JP6028984B2 - How to replace the pier - Google Patents

How to replace the pier Download PDF

Info

Publication number
JP6028984B2
JP6028984B2 JP2015041531A JP2015041531A JP6028984B2 JP 6028984 B2 JP6028984 B2 JP 6028984B2 JP 2015041531 A JP2015041531 A JP 2015041531A JP 2015041531 A JP2015041531 A JP 2015041531A JP 6028984 B2 JP6028984 B2 JP 6028984B2
Authority
JP
Japan
Prior art keywords
pier
column
existing
piers
pair
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2015041531A
Other languages
Japanese (ja)
Other versions
JP2016160686A (en
Inventor
明 曽我
明 曽我
隆 志熊
隆 志熊
慈弘 笠間
慈弘 笠間
孝史朗 高田
孝史朗 高田
智明 青山
智明 青山
辰男 緒方
辰男 緒方
憲夫 垣内
憲夫 垣内
孝輔 西浦
孝輔 西浦
Original Assignee
三井造船鉄構エンジニアリング株式会社
西日本高速道路株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 三井造船鉄構エンジニアリング株式会社, 西日本高速道路株式会社 filed Critical 三井造船鉄構エンジニアリング株式会社
Priority to JP2015041531A priority Critical patent/JP6028984B2/en
Publication of JP2016160686A publication Critical patent/JP2016160686A/en
Application granted granted Critical
Publication of JP6028984B2 publication Critical patent/JP6028984B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、道路橋、鉄道橋などの橋梁の上部構造を支持する既存の橋脚を、新規のものに建て替える橋脚の交換方法に関する。   The present invention relates to a method of exchanging bridge piers that rebuilds existing piers that support the superstructure of bridges such as road bridges and railway bridges to new ones.

道路橋又は鉄道橋などの橋梁の中間部分を構成する橋脚がある。
既存の橋脚は、経年劣化による老朽化や、大型地震に対する耐震性能を強化するために補強や交換(建て替え)作業が必要となる。
橋脚の補強は、一般に柱部の外周に補強鋼板を巻き付けたり、モルタルを吹き付けたりするなどして容易かつ安価に強度を高めることができる。
There are piers that constitute the middle part of a bridge such as a road bridge or a railway bridge.
Existing bridge piers need to be reinforced and replaced (rebuilt) in order to improve the seismic performance against aging due to aging and large earthquakes.
In general, the strength of the pier can be easily and inexpensively increased by winding a reinforcing steel plate around the outer periphery of the column portion or spraying mortar.

一方、橋脚の建て替えの場合には、既存の上部構造を支持しながら作業を進めなければならず、いかに安全性を確保し、施工コストを抑制するかが課題となっている。また、幹線道路の場合には、通行止めを極力少なくして短期間で施工することが求められている。   On the other hand, when rebuilding piers, work must be carried out while supporting the existing superstructure, and how to secure safety and reduce construction costs is a challenge. Moreover, in the case of a main road, it is required to perform the construction in a short period with as few road closures as possible.

従来の交換方法としてベント(仮受け台)を用いた工法がある。この工法は、まず既存の橋脚に近接した位置に仮設のベントを設置する。このベントにより上部構造を支持した状態を確保した後、既存の橋脚を解体、撤去する。そして既存の橋脚と同じ場所に新規橋脚を建設する。新規橋脚で上部構造を支持した後、ベントを解体、撤去している。
この他、橋脚が2つの単柱型橋脚で構成されている場合の橋脚の交換方法は次のような工程を採用していた。
As a conventional replacement method, there is a method using a vent (temporary cradle). In this method, a temporary vent is first installed at a position close to the existing pier. After ensuring that the upper structure is supported by this vent, the existing pier is dismantled and removed. A new pier will be constructed at the same location as the existing pier. After supporting the superstructure with the new pier, the vent is dismantled and removed.
In addition, when the pier is composed of two single-column piers, the pier replacement method employs the following process.

図4は従来の橋脚の交換方法の説明図である。なお各ステップの上図は単柱式橋脚の先端から下方の平面図を示し、下図は橋脚の正面図を示す。
上部構造220の横桁の下部に仮支点用横梁222を設置する(ステップ100)。既存支承110aが支える主桁と比べ強度の小さい横桁に対して、仮支点用横梁222などの補強材を形成して仮支点との接触箇所を補強する。
FIG. 4 is an explanatory view of a conventional pier replacement method. The upper figure of each step shows a plan view below the tip of the single-column pier, and the lower figure shows a front view of the pier.
A temporary fulcrum cross beam 222 is installed below the cross beam of the upper structure 220 (step 100). A reinforcing member such as the temporary support fulcrum beam 222 is formed on the cross beam having a lower strength than the main beam supported by the existing bearing 110a to reinforce the contact point with the temporary support point.

一対の単柱式橋脚110の橋脚間に張出し式橋脚を設置可能な基礎120を施工する(ステップ101)。
ついで基礎120の上部に張出し式橋脚の柱部140を設置する(ステップ102)。
A foundation 120 on which an overhanging pier can be installed is constructed between the piers of the pair of single-column piers 110 (step 101).
Next, the column part 140 of the overhanging pier is installed on the upper part of the foundation 120 (step 102).

柱部140の上部に梁部160を設置する(ステップ103)。梁部160は既存の単柱式橋脚110を撤去することなく形成できるように、長手方向が一対の単柱式橋脚110の橋脚間よりも短い長さに設定されている。
上部構造220の荷重を支持する仮支点400を梁部160の上面に設置する(ステップ104)。仮支点400は、既存支承110aを除去した際に、一対の既存支承110aの支承間よりも狭い箇所で、上部構造220をバランスよく支持できる箇所を選択する必要がある。
The beam part 160 is installed on the upper part of the column part 140 (step 103). The beam portion 160 is set to have a length shorter than that between the pair of single-column piers 110 so that the beam unit 160 can be formed without removing the existing single-column piers 110.
The temporary fulcrum 400 that supports the load of the upper structure 220 is installed on the upper surface of the beam portion 160 (step 104). The temporary fulcrum 400 needs to be selected at a location that can support the upper structure 220 in a well-balanced manner at a location narrower than the interval between the pair of existing supports 110a when the existing support 110a is removed.

単柱式橋脚を撤去する(ステップ105)。一対の仮支点400の支点間は一対の既存支承の支点間よりも短いため、既存の単柱式橋脚を撤去すると、上部構造220の両端部分が下方に低下してしまい上部構造220に僅かな歪みが生じて負荷がかかるおそれがある。
一対の延長梁200をチェーンブロックなどの吊上げ手段を用いて梁部160まで吊上げて、梁部160の両端に接続する(ステップ106)。
The single pillar type pier is removed (step 105). Since the distance between the fulcrum points of the pair of temporary fulcrum 400 is shorter than the fulcrum point of the pair of existing bearings, when the existing single column type pier is removed, both end portions of the upper structure 220 are lowered downward, and the upper structure 220 has a slight amount. There is a risk of distortion and load.
The pair of extension beams 200 are lifted up to the beam portion 160 by using a lifting means such as a chain block and connected to both ends of the beam portion 160 (step 106).

延長梁200の上面で、既存支承が設置されていた箇所よりも外側にジャッキ300を設置して上部構造220をジャッキ受けする(ステップ107)。仮支点400のみで上部構造を支えていた際に生じた上部構造220の歪みが解消されるまで持ち上げる。   On the upper surface of the extension beam 200, the jack 300 is installed outside the portion where the existing support is installed, and the upper structure 220 is jacked (step 107). The upper structure 220 is lifted until the distortion of the upper structure 220 generated when the upper structure is supported only by the temporary fulcrum 400 is eliminated.

延長梁200の上面で既存支承が設置されていた箇所と同じ箇所に張出し式橋脚の新規の支承240を設置する(ステップ108)。
仮支点400及びジャッキ300を撤去すると張出し式橋脚100の支承240で上部構造220を支えることができ、橋脚の交換作業が完了する(ステップ109)。
A new support 240 of an overhanging pier is installed at the same location where the existing support was installed on the upper surface of the extension beam 200 (step 108).
When the temporary fulcrum 400 and the jack 300 are removed, the upper structure 220 can be supported by the support 240 of the overhanging pier 100, and the replacement work of the pier is completed (step 109).

また特許文献1に開示の橋脚の建て替え方法は、ラケット型の橋脚の建て替え方法であって、既存橋脚を挟むように新規橋脚を2つ建て、新規橋脚によって上部構造を支持してから既存橋脚を撤去している。   Moreover, the rebuilding method of the bridge pier disclosed in Patent Document 1 is a racket-type bridge pier rebuilding method. Two new piers are built so as to sandwich the existing pier, and the superstructure is supported by the new pier, and then the existing pier is installed. It has been removed.

特開2008−303698号公報JP 2008-303698 A

しかしながら、ベントを用いた交換方法では、既設橋脚の前後にベントを設置・施工するためのスペースを確保する必要がある。架設現場によっては、スペースを確保できず桁下の道路内などに設置しなければならない場合があり、長時間の車線規制あるいは通行止めを行わなければならないことがある。またベントによる仮支持の間も交通道路として使用するため、ベントの基礎は既存橋脚と同程度の規模が必要となる。さらに、仮基礎設置時の施工性に配慮して、省スペース化のため直接基礎とする場合には、既設橋脚の基礎よりも規模の大きな基礎寸法が必要となる。   However, in the replacement method using the vent, it is necessary to secure a space for installing and constructing the vent before and after the existing pier. Depending on the construction site, there is a case where a space cannot be secured and it must be installed in a road under the girder, etc., and it may be necessary to perform long-term lane regulation or traffic closure. Also, since the temporary support by the vent is used as a traffic road, the base of the vent needs to be the same size as the existing pier. Furthermore, in consideration of workability at the time of temporary foundation installation, when using a direct foundation for space saving, a foundation size larger than the foundation of the existing pier is required.

また図4に示す交換方法では、既存支承よりも支点間の短い仮支点で仮支持している間に上部構造に歪み等が生じて負荷がかかるおそれがある。さらに、既存支承の換わりに上部構造の荷重を支える仮支点とジャッキの間が離れているため、上部構造に歪等の負荷がかかるおそれがある。このため、交換作業の安全性を十分に確保することができないおそれがあった。   Further, in the replacement method shown in FIG. 4, there is a risk that the upper structure may be distorted or the like while being temporarily supported at a temporary fulcrum between fulcrums than the existing bearing. Furthermore, since the temporary fulcrum supporting the load of the upper structure is separated from the jack in place of the existing bearing, there is a risk that a load such as strain is applied to the upper structure. For this reason, there is a possibility that the safety of the replacement work cannot be sufficiently ensured.

さらに、仮支点及び仮支点用横梁を用いることにより作業コストがかかり、交換作業にかかる日数が長期化してしまう問題があった。   In addition, the use of temporary fulcrum and temporary fulcrum crossbeams increases the work cost and prolongs the number of days for replacement work.

特許文献1に示す建て替え方法では、2つの新規橋脚を形成しているためコスト高となり、かつ設置スペースも確保しなければならない。   In the rebuilding method shown in Patent Document 1, since two new piers are formed, the cost is high and the installation space must be secured.

また、既存支承と異なる箇所に新規支承を形成する場合には、主桁に別途補強部を設ける必要があり、かつ、支承の数が既設より増えることでイニシャルコストの他、将来的な維持管理コストも高くなる。   In addition, when a new bearing is formed at a location different from the existing bearing, it is necessary to provide a separate reinforcing part in the main girder, and the number of bearings increases from the existing one, so that the initial cost and future maintenance management Costs also increase.

上記従来技術の問題点を解決するため、本発明は、交換作業の安全性を高めることができる橋脚の交換方法を提供することを目的としている。また本発明は、施工コストを抑えることができる橋脚の交換方法を提供することを目的としている。   In order to solve the above-described problems of the prior art, an object of the present invention is to provide a bridge pier replacement method capable of enhancing the safety of replacement work. Another object of the present invention is to provide a pier replacement method that can reduce the construction cost.

上記課題を解決するための第1の手段として、上部構造を支持する一対の単柱式橋脚の間に、張出し式橋脚の基礎と、前記基礎の上方に前記一対の単柱式橋脚の橋脚間よりも短い梁部を形成する工程と、前記単柱式橋脚が挿通する貫通孔を備えた一対の延長梁を前記単柱式橋脚の長手方向に沿って吊上げて前記梁部の両端にそれぞれ接続する工程と、前記基礎と前記梁部の間のスペースに張出し式橋脚の柱部を設置する工程と、前記梁部及び前記延長梁の上面、かつ前記単柱式橋脚の既存支承の周囲にジャッキを配置して前記上部構造をジャッキ受けする工程と、前記単柱式橋脚を切断し、前記単柱式橋脚の下部から取り除いて先端を前記貫通孔から引き抜いて撤去する工程と、前記貫通孔を閉塞して前記延長梁の上面に前記張出し式橋脚の新規支承を形成する工程と、を有することを特徴とする橋脚の交換方法を提供することにある。 As a first means for solving the above-mentioned problem, between the pair of single-column piers supporting the superstructure, between the foundation of the overhang-type pier and the piers of the pair of single-column piers above the foundation Forming a shorter beam portion and a pair of extended beams provided with through-holes through which the single-column pier is inserted are connected to both ends of the beam portion by lifting along the longitudinal direction of the single-column pier A step of installing an overhanging pier column in a space between the foundation and the beam portion , and a jack around the upper surface of the beam portion and the extension beam and around the existing support of the single column pier. Placing the upper structure and receiving the upper structure, cutting the single-column pier, removing from the lower portion of the single-column pier, removing the tip from the through-hole, and removing the through-hole. The overhanging pier is closed on the upper surface of the extension beam. And to provide a method of replacing piers characterized by having a step of forming a Tadashi bearing.

上記課題を解決するための第2の手段として、前記延長梁は、前記梁部の長手方向に沿って前記貫通孔の径方向に二分割された一対の半割構造体を組み合わせて形成することを特徴とする橋脚の交換方法を提供することにある。   As a second means for solving the above-mentioned problem, the extension beam is formed by combining a pair of halved structures divided into two in the radial direction of the through hole along the longitudinal direction of the beam portion. It is in providing the exchange method of the bridge pier characterized by this.

上記課題を解決するための第3の手段として、前記第1又は第2の手段において、前記柱部は材質に鉄筋コンクリートを用い、前記梁部及び前記延長梁は材質に鋼鉄を用いたことを特徴とする橋脚の交換方法を提供することにある。   As a third means for solving the above-mentioned problem, in the first or second means, the column part is made of reinforced concrete, and the beam part and the extension beam are made of steel. It is to provide a method for replacing the pier.

上記のような本発明によれば、従来工法のようなベントを用いて仮支持する必要がなく、桁下の道路などの交通規制を最小限に抑えることができ、かつ施工コストの低減化を図ることができる。   According to the present invention as described above, there is no need for temporary support using a vent as in the conventional construction method, traffic regulations such as under-sparing roads can be minimized, and construction costs can be reduced. Can be planned.

また新規橋脚を設置した後に、既存橋脚を撤去しているため、取り替え時の仮支持期間を大幅に短縮でき、かつ交通供用下での施工の安全性を向上させることができる。   In addition, since the existing pier is removed after the new pier is installed, the temporary support period at the time of replacement can be greatly shortened, and the safety of construction under traffic service can be improved.

さらに、既存橋脚を下方から切断・撤去する、いわゆるだるま落としの方式で撤去することにより、高所作業を低減して安全性を向上させることができ、かつ施工スペースを最小限に抑えることができる。   In addition, by cutting and removing existing piers from below, the so-called daruma drop method can be used to reduce work at high places and improve safety, while minimizing construction space. .

また、一対の既存支承の支点間よりも幅の狭い支点間で構造上支持しなければならない一対の仮支点による仮受期間がなく、上部構造に歪み等の負荷がかかるおそれがない。また、橋脚の延長梁を形成する工程まで既存橋脚で上部構造の荷重を支えながら交換作業を行うことができるので、上部構造に負荷をかけることなく作業の安全性を確保できる。   Moreover, there is no provisional receiving period by the pair of temporary fulcrums that must be structurally supported between the fulcrums narrower than the fulcrums of the pair of existing bearings, and there is no possibility of applying a load such as distortion to the upper structure. In addition, since the replacement work can be performed while supporting the load of the upper structure with the existing pier until the process of forming the extension beam of the pier, the safety of the work can be ensured without applying a load to the upper structure.

また、従来のような仮支点、横桁の補強材および仮設材を省略することにより施工コストを抑えることができ、かつ既存橋脚から新規橋脚へ速やかに移行でき橋脚の交換作業にかかる日数を短期化することができる。   In addition, construction costs can be reduced by omitting the temporary fulcrum, cross girder reinforcement and temporary materials as before, and the existing pier can be quickly transferred to the new pier, reducing the number of days required for pier replacement work. Can be

上記のような本発明によれば、既存の単柱式橋脚を撤去することなく延長梁を形成することができる。また、既存の単柱式橋脚を利用して安全かつ容易に延長梁を梁部まで吊上げて、接続させることができる。   According to the present invention as described above, the extension beam can be formed without removing the existing single-column pier. In addition, it is possible to safely and easily lift the extension beam to the beam portion and use the existing single-column pier.

上記のような本発明によれば、柱部に鉄筋コンクリートを用いているため、圧縮力に強く、強度を高めることができ、かつ安価であるため施工費を抑えることができる。また、梁部及び延長梁に鋼鉄を用いているため、形状加工の自由度が高く施工性が良く、交換作業にかかる日数を短期化することができる。   According to the present invention as described above, since the reinforced concrete is used for the column portion, it is strong in compressive force, can be increased in strength, and is inexpensive, so that the construction cost can be suppressed. Moreover, since steel is used for the beam portion and the extension beam, the degree of freedom of shape processing is high and the workability is good, and the number of days required for the replacement work can be shortened.

本発明の橋脚の交換方法の説明図である。It is explanatory drawing of the exchange method of the pier of this invention. 本実施形態の張出し式橋脚の説明図である。It is explanatory drawing of the overhang type pier of this embodiment. 本実施形態の延長梁の説明図である。It is explanatory drawing of the extension beam of this embodiment. 従来の橋脚の交換方法の説明図である。It is explanatory drawing of the replacement | exchange method of the conventional pier.

本発明の橋脚の交換方法の実施形態について、添付の図面を参照しながら以下詳細に説明する。ここで、本発明の橋脚の交換方法は、上部構造を幅方向に支持する一対の単柱式橋脚(円筒橋脚ともいう。)から張出し式橋脚(T型橋脚ともいう)に交換する方法を適用対象としている。一対の単柱式橋脚は所定間隔を開けて施工されており、この橋脚間には新たな張出し式橋脚を施工可能なスペースがあるものとする。   Embodiments of the pier replacement method of the present invention will be described below in detail with reference to the accompanying drawings. Here, the pier replacement method according to the present invention is a method of replacing a pair of single-column piers (also referred to as cylindrical piers) that support the upper structure in the width direction into an overhang type pier (also referred to as a T-type pier). It is targeted. A pair of single-column piers are constructed at a predetermined interval, and there is a space between these piers where a new overhanging pier can be constructed.

[張出し式橋脚10]
図2は本実施形態の張出し式橋脚の説明図である。同図の(1)は支承から下方に向けた橋脚の平面図であり、(2)は橋脚の正面図である。図示のように、本実施形態の張出し式橋脚10は、基礎12の上部に設置された柱部14と、柱部14の先端に接続する梁部16と、梁部16の両端に接続し単柱式橋脚(不図示)が挿通可能な貫通孔18を備えた延長梁20と、延長梁20の上面で上部構造22と接触する支承24を主な基本構成としている。
[Overhang type pier 10]
FIG. 2 is an explanatory view of the overhang type pier of this embodiment. (1) of the figure is a plan view of the pier facing downward from the support, and (2) is a front view of the pier. As shown in the figure, the overhang type pier 10 of the present embodiment includes a column portion 14 installed on the upper portion of the foundation 12, a beam portion 16 connected to the tip of the column portion 14, and a single end connected to both ends of the beam portion 16. An extension beam 20 provided with a through-hole 18 through which a column pier (not shown) can be inserted and a support 24 that contacts the upper structure 22 on the upper surface of the extension beam 20 are mainly configured.

基礎12は、橋脚の下部で荷重を支えて、この荷重を地盤へ伝える最下部の構造物である。柱部14は、基礎12の上部に設置されて上部構造22の荷重を支える構造物である。
前述の基礎12及び柱部14は、材質に鉄筋コンクリートを用いている。材質に鉄筋コンクリートを用いることにより、圧縮力に強く強度を高めることができ、かつ安価であるため施工費を抑えることができる。
The foundation 12 is a lowermost structure that supports a load at the lower part of the pier and transmits the load to the ground. The column part 14 is a structure that is installed on the upper part of the foundation 12 and supports the load of the upper structure 22.
The foundation 12 and the column part 14 are made of reinforced concrete as a material. By using reinforced concrete as the material, the strength can be enhanced strongly against the compressive force, and the construction cost can be reduced because it is inexpensive.

梁部16は、柱部14の上部に設置されて上部構造22の荷重を上部構造22の幅方向に亘って支える構造物である。本実施形態の梁部16は、材質に鋼鉄を用いている。材質に鋼鉄を用いると、形状加工の自由度が高く施工性が良く、鉄筋コンクリートと比べて交換作業にかかる日数を短期化することができる。
本実施形態の梁部16は、既存の一対の単柱式橋脚(不図示)の橋脚間よりも短い長さに設定している。このような梁部16の構成により、既存の一対の単柱式橋脚を撤去することなく、橋梁間の基礎12上に形成することができる。
本実施形態の延長梁20は、梁部16の両端から梁部16の長手方向に沿って延出し、梁部16と同様に上部構造22の荷重を上部構造22の幅方向に亘って支持する構造物である。延長梁20は、梁部16と同様に材質に鋼鉄を用いている。これにより、形状加工の自由度が高く、施工性を良くすることができる。
The beam portion 16 is a structure that is installed on the upper portion of the column portion 14 and supports the load of the upper structure 22 in the width direction of the upper structure 22. The beam portion 16 of this embodiment uses steel as the material. When steel is used as the material, the degree of freedom in shape processing is high and workability is good, and the number of days required for replacement work can be shortened compared to reinforced concrete.
The beam portion 16 of the present embodiment is set to a length shorter than that between the existing pair of single-column piers (not shown). With such a configuration of the beam portion 16, it can be formed on the foundation 12 between the bridges without removing the existing pair of single-column piers.
The extension beam 20 of this embodiment extends from both ends of the beam portion 16 along the longitudinal direction of the beam portion 16 and supports the load of the upper structure 22 over the width direction of the upper structure 22 in the same manner as the beam portion 16. It is a structure. The extension beam 20 is made of steel as the material of the beam portion 16. Thereby, the freedom degree of a shape process is high and workability can be improved.

図3は本実施形態の延長梁の説明図である。同図の(1)は平面図であり、(2)は単柱式橋脚の正面側から見た図である。延長梁20は、梁部16に接続した際に平面視で、単柱式橋脚11と重なる箇所に貫通孔18を設けている。この貫通孔18は、単柱式橋脚11が挿通可能なように、単柱式橋脚11の直径よりも大きい直径となるように設定している。なお、貫通孔18は、梁部16に接続して取付位置に設置した後、図2に示す閉塞部材19を用いて容易に塞ぐことができる。閉塞部材19は、延長梁20と同様に鋼鉄を用いることができる。また、閉塞部材19は、例えば、貫通孔18の直径よりも大きい直径の平板状の蓋と、貫通孔18に嵌合する筒体を組み合わせて形成することができる。また、延長梁20は、梁部16の長手方向に沿って貫通孔18の径方向に二分割された一対の半割構造体となる第1構造体20a及び第2構造体20bを組み合わせて形成することができる。このような構成の延長梁20は、単柱式橋脚11の下部で第1構造体20a及び第2構造体20bを組み合わせて形成した後、チェーンブロックなどの吊上げ手段を用いて梁部16まで、単柱式橋脚11の長手方向に沿って、単柱式橋脚11をガイドとして、安全かつ容易に吊上げることができる。   FIG. 3 is an explanatory diagram of the extension beam of the present embodiment. (1) of the same figure is a top view, (2) is the figure seen from the front side of the single pillar type pier. When the extension beam 20 is connected to the beam portion 16, the through-hole 18 is provided at a location overlapping the single column type pier 11 in plan view. The through hole 18 is set to have a diameter larger than the diameter of the single-column pier 11 so that the single-column pier 11 can be inserted. The through-hole 18 can be easily closed using the closing member 19 shown in FIG. 2 after being connected to the beam portion 16 and installed at the mounting position. The closing member 19 can use steel in the same manner as the extension beam 20. Further, the closing member 19 can be formed by combining, for example, a plate-like lid having a diameter larger than the diameter of the through hole 18 and a cylindrical body fitted into the through hole 18. The extension beam 20 is formed by combining a first structure body 20a and a second structure body 20b which are a pair of halved structures divided into two in the radial direction of the through hole 18 along the longitudinal direction of the beam portion 16. can do. The extension beam 20 having such a structure is formed by combining the first structure 20a and the second structure 20b at the lower part of the single-column pier 11, and then using the lifting means such as a chain block to the beam portion 16, The single column type pier 11 can be safely and easily lifted along the longitudinal direction of the single column type pier 11 using the single column type pier 11 as a guide.

新規支承となる支承24は、延長梁20の貫通孔18を閉塞した上面に設置して、温度変化の影響による上部構造22の伸縮を吸収し、上部構造22を支えて上部構造22の荷重を橋脚に伝達する構造物である。
このような本実施形態の張出し式橋脚10は、形状に自由度の高い鋼鉄を梁部16及び延長梁20に用い、安価で圧縮力に強いRC(鉄筋コンクリート)部材を柱部14及び基礎12に用い、鋼鉄とRC部材を組み合わせた複合橋脚となる。
A new support 24 is installed on the upper surface of the extension beam 20 where the through hole 18 is closed, absorbs expansion and contraction of the upper structure 22 due to the influence of temperature change, and supports the upper structure 22 to load the upper structure 22. It is a structure that transmits to the pier.
The overhanging pier 10 of this embodiment uses steel having a high degree of freedom in the shape for the beam portion 16 and the extension beam 20, and an inexpensive RC (steel reinforced concrete) member that is strong in compressive force for the column portion 14 and the foundation 12. Used as a composite pier that combines steel and RC members.

[橋脚の交換方法]
図1は本発明の橋脚の交換方法の説明図である。
一対の単柱式橋脚11の橋脚間に本実施形態の張出し式橋脚を設置可能な基礎12を施工する(ステップ10)。
[How to replace the pier]
FIG. 1 is an explanatory view of a method for replacing a pier according to the present invention.
A foundation 12 on which the overhang-type pier of this embodiment can be installed is constructed between the piers of the pair of single-column piers 11 (step 10).

基礎12の周囲で梁部16を仮組みする。仮組みした梁部16を下部架台32により所定高さまでジャッキアップする(ステップ11)。ついで、単柱式橋脚11の周囲で延長梁20を仮組みする。延長梁20を構成する第1構造体20a及び第2構造体20bは、梁部16の長手方向に沿って貫通孔18の径方向に二分割された一対の半割構造体である。この第1構造体20a及び第2構造体20bの半割状の貫通孔18同士を、間に単柱式橋脚11の下部を挟んで、単柱式橋脚11の径方向から軸心に向けて組み合わせる。貫通孔18に単柱式橋脚11が挿通した状態で、第1構造体20a及び第2構造体20bを互いに接続させる。そして梁部16の上面に設置した上部架台34からチェーンブロックなどの吊上げ手段を用いて、延長梁20を単柱式橋脚11の長手(軸)方向に沿って吊上げる。延長梁20を所定高さの梁部16まで吊上げた後、一対の延長梁20を梁部16の両端に接続させる。接続後は上部架台34を撤去する。   The beam portion 16 is temporarily assembled around the foundation 12. The temporarily assembled beam portion 16 is jacked up to a predetermined height by the lower frame 32 (step 11). Next, the extension beam 20 is temporarily assembled around the single column pier 11. The first structure 20a and the second structure 20b that constitute the extended beam 20 are a pair of halved structures that are divided in the radial direction of the through hole 18 along the longitudinal direction of the beam portion 16. The halved through-holes 18 of the first structure 20a and the second structure 20b are sandwiched between the lower portions of the single-column piers 11 and are directed from the radial direction of the single-column piers 11 toward the axis. combine. The first structure 20a and the second structure 20b are connected to each other with the single-column pier 11 inserted through the through hole 18. Then, the extension beam 20 is lifted along the longitudinal (axial) direction of the single-column pier 11 from the upper frame 34 installed on the upper surface of the beam portion 16 by using lifting means such as a chain block. After the extension beam 20 is lifted to the beam portion 16 having a predetermined height, the pair of extension beams 20 are connected to both ends of the beam portion 16. After the connection, the upper frame 34 is removed.

下部架台32を用いて梁部16及び延長梁20をジャッキアップして取付位置に設置する(ステップ12)。梁部16及び延長梁20は、材質に鋼鉄を用いており、鉄筋コンクリートと比べて軽量かつ形状加工の自由度が高く施工性が良いため、一対の単柱式橋脚11の橋脚間のスペースであっても、単柱式橋脚11を撤去することなく、チェーンブロック等の吊上げ手段を用いて容易に設置することができる。   The beam 16 and the extended beam 20 are jacked up using the lower frame 32 and installed at the mounting position (step 12). Since the beam portion 16 and the extension beam 20 are made of steel, and are lighter in weight and have a higher degree of freedom of shape processing and better workability than reinforced concrete, the space between the pair of single-column piers 11 is a space. However, it can be easily installed using lifting means such as a chain block without removing the single-column pier 11.

ついで基礎12と梁部16の間のスペースに張出し式橋脚の柱部14を設置する(ステップ13)。本実施形態の基礎12及び柱部14は、材質に鉄筋コンクリートを用いているため、圧縮力が強く、強度を高めて耐震性能を向上させている。   Next, the column portion 14 of the overhanging pier is installed in the space between the foundation 12 and the beam portion 16 (step 13). Since the foundation 12 and the column part 14 of this embodiment use reinforced concrete as a material, they have a strong compressive force and increase the strength to improve the earthquake resistance.

下部架台32を撤去する。梁部16及び延長梁20の上面、かつ単柱式橋脚11の既存支承11aの周囲にジャッキ30を配置して上部構造22をジャッキ受けする(ステップ14)。これまでの工程は、すべて既存の単柱式橋脚11の既存支承11aを介して上部構造22の荷重を支持しているため、従来の仮支点を用いる作業と比べて、交換作業の安全性を高めることができる。
単柱式橋脚11の下部を切断し、単柱式橋脚11の下部から取り除いて、単柱式橋脚11の先端にある既存支承11aを貫通孔18から引き抜いて撤去する(ステップ15)。上部構造22の荷重はジャッキ30で支えているため既存の単柱式橋脚11には一切荷重が作用していない。また、既存支承11aの周囲に配置したジャッキ30で荷重を受けているため、従来の仮支点を用いる作業と比べて、上部構造22に歪等の負荷が掛からない。よって、貫通孔18から容易に既存の単柱式橋脚11を引抜いて撤去することができる。
The lower mount 32 is removed. A jack 30 is disposed on the upper surface of the beam portion 16 and the extension beam 20 and around the existing support 11a of the single-column pier 11 to jack the upper structure 22 (step 14). Since all the processes so far support the load of the upper structure 22 through the existing bearing 11a of the existing single-column pier 11, the safety of the replacement work is improved compared to the work using the conventional temporary fulcrum. Can be increased.
The lower part of the single-column pier 11 is cut and removed from the lower part of the single-column pier 11, and the existing support 11a at the tip of the single-column pier 11 is pulled out from the through hole 18 and removed (step 15). Since the load of the upper structure 22 is supported by the jack 30, no load is applied to the existing single column type pier 11. Further, since the load is received by the jack 30 arranged around the existing bearing 11a, a load such as a strain is not applied to the upper structure 22 as compared with the work using the conventional temporary fulcrum. Therefore, the existing single column type pier 11 can be easily pulled out from the through hole 18 and removed.

閉塞部材19を用いて貫通孔18を閉塞する(ステップ16)。延長梁20は材質に鋼鉄を用いているため、鋼鉄の閉塞部材19で容易に閉塞することができる。
延長梁20の上面に張出し式橋脚の新規の支承24を設置する(ステップ17)。新規の支承24の中心を、閉塞した貫通孔18の中心に位置合わせすることにより、既存支承11aと同じ箇所に、容易に取り付けることができる。
最後にジャッキを撤去すると張出し式橋脚10の支承24で上部構造22を支えることができ、橋脚の交換作業が完了する(ステップ18)。
The through hole 18 is closed using the closing member 19 (step 16). Since the extension beam 20 is made of steel, it can be easily closed by the steel closing member 19.
A new support 24 of an overhanging pier is installed on the upper surface of the extension beam 20 (step 17). By aligning the center of the new support 24 with the center of the closed through-hole 18, it can be easily attached to the same location as the existing support 11a.
Finally, when the jack is removed, the upper structure 22 can be supported by the support 24 of the overhang type pier 10, and the pier replacement operation is completed (step 18).

このような本発明の橋脚の交換方法によれば、従来のような一対の既存支承の支点間よりも幅の狭い支点間で構造上支持しなければならない一対の仮支点による仮受期間がなく、上部構造に歪み等の負荷が掛かるおそれがない。また、張出し式橋脚の延長梁を形成する工程まで既存橋脚で上部構造の荷重を支えながら交換作業を行うことができるので、上部構造に負荷をかけることなく作業の安全性を確保できる。   According to the pier replacement method of the present invention as described above, there is no provisional reception period by a pair of temporary fulcrums that must be structurally supported between fulcrums narrower than the conventional fulcrum of a pair of existing bearings. There is no risk that the upper structure is subjected to a load such as distortion. In addition, since the replacement work can be performed while supporting the load of the superstructure with the existing pier until the process of forming the extension beam of the overhang type pier, the safety of the work can be ensured without applying a load to the superstructure.

また、従来のような仮支点、横桁の補強材および仮設材を省略することにより施工コストを抑えることができ、かつ既存橋脚から新規橋脚へ速やかに移行でき橋脚の交換作業にかかる日数を短期化することができる。   In addition, construction costs can be reduced by omitting the temporary fulcrum, cross girder reinforcement and temporary materials as before, and the existing pier can be quickly transferred to the new pier, reducing the number of days required for pier replacement work. Can be

本発明の橋脚の交換方法は、一対の単柱式橋脚の間に形成する張出し式橋脚の構成を採用するあらゆる道路橋又は鉄道橋の橋梁を構成する橋脚に適用可能である。   The pier replacement method of the present invention can be applied to any pier that constitutes a bridge of any road bridge or railroad bridge that employs the construction of an overhanging pier formed between a pair of single-column piers.

10………張出し式橋脚、11………単柱式橋脚、11a………既存支承、12………基礎、14………柱部、16………梁部、18………貫通孔、19………閉塞部材、20………延長梁、20a………第1構造体、20b………第2構造体、22………上部構造、24………支承、30………ジャッキ、32………下部架台、34………上部架台、100………張出し式橋脚、110………単柱式橋脚、110a………既存支承、120………基礎、140………柱部、160………梁部、200………延長梁、220………上部構造、222………仮支点用横梁、240………支承、300………ジャッキ、400………仮支点。 10 ......... Overhang type pier, 11 ......... Single column type pier, 11a ......... Existing bearing, 12 ......... Base, 14 ...... Column, 16 ......... Beam, 18 ......... Through hole , 19 ...... Closing member, 20 ...... Extension beam, 20 a ...... First structure, 20 b ...... Second structure, 22 ...... Superstructure, 24 ...... Bearing, 30 ...... Jack, 32 ......... Lower frame, 34 ......... Upper frame, 100 ...... Overhang type pier, 110 ......... Single-column type pier, 110a ...... Existing bearing, 120 ......... Base, 140 ......... Column, 160 ......... Beam, 200 ... Extension beam, 220 ... Superstructure, 222 ... Temporary fulcrum cross beam, 240 ... Support, 300 ... Jack, 400 ... fulcrum.

Claims (3)

上部構造を支持する一対の単柱式橋脚の間に、張出し式橋脚の基礎と、前記基礎の上方に前記一対の単柱式橋脚の橋脚間よりも短い梁部を形成する工程と、
前記単柱式橋脚が挿通する貫通孔を備えた一対の延長梁を前記単柱式橋脚の長手方向に沿って吊上げて前記梁部の両端にそれぞれ接続する工程と、
前記基礎と前記梁部の間のスペースに張出し式橋脚の柱部を設置する工程と、
前記梁部及び前記延長梁の上面、かつ前記単柱式橋脚の既存支承の周囲にジャッキを配置して前記上部構造をジャッキ受けする工程と、
前記単柱式橋脚を切断し、前記単柱式橋脚の下部から取り除いて先端を前記貫通孔から引き抜いて撤去する工程と、
前記貫通孔を閉塞して前記延長梁の上面に前記張出し式橋脚の新規支承を形成する工程と、
を有することを特徴とする橋脚の交換方法。
Forming a foundation of an overhanging pier between a pair of single-column piers that support the superstructure, and forming a beam portion shorter than the pier of the pair of single-column piers above the foundation;
A step of lifting a pair of extension beams provided with through-holes through which the single-column pier is inserted, along the longitudinal direction of the single-column pier, and connecting to both ends of the beam portion;
Installing a pillar portion of an overhanging pier in a space between the foundation and the beam portion;
Jacking the upper structure by placing a jack around the upper surface of the beam portion and the extension beam and around the existing bearing of the single-column pier;
Cutting the single-column pier, removing from the lower portion of the single-column pier, pulling the tip out from the through hole and removing it;
Closing the through hole and forming a new support for the overhanging pier on the upper surface of the extension beam;
A method of exchanging piers characterized by comprising:
前記延長梁は、前記梁部の長手方向に沿って前記貫通孔の径方向に二分割された一対の半割構造体を組み合わせて形成することを特徴とする請求項1に記載の橋脚の交換方法。   2. The pier replacement according to claim 1, wherein the extension beam is formed by combining a pair of halved structures divided into two in the radial direction of the through hole along the longitudinal direction of the beam portion. Method. 前記柱部は材質に鉄筋コンクリートを用い、前記梁部及び前記延長梁は材質に鋼鉄を用いたことを特徴とする請求項1又は2に記載の橋脚の交換方法。   The pier replacement method according to claim 1 or 2, wherein the pillar portion is made of reinforced concrete, and the beam portion and the extension beam are made of steel.
JP2015041531A 2015-03-03 2015-03-03 How to replace the pier Active JP6028984B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015041531A JP6028984B2 (en) 2015-03-03 2015-03-03 How to replace the pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015041531A JP6028984B2 (en) 2015-03-03 2015-03-03 How to replace the pier

Publications (2)

Publication Number Publication Date
JP2016160686A JP2016160686A (en) 2016-09-05
JP6028984B2 true JP6028984B2 (en) 2016-11-24

Family

ID=56844525

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015041531A Active JP6028984B2 (en) 2015-03-03 2015-03-03 How to replace the pier

Country Status (1)

Country Link
JP (1) JP6028984B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111424530A (en) * 2020-03-25 2020-07-17 苏交科集团股份有限公司 Oblique-pulling type single-column pier anti-overturning device
CN113403968B (en) * 2021-07-15 2022-02-15 广东省九域工程技术咨询有限公司 Bridge pier underpinning method and underpinning structure
CN114753272A (en) * 2022-05-05 2022-07-15 中交路桥华东工程有限公司 Construction method of prestressed bearing platform for bridge pier repair

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2918475B2 (en) * 1995-03-02 1999-07-12 株式会社巴コーポレーション Pier construction method, pier dismantling method and lift-up / rotation device
JP4704279B2 (en) * 2006-06-01 2011-06-15 三菱重工鉄構エンジニアリング株式会社 Bridge construction method
JP4369506B2 (en) * 2007-05-08 2009-11-25 首都高速道路株式会社 How to rebuild the pier

Also Published As

Publication number Publication date
JP2016160686A (en) 2016-09-05

Similar Documents

Publication Publication Date Title
US8522381B1 (en) System and method for bridge pier replacement
EP3259405B1 (en) Method of building a foundation comprising a steel monopile and a concrete part and associated foundation for construction work
CN106149572B (en) A kind of beam bridge ruggedized construction and reinforcement means
KR101300073B1 (en) Lifting device for girder
JP6028984B2 (en) How to replace the pier
KR101527782B1 (en) Management and reverse displacement of composite bridge composite inclined support installation method
CN103866698A (en) Symmetrical suspension splicing bridge support seat end pseudo-suspension splicing construction method
CN110541364A (en) Bridge bent cap segmented prefabrication, assembly and fixation method
CN103132513A (en) Repairing method of damaged foundation pile of high-pile wharf
JP5124303B2 (en) Bridge girder rearrangement method and apparatus
KR102403925B1 (en) A temporary bridge and construction method for the temporary bridge
US10655287B2 (en) Reinforcement apparatus for reinforcing a structure comprising a pier and a cross-beam
CN207812181U (en) Track, track girder and its crane beam
JP7009724B2 (en) Column-beam frame repair method and repair column-beam frame
CN110792042A (en) Anti-overturning reinforcing method for rectangular single-column pier bridge
KR102222019B1 (en) Camber Connection Supporter of bent pressed girder and Bridge construction method therewith
JP6416539B2 (en) Bridge girder replacement method
KR101120163B1 (en) Construction method for temporary bridge
CN101845872B (en) Control method for strengthening beam steel protective layer
CN211735114U (en) A antidumping reinforced structure for rectangle single-column mound bridge
JP5982143B2 (en) Reinforcing structure and reinforcing method for existing structure
JP6618116B2 (en) Construction method of pier
JP2003293323A (en) Reinforcement structure of continuous girder bridge
KR101325230B1 (en) Manufacturing method for turn-over composite girder
KR102578490B1 (en) Bridge dismantling method

Legal Events

Date Code Title Description
A975 Report on accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A971005

Effective date: 20160719

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20160803

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20160823

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20160913

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20161005

R150 Certificate of patent or registration of utility model

Ref document number: 6028984

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250