JP5608054B2 - Precast reinforced concrete beam and floor assembly having the same - Google Patents

Precast reinforced concrete beam and floor assembly having the same Download PDF

Info

Publication number
JP5608054B2
JP5608054B2 JP2010258217A JP2010258217A JP5608054B2 JP 5608054 B2 JP5608054 B2 JP 5608054B2 JP 2010258217 A JP2010258217 A JP 2010258217A JP 2010258217 A JP2010258217 A JP 2010258217A JP 5608054 B2 JP5608054 B2 JP 5608054B2
Authority
JP
Japan
Prior art keywords
bundle
reinforced concrete
chord
precast
pca beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2010258217A
Other languages
Japanese (ja)
Other versions
JP2012107452A (en
Inventor
寛 江頭
英之 小坂
正夫 碓井
啓二 松本
恭司 野口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Mitsui Construction Co Ltd
Original Assignee
Sumitomo Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Mitsui Construction Co Ltd filed Critical Sumitomo Mitsui Construction Co Ltd
Priority to JP2010258217A priority Critical patent/JP5608054B2/en
Publication of JP2012107452A publication Critical patent/JP2012107452A/en
Application granted granted Critical
Publication of JP5608054B2 publication Critical patent/JP5608054B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Rod-Shaped Construction Members (AREA)

Description

本発明は、空調用ダクトルート等として用いられる矩形開口部を有するプレキャスト鉄筋コンクリート梁およびこれを有する床組に関する。
The present invention relates to a precast reinforced concrete beam having a rectangular opening used as an air conditioning duct route or the like and a floor assembly having the same .

ビルは、鉄筋コンクリートや鉄骨を素材とする柱と梁とによって柱梁架構を形成し、大梁や小梁からなる床組上に床スラブを打設して建造するが、オフィスビルにおいては、天井面に空調、給排水、電力供給等のためのダクトや配管類が多数設置されることから、天井高さが低くなることを避けるために梁の縦壁(ウエブ)にこれらダクトや配管類が通過する開口部(以下、ダクト開口部と記す)を設けることが一般的である。そのため、従来のオフィスビルでは、梁としてウエブにダクト開口部が形成されたH形鋼を採用し、これを鉄骨柱と組み合わせた鉄骨構造(全S構造)やRC(鉄筋コンクリート)柱と組み合わせたRC梁S構造とし、ダクト開口部による梁の強度低下を抑制することが多かった。   Buildings are constructed by forming a column beam structure with columns and beams made of reinforced concrete or steel, and placing floor slabs on a floor set consisting of large beams and small beams. Since there are many ducts and piping for air conditioning, water supply / drainage, power supply, etc., these ducts and piping pass through the vertical wall (web) of the beam in order to avoid a low ceiling height. It is common to provide an opening (hereinafter referred to as a duct opening). Therefore, conventional office buildings use H-shaped steel with duct openings formed on the web as beams, and RC structures combined with steel structures (all S structures) combined with steel columns and RC (reinforced concrete) columns. In many cases, the beam S structure is used to suppress the strength reduction of the beam due to the duct opening.

近年、鉄骨梁に較べて防振性能に優れ、建設コストが鋼材価格の変動に影響されにくいこと、耐火被覆が必要な鉄骨梁では意匠的見地から天井を設ける必要があるために空間の利用効率が悪いこと等の理由から、鉄筋コンクリート梁であるプレキャスト・プレストレストコンクリート(PCaPC)梁をオフィスビルに採用することが検討されている。   In recent years, it has superior vibration proofing performance compared to steel beams, construction costs are less susceptible to fluctuations in steel prices, and steel beams that require fireproof coating need to have a ceiling from a design standpoint. For reasons such as being bad, it has been studied to adopt precast prestressed concrete (PCaPC) beams, which are reinforced concrete beams, for office buildings.

また、鉄筋コンクリート梁にダクトや配管類が通過する開口部を設ける技術として、梁の上端側および下端側に上端主筋と下端主筋とをそれぞれ複数段に配筋して上端主筋群および下端主筋群を形成したうえで、上端主筋群を上端拘束筋によって拘束し、下端主筋群を下端拘束筋によって拘束するものが提案されている(特許文献1参照)。この鉄筋コンクリート梁では、上端主筋群を含む上端側の仮想梁と下端主筋群を含む下端側の仮想梁とによってせん断力に抵抗できるため、上端主筋と下端主筋とにわたって巻き付ける拘束筋を省略あるいは削減することで、両仮想梁の間に容易に開口部を設けられるようにしている。   In addition, as a technique to provide openings through which ducts and pipes pass in reinforced concrete beams, upper and lower main bars are arranged in multiple stages on the upper and lower ends of the beam, and the upper and lower main bars are arranged. There has been proposed a structure in which the upper principal muscle group is constrained by the upper-end restraint muscle and the lower-end principal muscle group is restrained by the lower-end restraint muscle (see Patent Document 1). In this reinforced concrete beam, the upper end side virtual beam including the upper end main reinforcement group and the lower end side virtual beam including the lower end main reinforcement group can resist the shearing force. Thus, an opening can be easily provided between both virtual beams.

特開2010−13797号公報JP 2010-13797 A

しかしながら、特許文献1の鉄筋コンクリート梁では、上端側仮想梁と下端側仮想梁とでせん断力に抵抗できるが、上端側仮想梁と下端側仮想梁とを無筋コンクリートからなる中間部で連結する構造であり、曲げモーメントに起因する水平方向のせん断応力度が最大になる中間部の取り扱いが曖昧である。また、垂直方向のせん断力に対する応力負担部材である上端側仮想梁および下端側仮想梁の他に、中間部を有するものであるため、鉄骨梁に比べて重量化しがちな鉄筋コンクリート梁を軽量化するのに最適な構造とは言い難かった。また、特許文献1の鉄筋コンクリート梁では、同一形状の円形開口部を複数有しているため、矩形断面が多い空調用ダクトの収まりが悪く、ダクトの形状や大きさによっては開口部に通すことができないという問題もある。   However, in the reinforced concrete beam of Patent Literature 1, the upper end side virtual beam and the lower end side virtual beam can resist the shearing force, but the upper end side virtual beam and the lower end side virtual beam are connected by an intermediate portion made of unreinforced concrete. And the handling of the intermediate portion where the shear stress in the horizontal direction due to the bending moment is maximum is ambiguous. In addition to the upper virtual beam and the lower virtual beam, which are stress bearing members against the shear force in the vertical direction, it has an intermediate part, so the weight of reinforced concrete beams that tend to be heavier than steel beams is reduced. It was hard to say that it was the optimal structure. In addition, since the reinforced concrete beam of Patent Document 1 has a plurality of circular openings of the same shape, the air conditioning duct having a large number of rectangular cross-sections is poorly fit, and depending on the shape and size of the duct, it can be passed through the openings. There is also a problem that it cannot be done.

本発明は、このような背景に鑑みなされたもので、ダクト等の通過に供される複数の矩形開口部を設けながら、強度の確保と重量の軽減とを実現し得る鉄筋コンクリート梁を提供することをその主な目的とする。   The present invention has been made in view of such a background, and provides a reinforced concrete beam capable of ensuring strength and reducing weight while providing a plurality of rectangular openings for passage through a duct or the like. Is its main purpose.

上記課題を解決するために、本発明は、上弦部(11)と下弦部(12)とが複数の束部(13〜16)で連結され、束部間に梁幅方向に貫通する矩形の開口部(21〜24)が複数形成されたプレキャスト鉄筋コンクリート梁(PCa梁)であって、軸方向の端部側における束部長さと開口部長さとの比が軸方向の中央側における束部長さと開口部長さとの比よりも大きい(A1/B1>A4/B4)ことを特徴とする。   In order to solve the above problems, the present invention is a rectangular shape in which an upper chord part (11) and a lower chord part (12) are connected by a plurality of bundle parts (13 to 16) and penetrate between the bundle parts in the beam width direction. A precast reinforced concrete beam (PCa beam) in which a plurality of openings (21 to 24) are formed, and the ratio of the bundle length and the opening length on the end side in the axial direction is the bundle length and the opening length on the central side in the axial direction. (A1 / B1> A4 / B4).

この構成によれば、鉄筋コンクリート梁を、上弦部、下弦部および束部がそれぞれ構造要素として応力負担するフィーレンディール構造とし、各部の負担応力を明確な構造計算に基づいて求めることができる。そのため、ダクト等の大きさや形状に合わせて開口部長さを柔軟に対応させることができる。また、束部の水平方向せん断力の負担は端部に近くなるほど大きくなるが、軸方向の端部側における束部長さと開口部長さとの比を軸方向の中央側における束部長さと開口部長さとの比よりも大きくすることで、力学的に合理的な構造となり、強度の確保と軽量化との両立を実現できる。また、束部が垂直方向せん断力に対しても応力負担し得ることによっても、せん断力が最も大きくなる端部近傍に束部が配置されることで、鉄筋コンクリート梁全体としての軽量化が図られる。さらに、開口部が矩形であるため、構造要素として寄与しない余肉が無くなり、重量の増加を抑制できる。   According to this configuration, the reinforced concrete beam has a feelendel structure in which the upper chord part, the lower chord part, and the bundle part each bear a stress as a structural element, and the burden stress of each part can be obtained based on a clear structural calculation. Therefore, it is possible to flexibly correspond to the opening length according to the size and shape of the duct or the like. In addition, the load of the horizontal shearing force of the bundle portion increases as it approaches the end portion, but the ratio of the bundle portion length and the opening length on the end portion side in the axial direction is the ratio of the bundle portion length and the opening portion length on the central side in the axial direction By making it larger than the ratio, a mechanically rational structure can be achieved, and both the securing of strength and the weight reduction can be realized. In addition, because the bundle portion can bear a stress even with respect to the vertical direction shear force, the bundle portion is arranged in the vicinity of the end portion where the shear force is the largest, thereby reducing the weight of the reinforced concrete beam as a whole. . Furthermore, since the opening is rectangular, there is no surplus that does not contribute as a structural element, and an increase in weight can be suppressed.

また、本発明の一側面によれば、端部側の下部が斜めに切り欠かれた構成とすることができる。この構成によれば、鉄筋コンクリート梁の端部、すなわち大梁や柱に沿ってダクト等を配置することが可能となり、設備配置の設計自由度を高めることができる。   In addition, according to one aspect of the present invention, the lower part on the end side can be cut off obliquely. According to this structure, it becomes possible to arrange | position a duct etc. along the edge part of a reinforced concrete beam, ie, a big beam, and a pillar, and can raise the design freedom of equipment arrangement | positioning.

また、本発明の一側面によれば、上弦部と下弦部との少なくとも一方において、端部側における梁幅が中央側における梁幅よりも大きくされた構成とすることができる。この構成によれば、せん断力が大きな端部側の強度を向上でき、比較的必要強度の低い中央側の梁幅を小さくできるため、鉄筋コンクリート梁をより一層軽量化することができる。また、端部に切欠を設ける場合には端部の補強に好適である。   Further, according to one aspect of the present invention, the beam width on the end side can be made larger than the beam width on the center side in at least one of the upper chord part and the lower chord part. According to this configuration, the strength on the end portion side where the shearing force is large can be improved, and the beam width on the center side having a relatively low required strength can be reduced, so that the reinforced concrete beam can be further reduced in weight. Moreover, when providing a notch in an edge part, it is suitable for reinforcement of an edge part.

また、本発明の一側面によれば、下弦部には、PC鋼線(61,62)によってプレストレスが付与された構成とすることができる。この構成によれば、下弦部の引張強度が向上するため、断面の縮小化および鉄筋コンクリート梁の大スパン化を図ることができる。また、PC鋼線は高強度鉄筋に比べて安価であるため、製造コストを低減できる。さらに、高強度鉄筋を用いる場合には製造長さに限界があるが、PC鋼線を用いれば梁の製作長さに制限が加わることもない。   Moreover, according to one side of this invention, it can be set as the structure by which the prestress was provided to the lower chord part by PC steel wire (61, 62). According to this configuration, since the tensile strength of the lower chord portion is improved, it is possible to reduce the cross section and increase the span of the reinforced concrete beam. Moreover, since the PC steel wire is less expensive than the high-strength reinforcing bar, the manufacturing cost can be reduced. Furthermore, when a high-strength reinforcing bar is used, the manufacturing length is limited, but when a PC steel wire is used, there is no limitation on the beam manufacturing length.

また、本発明の一側面によれば、下弦部には、主筋が配置されず、PC鋼線を取り囲む横補強筋(42)が配置された構成とすることができる。この構成によれば、PC鋼線を用いることで下弦部を小断面化することができる一方、下弦部に通常量の鉄筋とPC鋼線とを納めると、間隙が小さくなってコンクリートの充填性が悪化するが、主筋を省略することでコンクリート充填性を改善し、PC鋼線を横補強筋で直接またはコンクリートを介して拘束することでPC鋼線の定着を確実なものとし、下弦部の小断面化および品質確保の両立を実現することができる。   Moreover, according to one side of this invention, it can be set as the structure by which the main reinforcement is not arrange | positioned in the lower chord part, but the horizontal reinforcement (42) surrounding PC steel wire is arrange | positioned. According to this configuration, the lower chord can be reduced in cross section by using the PC steel wire. On the other hand, when a normal amount of rebar and PC steel wire are placed in the lower chord, the gap becomes smaller and the concrete can be filled. However, by omitting the main bars, the concrete filling property is improved, and the PC steel wires are restrained directly or through the concrete with the horizontal reinforcing bars to ensure the fixing of the PC steel wires. It is possible to realize both a small cross section and quality assurance.

また、本発明の一側面によれば、上弦部、下弦部および束部は、個別にプレキャスト形成された別部材からなり、PC鋼棒または鉄筋を介して接合/一体化された構成とすることができる。この構成によれば、型枠の組立や鉄筋の組立、コンクリートの打設が容易となること等により、生産性を向上し、製造コストを低減することができる。   Moreover, according to one aspect of the present invention, the upper chord part, the lower chord part, and the bundle part are made of separate members that are individually precast, and are joined / integrated via PC steel bars or reinforcing bars. Can do. According to this configuration, it is possible to improve the productivity and reduce the manufacturing cost by facilitating the assembly of the mold, the assembly of the reinforcing bars, and the placement of the concrete.

このように本発明によれば、ダクト等の通過に供される複数の開口部を設けながら、強度の確保と重量の軽減とを図り得る鉄筋コンクリート梁を提供することができる。   As described above, according to the present invention, it is possible to provide a reinforced concrete beam capable of ensuring strength and reducing weight while providing a plurality of openings for passage through a duct or the like.

第1実施形態に係るPCa梁を適用した床組の透視斜視図The perspective view of the floor set to which the PCa beam according to the first embodiment is applied 図1に示すPCa梁の正面図Front view of the PCa beam shown in FIG. 図1に示すPCa梁の平面図Plan view of the PCa beam shown in FIG. 図1に示すPCa梁の要部縦断面図Longitudinal section of the main part of the PCa beam shown in FIG. 図4中のV−V断面図VV sectional view in FIG. 図4中のVI−VI断面図VI-VI cross section in FIG. 図4中のVII−VII断面図VII-VII sectional view in FIG. 変形例に係るPCa梁の要部側面図Side view of main part of PCa beam according to modification 図1に示すPCa梁の製造手順の説明図Explanatory drawing of the manufacturing procedure of the PCa beam shown in FIG. 図1に示すPCa梁の変形例に係る製造手順の説明図Explanatory drawing of the manufacturing procedure which concerns on the modification of the PCa beam shown in FIG. 第2実施形態に係るPCa梁の製造手順の説明図Explanatory drawing of the manufacturing procedure of PCa beam concerning a 2nd embodiment 第3実施形態に係るPCa梁の製造手順の説明図Explanatory drawing of the manufacturing procedure of PCa beam concerning a 3rd embodiment 図12に示すPCa梁の製造手順の変形例の説明図Explanatory drawing of the modification of the manufacturing procedure of the PCa beam shown in FIG. 第4実施形態に係るPCa梁の製造手順の説明図Explanatory drawing of the manufacturing procedure of PCa beam concerning a 4th embodiment 図14に示すPCa梁の各部断面図Cross-sectional view of each part of PCa beam shown in FIG. 第5実施形態に係るPCa梁の製造手順の説明図Explanatory drawing of the manufacturing procedure of PCa beam concerning a 5th embodiment 図16に示すPCa梁の接合構造の要部断面図Cross-sectional view of the principal part of the PCa beam joint structure shown in FIG. 図16に示すPCa梁の変形例に係る接合構造の要部断面図Sectional drawing of the principal part of the joining structure which concerns on the modification of the PCa beam shown in FIG. 第6実施形態に係るPCa梁の製造手順の説明図Explanatory drawing of the manufacturing procedure of PCa beam concerning a 6th embodiment

以下、図面を参照して、本発明の鉄筋コンクリート梁(以下、単にPCa梁1と記す。)をオフィスビル用建物の床組に適用したいくつかの実施形態を詳細に説明する。なお、PCa梁1については、説明の便宜上、図1中の斜め左下方を左とし、斜め右上方を右とするものとする。   Hereinafter, several embodiments in which a reinforced concrete beam (hereinafter simply referred to as a PCa beam 1) of the present invention is applied to a floor set of a building for an office building will be described in detail with reference to the drawings. For the convenience of description, the PCa beam 1 is assumed to have the lower left diagonal in FIG. 1 as the left and the upper right diagonal as the right.

≪第1実施形態≫
図1に示すように、PCa鉄筋コンクリート梁(以下、単にPCa梁1と記す。)はPCコンクリート製の小梁であり、両端が一対の大梁2に連結されるとともに、その上部に床スラブ3が構築されている。図2にも示すように、PCa梁1は、左右方向(軸方向)に延設された上弦部11および下弦部12、これら上弦部11と下弦部12とを連結すべく左右対称に各一対配置された第1〜第4束部13〜16を有している。
<< First Embodiment >>
As shown in FIG. 1, a PCa reinforced concrete beam (hereinafter simply referred to as a PCa beam 1) is a small beam made of PC concrete, and both ends are connected to a pair of large beams 2, and a floor slab 3 is formed on the upper part thereof. Has been built. As shown also in FIG. 2, the PCa beam 1 includes a pair of upper and lower chord portions 11 and 12 that extend in the left-right direction (axial direction), and a pair of left and right symmetrical portions to connect the upper chord portion 11 and the lower chord portion 12. It has the 1st-4th bundle parts 13-16 arranged.

第1束部13と第2束部14との間には矩形の第1開口部21が形成され、第2束部14と第3束部15との間には矩形の第2開口部22が形成され、第3束部15と第4束部16との間には矩形の第3開口部23が形成され、2つの第4束部16の間には矩形の第4開口部24が形成されている。なお、これら第1〜第4開口部21〜24は、それぞれPCa梁1を梁幅方向に貫通する態様で形成される。   A rectangular first opening 21 is formed between the first bundle 13 and the second bundle 14, and a rectangular second opening 22 is formed between the second bundle 14 and the third bundle 15. A rectangular third opening 23 is formed between the third bundle portion 15 and the fourth bundle portion 16, and a rectangular fourth opening portion 24 is formed between the two fourth bundle portions 16. Is formed. In addition, these 1st-4th opening parts 21-24 are each formed in the aspect which penetrates the PCa beam 1 in a beam width direction.

これら開口部21〜24は、オフィスビルの空調ダクトなどの配管ルートとなっており、RC梁としては大きく、且つ矩形の開口部21〜24が多数設けられたことにより、図2中に破線で示すように配管ルートを自由に設定することができ、比較的大断面のダクトなどを用いることが可能となっている。また、改装時に配管ルートを変更することも容易になっている。   These openings 21 to 24 are piping routes such as air conditioning ducts of office buildings, and are large as RC beams, and a large number of rectangular openings 21 to 24 are provided. As shown, the piping route can be freely set, and a duct having a relatively large cross section can be used. It is also easy to change the piping route during renovation.

大梁2の側面には架台部2aが形成されており、PCa梁1はこの架台部2a上に上弦部11が載置された状態で大梁2に結合される。PCa梁1は、左右の端部の下部が斜めに切り欠かれて略逆台形を呈しており、大梁2との間に略三角形の空隙25を形成している。そのため、下弦部12が上弦部11よりも短くなっており、梁端部に配置された第1束部13も一辺が垂直な逆台形となっている。   A frame portion 2a is formed on the side surface of the large beam 2, and the PCa beam 1 is coupled to the large beam 2 with the upper chord portion 11 placed on the frame portion 2a. The PCa beam 1 has a substantially inverted trapezoidal shape in which the lower portions of the left and right end portions are obliquely cut out, and a substantially triangular gap 25 is formed between the PCa beam 1 and the large beam 2. Therefore, the lower chord part 12 is shorter than the upper chord part 11, and the 1st bundle part 13 arrange | positioned at the beam end part is also an inverted trapezoid whose one side is perpendicular | vertical.

このように、PCa梁1の端部に空隙25が形成されたことにより、従来困難とされていた大梁2に沿って空調ダクトなどを設けることが可能になっており、設備配置の設計自由度が高まっている。なお、本実施形態ではPCa梁1を大梁2に架設しているが、PCa梁1を柱に架設する場合には架設する柱に沿って空調ダクトなどを設けることが可能になる。   As described above, since the gap 25 is formed at the end of the PCa beam 1, it is possible to provide an air-conditioning duct or the like along the large beam 2 that has been considered difficult in the past. Is growing. In this embodiment, the PCa beam 1 is installed on the large beam 2. However, when the PCa beam 1 is installed on a column, an air conditioning duct or the like can be provided along the installed column.

図3に示すように、上弦部11は、中央部11aにおいて幅が最も小さく、中央部11aに隣接する側部11c、側部11cに隣接する側端部11eへ向かうにつれて幅が大きくなっている。また、上弦部11の中央部11aと側部11cとの間、および側部11cと側端部11eとの間には、その幅を徐々に変化させた連結部11b,11dがそれぞれ設けられている。   As shown in FIG. 3, the upper chord portion 11 has the smallest width at the central portion 11a, and the width increases toward the side portion 11c adjacent to the central portion 11a and the side end portion 11e adjacent to the side portion 11c. . In addition, connecting portions 11b and 11d whose widths are gradually changed are provided between the central portion 11a and the side portion 11c of the upper chord portion 11 and between the side portion 11c and the side end portion 11e, respectively. Yes.

また、下弦部12も上弦部11と同様にその幅を変化させており、上弦部11よりも短いために、端部の幅は上弦部11の側部11cと同一となっている。同様に、中央寄りに配置された第2〜第4束部14〜16も上弦部11と同様にその幅を変化させる一方、第1束部13は上弦部11の側部11cと同一幅となっており、上弦部11の側端部11eおよび連結部11dにおけるPCa梁1の断面がT字になっている。   Further, the lower chord portion 12 also changes its width in the same manner as the upper chord portion 11 and is shorter than the upper chord portion 11, so that the width of the end portion is the same as the side portion 11 c of the upper chord portion 11. Similarly, the second to fourth bundle portions 14 to 16 arranged closer to the center also change the width in the same manner as the upper chord portion 11, while the first bundle portion 13 has the same width as the side portion 11 c of the upper chord portion 11. The cross section of the PCa beam 1 at the side end portion 11e of the upper chord portion 11 and the connecting portion 11d is T-shaped.

PCa梁1に作用するせん断力は、通常、端部側ほど大きくなる。そこで、このように上弦部11の幅を側端部11eにおいて最も大きくしたことで、大梁2との連結部においてもPCa梁1がせん断力に抵抗できるようになっている。また、PCa梁1の端部が切りかかれていても、幅広の上弦部11が切り欠きによるせん断耐力の低下を好適に補っている。一方、上弦部11および下弦部12を含むPCa梁1の全体の幅を端部側ほど大きくしたことで、せん断力に耐え得る強度を確保しつつ、PCa梁1の軽量化が図られている。   The shearing force acting on the PCa beam 1 usually increases toward the end side. Therefore, the width of the upper chord portion 11 is maximized at the side end portion 11e in this way, so that the PCa beam 1 can resist the shearing force even at the connecting portion with the large beam 2. Moreover, even if the end portion of the PCa beam 1 is cut, the wide upper chord portion 11 suitably compensates for a decrease in shear strength due to the notch. On the other hand, by increasing the overall width of the PCa beam 1 including the upper chord part 11 and the lower chord part 12 toward the end side, the PCa beam 1 is reduced in weight while ensuring the strength to withstand shearing force. .

図4〜図7に示すように、上弦部11には、上下方向に3段に主筋31が配置されている。なお、本実施形態におけるPCa梁1は、床スラブ3の打設後に、PCa梁1と一体となった床スラブコンクリートの一部が小梁の一部を構成することになるが、大梁2に架設する前のPCa梁1としては、下側2段の主筋31のみが主筋として機能を果たしている。したがって、大梁2への架設時点で上弦部11の上方に露出する上段の主筋31は本来、PCa梁1の主筋には含まれないが、鉄筋に関する説明においてはこれら上段の主筋31を含めてPCa梁1の主筋31として説明する。なお、図4〜図7においては図が煩雑となるのを避けるためにハッチングを省略している。   As shown in FIG. 4 to FIG. 7, the main chord portion 11 has three main bars 31 arranged vertically in the vertical direction. In the PCa beam 1 in this embodiment, after the floor slab 3 is placed, a part of the floor slab concrete integrated with the PCa beam 1 constitutes a part of the small beam. For the PCa beam 1 before erection, only the lower two-stage main bars 31 function as main bars. Therefore, the upper main bar 31 exposed above the upper chord portion 11 at the time of erection to the large beam 2 is not originally included in the main bar of the PCa beam 1, but in the description related to the reinforcing bar, the upper main bar 31 including the upper main bar 31 is included. The main reinforcement 31 of the beam 1 will be described. In FIGS. 4 to 7, hatching is omitted in order to avoid complication of the drawings.

図7に示すように、上弦部11の中央部11aにおいては、各段につき複数の主筋31が配置され、これら主筋31を取り囲む横補強筋41および中段の主筋31を跨ぐ幅止め筋44が軸方向に所定の間隔に設けられている。図6に示すように、上弦部11の側部11cにおいては、幅の増大に合わせて下段および中段において中央部11a(図7)よりも多い本数の主筋31が、上段において中央部11aと同じ本数の主筋31がそれぞれ配置され、これら主筋31を取り囲む横補強筋41および中段の主筋31を跨ぐ幅止め筋44が軸方向に所定の間隔に設けられている。図5に示すように、上弦部11の側端部11eにおいては、更なる幅の増大に合わせて下段および中段において側部11c(図6)よりも更に多い本数の主筋31が、上段において側部11cと同じ本数の主筋31が側部11cと同じ位置にそれぞれ配置され、下段および中段の全ての主筋31を取り囲む第1横補強筋41a、下段および中段のうち内側の複数本の主筋31を取り囲む第2横補強筋41b、および中段のうち最も内側に配置された一対の主筋31を跨ぐ幅止め筋44が、軸方向に所定の間隔に設けられている。   As shown in FIG. 7, in the central portion 11 a of the upper chord portion 11, a plurality of main reinforcing bars 31 are arranged for each step, and a lateral reinforcing bar 41 that surrounds the main reinforcing bars 31 and a width stop bar 44 that straddles the middle main bar 31 is an axis It is provided at predetermined intervals in the direction. As shown in FIG. 6, in the side part 11c of the upper chord part 11, the number of main bars 31 in the lower stage and the middle stage is larger than the central part 11a (FIG. 7) in accordance with the increase in width, and is the same as the central part 11a in the upper stage. A number of main bars 31 are arranged, respectively, and horizontal reinforcing bars 41 surrounding the main bars 31 and width stopper bars 44 straddling the middle main bars 31 are provided at predetermined intervals in the axial direction. As shown in FIG. 5, at the side end portion 11e of the upper chord portion 11, the number of main bars 31 in the lower and middle tiers is larger than the side portion 11c (FIG. 6) as the width further increases. The same number of main bars 31 as the part 11c are arranged at the same position as the side part 11c, and the first horizontal reinforcing bars 41a surrounding all the lower and middle main bars 31 and the inner main bars 31 among the lower and middle stages. The surrounding second horizontal reinforcing bars 41b and the width stopping bars 44 straddling the pair of innermost main bars 31 arranged in the innermost stage are provided at predetermined intervals in the axial direction.

下弦部12には、図7に示すように主筋は配置されておらず、その全長にわたって延在しプレテンションが与えられたPC鋼線61が、上下方向に複数段(ここでは3段)且つ各段につき複数(ここでは2本)の配置で設けられている。なお、PC鋼線61は必ずしも横補強筋42に内接し、横補強筋42に直接拘束される必要はなく、コンクリートを介して横補強筋42に間接的に拘束されるように、横補強筋42の内側に配置されていればよい。また、図4によく示されるように、下弦部12の端部近傍には、曲げモーメントに抵抗するために(曲げモーメントに起因する水平方向のせん断力に抵抗するために)、第1および第2束部13,14において端部へ向けて上向きに傾斜して上弦部11に至る補強筋45が適宜に配置されている。他方、これらPC鋼線61および補強筋45を取り囲む横補強筋42が軸方向に所定の間隔に設けられている。   As shown in FIG. 7, the lower chord portion 12 is not provided with a main bar, and a PC steel wire 61 that is pretensioned and extends over the entire length thereof has a plurality of stages (here, three stages) and Each stage is provided in a plurality (two in this case). The PC steel wire 61 is not necessarily inscribed in the lateral reinforcing bar 42 and does not need to be directly restrained by the lateral reinforcing bar 42, but is indirectly restrained by the lateral reinforcing bar 42 through concrete. What is necessary is just to be arrange | positioned inside 42. Also, as well shown in FIG. 4, the first chord part 12 and the first chord part 12 are arranged near the end of the lower chord part 12 in order to resist the bending moment (to resist the horizontal shearing force caused by the bending moment). In the two bundle portions 13 and 14, reinforcing bars 45 that are inclined upward toward the end portion and reach the upper chord portion 11 are appropriately arranged. On the other hand, lateral reinforcing bars 42 surrounding the PC steel wire 61 and the reinforcing bars 45 are provided at predetermined intervals in the axial direction.

このように下弦部12にPC鋼線61が配置され、プレストレスが付与されることにより、下弦部12の引張強度が向上するため、断面の縮小化およびPCa梁1の大スパン化が可能になっている。   Since the PC steel wire 61 is arranged in the lower chord part 12 and prestress is applied in this way, the tensile strength of the lower chord part 12 is improved, so that the cross section can be reduced and the PCa beam 1 can have a large span. It has become.

また、下弦部12にPC鋼線61を配置したことによって下弦部12の小断面化が可能になる一方、下弦部12に通常量の鉄筋とPC鋼線61とを納めると、間隙が小さくなってコンクリートの充填性が悪化するが、主筋を省略したことで、最も小断面とされた中央側においてもコンクリートの充填性を確保することができるようになっている。加えて、PC鋼線61を取り囲むように横補強筋42を配置したことにより、下弦部12の強度を高めてPC鋼線61の定着を確実なものとし、下弦部12の小断面化および品質確保の両立が実現されている。   In addition, by arranging the PC steel wire 61 in the lower chord portion 12, it is possible to reduce the cross section of the lower chord portion 12. On the other hand, when a normal amount of rebar and the PC steel wire 61 are placed in the lower chord portion 12, the gap is reduced. The concrete fillability deteriorates, but by omitting the main bars, the concrete fillability can be secured even at the center side having the smallest cross section. In addition, by arranging the horizontal reinforcing bars 42 so as to surround the PC steel wire 61, the strength of the lower chord portion 12 is increased and the fixing of the PC steel wire 61 is ensured. The balance of securing is realized.

束部13〜16においては、図4に示すように、上弦部11の横補強筋41および下弦部12の横補強筋42が連結し、上弦部11の主筋31および下弦部12のPC鋼線61を取り囲む1つの横補強筋43をなしており、この横補強筋43が束部13〜16における上弦部11および下弦部12に対する接合強度を高めるためのせん断補強筋として機能している。   In the bundle portions 13 to 16, as shown in FIG. 4, the horizontal reinforcing bar 41 of the upper chord part 11 and the horizontal reinforcing bar 42 of the lower chord part 12 are connected, and the main bar 31 of the upper chord part 11 and the PC steel wire of the lower chord part 12. One horizontal reinforcing bar 43 surrounding 61 is formed, and this horizontal reinforcing bar 43 functions as a shear reinforcing bar for increasing the bonding strength to the upper chord part 11 and the lower chord part 12 in the bundle parts 13 to 16.

このように構成されたPCa梁1は、上弦部11、下弦部12および束部13〜16が剛体結合されたフィーレンディール構造となっており、各部の負担応力を明確な構造計算に基づいて求めることができる。   The PCa beam 1 configured as described above has a feelendel structure in which the upper chord part 11, the lower chord part 12 and the bundle parts 13 to 16 are rigidly coupled, and the stress applied to each part is based on a clear structural calculation. Can be sought.

図2に戻り、逆台形を呈する第1束部13の上端縁の長さと下端縁の長さとの平均値をとった第1束部13の長さ(軸方向長さ)A1と、第2〜第4束部14〜16の長さA2〜A4との関係は、下式に示す関係となっている。
A1>A2>A3>A4 (1)
Returning to FIG. 2, the length (axial length) A <b> 1 of the first bundle portion 13 taking the average value of the length of the upper end edge and the length of the lower end edge of the first bundle portion 13 exhibiting an inverted trapezoid, The relationship between the fourth bundle portions 14 to 16 and the lengths A2 to A4 is expressed by the following equation.
A1>A2>A3> A4 (1)

一方、第1〜第4開口部21〜24の長さ(軸方向長さ)をB1〜B4とすると、束部13〜16の長さA1〜A4と、中央部側に隣接する開口部21〜24の長さB1〜B4との比(A/B)は、下式に示す関係となっている。
(A1/B1)>(A2/B2)>(A3/B3)>(A4/B4) (2)
つまり、軸方向の端部側における束部長さと開口部長さとの比が軸方向の中央側における束部長さと開口部長さとの比よりも大きくなっている。
On the other hand, when the lengths (axial lengths) of the first to fourth openings 21 to 24 are B1 to B4, the lengths A1 to A4 of the bundle parts 13 to 16 and the opening 21 adjacent to the central part side. The ratio (A / B) to the lengths B1 to B4 of ˜24 has the relationship shown in the following formula.
(A1 / B1)> (A2 / B2)> (A3 / B3)> (A4 / B4) (2)
That is, the ratio of the bundle length and the opening length on the end side in the axial direction is larger than the ratio of the bundle length and the opening length on the central side in the axial direction.

束部13〜16の長さおよび配置間隔がこのように設定されたことにより、端部ほど大きくなる、曲げモーメントに起因する水平方向のせん断力に対し、力学的に合理的な構造で抵抗することができ、PCa梁1の強度の確保と軽量化との両立が可能になっている。また、下弦部12の端部に垂直方向せん断力の応力負担部材となり得る第1束部13が配置されたことにより、第1束部13の上方において上弦部11の断面を適切に縮小化できるため、PCa梁1の軽量化が図られている。   By setting the lengths and the arrangement intervals of the bundle portions 13 to 16 in this way, it resists the shear force in the horizontal direction caused by the bending moment, which becomes larger at the end portion, with a mechanically rational structure. Therefore, both the securing of the strength of the PCa beam 1 and the weight reduction can be achieved. In addition, since the first bundle portion 13 that can be a stress bearing member for vertical shearing force is disposed at the end portion of the lower chord portion 12, the cross section of the upper chord portion 11 can be appropriately reduced above the first bundle portion 13. Therefore, weight reduction of the PCa beam 1 is achieved.

また、開口部21〜24が矩形とされたことにより、大断面で矩形状が多い空調ダクトの収まりが良くなるだけでなく、円形開口部とした場合に生じる構造要素として寄与しない余肉部分が生じないため、PCa梁1の重量の増加が抑制されている。   In addition, since the openings 21 to 24 are rectangular, not only does the air conditioning duct fit in a large cross section with many rectangles, but there is also a surplus portion that does not contribute as a structural element that occurs when the circular opening is used. Since it does not occur, an increase in the weight of the PCa beam 1 is suppressed.

一方、上記構成に対し、図8に示すように、左右の端部の切欠を小さくしてPCa梁1を構成することも可能である。このようにすれば、下弦部12における第1束部13が連結する部分の長さが大きくなるため、PC鋼線61の端部における定着長さを十分確保することができ、必要なプレストレスを下弦部12に付与することができる。また、図8に示すように、上弦部11において、側部11cおよび連結部11bを設けることなく、最も幅が小さな中央部11aと最も幅が大きな側端部11eとを連結部11dが直接連結するように構成することも可能である。このようにすることにより、鉄筋および型枠の組立を容易にすることができる。   On the other hand, as shown in FIG. 8, the PCa beam 1 can be configured by reducing the left and right end cutouts. In this way, the length of the portion of the lower chord portion 12 to which the first bundle portion 13 is connected is increased, so that the fixing length at the end of the PC steel wire 61 can be sufficiently secured, and the necessary prestress is achieved. Can be applied to the lower chord part 12. Further, as shown in FIG. 8, in the upper chord part 11, the connecting part 11d directly connects the center part 11a having the smallest width and the side end part 11e having the largest width without providing the side part 11c and the connecting part 11b. It is also possible to configure so as to. By doing in this way, an assembly of a reinforcing bar and a formwork can be made easy.

次に、このような構成を有するPCa梁1をより合理的且つ高品質に製造するための手順について説明する。図9は、PCa梁1の鉄筋組立手順の説明図であり、(A)は正面図を、(B)は(A)中のB−B断面図を、(C)は(A)中のC−C断面図を示している。   Next, a procedure for manufacturing the PCa beam 1 having such a configuration with more rational and high quality will be described. FIG. 9 is an explanatory view of a rebar assembling procedure of the PCa beam 1, (A) is a front view, (B) is a BB cross-sectional view in (A), and (C) is in (A). CC sectional drawing is shown.

PCa梁1の鉄筋を組み立てる際には、まず図9に実線および破線で示すように、開口部21〜24の位置を考慮せずに、上弦部11の主筋31および下弦部12の段取り筋32を取り囲む横補強筋43をPCa梁1の全長にわたって配置する。その後、開口部21〜24の位置に合わせ、破線で示す横補強筋43の中央部分を切断除去し、上弦部11の主筋31の下端および下弦部12の段取り筋32の上端にそれぞれ幅止め筋44を配置し、上下に残った横補強筋43の一部が上弦部11の横補強筋41の側部および下弦部12の横補強筋42の側部となってそれぞれ主筋31および段取り筋32を取り囲む横補強筋41,42を形成する。   When assembling the reinforcing bars of the PCa beam 1, first, as shown by solid and broken lines in FIG. 9, the main bars 31 of the upper chord part 11 and the setup bars 32 of the lower chord part 12 without considering the positions of the openings 21 to 24. Is disposed over the entire length of the PCa beam 1. Thereafter, in accordance with the positions of the openings 21 to 24, the central portion of the horizontal reinforcing bar 43 indicated by a broken line is cut and removed, and the width stop bars are respectively provided at the lower end of the main bar 31 of the upper chord part 11 and the upper end of the setup bar 32 of the lower chord part 12. 44, and a part of the horizontal reinforcing bar 43 remaining above and below becomes the side part of the horizontal reinforcing bar 41 of the upper chord part 11 and the side part of the horizontal reinforcing bar 42 of the lower chord part 12, respectively. The lateral reinforcing bars 41 and 42 surrounding the rim are formed.

或いは、図10に示す変形例のように、上弦部11の横補強筋41および下弦部12の横補強筋42と、上弦部11の主筋31および下弦部12の段取り筋32を取り囲む横補強筋43とを、交互配置になるようにPCa梁1の全長にわたって配置する。その後、開口部21〜24の位置に合わせ、破線で示す横補強筋43の中央部分を切断除去し、上弦部11の主筋31の下端および下弦部12の段取り筋32の上端にそれぞれ幅止め筋44(図示省略)を配置し、上下に残った横補強筋43の一部が上弦部11の横補強筋41の側部および下弦部12の横補強筋42の側部となってそれぞれ主筋31および段取り筋32を取り囲む横補強筋41,42を形成するようにしてもよい。   Alternatively, as in the modification shown in FIG. 10, the lateral reinforcement bars 41 that surround the horizontal reinforcement bars 41 of the upper chord part 11 and the horizontal reinforcement bars 42 of the lower chord part 12, and the main bars 31 of the upper chord part 11 and the setup bars 32 of the lower chord part 12. 43 are arranged over the entire length of the PCa beam 1 so as to be alternately arranged. Thereafter, in accordance with the positions of the openings 21 to 24, the central portion of the horizontal reinforcing bar 43 indicated by a broken line is cut and removed, and the width stop bars are respectively provided at the lower end of the main bar 31 of the upper chord part 11 and the upper end of the setup bar 32 of the lower chord part 12. 44 (not shown) are arranged, and a part of the horizontal reinforcing bar 43 left and right is a side part of the horizontal reinforcing bar 41 of the upper chord part 11 and a side part of the horizontal reinforcing bar 42 of the lower chord part 12. Alternatively, the lateral reinforcing bars 41 and 42 surrounding the setup bar 32 may be formed.

PCa梁1の鉄筋をこのように組み立てることにより、不等長さ且つ不等間隔に配置される束部13〜16に応じて変則的に横補強筋41〜43を配置する必要がなく、鉄筋組立作業を効率化することができる。また、このような手順で組み立てることにより、意匠的観点で様々な形態に開口部を設けることができるPCa梁1に対し、様々な形態のPCa梁1の汎用鉄筋として用いることができ、これによっても鉄筋組立作業を効率化することができる。   By assembling the reinforcing bars of the PCa beam 1 in this way, it is not necessary to irregularly arrange the lateral reinforcing bars 41 to 43 according to the bundle portions 13 to 16 arranged at unequal lengths and at unequal intervals. Assembling work can be made efficient. Moreover, by assembling in such a procedure, it can be used as a general-purpose reinforcing bar for the PCa beam 1 having various forms with respect to the PCa beam 1 in which openings can be provided in various forms from a design viewpoint. Also, rebar assembly work can be made more efficient.

≪第2実施形態≫
図11を参照してPCa梁1の合理的な製造方法の第2実施形態を説明する。なお、上記実施形態と同様の部材または部位には同一の符号を付すものとし、上記実施形態と重複する説明は省略する。以降の実施形態においても同様とする。
<< Second Embodiment >>
A second embodiment of a rational manufacturing method of the PCa beam 1 will be described with reference to FIG. In addition, the same code | symbol shall be attached | subjected to the member or site | part similar to the said embodiment, and the description which overlaps with the said embodiment is abbreviate | omitted. The same applies to the following embodiments.

図11(A)に示すように、上弦部11のうち中央部11a、連結部11bおよび側部11c、並びに第2〜第4束部14を構成する上側部材51を鉄筋コンクリートにより一体にプレキャスト成形するとともに、上弦部11のうち側端部11eおよび連結部11d、第1束部13、並びに下弦部12を構成する下側部材52を鉄筋コンクリートにより一体にプレキャスト成形する。なお、上側部材51および下側部材52の鉄筋の配置は上記一般的構成のものとは異なるが、概略同様であり、詳細な変更は発明の要旨に関係しないため、ここでは説明を省略する。以下の実施形態でも同様とする。   As shown in FIG. 11 (A), the upper member 51 constituting the central portion 11a, the connecting portion 11b and the side portion 11c, and the second to fourth bundle portions 14 in the upper chord portion 11 is precast-molded integrally with reinforced concrete. At the same time, the lower end member 52 constituting the side end portion 11e and the connecting portion 11d, the first bundle portion 13, and the lower chord portion 12 of the upper chord portion 11 is precast-molded integrally with reinforced concrete. The arrangement of the reinforcing bars of the upper member 51 and the lower member 52 is different from that of the above-described general configuration, but is substantially the same, and detailed changes are not related to the gist of the invention, so the description is omitted here. The same applies to the following embodiments.

上側部材51をプレキャスト成形する際には、上弦部11が上側となるように、すなわち図11の紙面の上側が天を向くように鉄筋および型枠を組み、コンクリートを打設するとよい。このような方向にコンクリートを打設することにより、全ての部位にコンクリートを容易に充填することができ、いわゆる豆板やジャンカなどの施工不良が発生することを防止できる。   When the upper member 51 is precast-molded, it is preferable to assemble concrete with a reinforcing bar and a formwork so that the upper chord portion 11 is on the upper side, that is, the upper side of the paper surface of FIG. By placing the concrete in such a direction, it is possible to easily fill all parts with concrete, and it is possible to prevent the occurrence of construction defects such as so-called bean plates and jumpers.

一方、下側部材52をプレキャスト成形する際には、下弦部12が上側となるように、すなわち図11の紙面の下側が天を向くように鉄筋および型枠を組み、コンクリートを打設するのが好ましい。このような方向にコンクリートを打設することにより、全ての部位にコンクリートを容易に充填することができるとともに、コンクリートの横流しによる材料分離や仕上げ面の高低差による下側仕上げ面の隆起などの施工不良が発生することも防止できる。   On the other hand, when the lower member 52 is precast-molded, the rebar and the formwork are assembled so that the lower chord 12 is on the upper side, that is, the lower side of the paper of FIG. Is preferred. By placing concrete in this direction, it is possible to easily fill all parts with concrete, as well as material separation by cross-flowing concrete and ridges on the lower finished surface due to the height difference of the finished surface. It is possible to prevent the occurrence of defects.

また、下側部材52をプレキャスト成形する際には、下弦部12の型枠内にPC鋼線61を通して緊張しておき、高強度コンクリートを打設して所定の強度が発現した後、緊張を解除して下弦部12に全長にわたってプレストレスを付与する。   Further, when the lower member 52 is precast-molded, it is strained through the PC steel wire 61 in the mold of the lower chord portion 12, and after high strength concrete is cast to express a predetermined strength, the tension is applied. Release and apply prestress to the lower chord part 12 over the entire length.

上側部材51の端部、すなわち上弦部11の側部11cの端面からは、下側部材52に含まれる上弦部11と接合するために主筋31を突出させており、下側部材52は、後に上弦部11を接合するために当該突出した主筋31を受容させる箇所をコンクリートが未打設の状態としておく。   From the end portion of the upper member 51, that is, the end surface of the side portion 11 c of the upper chord portion 11, the main bar 31 protrudes in order to join the upper chord portion 11 included in the lower member 52. In order to join the upper chord part 11, the place where the protruding main bar 31 is received is left in a state where the concrete is not placed.

上側部材51の第2〜第4束部14〜16を構成する部分は、実際の第2〜第4束部の高さh(図11(B)参照)よりも大きな高さ寸法を有する矩形に形成されている。一方、下側部材52の第2〜第4束部14〜16と接合する部分には、第2〜第4束部14〜16の長さ(PCa梁1の軸方向における長さ)と略同一長さにわたって下弦部12が切り欠かれて形成された凹部52aが設けられている。また、第1束部13を構成する部分も、実際の第1束部13の高さh(図11(B)参照)よりも大きな高さ寸法を有するように形成されている。一方、上側部材51の第1束部13と接合する部分には、第1束部13の長さと略同一長さにわたって上弦部11が切り欠かれて凹部51aが形成されている。   The part which comprises the 2nd-4th bundle parts 14-16 of the upper side member 51 is a rectangle which has a height dimension larger than the height h (refer FIG. 11 (B)) of actual 2nd-4th bundle parts. Is formed. On the other hand, the length of the second to fourth bundle portions 14 to 16 (the length in the axial direction of the PCa beam 1) is substantially equal to the portion of the lower member 52 that joins the second to fourth bundle portions 14 to 16. A recess 52a formed by cutting out the lower chord 12 over the same length is provided. Moreover, the part which comprises the 1st bundle part 13 is also formed so that it may have a height dimension larger than the actual height h of the 1st bundle part 13 (refer FIG. 11 (B)). On the other hand, in the portion of the upper member 51 that joins the first bundle portion 13, the upper chord portion 11 is cut out over the substantially same length as the length of the first bundle portion 13, and a recess 51 a is formed.

次に、これら上側部材51および下側部材52を、図11(B)に示すように一体に接合して一本のPCa梁1を形成する。具体的には、上側部材51の第2〜第4束部14〜16を構成する部分を下側部材52の対応する凹部52aにそれぞれ嵌合させ、下側部材52の第1束部13を構成する部分を上側部材51の凹部51aに嵌合させ、下側部材52のコンクリートが未打設とされた部分に、上側部材の主筋31の突出部分を配置した状態でコンクリートを打設して一体化する。このようにして接合することにより、上側部材51と下側部材52とが直接的に接合される。   Next, the upper member 51 and the lower member 52 are integrally joined as shown in FIG. 11B to form one PCa beam 1. Specifically, the portions constituting the second to fourth bundle portions 14 to 16 of the upper member 51 are respectively fitted into the corresponding concave portions 52 a of the lower member 52, and the first bundle portion 13 of the lower member 52 is moved. The portion to be configured is fitted into the concave portion 51a of the upper member 51, and the concrete is placed in a state where the projecting portion of the main reinforcement 31 of the upper member is disposed in the portion where the concrete of the lower member 52 is not placed. Integrate. By joining in this way, the upper member 51 and the lower member 52 are directly joined.

なお、第2〜第4束部14〜16を構成する部分と凹部52aとの間、および第1束部13を構成する部分と凹部51aとの間にはモルタルなどを敷いておき、両部材が密着するようにするとよい。   In addition, between the part which comprises the 2nd-4th bundle parts 14-16 and the recessed part 52a, and the part which comprises the 1st bundle part 13, and the recessed part 51a, mortar etc. are spread | laid, both members It is good to make it adhere.

このようにして製造されるPCa梁1は、図11の(A)に示す段階では、上側部材51が、第1〜第4開口部21〜24の各上縁21u、22u、23u、24uと、第1開口部21の梁中央側の側縁21scと、第2〜第4開口部22〜24の両側縁22sc、22se、23sc、23se、24sとを画定するように形成される。また、下側部材52は、第1〜第4開口部21〜24の各下縁21l、22l、23l、24lと、第1開口部21の梁端側の側縁21seとを画定するように形成される。このように分割して上側部材51と下側部材52とを別々にプレキャスト成形することにより、各部材の開口部周辺へのコンクリートの充填性を担保し、品質の確保を容易にすることができる。   In the PCa beam 1 manufactured in this way, at the stage shown in FIG. 11 (A), the upper member 51 has the upper edges 21u, 22u, 23u, 24u of the first to fourth openings 21 to 24u. The first opening 21 is formed so as to define a side edge 21sc on the beam center side and both side edges 22sc, 22se, 23sc, 23se, 24s of the second to fourth openings 22-24. The lower member 52 defines the lower edges 21l, 22l, 23l, and 24l of the first to fourth openings 21 to 24 and the side edge 21se on the beam end side of the first opening 21. It is formed. By splitting the upper member 51 and the lower member 52 separately in this way, the concrete filling property around the opening of each member can be ensured and the quality can be easily ensured. .

また、PCa梁1を複数に分割したプレキャストコンクリート部材で構成することにより、部材重量を軽減することができるため、上側部材51と下側部材52との接合を現場で行うようにすれば、工場での取り扱いや現場への搬送を容易にすることができる。また、PCa梁1にプレストレスを付与する場合であっても、PC鋼線61を用いてプレストレスを付与することで、通常のPC工場での製造が可能となり、部材も小さくて済むため取り扱いも容易になる。   In addition, since the weight of the member can be reduced by configuring the PCa beam 1 with a precast concrete member divided into a plurality of parts, if the upper member 51 and the lower member 52 are joined on site, the factory Can be easily handled and transported to the site. Even when prestress is applied to the PCa beam 1, by applying prestress using the PC steel wire 61, it becomes possible to manufacture in a normal PC factory, and handling is possible because the members can be small. Will also be easier.

さらに、引張力が作用する下弦部12にプレストレスを付与することにより、部材断面を効果的に縮小化することができる。また、PCa梁1にプレストレスを付与する場合には、プレストレスが与えられる部位に圧縮強度の高い高強度コンクリートを用いる必要があるが、PCa梁1を一体物として成形した場合には、本来は必要のない部位にまで高強度コンクリートを用いることでコストアップを招くことになるが、PCa梁1を上側部材51と下側部材52とに分割してプレキャスト成形することにより、高価な高強度コンクリートと安価な通常のコンクリートとの使い分けが可能となり、材料コストを削減することができる。   Furthermore, by applying prestress to the lower chord part 12 on which a tensile force acts, the member cross section can be effectively reduced. In addition, when prestress is applied to the PCa beam 1, it is necessary to use high-strength concrete with high compressive strength at the site where the prestress is applied. However, when the PCa beam 1 is molded as an integral part, However, the use of high-strength concrete even in areas where it is not necessary increases the cost. However, by splitting the PCa beam 1 into an upper member 51 and a lower member 52 and precast molding, expensive high strength It is possible to selectively use concrete and inexpensive ordinary concrete, and the material cost can be reduced.

一方、PCa梁1を一体物とし且つプレストレスを付与する場合には、梁断面において重心位置に対してプレストレス合力の作用位置が大きく偏心する。そのため、PCa梁1全体に上向きの曲げ応力が発生し、施工途中に上弦部11および束部13〜16に過剰な応力によるひび割れが生じやすい。これに対し、本実施形態では、PCa梁1を上側部材51と下側部材52とに分割して成形するため、プレストレス合力の作用位置を下弦部12の重心と略同じ位置にすることができる。そのため、プレストレスによるひび割れの発生を防止できる。   On the other hand, when the PCa beam 1 is integrated and prestress is applied, the prestress resultant force position is greatly decentered with respect to the center of gravity position in the beam cross section. Therefore, upward bending stress is generated in the entire PCa beam 1, and cracks due to excessive stress are likely to occur in the upper chord portion 11 and the bundle portions 13 to 16 during the construction. On the other hand, in this embodiment, since the PCa beam 1 is divided into the upper member 51 and the lower member 52 and formed, the prestress resultant force is applied at a position substantially the same as the center of gravity of the lower chord portion 12. it can. Therefore, the generation of cracks due to prestress can be prevented.

他方、上側部材51をプレキャスト成形する際に、少なくとも一部の束部(第2〜第4束部14〜16)を一体成形すること、或いは、下側部材52をプレキャスト成形する際に、少なくとも一部の束部(第1束部13)を一体成形することにより、部材点数および接合箇所を少なくすることができる。そのため、PCa梁1の組立作業を容易にすることができる。   On the other hand, when the upper member 51 is precast-molded, at least a part of the bundle portions (second to fourth bundle portions 14-16) are integrally molded, or when the lower member 52 is precast-molded, at least By integrally molding a part of the bundle portions (first bundle portion 13), the number of members and the joint locations can be reduced. Therefore, the assembly work of the PCa beam 1 can be facilitated.

なお、本実施形態では、上側部材51および下側部材52に一体成形された束部13〜16を構成する部分が、それぞれ各束部13〜16の全体と、一体成形されない他方の部材が構成する下弦部12または上弦部11の一部(すなわち嵌合凸部)とを構成するように分割しているが、それぞれ各束部13〜16の一部を構成するように分割することも可能である。   In addition, in this embodiment, the part which comprises the bundle parts 13-16 integrally molded by the upper side member 51 and the lower side member 52 respectively comprises the whole each bundle part 13-16, and the other member which is not integrally molded. The lower chord part 12 or the upper chord part 11 is divided so as to constitute a part (that is, the fitting convex part), but can be divided so as to constitute a part of each of the bundle parts 13 to 16, respectively. It is.

≪第3実施形態≫
次に、図12を参照してPCa梁1の合理的な製造方法の第3実施形態を説明する。なお、図12(B)には、PCa梁1の側面図の上方にPCa梁1の平面図を併せて示している。
«Third embodiment»
Next, a third embodiment of a rational manufacturing method of the PCa beam 1 will be described with reference to FIG. In FIG. 12B, a plan view of the PCa beam 1 is also shown above the side view of the PCa beam 1.

本実施形態のPCa梁1は、図8に示したもののように上弦部11において中央部11aと側端部11eとが連結部11dによって直接連結された構成となっている。このPCa梁1の製造手順は、次の通りである。まず図12(A)に示すように、上弦部11の中央部11a、および第2〜第4束部14を構成する上側部材51を鉄筋コンクリートにより一体にプレキャスト成形するとともに、第1束部13および下弦部12を構成する下側部材52を鉄筋コンクリートにより一体にプレキャスト成形し、さらに、上弦部11のうち側端部11eおよび連結部11d、並びに第1束部13を構成する端部材53を鉄筋コンクリートにより一体にプレキャスト成形する。   As shown in FIG. 8, the PCa beam 1 of this embodiment has a configuration in which the central portion 11a and the side end portion 11e are directly connected to each other at the upper chord portion 11 by the connecting portion 11d. The manufacturing procedure of this PCa beam 1 is as follows. First, as shown in FIG. 12 (A), the central part 11a of the upper chord part 11 and the upper member 51 constituting the second to fourth bundle parts 14 are precast-molded integrally with reinforced concrete, and the first bundle part 13 and The lower member 52 constituting the lower chord portion 12 is precast-molded integrally with reinforced concrete, and the side end portion 11e and the connecting portion 11d of the upper chord portion 11 and the end member 53 constituting the first bundle portion 13 are made of reinforced concrete. Precast molding as one piece.

本実施形態においても、上側部材51をプレキャスト成形する際には、上弦部11が上側となるようにコンクリートを打設し、下側部材52をプレキャスト成形する際には、下弦部12が上側となるようにコンクリートを打設するとよい。また、端部材53をプレキャスト成形する際には、上弦部11が上側となるようにコンクリートを打設するとよい。   Also in this embodiment, when the upper member 51 is precast-molded, concrete is placed so that the upper chord portion 11 is on the upper side, and when the lower member 52 is precast-molded, the lower chord portion 12 is on the upper side. It is better to cast concrete so that In addition, when pre-casting the end member 53, it is preferable to cast concrete so that the upper chord portion 11 is on the upper side.

また、下側部材52をプレキャスト成形する際には、下弦部12の型枠内にPC鋼線61を通して緊張しておき、高強度コンクリートを打設し、所定の強度が発現した後に緊張を解除して下弦部12に全長にわたってプレストレスを付与するようにするとともに、PC鋼線61を下弦部12の端面から所定長さ以上延出させておく。   Further, when the lower member 52 is precast-molded, it is strained through the PC steel wire 61 in the form of the lower chord portion 12, high-strength concrete is placed, and the tension is released after a predetermined strength is developed. Thus, prestress is applied to the lower chord portion 12 over the entire length, and the PC steel wire 61 is extended from the end surface of the lower chord portion 12 by a predetermined length or more.

端部材53には、第1束部13から下方へ突出して下弦部12の側端面に接合される突出部53cを形成するとともに、この突出部53cの下弦部12との接合面から上弦部11の端部へ至るように斜めに図示しないシース管を埋め込んでおき、下弦部12の端面から延出したPC鋼線61を挿通させ得るようにしておく。また、端部材53は、後に上弦部11を接合するためにその端面から突出した主筋31を受容すべくコンクリートの一部を未打設の状態にしておく。   The end member 53 is formed with a protruding portion 53c that protrudes downward from the first bundle portion 13 and is joined to the side end surface of the lower chord portion 12, and the upper chord portion 11 from the joint surface with the lower chord portion 12 of the protruding portion 53c. A sheath tube (not shown) is embedded obliquely so as to reach the end of the steel plate so that the PC steel wire 61 extending from the end surface of the lower chord portion 12 can be inserted. Further, the end member 53 leaves a part of the concrete in an unplaced state so as to receive the main bar 31 protruding from the end face in order to join the upper chord portion 11 later.

次に、これら上側部材51および下側部材52を、図12(B)に示すように一体に接合して一本のPCa梁1とする。具体的には、上側部材51の第2〜第4束部14〜16を構成する部分を下側部材52の対応する凹部52aにそれぞれ嵌合させ、端部材53の突出部53cを下側部材52の端面に合わせ且つ第1束部13を構成する部分を上側部材51の凹部51aに嵌合させてシース管にPC鋼線61を挿通して緊張および定着作業を行い、端部材53のコンクリートが未打設とされた部分に上側部材の主筋31の突出部分を配置してコンクリートを打設する。このように接合することにより、上側部材51と下側部材52とが、第2〜第4束部14〜16では直接的に、第1束部13では端部材53を介して間接的に接合される。   Next, the upper member 51 and the lower member 52 are integrally joined to form one PCa beam 1 as shown in FIG. Specifically, the portions constituting the second to fourth bundle portions 14 to 16 of the upper member 51 are respectively fitted into the corresponding concave portions 52a of the lower member 52, and the protruding portion 53c of the end member 53 is set to the lower member. 52, the portion constituting the first bundle portion 13 is fitted into the concave portion 51a of the upper member 51, the PC steel wire 61 is inserted into the sheath tube, and the tension and fixing work is performed. The concrete portion is placed by placing the protruding portion of the main reinforcement 31 of the upper member in the portion where is not placed. By joining in this way, the upper member 51 and the lower member 52 are joined directly by the second to fourth bundle parts 14 to 16 and indirectly by the end member 53 at the first bundle part 13. Is done.

なお、PC鋼線61は、下弦部12をプレキャスト成形する際にプレテンション方式として用いられた後、端部材53との接合時に図中に黒塗り矢印で示すように斜め上方へ緊張されて端部材53の上弦部11端部に定着されて端部材53にプレストレスを付与するポストテンション方式としても用いられる。つまり、PC鋼線61がプレテンションおよびポストテンションの両方式に兼用されている。   The PC steel wire 61 is used as a pre-tensioning method when the lower chord portion 12 is precast-molded, and then is endured obliquely upward as shown by the black arrow in the drawing when joining the end member 53. It is also used as a post-tension system that is fixed to the end portion of the upper chord portion 11 of the member 53 and applies prestress to the end member 53. That is, the PC steel wire 61 is used for both pre-tension and post-tension types.

ここで、PC鋼線61にポストテンションを付与するタイミングは、上記のような端部材53との接合時に限定されることはなく、端部材53を接合してPCa梁1を大梁2に架設した後とすることもできる。このような時期に行うことにより、PCa梁1の組立後にポストテンションを付与する場合でもひび割れなどの発生を確実に回避することができる。   Here, the timing at which the post tension is applied to the PC steel wire 61 is not limited to the time of joining with the end member 53 as described above, and the PCa beam 1 is installed on the large beam 2 by joining the end member 53. It can be later. By performing at such a time, even when post tension is applied after the assembly of the PCa beam 1, it is possible to reliably avoid the occurrence of cracks and the like.

このようにして製造されるPCa梁1は、図12の(A)に示す段階では、上側部材51が、第2実施形態と同様に、第1〜第4開口部21〜24の各上縁21u、22u、23u、24uと、第1開口部21の梁中央側の側縁21scと、第2〜第4開口部22〜24の両側縁22sc、22se、23sc、23se、24sを画定するように形成される。また、下側部材52は、第1〜第4開口部21〜24の各下縁21l、22l、23l、24lを画定するように形成され、端部材53が、第1開口部21の梁端側の側縁21seを画定するように形成される。   In the PCa beam 1 manufactured as described above, at the stage shown in FIG. 12A, the upper member 51 is connected to the upper edges of the first to fourth openings 21 to 24 in the same manner as in the second embodiment. 21u, 22u, 23u, 24u, side edge 21sc on the beam center side of the first opening 21, and both side edges 22sc, 22se, 23sc, 23se, 24s of the second to fourth openings 22-24 are defined. Formed. The lower member 52 is formed so as to demarcate the lower edges 21 l, 22 l, 23 l, and 24 l of the first to fourth openings 21 to 24, and the end member 53 is a beam end of the first opening 21. It is formed so as to define a side edge 21se on the side.

このように分割して上側部材51と下側部材52と端部材53とを別々にプレキャスト成形することにより、各部材の開口部周辺へのコンクリートの充填性を担保できるだけでなく、各部材の長さをPCa梁1の長さに比べて短くすることができるため、各部材の取り扱いや運搬をより容易にすることができる。   By dividing the upper member 51, the lower member 52, and the end member 53 separately by precast molding in this way, not only can the concrete fillability around the opening of each member be secured, but also the length of each member. Since the length can be made shorter than the length of the PCa beam 1, each member can be handled and transported more easily.

<変形例>
本実施形態においては、図13に示す変形例のように、下弦部12の内部に設けられるPC鋼線61を下弦部12の端部で切断するようにし、下弦部12の端部或いは下弦部12の全長に渡って主筋31を配置し、この主筋31を上弦部11に至るように下弦部12の端面から斜めに突出させておき、上側部材51と下側部材52とを第2〜第4束部14〜16で当接するように適正配置した後に、上弦部11の主筋31および下弦部12の主筋31を巻き込むようにコンクリートを打設することで、上側部材51および下側部材52の成形後に端部材53をプレキャスト成形することもできる。このような接合によっても、上側部材51と下側部材52とを、第2〜第4束部14〜16では直接的に、第1束部13では端部材53を介して間接的に接合することができる。
<Modification>
In the present embodiment, as in the modification shown in FIG. 13, the PC steel wire 61 provided inside the lower chord portion 12 is cut at the end portion of the lower chord portion 12, and the end portion of the lower chord portion 12 or the lower chord portion The main bar 31 is arranged over the entire length of the twelve part, and the main bar 31 is obliquely projected from the end surface of the lower chord part 12 so as to reach the upper chord part 11, and the upper member 51 and the lower member 52 are second to second. After arranging appropriately so that it may contact | abut with the 4 bundle parts 14-16, by placing concrete so that the main reinforcement 31 of the upper chord part 11 and the main reinforcement 31 of the lower chord part 12 may be wound, upper member 51 and lower member 52 of The end member 53 can also be precast molded after molding. Also by such joining, the upper member 51 and the lower member 52 are joined directly by the second to fourth bundle portions 14 to 16 and indirectly by the end member 53 at the first bundle portion 13. be able to.

≪第4実施形態≫
図14および図15に示すように、本実施形態に係るPCa梁1は、第3実施形態と同様に、上側部材51と下側部材52と左右の端部材53とから構成される。本実施形態では、上側部材51が、上弦部11の中央部11aと第1〜第4束部13〜16の上半部分とを一体にプレキャスト成形され、下側部材52が、下弦部12と第1〜第4束部13〜16の下半部分とを一体にプレキャスト成形され、端部材53が、上弦部11の側端部11eおよび連結部11dと第1束部13の側部とを一体にプレキャスト成形されている。
<< Fourth Embodiment >>
As shown in FIGS. 14 and 15, the PCa beam 1 according to this embodiment includes an upper member 51, a lower member 52, and left and right end members 53, as in the third embodiment. In the present embodiment, the upper member 51 is precast-molded integrally with the central portion 11 a of the upper chord portion 11 and the upper half portions of the first to fourth bundle portions 13 to 16, and the lower member 52 is connected to the lower chord portion 12. The lower half of the first to fourth bundle parts 13 to 16 is precast-molded integrally, and the end member 53 includes the side end part 11e and the connecting part 11d of the upper chord part 11 and the side part of the first bundle part 13. It is precast molded integrally.

上側部材51の第1〜第4束部13〜16を構成する部分の下面と下側部材52の第1〜第4束部13〜16を構成する部分の上面との一方(ここでは下側部材52側)には、凸部52bが形成され、その他方(ここでは上側部材51側)には、これら凸部53bに対して補完的な形状を呈する凹部51aが形成されている。そして、上側部材51と下側部材52とは、第1〜第4束部13〜16において凸部52bを凹部51aに嵌合させた状態で接合されることにより、嵌合部分がせん断キーとなって、曲げモーメントに起因して生じる水平方向のせん断力に抵抗できるようになっている。また、これら第1〜第4束部13〜16が上下方向の中央近傍で接合されることにより、水平方向のせん断力が最も小さくなる位置に接合部が配置されるようになっている。   One of the lower surface of the portion constituting the first to fourth bundle portions 13 to 16 of the upper member 51 and the upper surface of the portion constituting the first to fourth bundle portions 13 to 16 of the lower member 52 (here, the lower side) A convex portion 52b is formed on the member 52 side, and a concave portion 51a having a shape complementary to the convex portion 53b is formed on the other side (here, the upper member 51 side). Then, the upper member 51 and the lower member 52 are joined in a state where the convex portion 52b is fitted to the concave portion 51a in the first to fourth bundle portions 13 to 16, so that the fitting portion becomes a shear key. Thus, it can resist the horizontal shearing force caused by the bending moment. In addition, the first to fourth bundle portions 13 to 16 are joined in the vicinity of the center in the vertical direction, so that the joint portion is arranged at a position where the horizontal shearing force is minimized.

また、本実施形態のPCa梁1は、下弦部12全長にわたって直線状に設けられたPC鋼線61を有する他、PCa梁1の中央部において下弦部12に位置し、PCa梁1の軸方向端部において上弦部11に位置するように、緩やかな曲線を描いてPCa梁1の略全長にわたって設けられたPC鋼線62を有している。そのため、第1開口部21は、矩形ではなく台形となっている。   In addition, the PCa beam 1 of the present embodiment has a PC steel wire 61 provided linearly over the entire length of the lower chord portion 12, and is located at the lower chord portion 12 in the central portion of the PCa beam 1, and the axial direction of the PCa beam 1 A PC steel wire 62 is provided over the substantially entire length of the PCa beam 1 in a gentle curve so as to be located at the upper chord 11 at the end. Therefore, the 1st opening part 21 is not a rectangle but trapezoid.

PC鋼線61は、下弦部12をプレキャスト成形する際にテンションが付与され、所定期間の養生後にテンションを解除することで下弦部12にプレストレスを与えるプレテンション方式であり、コンクリート打設前に緊張するために直線状に配置される。一方、PC鋼線62は、曲げモーメントに効率的に抵抗するために、PC鋼線62を梁中央部では下側に位置するとともに梁端部では上側に位置するような懸垂曲線状に配置するため、下側部材52および端部材53のプレキャスト成形後にテンションを付与するポストテンション方式である。また、PC鋼線62は、下側部材52と端部材53との接合時に緊張するようにすることも可能であるが、ひび割れなどを防止するためにPCa梁1を大梁2間に架設した後に緊張するのが好ましい。   The PC steel wire 61 is a pre-tension system in which tension is applied when the lower chord part 12 is precast-molded and pre-stress is applied to the lower chord part 12 by releasing the tension after curing for a predetermined period. Arranged in a straight line to be tense. On the other hand, in order to efficiently resist the bending moment, the PC steel wire 62 is arranged in a suspended curve shape such that the PC steel wire 62 is positioned on the lower side at the beam center and on the upper side at the beam end. Therefore, it is a post-tension method in which tension is applied after precast molding of the lower member 52 and the end member 53. The PC steel wire 62 may be tensioned when the lower member 52 and the end member 53 are joined, but after the PCa beam 1 is installed between the large beams 2 in order to prevent cracks and the like. It is preferable to be nervous.

このように、プレテンション方式のPC鋼線61とポストテンション方式のPC鋼線62とを併用することで、PCa梁1に対し、工場生産による製造コストの低下と現場施工による効果的な強度付与との両立を実現することができる。   In this way, by using the pre-tension type PC steel wire 61 and the post-tension type PC steel wire 62 in combination, the PCa beam 1 can be effectively reduced in production cost by factory production and effectively strengthened by on-site construction. Can be achieved.

≪第5実施形態≫
次に、本発明の第5実施形態について説明する。図16(A)に示すように、本実施形態のPCa梁1は、上弦部11のうち中央部11aの大部分がプレキャスト成形された1本の上側部材51から構成され、下弦部12の大部分がプレキャスト成形された1本の下側部材52から構成され、第1束部13および上弦部11の端部が端部材53から構成され、第2〜第4束部14〜16が個別にプレキャスト形成された第2〜第4束部材54〜56から構成されており、図16(B)に示すように、これら各部材51〜56を一体化することで1本のPCa梁1が構成されている。
«Fifth embodiment»
Next, a fifth embodiment of the present invention will be described. As shown in FIG. 16 (A), the PCa beam 1 of this embodiment is composed of one upper member 51 in which most of the central portion 11a of the upper chord portion 11 is precast, and the lower chord portion 12 is large. The first part 13 and the upper chord part 11 are composed of end members 53, and the second to fourth bundle parts 14 to 16 are individually formed. It is comprised from the 2nd-4th bundle members 54-56 by which the precast formation was carried out, and as shown in FIG.16 (B), one each PCa beam 1 is comprised by integrating these members 51-56. Has been.

代表例として第3束部15周辺を示す図17に示すように、上側部材51の下面および下側部材52の上面には、凹部51a,52aがそれぞれ形成され、端部材53および第2〜第4束部材54〜56の上面および下面には、これら凹部51a,52aに対して補完的な形状を呈する凸部53b,54b,55b,56bが形成されており、端部材53および第2〜第4束部材54〜56が上側部材51および下側部材52に対してそれぞれ凸部53b,54b,55b,56bを嵌合させた状態で接合されることにより、凸部53b,54b,55b,56bがせん断キーとなって曲げモーメントに起因して生じる水平方向のせん断力に抵抗できるようになっている。   As shown in FIG. 17 showing the periphery of the third bundle portion 15 as a representative example, recesses 51a and 52a are formed on the lower surface of the upper member 51 and the upper surface of the lower member 52, respectively, and the end member 53 and the second to second members are formed. Convex portions 53b, 54b, 55b, and 56b that are complementary to the concave portions 51a and 52a are formed on the upper surface and the lower surface of the four bundle members 54 to 56, respectively. The four bundle members 54 to 56 are joined to the upper member 51 and the lower member 52 in a state where the convex portions 53b, 54b, 55b, and 56b are fitted to each other, whereby the convex portions 53b, 54b, 55b, and 56b are joined. Becomes a shear key and can resist the horizontal shearing force caused by the bending moment.

また、上側部材51、下側部材52、端部材53および第2〜第4束部材54〜56には、PC鋼棒81を挿通するための貫通孔82がそれぞれ穿設されており、端部材53および第2〜第4束部材54〜56は、各凸部53b,54b,55b,56bを上側部材51および下側部材52の対応する凹部51a,52aに係合させた状態で、一本の直線状になった貫通孔82に挿入された緊張材としての複数(ここでは2本)のPC鋼棒81によって一体結合されている。   The upper member 51, the lower member 52, the end member 53, and the second to fourth bundle members 54 to 56 are each provided with a through hole 82 for inserting the PC steel rod 81, and the end member 53 and the second to fourth bundle members 54 to 56 are in a state where the convex portions 53b, 54b, 55b, and 56b are engaged with the corresponding concave portions 51a and 52a of the upper member 51 and the lower member 52, respectively. Are integrally joined by a plurality (two in this case) of PC steel bars 81 as tension members inserted into the straight through-holes 82.

このPCa梁1を製造する手順は以下の通りである。まず、1本の上側部材51を鉄筋コンクリートによりプレキャスト成形するステップと平行して、1本の下側部材52を鉄筋コンクリートによりプレキャスト成形するとともに、端部材53および第2〜第4束部材54〜56を鉄筋コンクリートによりプレキャスト成形する。その後、上側部材51と下側部材52との間に端部材53および第2〜第4束部材54〜56を配置した状態で貫通孔82にPC鋼棒81を挿入し、PC鋼棒81をジャッキなどによって緊張した状態で上下端をそれぞれ上側部材51および下側部材52に係止することにより、端部材53および第2〜第4束部材54〜56を、上側部材51および下側部材52に圧着接合させる。   The procedure for manufacturing the PCa beam 1 is as follows. First, in parallel with the step of precast molding one upper member 51 with reinforced concrete, one lower member 52 is precast molded with reinforced concrete, and the end member 53 and the second to fourth bundle members 54 to 56 are formed. Precast molding with reinforced concrete. Thereafter, the PC steel rod 81 is inserted into the through hole 82 in a state where the end member 53 and the second to fourth bundle members 54 to 56 are disposed between the upper member 51 and the lower member 52, and the PC steel rod 81 is The upper and lower ends are locked to the upper member 51 and the lower member 52 while being tensioned by a jack or the like, so that the end member 53 and the second to fourth bundle members 54 to 56 are connected to the upper member 51 and the lower member 52. Crimp and bond to

PCa梁1がこのように上側部材51および下側部材52だけでなく、束部13〜16を構成する端部材53および第2〜第4束部材54〜56をも別々にプレキャスト成形することにより、各部材51〜56の形状を単純なものとし、鉄筋や型枠の組立、コンクリートの打設を容易にし、開口部21〜24周辺へのコンクリートの充填性を更に高め、品質の確保をさらに容易にしている。また、PCa梁1が複数のプレキャスト部材に分割されることで、部材重量を一層軽減して工場での取り扱いや現場への搬送も一層容易になっている。これらによって生産性が向上し、製造コストの低減も可能となる。   In this way, the PCa beam 1 separately precast-molds not only the upper member 51 and the lower member 52 but also the end member 53 and the second to fourth bundle members 54 to 56 constituting the bundle portions 13 to 16. The shape of each of the members 51 to 56 is simplified, the rebar and formwork assembly and concrete placement are facilitated, the concrete is more easily filled around the openings 21 to 24, and the quality is further secured. Making it easy. Further, since the PCa beam 1 is divided into a plurality of precast members, the weight of the members is further reduced, and handling at the factory and transportation to the site are further facilitated. As a result, productivity is improved and manufacturing costs can be reduced.

また、端部材53および第2〜第4束部材54〜56を、上側部材51および下側部材52にPC鋼棒81で圧着接合することにより、接合作業が容易になり、接合時に養生期間をとる必要もないため、例えば、PC工場で各部材51〜56を製造した後に現場で接合することも可能である。そのため、接合後では運搬や取り扱いが困難となるような大きなPCa梁1であっても、プレキャスト化が可能となる。   In addition, by joining the end member 53 and the second to fourth bundle members 54 to 56 to the upper member 51 and the lower member 52 with the PC steel rod 81, the joining work is facilitated, and the curing period is increased at the time of joining. Since it is not necessary to take it, for example, after manufacturing each member 51-56 in a PC factory, it is also possible to join on-site. Therefore, even a large PCa beam 1 that is difficult to transport and handle after joining can be precast.

<変形例>
次に第5実施形態のPCa梁1に対し、構成および製造方法が一部において相違する変形例について説明する。本変形例のPCa梁1は、図16に示す基本構成を有する上側部材51、下側部材52、端部材53および第2〜第4束部材54〜56によって構成され、これら各部材51〜56を一体化することで製造される。この点については第5実施形態のPCa梁1と同様である。
<Modification>
Next, a modification in which the configuration and the manufacturing method are partially different from those of the PCa beam 1 of the fifth embodiment will be described. The PCa beam 1 of this modification is configured by an upper member 51, a lower member 52, an end member 53, and second to fourth bundle members 54 to 56 having the basic configuration shown in FIG. It is manufactured by integrating. This is the same as the PCa beam 1 of the fifth embodiment.

代表例として第3束部15周辺を示す図18に示すように、本変形例の上側部材51、下側部材52、端部材53および第2〜第4束部材54〜56にも、貫通孔82がそれぞれ穿設されており、端部材53および第2〜第4束部材54〜56は、各凸部53b,54b,55b,56bを上側部材51および下側部材52の対応する凹部51a,52aに係合させた状態で、一本の直線状になった各貫通孔82に鉄筋83を挿入し、さらにこの貫通孔82に充填材としてグラウト84を充填することで、鉄筋83と各部材51〜56とを接合させ、端部材53および第2〜第4束部材54〜56を上側部材51および下側部材52にそれぞれ一体結合させている。   As shown in FIG. 18 showing the periphery of the third bundle portion 15 as a representative example, the upper member 51, the lower member 52, the end member 53 and the second to fourth bundle members 54 to 56 of this modification are also provided with through holes. 82 are respectively drilled, and the end member 53 and the second to fourth bundle members 54 to 56 are respectively provided with the convex portions 53b, 54b, 55b, and 56b corresponding to the concave portions 51a of the upper member 51 and the lower member 52, respectively. Reinforcing bar 83 and each member are inserted by inserting reinforcing bar 83 into each straight through-hole 82 in a state engaged with 52a, and further filling grout 84 as a filler in this through-hole 82. The end member 53 and the second to fourth bundle members 54 to 56 are integrally coupled to the upper member 51 and the lower member 52, respectively.

PCa梁1がこのように複数のプレキャスト部材を一体化することで構成されることにより、型枠の組立や鉄筋の組立、コンクリートの打設を容易にし、大量生産を容易にして生産性を向上し、製造コストの低減を図ることができる。また、鉄筋83およびグラウト84のみで各部材51〜56を接合できるため、接合作業も容易である。   The PCa beam 1 is constructed by integrating a plurality of precast members in this way, facilitating assembly of formwork, rebar assembly, and concrete placement, facilitating mass production and improving productivity. In addition, the manufacturing cost can be reduced. Moreover, since each member 51-56 can be joined only by the reinforcing bar 83 and the grout 84, joining work is also easy.

≪第6実施形態≫
図19(A)に示すように、本実施形態のPCa梁1も、上弦部11の大部分がプレキャスト成形された1本の上側部材51から構成され、下弦部12の大部分がプレキャスト成形された1本の下側部材52から構成される。一方、図19(B)に示すように、上側部材51と下側部材52とを対向配置した状態でコンクリートが打設され、このコンクリートの打設により、端部材53および第2〜第4束部材54〜56がプレキャスト形成されるとともに、上側部材51および下側部材52と端部材53および第2〜第4束部材54〜56とが一体化され、1本のPCa梁1が構成される。
<< Sixth Embodiment >>
As shown in FIG. 19A, the PCa beam 1 of this embodiment is also composed of one upper member 51 in which most of the upper chord portion 11 is precast-molded, and most of the lower chord portion 12 is precast-molded. It is composed of a single lower member 52. On the other hand, as shown in FIG. 19B, concrete is cast with the upper member 51 and the lower member 52 facing each other, and the end member 53 and the second to fourth bundles are placed by the placement of the concrete. The members 54 to 56 are precast formed, and the upper member 51 and the lower member 52, the end member 53, and the second to fourth bundle members 54 to 56 are integrated to form one PCa beam 1. .

つまり、このPCa梁1を製造するには、まず、その下面から束部13〜16の横補強筋43の上側部分43uが突出するように上側部材51をプレキャスト成形するとともに、その上面から束部13〜16の横補強筋43の下側部分43lが突出するように下側部材52をプレキャスト成形する。次に、上側部材51と下側部材52とを並置し、横補強筋43の上側部分43uと横補強筋43の下側部分43lとをオーバーラップさせた状態で束部13〜16の鉄筋すなわち横補強筋43を組み立て、束部13〜16の鉄筋を巻き込むようにコンクリートを打設することにより、束部13〜16をプレキャスト成形する。   That is, in order to manufacture the PCa beam 1, first, the upper member 51 is precast-molded so that the upper portion 43u of the lateral reinforcing bar 43 of the bundle portions 13 to 16 protrudes from the lower surface thereof, and the bundle portion from the upper surface thereof. The lower member 52 is precast-molded so that the lower portion 43l of the 13-16 horizontal reinforcing bars 43 protrudes. Next, the upper member 51 and the lower member 52 are juxtaposed, and the reinforcing bars of the bundle portions 13 to 16 in the state where the upper portion 43u of the lateral reinforcing bar 43 and the lower portion 43l of the lateral reinforcing bar 43 are overlapped, that is, By assembling the lateral reinforcing bars 43 and placing concrete so that the reinforcing bars of the bundle parts 13 to 16 are wound, the bundle parts 13 to 16 are precast-molded.

PCa梁1をこのように製造することにより、束部13〜16をコンクリート打設することで上側部材51および下側部材52を接合できるため、別途の接合作業を不要にすることができる。   By manufacturing the PCa beam 1 in this way, the upper member 51 and the lower member 52 can be joined by placing the bundle portions 13 to 16 into the concrete, so that a separate joining work can be eliminated.

以上で具体的実施形態についての説明を終えるが、本発明はこれらの実施形態に限定されるものではない。各部材の具体的形状や、配置などは、本発明の趣旨を逸脱しない範囲で適宜変更可能である。なお、上記実施形態に示した本発明に係るPCa梁の各構成要素およびPCa梁の各製造ステップは、必ずしも全てが必須ではなく、少なくとも本発明の趣旨を逸脱しない限りにおいて適宜取捨選択することが可能である。   This is the end of the description of specific embodiments, but the present invention is not limited to these embodiments. The specific shape and arrangement of each member can be changed as appropriate without departing from the spirit of the present invention. It should be noted that the constituent elements of the PCa beam and the manufacturing steps of the PCa beam according to the present invention shown in the above embodiment are not necessarily all necessary, and can be appropriately selected as long as they do not depart from the gist of the present invention. Is possible.

1 PCa梁
11 上弦部
12 下弦部
13 第1束部
14 第2束部
15 第3束部
16 第4束部
21 第1開口部
22 第2開口部
23 第3開口部
24 第4開口部
42 横補強筋
61 PC鋼線
62 PC鋼線
DESCRIPTION OF SYMBOLS 1 PCa beam 11 Upper chord part 12 Lower chord part 13 1st bundle part 14 2nd bundle part 15 3rd bundle part 16 4th bundle part 21 1st opening part 22 2nd opening part 23 3rd opening part 24 4th opening part 42 Lateral reinforcement 61 PC steel wire 62 PC steel wire

Claims (6)

建物における一対の大梁に両端が連結され、その上方に構築される床スラブを支持するプレキャスト鉄筋コンクリート梁であって、上弦部と、下弦部と、前記上弦部と前記下弦部とを連結する複数の束部とを有し、前記束部間に梁幅方向に貫通する矩形の開口部が複数形成され、軸方向の端部側における束部長さと開口部長さとの比が軸方向の中央側における束部長さと開口部長さとの比よりも大きく、かつ軸方向の端部側に配置された束部の長さが中央側に配置された束部の長さよりも大きいことを特徴とするプレキャスト鉄筋コンクリート梁。 Both ends to a pair of girders are connected in a building, a pre-cast reinforced concrete beams supporting the floor slab that is built thereabove, and upper chord section, and the lower chord section, a plurality of connecting the lower chord section and the top chord section and a bundle portion, the opening of the rectangular penetrating the beam width direction between the bundle portion is formed with a plurality, the bundle length in the axial direction end portion side and the opening director Satono ratio axial direction at the center side precast reinforced concrete being greater than the length of the bundle length and aperture director Satono ratio much larger than the, and the axial direction of the arranged bundle portion on the end side length beam portion arranged in the center side Beams. 前記下弦部には、PC鋼線によってプレストレスが付与されたことを特徴とする、請求項に記載のプレキャスト鉄筋コンクリート梁。 The precast reinforced concrete beam according to claim 1 , wherein the lower chord portion is prestressed by a PC steel wire. 前記下弦部には、主筋が配置されず、前記PC鋼線を取り囲む横補強筋が配置されたことを特徴とする、請求項に記載のプレキャスト鉄筋コンクリート梁。 The precast reinforced concrete beam according to claim 2 , wherein a main reinforcing bar is not arranged in the lower chord part, and a horizontal reinforcing bar surrounding the PC steel wire is arranged. 前記上弦部、前記下弦部および前記束部は、個別にプレキャスト形成された別部材からなり、前記上弦部、前記下弦部および前記束部を上下方向に貫通する貫通孔に挿入されたPC鋼棒または鉄筋を介して接合/一体化されたことを特徴とする、請求項1〜請求項のいずれか一項に記載のプレキャスト鉄筋コンクリート梁。 The upper chord part, the lower chord part, and the bundle part are made of separate members that are individually precast, and are inserted into through holes that penetrate the upper chord part, the lower chord part, and the bundle part in the vertical direction. The precast reinforced concrete beam according to any one of claims 1 to 3 , wherein the precast reinforced concrete beam is joined / integrated via a reinforcing bar. 請求項1〜請求項4のいずれか一項に記載されたプレキャスト鉄筋コンクリート梁と、前記大梁とを有する床組であって、
前記プレキャスト鉄筋コンクリート梁は、前記端部側の下部斜めに切り欠かれ、前記大梁との間に略三角形の空隙を形成することを特徴とする床組
A floor assembly comprising the precast reinforced concrete beam according to any one of claims 1 to 4 and the girder,
The precast concrete beam is cut at the bottom of the end portions at an angle, the floor assembly, which comprises forming voids substantially triangular between the girders.
前記大梁の側面には架台部が形成され、
前記プレキャスト鉄筋コンクリート梁は、前記上弦部を前記架台部に載置した状態で前記大梁に結合され、
前記上弦部の前記端部側における梁幅が前記中央側における梁幅よりも大きくされたことを特徴とする、請求項に記載の床組
A pedestal is formed on the side of the large beam,
The precast reinforced concrete beam is coupled to the girder in a state where the upper chord part is placed on the gantry part,
The floor assembly according to claim 5 , wherein a beam width on the end side of the upper chord portion is made larger than a beam width on the center side.
JP2010258217A 2010-11-18 2010-11-18 Precast reinforced concrete beam and floor assembly having the same Expired - Fee Related JP5608054B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010258217A JP5608054B2 (en) 2010-11-18 2010-11-18 Precast reinforced concrete beam and floor assembly having the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010258217A JP5608054B2 (en) 2010-11-18 2010-11-18 Precast reinforced concrete beam and floor assembly having the same

Publications (2)

Publication Number Publication Date
JP2012107452A JP2012107452A (en) 2012-06-07
JP5608054B2 true JP5608054B2 (en) 2014-10-15

Family

ID=46493330

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010258217A Expired - Fee Related JP5608054B2 (en) 2010-11-18 2010-11-18 Precast reinforced concrete beam and floor assembly having the same

Country Status (1)

Country Link
JP (1) JP5608054B2 (en)

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57130648A (en) * 1981-02-06 1982-08-13 Nippon Steel Corp Double layered gymnasium
JP2790817B2 (en) * 1988-09-02 1998-08-27 株式会社構建設計研究所 Frame structure
JP2832205B2 (en) * 1990-03-06 1998-12-09 清水建設株式会社 Connection structure of precast concrete beam and precast concrete beam connection
JPH07119500B2 (en) * 1991-11-07 1995-12-20 住友建設株式会社 Joining method for precast concrete members
JP2000054485A (en) * 1998-08-06 2000-02-22 Taisei Corp Haunch plate for column-beam connection of steel structure

Also Published As

Publication number Publication date
JP2012107452A (en) 2012-06-07

Similar Documents

Publication Publication Date Title
KR100971736B1 (en) Shear reinforcement with dual anchorage function each up and down
JP5406563B2 (en) Composite beam, building, and composite beam construction method
WO2011077822A1 (en) Half precast floor plank, and slab construction method using same
CN1821501B (en) Column-beam connection structure of building and connection method thereof
JP2013155514A (en) Pre-stressed concrete truss structure and method for manufacturing the same and form device
JP7158231B2 (en) Composite column, bridge pier using same, construction method
JP2010242390A (en) Joining method and structure of column / beam joint with steel brace
CN102051931B (en) A reinforcement cage and a method for installing the reinforcement cage for densely ribbed composite walls
JP5750246B2 (en) Composite beam, building, and composite beam construction method
KR101458435B1 (en) Half precast concrete column manufacturing method using saddle-type ties and dual hoops and constructing method using the same
KR20110067942A (en) Construction method of arch-shaped compound girder bridge with continuous span
JP6053417B2 (en) Bridge girder and bridge girder construction method
JP7118507B2 (en) Steel reinforced concrete wall pillar building structure
JP7430343B2 (en) Structures and their construction methods
KR20130075995A (en) Lateral supporter, composite concrete column structure having the same, and constructing method thereeof
KR101181160B1 (en) Prestressed precast concrete beam having efficient prestressing anchorage structure
JP6636345B2 (en) RC building and construction method of RC building
JP6574336B2 (en) Steel-framed reinforced concrete columns and buildings using the same
KR100727114B1 (en) Precast Segment for Haro Bridge Fabrication and Haro Bridge Fabrication Method
JP5608054B2 (en) Precast reinforced concrete beam and floor assembly having the same
JP2007254974A (en) Prestressed concrete floor slab bridge with steel / concrete structure using shape steel and construction method of this prestressed concrete floor slab bridge
JP2011089390A (en) Rigid connection structure of corner section
KR101315365B1 (en) Hybrid beam structure
JP5608055B2 (en) Method for manufacturing precast reinforced concrete beams
KR101878762B1 (en) Coupling structure of double type for girder and column capable of reducing girder height

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20130514

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20140114

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20140121

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20140311

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140826

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140829

R150 Certificate of patent or registration of utility model

Ref document number: 5608054

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees