JP5541520B2 - Underground construction - Google Patents

Underground construction Download PDF

Info

Publication number
JP5541520B2
JP5541520B2 JP2010226671A JP2010226671A JP5541520B2 JP 5541520 B2 JP5541520 B2 JP 5541520B2 JP 2010226671 A JP2010226671 A JP 2010226671A JP 2010226671 A JP2010226671 A JP 2010226671A JP 5541520 B2 JP5541520 B2 JP 5541520B2
Authority
JP
Japan
Prior art keywords
floor
construction
basement
pca
constructed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2010226671A
Other languages
Japanese (ja)
Other versions
JP2012077589A (en
Inventor
健太郎 中川
大 島崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP2010226671A priority Critical patent/JP5541520B2/en
Publication of JP2012077589A publication Critical patent/JP2012077589A/en
Application granted granted Critical
Publication of JP5541520B2 publication Critical patent/JP5541520B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は複数階の地下階を有する建物の施工に適用する地下構法に関する。   The present invention relates to an underground construction method applied to the construction of a building having a plurality of floors.

建物の地下階の躯体を施工するための地下構法として、たとえば特許文献1、2に示されるような逆打ち工法が知られている。これは、地盤掘削に先行して仮設の構真柱を建て込んだ後、地盤を段階的に掘削しながら地下階の躯体を上層部から下層部に向かって施工していくものである。   As an underground construction method for constructing a building on the basement floor of a building, for example, a reverse driving method as shown in Patent Documents 1 and 2 is known. In this method, a temporary construction column is built prior to ground excavation, and then the underground structure is constructed from the upper layer to the lower layer while excavating the ground step by step.

特開平6−146303号公報JP-A-6-146303 特許第2964295号公報Japanese Patent No. 2964295

上記従来の逆打ち工法ではH形鋼等の鉄骨による仮設の構真柱を設けることから、そのような仮設工事にかなりの手間と費用を要するものであって必ずしも合理的ではなく、その点で改善の余地を残している。   In the above-described conventional back-strike method, a temporary construction pillar made of a steel frame such as an H-shaped steel is provided, so that such temporary work requires considerable effort and cost, and is not always reasonable. There is room for improvement.

上記事情に鑑み、本発明は仮設の構真柱を用いることなく地下階の躯体を効率的に施工し得る有効適切な地下構法を提供することを目的とする。   In view of the above circumstances, an object of the present invention is to provide an effective and appropriate underground construction method capable of efficiently constructing a basement frame without using a temporary construction stem.

請求項1記載の発明は、複数階の地下階を有する建物の施工に際して、前記地下階のうちの上層部の任意の地下階もしくは地上1階を先行施工階として設定して該先行施工階の躯体をそれよりも下層の地下階の躯体よりも先行施工する地下構法であって、地盤を掘削して基礎底盤を形成した後、前記基礎底盤上に前記先行施工階に達する本設柱としてのPCa柱を自立状態で施工して、該PCa柱の上部に前記先行施工階の躯体を一体に先行施工し、しかる後に、前記先行施工階よりも上層階の躯体を施工しつつ、前記先行施工階の下方において該先行施工階よりも下層の地下階の躯体を前記基礎底盤上からの作業により後行施工することを特徴とする。   In the construction of the first aspect of the present invention, when constructing a building having a plurality of basement floors, an arbitrary basement floor in the upper part of the basement floor or the first floor above the ground is set as a preceding construction floor, It is an underground construction method in which the skeleton is preceded by a lower basement skeleton, and after the foundation is excavated to form the foundation bottom, the main pillar reaches the preceding construction floor on the foundation bottom. The PCa pillar is constructed in a self-supporting state, and the preceding construction floor frame is preliminarily constructed on the upper part of the PCa pillar, and then the preceding construction floor is constructed while the upper floor structure is constructed above the preceding construction floor. In the lower part of the floor, a basement floor structure lower than the preceding construction floor is constructed following the work from the foundation bottom.

請求項2記載の発明は、請求項1記載の地下構法であって、予め製作した所定長さの単位PCa柱を軸方向に連結することにより前記PCa柱を施工することを特徴とする。   The invention according to claim 2 is the underground construction method according to claim 1, characterized in that the PCa pillar is constructed by connecting in advance the unit PCa pillar of a predetermined length manufactured in advance in the axial direction.

請求項3記載の発明は、請求項1または2記載の地下構法であって、前記PCa柱を高強度コンクリートにより形成することを特徴とする。   Invention of Claim 3 is the underground construction method of Claim 1 or 2, Comprising: The said PCa pillar is formed with high-strength concrete.

請求項4記載の発明は、請求項1,2または3記載の地下構法であって、施工対象の建物を地下階の上層部もしくは地上1階に免震階を設定した免震構造建物として、前記免震階を前記先行施工階として設定することを特徴とする。   The invention according to claim 4 is the underground construction method according to claim 1, 2, or 3, wherein the building to be constructed is a base-isolated structure building having a base-isolated floor on the upper part of the basement or the ground floor, The seismic isolation floor is set as the preceding construction floor.

本発明の地下構法によれば、従来一般の逆打ち工法のように仮設の構真柱を施工することなく本設のPCa柱を早期に施工するので、仮設工事を大幅に軽減し得て効率的かつ合理的な施工が可能であり、しかも先行施工階の施工後はそれよりも上層階の施工と下層階の施工とを同時並行作業により実施できるので、建物全体の施工性を大幅に改善し得て工費削減と工期短縮に寄与し得る。
勿論、本設として設置するPCa柱は、仮設の構真柱として使用するH形鋼等の鉄骨に比べて小断面であっても充分な座屈強度を有するものとできるので、水平方向の支保を必要とすることなくそれ自体を充分に安定に自立させることができ、したがって地下階の下層部よりも上層部を先行施工する際の安全性と信頼性を充分に確保することができる。
According to the underground construction method of the present invention, the temporary PCa column is constructed at an early stage without constructing a temporary construction column as in the conventional general reverse driving method, so that the temporary construction can be greatly reduced and the efficiency is improved. The construction of the entire building can be greatly improved since the construction of the upper floor and the construction of the lower floor can be carried out simultaneously and concurrently after the construction of the preceding construction floor. It can contribute to reduction of construction cost and construction period.
Of course, the PCa column installed as a permanent installation can have sufficient buckling strength even if it has a small cross section compared to a steel frame such as H-shaped steel used as a temporary construction true column. Therefore, it is possible to ensure the safety and reliability sufficiently when the upper layer is preceded by the lower layer of the basement.

本発明の地下構法の実施形態を示すもので、施工するべき地下躯体の概略構成を示す図である。The embodiment of the underground construction method of this invention is shown, and is a figure which shows schematic structure of the underground frame which should be constructed. 同、地下躯体の施工手順を示す図である。It is a figure which shows the construction procedure of an underground frame. 同、地下躯体の施工手順を示す図である。It is a figure which shows the construction procedure of an underground frame.

以下、図1〜図3を参照して本発明の実施形態を説明する。
本実施形態が施工対象としている建物は地下3階建ての高層免震構造建物(地上階の階数は任意)であって、図1に示すように地下1階を免震階として地下1階の梁1を下部梁1aと上部梁1bとにより構成し、それらの間に免震装置(積層ゴム)1cを設置するものである。
Embodiments of the present invention will be described below with reference to FIGS.
The building to be constructed in this embodiment is a three-story high-rise base-isolated building (the number of floors on the ground floor is arbitrary). As shown in FIG. The beam 1 is composed of a lower beam 1a and an upper beam 1b, and a seismic isolation device (laminated rubber) 1c is installed between them.

本実施形態の地下構法は上記建物における地下3階から地下1階までの躯体を施工するに際し、免震階である地下1階を先行施工階として設定してその地下1階の梁1を地下2階や地下3階の梁よりも先行施工するものであり、そのために地下各階の本設柱としてのPCa柱(プレキャストコンクリート柱)10を早期に自立状態で施工することを主眼とする。   The underground construction method of this embodiment is to set up the first basement floor, which is a seismic isolation floor, as the preceding construction floor when constructing the building from the third basement floor to the first basement floor in the above-mentioned building. The construction is prior to the beams on the second and third floors, and for that purpose, the main purpose is to construct the PCa pillars (precast concrete pillars) 10 as the main pillars on the respective underground floors in an independent state at an early stage.

すなわち、本実施形態では地下階全体の施工領域を掘削した後、図2(a)に示すように基礎底盤4を通常の手法により施工し、その時点で(b)〜(e)に示すように本設のPCa柱10を自立状態で先行施工する。   That is, in this embodiment, after excavating the construction area of the entire underground floor, as shown in FIG. 2 (a), the foundation bottom 4 is constructed by a normal method, and as shown at (b) to (e) at that time. The pre-construction of the main PCa column 10 is carried out in a self-supporting state.

本実施形態におけるPCa柱10は、所定長さの単位PCa柱10aが軸方向に複数本(図示例では4本)連結されて基礎底盤4から地下1階の下部梁1aに達するものとされ、その全体が地下階の柱として機能して建物完成後はもとより施工段階から充分な座屈強度を有するものである。
なお、本実施形態では各単位PCa柱10aを高強度コンクリートにより形成しており、かつ図1に示しているように各単位PCa柱10aには柱主筋11を予め埋設しておき、その柱主筋11の上端部を若干上方に突出せしめておくとともに、各単位PCa柱10aの下端部には下段のPCa柱10aの柱主筋11の上端部が挿入される鉄筋継手12を予め埋設しておくと良い。
In the present embodiment, the PCa column 10 has a predetermined length of unit PCa columns 10a connected in the axial direction (four in the illustrated example) to reach the lower beam 1a on the first basement floor from the foundation bottom plate 4, The whole functions as a pillar of the underground floor and has sufficient buckling strength from the construction stage as well as after the building is completed.
In the present embodiment, each unit PCa column 10a is formed of high-strength concrete, and as shown in FIG. 1, a column main reinforcement 11 is embedded in each unit PCa column 10a in advance, and the column main reinforcement. 11 is protruded slightly upward, and a reinforcing bar joint 12 into which the upper end of the column main reinforcement 11 of the lower PCa column 10a is inserted is embedded in advance at the lower end of each unit PCa column 10a. good.

また、PCa柱10の中間部には後段で地下階の梁が接合されるものであり、図示例では4本の単位PCa柱10aのうち下から3本目の単位PCa柱10aの上部に対して地下2階の梁2としてのRC梁が接合されるので、その接合位置には梁主筋2aに連結されてその一部となる鉄筋13を予め埋設しておき、かつ接合面にはせん断力伝達のためのコッター14を予め形成しておくと良い。
さらに、最上段の単位PCa柱10aには先行施工階である地下1階の下部梁1aが接合されるので、柱主筋11を上方に大きく突出せしめておくとともにその先端部に定着板を取り付けておいて下部梁1aに対して強固に定着するようにしておくと良い。
In addition, a basement beam is joined to the middle portion of the PCa column 10 at a later stage. In the illustrated example, the four unit PCa columns 10a are connected to the upper part of the third unit PCa column 10a from the bottom. Since the RC beam as the beam 2 on the second basement floor is joined, a reinforcing bar 13 which is connected to the beam main reinforcing bar 2a and becomes a part thereof is embedded in advance at the joining position, and shear force is transmitted to the joining surface. A cotter 14 may be formed in advance.
Further, since the lower beam 1a of the first basement, which is the preceding construction floor, is joined to the uppermost unit PCa column 10a, the column main reinforcing bar 11 is projected largely upward and a fixing plate is attached to the tip thereof. It is preferable to fix firmly to the lower beam 1a.

上記のPCa柱10を基礎底盤4上に立設するためには、図2(a)に示すように、基礎底盤4を施工する際にPCa柱10の立設位置に予めアンカー筋4aを埋設しておく。
なお、基礎底盤4は普通コンクリートによることで通常は充分であるが、少なくともPCa柱10との接合部(たとえば図1にハッチングを付した範囲)には高強度コンクリートを打設してPCa柱10と同等の強度となるようにしておくことが好ましい。
In order to erect the above-mentioned PCa pillar 10 on the foundation bottom board 4, as shown in FIG. 2 (a), when constructing the foundation bottom board 4, the anchor bars 4a are embedded in advance in the standing position of the PCa pillar 10. Keep it.
Although it is usually sufficient that the foundation base 4 is made of ordinary concrete, high-strength concrete is cast at least at the joint with the PCa column 10 (for example, the hatched range in FIG. 1) to form the PCa column 10. It is preferable to have the same strength as the above.

そして、図2(b)〜(e)に示すように4本の単位PCa柱10aを順次連結してPCa柱10全体を自立状態で施工した後、図3(a)に示すように先行施工階である地下1階の下部梁1aをPCa柱10の柱頭部に一体に施工する。
下部梁1aとしては普通コンクリートによるRC梁とすることで充分であるが、PCa柱10との接合部(図1にハッチングで示す範囲)は免震装置1cの設置台としても機能するので、少なくともその部分は高強度コンクリートを用いてPCa柱10と同等の強度とすることが好ましい。
しかる後に、(b)に示すように下部梁1a上に免震装置1cを設置した後、上部梁1bを施工して地下1階の躯体を先行施工する。
And after connecting the four unit PCa pillar 10a sequentially as shown in FIG.2 (b)-(e) and constructing the PCa pillar 10 whole in a self-supporting state, as shown in FIG. The lower beam 1a in the first basement, which is the floor, is integrally constructed on the column head of the PCa column 10.
As the lower beam 1a, it is sufficient to use an RC beam made of ordinary concrete. However, since the joint with the PCa column 10 (range shown by hatching in FIG. 1) also functions as an installation base for the seismic isolation device 1c, at least The portion is preferably made of high strength concrete and has the same strength as the PCa pillar 10.
After that, as shown in (b), after installing the seismic isolation device 1c on the lower beam 1a, the upper beam 1b is constructed and the first floor basement is pre-constructed.

以上で先行施工階としての地下1階の躯体の施工が完了したので、以降はその上層階の躯体である地下1階の柱5を施工していくとともに、それとの同時並行作業により先行施工階よりも下層の地下階の躯体を後行施工する。すなわち基礎底盤4上からの作業により(c)に示すように地下2階の梁2を後行施工し、さらに地下3階の梁や床(図示略)順次施工すれば良い。   Now that the construction of the first floor basement as the preceding construction floor has been completed, the pillar 5 of the first basement, which is the upper floor of the upper floor, will be constructed. Afterwards, the lower basement frame will be installed. That is, the beam 2 on the second basement floor may be constructed as shown in (c) by work from above the foundation bottom board 4, and then the beam and floor (not shown) on the third basement floor may be sequentially constructed.

本実施形態の地下構法によれば、従来一般の逆打ち工法のように仮設の構真柱を施工することなく本設のPCa柱10を早期に施工するので、仮設工事を大幅に軽減し得て効率的かつ合理的な施工が可能であり、しかも先行施工階を施工した後はそれよりも上層階の施工と下層階の施工とを同時並行作業により実施できるので、建物全体の施工性を大幅に改善し得て工費削減と工期短縮に寄与し得る。
勿論、本設として設置するPCa柱10は、仮設の構真柱として使用するH形鋼等の鉄骨に比べて小断面であっても充分な座屈強度を有するものとできるので、水平方向の支保を必要とすることなくそのPCa柱10自体を充分に安定に自立させることができ、したがって地下階の上層部を下層部よりも先行施工する際の安全性と信頼性を充分に確保することができる。
According to the underground construction method of the present embodiment, the temporary PCa column 10 is constructed at an early stage without constructing a temporary construction true pillar as in the conventional reverse driving method, so that the temporary construction can be greatly reduced. The construction of the upper floor and the lower floor can be performed by simultaneous parallel work after the previous construction floor has been constructed. It can greatly improve and can contribute to reduction of construction cost and construction period.
Of course, the PCa column 10 to be installed as a permanent installation can have a sufficient buckling strength even if it has a small cross section compared to a steel frame such as an H-shaped steel used as a temporary construction column. The PCa pillar 10 itself can be made to be sufficiently stable and independent without the need for support, and therefore sufficiently secure safety and reliability when the upper part of the basement is preceded by the lower part. Can do.

なお、上記実施形態のようにPCa柱10を高強度コンクリートにより形成することにより普通コンクリートによる場合に比べて座屈強度をさらに高めることができ、かつ充分な小断面化を図ることができるが、PCa柱10は必ずしも高強度コンクリートによることはなく、普通コンクリートによるPCa柱10によって所望の座屈強度を確保する設計とすることでも良い。   In addition, by forming the PCa pillar 10 with high-strength concrete as in the above embodiment, the buckling strength can be further increased as compared with the case of ordinary concrete, and a sufficiently small cross section can be achieved. The PCa column 10 is not necessarily made of high-strength concrete, and may be designed to ensure a desired buckling strength by the PCa column 10 made of ordinary concrete.

また、PCa柱10を設置する際には、搬入作業や建方工程を考慮して上記実施形態のように所定長さの単位PCa柱10aを順次連結することが現実的であるが、その場合、各単位PCa柱10aの長さやその連結本数は地下階の階高や揚重機の仕様その他の作業条件を考慮して最適に設定すれば良いし、各単位PCa柱10aどうしを接合するための構造や、PCa柱10を基礎底盤4や地下階の梁に対して接合するための構造も任意である。
勿論、PCa柱10は必ずしも単位PCa柱10aの連結により施工することに限るものではなく、地下階の全高がさして大きくないような場合においては、先行施工するべき地下階の全高にわたる長尺のPCa柱10の全体を一括して立設してしまうことも不可能ではない。
Further, when installing the PCa pillars 10, it is practical to sequentially connect the unit PCa pillars 10a having a predetermined length as in the above-described embodiment in consideration of the carrying-in work and the construction process. The length of each unit PCa column 10a and the number of connected units may be optimally set in consideration of the height of the underground floor, the specifications of the hoist and other work conditions, and for joining the unit PCa columns 10a to each other. The structure and the structure for joining the PCa pillar 10 to the foundation bottom 4 and the basement beam are also arbitrary.
Of course, the PCa pillar 10 is not necessarily constructed by connecting the unit PCa pillars 10a. In the case where the total height of the basement floor is not so large, the long PCa over the entire height of the basement floor to be preceded by construction. It is not impossible to stand up the entire column 10 at once.

さらに、上記実施形態では免震階を地下1階とした建物を対象としているのでその地下1階を先行施工階として設定したが、通常は免震階を地上1階とすることが一般的であるので、その場合には先行施工階を地上1階とすることが現実的である。但し、本発明においては必ずしも免震階を先行施工階とすることに限ることはなく、先行施工階は地下階の上層部あるいは地上1階のうちのいずれか任意の階に設定すれば良い。
勿論、本発明の地下構法では複数階の地下階の柱を本設のPCa柱10として早期に施工すれば良いのであって、その限りにおいて本発明は非免震構造の建物の施工に際しても適用可能であることはもとより、建物全体の構造形式は任意であるし、様々な規模、用途の建物を施工する際に広く適用できるものであることは言うまでもない。
Furthermore, since the above embodiment is intended for buildings with the base isolation floor as the first basement floor, the basement first floor is set as the preceding construction floor, but usually the base isolation floor is the first floor above ground. In this case, it is realistic to set the preceding construction floor as the first floor above the ground. However, in the present invention, the seismic isolation floor is not necessarily limited to the preceding construction floor, and the preceding construction floor may be set to any one of the upper part of the basement floor or the first floor above the ground floor.
Of course, in the underground construction method of the present invention, it is only necessary to construct a plurality of basement columns as the main PCa column 10 at an early stage, and so long as the present invention is applied to the construction of a non-base-isolated building. Needless to say, the structural form of the entire building is arbitrary as well as being possible, and it can be widely applied when constructing buildings of various scales and uses.

1 梁(地下1階の躯体)
1a 下部梁
1b 上部梁
1c 免震装置(積層ゴム)
2 梁(地下2階の躯体)
4 基礎底盤
4a アンカー筋
5 柱(上層階の躯体)
10 PCa柱
10a 単位PCa柱
11 柱主筋
12 鉄筋継手
13 鉄筋
14 コッター
1 Liang (basement 1st floor)
1a Lower beam 1b Upper beam 1c Seismic isolation device (laminated rubber)
2 Beams (2nd basement frame)
4 Foundation floor 4a Anchor muscle 5 Pillar (upper frame)
10 PCa column 10a Unit PCa column 11 Column main bar 12 Reinforcement joint 13 Reinforcement 14 Cotter

Claims (4)

複数階の地下階を有する建物の施工に際して、前記地下階のうちの上層部の任意の地下階もしくは地上1階を先行施工階として設定して該先行施工階の躯体をそれよりも下層の地下階の躯体よりも先行施工する地下構法であって、
地盤を掘削して基礎底盤を形成した後、前記基礎底盤上に前記先行施工階に達する本設柱としてのPCa柱を自立状態で施工して、該PCa柱の上部に前記先行施工階の躯体を一体に先行施工し、
しかる後に、前記先行施工階よりも上層階の躯体を施工しつつ、前記先行施工階の下方において該先行施工階よりも下層の地下階の躯体を前記基礎底盤上からの作業により後行施工することを特徴とする地下構法。
When constructing a building having a plurality of basement floors, an arbitrary basement floor in the upper part of the basement floor or the first floor above the ground is set as a preceding construction floor, and the frame of the preceding construction floor is below the basement. It is an underground construction method that precedes the building on the floor,
After excavating the ground to form the foundation bottom, the PCa pillar as the main pillar reaching the preceding construction floor is constructed on the foundation bottom in a self-supporting state, and the frame of the preceding construction floor is formed above the PCa pillar. As a one-piece construction,
After that, while constructing the upper-floor frame from the preceding construction floor, the lower-floor basement floor below the preceding construction floor is constructed downstream from the foundation floor. An underground construction method characterized by that.
請求項1記載の地下構法であって、
予め製作した所定長さの単位PCa柱を軸方向に連結することにより前記PCa柱を施工することを特徴とする地下構法。
The underground construction method according to claim 1,
An underground construction method, wherein the PCa pillar is constructed by connecting in advance the unit PCa pillar having a predetermined length, which is produced in advance.
請求項1または2記載の地下構法であって、
前記PCa柱を高強度コンクリートにより形成することを特徴とする地下構法。
The underground construction method according to claim 1 or 2,
An underground construction method characterized in that the PCa pillar is formed of high-strength concrete.
請求項1,2または3記載の地下構法であって、
施工対象の建物を地下階の上層部もしくは地上1階を免震階とした免震構造建物として、前記免震階を前記先行施工階として設定することを特徴とする地下構法。
The underground construction method according to claim 1, 2, or 3,
A basement construction method characterized in that the building to be constructed is set as a base-isolated structure in which the upper part of the basement floor or the first floor above ground is a base-isolated floor, and the base isolation floor is set as the preceding construction floor.
JP2010226671A 2010-10-06 2010-10-06 Underground construction Active JP5541520B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010226671A JP5541520B2 (en) 2010-10-06 2010-10-06 Underground construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010226671A JP5541520B2 (en) 2010-10-06 2010-10-06 Underground construction

Publications (2)

Publication Number Publication Date
JP2012077589A JP2012077589A (en) 2012-04-19
JP5541520B2 true JP5541520B2 (en) 2014-07-09

Family

ID=46238148

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010226671A Active JP5541520B2 (en) 2010-10-06 2010-10-06 Underground construction

Country Status (1)

Country Link
JP (1) JP5541520B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103590423B (en) * 2013-11-30 2015-11-11 苏州建鑫建设集团有限公司 For the cast-in-place concrete PVC hollow tube wallboard of outer wall of basement

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0688342A (en) * 1992-09-08 1994-03-29 Ohbayashi Corp Constructing method of post
JP2004244982A (en) * 2003-02-17 2004-09-02 Toda Constr Co Ltd Construction method of building
JP4791997B2 (en) * 2007-04-04 2011-10-12 株式会社竹中工務店 Rebuilding method
JP5027752B2 (en) * 2008-07-29 2012-09-19 大成建設株式会社 Construction method of underground floor pillar and underground floor pillar

Also Published As

Publication number Publication date
JP2012077589A (en) 2012-04-19

Similar Documents

Publication Publication Date Title
KR20090094971A (en) Under ground top-down method
JP6166560B2 (en) Extension structure of seismic isolation building
KR100694493B1 (en) Downward construction method capable of using bracket support type temporary structure as working table
JP2016216900A (en) Structure
JP2015025292A (en) Building construction method and building
KR101140378B1 (en) Reinforcement
KR20150138785A (en) Vertical expansion remodeling method of existing building with seperate load path
JP3690437B2 (en) Seismic reinforcement structure for existing buildings
JP2005105531A (en) Foundation structure of building and its construction method
JP4873981B2 (en) Seismic reinforcement structure for existing buildings
JP5711897B2 (en) Seismic strengthening method and seismic strengthening frame for existing buildings
JP5429812B2 (en) Joining structure and method of shaft member and RC member
JP5866689B1 (en) PC lampway building
JP5228862B2 (en) Underground structure, construction method of underground structure
JP5541520B2 (en) Underground construction
JP4976938B2 (en) Seismic reinforcement structure
JP5191191B2 (en) Extension construction method of extension building
JP2006316495A (en) Foundation structure of bridge pier and its construction method
JP7274332B2 (en) junction structure
JP2017218855A (en) Rebuilt-building including existing underground exterior wall
JP5319445B2 (en) Building construction method
JP3116767B2 (en) Existing building seismic isolation structuring method
JP4449595B2 (en) Column-beam joint structure, method for constructing column-beam joint structure, method for constructing underground structure, and building
JP5814400B2 (en) Construction method of precast concrete construction structure and construction method of bulkhead structure of cage hoistway of middle-rise building elevator
JP2018178364A (en) Earthquake reinforcement structure for building and construction method thereof

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20130808

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20140306

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140408

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140423

R150 Certificate of patent or registration of utility model

Ref document number: 5541520

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150