JP6375079B1 - Joint structure of precast composite floor slab perpendicular to the bridge axis and its construction method - Google Patents

Joint structure of precast composite floor slab perpendicular to the bridge axis and its construction method Download PDF

Info

Publication number
JP6375079B1
JP6375079B1 JP2018093559A JP2018093559A JP6375079B1 JP 6375079 B1 JP6375079 B1 JP 6375079B1 JP 2018093559 A JP2018093559 A JP 2018093559A JP 2018093559 A JP2018093559 A JP 2018093559A JP 6375079 B1 JP6375079 B1 JP 6375079B1
Authority
JP
Japan
Prior art keywords
bridge axis
bridge
composite panel
joint
direction perpendicular
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2018093559A
Other languages
Japanese (ja)
Other versions
JP2019199710A (en
Inventor
敬人 藤川
敬人 藤川
繁樹 水上
繁樹 水上
康行 田村
康行 田村
太郎 利根川
太郎 利根川
健 岡部
健 岡部
夏実 佐藤
夏実 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Engineering Co Ltd
Original Assignee
Nippon Steel and Sumikin Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel and Sumikin Engineering Co Ltd filed Critical Nippon Steel and Sumikin Engineering Co Ltd
Priority to JP2018093559A priority Critical patent/JP6375079B1/en
Application granted granted Critical
Publication of JP6375079B1 publication Critical patent/JP6375079B1/en
Publication of JP2019199710A publication Critical patent/JP2019199710A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

【課題】急速施工が可能であり、強度的に優れ、かつ間詰めコンクリートの量を低減でき、現場作業が容易なプレキャスト合成床版の橋軸直角方向の継手構造を提供する。
【解決手段】
1径間の長さの主桁2と、底鋼板3と、底鋼板3上の複数のI形鋼4と、床版コンクリート5を構成要素とするプレキャスト合成パネルユニット1の橋軸直角方向の継手構造である。床版コンクリート5の継手面を凹凸形状とし、その凸部6からI形鋼4を突出させる。隣り合うパネルユニット1どうしの一方のパネルユニット1の継手位置では凸部6およびI形鋼4の端部が底鋼板3の端部より内側に位置し、他方のパネルユニット1の継手位置では凸部6およびI形鋼4の端部が底鋼板3の端部より外側に張り出している。これらを突き合わせて、双方のパネルユニット1の床版コンクリートの凸部6およびI形鋼4の端部が交互に位置するようにし、継手部に間詰めコンクリート9を打設する。
【選択図】 図1
The present invention provides a joint structure in a direction perpendicular to a bridge axis of a precast synthetic slab that is capable of rapid construction, is excellent in strength, can reduce the amount of interstitial concrete, and is easy to work on site.
[Solution]
A main girder 2 having a length between one diameter, a bottom steel plate 3, a plurality of I-shaped steels 4 on the bottom steel plate 3, and a precast composite panel unit 1 including a floor slab concrete 5 in the direction perpendicular to the bridge axis. It is a joint structure. The joint surface of the floor slab concrete 5 is formed into a concavo-convex shape, and the I-shaped steel 4 is projected from the convex portion 6. At the joint position of one panel unit 1 between adjacent panel units 1, the convex part 6 and the end of the I-shaped steel 4 are located inside the end part of the bottom steel plate 3, and the joint position of the other panel unit 1 is convex. The end portions of the portion 6 and the I-shaped steel 4 protrude outward from the end portion of the bottom steel plate 3. These are abutted so that the convex portions 6 of the floor slab concrete and the ends of the I-shaped steel 4 of both panel units 1 are alternately positioned, and the interstitial concrete 9 is placed in the joint portion.
[Selection] Figure 1

Description

本発明は、道路橋などに用いられるプレキャスト合成床版の橋軸直角方向の継手構造及びその施工方法に関するものである。   The present invention relates to a joint structure in a direction perpendicular to a bridge axis of a precast composite floor slab used for a road bridge and the like, and a construction method thereof.

橋梁の施工においては、交通規制や施工コストの問題などから急速施工が可能な工法が期待されている。特に、既設橋梁の老朽化に対し床版の架け替えを行う場合には、既設橋梁の周辺も含め、交通規制が必要となることから急速施工の必要性が高い。   In the construction of bridges, construction methods capable of rapid construction are expected due to problems such as traffic restrictions and construction costs. In particular, when replacing the floor slabs with the aging of existing bridges, traffic regulation is required, including the area around the existing bridges, and the need for rapid construction is high.

例えば、特許文献1には、所要の剛性を有し、かつ製作コストを低減した鋼・コンクリートの合成パネル構造と、その合成パネルを用いて現地工期短縮および施工の単純化を図った合成パネル橋梁の施工方法が記載されている。   For example, Patent Document 1 discloses a composite panel structure of steel / concrete that has the required rigidity and reduced manufacturing cost, and a composite panel bridge that uses the composite panel to shorten the construction period and simplify construction. The construction method is described.

この特許文献1記載の合成パネルは、底鋼板の下面に間隔をおいて配置した主桁の役割を担う複数の縦桁が固定され、底鋼板の上面には縦桁と直交方向にI形鋼などの形鋼からなりジベルの機能を持たせた横リブが間隔をおいて固定配置され、横リブが埋没するように現場打ちの床版コンクリートが充填された構造のものである。
特許文献2には、橋梁の改修工事におけるプレキャスト床版の継手部に多用されてきたいわゆるループ継手が記載されている。
In the composite panel described in Patent Document 1, a plurality of stringers serving as main girders arranged at intervals on the bottom surface of the bottom steel plate are fixed, and an I-shaped steel is formed on the top surface of the bottom steel plate in a direction orthogonal to the stringers. This is a structure in which horizontal ribs made of shaped steel such as gibber functions are fixedly arranged at intervals and filled with on-site floor slab concrete so that the horizontal ribs are buried.
Patent Document 2 describes a so-called loop joint that has been frequently used for a joint portion of a precast floor slab in bridge repair work.

特許文献3には、プレキャスト部材同士を高い耐力で接合可能な耐久性に優れた接合構造として、接合される双方のプレキャスト部材の接合側端部から有孔板(孔明き鋼板ジベル)を突設させ、隙間に充填材を充填するとともにそれらの有孔板の孔に挿通させたPC鋼材によって充填材の充填部にプレストレスを導入するようにした接合構造が記載されている。   In Patent Document 3, a perforated plate (perforated steel plate gibber) is projected from the joint side end of both precast members to be joined as a durable joint structure capable of joining precast members with high strength. In addition, there is described a joining structure in which a prestress is introduced into a filling portion of a filler by a PC steel material which is filled with a filler in a gap and is inserted into a hole of the perforated plate.

特許文献4には、既設橋の改修などにおいて急速施工を可能とするプレキャスト床版の継手構造に関し、継手端部に複数の切欠部を設けて凹凸形状とし、プレキャスト床版の凸部から突出させた継手用鉄筋を他方のプレキャスト床版の凹部内に納める形で間詰め材を充填するようにしたことで、間詰め材の充填量を低減して工期を短縮するとともに、継手部に構造的な弱点が生じないようにした継手構造が記載されている。   Patent document 4 relates to a joint structure of a precast floor slab that enables rapid construction in renovation of an existing bridge, etc., by providing a plurality of notches at the end of the joint to form a concavo-convex shape and projecting from the convex part of the precast floor slab. By filling the reinforcing bars for fittings into the recesses of the other precast slab, the filling material is filled, reducing the filling amount of the filling materials and shortening the construction period, A joint structure that does not cause any weak points is described.

特許文献5には、プレキャストコンクリート床版の接続構造として、プレキャストコンクリート床版本体から橋軸方向に突出する上側継手鉄筋および下側継手鉄筋の先端部にネジ切りしてナットを取り付けるか、または圧着グリップを固着し、継手鉄筋を突出させた対向する床版本体の端面間に間詰めコンクリートを充填する構造において、床版本体の端面厚さ方向の中央部に溝形のせん断キー部を形成した構造が記載されている。   In Patent Document 5, as a connection structure of a precast concrete floor slab, a screw is attached to the tip of the upper joint reinforcing bar and the lower joint reinforcing bar protruding from the main body of the precast concrete floor slab and a nut is attached, or crimping is performed. In the structure in which the concrete is filled between the end faces of the opposing floor slab body with the grips fixed and protruding joint reinforcing bars, a groove-shaped shear key is formed in the center of the end face thickness direction of the floor slab body The structure is described.

特開2004−137686号公報JP 2004-137686 A 特開2008−303538号公報JP 2008-303538 A 特開2009−209600号公報JP 2009-209600 A 特開2012−225144号公報JP 2012-225144 A 特開2015−001045号公報JP2015-001045A

特許文献1記載の発明は、鋼・コンクリートの合成床版構造の橋梁の現地工期短縮および施工の単純化を図ったものであるが、合成床版を構成するコンクリートは現場打ちであるため、工期を最小限に短縮する急速施工には適さない。   The invention described in Patent Document 1 is intended to shorten the local construction period and simplify the construction of the bridge of the steel / concrete composite floor slab structure. It is not suitable for rapid construction that shortens to a minimum.

特許文献2記載の発明は、ループ継手を形成する鉄筋の加工の問題などから床版厚を薄くすることが難しく、またループ継手と継手部に配置された鉄筋および充填コンクリートのみでは十分な継手強度が得られにくい。   In the invention described in Patent Document 2, it is difficult to reduce the floor slab thickness due to the problem of the processing of the reinforcing bar forming the loop joint, and the joint strength sufficient only with the reinforcing bar and the filled concrete arranged in the loop joint and the joint part. Is difficult to obtain.

特許文献3記載の発明は、継手部に孔明き鋼板ジベルを用いたものであるが、継手端部に孔明き鋼板ジベルを埋め込んでプレキャスト床版を製作しなければならず、製造コストが高く付き、また孔明き鋼板ジベルと鉄筋および充填コンクリートのみでは継手部が強度的な弱点となりやすい。   The invention described in Patent Document 3 uses a perforated steel plate gibel for the joint part, but a precast floor slab must be produced by embedding the perforated steel plate gibber at the joint end, which is expensive to manufacture. Moreover, a joint part tends to become a weak point of strength only with a perforated steel plate gibber, a reinforcing bar and filled concrete.

特許文献4記載の発明は、プレキャスト床版の継手端部を平面的にみて凹凸形状となるようにし、プレキャスト床版の凸部から突出させた継手用鉄筋を他方のプレキャスト床版の凹部内に納める形で間詰め材を充填するようにしたことで、間詰め材の充填量を低減して工期を短縮するとともに、継手部に構造的な弱点が生じないようにしたものであるが、継手部に作用するせん断力に対し、必ずしも十分な構造とは言えない。   In the invention described in Patent Document 4, the joint end of the precast floor slab is seen in a plan view so that it has a concave and convex shape, and the joint rebar protruding from the convex part of the precast floor slab is placed in the concave part of the other precast floor slab. By filling the padding material in a way that fits, the filling amount of the padding material is reduced, the work period is shortened, and no structural weakness is generated in the joint. It cannot be said that the structure is necessarily sufficient for the shearing force acting on the part.

特許文献5記載の発明は、継手部において橋軸方向に突出させた鉄筋の先端部にナットまたは圧着グリップを取り付けて重ね継手の機能を高めるとともに、床版本体の端面に形成した溝形のせん断キー部により、継手部の一体化を図ったものであるが、この場合も必ずしも継手部の強度が十分とは言えない。   The invention described in Patent Document 5 is a groove-shaped shear formed on the end face of the floor slab body by attaching a nut or a crimping grip to the tip of the reinforcing bar protruding in the bridge axis direction at the joint to enhance the function of the lap joint. Although the joint portion is integrated by the key portion, the strength of the joint portion is not always sufficient in this case as well.

また、特許文献2〜5記載の発明は、橋軸方向の継手を対象としており、主桁あるいは橋脚、橋台などに支持されているが、橋軸直角方向の継手の場合、継手部が主桁位置とは限らず、むしろ主桁位置から外れる場合も多く、その場合、継手部自体に大きなせん断耐力が要求される。   The inventions described in Patent Documents 2 to 5 are intended for joints in the bridge axis direction and are supported by a main girder, a bridge pier, an abutment, or the like. The position is not limited to the main girder position. In this case, a large shear strength is required for the joint itself.

本願発明は、上述のような従来技術における課題の解決を図ったものであり、現場での急速施工が可能であり、かつプレキャスト合成床版を補剛している補剛桁を利用することで強度的に優れた継手部を構成し、かつ間詰めコンクリートの量を低減でき、現場作業が容易なプレキャスト合成床版の橋軸直角方向の継手構造およびその施工方法を提供することを目的としたものである。   The invention of the present application is intended to solve the above-described problems in the prior art, and is capable of rapid construction on site, and by using a stiffening girder that stiffens a precast composite floor slab. The purpose of the present invention is to provide a joint structure in the direction perpendicular to the bridge axis of a precast synthetic floor slab that can form a joint part excellent in strength, reduce the amount of interstitial concrete, and is easy to work on site, and its construction method. Is.

本発明は、1径間に相当する長さを有する橋軸方向の主桁と、前記主桁の上面に固定された底鋼板と、前記底鋼板の上面に橋軸方向に間隔をおいて配置された複数の形鋼と、前記底鋼板の上面に打設された床版コンクリートとを構成要素とするプレキャスト合成パネルユニット(以下、単に「パネルユニット」と呼ぶ)が橋軸直角方向に複数並列配置されて連結されてなる合成パネル橋梁の橋軸直角方向の継手構造を工夫したものである。   The present invention includes a main girder in a bridge axis direction having a length corresponding to one diameter, a bottom steel plate fixed to the upper surface of the main girder, and an upper surface of the bottom steel plate spaced in the bridge axis direction. A plurality of precast composite panel units (hereinafter simply referred to as “panel units”) that are composed of a plurality of shaped steels and floor slab concrete cast on the top surface of the bottom steel plate are arranged in parallel in a direction perpendicular to the bridge axis. The joint structure in the direction perpendicular to the bridge axis of the composite panel bridge that is arranged and connected is devised.

本発明では、前記床版コンクリートの橋軸直角方向の継手面は平面視で凹凸形状に形成されており、前記形鋼が前記継手面の凹凸形状の凸部から突出しており、橋軸直角方向に隣り合うパネルユニットどうしのうちの一方のパネルユニットの継手位置では、前記凸部および前記形鋼の端部が前記底鋼板の端部より内側に位置しており、他方のパネルユニットの継手位置では、前記凸部および前記形鋼の端部が前記底鋼板の端部より外側に張り出している。   In the present invention, the joint surface in the direction perpendicular to the bridge axis of the floor slab concrete is formed in a concavo-convex shape in plan view, and the shape steel protrudes from the concavo-convex convex portion of the joint surface, In the joint position of one of the panel units adjacent to each other, the projection and the end of the shape steel are located inside the end of the bottom steel plate, and the joint position of the other panel unit Then, the said convex part and the edge part of the said shape steel have projected outside the edge part of the said bottom steel plate.

そして、前記一方のパネルユニットの底鋼板上に、前記他方のパネルユニットの前記凸部および前記形鋼の端部の張出し部が、双方のパネルユニットの床版コンクリートの凸部および形鋼の端部が橋軸方向に交互に位置するように配置され、双方の形鋼の端部を橋軸方向にみてオーバーラップするように配置した状態で、継手部に間詰めコンクリートが打設されていることを特徴とする。   And, on the bottom steel plate of the one panel unit, the protruding portion of the other panel unit and the projecting portion of the end of the shaped steel are the protruding portion of the floor slab concrete and the end of the shaped steel of both panel units. Placed so that the parts are alternately positioned in the direction of the bridge axis, and with the ends of both sections shaped so as to overlap when viewed in the direction of the bridge axis, the interstitial concrete is cast in the joint It is characterized by that.

本発明の合成パネル橋梁の橋軸直角方向の継手部の施工方法においては、橋台と橋脚または橋脚間に前記一方のパネルユニットを架設した後、前記他方のパネルユニットを、凸部および形鋼の端部の張出し部が前記一方のパネルユニットの底鋼板上に載置され、双方のパネルユニットの凸部および形鋼の端部が橋軸方向に交互に位置するように橋台または橋脚間に架設し、双方の形鋼の端部が橋軸方向にみてオーバーラップするようにして、継手部に間詰めコンクリートを打設する。   In the construction method of the joint portion in the direction perpendicular to the bridge axis of the composite panel bridge of the present invention, after the one panel unit is installed between the abutment and the pier or the pier, the other panel unit is made of a convex portion and a shape steel. The overhanging part of the end is placed on the bottom steel plate of the one panel unit, and it is installed between the abutment or the pier so that the convex part of both panel units and the end of the shaped steel are alternately positioned in the bridge axis direction. Then, the interstitial concrete is placed in the joint so that the ends of both shaped steels overlap when viewed in the bridge axis direction.

本発明では、パネルユニットを構成する床版コンクリートの継手面を凹凸形状に形成し、パネルユニットに内蔵された補剛桁の機能を有する形鋼の突出部がこの継手面の凸部から突出する形態となっているため、隣り合う双方のパネルユニットの継手面の凹凸形状をフィンガージョイントのように噛み合わせる形で形鋼の端部が他方のパネルユニットの継手面の凹部に納まるため、この部分に充填される間詰めコンクリートの打設量を少なくしつつ強固な接合構造が得られる。   In this invention, the joint surface of the floor slab concrete which comprises a panel unit is formed in an uneven | corrugated shape, and the protrusion part of the shape steel which has the function of the stiffening girder built in the panel unit protrudes from the convex part of this joint surface. This is because the end of the shaped steel fits into the recess of the joint surface of the other panel unit in a form that meshes the concave and convex shape of the joint surface of both adjacent panel units like a finger joint. A strong joint structure can be obtained while reducing the amount of placement concrete to be filled in.

また、本発明ではパネルユニットに1径間に相当する長さを有する橋軸方向の主桁が一体化されているため、鋼とコンクリートからなる合成床版構造のパネルユニットを橋台または橋脚間に架設する際に、パネルユニット自体に十分な剛性が確保されているため、施工がスムーズであり、継手部の間詰め部分についても剛性的に安定した状態で間詰めコンクリートの打設を行うことができる。   In the present invention, since the main girder in the bridge axis direction having a length corresponding to one diameter is integrated with the panel unit, the panel unit of the composite floor slab structure made of steel and concrete is placed between the abutment or the pier. When installing, the panel unit itself has sufficient rigidity, so the construction is smooth, and it is possible to place the interstitial concrete in a state where the joint interstitial part is rigidly stable. it can.

なお、上述の橋軸直角方向に複数並列配置されるパネルユニットは、全てのパネルユニットが一体化された主桁を有する場合に限らず、一部のパネルユニットについては主桁を有さないパネルユニット、すなわち底鋼板と底鋼板の上面に橋軸方向に間隔をおいて配置された複数の形鋼とを構成要素とするパネルユニットを用いることもできる。   The panel units arranged in parallel in the direction perpendicular to the bridge axis are not limited to cases in which all panel units have an integrated main girder, but some panel units have no main girder. It is also possible to use a unit, that is, a panel unit having as constituent elements a bottom steel plate and a plurality of section steels arranged on the top surface of the bottom steel plate at intervals in the bridge axis direction.

床版コンクリートの継手面の凸部の形状については、さらにこの凸部の橋軸直角方向の断面が上方向に広がる逆台形状となるようにすれば、継手部に後から打設される間詰めコンクリートの上方への抜け出しを拘束する効果が得られる。   About the shape of the convex part of the joint surface of the floor slab concrete, if the cross section of the convex part in the direction perpendicular to the bridge axis is an inverted trapezoidal shape that spreads upward, The effect of restricting the upward slipping of the stuffed concrete is obtained.

その他、床版コンクリートの継手面の凸部の形状については、橋軸直角方向の断面の両側が凹凸形状となるようにしても、同様に間詰めコンクリートの上方への抜け出しの拘束効果や一体性の向上の効果が得られる。   In addition, as for the shape of the convex part of the joint surface of floor slab concrete, even if both sides of the cross section in the direction perpendicular to the bridge axis are concave and convex, the restraining effect and integrity of upward slipping of the interstitial concrete are the same The effect of improvement is obtained.

パネルユニットの床版コンクリート内に埋設されて補剛桁の機能を有する形鋼の断面形状は特に限定されないが、断面剛性や価格、取り扱いの容易さなどからI形鋼などの形鋼が有利である。また、I形鋼などの場合、フランジ形状によるアンカー効果も得られる。   The cross-sectional shape of the shape steel embedded in the floor slab concrete of the panel unit and having the function of a stiffening girder is not particularly limited, but the shape steel such as I-shape steel is advantageous because of the cross-sectional rigidity, price, and ease of handling. is there. Further, in the case of I-shaped steel, an anchor effect due to the flange shape can be obtained.

また、本発明ではパネルユニットの下面に鋼板が一体化されている構造であるため、製作や運搬に便利であり、また架設状態において床版下面の止水性が高いという利点がある。   Further, in the present invention, since the steel plate is integrated with the lower surface of the panel unit, it is convenient for production and transportation, and there is an advantage that the waterproofing of the lower surface of the floor slab is high in the installed state.

本発明ではパネルユニットに1径間に相当する長さを有する橋軸方向の主桁が一体化されているため、鋼とコンクリートからなる合成床版構造のパネルユニットを橋台または橋脚間に架設する際に、パネルユニット自体に十分な剛性が確保されているため、施工がスムーズであり、継手部の間詰め部分についても剛性的に安定した状態で間詰めコンクリートの打設を行うことができる。   In the present invention, since the main girder in the bridge axis direction having a length corresponding to one diameter is integrated with the panel unit, a panel unit having a composite floor slab structure made of steel and concrete is installed between the abutment or the pier. At this time, since sufficient rigidity is ensured in the panel unit itself, the construction is smooth, and it is possible to place the interstitial concrete in a state where the interstitial part interstitial part is rigidly stable.

本発明では、橋軸直角方向に並列するパネルユニットに内蔵された補剛桁の機能を有する形鋼の端部が隣り合うパネルユニット間の継手部に突出し、双方のパネルユニットの形鋼の端部が橋軸方向にみてオーバーラップする形で継手部の間詰めコンクリート内に配置されるため、強固な継手構造が得られる。   In the present invention, the ends of the structural steels having the function of stiffening girders built in the panel units arranged in the direction perpendicular to the bridge axis protrude into the joints between adjacent panel units, and the ends of the structural steels of both panel units. Since the portions are arranged in the joint concrete between the joint portions so as to overlap in the bridge axis direction, a strong joint structure can be obtained.

また、本発明では、パネルユニットを構成する床版コンクリートの継手面を凹凸形状に形成し、補剛桁の機能を有する形鋼の端部がこの継手面の凸部から突出する形態となっており、隣り合う双方のパネルユニットの継手面の凹凸形状をフィンガージョイントのように噛み合わせる形で形鋼の端部が他方のパネルユニットの継手面の凹部に納まるため、この部分に充填される間詰めコンクリートの打設量を少なくしつつ強固な接合構造が得られる。   Moreover, in this invention, the joint surface of the floor slab concrete which comprises a panel unit is formed in an uneven | corrugated shape, and it becomes a form which the edge part of the shaped steel which has a function of a stiffening girder protrudes from the convex part of this joint surface. Because the end of the shaped steel fits into the concave part of the joint surface of the other panel unit by engaging the concave and convex shape of the joint surface of both adjacent panel units like a finger joint. A strong joint structure can be obtained while reducing the amount of stuffed concrete.

本発明の一実施形態について、パネルユニットの橋脚への架設の状態を示したもので、(a)は架設された状態の平面図、(b)は一方のパネルユニットが架設され、他方のパネルユニットが架設される直前の断面図、(c)は双方のパネルユニットが架設された状態の断面図である。The embodiment of the present invention shows a state where the panel unit is installed on the pier, (a) is a plan view of the installed state, (b) is one panel unit is installed, the other panel Sectional view immediately before the unit is erected, (c) is a sectional view in a state where both panel units are erected. 両側のパネルユニットが架設された状態で、間のパネルユニットを架設する様子を示した斜視図である。It is the perspective view which showed a mode that the panel unit of between was installed in the state in which the panel unit of both sides was constructed. 本発明の継手構造の他の実施形態における橋軸方向の断面図である。It is sectional drawing of the bridge axis direction in other embodiment of the joint structure of this invention. 本発明の継手構造のさらに他の実施形態における橋軸方向の断面図である。It is sectional drawing of the bridge axis direction in other embodiment of the joint structure of this invention. 本発明の継手構造のさらに他の実施形態における橋軸方向の断面図である。It is sectional drawing of the bridge axis direction in other embodiment of the joint structure of this invention. 本発明が適用される合成パネル橋梁の架設における施工手順を示す斜視図である。It is a perspective view which shows the construction procedure in construction of the composite panel bridge to which this invention is applied. 図6に続く施工手順を示す斜視図である。It is a perspective view which shows the construction procedure following FIG. 図7に続く施工手順を示す斜視図である。It is a perspective view which shows the construction procedure following FIG. 図8に続く施工手順を示す斜視図である。It is a perspective view which shows the construction procedure following FIG. 図9に続く施工手順を示す斜視図である。It is a perspective view which shows the construction procedure following FIG. 図10に続く施工手順を示す斜視図である。It is a perspective view which shows the construction procedure following FIG. 図11に続く施工手順を示す斜視図である。It is a perspective view which shows the construction procedure following FIG. 図12に続く施工手順を示す斜視図である。It is a perspective view which shows the construction procedure following FIG. 図13に続く施工手順を示す斜視図である。It is a perspective view which shows the construction procedure following FIG. 本発明の継手構造の他の実施形態(一部のパネルユニットは橋軸方向の主桁を有さない場合)における施工手順を示した斜視図である。It is the perspective view which showed the construction procedure in other embodiment (when some panel units do not have the main girder of a bridge axis direction) of the joint structure of this invention. 図15に続く施工手順を示した斜視図である。It is the perspective view which showed the construction procedure following FIG. 図16に続く施工手順を示した斜視図である。It is the perspective view which showed the construction procedure following FIG. 図16で用いられるパネルユニットを拡大して示した斜視図である。It is the perspective view which expanded and showed the panel unit used in FIG. 図17に続く施工手順を示した斜視図である。It is the perspective view which showed the construction procedure following FIG. 図19で用いられるパネルユニットを拡大して示した斜視図である。It is the perspective view which expanded and showed the panel unit used in FIG.

以下、本発明の具体的な実施形態を添付図面に基づいて説明する。
図1は本発明の継手構造の一実施形態について、パネルユニット1(プレキャスト合成パネルユニット)の橋脚への架設の状態を示したもので、図2は両側のパネルユニット1a、1cが架設された状態で、間にパネルユニット1bを架設する様子を示した斜視図である。
Hereinafter, specific embodiments of the present invention will be described with reference to the accompanying drawings.
FIG. 1 shows a state in which a panel unit 1 (precast composite panel unit) is installed on a bridge pier according to an embodiment of the joint structure of the present invention. FIG. 2 shows that both panel units 1a and 1c are installed. It is the perspective view which showed a mode that the panel unit 1b was constructed in the state.

パネルユニット1は、図2および後述する図6〜図14に示すように、1径間(橋台11と橋脚12間、または隣り合う橋脚12間の距離に相当)に相当する長さを有する橋軸方向の主桁2と、主桁2の上面に固定された底鋼板3と、底鋼板3の上面に橋軸方向に間隔をおいて配置された複数の形鋼(本実施例ではI形鋼4)と、底鋼板3の上面に打設された床版コンクリート5とを構成要素とする。   The panel unit 1 has a length corresponding to one span (corresponding to a distance between the abutment 11 and the pier 12 or between the adjacent piers 12) as shown in FIG. 2 and FIGS. A main girder 2 in the axial direction, a bottom steel plate 3 fixed to the upper surface of the main girder 2, and a plurality of sections (I-shape in this embodiment) arranged on the upper surface of the bottom steel plate 3 at intervals in the bridge axis direction. Steel 4) and floor slab concrete 5 placed on the upper surface of the bottom steel plate 3 are used as constituent elements.

このパネルユニット1を橋台11と橋脚12または橋脚12間に架設し、橋軸直角方向に複数並列配置して連結し、橋軸方向にも複数径間架設して行くことで鋼コンクリート合成構造の合成パネル橋梁が構築される。   This panel unit 1 is installed between the abutment 11 and the pier 12 or the pier 12 and connected in parallel in a direction perpendicular to the bridge axis, and a plurality of spans are installed in the bridge axis direction. A composite panel bridge is constructed.

なお、図示した実施例は、既設橋梁の老朽化に対し橋梁の床版の架け替え工事を行う場合を想定した例であり、橋脚12の既設の支承14上に橋軸直角方向の横桁15を設置し、パネルユニット1を構成する主桁2を橋台11上に設置した支承13と橋脚12の横桁15間に架設する構造としている。主桁2の横桁15への架設部分は、主桁2の上フランジ側の一部が突出部2aとして残された形で切欠かれた形状となっており、この突出部2aを横桁15の上面に載置している。   The illustrated embodiment is an example in which a bridge floor slab is replaced when the existing bridge is aged, and a cross beam 15 in a direction perpendicular to the bridge axis is placed on the existing support 14 of the pier 12. The main girder 2 constituting the panel unit 1 is constructed between the support 13 installed on the abutment 11 and the cross girder 15 of the pier 12. The portion of the main girder 2 that extends to the cross beam 15 has a shape in which a part of the upper flange side of the main girder 2 is left as a protruding portion 2a. It is placed on the top surface of the.

パネルユニット1を構成する床版コンクリート5の橋軸直角方向の継手面は平面視で凹凸形状に形成されており、前述のI形鋼4が継手面の凹凸形状の凸部6から突出しており、図1に示すように橋軸直角方向に隣り合うパネルユニット1どうしのうちの一方のパネルユニット1の継手位置では、凸部6およびI形鋼4の端部が底鋼板3の端部より内側に位置しており、他方のパネルユニット1の継手位置では、凸部6およびI形鋼4の端部が底鋼板3の端部より外側に張り出している。   The joint surface in the direction perpendicular to the bridge axis of the floor slab concrete 5 constituting the panel unit 1 is formed in a concavo-convex shape in plan view, and the I-shaped steel 4 protrudes from the concavo-convex convex portion 6 of the joint surface. As shown in FIG. 1, at the joint position of one of the panel units 1 adjacent to each other in the direction perpendicular to the bridge axis, the end of the convex portion 6 and the I-shaped steel 4 are more than the end of the bottom steel plate 3. At the joint position of the other panel unit 1, the convex portion 6 and the end of the I-shaped steel 4 protrude outward from the end of the bottom steel plate 3.

そして、一方のパネルユニット1の底鋼板3上に、他方のパネルユニット1の凸部6およびI形鋼4の端部の張出し部が載った状態で、双方のパネルユニット1の床版コンクリートの凸部6およびI形鋼4の端部が橋軸方向に交互に位置し、橋軸方向にみて双方のI形鋼4の端部オーバーラップした状態で、継手部に間詰めコンクリート9が打設されている。   And in the state where the protruding part 6 of the other panel unit 1 and the overhanging part of the end of the I-shaped steel 4 are placed on the bottom steel plate 3 of one panel unit 1, the floor slab concrete of both panel units 1 is placed. With the protrusions 6 and the ends of the I-shaped steel 4 positioned alternately in the direction of the bridge axis, the ends of the both I-shaped steels 4 overlapped when viewed in the direction of the bridge axis. It is installed.

なお、図示した実施例において、継手部で隣接する底鋼板3の端部どうしは、図1に示すように、あらかじめ一方のパネルユニット1の底鋼板3の端部に取り付けておいた添接板7とボルト8を介して接合されるようになっているが、これに限定されるものではない。   In the illustrated embodiment, the end portions of the bottom steel plates 3 adjacent to each other at the joint portion are attached to the end portions of the bottom steel plate 3 of one panel unit 1 in advance as shown in FIG. However, the present invention is not limited to this.

このように、橋軸直角方向に並列するパネルユニット1に内蔵された補剛桁の機能を有するI形鋼4の端部が隣り合うパネルユニット1間の継手部に突出し、双方のパネルユニット1のI形鋼4の端部がオーバーラップする形で間詰めコンクリート9内に配置されるため、強固な継手構造が得られる。   In this way, the ends of the I-shaped steel 4 having the function of a stiffening girder built in the panel unit 1 arranged in parallel to the direction perpendicular to the bridge axis project into the joint between the adjacent panel units 1, and both panel units 1 Since the ends of the I-shaped steel 4 are arranged in the interstitial concrete 9 so as to overlap, a strong joint structure can be obtained.

なお、必要に応じ、この継手部の間詰めコンクリート9内に橋軸方向の緊張材を配置して間詰めコンクリート9の橋軸方向のはらみ出しの抑制を図ることもできる。   In addition, if necessary, a tension member in the bridge axis direction can be arranged in the jointed concrete 9 of the joint portion so as to suppress the protruding concrete 9 in the bridge axis direction.

また、隣り合う双方のパネルユニット1の継手面の凹凸形状をフィンガージョイントのように噛み合わせる形でI形鋼4の端部が他方のパネルユニット1の継手面の凹部に納まるため、この部分に充填される間詰めコンクリート9の打設量を少なくしつつ強固な接合構造が得られる。   Moreover, since the edge part of I-shaped steel 4 fits into the recessed part of the joint surface of the other panel unit 1 in the form which mesh | engages the uneven | corrugated shape of the joint surface of both adjacent panel units 1 like a finger joint, in this part A firm joint structure can be obtained while reducing the amount of placement concrete 9 to be filled.

図3は、本発明の継手構造の他の実施形態における継手部分の橋軸方向の断面を示したものである。図3の例ではパネルユニット1を構成する床版コンクリート5の継手面の凸部6の橋軸直角方向の断面形状が上方向に広がる逆台形状となるように凸部6の側面にテーパーを設けている。   FIG. 3 shows a cross-section in the bridge axis direction of a joint portion in another embodiment of the joint structure of the present invention. In the example of FIG. 3, the side surface of the convex portion 6 is tapered so that the cross-sectional shape in the direction perpendicular to the bridge axis of the convex portion 6 of the joint surface of the floor slab concrete 5 constituting the panel unit 1 is an upward trapezoidal shape. Provided.

このような逆台形状の断面形状とすることで、継手部に後から打設される間詰めコンクリート9の上方への抜け出しを拘束する効果が得られる。   By adopting such an inverted trapezoidal cross-sectional shape, an effect of restraining upward slipping of the padded concrete 9 to be placed later on the joint portion is obtained.

図4は、本発明の継手構造のさらに他の実施形態における継手部分の橋軸方向の断面を示したものである。図4の例は凸部6の橋軸直角方向の断面形状において、両側が凹凸形状となるようにして、継手部に後から打設される間詰めコンクリート9の上方への抜け出しを拘束するとともに、床版コンクリート5と間詰めコンクリート9の一体性の強化を図ったものである。   FIG. 4 shows a cross-section in the bridge axis direction of a joint portion in still another embodiment of the joint structure of the present invention. In the example of FIG. 4, in the cross-sectional shape of the convex portion 6 in the direction perpendicular to the bridge axis, both sides are concave and convex so as to restrain the interstitial concrete 9 from being pulled out to the upper portion of the joint portion afterward. The integration of the floor slab concrete 5 and the interstitial concrete 9 is reinforced.

図5は、図4の実施形態に対し、床版コンクリート5の凸部6の側面における上下方向の凹凸形状の凹凸を逆にした場合であり、効果は図4の場合とほぼ同様である。   FIG. 5 shows a case where the unevenness of the uneven shape in the vertical direction on the side surface of the convex portion 6 of the floor slab concrete 5 is reversed with respect to the embodiment of FIG. 4, and the effect is almost the same as the case of FIG.

図6〜図14は、図2で説明した本発明が適用される合成パネル橋梁の架設における施工手順を参考的に示したものであり、以下の手順で施工が行われる。   FIGS. 6-14 shows the construction procedure in construction of the composite panel bridge to which this invention demonstrated in FIG. 2 is applied, and construction is performed in the following procedures.

(1) 横桁15の設置(図6〜7参照)
既設の床版を取り除いた橋台11上に主桁2の配置に応じた支承13を設置する。橋脚12側については、既設の支承14を使用し、支承14の上に、橋軸直角方向の横桁15を設置する。
(1) Installation of the horizontal beam 15 (see Figs. 6-7)
A support 13 corresponding to the arrangement of the main girder 2 is installed on the abutment 11 from which the existing floor slab has been removed. On the pier 12 side, an existing support 14 is used, and a cross beam 15 in a direction perpendicular to the bridge axis is installed on the support 14.

(2) パネルユニット1aの架設(図8〜9参照)
パネルユニット1aを構成する主桁2を橋台11上に設置した支承13と橋脚12の横桁15間に架設する。主桁2の横桁15への架設部分は、図2で説明したように、主桁2の上フランジ側の一部が突出部2aとして残された形で切欠かれた形状となっており、この突出部2aを横桁15の上面に架設する。
(2) Installation of panel unit 1a (see Figs. 8-9)
The main girder 2 constituting the panel unit 1a is installed between the support 13 installed on the abutment 11 and the horizontal girder 15 of the pier 12. As described with reference to FIG. 2, the portion of the main girder 2 installed on the horizontal girder 15 has a shape that is notched in such a way that a part of the upper flange side of the main girder 2 is left as the protruding portion 2a. This protruding portion 2 a is installed on the upper surface of the cross beam 15.

パネルユニット1aは、図2に示すように、凸部6およびI形鋼4の端部が底鋼板3の端部より内側に位置している。   As shown in FIG. 2, the panel unit 1 a has the convex portions 6 and the end portions of the I-shaped steel 4 positioned inside the end portions of the bottom steel plate 3.

(3) パネルユニット1cの架設(図10〜11参照)
同様に、凸部6およびI形鋼4の端部が底鋼板3の端部より内側に位置しているパネルユニット1cを橋台11上に設置した支承13と橋脚12の横桁15間に架設する。
(3) Installation of the panel unit 1c (see Figs. 10-11)
Similarly, the panel unit 1c in which the end portions of the convex portion 6 and the I-shaped steel 4 are located inside the end portion of the bottom steel plate 3 is installed between the support 13 on the abutment 11 and the cross beam 15 of the pier 12. To do.

(4) パネルユニット1cの架設(図12〜14参照)
凸部6およびI形鋼4の端部が底鋼板3の端部より外側に張り出しているパネルユニット1cを橋台11上に設置した支承13と橋脚12の横桁15間に架設する。
(4) Installation of panel unit 1c (see Figs. 12-14)
A panel unit 1c in which the end portions of the convex portion 6 and the I-shaped steel 4 project outward from the end portion of the bottom steel plate 3 is installed between the support 13 installed on the abutment 11 and the cross beam 15 of the pier 12.

パネルユニット1bの架設により、パネルユニット1bの両側の凸部6およびI形鋼4の端部が両側のパネルユニット1a、1cの底鋼板3上に載る。隣接する底鋼板3どうしは図1で説明したように、添接板7とボルト8を介して接合する。   By installing the panel unit 1b, the convex portions 6 on both sides of the panel unit 1b and the ends of the I-shaped steel 4 are placed on the bottom steel plates 3 of the panel units 1a and 1c on both sides. Adjacent bottom steel plates 3 are joined to each other via a contact plate 7 and bolts 8 as described in FIG.

(5) 間詰めコンクリート9の打設
両側からI形鋼4が突出する凹凸形状の継手部に図1に示される間詰めコンクリート9を打設する。
(5) Placing the interstitial concrete 9 The interstitial concrete 9 shown in FIG. 1 is cast in the concave and convex joints from which the I-shaped steel 4 protrudes from both sides.

以上の作業により、橋台11と橋脚12間の1径間の床版パネルの架設が完了する。続く径間についても基本的には同様の手順で施工を行うことができる。   With the above operation, the installation of the floor slab panel of one diameter between the abutment 11 and the pier 12 is completed. For the subsequent span, construction can be basically performed in the same procedure.

図15〜図20は、本発明の継手構造の他の実施形態として、一部のパネルユニットは橋軸方向の主桁を有さない場合における施工手順とパネルユニットの構造を示したものである。   FIGS. 15 to 20 show the construction procedure and the structure of the panel unit when some panel units do not have a main girder in the bridge axis direction as other embodiments of the joint structure of the present invention. .

一部のパネルユニットについて、橋軸方向の主桁を有さないパネルユニット1´を用いる点以外は、基本的に前述の実施形態と同様である。   Some of the panel units are basically the same as those in the above-described embodiment except that the panel unit 1 ′ having no main beam in the bridge axis direction is used.

(1) 横桁15の設置(図15、図16参照)
既設の床版と橋桁を取り除いた橋台11上に主桁2の配置に応じた支承13を設置する。橋脚12への橋軸直角方向の横桁15の設置については、前述の実施形態と同様、既設の支承14を使用し、支承14の上に、橋軸直角方向の横桁15を設置する。
(1) Installation of the horizontal girder 15 (see Figs. 15 and 16)
A support 13 according to the arrangement of the main girder 2 is installed on the abutment 11 from which the existing floor slab and bridge girder are removed. As for the installation of the cross beam 15 in the direction perpendicular to the bridge axis on the pier 12, the existing support 14 is used, and the cross beam 15 in the direction perpendicular to the bridge axis is installed on the support 14, as in the above-described embodiment.

(2) 主桁2を一体化したパネルユニット1の架設(図17、図18参照)
パネルユニット1を構成する主桁2を橋脚12上に設置した横桁15間に架設する。なお、パネルユニット1の片端が横桁15を介さず、直接、橋台または橋脚上の支承上に架設される場合もある。
(2) Installation of panel unit 1 with main girder 2 integrated (see Figs. 17 and 18)
The main girder 2 constituting the panel unit 1 is installed between horizontal beams 15 installed on the pier 12. In some cases, one end of the panel unit 1 is directly installed on a support on an abutment or a pier without passing through the cross beam 15.

(3) 主桁2を有さないパネルユニット1´の架設(図19、図20参照)
本実施形態では、主桁2を有さないパネルユニット1´も用いており、先に架設したパネルユニット1´間に、主桁2を有さないパネルユニット1´に架設して行く。
(3) Installation of panel unit 1 'without main girder 2 (see Figs. 19 and 20)
In the present embodiment, a panel unit 1 ′ not having the main beam 2 is also used, and the panel unit 1 ′ having no main beam 2 is installed between the previously installed panel units 1 ′.

その他の構成および施工手順は、基本的に前述の実施形態と同様であるので、共通する事項の説明は省略する。   Other configurations and construction procedures are basically the same as those in the above-described embodiment, and thus description of common matters is omitted.

1…パネルユニット、2…主桁、2a…突出部、3…底鋼板、4…I形鋼、5…床版コンクリート、6…凸部、7…添接板、8…ボルト、9…間詰めコンクリート、
11…橋台、12…橋脚、13…支承、14…支承、15…横桁
DESCRIPTION OF SYMBOLS 1 ... Panel unit, 2 ... Main girder, 2a ... Protruding part, 3 ... Bottom steel plate, 4 ... I-shaped steel, 5 ... Floor slab concrete, 6 ... Convex part, 7 ... Connecting plate, 8 ... Bolt, 9 ... Between Stuffed concrete,
11 ... Abutment, 12 ... Bridge pier, 13 ... Support, 14 ... Support, 15 ... Horizontal girder

Claims (6)

1径間に相当する長さを有する橋軸方向の主桁と、前記主桁の上面に固定された底鋼板と、前記底鋼板の上面に橋軸方向に間隔をおいて配置された複数の形鋼と、前記底鋼板の上面に打設された床版コンクリートとを構成要素とするプレキャスト合成パネルユニットが橋軸直角方向に複数並列配置されて連結されてなる合成パネル橋梁の橋軸直角方向の継手構造であって、
前記床版コンクリートの橋軸直角方向の継手面は平面視で凹凸形状に形成されており、前記形鋼が前記継手面の凹凸形状の凸部から突出しており、
橋軸直角方向に隣り合うパネルユニットどうしのうちの一方のプレキャスト合成パネルユニットの継手位置では、前記凸部および前記形鋼の端部が前記底鋼板の端部より内側に位置しており、他方のプレキャスト合成パネルユニットの継手位置では、前記凸部および前記形鋼の端部が前記底鋼板の端部より外側に張り出しており、
前記一方のプレキャスト合成パネルユニットの底鋼板上に、前記他方のプレキャスト合成パネルユニットの前記凸部および前記形鋼の端部の張出し部が、双方のプレキャスト合成パネルユニットの床版コンクリートの凸部および形鋼の端部が橋軸方向に交互に位置するように配置され、双方の形鋼の端部を橋軸方向にみてオーバーラップするように配置した状態で、継手部に間詰めコンクリートが打設されている
ことを特徴とする合成パネル橋梁の橋軸直角方向の継手構造。
A main girder in the bridge axis direction having a length corresponding to one diameter, a bottom steel plate fixed to the upper surface of the main girder, and a plurality of plates arranged at intervals on the upper surface of the bottom steel plate in the bridge axis direction The direction perpendicular to the bridge axis of a composite panel bridge in which a plurality of precast composite panel units, each of which includes a structural steel and floor slab concrete placed on the top surface of the bottom steel plate, are arranged in parallel in the direction perpendicular to the bridge axis. The joint structure of
The joint surface in the direction perpendicular to the bridge axis of the floor slab concrete is formed in a concavo-convex shape in plan view, and the shape steel protrudes from the concavo-convex convex portion of the joint surface,
At the joint position of one precast composite panel unit among the panel units adjacent to each other in the direction perpendicular to the bridge axis, the end of the convex portion and the shape steel is located on the inner side of the end of the bottom steel plate, In the joint position of the precast composite panel unit, the protruding portion and the end of the shape steel protrude outward from the end of the bottom steel plate,
On the bottom steel plate of the one precast composite panel unit, the projecting portion of the other precast composite panel unit and the protruding portion of the end of the shape steel are the convex portions of the floor slab concrete of both precast composite panel units and With the ends of the section steels arranged alternately in the direction of the bridge axis and with the ends of both sections shaped so as to overlap when viewed in the direction of the bridge axis, the interstitial concrete is cast into the joint. A joint structure in the direction perpendicular to the bridge axis of a composite panel bridge.
請求項1記載の合成パネル橋梁の橋軸直角方向の継手構造において、橋軸直角方向に複数並列配置されて連結されてなる前記プレキャスト合成パネルユニットのうち、一部のプレキャスト合成パネルユニットは前記橋軸方向の主桁を有さず、底鋼板と、前記底鋼板の上面に橋軸方向に間隔をおいて配置された複数の形鋼と、前記底鋼板の上面に打設された床版コンクリートとを構成要素とするプレキャスト合成パネルユニットであることを特徴とする合成パネル橋梁の橋軸直角方向の継手構造。   2. The joint structure of the composite panel bridge according to claim 1, wherein a plurality of precast composite panel units are connected in parallel with each other in a direction perpendicular to the bridge axis. Floor slab concrete that does not have a main girder in the axial direction, a bottom steel plate, a plurality of section steels arranged on the top surface of the bottom steel plate at intervals in the bridge axis direction, and is placed on the top surface of the bottom steel plate A joint structure in the direction perpendicular to the bridge axis of a composite panel bridge, characterized in that it is a precast composite panel unit with and as components. 請求項1または2記載の合成パネル橋梁の橋軸直角方向の継手構造において、前記凸部の橋軸直角方向の断面が上方向に広がる逆台形状であることを特徴とする合成パネル橋梁の橋軸直角方向の継手構造。   3. A composite panel bridge bridge according to claim 1 or 2, wherein a cross section of the convex portion in the direction perpendicular to the bridge axis has an inverted trapezoidal shape extending upward. Joint structure in the direction perpendicular to the axis. 請求項1または2記載の合成パネル橋梁の橋軸直角方向の継手構造において、前記凸部の橋軸直角方向の断面の両側が凹凸形状であることを特徴とする合成パネル橋梁の橋軸直角方向の継手構造。   3. A joint structure in a direction perpendicular to the bridge axis of the composite panel bridge according to claim 1 or 2, wherein both sides of the cross section in the direction perpendicular to the bridge axis of the convex part are uneven. Joint structure. 請求項1〜4のいずれか一項に記載の合成パネル橋梁の橋軸直角方向の継手構造において、前記形鋼はI形鋼であることを特徴とする合成パネル橋梁の橋軸直角方向の継手構造。   The joint structure in the direction perpendicular to the bridge axis of the composite panel bridge according to any one of claims 1 to 4, wherein the shape steel is an I-shaped steel. Construction. 請求項1〜5のいずれか一項に記載の合成パネル橋梁の橋軸直角方向の継手構造を備えた合成パネル橋梁の橋軸直角方向の継手部の施工方法であって、
橋台と橋脚または橋脚間に前記一方のプレキャスト合成パネルユニットを架設した後、前記他方のプレキャスト合成パネルユニットを、前記凸部および前記形鋼の端部の張出し部が前記一方のプレキャスト合成パネルユニットの底鋼板上に載置され、双方のプレキャスト合成パネルユニットの凸部および形鋼の端部が橋軸方向に交互に位置するように橋台または橋脚間に架設し、双方の形鋼の端部が橋軸方向にみてオーバーラップするようにして、継手部に間詰めコンクリートを打設することを特徴とする合成パネル橋梁の橋軸直角方向の継手部の施工方法。
A construction method for a joint portion in a direction perpendicular to the bridge axis of a composite panel bridge comprising the joint structure in a direction perpendicular to the bridge axis of the composite panel bridge according to any one of claims 1 to 5,
After the one precast composite panel unit is installed between the abutment and the pier or the pier, the other precast composite panel unit is connected to the projecting portion and the protruding portion of the end of the shape steel of the one precast composite panel unit. It is placed on the bottom steel plate, and it is installed between the abutment or the pier so that the convex part of both precast composite panel units and the end of the shape steel are alternately located in the bridge axis direction. A method for constructing a joint part in a direction perpendicular to the bridge axis of a composite panel bridge, characterized in that interstitial concrete is cast in the joint part so as to overlap in the bridge axis direction.
JP2018093559A 2018-05-15 2018-05-15 Joint structure of precast composite floor slab perpendicular to the bridge axis and its construction method Active JP6375079B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2018093559A JP6375079B1 (en) 2018-05-15 2018-05-15 Joint structure of precast composite floor slab perpendicular to the bridge axis and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2018093559A JP6375079B1 (en) 2018-05-15 2018-05-15 Joint structure of precast composite floor slab perpendicular to the bridge axis and its construction method

Publications (2)

Publication Number Publication Date
JP6375079B1 true JP6375079B1 (en) 2018-08-15
JP2019199710A JP2019199710A (en) 2019-11-21

Family

ID=63165874

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2018093559A Active JP6375079B1 (en) 2018-05-15 2018-05-15 Joint structure of precast composite floor slab perpendicular to the bridge axis and its construction method

Country Status (1)

Country Link
JP (1) JP6375079B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110184901A (en) * 2019-06-20 2019-08-30 福州大学 Seamless bridge corbel back slab construction and its design method with X-shaped steel muscle
CN111305065A (en) * 2020-04-01 2020-06-19 中铁第一勘察设计院集团有限公司 Assembled bridge protection plate structure system and construction method thereof
JP2020100967A (en) * 2018-12-20 2020-07-02 鹿島建設株式会社 Fixed structure of main girder and precast slab and method of fixing main girder and precast slab
JP2021042637A (en) * 2019-09-13 2021-03-18 鹿島建設株式会社 Joint structure

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7366806B2 (en) * 2020-03-10 2023-10-23 株式会社大林組 connection structure

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3908642B2 (en) * 2002-10-15 2007-04-25 新日本製鐵株式会社 Composite panel structure and panel bridge structure and construction method of continuous composite girder bridge
JP5667546B2 (en) * 2011-04-08 2015-02-12 横河工事株式会社 Precast floor slab and its joint structure and connection method
JP5718133B2 (en) * 2011-04-08 2015-05-13 横河工事株式会社 Precast floor slab and its joint structure

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020100967A (en) * 2018-12-20 2020-07-02 鹿島建設株式会社 Fixed structure of main girder and precast slab and method of fixing main girder and precast slab
JP7178895B2 (en) 2018-12-20 2022-11-28 鹿島建設株式会社 Fixing structure between main girder and precast floor slab and fixing method between main girder and precast floor slab
CN110184901A (en) * 2019-06-20 2019-08-30 福州大学 Seamless bridge corbel back slab construction and its design method with X-shaped steel muscle
CN110184901B (en) * 2019-06-20 2024-02-06 福州大学 Seamless bridge approach plate structure with X-shaped reinforcing steel bars and design method thereof
JP2021042637A (en) * 2019-09-13 2021-03-18 鹿島建設株式会社 Joint structure
JP7254007B2 (en) 2019-09-13 2023-04-07 鹿島建設株式会社 junction structure
CN111305065A (en) * 2020-04-01 2020-06-19 中铁第一勘察设计院集团有限公司 Assembled bridge protection plate structure system and construction method thereof

Also Published As

Publication number Publication date
JP2019199710A (en) 2019-11-21

Similar Documents

Publication Publication Date Title
JP6375079B1 (en) Joint structure of precast composite floor slab perpendicular to the bridge axis and its construction method
JP2009041227A (en) Structure and method for joining precast floor slabs together
KR101652664B1 (en) Precast deckplate and composite slab and concrete slab manufacturing method using the same
JP2012077471A (en) Joint structure of precast members and concrete precast members
JP2001342611A (en) Bridge girder
KR102597084B1 (en) Steel Ccomposite Rahmen Bridge Structure and its Construction Method
KR101962574B1 (en) Steel-Composite Girder with Precast Concrete Beam and Bridge with the Same
KR20140144035A (en) The hybrid girder structures prestressed by using the external prestressing mechanism, and the construction method by rigid connection
JP7169152B2 (en) Joint structure of precast concrete members
JP2014105547A (en) Structure for fixing precast floor slab
JP5372587B2 (en) Steel / concrete composite floor slab
JP4406879B2 (en) Bridge girder construction method
JP2010261270A (en) Construction method of composite structure and composite structure building
KR101402620B1 (en) Construction method of slab type rahmen birdge using Half-PC slab for slab bridge
KR20080111686A (en) Bridge and slab integrated PHC composite girder using PHC girder
KR100554342B1 (en) Perforated plate and manufacturing method thereof
JP5508070B2 (en) Joining structure and joining method of steel member and concrete member
JP6918469B2 (en) Construction method of precast member, erection structure of precast member, erection structure of precast member
JP4293696B2 (en) Construction method of composite floor slab bridge
JP7157092B2 (en) Construction method of precast concrete structure
KR101639592B1 (en) Prefabricated lightweight girder and the bridge construction method using the same
KR102200400B1 (en) Precast segment, pillar structure including the same and construction method of pillar structure usinging the same
JP4413763B2 (en) Bridge web unit and main girder manufacturing method using the web unit
JP2508677B2 (en) Reinforcement method of bridge reinforced concrete slab
JP2008088634A (en) Steel concrete composite slab

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180515

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20180515

A80 Written request to apply exceptions to lack of novelty of invention

Free format text: JAPANESE INTERMEDIATE CODE: A80

Effective date: 20180612

TRDD Decision of grant or rejection written
A975 Report on accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A971005

Effective date: 20180706

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20180717

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20180720

R150 Certificate of patent or registration of utility model

Ref document number: 6375079

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250