長大に打設するマス
コンクリート用の配筋作業時におけるマスコンクリート
用の型枠1内に、その長手方向複数箇所へ、マスコンク
リートの厚み方向全長に延びるゴムチューブ2が、マス
コンクリートの幅方向に多数本並設してなるゴムチュー
ブ型枠群3を配置する。
First, as shown in Fig. 1, in the formwork 1 for mass concrete during reinforcement work for thick and long mass concrete, reinforcement is placed at multiple locations in the longitudinal direction of the mass concrete, extending over the entire length of the mass concrete in the thickness direction. A rubber tube form group 3 is arranged in which a large number of rubber tubes 2 are arranged in parallel in the width direction of the mass concrete.

なおこの時に各ゴムチューブ2の支持は、第2図に示す
如く各ゴムチューブ2が一列になるように、型枠1の幅
方向へ延びる2本の支持鉄筋4゜4で挟持して行う、こ
こで符号5は、後述する各ゴムチューブ2への空気また
は水充填時の脹らみに対して、2本の支持鉄筋4.4の
間隔が開かないように設けられる間隔保持筋である。
At this time, each rubber tube 2 is supported by being held between two supporting reinforcing bars 4°4 extending in the width direction of the formwork 1 so that each rubber tube 2 is lined up as shown in FIG. Here, reference numeral 5 denotes a spacing reinforcing bar that is provided so that the spacing between the two supporting reinforcing bars 4.4 does not widen due to swelling when each rubber tube 2 is filled with air or water, which will be described later.

次にこのゴムチューブ型枠群3における各ゴムチューブ
2内に空気または水を充填し、第3図に示す如く各ゴム
チューブ2,2間の間隙を塞いでマスコンクリート用の
型枠1内を各ゴムチューブ型枠群3で複数個に分割した
後、この複数個に分割された型枠1内へ第4図に示す如
くコンクリート6を一度に打設する。この時にコンクリ
ート6の打設は、ゴムチューブ型枠群3を挟んで左右均
等の高さで全長に渡って行う。
Next, each rubber tube 2 in this rubber tube form group 3 is filled with air or water, and the gap between each rubber tube 2 is closed as shown in FIG. After each rubber tube form group 3 is divided into a plurality of pieces, concrete 6 is poured into the formwork 1 divided into a plurality of pieces at once as shown in FIG. At this time, the concrete 6 is placed across the entire length of the rubber tube form group 3 at equal heights on both sides.

その後この分割型枠1内への打設コンクリート6の凝固
後、各ゴムチューブ2内の空気または水を若干抜いて各
ゴムチューブ型枠群3を取り外し、第5図に示す如(各
ゴムチューブ型枠群3の取り外し後の空間へ新たにコン
クリート7を打設する。
After the concrete 6 poured into the divided formwork 1 solidifies, some air or water is removed from each rubber tube 2 and each rubber tube formwork group 3 is removed. New concrete 7 is placed in the space after the formwork group 3 has been removed.

なお各ゴムチューブ2内の空気または水を若干抜く時は
、コンクリート6の打設後、コンクリート6が崩れなく
なる時点の約3時間以降に行う。
Note that when the air or water in each rubber tube 2 is to be slightly removed, this is done approximately 3 hours after the concrete 6 has been placed until the concrete 6 stops collapsing.

また新たなコンクリート7の打設は、コンクリート6が
外気温程度まで低くなった時点(熱膨張していたコンク
リート6が収縮した時点)のコンクリート6打設後約7
日で行う。そしてここで使用するコンクリート7は、僅
かに膨張するものが良い。
In addition, the new concrete 7 should be placed at approximately 7 pm after the concrete 6 is placed when the concrete 6 becomes as low as the outside temperature (when the thermally expanding concrete 6 contracts).
Do it in days. The concrete 7 used here is preferably one that expands slightly.

このようにしてマスコンクリートの施工作業が完了する
。そして−度に多量に打設するコンクリート6は、各ゴ
ムチューブ型枠群3で複数に分割されているので、全体
が一体の大塊ではないので凝固時における所謂マスコン
ひびわれの発生がない。
In this way, the mass concrete construction work is completed. Since the concrete 6, which is cast in large quantities at one time, is divided into a plurality of parts by each rubber tube form group 3, the whole is not a single large lump, so that so-called mass concrete cracks do not occur during solidification.

なおここで使用されるゴムチューブ2は、第6図に示す
如(、内部への空気または水充填時において外形状が波
状の凹凸形状になるように形成されている。
As shown in FIG. 6, the rubber tube 2 used here is formed so that its outer shape becomes a wavy uneven shape when the inside is filled with air or water.

これは、コンクリート6とゴムチューブ型枠群3取り外
し後の空間へ新たに打設するコンクリート7との結合が
確実に行われるべく、コンクリート6の打設面に凹凸を
形成するため。またはマスコンクリート用の鉄筋をシー
ルするためのものである。
This is to form irregularities on the pouring surface of the concrete 6 so that the concrete 6 and the new concrete 7 to be poured into the space after the rubber tube formwork group 3 is removed will be reliably bonded to each other. Or for sealing reinforcing bars for mass concrete.

(発明の効果〕 この発明のマスコンクリートの施工方法は、厚く長大に
打設するマスコンクリート用の配筋作業時における前記
マスコンクリート用の型枠内に、その長手方向複数箇所
へ、前記マスコンクリートの厚み方向全長に延びるゴム
チューブが前記マスコンクリートの幅方向に多数本並設
してなるゴムチューブ型枠群を配置する。
(Effects of the Invention) The method for constructing mass concrete of the present invention is such that the mass concrete is placed at multiple locations in the longitudinal direction within the formwork for mass concrete during reinforcement work for mass concrete that is cast thick and long. A rubber tube form group is arranged in which a large number of rubber tubes extending over the entire length in the thickness direction are arranged in parallel in the width direction of the mass concrete.

そして次にこのゴムチューブ型枠群における各ゴムチュ
ーブ内に空気または水を充填し、各ゴムチューブ間の間
隙を塞いで前記マスコンクリート用の型枠内を前記各ゴ
ムチューブ型枠群で複数個に分割した後、この複数個に
分割された型枠内へコンクリートを打設する。
Next, each rubber tube in this rubber tube form group is filled with air or water, the gap between each rubber tube is closed, and the mass concrete form is filled with a plurality of rubber tube form groups. After dividing the mold into multiple pieces, concrete is poured into the formwork.

その後この分割型枠内への打設コンクリートの凝固後、
前記各ゴムチューブ内の空気または水を抜いて各ゴムチ
ューブ型枠群を取り外し、各ゴムチューブ型枠群取り外
し後の空間へ新たにコンクリートを打設することを特徴
としている。
Then, after solidifying the concrete poured into this divided formwork,
The method is characterized in that the air or water in each rubber tube is removed, each rubber tube form group is removed, and new concrete is poured into the space after each rubber tube form group has been removed.

そしてこの方法によれば、マスコンクリート用型枠内へ
のコンクリートの打設を一度に行っても、マスコンクリ
ート用型枠が各ゴムチューブ型枠群で複数個に分割され
ているので、全体が一体の大塊とならず、凝固時におけ
る所謂マスコンひびわれが発生し゛ない。
According to this method, even if concrete is poured into the mass concrete formwork all at once, the mass concrete formwork is divided into multiple pieces by each group of rubber tube formworks, so the whole concrete is cast in one go. It does not form a single large lump, and so-called mass condensation cracks do not occur during solidification.

またゴムチューブは、内部への空気または水充填時にお
いて外形状が波状の凹凸形状になるように形成されてい
る。そのためコンクリートの打設面に凹凸を形成して、
最初に多量に打設するコンクリートと、ゴムチューブ型
枠群の取り外し後の空間へ新たに打設するコンクリート
との結合を確実に行わせることができる。またはマスコ
ンクリート用の鉄筋をシールすることもできる。
Further, the rubber tube is formed so that its outer shape becomes a wavy uneven shape when the inside is filled with air or water. Therefore, unevenness is formed on the concrete pouring surface,
It is possible to reliably connect the concrete that is placed in large quantities initially with the concrete that is newly placed in the space after the rubber tube formwork group has been removed. Alternatively, it can also seal reinforcing bars for mass concrete.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図はマスコンクリート用の型枠にゴムチューブ型枠
群を設けた状態を示す概略斜視図、第2図および第3図
は第1図におけるA部拡大平面図、第4図はマスコンク
リート用型枠内へのコンクリート打設状態を示す斜視図
、第5図は各ゴムチューブ型枠群取り外し後の空間へ新
たなコンクリートを打設した状態を示す斜視図、第6図
はゴムチューブを示す斜視図である。 l・・・マスコンクリート用の型枠、2・・・ゴムチュ
ーブ、3・・・ゴムチューブ型枠群、4・・・支持鉄筋
、5・・・間隔保持筋、6.7・・・コンクリート。 第11!i!I 第 2− 第 図 第 図 第 図
Figure 1 is a schematic perspective view showing a group of rubber tube forms installed in a mass concrete formwork, Figures 2 and 3 are enlarged plan views of section A in Figure 1, and Figure 4 is a mass concrete formwork. Figure 5 is a perspective view showing the state of concrete being poured into the formwork, Figure 5 is a perspective view showing the state in which new concrete has been poured into the space after each rubber tube form group has been removed, and Figure 6 is a perspective view showing the state of concrete being poured into the space after each rubber tube form group has been removed. FIG. l...Mass concrete formwork, 2...Rubber tube, 3...Rubber tube formwork group, 4...Support reinforcing bars, 5...Spacing reinforcement, 6.7...Concrete . 11th! i! I Part 2- Figure Figure Figure

Claims (2)

【特許請求の範囲】[Claims] (1)厚く長大に打設するマスコンクリート用の配筋作
業時における前記マスコンクリート用の型枠内に、その
長手方向複数箇所へ、前記マスコンクリートの厚み方向
全長に延びるゴムチューブが前記マスコンクリートの幅
方向に多数本並設してなるゴムチューブ型枠群を配置し
、このゴムチューブ型枠群における各ゴムチューブ内に
空気または水を充填し、各ゴムチューブ間の間隙を塞い
で前記マスコンクリート用の型枠内を前記各ゴムチュー
ブ型枠群で複数個に分割した後、この複数個に分割され
た型枠内へコンクリートを打設し、 この分割型枠内への打設コンクリートの凝固後、前記各
ゴムチューブ内の空気または水を抜いて各ゴムチューブ
型枠群を取り外し、各ゴムチューブ型枠群取り外し後の
空間へ新たにコンクリートを打設することを特徴とする
マスコンクリートの施工方法。
(1) During reinforcing work for mass concrete that is cast thick and long, rubber tubes extending the entire length in the thickness direction of the mass concrete are placed in the formwork for the mass concrete at multiple locations in the longitudinal direction of the mass concrete. A rubber tube form group consisting of a large number of rubber tube forms arranged side by side in the width direction is arranged, and each rubber tube in this rubber tube form group is filled with air or water to close the gap between each rubber tube to form the mass. After dividing the inside of the concrete formwork into a plurality of pieces using each of the rubber tube formwork groups, concrete is poured into the formwork divided into the plurality of pieces, and concrete is poured into the divided formwork. After solidification, the air or water in each rubber tube is removed, each rubber tube formwork group is removed, and new concrete is poured into the space after each rubber tube formwork group has been removed. Construction method.
(2)ゴム・チューブへの空気または水の充填時におい
て外形状が波状の凹凸形状になることを特徴とする請求
項1のマス・コンクリートの施工方法。
(2) The mass concrete construction method according to claim 1, wherein the outer shape becomes a wavy uneven shape when the rubber tube is filled with air or water.
JP20341588A 1988-08-16 1988-08-16 Mass concrete construction method Pending JPH0254067A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP20341588A JPH0254067A (en) 1988-08-16 1988-08-16 Mass concrete construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP20341588A JPH0254067A (en) 1988-08-16 1988-08-16 Mass concrete construction method

Publications (1)

Publication Number Publication Date
JPH0254067A true JPH0254067A (en) 1990-02-23

Family

ID=16473697

Family Applications (1)

Application Number Title Priority Date Filing Date
JP20341588A Pending JPH0254067A (en) 1988-08-16 1988-08-16 Mass concrete construction method

Country Status (1)

Country Link
JP (1) JPH0254067A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0480467A (en) * 1990-07-20 1992-03-13 Toda Constr Co Ltd Reinforced concrete pouring method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0480467A (en) * 1990-07-20 1992-03-13 Toda Constr Co Ltd Reinforced concrete pouring method

Similar Documents

Publication Publication Date Title
CN106869402B (en) Assembly concrete component and its manufacturing method
JPH0254067A (en) Mass concrete construction method
CN111456105B (en) Construction method of post-pouring belt of underground garage bottom plate
US2116946A (en) Pre-cast building unit or slab and method of assembling same
JPS6134539B2 (en)
JP7420299B2 (en) How to build a structure
CN218233577U (en) High water level underground outer wall post-cast strip protective structure
JPS5988567A (en) Heat insulating mold frame with electric heater
CN210621492U (en) Deck-type box type arch bridge arch ring bottom plate pressing die structure
JPH0531604B2 (en)
JPS6228389A (en) Precast heat accumulating tank made of concrete
JPS61290137A (en) Construction of columnar pillar
JPH04111866A (en) Manufacture of hollow precast reinforced concrete column and beam member
CN119122264A (en) A formwork-free tool for post-casting strip of top plate
CN118110262A (en) A seamless construction method for super-long concrete structure of gymnasium
CN117822770A (en) A 3D printed shear wall structure and construction method thereof
JPH0116801Y2 (en)
JPS60133160A (en) Concrete casting method on deck plate
JPH0718235B2 (en) Concrete placing method and apparatus
JPS6149052A (en) Construction of reinforced concrete structure
JPH0841893A (en) Manufacture of caisson bottom slab section and bottom slab section structure of caisson
CN118855217A (en) A construction and manufacturing method for post-casting belt of settlement
JPS58110755A (en) Damming of beam vertical spliced part in constructing reinforced concrete building
SU1260447A1 (en) Method of constructing monolithic ferroconcrete wall on foundation plate
JP2004183281A (en) Construction method for concrete structure, form block used in the method, and form block manufacturing method