JP4666674B2 - Wall structure with filling material - Google Patents
Wall structure with filling material Download PDFInfo
- Publication number
- JP4666674B2 JP4666674B2 JP2003038127A JP2003038127A JP4666674B2 JP 4666674 B2 JP4666674 B2 JP 4666674B2 JP 2003038127 A JP2003038127 A JP 2003038127A JP 2003038127 A JP2003038127 A JP 2003038127A JP 4666674 B2 JP4666674 B2 JP 4666674B2
- Authority
- JP
- Japan
- Prior art keywords
- wall
- wall body
- filling material
- members
- ground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Revetment (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、砂防ダム、堤防、堰、擁壁、護岸などに用いる中詰材を有する壁体構造物に関するものである。
【0002】
【従来の技術】
この種の先行技術の1例としては、例えば、特開昭62−137311号公報に開示のものがある。
【0003】
前記従来技術は、良い面としては奥深い山奥など施工機械を搬入できず、人力により施工せざるを得ない場合には適しているものと考えられる。しかし、反対にこの従来技術の問題点を示せば、下記のとおりである。ずなわち、▲1▼多数の鋼矢板セグメントを組立て、多数のタイ材の取付けを行う必要があるため、施工が煩雑で、施工期間と施工コストが嵩む場合がある。▲2▼上下の鋼矢板セグメント間の目地が開く場合がある。▲3▼鋼矢板の有する対荷機能の一つである曲げ剛性を有効に活用していない。▲4▼多数の鋼矢板セグメントで壁体を構成するため、壁体としての一体性に欠ける。
【0004】
【特許文献1】
特開昭62−137311号公報
【0005】
また、従来構造の他例として、図1に示す1段タイロッドタイプ(aタイプ)と、図2に示す2段タイロッドタイプ(bタイプ)とがある。
【0006】
図1に示す1段タイロッドタイプ(aタイプ)の内容を説明すると、鋼矢板等の壁体構成部材3を打設などの手段で基礎地盤4に貫入させて、2列の壁体5(図の右側の後部列の壁体は図示を省略する)を構築し、対向する壁体構成部材3の頭部3aの近傍を連結材(タイロッドなどのタイ材)7で互いに連結した後、2列の壁体5の間に中詰材8を充填して長い根入れ長(イ)を有する二重壁構造物を構築するものである。9は水面、19は笠コンクリート(構造物長手方向連結材)である。
【0007】
前記の壁体構造部材3の根入れ長(イ)は、中詰材8側からの土水圧によって壁体構成部材3の下方部が外側に跳ね出されるのを防止するという重要な役目を果たすためのものである。
【0008】
従来より、二重壁における鋼矢板等の壁体構成部材3の基礎地盤4への根入れ長(イ)は、「控え工(タイロッド)式鋼矢板壁構造」における前面鋼矢板壁の根入れ長と同等以上に設定されている。
【0009】
この根入れ長は、次の設計要素に支配される。
▲1▼壁高、▲2▼タイロッド取付点位置(ロ)、▲3▼中詰材8から壁体5に作用する主働土圧及び残留水圧、▲4▼基礎地盤4から壁体5に作用する受働土圧、▲5▼土圧を支配する土の単位体積重量、内部摩擦角及び壁面摩擦角、等である。
【0010】
例えば、基礎地盤4が比較的良質な場合に適用されるフリーアースサポート法による鋼矢板等の壁体構成部材3の根入れ長は、次式で算定される。
【0011】
【式1】
MR/MS≧FS
ここに、
MS:(主働土圧+残留水圧)によるタイロッド取付点(ロ)回りのモーメント
MR:受働土圧によるタイロッド取付点(ロ)回りのモーメント
FS:安全率
なお、ボイリング対策としての根入れ長の方が長い場合には、これを施工根入れ長とすることもある。
【0012】
[1段タイロッドタイプの技術上の問題点]
▲1▼根入れ長(イ)が長くなると、壁体構成部材3の部材長が長くなる。壁体構成部材3の部材長が長くなると、壁体構成部材3の施工現場までの輸送が困難になる場合がある。特に、砂防ダム等のように施工現場が山間部の場合には、このことは大きな問題となる。
【0013】
▲2▼壁体構成部材3の基礎地盤4への根入れ長(イ)が長くなると、基礎地盤4への打設作業が困難となる場合がある。特に、火山地域においては、基礎地盤4の中に噴石が埋没していることが多く、これが障害となって壁体構成部材3の基礎地盤4への打設作業が困難となる。
【0014】
▲3▼壁体構成部材3の部材長が長くなると、狭溢域における壁体構成部材3のハンドリングが困難となる。特に、山間部の狭溢域において砂防ダム等の建設に使用する場合には、ハンドリング中の壁体構成部材3が周辺の樹木に衝突し、樹木に損傷を与えるという問題も発生する。
【0015】
▲4▼壁体構成部材3の基礎地盤4への根入れ長(イ)が長くなると、「打ち伸び」、「打ち縮み」などの施工誤差が生じやすくなる。
【0016】
次に、図2に示す2段タイロッドタイプ(bタイプ)の内容を説明すると、鋼矢板等の壁体構成部材3を所定の安全率の下で、1列の壁体5としての構造安定(部材安定)を確保できるだけ基礎地盤4に根入れ長(イ)だけ根入れさせる。この根入れ長(イ)は中詰材8側からの土水圧によって壁体5の下方部が外側に跳ね出されるのを防止するためのものである。このようにして、2列の壁体5(後方壁体は図を省略する)を構成し、対向する壁体構成部材3の頭部3aの近傍及び下方部(基礎地盤面より上の部分)を連結材7、7a(上段タイロッドと下段タイロッド等のタイ材)で互いに結合した後、2列の壁体5の間に中詰材8を充填して長い根入れ長(イ)を有する二重壁構造体を構築する。
【0017】
ただし、このときの根入れ長(イ)は、他の条件が同じであれば、前記した1段タイロッド(aタイプ)よりも若干短くなる。このような構造物の設計・施工事例はあまりみられないが、「鋼矢板二重壁式締め切り工法、国土開発技術研究センター、pp.57〜59,2001,山海堂」には、2段タイロッド式二重壁構造物における鋼矢板の根入れ長の算定に関し、次のような主旨の記載がある。
【0018】
【式2】
MR/MS≧FS
ここに、
MS:下段タイロッドより下方における(主働土圧+残留水圧)による下段タイロッド取付点回りのモーメント
MR:下段タイロッドより下方における受働土圧による下段タイロッド取付点(ハ)回りのモーメント
FS:安全率
【0019】
[2段タイロッドタイプの技術上の問題点]
2段タイロッドタイプの壁体構成部材3の根入れ長(イ)の長さは、前記の算定法によると、1段タイロッドタイプよりも若干短くなるだけなので、技術上の問題点は、1段タイロッドタイプの場合と同様である。
【0020】
【発明が解決しようとする課題】
前記のとおり、従来のこの種の中詰材を有する壁体構造物にあっては、長い根入れ長を必要とし、鋼矢板等の壁体構成部材の部材長が長く、このため、部材の搬送の問題や基礎地盤への打設時の問題があった。本発明はこれらの点を解消できる中詰材を有する壁体構造物を提案することを目的とする。
【0021】
【課題を解決するための手段】
前記の課題を解決するため、本発明に係る中詰材を有する壁体構造物は、次のように構成する。
【0023】
第1の発明は、多数の第1の壁体構成部材(1)により第1の壁体(10)が構成され、前記第1の壁体(10)と所定間隔(B)だけ隔てた位置に、多数の第2の壁体構成部材(2)により第2の壁体(20)が構成され、前記第1の壁体(10)と前記第2の壁体(20)は、上方部において上方連結材(30)により互いに連結され、前記第1の壁体(10)および第2の壁体(20)はその下方部においてコンクリート基礎からなる第1の下方部支持装置(11)及び第2の下方部支持装置(21)により基礎地盤(110)に1〜2mの根入れ長で固定され、前記第1の壁体(10)と前記第2の壁体(20)の間には中詰材(200)が適宜高さまで配置されていることを特徴とする。
【0025】
第2の発明は、多数の第1の壁体構成部材(1)により第1の壁体(10)が構成され、前記第1の壁体(10)と所定間隔(B)だけ隔てた位置に、多数の第2の壁体構成部材(2)により第2の壁体(20)が構成され、前記第1の壁体(10)の上方部と前記第2の壁体(20)の下方部は、斜め連結材(80)により連結され、前記第1の壁体(10)の下方部と前記第2の壁体(20)の上方部は、斜め連結材(80)により連結され、前記第1の壁体(10)および第2の壁体(20)はその下方部においてコンクリート基礎からなる第1の下方部支持装置(11)及び第2の下方部支持装置(21)により基礎地盤(110)に1〜2mの根入れ長で固定され、前記第1の壁体(10)と前記第2の壁体(20)の間には中詰材(200)が適宜高さまで配置されていることを特徴とする。
【0027】
第3の発明は、第1〜第2のいずれかの発明において、第1の壁体構成部材(1)並びに第2の壁体構成部材(2)の一方又は両方の下端部の法線方向において、溝形鋼からなる第1の壁体構成部材下端部支持装置(13)並びに第2の壁体構成部材下端部支持装置(23)の一方又は両方が配置されていることを特徴とする。
【0028】
第4の発明は、第3の発明において、鋼矢板などの鋼製の第1の壁体構成部材(1)並びに第2の壁体構成部材(2)の一方又は両方の下端部と、溝形鋼からなる第1の壁体構成部材下端部支持装置(13)並びに第2の壁体構成部材下端部支持装置(23)の一方又は両方が連結鋼板(33)を介して溶接接合などの手段により連結されていることを特徴とする。
【0029】
第5の発明は、第1の発明において、中詰材(200)が土砂、石材または改良土などの充填材であることを特徴とする。
【0030】
第6の発明は、第1又は第2の発明において、土砂、石材または改良土などの充填材が層状に配置されて中詰材(200)を形成していることを特徴とする。
【0034】
第7の発明は、第1〜第6の何れかの発明において、第1の壁体(10)並びに第2の壁体(20)の一方又は両方の外側に盛土材(300)が配置されていることを特徴とする。
【0035】
第8の発明は、第1〜3、5〜7の何れかの発明において、第1の壁体構成部材(1)及び/又は第2の壁体構成部材(2)が鋼矢板や鋼管矢板などの部材軸方向両側縁に嵌合継手を有する部材であること特徴とする。
【0036】
第9の発明は、第1〜8の何れかの発明において、上方連結材(30)並びに下方連結材(40)並びに中間連結材(70)並びに斜め連結材(80)の何れか又は全ての連結材の頭部に保護装置(600)が設けられていることを特徴とする。
【0039】
第10の発明は、第1〜9の何れかの発明において、第1の壁体(10)と第2の壁体(20)の上方部が構造物長手方向において、構造物長手方向連結材(1000)と構造物長手方向連結材(2000)により連結されていることを特徴とする。
【0040】
第11の発明は、第10の発明において、構造物長手方向連結材(1000)と構造物長手方向連結材(2000)が構造物長手直角方向において、適宜間隔で配置された多数の断面方向連結材(3000)により連結されていることを特徴とする。
【0041】
第12の発明は、第11の発明において、前記多数の断面方向連結材(3000)が構造物長手方向において、連続的に配置され頂版(3100)を形成していることを特徴とする。
【0042】
第13の発明は、第10〜第12の何れかの発明において、一方の構造物長手方向連結材(2000)の高さが他方の構造物長手方向連結材(1000)の高さよりも高いことを特徴とする。
【0043】
第14の発明は、第1〜13の何れかの発明において、第1の壁体(10)と第2の壁体(20)の一方又は両方が適宜角度で傾斜して配置されていることを特徴とする。
【0044】
第15の発明は、第1又は第2の発明において、前記中詰材(200)を有する壁体構造物が人工的に形成された基礎地盤(1110)に構築されていることを特徴とする。
【0045】
第16の発明は、第15の発明において、前記基礎地盤(1110)は、断面方向の両端部に多数の第3の壁体構成部材(1001)並びに第4の壁体構成部材(1002)から構成された第3の壁体(1010)並びに第4の壁体(1020)が地盤面(100)に配置され、前記第3の壁体(1010)並びに第4の壁体(1020)の間に中詰材(1200)が配置されることにより形成された人工地盤(6000)であることを特徴とする。
【0046】
第17の発明は、第15の発明において、前記基礎地盤(1110)が、前記中詰材(200)を有する壁体構造物であって、上方連結材(1030)が前記第1の壁体(10)及び前記第2の壁体(20)よりも下方に配置されていることを特徴とする。
【0051】
本発明を、図2を援用してさらに説明する。
【0052】
本発明に最も近いタイプは、図2に示す2段タイロッドタイプ(bタイプ)である。このbタイプは、河川における仮締め切り工事での適用を想定した構造物である。そして、壁体5の基礎地盤4への根入れ長(イ)は、前述したとおり下段タイロッド(連結材7a)よりも下の土水圧(主働土圧、残留水圧、受働土圧)による下段タイロッド取付点(ハ)回りのモーメントに対する釣り合いから算定される長さとしている。これは仮設構造物の一つである多段切梁工法における鋼矢板などの壁体構成部材の根入れ長の算定方法を準用したものと推定される。
【0053】
[二重壁構造物の壁体安定に関する考察]
一方、本発明は、二重壁構造物に関する次の考察に基づき案出されたものである。すなわち、二重壁構造物の安定には、大きく分けて、<I>1列の壁体としての部材安定(内部安定)と、<II>二重壁構造物としての全体安定(外部安定)に大別される。
【0054】
<I>1列の壁体としての部材安定(内部安定)
1列の壁体としての部材安定を確保するためには、図2において、壁体5の下方部が中詰材8側からの土水圧によって外側に跳ね出されるのを防止する必要がある。その手段として、以下の方法が考えられる。
【0055】
▲1▼壁体5の根入れ部(イ)に作用する基礎地盤4の受働側抵抗土圧を利用する[従来技術]。
【0056】
▲2▼壁体5の下方部に支持点を設ける。支持点の設置方法には、次の(a)、(b)の2方法がある。
(a)タイ材を設置する。(b)壁体の下方部に余長部を設け、この余長部を基礎地盤中に設けたコンクリート等の経時硬化性材料の中に埋設固定する。
【0057】
▲3▼壁体下方部にタイ材を設置するとともに、壁体の下方部を基礎地盤に根入れさせる。これは、タイ材による抵抗と基礎地盤の抵抗の両方を利用しようとする方法である。このとき、壁体下方部の基礎地盤への根入れ長が長くなるほど基礎地盤による抵抗の分担が増加し、逆に、タイ材による抵抗の分担が小さくなる。すなわち、壁体下方部の外側への跳ね出しに対する抵抗力を定性的にあらわせば、次のようになる。壁体下方部の外側への跳ね出しに対する抵抗力=壁体の根入れ部における基礎地盤の抵抗力+タイ材の抵抗力。したがって、この方法は、さらに、次の(C1)、(C2)の2タイプに分類できる。
【0058】
(C1)壁体下方部の基礎地盤への根入れ長を長くして、タイ材の抵抗力の分担を小さくする[従来技術]。
(C2)壁体下方部の基礎地盤への根入れ長を短くして、タイ材の抵抗力の分担を大きくする。
【0059】
従来技術(aタイプ)である1段タイロッドタイプは、前記▲1▼の方法に対応し、従来技術(bタイプ)である2段タイロッドタイプは、前記▲3▼の(C1)の方法に対応する。本発明は、前記▲2▼及び▲3▼の(C2)に対応するものである。
【0060】
<II>全体安定(外部安定)
壁体構造物を二重壁構造物として完成し、これに土石流等の水平外力が作用した場合の全体安定を確保するための抵抗要素について考察すると、次のとおりである。
【0061】
▲1▼基礎地盤中に壁体下方部が十分に根入れされている場合
抵抗力=中詰材のせん断剛性に基づく抵抗力+壁体の曲げ剛性に基づく抵抗力+基礎地盤の受働側抵抗に基づく抵抗力。
【0062】
▲2▼基礎地盤に壁体下方部が十分に根入れされていないか、根入れ長がゼロの場合抵抗力≒中詰材のせん断剛性に基づく抵抗力
【0063】
従来技術(aタイプ)である1段タイロッドタイプ及び、従来技術である(bタイプ)2段タイロッドタイプは、前記[0061]の▲1▼に対応する。
【0064】
本発明は、壁体の基礎地盤への根入れ長が「無し」またはあっても「かなり短い」ため、前記[0062]の▲2▼に対応する。
【0065】
本発明者は、前記の各事項を検討したうえ、これらの事項を踏まえてさらに研究し、二重壁構造物の安定と壁体の基礎地盤への根入れ長の関係について次のように考えた。
【0066】
壁体構造物が二重壁構造物として完成した場合、その後に作用する土石流等の水平外力に対しては、基礎地盤の支持力に問題がなければ、中詰材のせん断剛性のみでも抵抗することができる。すなわち、中詰材のせん断抵抗に基づく壁体幅の適切な設定により二重壁構造物として成立する。これには、壁体下方部の基礎地盤への根入れは必ずしも必要としない。このとき、壁体は中詰材の形状保持の役目を担えばよい。
【0067】
したがって、中詰材側からの土水圧による壁体下方部の跳ね出し防止のために地盤面近傍にタイ材や下方部支持装置を設置したりすることを前提にすると、壁体下方部の基礎地盤への根入れは、中詰材の漏洩防止と壁体構成部材の施工中の立設安定確保程度でよいと判断できる。具体的には、壁高、地盤強度、施工方法にもよるが、1〜2m前後の根入れ長でよい。
【0068】
また、施工中の壁体構成部材の立設安定状態を確保する措置及び、中詰材の漏洩防止装置を配置する措置を講ずる場合には、壁体下方部の基礎地盤への根入れ長はゼロでもよい。
【0069】
このように、本発明は、「2列の壁体間に中詰材を配置した二重壁構造物は、基礎地盤の支持力に問題がないことを前提にすると、中詰材の漏洩さえなければ構造物として成立するため、基礎地盤への壁体の根入れは必ずしも必要としない」との考えを基本としている。
【0070】
前記の各事項を踏まえて本発明者は請求項1〜19に記載の発明を提案するものである。また、前述において、中詰材による主働土圧の鉛直下向き成分により壁体に押し込み力が作用するとの考えもある。このとき、壁高、地盤条件等にもよるが、1〜2m前後の根入れ長では、部材軸方向の支持力が不足することがある。このようなときの対応策として、請求項13及び14を案出した。
【0071】
【発明の実施の形態】
以下、本発明の実施形態を図1〜図46を参照して順に説明する。また、各実施形態における共通の構成要素には共通符号を付して重複説明を省略する。
【0072】
各図に示す構成は、請求項1〜請求項26に対応する実施形態である。以下の説明では、各請求項の項目を対応させながら各図に示す構造を説明する。また、請求項の項目は、複数の実施形態(つまり、複数の図に示す構成)にまたがって複数の具体的構造例で示すことがある。
【0073】
図3、図4について説明する。図3は、第1実施形態に係る中詰材を有する壁体構造物を示し、請求項1に対応する。同図において、多数の壁体構成部材1により壁体10が構成され、前記壁体10と所定間隔Bだけ隔てた位置に、多数の壁体構成部材2により壁体20が構成され、前記壁体10と前記壁体20の間は、上方部において、多数の上方連結材30により互いに連結されると共に、地盤面100の近傍においては多数の下方連結材40により互いに連結され、前記壁体10と前記壁体20の間には、その間を埋め尽くすように土砂等の中詰材200が配置されている。
【0074】
さらに説明すると、壁体構成部材1、2は、鋼矢板又は鋼管矢板を構造物長手方向に連結して構成される。壁体構成部材1、2が鋼管矢板の場合は、例えば、T字状の鋼製継手と嵌合溝を有する鋼製パイプからなる継手、或いは嵌合溝を有する継手鋼管の鋼製継手同士からなる継手を交互に噛合わせながら構成される。
【0075】
図3の第1実施形態では、壁体構成部材1、2の下端は地盤面100に接しており、基礎地盤110中に進入してはいない。このため壁体10および壁体20の下端と地盤面100の間から中詰材200が漏出することがないように、壁体10および壁体20の下方部には適宜手段により中詰材200の漏洩防止装置が配置される(図3には図示せず)。
【0076】
上方連結材30と下方連結材40は、中詰材200により壁体10および壁体20を外側に押開く力を制御するためのもので、鋼線や棒鋼などの抗張材を両壁体1、2に貫通させた上、任意手段からなる定着部17で固定している。
【0077】
さらに、壁体10、20の上端には、それぞれコンクリート製の笠コンクリート(構造物長手方向連結材)19、29が構築され、各壁体10、20の構造物長手方向連結材19、29の間を中詰材8に対する表面保護層18が配置されている。
【0078】
このようにして本発明の第1実施形態に係る中詰材を有する壁体構造物は、地盤面100と、上方連結材30と下方連結材40で連結された壁体10、20で囲まれる領域に中詰材200を充填して構築されている。したがって、第1実施形態の壁体構造物は、強固な壁体を構成しており、かつ構造物が簡潔で、しかも壁体構成部材1、2も短寸で運搬や取扱いが容易で施工性に優れ、経済的であるなどの優れた作用効果を有している。
【0079】
第1実施形態及び後述の実施形態において、基礎地盤110および地盤面100は、自然状態での地盤面および人為的に造成した地盤面を含む。また、土石流や泥流等不測の水平外力により壁体10、20の一方が抜け上がりそうになった場合の対策として、壁体構成部材の下部と下端部支持装置を連結しておくとよい(図5に示す)。こうすることにより、当該壁体構成部材の下端部支持装置の上部に存在する中詰材200の重量が押さえ荷重として機能するため、壁体構成部材の抜け上がりを防止することができる(詳細は後述する)。
【0080】
図4(a)、(b)、図4は第1実施形態の変形例としての第2、第3実施形態を示し、それぞれ請求項4、5に対応する。つまり、図4(a)の第2実施形態では、図示左側の壁体10の所定の長さを有する余長部(中詰材200の流出防止用根入れ部)12が基礎地盤110に所定長さ進入している。図4(b)の第3実施形態では、図示右側の壁体20の所定の長さを有する余長部22が基礎地盤110に進入している。このように第2、第3実施形態によると、基礎地盤110に進入している壁体10または壁体20は、それだけ基礎地盤110との結合が強固になると共に、基礎地盤110との間に隙間が生じるのを防止することができる。したがって、第2、第3実施形態によると余長部12、22を設けたことで、壁体10または壁体20安定度が一層向上して、壁体構造物の強度向上に寄与すると共に、余長部12、22がある壁体側の下方部に対して中詰材200の漏洩防止装置を不要または簡略化できるとともに、壁体構成部材の施工時における立設安定に寄与する。他の構成は第1実施形態と同じである。
【0081】
図5(a)〜(c)は、第4実施形態を示し、それぞれ請求項6、7に対応する。すなわち、この第4実施形態では、壁体構成部材1、2の一方又は両方(図には壁体構成部材2の例を示す)の下端部の法線方向において、壁体構成部材下端部支持装置23が配置されている。第4実施形態では、下端部支持装置23は、例えば、地盤面100に対して開孔溝を上向きにして配置した溝形鋼で構成されていると共に、壁体構成部材1、2が鋼矢板で構成されており、壁体構成部材1、2の下端が下端部支持装置23の開口溝に当てがわれ、連結鋼板33を介して溶接にて下端部支持装置23に固着されている。すなわち、側面略鈎形の大小の連結鋼板33の下方垂直部が下端部支持装置23の両外側面に当てがわれて溶接31にて固着されていると共に、連結鋼板33の上方垂直部が壁体構成部材(鋼矢板)のウェブ両側面に当てがわれ、その当接部が溶接31されている。
【0082】
第4実施形態によると、壁体構造物の長手方向に伸長する溝形鋼の下端部支持装置13は、その上部に存在する中詰材200の重量を押さえ荷重として機能させることができるため、壁体構成部材の抜け上がりを防止することができる。さらに、中詰材200の漏洩防止部材としても機能する。
【0083】
図6(a)、(b)は、第5、第6実施形態を示し、請求項7に対応する。つまり、この実施形態は、第4実施形態の溝形鋼の下端部支持装置13に代えて中詰材200の漏洩防止装置14、24を設けた例である。図6(a)では、漏洩防止装置14、24を山形鋼(アングル材)で構成した例であり、その垂直部を壁体構成部材1、2の下端部に当てがい、水平部を地盤面に接地させている。壁体構成部材と山形鋼(アングル材)との間の空隙はコンクリートなどの充填材で充填される。
【0084】
図6(b)では、左右の壁体構成部材1、2の間わたって漏洩防止装置14、24として略コ字形を形成するように土木シートを配置して、その水平部を地盤面100に設置し両端の立ち上り部を左右の壁体構成部材1、2の内側面に沿わせ、この土木シートの上側に中詰材200を充填している。
【0085】
このように、図6(a)、(b)の第5、第6実施形態では、山形鋼(アングル材)や土木シートからなる漏洩防止装置14、24により壁体構成部材1、2と基礎地盤110との隙間を密閉でき、中詰材200の漏洩を防止すると共に、基礎地盤110に対しても安定に支持できる。
【0086】
図7(a)、(b)は、第7、第8実施形態を示し、それぞれ請求項3に対応する。この第7、第8実施形態では、前記壁体10および壁体20の下端部が下方部支持装置(コンクリート基礎)11及び下方部支持装置(コンクリート基礎)21により基礎地盤110に固定された例を示す。
【0087】
第7、第8実施形態によると、壁体構成部材1、2の下端部は壁体構造物の長手方向に伸長する下方部支持装置(コンクリート基礎)11及び下方部支持装置(コンクリート基礎)21により基礎地盤110にしっかりと固定されている。また、下方部支持装置(コンクリート基礎)11及び下方部支持装置(コンクリート基礎)21は、中詰材200の漏洩防止装置としても機能する。他の構成は前の実施形態と同じである。
【0088】
図8(a)は、第9実施形態を示し、請求項10に対応する。すなわち、第9実施形態では、土砂、石材または改良土などの充填材200a、200b、200c,200dが層状に配置されて中詰材200を形成している。
【0089】
第9実施形態によると、充填材200a、200b、200c、200dの下部の比重を重くする等その材料を適切に選択・組合わせることにより、安定した壁体構造物を経済的に構築できる。他の構成は前の実施形態と同じである。
【0090】
図8(b)は、第10実施形態を示し、請求項11に対応する。すなわち、第10実施形態では、上方連結材30と下方連結材40の間に少なくとも1段の鋼線や棒鋼などの抗張材からなる中間連結材70が配置されている例を示す。
【0091】
図9(a)は第11実施形態を示す。この第11実施形態では、両壁体10、20がコンクリート基礎からなる下方部支持装置11、21を介して基礎地盤110に設置されており、この壁体構造において、上方連結材30と下方連結材40と中間連結材70に加えて、或いは下方連結材40に変えて下方部支持装置11、21間に地中連結材を配置してもよい(なお、図示を省略する)。
【0092】
第11実施形態によると、上方連結材30と下方連結材40と中間連結材70により、中詰材200により壁体10および壁体20を外側に押開く力をより確実に制御することができ、また、壁体構成部材1、2を小断面化することができ、さらに、コンクリート基礎からなる下部支持装置11、21により基礎地盤110への固着が確実となる。
【0093】
図9(b)は、第12実施形態を示し、請求項17に対応する。すなわち、第12実施形態では、上方連結材30、下方連結材40、中間連結材70の何れか又は全ての連結材と、鋼矢板からなる壁体10、20における1枚おきの壁体構成部材1、2とが、鋼矢板のウエブにおける定着部17で結合され、腹起を使用せずに直接的に連結されている例を示す。この第12実施形態によると腹起を使用しないため構成が簡潔となる。
【0094】
図10(a)、(b)は、第13、第14実施形態を示し、それぞれ先の第12実施形態の変形例を示す。図10(a)の第13実施形態では、先の図5の第4実施形態に関係する。つまり、基礎地盤110を幅広にかつ壁体構造物の長手方向に延長して掘削して左右の壁体10、20にわたってコンクリート基礎の下方部支持装置400を構築する。さらに、壁体下端部支持装置13は、開口溝を上向きにした溝形鋼で構成されていると共に、コンクリート基礎の下方部支持装置400の底面に配置されている。また、壁体構成部材1、2は鋼矢板で構成されており、壁体構成部材1、2の下端が下端部支持装置13の開口溝に当てがわれ、連結鋼板33を介して溶接にて下端部支持装置13に固着されている。この下端部支持装置13を含む壁体構成部材1、2の下端部はコンクリート基礎400の中に埋設されており、強固に基礎地盤110に固定される。
【0095】
図10(b)の第14実施形態は、第13実施形態の変形例で、コンクリート基礎400の中において、両壁体構成部材1、2の間が鋼線や棒鋼などの抗張材からなる下部連結材40で連結された例を示し、この構成によりコンクリート基礎400の強度が一層向上する。
【0096】
図11は、第15実施形態を示す。第15実施形態は、図4に示した第2、第3実施形態の変形例で、壁体構成部材1、2の余長部12、22を基礎地盤110中に貫入させ、さらに中間連結材70を設けた例を示す。この第15実施形態によると、壁体構成部材1、2の余長部12、22を基礎地盤110中に貫入させたこと、中間連結材70を設けたことで、図4に示した第2、3実施形態よりも基礎地盤110への固定度と壁体10、20の強度が一層向上する。
【0097】
図12(a)、(b)は、第16、第17実施形態を示し、それぞれ図10(a)、(b)のコンクリート基礎400に代えて地盤改良部410を構築し、この地盤改良部410に壁体構成部材1、2の余長部12、22を設置した例を示す。
【0098】
図13は第17実施形態を示し、基礎地盤110に直接、壁体構成部材1、2の余長部12、22を設置した例を示す。第17実施形態が先の図11に示した第15実施形態と相違するのは、中間連結材70を省略すると共に、腹起し420を設けた点であり、他の構成は第15実施形態と同じである。
【0099】
図14(a)、(b)は、第19、20実施形態を示し、いずれも請求項3に対応する。すなわち、第19、20実施形態では、壁体構成部材1、2の下端がコンクリートブロックからなる下方部支持装置11、21の内部に設置されている例を示す。図14(a)の第19実施形態ではコンクリートブロックの頭部が基礎地盤110の地盤面100の上方に突出しており、かつ壁体構成部材1、2の下端部がコンクリートブロックの内部に設置され、さらに壁体構成部材1、2の間が下方部連結材40で連結された例を示す。また、図14(b)の第20実施形態ではコンクリートブロック11、21が基礎地盤110中に設置され、したがって壁体構成部材1、2の下方が地盤面100からの余長部12、22を有してコンクリートブロック11、12内部に設置されている例を示す。
【0100】
図15(a)、(b)、(c)は、第21、第22、第23実施形態を示し、いずれも請求項8に対応する。図15(a)、(b)の第21、第22実施形態では、地盤面100と接した壁体構成部材1、2の下端で、かつ壁体10と20の内側面と外側面に接してコンクリートブロックからなる中詰材200の漏洩防止装置14と24が配置されている。また、図15(c)の第23実施形態では、地盤面100と接した壁体構成部材1、2の下端で、かつ壁体10と20の内側面に接して山形鋼(アングル材)からなる中詰材200の漏洩防止装置14と24が配置されている。壁体構成部材と山形鋼との間の空隙はコンクリートなどの充填材で充填される。
【0101】
第21、第22、第23実施形態によっても、壁体10と20からの中詰材200の漏洩防止と、壁体10と20の基礎地盤110への強固な固定が可能となる。
【0102】
図16(a)、(b)は、第24、第25実施形態を示し、いずれも請求項1、3、7に対応する。図16(a)に示す第24実施形態では、壁体構成部材1、2の下端が地盤面100と接していると共に、上方連結材30と下方連結材40は、壁体10と20の内側において腹起し420により固定された例を示している。他の構成は図3(a)に示す第1実施形態と同じである。図16(b)に示す第25実施形態では、壁体構成部材1、2の下端が余長部12、22を有して基礎地盤110に貫入され、地盤面100と接した壁体構成部材1、2の下端が壁体10と20の下方部内側面に接して山形鋼(アングル材)からなる中詰材200の漏洩防止装置14と24が配置されている。壁体構成部材と山形鋼との間の空隙はコンクリートなどの充填材で充填される。
【0103】
図17(a)、(b)は、第26、第27実施形態を示し、それぞれ請求項3に対応する。すなわち、第26、第27実施形態では、基礎地盤110を掘削して下方部支持装置(コンクリート基礎)11及び下方部支持装置(コンクリート基礎)21を構築し、壁体10および壁体20の下端部をコンクリート基礎11、21の底面に達するまで貫入した例を示し、図10(a)、(b)に示す第13、第14実施形態の変形例である。
【0104】
図18(a)は、第28実施形態を示し、図8(a)の第9実施形態の変形例であり、請求項12に対応する。すなわち、第28実施形態では、壁体10、20の余長部12、22が基礎地盤110に貫入され、土砂、石材または改良土などの中詰材200が下から順に改良土200e、土砂200f、改良土200e、土砂200f、改良土200eが5層に配置されて中詰材200を形成している例を示す。
【0105】
第28実施形態によると、土砂200eと改良土200fを多層に配置して中詰材200を形成していることで、安定した壁体構造物を経済的に構築できる。
【0106】
図18(b)は、第29実施形態を示す。この第29実施形態では、基礎地盤110中に壁体10、20の余長部12、22を貫入すると共に、壁体10、20の内側に腹起420を設置した例を示す。
【0107】
図19(a)、(b)は、第30、第31実施形態を示す。この第30実施形態では、壁体10、20下端部を地盤面100に接して設置し、かつ壁体10、20の内側に腹起420を設置した例を示す。同じく第31実施形態では、壁体10、20の余長部12、22を基礎地盤110に貫入し、かつ壁体10、20の内側に腹起420を設置した例を示す。図20(a)、(b)は、図19(b)のa−a断面図で、壁体構成部材1、2を鋼矢板で構成した例を示し、図20(c)は鋼矢板の拡大図である。
【0108】
図21は、第32実施形態を示す。この第32実施形態は、図11の第15実施形態において、中間連結材70の構成を省略したものである。このような構成にすると、壁体構成部材の断面を大きくする必要がある。
【0109】
図22は、第33実施形態を示す。この第33実施形態は、図13の第18実施形態において、中間連結材70の構成を追加したものである。このような構成にすると、壁体構成部材の小断面化が可能となる。
【0110】
図23(a)、(b)は、第34、第35実施形態を示す。この第34、第35実施形態は、図15(a)、(b)に示す第21、22実施形態において、下方連結材40の両端部と壁体10、20との連結部に設ける腹起し420を省略した例を示す。
【0111】
図24は第36実施形態を示す。この第36実施形態は、図17(a)に示す第26実施形態において、上方部連結材30の両端部と壁体10、20との連結部に設ける腹起し420を省略した例を示す。
【0112】
図25、図26、図27は、第37、第38、第39実施形態を示し、請求項15に対応する。すなわち、第37〜第39実施形態では、壁体10と壁体20一方又は両方の外側に盛土材300が配置されている点で共通する。また、各実施形態の差異としては、図25の第37実施形態では、壁体10と壁体20の間にも盛土材300が地盤表面100と同じレベルまで充填されていて、その上の中詰材200が充填され、かつ中詰材200中に下方連結材40が配置されている。
【0113】
図26の第38実施形態では、壁体10と壁体20の間には盛土材300が充填されず、中詰材200が充填され、盛土材300のレベルよ下がった部位において、中詰材200中に下方連結材40が配置されている。
【0114】
図27の第39実施形態では、壁体10と壁体20の間には盛土材300が充填されず、中詰材200が充填され、盛土材300のレベルより下がった部位において、中詰材200の中に下方連結材40が配置されていると共に、さらに、一方の壁体10の外側の盛土材300のレベルが壁体20の外側の盛土材300よりも高レベルに配置されている。
【0115】
第37、第38、第39実施形態によると、盛土材300により壁体構造物の構造的簡易性を確保した上、さらに壁体強度を向上させることができ、土石流等の外力が壁体構造物に作用したときも強力に抵抗でき、壁体強度が要求される場合に適用できる。また、特に、図27に示す左側の盛土材300に植生等を施すことにより修景効果を発揮させることもできる。
【0116】
図28、図29は、第40、第41実施形態を示し、第1〜第39の各実施形態で示した上方連結材30、下方連結材40、中間連結部70等を壁体10、20に定着する定着部17(図28、図29では連結部590として示す)おける保護装置590を示し、請求項18に対応する。
【0117】
図28において、壁体構成部材1、2が鋼矢板である場合(図では、下方連結材40及び壁体構成部材1を例として説明する)において、鋼矢板のフランジ35に開設の孔50に下方連結材40の端部を挿通し、その先端のネジ部にナット51を締結している。さらに、この締結部の外側を閉じるように所定寸法の鋼板からなる連結部材保護装置600が配置され、鋼板の両側部が鋼矢板の両ウェブ(斜面部)34の内側に溶接で固着された例を示す。
【0118】
図29においては、図28の構成に加えて連結部材保護装置600である鋼板と鋼矢板のウェブ34とフランジ35とで囲まれる空間に締結部のナット51が埋るように経時硬化性充填材620を充填した例を示す。
【0119】
図28、図29の連結構造によると、下方連結材40等を壁体構成部材1、2に簡潔かつ確実に連結できると共に、連結部590を保護し、かつ連結部590から中詰材200が漏洩しないように構成できる。
【0120】
図30(a)、(b)、図31は、第42、第43、第44実施形態を示し、請求項2、12に対応する。すなわち、各図には壁体10と壁体20との間に棒鋼、鋼線等の抗張材からなる斜め連結材80が配置されている。図示例では、2本の斜め連結材80がたすき掛に配置され、斜め連結材80の両端部はそれぞれ連結部810を介して壁体構成部材1、2の上下端部に連結され、かつ中詰材200が充填された例が示されている。その他の構成は、図3(a)に示した第1実施形態その他と同じであり、共通要素に共通符号付して説明を省略する。
【0121】
第42、第43、第44実施形態によると、複数本の斜め連結材80により、中詰材200による壁体10、20の外側への膨らみを強固に阻止するとともに、水平方向の耐荷力を飛躍的に向上でき、上方連結材30、下方連結材40、中間連結材70等に代えて用いることができ、またはこれと併用することで壁体強度が一層向上する。
【0122】
図32(a)、(b)は第45実施形態を示し、図33はその変形例として第46実施形態を示し、図34(a)、(b)は、第47実施形態を示し、これらは請求項13に対応する。
【0123】
図32〜図34の第45、第46、第47実施形態では、壁体構成部材1、2の近傍には、H形鋼などからなる荷重伝達用柱部材15、25の一方又は両方が配置され、溶接接合、ボルト接合、コンクリートへの埋設または掛止装置による掛止などの手段により連結または掛止されている(図には溶接手段を示す)。また、荷重伝達用柱部材15、25は、基礎地盤110に所定の長さ根入れされている。
【0124】
さらに詳細には、図32(a)、(b)の第45実施形態では、荷重伝達用柱部材15と25が鋼矢板の壁体構成部材1と2の内側に突出するフランジの背面側に設けた例が示されている。また、図33の第46実施形態では、フランジの内面側に設けた例が示されている。また、図34の第47実施形態では、鋼矢板の壁体構成部材1と2の下端部が溝形鋼からなる下方部支持装置13、23で支持され、H形鋼などからなる荷重伝達用柱部材15と25が下方部支持装置11、21に溶接等で固着された例が示されている(なお、非固着でもよい)。荷重伝達用柱部材15と25は、壁体構造物の長手方向に間隔をあけて配置して構わない。
【0125】
第45、第46、第47実施形態によると、荷重伝達用柱部材15と25は壁体の長手方向に間隔をおいて配置しても十分に荷重伝達機能を発揮し、少ない材料で壁体構造物の安定向上に寄与するものである。
【0126】
図35、図36は第48実施形態を示し、請求項13に対応する。すなわち、第48実施形態では、壁体構成部材1、2の一方又は両方の近傍には、H形鋼などからなる荷重伝達用柱部材15、25が配置され、掛止装置630による掛止手段により掛止されている。さらに詳細には、掛止装置630は2枚の鋼板を間隔をあけて垂直かつ平行に配置し、垂直な辺を鋼矢板からなる壁体構成部材1と2のウェブ内面に当てがい当接部を溶接にて固定し、この掛止装置630の下面にH型鋼からなる荷重伝達用柱部材15の上端を掛止した例を示す。
【0127】
第48実施形態の作用効果は、第45、第46、第47実施形態と同じで、荷重伝達用柱部材15が、壁体に作用する部材軸方向荷重を支持するのに寄与する。
【0128】
図37(a)、(b)は第49実施形態を示し、請求項13に対応する。すなわち、第49実施形態では、壁体構成部材1と2の一方又は両方の近傍には、H形鋼などからなる荷重伝達用柱部材15(他方の荷重伝達用柱部材は省略する)が配置され、壁体構成部材1と2と一体に設けられた例が示されている。すなわち、第49実施形態では、H形鋼からなる荷重伝達用柱部材15の長さ寸法が、鋼矢板の壁体構成部材1と2の長さ寸法よりも長く設けられ、かつ外側に張出す鋼矢板のフランジの内面に沿って配置されている。この荷重伝達用柱部材15の上端部と壁体構成部材1と2の上端部は、荷重伝達用柱部材15の上端の方法が上に出るように配置され、構造物長手方向連結材19に埋設される一方、荷重伝達用柱部材15の下端は、壁体構成部材1と2の下端よりも基礎地盤110中に深く進入している。
【0129】
第49実施形態の作用効果は、第37、第38、第39、第40実施形態と略同じで、荷重伝達用柱部材15が壁体構造物の安定向上に寄与し、かつ構成が簡潔である。
【0130】
図38(a)、(b)、(c)は第50実施形態を示し、請求項14に対応する。すなわち、第50実施形態では、壁体構成部材1と2の一方又は両方が鋼矢板で構成されると共に、壁体構成部材1と2の下部位置において、かつ、壁体構成部材1と2の複数本おきに間隔をおいて、溝部を内向きに配置した鋼矢板に対し、溝部が閉口するように対向部鋼矢板を配置し、両鋼矢板の当接部を溶接にて接合して一体化することにより筒状断面部材16と26を構成した例を示す。
【0131】
図39(a)、(b)は、第51実施形態を示し、請求項21、22に対応する。すなわち、同図においては、壁体10と壁体20の上方部が構造物長手方向において、構造物長手方向連結材1000と構造物延長方向連結材2000により連結されている。また、壁体10と壁体20の上方部が、構造物長手直角方向において、適宜間隔で配置された断面方向連結材3000により連結されている。他の構成は先の実施形態と同じである。すなわち、壁体10および壁体20と下方部支持装置(コンクリート基礎)11および21との結合構造は、図17に示す例と同じであり、また、壁体10および壁体20の横断面構造は図20(a)と同じである。
【0132】
図40(a)、(b)は、第52実施形態を示し、請求項23に対応する。すなわち、同図においては、前記多数の断面方向連結材3000が構造物長手方向において、連続的に配置され頂版3100を形成している。他の構成は第51実施形態と同じである。
【0133】
図41(a)、(b)、図42(a)、(b)は、第53、第54、第55、第56の各実施形態を示し、これらは請求項24に対応する。すなわち、同図においては、一方の構造物長手方向連結材2000の高さが他方の構造物長手方向連結材1000の高さよりも高く設けられている。図42(b)の第56実施形態では、壁体10と壁体20の上方部が、構造物長手直角方向において、適宜間隔で配置された断面方向連結材3000により連結されている。なお、図41(a)における壁体20の上方部は壁体10よりも高く設けてあるのに対し、図41(b)における壁体10と壁体20の上方部は同じ高さに設けた例を示す。また、図43(a)における壁体10と壁体20の下端部は地表面100に位置しているのに対し、図43(b)における壁体10と壁体20の下端の余長部は地中に所定長進入させて設けてある。
(b)
【0134】
図43(a)、(b)、図44(a)、(b)、図45は、第57、第58、第59、第60、第61実施形態を示し、これらは請求項25に対応する。すなわち、同図においては、壁体10と壁体20の下方部が、構造物長手方向においてその底面が傾斜または水平である下方部断面方向連結材5000により、連続的かつ一体的に連結されている。他の構成は先の実施形態と同じである。
【0135】
さらに、図44(a)、(b)、図45の第59、第60、第61実施形態は、請求項26にも対応する。すなわち、同図においては、壁体10と壁体20の一方又は両方が適宜角度で傾斜して配置されている。例えば、図44(a)では、壁体10は垂直であるのに対し、壁体20は上部が外側に所定角度傾斜している。図44(b)では、壁体10と壁体20が平行に一方に所定角度傾斜している。図45では、壁体10と壁体20の下方部がそれぞれ「ハ」の字状に拡がるように所定角度傾斜している。このように壁体10と壁体20の一方又は両方が適宜角度で傾斜して配置されている場合に、壁体10と壁体20を下方部断面方向連結材5000により、連続的かつ一体的に連結することは壁体10と壁体20の拡開を阻止する上で有効に作用する。他の構成は先の実施形態と同じである。
【0136】
図46、図47は、第62、第63実施形態を示し、請求項27、28に対応する。すなわち、同図においては、壁体10と壁体20の間に中詰材200が適宜高さまで配置されている壁体構造物が基礎地盤110に構築され、この基礎地盤110は、断面方向の両端部に多数の壁体構成部材1001、1002から構成された壁体1010、1020が地盤面100に配置され、前記壁体1010、1020の間に中詰材1200が配置されることにより形成された人口地盤6000であることに特徴がある。
【0137】
図46、図47において、壁体1010、1020の上端には構造物長手方向連結材1019、1029が設置されており、中詰材1200の上面には表面保護層1018が設けられている。また、図46の人口地盤6000にあっては、壁体構造物における壁体構成部材1、2の下端は、中詰材1200に所定深さ進入しており、また壁体10と壁体20を連結する下方連結材40は、中詰材200に埋設して設けられている。これに対し、図47の人口地盤6000にあっては、壁体構造物における壁体構成部材1、2の下端は、中詰材1200を貫通して地盤面100に所定深さ進入しており、また壁体10と壁体20を連結する下方連結材40は、中詰材1200に埋設して設けられている。他の構成は、先の各実施形態と同じである。
【0138】
図48は、第64実施形態を示し、請求項27、29に対応する。すなわち、同図においては、基礎地盤(1110)は、断面方向の両端部に多数の壁体構成部材(1001)、(1002)から構成された壁体(1010)、(1020)が地盤面(100)に配置され、前記壁体(1010)、(1020)の間に中詰材(1200)が配置されることにより形成された人口地盤(6000)である。また、同図において、多数の上方連結材(1030)が前記壁体(10)及び前記壁体(20)よりも下方に配置されているものである。他の構成は、先の各実施形態と同じである。
【0139】
なお、本発明において、上方と下方の連結材30、40は少なくとも抗張材の性能を有するものであればよい。したがって、形鋼(H形鋼、溝形鋼)、帯鋼、鋼管などの鋼製部材や化学繊維からなるロープ状部材でもよい。
【0140】
鋼矢板からなる壁体と連結材との間の力の伝達に腹起を使用する場合、これらの部材間の接合仕様の詳細は、例えば、周知の「矢板腹起しの標準設計(案)、港湾技研資料No.363、Dec.1980、運輸省港湾技術研究所」に準じてもよい。
【0141】
腹起を使用しない場合、連結材は1枚おきの壁体構成部材(鋼矢板)毎または各壁体構成部材(鋼矢板)に取付けるものとする。
【0142】
壁体構成部材下端部支持装置13、23同士を溝形鋼等の形鋼で連結してもよい。
【0143】
【発明の効果】
本発明の効果は、次のとおりである。
【0144】
▲1▼長い根入れ長を必要としないので、鋼矢板等の壁体構成部材の部材長が、短くてすむ。このため、部材の搬送の問題や基礎地盤への打設時の問題を解消できる。
【0145】
▲2▼煩雑な施工をする必要がないので、施工期間が短くてすむ。また、高度な施工管理技術も必要とせず、建設コストも安価である。
【0146】
▲3▼地盤条件に起因する「打ち伸び」、「打ち縮み」等の施工誤差が少なく、精度良く壁体構成部材を設置することができる。
【0147】
▲4▼精度良く壁体構成部材を設置することができるので、壁体構成部材に予めタイ材等の連結材を挿通するための孔を開口しておくことができる。これにより、施工期間の短縮と建設コストの縮減を図ることができる。
【0148】
▲5▼壁体構成部材に押し込み力が作用した場合、壁体構成部材の下端部支持装置により荷重が分散されるため、基礎地盤に伝達される荷重の荷重強度を小さくすることができる。
【0149】
▲6▼荷重伝達用柱状部材により、壁体に作用する押し込み力に対して効率的に抵抗することができる。
【0150】
▲7▼二重壁の前面や背面に盛土材を配置することにより、修景効果や土石流や泥流などによる衝撃から構造物の保護効果が得られる。
【図面の簡単な説明】
【図1】1段タイロッドタイプの壁体構造物の説明図である。
【図2】2段タイロッドタイプの壁体構造物の説明図である。
【図3】第1実施形態の説明図である。
【図4】(a)は第2実施形態の説明図、(b)は第3実施形態の説明図である。
【図5】(a)は第4実施形態の説明図、(b)は、(a)の円内の詳細図、(c)は、(b)のロ−ロ断面図である。
【図6】(a)は第5実施形態の説明図、(b)は第6実施形態の説明図である。
【図7】(a)は第7実施形態の説明図、(b)は第8実施形態の説明図である。
【図8】(a)は第9実施形態の説明図、(b)は第10実施形態の説明図である。
【図9】(a)は第11実施形態の説明図、(b)は第12実施形態の説明図である。
【図10】(a)は第13実施形態の説明図、(b)は第14実施形態の説明図である。
【図11】第15実施形態の説明図である。
【図12】(a)は第16実施形態の説明図、(b)は第17実施形態の説明図である。
【図13】第18実施形態の説明図である。
【図14】(a)は第19実施形態の説明図、(b)は第20実施形態の説明図である。
【図15】(a)は第21実施形態の説明図、(b)は第22実施形態の説明図(c)は第23実施形態の説明図である。
【図16】(a)は第24実施形態の説明図、(b)は第25実施形態の説明図である。
【図17】(a)は第26実施形態の説明図、(b)は第27実施形態の説明図である。
【図18】(a)は第28実施形態の説明図、(b)は第29実施形態の説明図である。
【図19】(a)は第30実施形態の説明図、(b)は第31実施形態の説明図である。
【図20】(a)は、図19(b)のa−a断面図、(b)は、壁体の詳細図である。
【図21】第32実施形態の説明図である。
【図22】第33実施形態の説明図である。
【図23】(a)は第34実施形態の説明図、(b)は第35実施形態の説明図である。
【図24】第36実施形態の説明図である。
【図25】第37実施形態の説明図である。
【図26】第38実施形態の説明図である。
【図27】第39実施形態の説明図である。
【図28】(a)は第40実施形態の説明図、(b)は(a)のホ−ホ断面図である。
【図29】第41実施形態の説明図、(b)は(a)のヘ−ヘ断面図である。
【図30】(a)は第42実施形態の説明図、(b)は第43実施形態の説明図である。
【図31】第44実施形態の説明図である。
【図32】(a)は第45実施形態の説明図、(b)は、(a)のト−ト断面図である。
【図33】第46実施形態の説明図である。
【図34】第47実施形態の説明図である。
【図35】第48実施形態の説明図である。
【図36】(a)、(b)は、図35要部の詳細図である。
【図37】(a)は第49実施形態の説明(b)は(a)の拡大横断面図である。
【図38】(a)は、第50実施形態の説明図、(b)は、(a)のチ−チ断面図、(c)は筒状断面部材の詳細図である。
【図39】(a)は、第51実施形態の説明図、(b)は、(a)のリ−リ断面図、(c)は筒状断面部材の詳細図である。
【図40】(a)は、第52実施形態の説明図、(b)は、(a)のヌ−ヌ断面図である。
【図41】(a)は、第53実施形態の説明図、(b)は、第54実施形態の説明図である。
【図42】(a)は、第55実施形態の説明図、(b)は、第56実施形態の説明図である。
【図43】(a)は、第57実施形態の説明図、(b)は、第58実施形態の説明図である。
【図44】(a)は、第59実施形態の説明図、(b)は、第60実施形態の説明図である。
【図45】第61実施形態の説明図である。
【図46】第62実施形態の説明図である。
【図47】第63実施形態の説明図である。
【図48】第64実施形態の説明図である。
【符号の説明】
1 壁体構成部材
2 壁体構成部材
3 壁体構成部材
4 基礎地盤
5 壁体
6 二重壁構造物
7 連結材
7a 連結材
8 中詰材
9 水面
10 壁体
11 下方部支持装置
12 余長部
13 下端部支持装置
14 漏洩防止装置
15 荷重伝達用柱部材
16 筒状断面部材
17 定着部
18 表面保護層
19 笠コンクリート(構造物長手方向連結材)
20 壁体
21 下方部支持装置
22 余長部
23 下端部支持装置
24 漏洩防止装置
25 荷重伝達用柱部材
26 筒状断面部材
29 構造物長手方向連結材
30 上方連結材
31 溶接
33 連結鋼板
40 下方連結材
50 孔
51 ナット
70 中間連結材
80 斜材
100 地盤面
110 基礎地盤
200 中詰材
300 盛土材
400 コンクリート基礎
410 地盤改良部
420 腹起
590 連結部
600 連結部材保護装置
620 経時硬化性充填材
630 掛止装置
810 連結材
1000 構造物長手方向連結材
1001 壁体構成部材
1002 壁体構成部材
1010 壁体
1018 表面保護層
1019 構造物長手方向連結材
1020 壁体
1029 構造物長手方向連結材
1200 中詰材
2000 構造物長手方向連結材
3000 構造物断面方向連結材
3100 頂版
5000 下方部断面方向連結材
6000 人工地盤[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a wall structure having a filling material used for a sabo dam, a bank, a dam, a retaining wall, a revetment and the like.
[0002]
[Prior art]
An example of this type of prior art is disclosed in, for example, Japanese Patent Application Laid-Open No. 62-137311.
[0003]
The above prior art is considered to be suitable when a construction machine such as a deep mountain cannot be carried in as a good aspect and construction is unavoidable. However, on the contrary, the problems of this prior art are as follows. In other words, (1) since it is necessary to assemble a large number of steel sheet pile segments and attach a large number of tie materials, the construction is complicated, and the construction period and construction cost may increase. (2) The joint between the upper and lower steel sheet pile segments may open. (3) The bending rigidity, which is one of the loading functions of steel sheet piles, is not effectively utilized. (4) Since the wall body is composed of a large number of steel sheet pile segments, it lacks unity as a wall body.
[0004]
[Patent Document 1]
JP-A-62-137311
[0005]
As other examples of the conventional structure, there are a one-stage tie rod type (a type) shown in FIG. 1 and a two-stage tie rod type (b type) shown in FIG.
[0006]
The contents of the one-stage tie rod type (a type) shown in FIG. 1 will be described. A wall
[0007]
The length of penetration (a) of the
[0008]
Conventionally, the length (b) of the
[0009]
This penetration length is governed by the following design factors.
(1) Wall height, (2) Tie rod attachment point position (b), (3) Main earth pressure and residual water pressure acting on the wall body 5 from the filling material 8 and (4) Acting on the wall body 5 from the
[0010]
For example, the penetration length of the
[0011]
[Formula 1]
MR/ MS≧ FS
here,
MS: Moment around tie rod attachment point (b) due to (main earth pressure + residual water pressure)
MR: Moment around tie rod attachment point (b) due to passive earth pressure
FS:safety ratio
In addition, when the penetration length as a countermeasure against boiling is longer, this may be set as the construction penetration depth.
[0012]
[Technical problems of single-stage tie rod type]
{Circle around (1)} When the root insertion length (a) is increased, the member length of the
[0013]
{Circle around (2)} If the length of penetration (i) of the
[0014]
{Circle around (3)} When the length of the
[0015]
{Circle around (4)} When the penetration length (i) of the
[0016]
Next, the contents of the two-stage tie rod type (b type) shown in FIG. 2 will be described. The structural stability of the
[0017]
However, the penetration length (a) at this time is slightly shorter than the above-described one-stage tie rod (a type) if the other conditions are the same. Although there are not many examples of design and construction of such structures, “Steel sheet pile double wall type deadline method, National Land Development Technology Research Center, pp. 57-59,2001, Sankai-do” Regarding the calculation of the steel sheet pile penetration length in the double wall structure, there is the following description.
[0018]
[Formula 2]
MR/ MS≧ FS
here,
MS: Moment around the lower tie rod attachment point due to (main earth pressure + residual water pressure) below the lower tie rod
MR: Moment around the lower tie rod attachment point (c) due to passive earth pressure below the lower tie rod
FS:safety ratio
[0019]
[Technical problems of the two-stage tie rod type]
According to the above calculation method, the length of the base material (b) of the two-stage tie rod
[0020]
[Problems to be solved by the invention]
As described above, in the conventional wall structure having this type of filling material, a long penetration length is required, and the length of the wall structure member such as a steel sheet pile is long. There were problems with transportation and when placing on the foundation ground. An object of this invention is to propose the wall body structure which has a filling material which can eliminate these points.
[0021]
[Means for Solving the Problems]
In order to solve the above-mentioned problem, a wall structure having a filling material according to the present invention is configured as follows.
[0023]
In the first invention, the first wall body (10) is constituted by a number of first wall body constituting members (1), and the first wall body (10) is separated from the first wall body (10) by a predetermined distance (B). In addition, the second wall body (20) is constituted by a large number of second wall body constituting members (2), and the first wall body (10) and the second wall body (20) The first wall body (10) and the second wall body (20) are connected to each other by an upper connecting member (30) in the first lower portion supporting device (11) made of a concrete foundation at the lower portion thereof, and Fixed to the foundation ground (110) by a second lower support device (21) with a penetration depth of 1 to 2 m, between the first wall body (10) and the second wall body (20). Is characterized in that the filling material (200) is arranged to a suitable height.
[0025]
In the second invention, the first wall body (10) is constituted by a number of first wall body constituting members (1), and the first wall body (10) is separated from the first wall body (10) by a predetermined distance (B). In addition, the second wall body (20) is constituted by a large number of second wall body constituting members (2), and the upper part of the first wall body (10) and the second wall body (20) The lower part is connected by an oblique connecting member (80), and the lower part of the first wall (10) and the upper part of the second wall (20) are connected by an oblique connecting member (80). The first wall body (10) and the second wall body (20) are formed by a first lower portion support device (11) and a second lower portion support device (21) which are made of a concrete foundation in the lower portion thereof. Fixed to the foundation ground (110) with a penetration depth of 1 to 2 m, and the space between the first wall (10) and the second wall (20) is filled (200) is characterized in that it is arranged to suitably height.
[0027]
A third aspect of the present invention is the normal direction of one or both lower ends of the first wall member (1) and the second wall member (2) in any of the first to second inventions. 1, wherein one or both of the first wall member constituting member lower end supporting device (13) and the second wall member constituting member lower end supporting device (23) made of channel steel are arranged. .
[0028]
4th invention is the groove | channel of 1st or both of 1st wall body structural members (1) and 2nd wall body structural members (2) made from steel, such as a steel sheet pile, in 3rd invention, and a groove | channel. One or both of the first wall body member lower end support device (13) and the second wall body member lower end support device (23) made of section steel are welded or joined via the connecting steel plate (33). It is characterized by being connected by means.
[0029]
The fifth invention is characterized in that, in the first invention, the filling material (200) is a filler such as earth and sand, stone or improved soil.
[0030]
A sixth invention is characterized in that, in the first or second invention, fillers such as earth and sand, stone, or improved soil are arranged in layers to form the filling material (200).
[0034]
According to a seventh invention, in any one of the first to sixth inventions, the embankment material (300) is disposed outside one or both of the first wall body (10) and the second wall body (20). It is characterized by.
[0035]
According to an eighth invention, in any one of the first to third and fifth to seventh inventions, the first wall member (1) and / or the second wall member (2) is a steel sheet pile or a steel pipe sheet pile. It is a member which has a fitting joint in the both-sides edge of member axial directions, such as.
[0036]
According to a ninth invention, in any one of the first to eighth inventions, any or all of the upper connecting member (30), the lower connecting member (40), the intermediate connecting member (70), and the oblique connecting member (80). A protective device (600) is provided on the head of the connecting member.
[0039]
According to a tenth aspect of the present invention, in any one of the first to ninth aspects, the upper portion of the first wall body (10) and the second wall body (20) is in the structure longitudinal direction, and the structure longitudinal direction connecting member (1000) and the structure longitudinal direction connecting material (2000).
[0040]
An eleventh aspect of the invention is the tenth aspect of the invention, wherein the structure longitudinal direction connecting member (1000) and the structure longitudinal direction connecting member (2000) are connected in a number of cross-sectional directions connected at appropriate intervals in the structure longitudinal direction. It is characterized by being connected by a material (3000).
[0041]
The twelfth invention is characterized in that, in the eleventh invention, the plurality of cross-linking members (3000) are continuously arranged in the longitudinal direction of the structure to form a top plate (3100).
[0042]
In a thirteenth aspect of the invention according to any one of the tenth to twelfth aspects of the invention, the height of one structural longitudinal direction connecting member (2000) is higher than the height of the other structural longitudinal direction connecting member (1000). It is characterized by.
[0043]
In a fourteenth invention according to any one of the first to thirteenth inventions, one or both of the first wall body (10) and the second wall body (20) are disposed at an appropriate angle. It is characterized by.
[0044]
A fifteenth aspect of the invention is characterized in that, in the first or second aspect of the invention, the wall structure having the filling material (200) is constructed on an artificially formed foundation ground (1110). .
[0045]
In a sixteenth aspect based on the fifteenth aspect, the foundation ground (1110) includes a plurality of third wall body constituent members (1001) and fourth wall body constituent members (1002) at both ends in the cross-sectional direction. The configured third wall body (1010) and fourth wall body (1020) are disposed on the ground surface (100), and are between the third wall body (1010) and the fourth wall body (1020). It is the artificial ground (6000) formed by disposing the filling material (1200) on the surface.
[0046]
In a seventeenth aspect based on the fifteenth aspect, the foundation ground (1110) is a wall structure having the filling material (200), and the upper connecting member (1030) is the first wall. (10) It is arrange | positioned below the said 2nd wall body (20), It is characterized by the above-mentioned.
[0051]
The invention will be further described with the aid of FIG.
[0052]
The type closest to the present invention is the two-stage tie rod type (b type) shown in FIG. This b type is a structure that is assumed to be used for temporary deadline construction in rivers. And, as described above, the length of penetration (i) of the wall 5 into the
[0053]
[Study on wall stability of double wall structure]
On the other hand, this invention is devised based on the following consideration regarding a double wall structure. That is, the stability of the double wall structure can be broadly divided into <I> member stability as a single-row wall (internal stability), and <II> overall stability as a double wall structure (external stability). It is divided roughly into.
[0054]
<I> Stability of members as a row of walls (internal stability)
In order to ensure the stability of the members as one row of wall bodies, it is necessary to prevent the lower part of the wall body 5 from jumping outward due to the earth water pressure from the filling material 8 side in FIG. As the means, the following method can be considered.
[0055]
{Circle around (1)} Utilizing the passive resistance earth pressure of the
[0056]
(2) A support point is provided at the lower part of the wall body 5. There are the following two methods (a) and (b) for installing the support points.
(A) Install Thai material. (B) An extra length is provided in the lower part of the wall body, and the extra length is embedded and fixed in a time-curable material such as concrete provided in the foundation ground.
[0057]
(3) A tie material is installed at the lower part of the wall body, and the lower part of the wall body is rooted in the foundation ground. This is a method of trying to use both the resistance of the tie material and the resistance of the foundation ground. At this time, as the penetration length of the lower part of the wall body into the foundation ground becomes longer, the share of resistance by the foundation ground increases, and conversely, the share of resistance by the tie material becomes smaller. That is, if the resistance against the outward jumping of the lower part of the wall body is qualitatively expressed, the following is obtained. Resistance to jumping out of the lower part of the wall = resistance of the foundation ground at the base of the wall + resistance of the tie. Therefore, this method can be further classified into the following two types (C1) and (C2).
[0058]
(C1) Extending the penetration length of the lower part of the wall body into the foundation ground to reduce the share of resistance of the tie material [conventional technology].
(C2) Shorten the penetration depth of the lower part of the wall body into the foundation ground to increase the share of resistance of the tie material.
[0059]
The conventional tie rod type (a type) corresponds to the method (1), and the conventional tie rod type (b type) corresponds to the method (C1) (3). To do. The present invention corresponds to the above (2) and (C2) of (3).
[0060]
<II> Overall stability (external stability)
When the wall structure is completed as a double wall structure and the resistance elements for ensuring the overall stability when horizontal external forces such as debris flow are applied to the structure are as follows.
[0061]
(1) When the lower part of the wall is fully embedded in the foundation ground
Resistance = Resistance based on the shear stiffness of the filling material + Resistance based on the bending stiffness of the wall + Resistance based on the passive resistance of the foundation ground.
[0062]
(2) If the lower part of the wall is not fully embedded in the foundation ground, or if the rooting length is zero, the resistance force is equal to the resistance force based on the shear rigidity of the filling material.
[0063]
The prior art (a type) one-stage tie rod type and the prior art (b type) two-stage tie rod type correspond to (1) in [0061] above.
[0064]
The present invention corresponds to (2) of [0062] above because the length of penetration of the wall body into the foundation ground is “none” or even “very short”.
[0065]
The present inventor examined each of the above items, and further studied based on these items, and considered the relationship between the stability of the double wall structure and the penetration depth of the wall body into the foundation ground as follows. It was.
[0066]
When the wall structure is completed as a double wall structure, the horizontal external force such as debris flow that acts afterwards resists only the shear rigidity of the filling material if there is no problem with the supporting force of the foundation ground. be able to. That is, a double wall structure is established by appropriately setting the wall width based on the shear resistance of the filling material. For this, it is not always necessary to insert the lower part of the wall into the foundation ground. At this time, the wall body may serve to maintain the shape of the filling material.
[0067]
Therefore, assuming that a tie material and a lower part support device are installed near the ground surface in order to prevent the lower part of the wall body from jumping out due to earth water pressure from the filling material side, the foundation of the lower part of the wall body It can be determined that the rooting into the ground is sufficient to prevent leakage of the filling material and to ensure standing stability during construction of the wall member. Specifically, although it depends on the wall height, ground strength, and construction method, a penetration depth of about 1 to 2 m may be used.
[0068]
In addition, when taking measures to ensure the standing stability of the wall components during construction and measures to prevent leakage of the filling material, the installation length of the lower part of the wall to the foundation ground is Zero is acceptable.
[0069]
Thus, according to the present invention, "a double wall structure in which the filling material is disposed between the two rows of wall bodies is assumed to have no problem in the bearing capacity of the foundation ground, and even the leakage of the filling material. It is based on the idea that it will not be necessary to have a wall in the foundation ground because it will be established as a structure without it.
[0070]
Based on the above matters, the present inventor proposes the invention described in
[0071]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described in order with reference to FIGS. In addition, common components in the embodiments are denoted by common reference numerals, and redundant description is omitted.
[0072]
The configuration shown in each figure is an embodiment corresponding to
[0073]
3 and 4 will be described. FIG. 3 shows a wall structure having a filling material according to the first embodiment, and corresponds to claim 1. In the drawing, a
[0074]
More specifically, the
[0075]
In the first embodiment of FIG. 3, the lower ends of the
[0076]
The upper connecting
[0077]
Furthermore, the caps concrete (structure longitudinal direction connection material) 19 and 29 made from concrete is each constructed | assembled at the upper end of the
[0078]
In this way, the wall structure having the filling material according to the first embodiment of the present invention is surrounded by the
[0079]
In the first embodiment and the embodiments described later, the
[0080]
4 (a), 4 (b), and 4 show second and third embodiments as modifications of the first embodiment, corresponding to
[0081]
5A to 5C show a fourth embodiment and correspond to
[0082]
According to the fourth embodiment, the lower
[0083]
FIGS. 6A and 6B show fifth and sixth embodiments and correspond to claim 7. That is, this embodiment is an example in which the
[0084]
In FIG. 6 (b), the civil engineering sheet is arranged so as to form a substantially U-shape as the
[0085]
As described above, in the fifth and sixth embodiments shown in FIGS. 6A and 6B, the
[0086]
FIGS. 7A and 7B show seventh and eighth embodiments, respectively, corresponding to the third aspect. In the seventh and eighth embodiments, the lower ends of the
[0087]
According to the seventh and eighth embodiments, the lower ends of the
[0088]
FIG. 8A shows a ninth embodiment and corresponds to claim 10. That is, in the ninth embodiment,
[0089]
According to the ninth embodiment, a stable wall structure can be economically constructed by appropriately selecting and combining the materials such as increasing the specific gravity of the lower portions of the
[0090]
FIG. 8B shows a tenth embodiment and corresponds to claim 11. That is, in the tenth embodiment, an example in which an
[0091]
FIG. 9A shows an eleventh embodiment. In this eleventh embodiment, both
[0092]
According to the eleventh embodiment, the upper connecting
[0093]
FIG. 9B shows a twelfth embodiment and corresponds to claim 17. That is, in the twelfth embodiment, every one or all of the upper connecting
[0094]
FIGS. 10A and 10B show the thirteenth and fourteenth embodiments, respectively, and modifications of the previous twelfth embodiment. The thirteenth embodiment shown in FIG. 10A relates to the fourth embodiment shown in FIG. That is, the lower
[0095]
The fourteenth embodiment of FIG. 10B is a modification of the thirteenth embodiment, and in the
[0096]
FIG. 11 shows a fifteenth embodiment. The fifteenth embodiment is a modification of the second and third embodiments shown in FIG. 4, and the
[0097]
12 (a) and 12 (b) show the sixteenth and seventeenth embodiments, respectively, and a
[0098]
FIG. 13 shows a seventeenth embodiment and shows an example in which the
[0099]
FIGS. 14A and 14B show nineteenth and twentieth embodiments, both of which correspond to the third aspect. That is, in the nineteenth and twentieth embodiments, an example is shown in which the lower ends of the
[0100]
FIGS. 15A, 15B, and 15C show the twenty-first, twenty-second, and twenty-third embodiments, all corresponding to the eighth aspect. In the twenty-first and twenty-second embodiments of FIGS. 15A and 15B, the lower ends of the wall-
[0101]
Also according to the twenty-first, twenty-second, and twenty-third embodiments, it is possible to prevent leakage of the filling
[0102]
FIGS. 16A and 16B show twenty-fourth and twenty-fifth embodiments, both corresponding to
[0103]
FIGS. 17A and 17B show twenty-sixth and twenty-seventh embodiments, respectively, corresponding to the third aspect. That is, in the twenty-sixth and twenty-seventh embodiments, the lower ground support device (concrete foundation) 11 and the lower support device (concrete foundation) 21 are constructed by excavating the
[0104]
FIG. 18A shows the twenty-eighth embodiment, which is a modification of the ninth embodiment of FIG. 8A and corresponds to claim 12. That is, in the twenty-eighth embodiment, the
[0105]
According to the twenty-eighth embodiment, a stable wall structure can be economically constructed by arranging the earth and sand 200e and the improved earth 200f in multiple layers to form the filling
[0106]
FIG. 18B shows a twenty-ninth embodiment. In the 29th embodiment, an example in which the
[0107]
FIGS. 19A and 19B show thirtieth and thirty-first embodiments. The 30th embodiment shows an example in which the lower ends of the
[0108]
FIG. 21 shows a thirty-second embodiment. In the thirty-second embodiment, the configuration of the intermediate connecting
[0109]
FIG. 22 shows a thirty-third embodiment. This 33rd embodiment adds the structure of the intermediate |
[0110]
FIGS. 23A and 23B show the 34th and 35th embodiments. In the thirty-fourth and thirty-fifth embodiments, in the twenty-first and twenty-second embodiments shown in FIGS. 15 (a) and 15 (b), the abdomen provided at the connecting portion between both ends of the lower connecting
[0111]
FIG. 24 shows a thirty-sixth embodiment. The thirty-sixth embodiment shows an example in which, in the twenty-sixth embodiment shown in FIG. 17A, the
[0112]
25, 26, and 27 show the thirty-seventh, thirty-eighth, and thirty-ninth embodiments and correspond to the fifteenth aspect. That is, the thirty-seventh to thirty-ninth embodiments are common in that the
[0113]
In the thirty-eighth embodiment of FIG. 26, the filling
[0114]
In the thirty-ninth embodiment of FIG. 27, the filling
[0115]
According to the thirty-seventh, thirty-eighth and thirty-ninth embodiments, the embedding
[0116]
28 and 29 show the 40th and 41st embodiments, and the upper connecting
[0117]
In FIG. 28, when the
[0118]
In FIG. 29, in addition to the configuration of FIG. 28, the time-curable filler is such that the
[0119]
28 and 29, the lower connecting
[0120]
FIGS. 30A, 30B, and 31 show the forty-second, forty-third, and forty-fourth embodiments, and correspond to
[0121]
According to the forty-second, forty-third, and forty-fourth embodiments, the plurality of
[0122]
FIGS. 32A and 32B show the 45th embodiment, FIG. 33 shows the 46th embodiment as a modification thereof, and FIGS. 34A and 34B show the 47th embodiment. Corresponds to claim 13.
[0123]
In the forty-fifth, forty-sixth and forty-seventh embodiments of FIGS. 32 to 34, one or both of load
[0124]
More specifically, in the forty-fifth embodiment shown in FIGS. 32 (a) and 32 (b), the load
[0125]
According to the forty-fifth, forty-sixth and forty-seventh embodiments, the load
[0126]
35 and 36 show a forty-eighth embodiment and correspond to the thirteenth aspect. That is, in the forty-eighth embodiment, the load
[0127]
The operational effects of the forty-eighth embodiment are the same as those of the forty-fifth, forty-sixth and forty-seventh embodiments, and the load
[0128]
37A and 37B show a 49th embodiment and correspond to the thirteenth aspect. That is, in the forty-ninth embodiment, a load transmitting column member 15 (the other load transmitting column member is omitted) made of H-section steel or the like is disposed in the vicinity of one or both of the
[0129]
The operational effects of the forty-ninth embodiment are substantially the same as those of the thirty-seventh, thirty-eighth, thirty-ninth and forty-fourth embodiments, and the load
[0130]
38 (a), (b), and (c) show a 50th embodiment and correspond to claim 14. That is, in the 50th embodiment, one or both of the wall body
[0131]
39A and 39B show a 51st embodiment and correspond to the 21st and 22nd aspects. That is, in the same figure, the upper part of the
[0132]
FIGS. 40A and 40B show a 52nd embodiment and correspond to the 23rd aspect. In other words, in the drawing, the plurality of
[0133]
41 (a), (b), FIG. 42 (a), and (b) show the 53rd, 54th, 55th, and 56th embodiments, which correspond to the twenty-fourth aspect. That is, in the same figure, the height of one structure longitudinal
(B)
[0134]
43 (a), (b), FIG. 44 (a), (b) and FIG. 45 show the 57th, 58th, 59th, 60th and 61st embodiments, which correspond to claim 25. To do. That is, in the same figure, the lower part of the
[0135]
Furthermore, FIGS. 44 (a), (b), and the 59th, 60th and 61st embodiments of FIG. 45 also correspond to claim 26. In other words, in the figure, one or both of the
[0136]
FIGS. 46 and 47 show the 62nd and 63rd embodiments and correspond to the 27th and 28th aspects. That is, in the figure, a wall structure in which the filling
[0137]
In FIGS. 46 and 47, structure longitudinal
[0138]
FIG. 48 shows a 64th embodiment and corresponds to
[0139]
In the present invention, the upper and lower connecting
[0140]
When using an abduction to transmit force between a wall made of steel sheet piles and a connecting material, details of the specifications for joining these members are, for example, the well-known standard design of a sheet pile wake (draft) , Port Technology Research Document No. 363, Dec. 1980, Port Technology Research Institute, Ministry of Transport.
[0141]
When the belly is not used, the connecting member is attached to every other wall member (steel sheet pile) or to each wall member (steel sheet pile).
[0142]
You may connect wall body structural member lower end
[0143]
【The invention's effect】
The effects of the present invention are as follows.
[0144]
(1) Since a long penetration length is not required, the member length of the wall member constituting member such as a steel sheet pile can be shortened. For this reason, the problem of the conveyance of a member and the problem at the time of placing on a foundation ground can be solved.
[0145]
(2) Since it is not necessary to perform complicated construction, the construction period can be shortened. In addition, advanced construction management technology is not required, and the construction cost is low.
[0146]
(3) Construction errors such as “stretching” and “shrinking” due to the ground conditions are small, and the wall member can be installed with high accuracy.
[0147]
(4) Since the wall member can be installed with high accuracy, a hole for inserting a connecting material such as a tie material into the wall member can be opened in advance. Thereby, shortening of a construction period and reduction of construction cost can be aimed at.
[0148]
(5) When a pushing force is applied to the wall constituting member, the load is dispersed by the lower end support device for the wall constituting member, so that the load strength of the load transmitted to the foundation ground can be reduced.
[0149]
(6) The load-transmitting columnar member can efficiently resist the pushing force acting on the wall body.
[0150]
(7) By placing the embankment material on the front and back of the double wall, it is possible to obtain the effect of landscape protection and the protection of structures from impacts caused by debris flow and mud flow.
[Brief description of the drawings]
BRIEF DESCRIPTION OF DRAWINGS FIG. 1 is an explanatory view of a one-stage tie rod type wall structure.
FIG. 2 is an explanatory view of a two-stage tie rod type wall structure.
FIG. 3 is an explanatory diagram of the first embodiment.
4A is an explanatory diagram of the second embodiment, and FIG. 4B is an explanatory diagram of the third embodiment.
5A is an explanatory view of a fourth embodiment, FIG. 5B is a detailed view inside the circle of FIG. 5A, and FIG. 5C is a cross-sectional view of FIG.
6A is an explanatory diagram of a fifth embodiment, and FIG. 6B is an explanatory diagram of a sixth embodiment.
7A is an explanatory diagram of a seventh embodiment, and FIG. 7B is an explanatory diagram of an eighth embodiment.
8A is an explanatory diagram of a ninth embodiment, and FIG. 8B is an explanatory diagram of a tenth embodiment.
9A is an explanatory diagram of an eleventh embodiment, and FIG. 9B is an explanatory diagram of a twelfth embodiment.
10A is an explanatory diagram of a thirteenth embodiment, and FIG. 10B is an explanatory diagram of a fourteenth embodiment.
FIG. 11 is an explanatory diagram of a fifteenth embodiment.
12A is an explanatory diagram of a sixteenth embodiment, and FIG. 12B is an explanatory diagram of a seventeenth embodiment.
FIG. 13 is an explanatory diagram of an eighteenth embodiment.
14A is an explanatory diagram of a nineteenth embodiment, and FIG. 14B is an explanatory diagram of a twentieth embodiment.
15A is an explanatory diagram of a twenty-first embodiment, FIG. 15B is an explanatory diagram of a twenty-second embodiment, and FIG. 15C is an explanatory diagram of a twenty-third embodiment;
16A is an explanatory diagram of a twenty-fourth embodiment, and FIG. 16B is an explanatory diagram of a twenty-fifth embodiment.
17A is an explanatory diagram of a 26th embodiment, and FIG. 17B is an explanatory diagram of a 27th embodiment.
18A is an explanatory diagram of a twenty-eighth embodiment, and FIG. 18B is an explanatory diagram of a twenty-ninth embodiment.
FIG. 19A is an explanatory diagram of the thirty-first embodiment, and FIG. 19B is an explanatory diagram of the thirty-first embodiment.
20A is a cross-sectional view taken along the line aa of FIG. 19B, and FIG. 20B is a detailed view of the wall body.
FIG. 21 is an explanatory diagram of a thirty-second embodiment.
FIG. 22 is an explanatory diagram of a thirty-third embodiment.
23A is an explanatory diagram of a thirty-fourth embodiment, and FIG. 23B is an explanatory diagram of a thirty-fifth embodiment.
FIG. 24 is an explanatory diagram of a thirty-sixth embodiment.
FIG. 25 is an explanatory diagram of a thirty-seventh embodiment.
FIG. 26 is an explanatory diagram of a thirty-eighth embodiment.
FIG. 27 is an explanatory diagram of a 39th embodiment.
FIG. 28A is an explanatory view of a forty-first embodiment, and FIG. 28B is a sectional view of the hoof of FIG.
FIG. 29 is an explanatory diagram of a forty-first embodiment, and (b) is a sectional view taken along the line (a).
30A is an explanatory diagram of a forty-second embodiment, and FIG. 30B is an explanatory diagram of a forty-third embodiment.
FIG. 31 is an explanatory diagram of the forty-fourth embodiment.
FIG. 32A is an explanatory view of a 45th embodiment, and FIG. 32B is a sectional view of the tote of FIG.
FIG. 33 is an explanatory diagram of a forty-sixth embodiment.
FIG. 34 is an explanatory diagram of a 47th embodiment.
FIG. 35 is an explanatory diagram of a forty-eighth embodiment.
36 (a) and 36 (b) are detailed views of the main part of FIG.
FIG. 37A is an explanation of the 49th embodiment, and FIG. 37B is an enlarged cross-sectional view of FIG.
38 (a) is an explanatory view of a 50th embodiment, FIG. 38 (b) is a cross sectional view of (a), and FIG. 38 (c) is a detailed view of a cylindrical cross sectional member.
39 (a) is an explanatory view of a 51st embodiment, FIG. 39 (b) is a relay sectional view of (a), and FIG. 39 (c) is a detailed view of a cylindrical sectional member.
40A is an explanatory diagram of a 52nd embodiment, and FIG. 40B is a sectional view of the Nuno in FIG. 40A.
41A is an explanatory diagram of a 53rd embodiment, and FIG. 41B is an explanatory diagram of a 54th embodiment.
42A is an explanatory diagram of a 55th embodiment, and FIG. 42B is an explanatory diagram of a 56th embodiment.
43A is an explanatory diagram of a 57th embodiment, and FIG. 43B is an explanatory diagram of a 58th embodiment.
44A is an explanatory diagram of the 59th embodiment, and FIG. 44B is an explanatory diagram of the 60th embodiment. FIG.
45 is an explanatory diagram of the 61st embodiment. FIG.
FIG. 46 is an explanatory diagram of the 62nd embodiment.
FIG. 47 is an explanatory diagram of the 63rd embodiment.
FIG. 48 is an explanatory diagram of the 64th embodiment.
[Explanation of symbols]
1 Wall component
2 Wall components
3 wall components
4 foundation ground
5 walls
6 Double wall structure
7 Connecting materials
7a Connecting material
8 Filling material
9 Water surface
10 Wall
11 Lower part support device
12 Extra length
13 Lower end support device
14 Leakage prevention device
15 Pillar member for load transmission
16 Cylindrical cross-section member
17 Fixing part
18 Surface protective layer
19 Caps concrete (connecting material in the longitudinal direction of the structure)
20 Wall
21 Lower part support device
22 Extra length
23 Lower end support device
24 Leakage prevention device
25 Pillar member for load transmission
26 Cylindrical cross-section member
29 Longitudinal connecting material for structures
30 Upper connecting material
31 Welding
33 Connecting steel plates
40 Lower connecting material
50 holes
51 nuts
70 Intermediate connecting material
80 diagonal
100 Ground surface
110 Foundation ground
200 Filling material
300 Filling material
400 concrete foundation
410 Ground improvement department
420 Upset
590 connecting part
600 Connecting member protection device
620 Time-curing filler
630 latching device
810 connecting material
1000 Longitudinal connecting material for structures
1001 Wall structural members
1002 Wall structural members
1010 Wall
1018 Surface protective layer
1019 Structure longitudinal connector
1020 Wall
1029 Structure longitudinal connector
1200 Filling material
2000 Longitudinal connecting material for structures
3000 Structure cross-sectional connection material
3100 top plate
5000 Lower section cross-section connecting material
6000 artificial ground
Claims (17)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2003038127A JP4666674B2 (en) | 2003-02-17 | 2003-02-17 | Wall structure with filling material |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2003038127A JP4666674B2 (en) | 2003-02-17 | 2003-02-17 | Wall structure with filling material |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2004244983A JP2004244983A (en) | 2004-09-02 |
| JP4666674B2 true JP4666674B2 (en) | 2011-04-06 |
Family
ID=33022733
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2003038127A Expired - Fee Related JP4666674B2 (en) | 2003-02-17 | 2003-02-17 | Wall structure with filling material |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP4666674B2 (en) |
Families Citing this family (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4614928B2 (en) * | 2005-12-26 | 2011-01-19 | 昇 岩▲崎▼ | Lightweight embankment method |
| JP4685809B2 (en) * | 2007-01-26 | 2011-05-18 | 新日本製鐵株式会社 | Wall structure and its construction method |
| JP5445351B2 (en) * | 2010-06-25 | 2014-03-19 | 新日鐵住金株式会社 | Filling reinforcement structure |
| JP5464370B2 (en) * | 2010-12-20 | 2014-04-09 | 新日鐵住金株式会社 | Filling reinforcement structure |
| JP6196901B2 (en) * | 2013-12-20 | 2017-09-13 | 五洋建設株式会社 | Construction methods and structures that reinforce existing structures |
| JP6600582B2 (en) * | 2016-03-02 | 2019-10-30 | 五洋建設株式会社 | Method of forming structure and structure |
| JP7226725B1 (en) | 2022-01-26 | 2023-02-21 | 国立大学法人神戸大学 | Diagonal support pile type sheet pile quay |
Family Cites Families (13)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6040530U (en) * | 1983-08-25 | 1985-03-22 | 住金鋼材工業株式会社 | steel dam |
| JPS62137311A (en) * | 1985-12-09 | 1987-06-20 | Kyosei Gijutsu Kaihatsu Kiko Kk | Construction of steel sheet pile segment double-wall structure |
| GB8602783D0 (en) * | 1986-02-05 | 1986-03-12 | Vidal H | Stabilised earth structures |
| JPH03158516A (en) * | 1989-11-15 | 1991-07-08 | Sabou Jisuberi Gijutsu Center | Hybrid structured debris barrier |
| JPH04302612A (en) * | 1991-03-29 | 1992-10-26 | Nippon Kensetsugiyou Keiei Kyokai | Double sheet pile type cofferdam construction and plate anchor device for deformation inbition of fill-in sand |
| JP2551375Y2 (en) * | 1992-08-07 | 1997-10-22 | 日鐵建材工業株式会社 | Double wall structure |
| JP3363219B2 (en) * | 1993-09-30 | 2003-01-08 | 常太郎 岩淵 | Sabo dam structure |
| JP3270433B2 (en) * | 1998-12-22 | 2002-04-02 | 大和クレス株式会社 | Rooted retaining wall |
| JP3301739B2 (en) * | 1999-07-29 | 2002-07-15 | 中国電力株式会社 | Caisson offshore structure |
| JP2001288726A (en) * | 2000-04-06 | 2001-10-19 | Nkk Corp | Construction method of double sheet pile type harbor civil engineering structure |
| JP2002212930A (en) * | 2001-01-15 | 2002-07-31 | Nippon Steel Corp | Wall structure |
| JP2003013451A (en) * | 2001-07-02 | 2003-01-15 | Sumitomo Metal Ind Ltd | Embankment reinforcement structure |
| JP2003027461A (en) * | 2001-07-16 | 2003-01-29 | Nippon Steel Corp | Double cut-off steel sheet pile wall with oblique tie connection |
-
2003
- 2003-02-17 JP JP2003038127A patent/JP4666674B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JP2004244983A (en) | 2004-09-02 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR102015564B1 (en) | Panel-type retaining wall structure with h-pile and joint device and construction method thereof | |
| KR101274974B1 (en) | Earth retaining wall and construction method thereof | |
| KR101640795B1 (en) | Furlable earth retaining structure for provisional facilities and construction method thereof | |
| US20140270990A1 (en) | Precast concrete retaining wall | |
| KR100776373B1 (en) | Two-column pile blocking method | |
| CN107250460A (en) | Precast Block Retaining Wall Method for Preventing Landslides | |
| KR20200124949A (en) | Anchor Tension way sheathing structure and sheathing method of construction | |
| KR20140013497A (en) | Method for constructing block type reinforced retaining wall in cut site | |
| JP4666674B2 (en) | Wall structure with filling material | |
| CN213571956U (en) | Combined construction method pile supporting structure | |
| KR100633796B1 (en) | Central Reinforced Connection Structure of Temporary Temporary Construction | |
| KR100789209B1 (en) | Block construction using synthetic piles and beams | |
| KR20090057708A (en) | Block structure using two rows of piles | |
| KR102495095B1 (en) | Connecting Beam, Pile using such Connecting Beam, Wall Structure using such Pile, and Constructing Method of such Wall Structure | |
| KR20110051474A (en) | Eco-friendly retaining wall using PA file | |
| KR100842372B1 (en) | Pre-tensioned Soil Nail Method by Top-Down Method | |
| CN216689443U (en) | Domatic mud-rock flow protective structure | |
| KR20230037004A (en) | Retain wall structure | |
| KR101342130B1 (en) | Eco greening and reinforcing facilities for slope of road | |
| CN214401802U (en) | Pile anchor type cover plate foundation pit support structure | |
| KR102194381B1 (en) | Pile for Earth self-retaining wall using double I beam | |
| KR100831332B1 (en) | Underground wall for civil engineering and construction method | |
| KR102195496B1 (en) | Pile for earth self-retaining wall using cast in place concrete pile with double I beam | |
| KR102490872B1 (en) | Reinforced earth retaining wall and construction method using tensile force of steel rod piles | |
| KR101218825B1 (en) | Method of land-side protection wall using bracing |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20051104 |
|
| RD02 | Notification of acceptance of power of attorney |
Free format text: JAPANESE INTERMEDIATE CODE: A7422 Effective date: 20051104 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20051130 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070405 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070410 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070611 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20070611 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20071211 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080212 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20090317 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20090518 |
|
| A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20100511 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20100811 |
|
| A911 | Transfer to examiner for re-examination before appeal (zenchi) |
Free format text: JAPANESE INTERMEDIATE CODE: A911 Effective date: 20100818 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20101214 |
|
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20110108 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140121 Year of fee payment: 3 |
|
| R151 | Written notification of patent or utility model registration |
Ref document number: 4666674 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R151 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140121 Year of fee payment: 3 |
|
| S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140121 Year of fee payment: 3 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| LAPS | Cancellation because of no payment of annual fees |