JPH0238627A - Rebuilding of existing building - Google Patents
Rebuilding of existing buildingInfo
- Publication number
- JPH0238627A JPH0238627A JP63186725A JP18672588A JPH0238627A JP H0238627 A JPH0238627 A JP H0238627A JP 63186725 A JP63186725 A JP 63186725A JP 18672588 A JP18672588 A JP 18672588A JP H0238627 A JPH0238627 A JP H0238627A
- Authority
- JP
- Japan
- Prior art keywords
- slab
- tunnel
- existing
- underground
- ground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 claims description 16
- 238000010276 construction Methods 0.000 description 11
- 238000009412 basement excavation Methods 0.000 description 7
- 230000000694 effects Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 239000000470 constituent Substances 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Abstract
Description
【発明の詳細な説明】
〈産業上の利用分野〉
本発明は地上の既設構造物を使用しつつ、その地下部に
建替用の構造物の基礎部を構築する、既設構造物の建替
工法に関する。[Detailed Description of the Invention] <Industrial Application Field> The present invention relates to the reconstruction of an existing structure, in which the existing structure above ground is used and the foundation of the structure to be reconstructed is constructed underground. Regarding construction methods.
〈従来の技術〉
大規模な範囲に渡って集合住宅等の既設構造物を建て替
えするには、■地上に存在する既設構造物を移設又は解
体した後、■開削工や基礎工を行って、構造物の地下部
を構築し、■最後に基礎部の上方に地上部を構築してい
る。<Conventional technology> In order to rebuild an existing structure such as an apartment complex over a large area, it is necessary to: ■ Relocate or demolish the existing structure on the ground, ■ Perform excavation work or foundation work, The underground part of the structure is constructed, and finally the above-ground part is constructed above the foundation.
〈本発明が解決しようとする問題点〉
上記した従来の既設構造物の建替技術には次のような課
題がある。<Problems to be Solved by the Present Invention> The conventional techniques for rebuilding existing structures described above have the following problems.
〈イ〉既設構造物の建替工事中は、既設構造物の使用が
不可能となる。<B> During the reconstruction work of the existing structure, it will be impossible to use the existing structure.
そのため、既設構造物を維持したまま、建て替えられる
技術の提案が望まれている。Therefore, it is desired to propose a technology that allows rebuilding existing structures while maintaining them.
〈口〉一般に既設構造物の建替には、ある程度の地土建
りに仮設スペースが必要とされる。<Exposure> Generally, when rebuilding an existing structure, a certain amount of temporary space is required on the land.
又、既設構造物内の各種収容物を仮置きする仮移転スペ
ースも要求される。Additionally, a temporary relocation space is also required to temporarily store various items stored in the existing structure.
しかし、地価の高騰傾向にある最近は、これらのスペー
スを確保することが困難になりつつある。However, with land prices on the rise, it is becoming increasingly difficult to secure these spaces.
〈本発明の目的〉
本発明は以上の点に鑑みて成されたもので、次のような
既設構造物の建替工法を提供することを目的とする。<Object of the present invention> The present invention has been made in view of the above points, and an object thereof is to provide the following method for rebuilding an existing structure.
〈イ〉既設構造物を維持したまま、建替工事を行える、
既設構造物の建替工法。(a) Reconstruction work can be carried out while maintaining the existing structure,
Reconstruction method for existing structures.
〈口〉土地の有効利用が図れる、既設構造物の建替工法
。<Explanation> A method of rebuilding existing structures that allows for effective use of land.
〈本発明の構成〉
以下、図面を参照しながら本発明に係る既設構造物の建
替工法の一実施例について説明する。<Configuration of the Present Invention> An embodiment of the method for rebuilding an existing structure according to the present invention will be described below with reference to the drawings.
〈イ〉トンネルの掘削(第2図) 建替予定地の周辺に立坑1を構築する。<B> Tunnel excavation (Figure 2) Vertical shaft 1 will be constructed around the planned reconstruction site.
この際、必要に応じて止水壁10を構築する。At this time, a water stop wall 10 is constructed as necessary.
そして、立坑1から建替予定地の地下部の全域にわたっ
てトンネル2を掘削する。Then, a tunnel 2 is excavated from the shaft 1 to the entire underground part of the planned reconstruction site.
トンネル2の掘削方法は、地上に立設する既設構造物3
の基礎形式に応じて選定する。The excavation method for tunnel 2 is based on the existing structure 3, which is erected on the ground.
Select according to the basic form.
掘削方法としては、例えば既設構造物3の基礎形式が直
接基礎の場合は、シールド工法やメツセル工法等を採用
し、又、杭基礎の場合は、メツセル工法等を採用する。As the excavation method, for example, if the foundation type of the existing structure 3 is a direct foundation, the shield method or the Metsusel method is adopted, and in the case of a pile foundation, the Metsusel method or the like is adopted.
トンネル2を掘削する際、必要に応じてバイブルーフ工
法や薬液注入工法等の補助工法を併用する。When excavating the tunnel 2, auxiliary construction methods such as the bi-roof construction method and the chemical injection method are used in combination as necessary.
尚、既設構造物3の基礎形式が杭基礎の場合は、既設構
造物30基礎の一部を構成する既設杭31とトンネル2
が衝突することになるが、地盤沈下の防止を目的として
、トンネル2に既設杭31を貫通させた状態で掘削する
。In addition, if the foundation type of the existing structure 3 is a pile foundation, the existing piles 31 and the tunnel 2, which constitute a part of the foundation of the existing structure 30,
However, in order to prevent ground subsidence, the tunnel 2 is excavated with the existing piles 31 passing through it.
〈口〉基礎杭の構築(第2図)
リバースサーキュレーション工法等によりトンネル2の
下方にのびる基礎杭4を構築する。<Entrance> Construction of foundation piles (Figure 2) The foundation piles 4 extending below the tunnel 2 are constructed using the reverse circulation construction method.
くハ〉PCスラブの構築(第2.3図)次に、トンネル
2のスラブ面に、PCスラブ21を構築する。〉Construction of PC Slab (Fig. 2.3) Next, a PC slab 21 is constructed on the slab surface of the tunnel 2.
PCスラブ21は、基礎杭4及び既設杭31と一体に構
築する。The PC slab 21 is constructed integrally with the foundation pile 4 and the existing pile 31.
このPCスラブ21は、地下を施工する際に土砂の崩落
防止用の天版として機能する他、最終的には構造物の構
成材となる。This PC slab 21 not only functions as a ceiling plate to prevent earth and sand from collapsing during underground construction, but also ultimately becomes a constituent material of the structure.
PCスラブ21の構築法としては、トンネル2のスラブ
面に、基礎杭4を包囲するように鉄筋と共にPC鋼材を
ループ状に配筋してコンクリートを打設した後、スラブ
の途上において、pcm材を緊張して定着する方法を採
用できる。The method for constructing the PC slab 21 is to place concrete on the slab surface of the tunnel 2 by arranging PC steel in a loop along with reinforcing bars so as to surround the foundation piles 4, and then placing PCM material in the middle of the slab. You can use a method to maintain tension.
尚、PCスラブ21のプレストレスの導入法は、トンネ
ル2の高さや施工範囲等を考慮して最適な公知のプレス
トレスの導入法を採用する。As for the prestress introduction method for the PC slab 21, an optimal known prestress introduction method is adopted in consideration of the height of the tunnel 2, the construction range, etc.
又、必要に応じてトンネル2内の上部空洞に発泡モルタ
ルを充填する。Further, if necessary, the upper cavity within the tunnel 2 is filled with foamed mortar.
〈二〉スラブ下の掘削(第4図)
基礎杭4群と一体構造のPCスラブ21を構築したら、
PCスラブ21の下方を掘削して、地下空間5を形成す
る。<2> Excavation under the slab (Fig. 4) After constructing the PC slab 21, which is integrated with the four groups of foundation piles,
An underground space 5 is formed by excavating below the PC slab 21.
PCスラブ21の上方の総荷重は、PCスラブ21と一
体の基礎杭4群により支持されるので、地下空間5の掘
削中の崩壊が阻止される。Since the total load above the PC slab 21 is supported by the four groups of foundation piles integrated with the PC slab 21, collapse during excavation of the underground space 5 is prevented.
PCスラブ21の下方の掘削作業に際し、地下空間5に
連通する削土搬出用坑道を事前に構築しておく方法を採
用した場合は、大量の排土作業を高能率に行える。When excavating below the PC slab 21, if a method is adopted in which a tunnel for removing excavated earth that communicates with the underground space 5 is constructed in advance, a large amount of earth can be removed with high efficiency.
〈ホ〉地下施設の構築(第5図)
地下空間5の内面に、コンクリートを打設して地下施設
7を構築する。<E> Construction of underground facilities (Fig. 5) Concrete is poured on the inner surface of the underground space 5 to construct the underground facilities 7.
そして、必要に応じて地上側の既設構造物3の施設を地
下施設7へ移設する。Then, the facilities of the existing structure 3 on the ground side are relocated to the underground facility 7 as necessary.
〈ホ〉地上施設の構築(第6図〉 最後に、地下施設7の上部に地上施設8を構築する。<E> Construction of ground facilities (Figure 6) Finally, the aboveground facility 8 is constructed above the underground facility 7.
地上施設8は、既設構造物3群を順次撤去しながら構築
する他、−度に既設構造物3群を撤去して構築する方法
が考えられる。In addition to constructing the above-ground facility 8 by sequentially removing three groups of existing structures, it is also possible to construct the above-ground facility by removing three groups of existing structures one by one.
く本発明の効果〉
本発明は以上説明したようになるから次の効果が得られ
る。Effects of the Present Invention> Since the present invention is as explained above, the following effects can be obtained.
〈イ〉地上の既設構造物を維持したまま、建替構造物の
基礎工事を行える。<B> Foundation work for the reconstructed structure can be carried out while maintaining the existing structure above ground.
又、建替構造物の地下施設が完成した後に、地上施設を
構築するため、既設構造物の使用中止期間を最小限にお
さえることができる。Furthermore, since the above-ground facilities are constructed after the underground facilities of the reconstructed structure are completed, the period during which the existing structure is discontinued can be kept to a minimum.
〈口〉完成した地下施設を、地上側の既設構造物の移設
空間として活用できる。<Exit> The completed underground facility can be used as a space for relocating existing structures above ground.
くハ〉地上部廻りの仮設スペースを最小限におさえられ
る。Kuha> Temporary space around the above ground area can be kept to a minimum.
(二〉地上部での土地の有効利用が図れる。(2) Effective use of land above ground can be achieved.
くホ〉PCスラブは、止水壁や土止壁の切梁として兼用
できる他、最終的に構造物の一部として有効に活用する
ことができる。Kuho〉PC slabs can be used not only as struts for water-stop walls and earth-retaining walls, but also as a final part of a structure.
〈へ〉大規模な市場や集合住宅地等の建替工事に好適で
ある。〈〈〈〈〉It is suitable for reconstruction work of large-scale markets and residential complexes.
第1図二本発明に係る一実施例の説明図であって地下施
設の構築時の部分断面図
第2図:トンネル掘削時のトンネル縦断面図第3図;P
Cスラブの構築時のトンネル縦断面図第4図:PCスラ
ブ下の掘削時の縦断面図第5図:地下施設の構築時の縦
断面図
第6図:地上施設の構築時の断面図Fig. 1 2 is an explanatory diagram of one embodiment of the present invention, which is a partial sectional view during construction of an underground facility Fig. 2: longitudinal sectional view of a tunnel during tunnel excavation Fig. 3;
Figure 4: Vertical cross section of the tunnel when constructing the C slab Figure 5: Vertical cross section when constructing underground facilities Figure 6: Cross section when constructing above ground facilities
Claims (1)
下部の全域にわたってトンネルを掘削し、トンネルのス
ラブ面に下方にのびる基礎杭を構築し、 次に、トンネルのスラブ面に、前記基礎杭と一体構造で
あって、プレストレスを導入したPCスラブを構築し、 前記PCスラブを介して基礎杭群で地盤を支持しつつP
Cスラブの下方を掘削して地下施設を構築し、 地上の既設構造物を撤去しながら前記地下施設と一体の
地上施設を構築する、 既設構造物の建替工法。(1) Excavate a tunnel across the entire underground area of the planned reconstruction site while maintaining the existing structures above ground, and construct foundation piles that extend downward on the slab surface of the tunnel. Next, on the slab surface of the tunnel, A prestressed PC slab is constructed that is integral with the foundation pile, and the foundation piles are used to support the ground through the PC slab.
A method for rebuilding existing structures, in which underground facilities are constructed by excavating below the C slab, and above-ground facilities are constructed that are integrated with the above-mentioned underground facilities while removing the existing above-ground structures.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP63186725A JP2657671B2 (en) | 1988-07-28 | 1988-07-28 | Reconstruction method for existing structures |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP63186725A JP2657671B2 (en) | 1988-07-28 | 1988-07-28 | Reconstruction method for existing structures |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0238627A true JPH0238627A (en) | 1990-02-08 |
JP2657671B2 JP2657671B2 (en) | 1997-09-24 |
Family
ID=16193542
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP63186725A Expired - Lifetime JP2657671B2 (en) | 1988-07-28 | 1988-07-28 | Reconstruction method for existing structures |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2657671B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001271365A (en) * | 2000-03-24 | 2001-10-05 | Kajima Corp | Construction method for underground structure |
US8011636B2 (en) | 2008-05-15 | 2011-09-06 | Iwatsu Electric Co., Ltd. | Electronic apparatus with a stand |
CN111335670A (en) * | 2020-03-18 | 2020-06-26 | 同济大学建筑设计研究院(集团)有限公司 | Method for constructing foundation pit and newly adding underground structure in situ under existing reserved building |
-
1988
- 1988-07-28 JP JP63186725A patent/JP2657671B2/en not_active Expired - Lifetime
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001271365A (en) * | 2000-03-24 | 2001-10-05 | Kajima Corp | Construction method for underground structure |
JP4485006B2 (en) * | 2000-03-24 | 2010-06-16 | 鹿島建設株式会社 | Construction method for underground structures |
US8011636B2 (en) | 2008-05-15 | 2011-09-06 | Iwatsu Electric Co., Ltd. | Electronic apparatus with a stand |
CN111335670A (en) * | 2020-03-18 | 2020-06-26 | 同济大学建筑设计研究院(集团)有限公司 | Method for constructing foundation pit and newly adding underground structure in situ under existing reserved building |
Also Published As
Publication number | Publication date |
---|---|
JP2657671B2 (en) | 1997-09-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR20200098362A (en) | tunnel shaft and Construction Method forstructures according to the excavation. | |
CN113266017B (en) | Regulation and storage tank construction method based on 'permanent-face integrated' inner support structure of deep foundation pit | |
JP2000352296A (en) | Method o constructing passage just under underground structure | |
KR100376590B1 (en) | Multi-phased underground construction method for wide excavation using permanent structural members as temporary struts | |
KR0179708B1 (en) | Working method for underground structure of a building | |
JPH0238627A (en) | Rebuilding of existing building | |
CN206873459U (en) | A kind of large-span steel-reinforced concrete foundation ditch support system | |
CN206220558U (en) | Old City Wall door opening ruggedized construction | |
CN105804086A (en) | Construction method for support change joints in foundation trench reverse building method construction | |
JPS62288269A (en) | Method for extending underground stair of building | |
CN106522576B (en) | Old City Wall door opening reinforcement means and ruggedized construction | |
JP2813807B2 (en) | How to build an underground tunnel | |
JPH07243269A (en) | Method of building underground parking lot | |
JPH06228979A (en) | Inverted lining method for building-construction | |
JPH0584773B2 (en) | ||
JPH02300422A (en) | Construction of underground structure | |
JPH11152762A (en) | Structure and its construction method | |
JPS61186623A (en) | Method of building foundation of building | |
JPH02266016A (en) | Structural process of underground concrete body of building | |
JPH04194277A (en) | Demolishing method for building | |
JP3646698B2 (en) | Construction method for underground structures | |
JP2835815B2 (en) | Foundation structure for wooden buildings and its construction method | |
JPH03228921A (en) | Execution method for concrete foundation work | |
TW418274B (en) | A pre-cast and site-cast combined construction method of retaining and waterproof diaphragm wall | |
JPS59233028A (en) | Residential land formation work on sloped ground |