JP6298688B2 - Embankment - Google Patents

Embankment Download PDF

Info

Publication number
JP6298688B2
JP6298688B2 JP2014075282A JP2014075282A JP6298688B2 JP 6298688 B2 JP6298688 B2 JP 6298688B2 JP 2014075282 A JP2014075282 A JP 2014075282A JP 2014075282 A JP2014075282 A JP 2014075282A JP 6298688 B2 JP6298688 B2 JP 6298688B2
Authority
JP
Japan
Prior art keywords
steel
footing
concrete composite
concrete
precast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2014075282A
Other languages
Japanese (ja)
Other versions
JP2015196983A (en
Inventor
貴志 岩川
貴志 岩川
竹内 大輔
大輔 竹内
卓弥 松尾
卓弥 松尾
Original Assignee
株式会社横河住金ブリッジ
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社横河住金ブリッジ filed Critical 株式会社横河住金ブリッジ
Priority to JP2014075282A priority Critical patent/JP6298688B2/en
Publication of JP2015196983A publication Critical patent/JP2015196983A/en
Application granted granted Critical
Publication of JP6298688B2 publication Critical patent/JP6298688B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Description

本発明は、海岸や河岸などに設けられ、津波や洪水等による水災害を防ぐ防波堤、防潮堤を構築したり、既存の堤防を嵩上げたりするのに好適な堤体に関する。   The present invention relates to an embankment suitable for building a breakwater, a tide embankment, or raising an existing embankment that is provided on a coast or a riverbank and prevents water disasters caused by tsunamis, floods, and the like.

日本は台風の進路上に位置するため毎年台風が襲来し河川等の氾濫による洪水を引き起こしている。また、2011年3月11日に発生した東日本大震災では、想定外の大津波により堤防が決壊したり海水が堤防を乗り越えるなどして想定外の壊滅的な被害をもたらし、津波対策も考慮して構築されたものでも既存の防波堤、防潮堤等の堤防では不十分であることが判明した。   Since Japan is located on the course of typhoons, typhoons hit every year, causing flooding due to river flooding. Also, in the Great East Japan Earthquake that occurred on March 11, 2011, the dyke broke down due to an unexpected large tsunami, and seawater crossed the levee, causing unexpected catastrophic damage. Even the constructed ones were found to be inadequate with existing breakwaters such as breakwaters and seawalls.

そのため、大津波を想定した堤防の構築が緊急課題となっており、既存堤防の嵩上げが図られたり、新たな堤防の開発が行われている。新たに開発される堤防の中には、プレキャスト化された壁体によるもの、コンクリート躯体によるものもある。   For this reason, the construction of a dike that assumes a large tsunami is an urgent issue, and the existing dike is being raised or a new dike is being developed. Some newly developed dikes are due to precast walls and concrete frames.

プレキャスト化された壁体によるものとしては、例えば、特許文献1がある。ここには、「鋼管杭と、該鋼管杭に支持されたフーチングと、該フーチングの上方に配置され、面内方向に貫通する壁体貫通孔を有し、該壁体貫通孔の内面には壁体さや管を有するプレキャスト壁体と、を備えた堤体であって、前記フーチングは厚さ方向に貫通するフーチング貫通孔を有し、該フーチング貫通孔の内面にはフーチングさや管が備えられ、該フーチングさや管は前記フーチングの上面よりも上方の位置まで延伸し、該フーチングさや管に前記鋼管杭が差し込まれ、前記フーチングさや管は前記プレキャスト壁体の前記壁体さや管に差し込まれ、前記フーチングさや管と該フーチングさや管に差し込まれた前記鋼管杭との間隙にはグラウト材が充填されていることを特徴とする堤体」が記載されている。   For example, Patent Document 1 discloses a precast wall body. This includes “a steel pipe pile, a footing supported by the steel pipe pile, and a wall body through hole that is disposed above the footing and penetrates in the in-plane direction. A precast wall body having a wall sheath and a pipe, wherein the footing has a footing through hole penetrating in a thickness direction, and an inner surface of the footing through hole is provided with a footing sheath. The footing sheath extends to a position above the upper surface of the footing, the steel pipe pile is inserted into the footing sheath, the footing sheath is inserted into the wall sheath of the precast wall, There is described “a dam body characterized in that a grout material is filled in a gap between the footing sheath and the pipe and the steel pipe pile inserted into the footing sheath”.

また、コンクリート躯体によるものとしては、例えば、特許文献2がある。ここには、「地盤中に貫入された鋼管杭の上端にフーチングを構築し、該フーチングの上に堤体を立設した防潮堤において、前記堤体を構成するコンクリート躯体の表面に鋼板パネルを配置し、該鋼板パネルと前記コンクリート躯体とを一体に接合したことを特徴とする防潮堤」が記載されている。   Moreover, as a thing by a concrete frame, there exists patent document 2, for example. Here, “a footing is constructed at the upper end of a steel pipe pile that has penetrated into the ground, and a steel plate panel is placed on the surface of the concrete frame that constitutes the dam body in a tide embankment in which a levee body is erected on the footing. There is described a “sea levee characterized in that the steel plate panel and the concrete frame are integrally joined to each other”.

また、堤防の嵩上げに関するものとしては、例えば、特許文献3がある。ここには、「河川や海岸等の各種水域に設置された既設堤を嵩上げするための嵩上げ堤において、断面略コ字形で前記既設堤方向に開口部を有し、前記既設堤の上端部との間に中空部を形成する平板連結体と、前記平板連結体の内側に突出し、前記既設提の上端部に当接して既設提に対する垂直方向の位置を決める位置決め部と、前記平板連結体の両側板を前記既設堤の上部両側壁に固定する固定部材とからなることを特徴とする嵩上げ堤」が記載されている。   Moreover, there exists patent document 3 as a thing regarding the raising of the embankment, for example. Here, "in the uplift bank for raising the existing levee installed in various water areas such as rivers and coasts, has an opening in the direction of the existing dam with a substantially U-shaped cross section, and the upper end of the existing levee A flat plate connecting body forming a hollow portion therebetween, a positioning portion that protrudes inside the flat plate connecting body, abuts on an upper end portion of the existing lantern and determines a vertical position with respect to the existing lantern, and There is described "raised levee characterized by comprising fixing members for fixing both side plates to upper both side walls of the existing levee".

一方、震災復興に際して、沿岸部へのコンクリートの供給不足、人手不足(熟練工の不足)、道路事情による大型部材、重量部材の陸上輸送の困難性、輸送コストの増大などが叫ばれており、既存堤防の嵩上げや新たな堤防の構築を行う場合も、これらのことを考慮する必要がある。   On the other hand, during the reconstruction of the earthquake disaster, there have been calls for shortage of concrete supply to the coast, lack of manpower (insufficiency of skilled workers), large parts due to road conditions, difficulty in transporting heavy parts on land, and increased transportation costs. These also need to be taken into account when raising an existing levee or constructing a new levee.

特許第5024489号公報Japanese Patent No. 5024489 特開2013−234449号公報JP 2013-234449 A 特開2006−45814号公報JP 2006-45814 A

本発明は、上述のような背景・課題を鑑みて成したものであり、大津波にも対応可能な強固で高品質なものであるとともに、資材や部材の陸上輸送が可能であり、施工が熟練工を必要とせず容易であり、場所打ちコンクリートによる施工を少なくして施工現場でコンクリート使用量をできるだけ抑制した堤体を提供することを目的とするものである。   The present invention has been made in view of the background and problems as described above, and is strong and high-quality capable of dealing with large tsunamis, and can be used for land transportation of materials and members. The purpose of the present invention is to provide a levee body that does not require a skilled worker, is easy, reduces the amount of cast-in-place concrete, and suppresses the amount of concrete used at the construction site as much as possible.

本願の請求項1に係る堤体は、「基礎部の上にプレキャスト堅壁を堤体連続方向に並べて壁面を形成した堤体であって、該基礎部は、二列に配列された鋼管杭と該鋼管杭に支持され堤体連続方向に所定の間隔をあけて並設される鋼・コンクリート複合フーチングと該鋼・コンクリート複合フーチング間に配置される鋼・コンクリート複合接続部とからなり、前記鋼・コンクリート複合フーチング上に立設される前記プレキャスト堅壁は、該鋼・コンクリート複合フーチングにおける壁面直角方向の中央部に設けられていることを特徴とする堤体」である。   The dam body according to claim 1 of the present application is “a dam body in which precast hard walls are arranged on the foundation portion in the continuum direction to form a wall surface, and the foundation portion includes steel pipe piles arranged in two rows. A steel / concrete composite footing supported by the steel pipe pile and arranged in parallel with a predetermined interval in the bank body continuous direction, and a steel / concrete composite joint disposed between the steel / concrete composite footings, The above-mentioned precast hard wall erected on the concrete composite footing is a dam body characterized in that it is provided at a central portion in the direction perpendicular to the wall surface of the steel / concrete composite footing.

本発明の堤体は、大別して基礎部と堤体の壁面を形成するプレキャスト堅壁とからなり、これらは工場で製作されるユニットを主体としたものである。そして、該ユニットは各々施工現場に運ばれた後組み立てられ、前記基礎部の上に前記プレキャスト堅壁を堤体連続方向に並べることにより堤体が構築される。   The levee body of the present invention is roughly divided into a base portion and a precast hard wall that forms the wall surface of the dam body, and these are mainly units manufactured in a factory. The units are assembled after being transported to the construction site, and the bank is constructed by arranging the precast hard walls on the foundation in the bank body continuous direction.

各ユニットは工場で製作されるので安定した高品質のものとなる。また、施工現場での作業は、作業マニュアルに沿ってこれらユニットを組み立てたり一部に場所打ちコンクリートを打設するだけなので、熟練工の技能や勘に頼ることなく堤体を構築できる。   Each unit is manufactured at the factory, so it is stable and of high quality. In addition, the work at the construction site can be built without relying on the skills and intuition of skilled workers because these units are simply assembled according to the work manual or cast in place in part.

前記基礎部は、鋼管杭と鋼・コンクリート複合フーチングと鋼・コンクリート複合接続部とからなる。鋼管杭は従来から杭施工に用いられているものであり、堤体連続方向(堤体の壁面方向)に所定の間隔で二列に配列される。   The foundation includes a steel pipe pile, a steel / concrete composite footing, and a steel / concrete composite connection. Steel pipe piles are conventionally used for pile construction, and are arranged in two rows at predetermined intervals in the bank body continuous direction (wall surface direction of the bank body).

前記鋼・コンクリート複合フーチングは、二列に配列された鋼管杭の各列1本づつの2本で支持される形で、これら鋼管杭の堤体連続方向の間隔に合せて所定の間隔で、鋼管杭の上の堤体連続方向に並設される。   The steel-concrete composite footing is supported by two of each row of steel pipe piles arranged in two rows, and at a predetermined interval according to the interval in the dam body continuous direction of these steel pipe piles, It is arranged side by side in the continuous direction of the embankment on the steel pipe pile.

この鋼・コンクリート複合フーチングは、工場で製作される鋼製箱枠からなるユニット(フーチングユニット)を主体としてなるものであり、該フーチングユニットをコンクリートで被覆してなる鋼・コンクリート複合構造のハイブリッド型のものである。このようなハイブリッド型のものにすることにより、強固な基礎部が簡便な施工で得られると共に場所打ちコンクリートによる施工を少なくして施工現場でコンクリート使用量をできるだけ抑制できる。   This steel / concrete composite footing consists mainly of a unit (footing unit) made of a steel box frame manufactured at a factory, and is a hybrid type of steel / concrete composite structure in which the footing unit is covered with concrete. belongs to. By adopting such a hybrid type, a solid foundation can be obtained by simple construction, and construction by cast-in-place concrete can be reduced to reduce the amount of concrete used at the construction site as much as possible.

前記鋼製箱枠は、鋼板やH形鋼等の鋼材を用いて箱状に枠組みしたものであり、施工現場に設置した際の並設方向(堤体連続方向)に対する直角方向の長さが長い縦長のものである。該箱枠の横幅(並設方向の長さ)は前記鋼管杭の杭頭径より大きい。   The steel box frame is formed in a box shape using a steel material such as a steel plate or H-shaped steel, and has a length in a direction perpendicular to the juxtaposed direction (bank body continuous direction) when installed at a construction site. Long vertical ones. The width of the box frame (length in the juxtaposed direction) is larger than the pile head diameter of the steel pipe pile.

この鋼製箱枠の寸法は、一般的には、高さ1〜2m、幅1.5〜2.5m、長さ5〜10m程度であるが、荷重条件により適宜決定されるものである。   The dimensions of the steel box frame are generally about 1 to 2 m in height, 1.5 to 2.5 m in width, and about 5 to 10 m in length, but are appropriately determined depending on load conditions.

また、この鋼製箱枠は、長さの長い縦方向に複数の区画に区分けされており、前記鋼管杭と連結するための区画と前記プレキャスト堅壁と連結するための区画が設けられている。このように区分けすることによって、強固なフーチングユニットにすることができるとともに、役割のない区画を中空にすることによりコンクリートの使用量を減らしてフーチングユニットの軽量化が図れる。   Moreover, this steel box frame is divided into a plurality of sections in the longitudinal direction having a long length, and a section for connecting to the steel pipe pile and a section for connecting to the precast hard wall are provided. By partitioning in this way, it is possible to make a strong footing unit, and by reducing the amount of concrete used by making the section without a role hollow, the weight of the footing unit can be reduced.

鋼・コンクリート複合接続部も、上記鋼・コンクリート複合フーチングと同様、工場で製作される鋼製箱枠からなるユニット(接合ユニット)を主体としてなるものであり、該接合ユニットをコンクリートで被覆してなる鋼・コンクリート複合構造のハイブリッド型のものである。   Similar to the steel / concrete composite footing, the steel / concrete composite joint is mainly composed of a unit (joint unit) made of a steel box frame manufactured in a factory, and the joint unit is covered with concrete. It is a hybrid type of steel / concrete composite structure.

この鋼・コンクリート複合接続部は、前記プレキャスト堅壁に作用する荷重を受け持ち、鋼・コンクリート複合フーチングにその荷重を伝達するといった役割を果たすため、堤体連続方向に所定の間隔で敷設される隣設した鋼・コンクリート複合フーチング間に設けられる。該鋼・コンクリート複合接続部と前記鋼・コンクリート複合フーチングとの接続は、例えば、高力ボルトを用いた添接継手や引張継手、もしくは孔明き鋼板と鉄筋を用いたコンクリートの付着による接合などにより行われる。   This steel / concrete composite joint is responsible for the load acting on the precast rigid wall and plays the role of transmitting the load to the steel / concrete composite footing. Between steel and concrete composite footings. The connection between the steel / concrete composite joint and the steel / concrete composite footing is, for example, by joining with a joint using a high-strength bolt or a tensile joint, or by joining concrete using a perforated steel plate and a reinforcing bar. Done.

上記接合ユニットの鋼製箱枠も鋼板やH形鋼等の鋼材を用いて箱状に枠組みしたものである。該箱枠の寸法は、前記フーチングユニットの寸法、隣り合う前記フーチングユニット間の距離に基づいて決められ、鋼・コンクリート複合接続部の高さは前記鋼・コンクリート複合フーチングの高さと同じである。   The steel box frame of the joining unit is also a box-like frame made of a steel material such as a steel plate or H-shaped steel. The size of the box frame is determined based on the size of the footing unit and the distance between adjacent footing units, and the height of the steel / concrete composite joint is the same as the height of the steel / concrete composite footing.

前記鋼・コンクリート複合フーチングと前記鋼・コンクリート複合接続部の上に立設され堤体の壁面を形成するプレキャスト堅壁は、鉄筋コンクリート製のプレキャスト部材からなる。   The precast hard wall standing on the steel / concrete composite footing and the steel / concrete composite joint and forming the wall surface of the levee body is made of a reinforced concrete precast member.

コンクリートの種類は特に限定されない。通常、普通コンクリートであるが、高強度コンクリート、重量骨材を用いた重量コンクリート、海水の塩分による腐食や劣化を考慮したポリマーコンクリート、耐酸コンクリート、耐硫酸塩コンクリートなどを用いることもできる。   The type of concrete is not particularly limited. Usually, it is ordinary concrete, but high-strength concrete, heavy-weight concrete using heavy aggregates, polymer concrete, acid-resistant concrete, sulfate-resistant concrete, etc. that take into account corrosion and deterioration due to seawater salt can also be used.

このプレキャスト堅壁は、壁面部とその下方の基礎連結部とからなる。壁面部の面は、通常、前記鋼・コンクリート複合フーチングや鋼・コンクリート複合接続部に対し垂直な直面であるが、必ずしもこれには限定されず、曲面を有するものであってもよい。   The precast hard wall is composed of a wall surface portion and a foundation connecting portion below the wall surface portion. The surface of the wall surface portion is usually a surface perpendicular to the steel / concrete composite footing or the steel / concrete composite connection portion, but is not necessarily limited thereto, and may have a curved surface.

また、壁面を補強するために壁面部の表面に鋼板を貼ったりクッション材等のエネルギー吸収材を貼ったりしてもよい。耐久性を向上させるために遮塩性の被覆材でコーティングすることもできる。景観、美観の観点から、壁面に文字や模様や色を施したり緑化したりすることもできる。   Moreover, in order to reinforce a wall surface, you may stick a steel plate on the surface of a wall surface part, or may paste energy absorption materials, such as a cushioning material. In order to improve durability, it can also be coated with a salt barrier coating. From the viewpoint of landscape and aesthetics, letters, patterns and colors can be applied to the walls and greened.

プレキャスト堅壁における前記基礎連結部には、予め機械式継手方式における雌継手部材(例えば、継手パイプ)が仕込まれており、モルタル充填方式などの機械式継手方式により前記鋼・コンクリート複合フーチングや鋼・コンクリート複合接続部と連結される。   A female joint member (for example, a joint pipe) in a mechanical joint system is pre-installed in the foundation connecting portion in the precast hard wall, and the steel / concrete composite footing or steel / Connected with concrete composite connection.

前述の通り、上記プレキャスト堅壁は上記鋼・コンクリート複合フーチングと上記鋼・コンクリート複合接続部の上に立設されるが、鋼・コンクリート複合フーチング上に立設されるプレキャスト堅壁は、鋼・コンクリート複合フーチングとプレキャスト堅壁とで縦断面が逆T型になるように、鋼・コンクリート複合フーチングにおける壁面直角方向の中央部に設けられる。   As described above, the precast hard wall is erected on the steel / concrete composite footing and the steel / concrete composite joint, but the precast hard wall erected on the steel / concrete composite footing is steel / concrete composite. The steel / concrete composite footing is provided at the center in the direction perpendicular to the wall surface so that the vertical cross section of the footing and the precast hard wall is an inverted T shape.

前述の通り、プレキャスト堅壁は直壁に限らず曲壁や直壁と曲壁の組み合わせであったりする場合もあるので、ここでいう「逆T型」とは、プレキャスト堅壁が鋼・コンクリート複合フーチングにおける壁面直角方向の中央部で立設されているもののすべてをいう。   As mentioned above, the precast hard wall is not limited to a straight wall, but may be a curved wall or a combination of a straight wall and a curved wall. It means all of those that are erected at the center in the direction perpendicular to the wall surface.

このように、鋼・コンクリート複合フーチングとプレキャスト堅壁との連結構造を逆T型にすることにより、例えば、津波における押波と引波のどちらにも対応できるといった効果が得られる。   Thus, by making the connection structure of the steel / concrete composite footing and the precast hard wall into an inverted T shape, for example, an effect of being able to cope with either a tsunami wave or a wave wave is obtained.

プレキャスト堅壁の寸法は特に限定されないが、トラックでの陸上輸送を考えると、長さ(高さ)15m以下、重さ25t以下となるようにするのが好ましい。   The dimensions of the precast hard wall are not particularly limited, but considering land transportation by truck, it is preferable that the length (height) is 15 m or less and the weight is 25 t or less.

本願の請求項2に係る堤体は、「前記鋼・コンクリート複合フーチングは、H形鋼を用いて形成した箱枠からなるフーチングユニットを用いたものであり、該フーチングユニットの周囲をコンクリートで被覆したものであることを特徴とする請求項1に記載の堤体」である。   The embankment according to claim 2 of the present application is “the steel / concrete composite footing uses a footing unit made of a box frame formed of H-shaped steel, and the periphery of the footing unit is covered with concrete. The levee body according to claim 1, wherein

前述の通り、本発明では、鋼・コンクリート複合フーチングは、工場で製作される鋼製箱枠からなるユニット(フーチングユニット)を主体としてなるものであり、該フーチングユニットをコンクリートで被覆してなる鋼・コンクリート複合構造のハイブリッド型のものである。   As described above, in the present invention, the steel / concrete composite footing is mainly a unit (footing unit) made of a steel box frame manufactured at a factory, and the steel obtained by covering the footing unit with concrete.・ A hybrid type of concrete composite structure.

上記鋼製箱枠は鋼板やH形鋼等の鋼材を用いて作られるが、H形鋼を用いて作るのが好ましい。H形鋼を用いることによって、鋼材の鋼重が削減、鋼材加工が容易、現場で部材連結が容易、プレキャスト堅壁への接続鉄筋の定着が容易といったメリットが生まれる。   The steel box frame is made of a steel material such as a steel plate or H-shaped steel, but is preferably made of H-shaped steel. By using the H-shaped steel, there are merits that the steel weight of the steel material is reduced, the steel material processing is easy, the member connection is easy on the site, and the connection reinforcing bar to the precast hard wall is easily fixed.

本願の請求項3に係る堤体は、「前記鋼・コンクリート複合接続部は、H形鋼を用いて形成した箱枠からなる接合ユニットを用いたものであり、該接合ユニットの周囲をコンクリートで被覆したものであることを特徴とする請求項1または2に記載の堤体」である。   The embankment according to claim 3 of the present application is “the steel / concrete composite connecting portion uses a connecting unit made of a box frame formed of H-shaped steel, and the periphery of the connecting unit is made of concrete. The levee according to claim 1 or 2, characterized in that it is covered.

前述の通り、本発明では、鋼・コンクリート複合接続部も、上記鋼・コンクリート複合フーチングと同様、工場で製作される鋼製箱枠からなるユニット(接合ユニット)を主体としてなるものであり、該接合ユニットをコンクリートで被覆してなる鋼・コンクリート複合構造のハイブリッド型のものである。   As described above, in the present invention, the steel / concrete composite connecting portion is mainly composed of a unit (joining unit) made of a steel box frame manufactured in a factory, like the steel / concrete composite footing, It is a hybrid type of steel / concrete composite structure in which the joining unit is covered with concrete.

したがって、上記フーチングユニットと同様、H形鋼を用いることによって、鋼材の鋼重が削減、鋼材加工が容易、現場で部材連結が容易、プレキャスト堅壁への接続鉄筋の定着が容易といったメリットが生まれるので、H形鋼を用いて箱枠を形成するのは好ましい。   Therefore, as with the above footing unit, the use of H-section steel has the advantages of reducing the steel weight of the steel material, facilitating steel material processing, facilitating member connection on site, and facilitating fixing of the connecting rebar to the precast hard wall. It is preferable to form a box frame using H-shaped steel.

本願の請求項4に係る堤体は、「前記フーチングユニットは長さ方向に5つに区画されており、この区画は、前記プレキャスト堅壁が立設される該フーチングユニット中央部の区画と、該区画に対して対称的に両外側に設けられ二列に配列された各列の前記鋼管杭の上端部を差し込むための挿入孔が設けられた2つの区画と、これら区画と前記中央部の区画との間に設けられる中空の2つの区画とからなることを特徴とする請求項に記載の堤体」である。 The bank body according to claim 4 of the present application is “the footing unit is divided into five in the length direction, and this section includes a section in the center of the footing unit on which the precast hard wall is erected, Two compartments provided with insertion holes for inserting the upper ends of the steel pipe piles in each row arranged symmetrically with respect to the compartments in two rows, and the compartments in the middle portion and the compartments The levee body according to claim 2 , characterized in that it comprises two hollow sections provided between the two.

本発明では、高さ方向において、鋼・コンクリート複合フーチングは鋼管杭とプレキャスト堅壁との間に設置され、これら鋼管杭とプレキャスト堅壁は各々フーチングユニットと連結される。   In the present invention, in the height direction, the steel / concrete composite footing is installed between the steel pipe pile and the precast hard wall, and each of the steel pipe pile and the precast hard wall is connected to the footing unit.

フーチングユニットが一つの箱枠からなるものであると、鋼管杭やプレキャスト堅壁との連結作業がし難くなる。箱枠を複数の区画に区切っておけば、フーチングユニットと鋼管杭との連結作業、フーチングユニットとプレキャスト堅壁との連結作業が別々に行えるので堤体の構築施工がし易くなる。また、コンクリートの使用量を減らしたり、軽量化して陸上輸送し易くすることもできる。   If the footing unit is composed of one box frame, it is difficult to connect the steel pipe pile or the precast hard wall. If the box frame is divided into a plurality of sections, the connecting work between the footing unit and the steel pipe pile and the connecting work between the footing unit and the precast hard wall can be performed separately, so that the construction work of the levee body is facilitated. In addition, the amount of concrete used can be reduced or the weight can be reduced to facilitate transportation on land.

フーチングユニットの区画構造は特に限定されないが、前記プレキャスト堅壁が立設される該フーチングユニット中央部の区画と、該区画に対して対称的に両外側に設けられ二列に配列された各列の前記鋼管杭の上端部を差し込むための挿入孔が設けられた2つの区画と、これら区画と前記中央部の区画との間に設けられる中空の2つの区画の5つの区画に区分けされているのが好ましい。   The partitioning structure of the footing unit is not particularly limited, but the central part of the footing unit where the precast hard wall is erected and the two rows arranged symmetrically with respect to the partition and arranged in two rows It is divided into five sections: two sections provided with an insertion hole for inserting the upper end of the steel pipe pile, and two hollow sections provided between these sections and the center section. Is preferred.

プレキャスト堅壁をフーチングユニット中央部の区画で連結することにより、鋼・コンクリート複合フーチングとプレキャスト堅壁との逆T型構造が容易に得られる。   By connecting the precast hard wall at the central section of the footing unit, an inverted T-shaped structure of the steel / concrete composite footing and the precast hard wall can be easily obtained.

二列に配列された鋼管杭における各列の鋼管杭とフーチングユニットとの連結は、フーチングユニットの両外側の区画を用いて行い、該区画内に各々鋼管杭の上端部(杭頭部)を挿入しコンクリートで固めることにより行うのが好ましい。そのため、前記両外側の区画には鋼管杭の上端部が挿入できる程度の挿入孔が設けられているのが好ましい。   The connection between the steel pipe piles and the footing units in each row in the steel pipe piles arranged in two rows is performed using the outer sections of the footing unit, and the upper ends (pile heads) of the steel pipe piles are respectively placed in the sections. This is preferably done by inserting and hardening with concrete. Therefore, it is preferable that an insertion hole is provided in the outer sections so that the upper end of the steel pipe pile can be inserted.

これら両外側の区画と前記中央部の区画との間は、上記のような他部材との連結といった役割もないので、中空にしておくのが好ましい。中空部があっても、H形鋼等の剛性の高い鋼材で箱枠を形成し被覆が必要な部分をコンクリートで被覆しておけば強度や耐久性で問題になることはない。中空部(中空の区画)を設けることで、コンクリートの使用量を低減できるとともにフーチングユニットの軽量化が図れ、陸上輸送し易くなる。   It is preferable to keep the space between these outer compartments and the central compartment because they do not have a role of connection with other members as described above. Even if there is a hollow portion, there is no problem in strength and durability if a box frame is formed with a steel material having high rigidity such as H-shaped steel and a portion requiring coating is covered with concrete. By providing the hollow portion (hollow section), the amount of concrete used can be reduced, the weight of the footing unit can be reduced, and transportation on land is facilitated.

なお、上記「中空」は、モルタルやコンクリート等のセメント硬化体が存在しないということであり、空間だけでなく、土砂、軽量充填材、エネルギー吸収材などが充填されている場合も含む。   The “hollow” means that a hardened cement body such as mortar or concrete does not exist, and includes not only a space but also a case where earth and sand, a lightweight filler, an energy absorbing material or the like is filled.

本願の請求項5に係る堤体は、「前記プレキャスト堅壁は鉄筋コンクリートからなり、壁面部と該壁面部の下方にあって該壁面部より厚みの厚い基礎連結部とで構成されることを特徴とする請求項1〜4のいずれか一項に記載の堤体」である。   The dam body according to claim 5 of the present application is characterized in that “the precast hard wall is made of reinforced concrete, and is composed of a wall surface portion and a foundation connecting portion below the wall surface portion and thicker than the wall surface portion. The levee body according to any one of claims 1 to 4.

前述の通り、プレキャスト堅壁は、鉄筋コンクリートを主体としたものであり、堤体の壁面を形成する壁面部とその下方にあって鋼・コンクリート複合フーチングや鋼・コンクリート複合接続部との連結に寄与する基礎連結部とが一体的に形成されたものからなる。   As mentioned above, the precast hard wall is mainly reinforced concrete, and contributes to the connection between the wall part forming the wall surface of the dam body and the steel / concrete composite footing and steel / concrete composite connection part below it. It consists of what was integrally formed with the base connection part.

これら壁面部と基礎連結部は、厳密に区分けされるものではないが、基礎連結部の厚みを壁面部の厚みより厚くし、墓石のように、基礎台の上に壁面部が立設している形態にするのが好ましい。基礎連結部の最大厚みは壁面部の最大厚みに対して1.5〜3.0倍が好ましい。   These wall sections and foundation connection sections are not strictly separated, but the thickness of the foundation connection section is made thicker than the wall section, and the wall section is erected on the foundation platform like a tombstone. It is preferable to adopt a form. The maximum thickness of the foundation connecting portion is preferably 1.5 to 3.0 times the maximum thickness of the wall surface portion.

このような形態にすることによって、プレキャスト堅壁が安定して立設できるとともに、基礎部との連結も強固にできる。   By adopting such a configuration, the precast hard wall can be stably erected and the connection with the foundation can be strengthened.

本願の請求項6に係る堤体は、「堤体連続方向における前記プレキャスト堅壁の壁幅は、前記鋼・コンクリート複合フーチングの幅よりも大きく、前記プレキャスト堅壁が前記鋼・コンクリート複合フーチングから隣設される前記鋼・コンクリート複合接続部に跨って設置されることを特徴とする請求項1〜5のいずれか一項に記載の堤体」である。   According to claim 6 of the present application, “the wall width of the precast hard wall in the continuous direction of the bank body is larger than the width of the steel / concrete composite footing, and the precast hard wall is adjacent to the steel / concrete composite footing. The levee body according to any one of claims 1 to 5, wherein the levee body is installed across the steel / concrete composite connecting portion.

前述の通り、プレキャスト堅壁は鋼・コンクリート複合フーチングと鋼・コンクリート複合接続部の上に交互に立設され堤体の壁面を形成するが、プレキャスト堅壁の堤体連続方向への壁幅は、通常、堤体連続方向に各々鋼・コンクリート複合フーチングと鋼・コンクリート複合接続部の幅に合せて作られ、一つの鋼・コンクリート複合フーチング上に一つのプレキャスト堅壁が、一つの鋼・コンクリート複合接続部上に一つのプレキャスト堅壁が各々立設するようにして堤体の壁面が構築される。   As mentioned above, the precast hard wall is alternately erected on the steel / concrete composite footing and the steel / concrete composite joint to form the wall surface of the levee body. The steel / concrete composite footings and the steel / concrete composite joints are made to match the width of the steel / concrete composite joints in the continuous direction of the dam body, and one precast hard wall is placed on one steel / concrete composite footing. The wall surface of the levee body is constructed so that one precast hard wall stands on each other.

しかし、このような堤体構造に限定されるものではなく、例えば、堤体連続方向における前記プレキャスト堅壁の壁幅を鋼・コンクリート複合フーチングの幅よりも大きくし、プレキャスト堅壁が鋼・コンクリート複合フーチングから隣設される鋼・コンクリート複合接続部に跨って立設した堤体構造にすることもできる。プレキャスト堅壁の壁幅は、例えば、鋼・コンクリート複合フーチングの幅に鋼・コンクリート複合接続部の幅の半分を足した長さである。   However, it is not limited to such a dam body structure. For example, the wall width of the precast hard wall in the continuous direction of the dam body is made larger than the width of the steel / concrete composite footing, and the precast hard wall is made of steel / concrete composite footing. It is also possible to make a dike structure standing upright across the steel-concrete composite connecting part. The wall width of the precast hard wall is, for example, a length obtained by adding half of the width of the steel / concrete composite joint to the width of the steel / concrete composite footing.

上記のように、プレキャスト堅壁が鋼・コンクリート複合フーチングから隣設される鋼・コンクリート複合接続部に跨って立設している堤体構造にすることによって、二列に配列された鋼管杭における対応する一対の鋼管杭に渡る長手方向の鋼製箱枠材に直接的に荷重が流れるようにし、荷重負担の分散化が図れるといった効果を得ることができる。   As mentioned above, by adopting a dam body structure where the precast hard wall is erected across the steel-concrete composite joint adjacent to the steel-concrete composite footing, it can be used in steel pipe piles arranged in two rows It is possible to obtain an effect that the load can be directly distributed to the longitudinal steel box frame material across the pair of steel pipe piles to be distributed and the load burden can be distributed.

本発明の堤体は、工場で製作した複数のユニットを主体とし、これらユニットを施工現場で組立てて構築されるものなので、安定した高品質なものであるとともに現場での施工が熟練工を必要とせず容易となる。   The levee body of the present invention is mainly composed of a plurality of units manufactured at a factory, and these units are assembled and constructed at the construction site, so that they are stable and of high quality and require on-site construction requiring skilled workers. It becomes easy.

また、上記高品質に加えて基礎部は鋼・コンクリート複合部材からなるものなので、大津波にも対応可能な強固な堤体とすることができる。   In addition to the above-mentioned high quality, the foundation is made of a steel / concrete composite member, so that it can be a strong dam body that can cope with a large tsunami.

また、基礎部を鋼製箱枠からなるユニットを主体とした鋼・コンクリート複合構造のハイブリッド型のものにすることにより、場所打ちコンクリートによる施工を少なくして施工現場でコンクリート使用量をできるだけ抑制した堤体を得ることができ、震災復興に際して発生した施工現場へのコンクリートの供給不足といった昨今の問題も解決できる。   In addition, by adopting a hybrid steel / concrete structure mainly composed of steel box frame units, the use of cast-in-place concrete is reduced to minimize the amount of concrete used at the construction site. A bank can be obtained and the current problems such as a shortage of concrete supply to the construction site that occurred during the earthquake reconstruction can be solved.

更に、施工現場で組み立てられる上記ユニットの寸法を調整すれば、道路事情が良くない沿岸部への輸送も可能となる。   Furthermore, if the dimensions of the unit assembled at the construction site are adjusted, transportation to coastal areas where road conditions are not good is possible.

本発明の堤体の一実施形態を示す斜視図である。(a)は表側(水辺側)から見た図、(b)は裏側(陸地側)から見た図である。It is a perspective view which shows one Embodiment of the bank body of this invention. (A) is the figure seen from the front side (waterside side), (b) is the figure seen from the back side (land side). 図1に記載した上記本発明の堤体の構造をよりわかり易く示した図である。(a)は正面図、(b)は平面図、(c)は側面図である。It is the figure which showed more easily the structure of the bank of the said invention described in FIG. (A) is a front view, (b) is a plan view, and (c) is a side view. 本発明の堤体の基礎部の構築に好適に用いることができるフーチングユニットを用いた鋼・コンクリート複合フーチングと、接合ユニットを用いた鋼・コンクリート複合接続部を示す斜視図である。(a)はフーチングユニットの図、(b)は鋼・コンクリート複合フーチングの図、(c)は鋼・コンクリート複合フーチングに接合ユニットを接続した図、(d)は鋼・コンクリート複合フーチングと鋼・コンクリート複合接続部との接続図である。It is a perspective view which shows the steel and concrete composite footing using the footing unit which can be used suitably for construction of the foundation part of the dam body of this invention, and the steel and concrete composite connection part using a joining unit. (A) is a diagram of a footing unit, (b) is a diagram of a steel / concrete composite footing, (c) is a diagram of a joint unit connected to a steel / concrete composite footing, and (d) is a steel / concrete composite footing and steel / concrete It is a connection figure with a concrete composite connection part. 本発明の堤体におけるプレキャスト堅壁を示す斜視図である。It is a perspective view which shows the precast hard wall in the bank body of this invention. 基礎部の構築過程を示す。(a)は鋼管杭の施工過程を、(b)はフーチングユニットの設置過程を、(c)は接合ユニットの設置過程を、(d)は基礎部の完成過程を、(e)は完成した基礎部を示す。The construction process of the foundation is shown. (A) is the steel pipe pile construction process, (b) is the footing unit installation process, (c) is the joining unit installation process, (d) is the foundation completion process, and (e) is completed. The basic part is shown. 基礎部の完成以降、該基礎部の上にプレキャスト堅壁を立設し本発明の堤体を完成させるまでの過程を示す。(f)はプレキャスト堅壁の立設過程を、(g)は土の埋め戻しによる堤体と道路の完成過程を示す。The process from the completion of the foundation to the completion of the dam body of the present invention by standing a precast hard wall on the foundation is shown. (F) shows the process of standing the precast hard wall, and (g) shows the completion process of the dam body and the road by backfilling the soil. プレキャスト堅壁と基礎部との連結方法の一例を示す図であり、プレキャスト堅壁における基礎連結部の縦断面拡大図である。It is a figure which shows an example of the connection method of a precast rigid wall and a foundation part, and is a longitudinal cross-sectional enlarged view of the foundation connection part in a precast rigid wall.

以下、本発明の実施形態について、図面に基づいて詳細に説明する。なお、本発明は、以下に説明する実施形態に限定されるものではない。   Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. Note that the present invention is not limited to the embodiments described below.

図1は、本発明の堤体1の一実施形態を示す斜視図である。(a)は表側(水辺側)から見た図、(b)は裏側(陸地側)から見た図である。   FIG. 1 is a perspective view showing an embodiment of a bank body 1 of the present invention. (A) is the figure seen from the front side (waterside side), (b) is the figure seen from the back side (land side).

この例では、本発明の堤体1は既設堤防2の上に構築されている。堤体1は、基礎部3と堤体1の壁面を形成するプレキャスト堅壁4とからなり、基礎部3の上にプレキャスト堅壁4を堤体連続方向に並べて壁面が形成されている。   In this example, the bank body 1 of the present invention is constructed on an existing bank 2. The levee body 1 includes a base portion 3 and a precast hard wall 4 that forms the wall surface of the dam body 1, and the wall surface is formed on the base portion 3 by arranging the precast hard walls 4 in the levee body continuous direction.

基礎部3は鋼管杭5と鋼・コンクリート複合フーチング6と鋼・コンクリート接続部7とからなる。鋼管杭5は所定の間隔で堤体連続方向に二列に配列されている。また、鋼・コンクリート複合フーチング6は、二列に配列された鋼管杭5の各列1本づつの2本で支持される形で、これら鋼管杭5の堤体連続方向の間隔に合せて所定の間隔で、鋼管杭5の上の堤体連続方向に並設されている。   The foundation 3 includes a steel pipe pile 5, a steel / concrete composite footing 6, and a steel / concrete connection portion 7. The steel pipe piles 5 are arranged in two rows in the bank body continuous direction at a predetermined interval. In addition, the steel / concrete composite footing 6 is supported by two of each row of the steel pipe piles 5 arranged in two rows, and is determined in accordance with the interval of the steel pipe piles 5 in the bank body continuous direction. Are arranged in parallel in the bank body continuous direction above the steel pipe pile 5.

また、隣り合う鋼・コンクリート複合フーチング6,6間のプレキャスト堅壁4の下には、鋼・コンクリート複合接続部7が設けられており、基礎部3における鋼管杭5上の基礎部は、堤体連続方向に鋼・コンクリート複合フーチング6と鋼・コンクリート複合接続部7とが交互に敷設された構造となっている。   Further, a steel / concrete composite connecting portion 7 is provided under the precast hard wall 4 between adjacent steel / concrete composite footings 6 and 6, and the foundation portion on the steel pipe pile 5 in the foundation portion 3 is a dam body. The steel / concrete composite footing 6 and the steel / concrete composite connection portion 7 are alternately laid in the continuous direction.

一方、プレキャスト堅壁4は図のような形状の鉄筋コンクリートからなり、図に示すように、鋼・コンクリート複合フーチング6と鋼・コンクリート複合接続部7の上に立設して堤体連続方向に並べられ、堤体1の壁面を形成している。   On the other hand, the precast hard wall 4 is made of reinforced concrete having a shape as shown in the figure, and as shown in the figure, is erected on the steel / concrete composite footing 6 and the steel / concrete composite connection portion 7 and arranged in the continuous direction of the levee body. The wall surface of the levee body 1 is formed.

この例では、堤体連続方向におけるプレキャスト堅壁4の壁幅は、鋼・コンクリート複合フーチング6と鋼・コンクリート複合接続部7の堤体連続方向における各幅の合計の1/2となっており、プレキャスト堅壁4は鋼・コンクリート複合フーチング6から隣設される鋼・コンクリート複合接続部7に跨って設置されている。このような形で設置することによって、二列に配列された鋼管杭における対応する一対の鋼管杭に渡る長手方向の鋼製箱枠材に直接的に荷重が流れるようにし、荷重負担の分散化が図れるといった効果が得られる。   In this example, the wall width of the precast rigid wall 4 in the bank body continuous direction is ½ of the total width in the bank body continuous direction of the steel / concrete composite footing 6 and the steel / concrete composite joint 7. The precast hard wall 4 is installed across the steel / concrete composite joint 7 adjacent to the steel / concrete composite footing 6. By installing in this way, load is distributed directly to the steel box frame material in the longitudinal direction across the corresponding pair of steel pipe piles in the steel pipe piles arranged in two rows, and the load burden is distributed The effect that can be achieved is obtained.

本発明では、図に示すように、プレキャスト堅壁4は、鋼・コンクリート複合フーチング6においては壁面直角方向の中央部に設けられ、鋼・コンクリート複合フーチング6とプレキャスト堅壁4とで縦断面が逆T型を形成する。このように、鋼・コンクリート複合フーチング6とプレキャスト堅壁4との連結構造を逆T型にすることり、例えば、津波における押波と引波のどちらにも対応できるといった効果が得られる。この例では、本発明の堤体1の裏側(陸地側)は、日常、道路8として活用される。   In the present invention, as shown in the figure, the precast hard wall 4 is provided at the center of the steel / concrete composite footing 6 in the direction perpendicular to the wall surface, and the vertical cross section of the steel / concrete composite footing 6 and the precast hard wall 4 is inverted T. Form a mold. As described above, by making the connecting structure of the steel / concrete composite footing 6 and the precast hard wall 4 into an inverted T shape, for example, an effect of being able to cope with both a tsunami wave and a wave wave is obtained. In this example, the back side (land side) of the levee body 1 of the present invention is used daily as the road 8.

図2は、図1に記載した上記本発明の堤体1の構造をよりわかり易く示した図である。(a)は正面図、(b)は平面図、(c)は側面図である。   FIG. 2 is a view showing the structure of the bank body 1 of the present invention described in FIG. 1 in an easy-to-understand manner. (A) is a front view, (b) is a plan view, and (c) is a side view.

図2(a)に示すように、本発明の堤体1は、大別して、基礎部3とプレキャスト堅壁4とからなる。そして、基礎部3は、鋼管杭5と鋼・コンクリート複合フーチング6と鋼・コンクリート複合接続部7とからなる。   As shown in FIG. 2A, the bank body 1 of the present invention is roughly composed of a base portion 3 and a precast hard wall 4. The foundation portion 3 includes a steel pipe pile 5, a steel / concrete composite footing 6, and a steel / concrete composite connection portion 7.

鋼・コンクリート複合フーチング6の下には鋼管杭5があり、鋼・コンクリート複合フーチング6は鋼管杭5の杭頭部が鋼・コンクリート複合フーチング6の中に入り込む形で鋼管杭5により支持されている。隣り合う鋼・コンクリート複合フーチング6,6の間にこれらを繋ぐ形で設けられる鋼・コンクリート複合接続部7の下には鋼管杭はない。   Below the steel / concrete composite footing 6 is a steel pipe pile 5, and the steel / concrete composite footing 6 is supported by the steel pipe pile 5 in such a manner that the pile head of the steel pipe pile 5 enters the steel / concrete composite footing 6. Yes. There is no steel pipe pile below the steel / concrete composite connecting portion 7 provided in such a manner that the steel / concrete composite footings 6 and 6 are connected to each other.

プレキャスト堅壁4は、堤体連続方向に壁面が形成するようにして、鋼・コンクリート複合フーチング6と鋼・コンクリート複合接続部7の上に立設している。プレキャスト堅壁4は図に示すように、鋼・コンクリート複合フーチング6と鋼・コンクリート複合接続部7に跨る形で設けられている。   The precast hard wall 4 is erected on the steel / concrete composite footing 6 and the steel / concrete composite connection portion 7 so that the wall surface is formed in the bank body continuous direction. As shown in the figure, the precast hard wall 4 is provided so as to straddle the steel / concrete composite footing 6 and the steel / concrete composite joint 7.

図2(b)、図2(c)に示すように、鋼管杭5は堤体連続方向に250〜450cm程度の所定の間隔で略平行に二列に設けられる。一列は水辺側鋼管杭の列であり、他の一列は内陸側鋼管杭の列である。これら二列の間隔は150〜600cm程度である。   As shown in FIGS. 2 (b) and 2 (c), the steel pipe piles 5 are provided in two rows substantially in parallel at predetermined intervals of about 250 to 450 cm in the bank body continuous direction. One row is a row of waterside steel pipe piles, and the other row is a row of inland side steel pipe piles. The distance between these two rows is about 150 to 600 cm.

上記鋼管杭5の上には、図に示すような形で、鋼・コンクリート複合フーチング6が鋼管杭5の間隔に合せて所定の間隔で設けられる。   On the steel pipe pile 5, a steel / concrete composite footing 6 is provided at a predetermined interval in accordance with the interval of the steel pipe pile 5 as shown in the figure.

鋼・コンクリート複合フーチング6は、鋼製箱枠からなるフーチングユニットをコンクリート9で被覆してなるものが好ましい。この例では、フーチングユニットは3つに区画されており、両外側の区画11,11には鋼管杭5の杭頭部が入り込んで接続され、各鋼・コンクリート複合フーチング6は2本の鋼管杭5,5により支持されている。中央部の区画10の上方にはプレキャスト堅壁4が立設している。   The steel / concrete composite footing 6 is preferably formed by covering a footing unit made of a steel box frame with concrete 9. In this example, the footing unit is divided into three parts, and the pile heads of the steel pipe piles 5 are inserted into and connected to the outer side parts 11 and 11, and each steel / concrete composite footing 6 has two steel pipe piles. 5 and 5 are supported. A precast hard wall 4 is erected above the central section 10.

鋼・コンクリート複合フーチング6の寸法は、概略、前記フーチングユニットの寸法にコンクリートの被覆厚を加えた寸法である。   The dimensions of the steel / concrete composite footing 6 are roughly the dimensions of the dimensions of the footing unit plus the concrete coating thickness.

図2(c)からわかるように、本発明の堤体1は、プレキャスト堅壁4と鋼・コンクリート複合フーチング6とで縦断面が逆T型となる構造となっている。鋼・コンクリート複合フーチングとプレキャスト堅壁との連結構造を逆T型にすることにより例えば、津波における押波と引波のどちらにも対応できるといった効果が得られる。   As can be seen from FIG. 2 (c), the dam body 1 of the present invention has a structure in which the vertical cross section is an inverted T-shape with the precast hard wall 4 and the steel / concrete composite footing 6. By making the connecting structure of the steel / concrete composite footing and the precast hard wall into an inverted T shape, for example, an effect of being able to cope with both a tsunami wave and a wave wave is obtained.

堤体連続方向に所定の間隔で設けられた隣り合う上記鋼・コンクリート複合フーチング6,6の間には、これらを繋ぐ形で、鋼・コンクリート複合接続部7が設けられる。   A steel / concrete composite connecting portion 7 is provided between the adjacent steel / concrete composite footings 6 and 6 provided at predetermined intervals in the bank body continuous direction so as to connect them.

この鋼・コンクリート複合接続部7も、上記鋼・コンクリート複合フーチング6と同様、鋼製箱枠からなる接合ユニットをコンクリート9で被覆してなるものが好ましい。   The steel / concrete composite connecting portion 7 is also preferably formed by covering a joining unit made of a steel box frame with concrete 9 like the steel / concrete composite footing 6.

鋼・コンクリート複合接続部7の寸法は、図2(a)に示すように、高さは鋼・コンクリート複合フーチング6と同じであり、横幅(堤体連続方向の幅)は、略隣り合う上記鋼・コンクリート複合フーチング6,6間の間隔である。   As shown in FIG. 2 (a), the dimensions of the steel / concrete composite connecting portion 7 are the same as those of the steel / concrete composite footing 6, and the lateral width (width in the bank body continuous direction) is substantially adjacent to the above. The distance between the steel / concrete composite footings 6 and 6.

縦幅(堤体連続方向に対して直角方向の幅)は特に限定されないが、プレキャスト堅壁4が堅固に立設できる幅であれば、できるだけ短い方が好ましい。通常、鋼・コンクリート複合ユニット6の縦幅(堤体連続方向に対して直角方向の長さ)の1/4〜1/3程度である。   The vertical width (width in the direction perpendicular to the bank body continuous direction) is not particularly limited, but is preferably as short as possible as long as the precast rigid wall 4 can be firmly erected. Usually, it is about 1/4 to 1/3 of the vertical width of the steel / concrete composite unit 6 (length in a direction perpendicular to the bank body continuous direction).

以上のように、本発明の堤体1では、鋼管杭5と鋼・コンクリート複合フーチング6とを接続するとともに隣り合う鋼・コンクリート複合フーチング6,6間を鋼・コンクリート複合接続部7で繋ぐことにより鋼管杭5と鋼・コンクリート複合フーチング6と鋼・コンクリート複合接続部7とが一体化して堅固な基礎部3が構築される。   As described above, in the levee body 1 of the present invention, the steel pipe pile 5 and the steel / concrete composite footing 6 are connected and the adjacent steel / concrete composite footings 6 and 6 are connected by the steel / concrete composite connection portion 7. As a result, the steel pipe pile 5, the steel / concrete composite footing 6 and the steel / concrete composite connecting portion 7 are integrated to form a solid foundation 3.

図3は、本発明の堤体1の基礎部3の構築に好適に用いることができるフーチングユニット12を用いた鋼・コンクリート複合フーチング6と、接合ユニット13を用いた鋼・コンクリート複合接続部7を示す斜視図である。(a)はフーチングユニット12の図、(b)は鋼・コンクリート複合フーチング6の図、(c)は鋼・コンクリート複合フーチング6に接合ユニット13を接続した図、(d)は鋼・コンクリート複合フーチング6と鋼・コンクリート複合接続部7との接続図である。   FIG. 3 shows a steel / concrete composite footing 6 using a footing unit 12 and a steel / concrete composite connection part 7 using a joining unit 13 that can be suitably used for the construction of the foundation 3 of the dam body 1 of the present invention. FIG. (A) is a view of the footing unit 12, (b) is a view of the steel / concrete composite footing 6, (c) is a view of the joining unit 13 connected to the steel / concrete composite footing 6, and (d) is a steel / concrete composite footing. FIG. 3 is a connection diagram of the footing 6 and the steel / concrete composite connection portion 7.

図3(a)に示すように、フーチングユニット12は縦長の鋼製箱枠からなる。この例ではH形鋼15を用いて箱枠を形成しているが、これに限定されるものではない。H形鋼を用いれば低価格で強固な箱枠を簡便に形成できるので好ましい。H形鋼15の表面にはコンクリートとの付着を良くするための頭付きスタッド16が設けられている。また、図に示すように、接続鉄筋26が中央部の区画にフーチングユニット12の短尺方向に所定の間隔で鉛直に設けられている。そのH形鋼15の表面への取り付け方法は、例えば、ねじ鉄筋用のナットによりH形鋼に定着させるといった方法である。   As shown in FIG. 3A, the footing unit 12 is composed of a vertically long steel box frame. In this example, the box frame is formed using the H-shaped steel 15, but the present invention is not limited to this. Use of an H-shaped steel is preferable because a strong box frame can be easily formed at a low price. A headed stud 16 is provided on the surface of the H-shaped steel 15 to improve adhesion to the concrete. Further, as shown in the figure, connecting reinforcing bars 26 are provided vertically at predetermined intervals in the short direction of the footing unit 12 in the central section. The method of attaching the H-shaped steel 15 to the surface is, for example, a method of fixing the H-shaped steel to the H-shaped steel with a nut for screw rebar.

図に示すように、この例では箱枠は中央部の区画10と両外側の区画11,11と間の区画14,14の5つの区画に仕切られている。区画の数はこれに限定されるものではなく、例えば、前述のように3つの区画であってもよい。複数の区画に仕切ることによって、中空部分を作り出すことができるので鋼・コンクリート複合フーチング6が軽量化できるといったメリットがある。   As shown in the figure, in this example, the box frame is divided into five sections, ie, sections 14 and 14 between a central section 10 and outer sections 11 and 11. The number of sections is not limited to this, and may be three sections as described above, for example. By partitioning into a plurality of compartments, a hollow portion can be created, so that there is an advantage that the steel / concrete composite footing 6 can be reduced in weight.

図3(b)に示すように、上記フーチングユニット12はその一部がコンクリート9(被覆コンクリート)で被覆され鋼・コンクリート複合フーチング6が作られる。被覆厚は特に限定されないが、塩害による腐食を考慮して十分なかぶりをとるものとする。この製造は工場で行われる。工場で製造することにより、安定した高品質のものが得られるとともに現場施工が簡略化できる。   As shown in FIG. 3 (b), a part of the footing unit 12 is covered with concrete 9 (covered concrete) to form a steel / concrete composite footing 6. The coating thickness is not particularly limited, but a sufficient cover is taken in consideration of corrosion due to salt damage. This production takes place in the factory. By manufacturing in the factory, stable and high quality products can be obtained and on-site construction can be simplified.

外側の区画11の下部には鋼管杭の杭頭部を鋼・コンクリート複合フーチング6の中に挿入するための挿入孔17が設けられているとともに、上部はコンクリートを充填するため開口している。間の区画14はコンクリート9で被覆されているものの中は中空となっている。中空にすることによりコンクリートの使用量を減らせるとともに鋼・コンクリート複合フーチング6の軽量化が図れる。   An insertion hole 17 for inserting a pile head of a steel pipe pile into the steel / concrete composite footing 6 is provided at the lower portion of the outer section 11, and the upper portion is opened to fill the concrete. The space 14 between them is hollow in what is covered with the concrete 9. By making it hollow, the amount of concrete used can be reduced and the weight of the steel / concrete composite footing 6 can be reduced.

図3(c)に示すように、接合ユニット13も鋼製箱枠からなる。この例では、フーチングユニット12と同様、H形鋼15を用いて作られている。このH形鋼15の表面にもコンクリートとの付着を良くするための頭付きスタッド16が設けられている。また、この接合ユニット13の上面にも、接続鉄筋26が図に示すように設けられる。   As shown in FIG.3 (c), the joining unit 13 also consists of steel box frames. In this example, like the footing unit 12, the H-shaped steel 15 is used. A headed stud 16 for improving adhesion to the concrete is also provided on the surface of the H-shaped steel 15. Further, a connecting reinforcing bar 26 is also provided on the upper surface of the joining unit 13 as shown in the figure.

図に示すように、接合ユニット13の四隅には、鋼・コンクリート複合フーチング6(フーチングユニット12)に接続するための接続端部18が備わっており、図に示すような形で高力ボルト19により接合ユニット13が鋼・コンクリート複合フーチング6(フーチングユニット12)に接続される。この接続は施工現場で行ってもよいが、予め図3(c)に示す形を工場で製作しておくことは好ましい。工場で行うことによって、確実に接続し易くなるとともに施工現場での作業が簡略化できる。   As shown in the figure, connection ends 18 for connecting to the steel / concrete composite footing 6 (footing unit 12) are provided at the four corners of the joining unit 13, and a high strength bolt 19 is formed in the form shown in the figure. Thus, the joining unit 13 is connected to the steel / concrete composite footing 6 (footing unit 12). This connection may be made at the construction site, but it is preferable to make the shape shown in FIG. By doing it at the factory, it is easy to connect reliably and the work at the construction site can be simplified.

上記鋼・コンクリート複合フーチング6と接合ユニット13は、両者接続あるいは無接続の形で現場に運ばれ設置される。この際、鋼・コンクリート複合フーチング6は2本の鋼管杭5,5の上に、図3(c)に示すように、鋼管杭の杭頭部が鋼・コンクリート複合フーチング6における両外側の区画11,11内にそれぞれ挿入された形で設置される。   The steel / concrete composite footing 6 and the joining unit 13 are transported to the site in a connected or non-connected form. At this time, the steel / concrete composite footing 6 is placed on the two steel pipe piles 5 and 5, and as shown in FIG. 11 and 11 are installed in the form inserted respectively.

図3(d)は一対の鋼管杭5,5と一つの鋼・コンクリート複合フーチング6と一つの鋼・コンクリート複合接続部7とを一体化した基礎部3を構成する基礎単体20の完成図である。   FIG. 3 (d) is a completed view of the foundation unit 20 constituting the foundation part 3 in which a pair of steel pipe piles 5, 5, one steel / concrete composite footing 6 and one steel / concrete composite connection part 7 are integrated. is there.

本発明の堤体1における基礎部3は、この基礎単体20を堤体連続方向に連結して並べる形で構築される。このような基礎部の構築であれば、施工が簡便であるとともに現場打ちコンクリートの使用量を抑制できる。   The foundation part 3 in the levee body 1 of the present invention is constructed in such a form that the foundation single bodies 20 are connected and arranged in the levee body continuous direction. If such a foundation is constructed, the construction is simple and the amount of on-site concrete used can be suppressed.

一つの鋼・コンクリート複合フーチング6と一つの鋼・コンクリート複合接続部7とからなる基礎単体20は、鋼・コンクリート複合フーチング6と接合ユニット13とを施工現場で図3(c)に示すように設置後、図3(d)に示すように、一部の接続端部18と接続鉄筋26を除いて現場打ちコンクリート21でフーチングユニット12の未被覆部分を被覆し開口部分を充填するとともに接合ユニット13を被覆することによって得られる。   As shown in FIG. 3 (c), the basic unit 20 composed of one steel / concrete composite footing 6 and one steel / concrete composite joint 7 has the steel / concrete composite footing 6 and the joining unit 13 as shown in FIG. After installation, as shown in FIG. 3 (d), the uncovered portion of the footing unit 12 is covered with the cast-in-place concrete 21 except for some of the connection end portions 18 and the connection reinforcing bars 26, and the opening portion is filled. 13 is obtained by coating.

同時に、鋼・コンクリート複合接続部7も完成する。図に示すように、鋼・コンクリート複合フーチング6の中央部の上面と鋼・コンクリート複合接続部7の上面からは、プレキャスト堅壁と連結するための接続鉄筋26が突出している。   At the same time, the steel / concrete composite connecting portion 7 is also completed. As shown in the drawing, a connecting reinforcing bar 26 for connecting to the precast hard wall protrudes from the upper surface of the central portion of the steel / concrete composite footing 6 and the upper surface of the steel / concrete composite connection portion 7.

本発明では、このように、フーチングユニット12のコンクリート被覆は工場でのコンクリート9による一部被覆と施工現場での現場打ちコンクリート21による残部被覆とによってなされ、接合ユニット13のコンクリート被覆は現場打ちコンクリート21による被覆によってなされる。   In the present invention, the concrete coating of the footing unit 12 is thus made by partial coating with concrete 9 at the factory and the remaining coating with the cast-in-place concrete 21 at the construction site, and the concrete coating of the joining unit 13 is done by cast-in-place concrete. This is done by covering with 21.

図4は、本発明の堤体1におけるプレキャスト堅壁4を示す斜視図である。ここでは、2つのプレキャスト堅壁4が連結した状態を示す。   FIG. 4 is a perspective view showing the precast hard wall 4 in the bank body 1 of the present invention. Here, a state where two precast hard walls 4 are connected is shown.

図に示すように、本発明の堤体1の壁面を形成するプレキャスト堅壁4は鉄筋コンクリート24からなり、壁面部22とその下方の基礎連結部23とからなる。   As shown in the drawing, the precast hard wall 4 forming the wall surface of the dam body 1 of the present invention is made of reinforced concrete 24, and is made up of a wall surface portion 22 and a foundation connecting portion 23 below the wall surface portion 22.

壁面部22は、文字通り、堤体1の壁面となる部分である。この例では、壁面部22は直面を有する平板状のものであるがこれに限定されるものではなく、湾曲状のもの、表面に凹凸があるもの、模様のあるものなど様々な形態を採ることができる。また、壁面を耐久性のある強固なものにすべく、壁面部22の表面に鋼板やFRC板等の補強板や波のエネルギーを吸収するクッション材を取付けてもよい。   The wall surface portion 22 is a portion that literally becomes the wall surface of the levee body 1. In this example, the wall surface portion 22 is a flat plate having a confrontation, but is not limited thereto, and may take various forms such as a curved shape, a surface with irregularities, and a pattern. Can do. In order to make the wall surface durable and strong, a reinforcing plate such as a steel plate or an FRC plate or a cushion material that absorbs wave energy may be attached to the surface of the wall surface portion 22.

壁面部22の寸法は、水圧等の荷重強度により鉄筋コンクリート断面計算により適宜決定する。   The dimension of the wall surface part 22 is appropriately determined by reinforced concrete cross-section calculation according to the load strength such as water pressure.

基礎連結部23は、壁面の一部を形成するとともにプレキャスト堅壁4が安定して立設するための土台や上記鋼・コンクリート複合フーチング6と鋼・コンクリート複合接続部7との連結部となる。   The foundation connecting part 23 forms a part of the wall surface and serves as a base for stably standing the precast hard wall 4 and a connecting part between the steel / concrete composite footing 6 and the steel / concrete composite connecting part 7.

したがって、図に示すように、基礎連結部23は上記壁面部22に比べて厚みが厚くなっているのが好ましい。この厚みは壁面部22の1.5〜3.0倍程度が好ましい。また、ここでは、基礎連結部23の上部にはテーパー25が設けられている。テーパー25を設けることによって、円滑な荷重伝達が図れるとともに、直角の段を設けた場合に比べて、津波時の衝突などに対して、重要な基部の角欠けなどが生じにくくなる利点がある。   Therefore, as shown in the figure, the base connecting portion 23 is preferably thicker than the wall surface portion 22. This thickness is preferably about 1.5 to 3.0 times that of the wall surface portion 22. Here, a taper 25 is provided on the upper portion of the base connecting portion 23. By providing the taper 25, smooth load transmission can be achieved, and compared with the case where a right-angle step is provided, there is an advantage that an important base portion is less likely to be broken due to a collision during a tsunami.

図5〜6は、図1に示す本発明の堤体1の施工例を示す斜視図である。   FIGS. 5-6 is a perspective view which shows the construction example of the bank body 1 of this invention shown in FIG.

図5は基礎部3の構築過程を示す。(a)は鋼管杭5の施工過程を、(b)はフーチングユニット12の設置過程を、(c)は接合ユニット13の設置過程を、(d)は基礎部3の完成過程を、(e)は完成した基礎部3を示す。   FIG. 5 shows the construction process of the foundation 3. (A) shows the construction process of the steel pipe pile 5, (b) shows the installation process of the footing unit 12, (c) shows the installation process of the joining unit 13, (d) shows the completion process of the foundation part 3, (e ) Shows the completed foundation 3.

まず、既設堤防2において、図5(a)に示すように、鋼管杭5による杭施工をし二列に所定間隔をおいて配列する。鋼・コンクリート複合フーチング6との接続部となる鋼管杭5の杭頭部は100cm程度地上に出す。杭内には杭上端から200cm程度の深さに底板を設け現場打ちコンクリートを杭頭部の杭内に充填する。必要に応じ、杭頭部には現場溶接によりズレ止め(鋼板)を設置する(図示省略)。鋼管杭5を打ち込んだ後、場合によっては杭頭を切断するなどして高さの調節を行う。   First, in the existing levee 2, as shown in FIG. 5 (a), pile construction by the steel pipe piles 5 is performed and arranged in two rows at a predetermined interval. The pile head of the steel pipe pile 5 which becomes a connection part with the steel / concrete composite footing 6 is put on the ground about 100 cm. In the pile, a bottom plate is provided at a depth of about 200 cm from the top of the pile, and the cast-in-place concrete is filled into the pile at the top of the pile. If necessary, a pile stopper (steel plate) is installed on the pile head by field welding (not shown). After driving the steel pipe pile 5, the height is adjusted by cutting the pile head or the like in some cases.

次に、図5(b)に示すように、工場で製作した鋼製箱枠からなるフーチングユニットの一部をコンクリート被覆してなる鋼・コンクリート複合フーチング6のユニットを、一組(2本)鋼管杭5,5の杭頭部が鋼・コンクリート複合フーチング6の中に入り込むようにして堤体連続方向に鋼管杭の間隔に合せた所定の間隔で設置する。   Next, as shown in FIG. 5 (b), a pair of steel / concrete composite footing 6 units (2 pieces), each of which is a concrete-covered part of a footing unit made of a steel box frame manufactured at a factory. The pile heads of the steel pipe piles 5 and 5 are installed at a predetermined interval in accordance with the interval between the steel pipe piles in the bank body continuous direction so that the pile heads enter the steel / concrete composite footing 6.

次に、図5(c)に示すように、工場で製作した鋼製箱枠からなる接合ユニット13を鋼・コンクリート複合フーチング6,6間に配置しこれらフーチング(フーチングユニット)と連結する。連結は高力ボルトにより行う。   Next, as shown in FIG.5 (c), the joining unit 13 which consists of a steel box frame manufactured at the factory is arrange | positioned between the steel and concrete composite footings 6 and 6, and it connects with these footings (footing unit). The connection is made with high strength bolts.

なお、この例では、上記鋼・コンクリート複合フーチング6と接合ユニット13とを工場でそれぞれ別々に製作して施工現場に運び施工現場で連結しているが、図3(c)に示したように、鋼・コンクリート複合フーチング6と接合ユニット13とを工場で連結した連結ユニットを施工現場に運び、施工現場で隣の鋼・コンクリート複合フーチング6と接合ユニット13の片側とを連結してもよい。このようにすれば、施工現場での連結作業が簡略化できる。   In this example, the steel / concrete composite footing 6 and the joining unit 13 are separately manufactured at the factory, transported to the construction site, and connected at the construction site. As shown in FIG. Alternatively, a connecting unit in which the steel / concrete composite footing 6 and the joining unit 13 are connected at the factory may be carried to the construction site, and the adjacent steel / concrete composite footing 6 and one side of the joining unit 13 may be connected at the construction site. In this way, the connection work at the construction site can be simplified.

次に、図5(d)と図5(e)に示すように、プレキャスト堅壁に連結される接続鉄筋の26の上部を除き、鋼材が露出しているコンクリートの未被覆部分はすべて現場打ちコンクリート21で被覆する。被覆厚は、前述のコンクリート9による被覆厚と同じである。このようにして、本発明の堤体1の基礎部3が既設堤防2の上に完成する。   Next, as shown in FIGS. 5 (d) and 5 (e), all the uncovered portions of the concrete where the steel material is exposed, except for the upper part of the connecting rebar 26 connected to the precast hard wall, are cast in place. Cover with 21. The coating thickness is the same as the coating thickness of the concrete 9 described above. In this way, the foundation 3 of the levee body 1 of the present invention is completed on the existing levee 2.

図6は、基礎部3の完成以降、該基礎部3の上にプレキャスト堅壁4を立設し本発明の堤体1を完成させるまでの過程を示す。(f)は、プレキャスト堅壁4の立設過程を、(g)は埋め戻しの土31による堤体1と道路8の完成過程を示す。   FIG. 6 shows the process from the completion of the foundation 3 to the completion of the dam body 1 of the present invention by standing the precast hard wall 4 on the foundation 3. (F) shows the standing process of the precast hard wall 4, and (g) shows the completion process of the dam body 1 and the road 8 by the backfilled soil 31.

図6(f)に示すように、完成した基礎部における鋼・コンクリート複合フーチング6と鋼・コンクリート複合接続部7の上に、堤体連続方向に壁面が形成されるようにしてプレキャスト堅壁4が立設して並べられる。鋼・コンクリート複合フーチング6においては、プレキャスト堅壁4と鋼・コンクリート複合フーチング6とで縦断面(側面)が逆T型になるように、その中央部に立設される。隣接するプレキャスト堅壁4,4同士の連結は、例えば、止水を目的としたシール材を挟み込み、これを鋼棒の引張力で締め付けて連結する。   As shown in FIG. 6 (f), the precast hard wall 4 is formed on the steel / concrete composite footing 6 and the steel / concrete composite joint 7 in the completed foundation so that a wall surface is formed in the continuous direction of the levee body. Standing up and lining up. The steel / concrete composite footing 6 is erected at the center of the precast rigid wall 4 and the steel / concrete composite footing 6 so that the longitudinal section (side surface) is an inverted T-shape. Adjacent precast hard walls 4 and 4 are connected to each other by, for example, sandwiching a sealing material for the purpose of water stop and tightening it with a tensile force of a steel rod.

その後、図6(g)に示すように、埋め戻しの土31により突出した鋼・コンクリート複合フーチング6,6の間を埋めることによって本発明の堤体1が完成する。埋め戻しの土31による埋め戻し形態は、必ずしも図に示すような形態に限定されるものではなく、例えば、プレキャスト堅壁4の下部の基礎連結部を覆い隠す形で盛土にしてもよい。また、埋め戻しの土31は単なる土砂だけでなくセメント等の固化材を混和したものでもよい。   Thereafter, as shown in FIG. 6 (g), the embankment 1 of the present invention is completed by filling the space between the steel / concrete composite footings 6, 6 protruding by the backfilling soil 31. The form of backfilling with the soil 31 for backfilling is not necessarily limited to the form shown in the figure, and for example, it may be embanked in such a manner as to cover the lower base connecting portion of the precast hard wall 4. The backfill soil 31 is not limited to mere soil and sand but may be a mixture of cement or other solidifying material.

プレキャスト堅壁4の裏側(陸地側)は道路8として利用することができる。その場合は、下層に路盤材を敷くなど従来の道路施工方法に準じて施工すれば良い。   The back side (land side) of the precast hard wall 4 can be used as the road 8. In that case, it may be constructed according to a conventional road construction method such as laying a roadbed material in the lower layer.

図7は、プレキャスト堅壁と基礎部との連結方法の一例を示す図であり、プレキャスト堅壁4における基礎連結部23の縦断面拡大図である。   FIG. 7 is a view showing an example of a method for connecting the precast hard wall and the foundation portion, and is an enlarged vertical cross-sectional view of the foundation connection portion 23 in the precast hard wall 4.

図に示すように、鉄筋コンクリート24で作られたプレキャスト堅壁4における基礎連結部23に配筋された鉄筋コンクリートの鉄筋27の下端にはモルタル充填式継手のパイプ28が設けられている。このモルタル充填式継手のパイプ28は、接続鉄筋26がしっかり挿入できる長さと、鉄筋径に若干の施工誤差が吸収できる寸法の内径を有している。また、このモルタル充填式継手のパイプ28内にモルタルが注入充填できるよう、パイプに繋がる形で、モルタル注入口29とモルタル排出口30が設けられている。   As shown in the figure, a mortar-filled joint pipe 28 is provided at the lower end of a reinforced concrete reinforcing bar 27 arranged in a foundation connecting portion 23 in a precast hard wall 4 made of reinforced concrete 24. The pipe 28 of this mortar filling type joint has a length that allows the connecting reinforcing bars 26 to be inserted firmly and an inner diameter that can absorb a slight construction error in the reinforcing bar diameter. Also, a mortar inlet 29 and a mortar outlet 30 are provided in a form connected to the pipe so that mortar can be injected and filled into the pipe 28 of the mortar filling type joint.

プレキャスト堅壁4と基礎部3との連結は、図5(d)に示すように、鋼・コンクリート複合フーチング6と鋼・コンクリート複合接続部7から上に突出して設けられた接続鉄筋26をプレキャスト堅壁4のモルタル充填式継手のパイプ28内に挿入し、接続鉄筋26の周囲をパイプ内に注入充填されたモルタルで固めることによってなされる。モルタルは高強度モルタルが好ましい。連結を強固なものにするために、接続鉄筋26を異形鉄筋にしてもよい。この例では連結箇所は2箇所であるがこれに限定されるものではなく、3箇所以上で連結してもよい。   As shown in FIG. 5 (d), the precast hard wall 4 and the foundation portion 3 are connected by connecting the steel / concrete composite footing 6 and the connecting rebar 26 projecting upward from the steel / concrete composite joint 7. 4 is inserted into the pipe 28 of the mortar-filled joint, and the periphery of the connecting reinforcing bars 26 is solidified with mortar injected and filled into the pipe. The mortar is preferably a high strength mortar. In order to strengthen the connection, the connecting reinforcing bars 26 may be deformed reinforcing bars. In this example, there are two connection locations, but the present invention is not limited to this, and connection may be performed at three or more locations.

以上の通り、本発明の堤体は、幾つかのプレキャスト部材(ユニット)を工場で製作し、これらを施工現場で組立てて構築するものであるからして、安定した高品質なものであるとともに現場での施工が熟練工を必要とせず容易となる。   As described above, the dike body of the present invention is manufactured by manufacturing several precast members (units) at a factory and assembling and constructing them at a construction site. Construction on site is easy without the need for skilled workers.

また、基礎部は鋼製箱枠からなるユニットを主体とした鋼・コンクリート複合構造のハイブリッド型のものなので強固であるとともに、場所打ちコンクリートによる施工を少なくして施工現場でコンクリート使用量をできるだけ抑制した堤体を得ることができ、震災復興に際して発生した施工現場へのコンクリートの供給不足といった昨今の問題も解決できる。   In addition, the foundation is strong because it is a hybrid type of steel / concrete composite structure mainly composed of steel box frame units, and it reduces the amount of concrete used at the construction site as much as possible by reducing the amount of cast-in-place concrete. This can solve the recent problems such as the shortage of concrete supply to the construction site that occurred during the earthquake reconstruction.

1…堤体、2…既設堤防、3…基礎部、4…プレキャスト堅壁、5…鋼管杭、6…鋼・コンクリート複合フーチング、7…鋼・コンクリート複合接続部、8…道路、9…コンクリート、10…中央部の区画、11…外側の区画、12…フーチングユニット、13…接合ユニット、14…間の区画、15…H形鋼、16…頭付きスタッド、17…挿入孔、
18…接続端部、19…高力ボルト、20…基礎単体、21…現場打ちコンクリート、
22…壁面部、23…基礎連結部、24…鉄筋コンクリート、25…テーパー、26…接続鉄筋、27…鉄筋コンクリートの鉄筋、28…モルタル充填式継手のパイプ、29…モルタル注入口、30…モルタル排出口、31…埋め戻しの土
DESCRIPTION OF SYMBOLS 1 ... Dam body, 2 ... Existing levee, 3 ... Foundation part, 4 ... Precast hard wall, 5 ... Steel pipe pile, 6 ... Steel-concrete composite footing, 7 ... Steel-concrete composite connection part, 8 ... Road, 9 ... Concrete, DESCRIPTION OF SYMBOLS 10 ... Section of center part, 11 ... Outer section, 12 ... Footing unit, 13 ... Joining unit, 14 ... Between section, 15 ... H-section steel, 16 ... Headed stud, 17 ... Insertion hole,
18 ... Connection end, 19 ... High strength bolt, 20 ... Single foundation, 21 ... In-situ concrete,
DESCRIPTION OF SYMBOLS 22 ... Wall part, 23 ... Foundation connection part, 24 ... Reinforced concrete, 25 ... Taper, 26 ... Connection reinforcement, 27 ... Reinforcement of reinforced concrete, 28 ... Pipe of mortar filling type joint, 29 ... Mortar injection port, 30 ... Mortar discharge port 31 ... Soil for backfilling

Claims (6)

基礎部の上にプレキャスト堅壁を堤体連続方向に並べて壁面を形成した堤体であって、該基礎部は、二列に配列された鋼管杭と該鋼管杭に支持され堤体連続方向に所定の間隔をあけて並設される鋼・コンクリート複合フーチングと該鋼・コンクリート複合フーチング間に配置される鋼・コンクリート複合接続部とからなり、前記鋼・コンクリート複合フーチング上に立設される前記プレキャスト堅壁は、該鋼・コンクリート複合フーチングにおける壁面直角方向の中央部に設けられていることを特徴とする堤体。   A dam body in which precast hard walls are arranged on a foundation portion in a wall continuation direction to form a wall surface, and the foundation portion is supported by two rows of steel pipe piles and supported by the steel pipe pile in a levee body continuation direction. The precast that is erected on the steel / concrete composite footing, comprising a steel / concrete composite footing arranged side by side and a steel / concrete composite joint disposed between the steel / concrete composite footings. An embankment characterized in that the hard wall is provided at a central portion of the steel / concrete composite footing in a direction perpendicular to the wall surface. 前記鋼・コンクリート複合フーチングは、H形鋼を用いて形成した箱枠からなるフーチングユニットを用いたものであり、該フーチングユニットの周囲をコンクリートで被覆したものであることを特徴とする請求項1に記載の堤体。   The steel / concrete composite footing uses a footing unit made of a box frame formed of H-shaped steel, and the surrounding of the footing unit is covered with concrete. The embankment described in 1. 前記鋼・コンクリート複合接続部は、H形鋼を用いて形成した箱枠からなる接合ユニットを用いたものであり、該接合ユニットの周囲をコンクリートで被覆したものであることを特徴とする請求項1または2に記載の堤体。   The steel / concrete composite connecting portion uses a joining unit composed of a box frame formed of H-shaped steel, and the periphery of the joining unit is covered with concrete. The bank body according to 1 or 2. 前記フーチングユニットは長さ方向に5つに区画されており、この区画は、前記プレキャスト堅壁が立設される該フーチングユニット中央部の区画と、該区画に対して対称的に両外側に設けられ二列に配列された各列の前記鋼管杭の上端部を差し込むための挿入孔が設けられた2つの区画と、これら区画と前記中央部の区画との間に設けられる中空の2つの区画とからなることを特徴とする請求項に記載の堤体。 The footing unit is divided into five sections in the length direction, and these sections are provided on the outer sides symmetrically with respect to the section in the center of the footing unit where the precast hard wall is erected. Two compartments provided with insertion holes for inserting the upper ends of the steel pipe piles in each row arranged in two rows, and two hollow compartments provided between these compartments and the central compartment The levee body according to claim 2 , comprising: 前記プレキャスト堅壁は鉄筋コンクリートからなり、壁面部と該壁面部の下方にあって該壁面部より厚みの厚い基礎連結部とで構成されることを特徴とする請求項1〜4のいずれか一項に記載の堤体。   The precast hard wall is made of reinforced concrete, and includes a wall surface portion and a foundation connecting portion below the wall surface portion and thicker than the wall surface portion. The listed embankment. 堤体連続方向における前記プレキャスト堅壁の壁幅は、前記鋼・コンクリート複合フーチングの幅よりも大きく、前記プレキャスト堅壁が前記鋼・コンクリート複合フーチングから隣設される前記鋼・コンクリート複合接続部に跨って設置されることを特徴とする請求項1〜5のいずれか一項に記載の堤体。   The wall width of the precast hard wall in the levee body continuous direction is larger than the width of the steel / concrete composite footing, and the precast hard wall straddles the steel / concrete composite joint adjacent to the steel / concrete composite footing. The bank body according to any one of claims 1 to 5, wherein the bank body is installed.
JP2014075282A 2014-04-01 2014-04-01 Embankment Active JP6298688B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2014075282A JP6298688B2 (en) 2014-04-01 2014-04-01 Embankment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2014075282A JP6298688B2 (en) 2014-04-01 2014-04-01 Embankment

Publications (2)

Publication Number Publication Date
JP2015196983A JP2015196983A (en) 2015-11-09
JP6298688B2 true JP6298688B2 (en) 2018-03-20

Family

ID=54546843

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2014075282A Active JP6298688B2 (en) 2014-04-01 2014-04-01 Embankment

Country Status (1)

Country Link
JP (1) JP6298688B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6944807B2 (en) * 2017-04-14 2021-10-06 株式会社横河Nsエンジニアリング Seawall and seawall construction method

Family Cites Families (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4951743A (en) * 1972-09-22 1974-05-20
JPS56138954U (en) * 1980-03-22 1981-10-21
JPS5789027A (en) * 1980-11-20 1982-06-03 Taisei Corp Multipillar type foundation construction method
JPS60175668A (en) * 1984-02-21 1985-09-09 川崎重工業株式会社 Construction of cylindrical tank
JPS646418A (en) * 1987-06-29 1989-01-11 Tokyu Kensetsu Kk Pile head pin-joint structure in pile foundation of building
JP2886376B2 (en) * 1992-02-17 1999-04-26 株式会社テノックス Anchor structure of pile head
JP2797238B2 (en) * 1993-04-05 1998-09-17 日本スプライススリーブ株式会社 Method of joining precast reinforced concrete wall members
JP4175225B2 (en) * 2003-09-18 2008-11-05 Jfeエンジニアリング株式会社 Footing structure and construction method thereof
JP2007032260A (en) * 2005-06-21 2007-02-08 Takao Miyake Assembly component for constructing reinforced concrete building and assembling work method
JP2008291601A (en) * 2007-05-28 2008-12-04 Nishimatsu Constr Co Ltd Pile head joining structure
US20090110484A1 (en) * 2007-10-24 2009-04-30 Fillingame O Wayne Storm surge breaker system, barrier system and method of constructing same
JP6008267B2 (en) * 2011-08-03 2016-10-19 株式会社石井鐵工所 Steel tank prefabricated concrete breakwater
JP5024489B1 (en) * 2012-02-08 2012-09-12 Jfeエンジニアリング株式会社 Embankment
JP5879193B2 (en) * 2012-05-07 2016-03-08 新日鉄住金エンジニアリング株式会社 Seawall

Also Published As

Publication number Publication date
JP2015196983A (en) 2015-11-09

Similar Documents

Publication Publication Date Title
JP2015183453A (en) Dam body
JP6166550B2 (en) Embankment
CN210482200U (en) Ecological bank protection structure of high and steep river course bank slope
JP6263864B2 (en) Seawall
JP7149919B2 (en) Improvement structure and improvement method of existing wharf
JP2013002086A (en) Pile frame structure and structure of the same
JP6938199B2 (en) Seawall panel, seawall and seawall construction method
JP3905776B2 (en) Revetment structure
JP6298688B2 (en) Embankment
CN209907412U (en) Assembled steel construction cofferdam
JP6166547B2 (en) Embankment
KR100245048B1 (en) Reinforced soil structure
JP2022115624A (en) Quay wall structure, and construction method of the same
JP2019137991A (en) Connection structure of structural steelwork and precast concrete member, structural wall with the connection structure and connection method of structural steelwork and precast concrete member
JP5280150B2 (en) Yamadome retaining wall and method of forming Yamadome retaining wall
JP6447669B2 (en) Seawall and construction method of seawall
CN201883449U (en) Sea wall structure of compound pile
JP7126889B2 (en) Steel wall and its construction method
JP2003321826A (en) Earthquake resisting property reinforced structure of levee body such as earth filling dam or the like
KR100227536B1 (en) Bell type caisson foundation method
JP7495904B2 (en) Improvement structure and method of existing wharf
JP4231194B2 (en) Revetment structure
TWI646239B (en) Stacking block for retaining wall and concrete structure using stacked block for retaining wall
JP7480069B2 (en) How to reinforce existing revetments
CN113373966B (en) Semi-fabricated pier foundation and construction method thereof

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20170302

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20171214

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20171219

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20180126

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20180220

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20180226

R150 Certificate of patent or registration of utility model

Ref document number: 6298688

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313114

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250