JP3968652B2 - Fire alarm system - Google Patents

Fire alarm system Download PDF

Info

Publication number
JP3968652B2
JP3968652B2 JP2002285317A JP2002285317A JP3968652B2 JP 3968652 B2 JP3968652 B2 JP 3968652B2 JP 2002285317 A JP2002285317 A JP 2002285317A JP 2002285317 A JP2002285317 A JP 2002285317A JP 3968652 B2 JP3968652 B2 JP 3968652B2
Authority
JP
Japan
Prior art keywords
test
unit
fire
fire detector
panel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2002285317A
Other languages
Japanese (ja)
Other versions
JP2004118805A (en
Inventor
伸二郎 松原
隆治 大内
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nohmi Bosai Ltd
Original Assignee
Nohmi Bosai Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nohmi Bosai Ltd filed Critical Nohmi Bosai Ltd
Priority to JP2002285317A priority Critical patent/JP3968652B2/en
Publication of JP2004118805A publication Critical patent/JP2004118805A/en
Application granted granted Critical
Publication of JP3968652B2 publication Critical patent/JP3968652B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Fire Alarms (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、マンション等の共同住宅の各住戸内に設置された火災感知器を、例えば管理室に設置された共同住宅用火災報知設備を制御する住棟受信機の機能および共同住宅インターホン通話設備を制御する通話制御盤の機能等を含む複合盤から各住戸に設置された住宅情報盤を介して遠隔操作にて動作試験を行う火災報知設備に関するものである。
【0002】
【従来の技術】
近年のマンション等の共同住宅には、火災の発生を監視し、火災が発生した場合はその火災を報知する共同住宅用火災報知設備(以下、「火災報知設備」という)が設けられている。このような火災報知設備は、図10に示すように、共同住宅の管理室等に設置され火災報知設備全体を制御する住棟受信機21と、各住戸内に設置される住宅情報盤22および火災感知器23と、各住戸の玄関先に設置されインターホン通話機能を有するドアホン24とを備えている。なお、25は住棟受信機21とともに管理室等に設置された通話制御盤で、共同住宅の例えば1階に設けられた共同玄関のドアの近傍に設置された共同玄関機26と、各住戸の住宅情報盤22(各住戸のドアホンを介する)とに接続され、共同玄関、各住戸および管理室の通話等のインターホン通話設備を制御している。そして、住棟受信機21等を備えた火災報知設備と通話制御盤25等を備えたインターホン通話設備とともに、共同住宅システム30を構成している。
【0003】
このように構成された共同住宅システム30を有する共同住宅において、各住戸に設置された火災感知器23が火災を感知すると、その旨の信号がドアホン24を介して住宅情報盤22に送られ、この信号を受信した住宅情報盤22は、住人に対して火災感知器23が作動した旨を報知し、住人が火災を確認して住宅情報盤22の確定スイッチを操作すると、住宅情報盤22から火災確定信号が住棟受信機21に出力され、住棟受信機21は共同住宅内、例えば火災確定信号を出力した住宅情報盤22の近隣(同じ階)やその直上階)に設置された住宅情報盤22に火災警報を発動するようになっている。
【0004】
このように、各住戸の火災を感知する火災感知器23は、通常火災の発生を監視しているが、火災発生時に正常に動作することが肝心であるため、定期的に動作試験(点検)を行うことが必要である。この動作試験は、点検作業員が火災感知器1個ずつに対してそれぞれ行うものであるが、火災感知器は住戸内に設置されているため、プライバシーの保護や住人が不在の場合でも定期点検が行えるように、戸外から火災感知器23に対して遠隔操作で行えるようになっている。
【0005】
例えば図10に示したドアホン24は、火災感知器23および住宅情報盤22に接続されているとともに、火災感知器23の動作試験を制御する外部試験器28が接続される試験接続端子(図示せず)および動作試験時と火災監視時との信号経路を切り換える切換接点(図示せず)等を備えている。
このようなドアホン24を用いて戸外から動作試験を行う場合、まず、外部試験器28をある住戸のドアホン24の試験接続端子に接続すると、切換接点が動作試験側に作動され、住戸外のドアホン24を介する火災感知器23と住宅情報盤22との接続が回路的に遮断されるとともに、住戸内の火災感知器23と外部試験器28とが回路的に接続される。ついで、点検作業員は、外部試験器28で個々の火災感知器23に予め付与されているアドレスを指定し、発報指令を送出して火災検出時の諸動作が正常に行われるか否かの動作確認をそれぞれ個別に行う。動作試験終了後、ドアホン24の試験接続端子から外部試験器28を外すと、切換接点は元の状態、つまり火災監視側に作動され、住戸内の火災感知器23と外部試験器28との接続が遮断されるとともに、ドアホン24を介する火災感知器23と住宅情報盤22とが回路的に接続される(例えば、特許文献1参照)。
【0006】
【特許文献1】
特開平11−219490号公報
【0007】
【発明が解決しようとする課題】
上記のような従来の共同住宅システム30は、各住戸のドアホン24に設けられた試験接続端子に外部試験器28を接続し、戸外の外部試験器28から住戸内に設置された火災感知器23に信号を送信して火災感知器23の動作試験を遠隔操作により行うようにしていた。しかしながら、このような戸外からの動作試験は、点検作業員が各住戸の玄関先(ドアホン24)まで足を運び、1軒ずつ行わなければならなかったため、住戸数の多い共同住宅では、場合によっては長期間かかってしまい、大変な作業になってしまうという問題があった。また、戸外からの動作試験は1軒ずつしか行えなかったため、共同住宅の全住戸の火災感知器23に対して一斉に動作試験を行うことができないという問題もあった。さらに、動作試験をやり直したり試験結果を1ヶ所で把握することができないなどの問題もあった。
【0008】
本発明は、上記のような課題を解決するためになされたもので、共同住宅システムにおける共同住宅の各住戸の火災感知器の動作試験を、遠隔操作により一斉または個別にかつ短時間で簡単に行うことのできる火災感知器の遠隔試験システムを備えた火災報知設備を提供することを目的としたものである。
【0009】
【課題を解決するための手段】
本発明に係る火災報知設備は、共同住戸の各住戸にそれぞれ設置された住宅情報盤と、各住戸内にそれぞれ設置され住宅情報盤に接続された火災感知器と、各住戸、管理室および共同玄関における通話および火災感知器からの警報を制御する複合盤とを備えてなり、複合盤に、表示手段と、操作手段と、各住戸の火災感知器の動作試験を遠隔操作により行う遠隔試験制御手段を設け、住宅情報盤に、複合盤との試験開始信号または終了信号および動作試験の結果の信号を含む通信信号を送受信する通信部と、火災感知器に対して動作試験を実行し、動作試験の結果を格納する記憶部を有する試験実行部とを設け、住宅情報盤は、通信部が複合盤からの遠隔試験の指示を受けると、試験実行部が遠隔試験の指示に基づいて火災感知器に対して動作試験を実行して、動作試験の結果を記憶部に格納し、通信部が複合盤から動作試験の結果の送信要求信号を受信すると、記憶部に格納された動作試験の結果を複合盤に送信し、複合盤の遠隔試験制御手段は、操作手段による遠隔試験の指示に基づいて全住戸の火災感知器、指定住戸の火災感知器または指定住戸の指定火災感知器に対し住宅情報盤を介して動作試験を行わせ、住宅情報盤に動作試験の結果の送信要求信号を送信し、住宅情報盤から受信した動作試験の結果を、表示手段に表示させるものである。
【0015】
本発明に係る火災報知設備は、各住戸の住宅情報盤に、住宅情報盤に接続された火災感知器の動作試験を行わせる試験制御手段を設け、試験制御手段は、複合盤から遠隔試験の指示または住宅情報盤に設けられた入力手段による試験入力があったときに、火災感知器の動作試験を行うものである。
【0017】
本発明に係る火災報知設備において、試験制御手段は、複合盤からの遠隔試験の指示または住宅情報盤の入力手段による試験入力とともに、動作試験を行わせる火災感知器の指定があったときに、指定火災感知器に対して動作試験を行うものである。
【0018】
【発明の実施の形態】
図1は本発明が適用される共同住宅システムの構成を示す系統図、図2は本発明の実施の形態の要部のブロック図である。図において、1は共同住宅の各住戸に設けられた住宅情報盤で、共同玄関のドア(図示せず)を解錠させる機能と、自住戸の玄関先のドアホン2、共同玄関および管理室とのインターホン通話機能と、火災、ガス漏れおよび防犯等の警報機能と、自住戸内の火災感知器3の遠隔試験機能等とを備えている。そして、後述する複合盤とは通信制御線L1を、ドアホン2とは通信制御線(通話線)L2を、火災感知器3とは通信制御線(信号線)L3を介して接続されている。
【0019】
4は例えば管理室に設置された複合盤で、共同玄関のドアを解錠させる機能、各住戸、管理室および共同玄関における通話および通信の制御機能等を備えたインターホン通話機能と、各住戸における火災、ガス漏れおよび防犯等の警報機能、各住戸の火災感知器3の遠隔試験制御機能等を備えた火災報知設備とが複合されていて、各住戸の住宅情報盤1、共同玄関に設けられた共同玄関機5および共同住宅の共有部6に通信制御線L1,L5,L6を介して接続されている。
【0020】
また、住宅情報盤1および複合盤4等は、通常、常用電源(図示せず)から電源を得ているが、常用電源から電源供給が絶たれた際には非常電源7から電源を得るようになっている。そして、これらにより共同住宅における共同住宅システム10が構成されている。なお、通信制御線L1およびL5は、解錠時の信号、警報時の信号および遠隔試験時の信号などの制御信号が送受信される制御線と、ドアホン、共同玄関および管理室における通話時の信号および警報時の信号などの音声信号が送受信される通話線を含む。
【0021】
住宅情報盤1は、図2に示すように、複合盤4との通信信号を送受信する通信部11と、住宅情報盤1に接続された火災感知器3(ここでは最大16個まで接続可能)に対して、火災検出時の諸動作が正常に行われるか否かの動作試験を実行する試験実行部12とを備えている。そして、試験実行部12は試験結果を格納する記憶部12aを有している。
【0022】
複合盤4は、図2に示すように、例えばLCDからなる表示部13と、表示部13の画面に表示された操作キーおよび表示部13の近傍に設けられた操作キー等からなり、各住戸の火災感知器3に対して遠隔試験を操作する操作部14と、操作部14の操作に基づいて火災感知器3に対して遠隔試験の開始または終了、全住戸、住戸単位または感知器単位のいずれかの遠隔試験の指示の設定、あるいは、試験結果の要求の有無などを設定する遠隔試験制御手段である試験設定部15と、試験設定部15の設定に基づいて試験開始信号または終了信号、試験結果要求信号および住宅情報盤1からの試験結果信号等の通信信号を送受信する遠隔試験制御手段である試験通信制御部16と、試験設定部15の設定に基づいて表示部13への表示を制御するとともに、試験通信制御部16からの試験結果に基づいて表示部13への表示を制御する遠隔試験制御手段である表示制御部17とを備えている。
【0023】
なお、試験設定部15により設定される全住戸とは、共同住宅の全住戸の火災感知器3に対して一斉に遠隔試験を行う場合で、住戸単位は、指定する住戸の火災感知器3に対して遠隔試験を行う場合だけでなく、複数棟ある共同住宅のいずれかの棟の火災感知器3あるいはある棟の1つのフロアの火災感知器3に対して遠隔試験を行う場合などを含み、感知器単位は、指定住戸の指定火災感知器3に対して遠隔試験を行う場合である。また、表示制御部17は、遠隔試験制御手段に含まれなくてもよい。
【0024】
そして、住宅情報盤1、火災感知器3および複合盤4により、火災感知器3の遠隔試験システムが構成される。
【0025】
次に、このように構成された共同住宅システム10における火災感知器3の遠隔試験システムの作用について、図3のフローチャートを用いて説明する。
通常、火災感知器3により火災発生の監視を行っている火災監視モードの共同住宅システム10において(S1)、その複合盤4の操作部14により表示部13に表示されている遠隔試験モードを選択すると(S2)、共同住宅システム10は遠隔試験モードになり、表示部13に図4に示す画面が表示され、火災感知器3に対する遠隔試験を全住戸、住戸単位または感知器単位のいずれかにおいて実施するかを操作部14により選択する(S3,S10,S18)。
【0026】
例えば表示部13に表示された図4に示す画面において、「全住戸」が選択されて「実行」キーが操作されると、複合盤4の試験設定部15は、操作部14の操作に基づいて遠隔試験を全住戸の火災感知器3に対して一斉に行う全住戸試験を実施することを設定し(S3)、その設定に基づいて試験通信制御部16は複合盤4から全住戸の各住宅情報盤1に通信信号である試験開始信号を送信する(S4)。このとき、表示部13は表示制御部17により全住戸試験用画面が表示される。ついで、各住宅情報盤1の通信部11が複合盤4からの試験開始信号を受信すると、各住宅情報盤1の試験実行部12は信号線L3を介して接続されている火災感知器3に対して動作試験をそれぞれ行い、その結果を試験実行部12に設けられた記憶部12aに格納する(S5)。そして、複合盤4の試験通信制御部16により複合盤4から各住戸の住宅情報盤1に試験結果の送信要求信号を送信すると(S6)、各住宅情報盤1の通信部11は試験実行部12の記憶部12aに格納された試験結果を複合盤4に送信し(S7)、複合盤4は試験通信制御部16により受信した試験結果を、図5に示すように、表示制御部17を介して表示部13に表示させる(S8)。
【0027】
ここで、火災感知器3の試験動作について簡単に説明する。住宅情報盤1から自己を指定された試験を開始する信号を受信したときに、その火災感知器3は自己の火災検出機能のチェックを行う。そして、その結果が正常であれば正常信号を、正常でなければ異常信号を住宅情報盤1の返信する。なお、火災感知器3の試験動作については、住宅情報盤1からの信号によって起動する方式でなく、検出出力の経時的監視、いわゆる定常値監視によって自己の検出機能をチェックして、住宅情報盤1から試験の信号を受信するときに、その定常値監視の結果から正常信号または異常信号を返送することも可能である。
また、火災感知器3は図示しないが動作表示灯が設けられていて、火災感知器3が自己の火災検出機能をチェックした結果が正常な場合、動作表示灯を所定時間点灯することで、外観的に火災感知器3が正常であることを確認できる。これによって、特定の火災感知器3を見ながらそれを含む遠隔試験を行って、その火災感知器3の動作表示灯が点灯しなければ、その火災感知器3が異常であることがわかる。
【0028】
複合盤4は、全住戸からの試験結果を受信すると、住宅情報盤1に試験終了信号を送信して(S9)、全住戸の各住宅情報盤1、火災感知器3および複合盤4に対する遠隔試験モードを解除し、共同住宅システム10を火災監視モードに戻すとともに、表示制御部17を介して表示部13に通常の火災発生監視画面を表示させる。
【0029】
また、例えば表示部13に表示された図4に示す画面において、「住戸単位」が選択されて「実行」キーが操作され、図6に示す画面において「試験住戸番号」が選択されて「実行」キーが操作されると、複合盤4の試験設定部15は、操作部14の操作に基づいて遠隔試験を指定住戸の火災感知器3に対して行う住戸単位試験を実施することを設定し(S10)、その設定に基づいて試験通信制御部16は複合盤4から指定住戸の住宅情報盤1に試験開始信号を送信する(S11)。このとき、表示部13は表示制御部17により住戸単位試験用画面が表示される。ここで、住戸の指定は、予め決められている住戸番号を用いることができる。なお、各住宅情報盤1に住戸番号とは無関係に個別のアドレスが付与されている場合は、そのアドレスを指定するようにしてもよい。このとき、表示部13は表示制御部17により住戸単位試験用画面が表示される。ついで、指定住戸の住宅情報盤1の通信部11が複合盤4からの試験開始信号を受信すると、住宅情報盤1の試験実行部12はその住宅情報盤1に接続されている各火災感知器3に対して動作試験を行い、その結果を試験実行部12に設けられた記憶部12aに格納する(S12)。そして、複合盤4の試験通信制御部16により複合盤4から指定住戸の住宅情報盤1に試験結果の送信要求信号を送信すると(S13)、指定住戸の住宅情報盤1の通信部11は試験実行部12の記憶部12aに格納された試験結果を複合盤4に送信し(S14)、複合盤4は試験通信制御部16により受信した指定住戸の試験結果を、図7に示すように、表示制御部17を介して表示部13に表示させる(S15)。
【0030】
複合盤4は、指定住戸からの試験結果を受信すると、試験設定部15により操作部14による他の住戸に対する遠隔試験を実施するかの操作に基づく住戸単位の試験続行または終了を設定し(S16)、他の住戸の試験続行が設定された場合は上述のステップS11に戻る。他の住戸の遠隔試験が続行されない場合、つまり住戸単位の遠隔試験を終了する場合は、指定住戸の住宅情報盤1に試験終了信号を送信して(S17)、指定住戸の住宅情報盤1、火災感知器3および複合盤4に対する遠隔試験モードを解除し、共同住宅システム10(指定住戸)を火災監視モードに戻すとともに、表示制御部17を介して表示部13に通常の火災発生監視画面を表示させる。
【0031】
さらに、例えば表示部13に表示された図4に示す画面において、「感知器単位」が選択されて「実行」キーが操作され、図8に示す画面において「試験住戸番号」および「試験感知器番号」が選択されて「実行」キーが操作されると、複合盤4の試験設定部15は、操作部14の操作に基づいて遠隔試験を指定住戸の指定火災感知器3に対して行う感知器単位試験を実施することを設定し(S18)、その設定に基づいて試験通信制御部16は複合盤4から指定住戸の住宅情報盤1に試験開始信号を送信する(S19)。このとき、表示部13は表示制御部17により感知器単位試験用画面が表示される。ここで、住戸の指定は、上述したのように予め決められている住戸番号でよく、また、住宅情報盤1に接続された火災感知器3は順番に1から番号が付けられており、試験を行う火災感知器3に付けられた番号を指定する。
【0032】
ついで、指定住戸の住宅情報盤1の通信部11が複合盤4からの試験開始信号を受信すると、住宅情報盤1の試験実行部12はその住宅情報盤1に接続されて指定された火災感知器3に対して動作試験を行い、その結果を試験実行部12に設けられた記憶部12aに格納する(S20)。そして、複合盤4の試験通信制御部16により複合盤4から指定住戸の住宅情報盤1に試験結果の送信要求信号を送信すると(S21)、指定住戸の住宅情報盤1の通信部11は試験実行部12の記憶部12aに格納された指定感知器の試験結果を複合盤4に送信し(S22)、複合盤4は試験通信制御部16により受信した試験結果を、図9に示すように、表示制御部17を介して表示部13に表示させる(S23)。
【0033】
複合盤4は、指定住戸の指定感知器からの試験結果を受信すると、試験設定部15により操作部14による同住戸または他の住戸のいずれかの火災感知器3に対する遠隔試験を実施するかの操作に基づく感知器単位の試験続行または終了を設定し(S24)、同住戸または他の住戸のいずれかの火災感知器3の試験続行が設定された場合は上述のステップS19に戻る。同住戸または他の住戸のいずれかの火災感知器3の遠隔試験が続行されない場合、つまり感知器単位の遠隔試験を終了する場合は、指定住戸の住宅情報盤1に試験終了信号を送信して(S25)、指定住戸の住宅情報盤1、指定火災感知器3および複合盤4に対する遠隔試験モードを解除し、共同住宅システム10(指定住戸の指定火災感知器3)を火災監視モードに戻すとともに、表示制御部17を介して表示部13に通常の火災発生監視画面を表示させる。
【0034】
このように、通信制御線L1を介して接続された各住戸の住宅情報盤1と複合盤4との間で、各住宅情報盤1に通信制御線(信号線)L3を介して接続された火災感知器3の遠隔試験を行うようにしたので、従来のように各住戸の玄関先まで点検作業員が足を運ぶなどの手間がなくなり、住戸数の多い共同住宅でも短時間で簡単に火災感知器3の遠隔試験を行うことができる火災感知器3の遠隔試験システムを備えた火災報知設備を得ることができる。また、複合盤4により遠隔試験を制御することができるため、遠隔試験の指示の設定、つまり全住戸、住戸単位または感知器単位の設定を任意に行うことができ、使い勝手のよい火災感知器3の遠隔試験システムを備えた火災報知設備を得ることができる。
【0035】
なお、上述の実施の形態では、各火災感知器3に対する試験動作を、複合盤4からの試験開始信号を住宅情報盤1に送信することで起動する場合を示したが、試験開始信号以外で起動するようにしてもよく、また、住宅情報盤1の盤面に入力手段として図示しない試験スイッチなどを設け、その試験スイッチの操作入力によって試験動作を起動するようにしてもよい。さらに、ドアホン2に外観では見えにくい箇所に試験スイッチ等を設け、戸外からこの試験スイッチによって住宅情報盤1に操作入力をするようにしてもよい。
【0036】
【発明の効果】
以上のように本発明に係る火災報知設備は、共同住戸の各住戸にそれぞれ設置された住宅情報盤と、各住戸内にそれぞれ設置され住宅情報盤に接続された火災感知器と、各住戸、管理室および共同玄関における通話および火災感知器からの警報を制御する複合盤とを備えてなり、複合盤に、各住戸の火災感知器の動作試験を遠隔操作により行う遠隔試験制御手段を設けたので、住戸数の多い共同住宅でも短時間で簡単に火災感知器の遠隔試験を行うことができる火災報知設備を得ることができる。
【0037】
本発明に係る火災報知設備において、遠隔試験制御手段は、遠隔試験の指示があると、全住戸の火災感知器、指定住戸の火災感知器または指定住戸の指定火災感知器に対し住宅情報盤を介して動作試験を行わせるので、従来のように各住戸の玄関先まで点検作業員が足を運ぶなどの手間がなくなり、住戸数の多い共同住宅でも短時間で簡単に火災感知器の遠隔試験を行うことができる火災報知設備を得ることができる。
【0038】
本発明に係る火災報知設備は、複合盤に表示手段および操作手段を設け、遠隔試験制御手段は、操作手段による遠隔試験の指示に基づいて全住戸の火災感知器、指定住戸の火災感知器または指定住戸の指定火災感知器に対し住宅情報盤を介して動作試験を行わせ、動作試験の結果を表示手段に表示させるので、遠隔試験の指示の設定、つまり全住戸、住戸単位または感知器単位の設定を任意に行うことができるとともに、動作試験の結果を1ヶ所で全て把握することができ、使い勝手のよい火災報知設備を得ることができる。
【0039】
本発明に係る火災報知設備において、遠隔試験制御手段は、操作手段の操作に基づいて動作試験の開始または終了、あるいは、全住戸、住戸単位または感知器単位のいずれかの遠隔試験の指示を設定する試験設定部と、試験設定部の設定に基づいて試験開始信号または終了信号および動作試験の結果の信号を含む通信信号を送受信する試験通信制御部と、試験設定部の設定および試験通信制御部からの動作試験の結果に基づいて表示手段への表示を制御する表示制御部とを備えたので、上記と同様な効果を得ることができる。
【0040】
本発明に係る火災報知設備において、住宅情報盤は、複合盤との試験開始信号または終了信号および動作試験の結果の信号を含む通信信号を送受信する通信部と、火災感知器に対して動作試験を実行する試験実行部とを備え、通信部が複合盤からの遠隔試験の指示を受けると、試験実行部は遠隔試験の指示に基づいて火災感知器に対して動作試験を実行するので、火災感知器の遠隔試験を短時間で簡単に行うことができる火災報知設備を得ることができる。
【0041】
本発明に係る火災報知設備は、共同住戸の各住戸にそれぞれ設置された住宅情報盤と、各住戸内にそれぞれ設置され住宅情報盤に接続された火災感知器と、各住戸、管理室および共同玄関における通話および火災感知器からの警報を制御する複合盤とを備えてなり、各住戸の住宅情報盤に、住宅情報盤に接続された火災感知器の動作試験を行わせる試験制御手段を設けたものである。
また、試験制御手段は、複合盤から遠隔試験の指示または住宅情報盤に設けられた入力手段による試験入力があったときに、火災感知器の動作試験を行うものである。
さらに、試験制御手段は、複合盤からの遠隔試験の指示または住宅情報盤の入力手段による試験入力とともに、動作試験を行わせる火災感知器の指定があったときに、指定火災感知器に対して動作試験を行うものである。
このように、住宅情報盤に、火災感知器の試験を行わせる試験制御手段を設けたので、従来のように外部試験器を点検作業員が持ち歩く必要がなく、住宅情報盤に対して試験入力を行えば、簡単に火災感知器の遠隔試験を行うことができる火災報知設備を得ることができる。
【図面の簡単な説明】
【図1】 本発明が適用される共同住宅システムの構成を示す系統図である。
【図2】 本発明の実施の形態の要部のブロック図である。
【図3】 本発明の実施の形態の作用を示すフローチャートである。
【図4】 本発明の実施の形態に係る表示部の遠隔試験時の画面を示す図である。
【図5】 本発明の実施の形態に係る表示部の全住戸試験時の画面を示す図である。
【図6】 本発明の実施の形態に係る表示部の住戸単位試験時の画面を示す図である。
【図7】 本発明の実施の形態に係る表示部の住戸単位試験時の他の画面を示す図である。
【図8】 本発明の実施の形態に係る表示部の感知器単位試験時の画面を示す図である。
【図9】 本発明の実施の形態に係る表示部の感知器単位試験時の他の画面を示す図である。
【図10】 従来の共同住宅システムの構成を示す系統図である。
【符号の説明】
1 住宅情報盤、3 火災感知器、4 複合盤、10 共同住宅システム、11 通信部、12 試験実行部、12a 記憶部、13 表示部、14 操作部、15 試験設定部、16 試験通信制御部、17 表示制御部、L1〜L6 通信制御線。
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a function of a residential building receiver that controls a fire alarm facility installed in a management room, for example, a fire detector installed in an apartment of a condominium, such as a condominium, and an intercom intercom call facility. This invention relates to a fire alarm system for performing an operation test by remote operation from a composite panel including a function of a call control panel for controlling the sound through a housing information panel installed in each dwelling unit.
[0002]
[Prior art]
Recent apartment houses such as condominiums are provided with a fire alarm facility for an apartment house (hereinafter referred to as “fire alarm facility”) for monitoring the occurrence of a fire and notifying the fire if a fire occurs. As shown in FIG. 10, such a fire alarm facility is installed in a management room or the like of an apartment house, and controls the entire fire alarm facility. A housing information board 22 installed in each dwelling unit and It includes a fire detector 23 and a door phone 24 installed at the front of each dwelling unit and having an interphone call function. Reference numeral 25 denotes a call control panel installed in the management room or the like together with the housing ridge receiver 21, for example, a common entrance machine 26 installed in the vicinity of a common entrance door provided on the first floor of the apartment house, and each dwelling unit. Connected to the housing information panel 22 (via the door phone of each dwelling unit), and controls intercom call facilities such as calls at the common entrance, each dwelling unit and the management room. The apartment system 30 is configured together with a fire alarm facility equipped with a residence building receiver 21 and an interphone call facility equipped with a call control panel 25 and the like.
[0003]
In the apartment house having the apartment house system 30 configured as described above, when the fire detector 23 installed in each dwelling unit detects a fire, a signal to that effect is sent to the house information board 22 via the door phone 24, Upon receiving this signal, the housing information board 22 notifies the resident that the fire detector 23 has been activated, and when the resident confirms the fire and operates the confirmation switch of the housing information board 22, the housing information board 22 A fire confirmation signal is output to the residence receiver 21, and the residence receiver 21 is installed in the apartment house, for example, in the vicinity (on the same floor) or immediately above the residence information board 22 that outputs the fire confirmation signal. A fire alarm is activated on the information board 22.
[0004]
As described above, the fire detector 23 that detects the fire of each dwelling unit normally monitors the occurrence of a fire. However, since it is important that the fire detector 23 operates normally in the event of a fire, a periodic operation test (inspection) is required. It is necessary to do. This operation test is performed by an inspection worker for each fire detector, but since the fire detector is installed in the dwelling unit, it is regularly checked even when there is no privacy protection and no resident. The fire detector 23 can be remotely operated from outside.
[0005]
For example, the door phone 24 shown in FIG. 10 is connected to the fire detector 23 and the house information panel 22 and is connected to an external tester 28 for controlling the operation test of the fire detector 23 (not shown). And a switching contact (not shown) for switching the signal path between the operation test and the fire monitoring.
When performing an operation test from the outside using such a door phone 24, first, when the external tester 28 is connected to the test connection terminal of the door phone 24 of a certain dwelling unit, the switching contact is operated to the operation test side, and the door phone outside the dwelling unit is operated. The connection between the fire detector 23 and the house information board 22 via the circuit 24 is cut off in circuit, and the fire detector 23 in the dwelling unit and the external tester 28 are connected in circuit. Next, the inspection worker designates addresses assigned to the individual fire detectors 23 in advance using the external tester 28, sends out a notification command, and whether or not various operations at the time of fire detection are performed normally. Confirm each operation individually. When the external tester 28 is removed from the test connection terminal of the door phone 24 after the operation test is completed, the switching contact is activated to the original state, that is, the fire monitoring side, and the connection between the fire detector 23 in the dwelling unit and the external tester 28 is performed. Is interrupted, and the fire detector 23 and the house information board 22 are connected in a circuit via the door phone 24 (see, for example, Patent Document 1).
[0006]
[Patent Document 1]
JP 11-219490 A
[0007]
[Problems to be solved by the invention]
In the conventional apartment system 30 as described above, the external tester 28 is connected to the test connection terminal provided in the door phone 24 of each dwelling unit, and the fire detector 23 installed in the dwelling unit from the external tester 28 outside. A signal is transmitted to the fire detector 23 to perform an operation test of the fire detector 23 by remote control. However, such an outdoor operation test has to be carried out by the inspection workers to the front door (door phone 24) of each dwelling unit one by one. Took a long time and was a difficult task. In addition, since the operation test from the outside could be performed only one house at a time, there was a problem that the operation test could not be performed on all the fire detectors 23 of all the dwelling units in the apartment house. Furthermore, there have been problems such as being unable to redo the operation test or grasping the test result at one place.
[0008]
The present invention has been made in order to solve the above-described problems, and it is possible to easily perform the operation test of the fire detector of each dwelling unit of the apartment house in the apartment house system simultaneously or individually and in a short time by remote control. The purpose of the present invention is to provide a fire alarm facility equipped with a remote test system for a fire detector that can be performed.
[0009]
[Means for Solving the Problems]
The fire alarm system according to the present invention includes a housing information panel installed in each dwelling unit, a fire detector installed in each dwelling unit and connected to the housing information panel, each dwelling unit, a control room, and a common unit. It is equipped with a composite panel that controls calls from the entrance and alarms from fire detectors. Display means, operating means, Remote test control means for remotely operating fire detectors in each dwelling unit When Provided Execute the operation test on the fire detector with the communication unit that transmits and receives the communication signal including the test start signal or end signal with the composite panel and the signal of the operation test result to the housing information board, and the result of the operation test The housing information board has a storage section for storing the test information, and when the communication section receives a remote test instruction from the composite board, the test execution section applies a fire test to the fire detector based on the remote test instruction. The operation test is executed, the result of the operation test is stored in the storage unit, and when the communication unit receives the transmission request signal of the result of the operation test from the composite panel, the result of the operation test stored in the storage unit is stored. The remote test control means of the composite panel sends the housing information panel to the fire detectors of all the dwelling units, the fire detectors of the designated dwelling units or the designated fire detectors of the designated dwelling units based on the remote test instruction by the operation means. Let the operation test through the house It transmits a transmission request signal results in the operation test in the distribution board, the result of operation test received from residential information panel on the display unit Is.
[0015]
Fire alarm equipment according to the present invention ,each A test control means is installed on the housing information panel of the dwelling unit to perform an operation test of the fire detector connected to the housing information panel. The test control means performs an operation test of the fire detector when there is a remote test instruction from the composite panel or a test input by the input means provided on the housing information panel. Is.
[0017]
In the fire alarm facility according to the present invention, the test control means, when there is an instruction for a remote test from the composite panel or a test input by the input means of the housing information panel, and a fire detector for performing an operation test is designated, The operation test is performed for the designated fire detector.
[0018]
DETAILED DESCRIPTION OF THE INVENTION
FIG. 1 is a system diagram showing a configuration of a shared housing system to which the present invention is applied, and FIG. 2 is a block diagram of a main part of an embodiment of the present invention. In the figure, 1 is a housing information board provided in each apartment of the apartment house, a function of unlocking the door of the apartment (not shown), a door phone 2 at the entrance of the apartment, an entrance of the apartment, and a management room. Intercom call function, alarm function such as fire, gas leak and crime prevention, remote test function of fire detector 3 in the dwelling unit, and the like. The composite board, which will be described later, is connected via a communication control line L1, the door phone 2 via a communication control line (call line) L2, and the fire detector 3 via a communication control line (signal line) L3.
[0019]
4 is a composite board installed in the management room, for example, an interphone call function with a function of unlocking the door of the common entrance, a call and communication control function in each dwelling unit, management room and common entrance, and It is combined with fire alarm equipment equipped with alarm functions such as fire, gas leakage and crime prevention, remote test control function of fire detector 3 of each dwelling unit, and is installed at the housing information panel 1 of each dwelling unit and the common entrance The common entrance machine 5 and the shared part 6 of the apartment house are connected via communication control lines L1, L5 and L6.
[0020]
In addition, the house information panel 1 and the composite panel 4 and the like normally obtain power from an ordinary power source (not shown). However, when the power supply from the ordinary power source is cut off, the emergency information source 7 obtains power. It has become. And the apartment house system 10 in an apartment house is comprised by these. The communication control lines L1 and L5 are a control line through which control signals such as an unlock signal, an alarm signal, and a remote test signal are transmitted and received, and a signal at the time of a call in a door phone, a common entrance, and a management room. And a communication line through which audio signals such as alarm signals are transmitted and received.
[0021]
As shown in FIG. 2, the housing information panel 1 includes a communication unit 11 that transmits and receives communication signals to and from the composite panel 4, and a fire detector 3 that is connected to the housing information panel 1 (up to 16 can be connected here). On the other hand, a test execution unit 12 that performs an operation test as to whether or not various operations at the time of fire detection are normally performed is provided. And the test execution part 12 has the memory | storage part 12a which stores a test result.
[0022]
As shown in FIG. 2, the composite panel 4 includes a display unit 13 made of, for example, an LCD, operation keys displayed on the screen of the display unit 13, operation keys provided in the vicinity of the display unit 13, and the like. The operation unit 14 for operating the remote test for the fire detector 3 of the fire detector 3 and the start or end of the remote test for the fire detector 3 based on the operation of the operation unit 14, for all units, units of units, or units of the sensor A test setting unit 15 which is a remote test control means for setting any remote test instruction or whether or not a test result is requested, and a test start signal or an end signal based on the setting of the test setting unit 15, Display on the display unit 13 based on the setting of the test communication control unit 16 which is a remote test control means for transmitting and receiving a communication signal such as a test result request signal and a test result signal from the house information panel 1 and the test setting unit 15 System As well as, and a display control unit 17 is a remote test control means for controlling display of the display unit 13 on the basis of the test results from the test communication control unit 16.
[0023]
In addition, all the dwelling units set by the test setting unit 15 are cases where a remote test is simultaneously performed on the fire detectors 3 of all the dwelling units of the apartment, and the unit of dwelling unit is assigned to the fire detector 3 of the designated dwelling unit. In addition to the case where a remote test is performed on a fire detector 3 in any one of a plurality of apartment buildings or a case where a remote test is performed on a fire detector 3 on one floor of a building, The sensor unit is a case where a remote test is performed on the designated fire sensor 3 of the designated dwelling unit. Further, the display control unit 17 may not be included in the remote test control unit.
[0024]
The house information panel 1, the fire detector 3 and the composite panel 4 constitute a remote test system for the fire detector 3.
[0025]
Next, the operation of the remote test system for the fire detector 3 in the apartment house system 10 configured as described above will be described with reference to the flowchart of FIG.
Normally, in the fire monitoring mode apartment house system 10 in which the fire occurrence is monitored by the fire detector 3 (S1), the remote test mode displayed on the display unit 13 is selected by the operation unit 14 of the composite panel 4 Then, the apartment house system 10 enters the remote test mode, the screen shown in FIG. 4 is displayed on the display unit 13, and the remote test for the fire detector 3 is performed in all the dwelling units, the dwelling unit or the sensor unit. Whether to implement is selected by the operation unit 14 (S3, S10, S18).
[0026]
For example, in the screen shown in FIG. 4 displayed on the display unit 13, when “all dwelling units” is selected and the “execute” key is operated, the test setting unit 15 of the composite panel 4 is based on the operation of the operation unit 14. The remote communication test is performed on all the fire detectors 3 of all the dwelling units at the same time (S3), and based on the setting, the test communication control unit 16 starts the combination panel 4 to each of the dwelling units. A test start signal which is a communication signal is transmitted to the house information board 1 (S4). At this time, the display unit 13 displays the all dwelling unit test screen by the display control unit 17. Next, when the communication unit 11 of each house information panel 1 receives the test start signal from the composite panel 4, the test execution unit 12 of each house information panel 1 connects to the fire detector 3 connected via the signal line L3. The operation test is performed on each of the results, and the result is stored in the storage unit 12a provided in the test execution unit 12 (S5). When the test communication control unit 16 of the composite panel 4 transmits a test request transmission request signal from the composite panel 4 to the housing information panel 1 of each dwelling unit (S6), the communication unit 11 of each housing information panel 1 becomes the test execution unit. 12 transmits the test results stored in the storage unit 12a to the composite panel 4 (S7), and the composite panel 4 displays the test results received by the test communication control unit 16 as shown in FIG. Display on the display unit 13 (S8).
[0027]
Here, the test operation of the fire detector 3 will be briefly described. When a signal for starting a test designated by the self is received from the house information panel 1, the fire detector 3 checks its own fire detection function. If the result is normal, the housing information panel 1 returns a normal signal, and if not normal, an abnormal signal is returned. Note that the test operation of the fire detector 3 is not started by a signal from the house information panel 1, but the self-detection function is checked by monitoring the detection output over time, so-called steady value monitoring, and the house information panel When a test signal is received from 1, it is possible to return a normal signal or an abnormal signal from the result of the steady value monitoring.
In addition, although the fire detector 3 is provided with an operation indicator (not shown) and the fire detector 3 has checked the fire detection function of the fire detector 3 and the result is normal, the operation indicator is turned on for a predetermined time. Thus, it can be confirmed that the fire detector 3 is normal. As a result, a remote test including the specific fire detector 3 is performed, and if the operation indicator of the fire detector 3 is not lit, it can be understood that the fire detector 3 is abnormal.
[0028]
When the composite panel 4 receives the test results from all the dwelling units, it transmits a test end signal to the housing information panel 1 (S9), and remotes the housing information panel 1, fire detector 3 and composite panel 4 of all the dwelling units. The test mode is canceled, the apartment house system 10 is returned to the fire monitoring mode, and a normal fire occurrence monitoring screen is displayed on the display unit 13 via the display control unit 17.
[0029]
Further, for example, in the screen shown in FIG. 4 displayed on the display unit 13, “unit of dwelling unit” is selected and the “execution” key is operated, and in the screen shown in FIG. When the key is operated, the test setting unit 15 of the composite panel 4 sets to perform a unit unit test for performing a remote test on the fire detector 3 of the designated unit based on the operation of the operation unit 14. (S10) Based on the setting, the test communication control unit 16 transmits a test start signal from the composite panel 4 to the housing information panel 1 of the designated dwelling unit (S11). At this time, the display unit 13 causes the display control unit 17 to display a unit unit test screen. Here, for the designation of the dwelling unit, a dwelling unit number determined in advance can be used. In addition, when an individual address is given to each house information board 1 regardless of the dwelling unit number, the address may be designated. At this time, the display unit 13 causes the display control unit 17 to display a unit unit test screen. Next, when the communication unit 11 of the housing information panel 1 of the designated dwelling unit receives the test start signal from the composite panel 4, the test execution unit 12 of the housing information panel 1 detects each fire detector connected to the housing information panel 1. 3 is subjected to an operation test, and the result is stored in the storage unit 12a provided in the test execution unit 12 (S12). When the test communication control unit 16 of the composite panel 4 transmits a test result transmission request signal from the composite panel 4 to the housing information panel 1 of the designated dwelling unit (S13), the communication unit 11 of the housing information panel 1 of the designated dwelling unit performs the test. The test result stored in the storage unit 12a of the execution unit 12 is transmitted to the composite board 4 (S14), and the composite board 4 shows the test result of the designated dwelling unit received by the test communication control unit 16, as shown in FIG. It is made to display on the display part 13 via the display control part 17 (S15).
[0030]
When the composite panel 4 receives the test result from the designated dwelling unit, the test setting unit 15 sets the continuation or end of the test for each dwelling unit based on the operation of whether to perform the remote test on another dwelling unit by the operation unit 14 (S16). ), When the test continuation of another dwelling unit is set, the process returns to step S11 described above. When the remote test of another dwelling unit is not continued, that is, when the remote test for each dwelling unit is finished, a test end signal is transmitted to the housing information panel 1 of the designated dwelling unit (S17), The remote test mode for the fire detector 3 and the composite panel 4 is canceled, the apartment house system 10 (designated dwelling unit) is returned to the fire monitoring mode, and a normal fire occurrence monitoring screen is displayed on the display unit 13 via the display control unit 17. Display.
[0031]
Further, for example, in the screen shown in FIG. 4 displayed on the display unit 13, “sensor unit” is selected and the “execute” key is operated, and in the screen shown in FIG. 8, “test dwell unit number” and “test sensor” When “No.” is selected and the “execution” key is operated, the test setting unit 15 of the composite panel 4 performs a remote test on the designated fire sensor 3 of the designated dwelling unit based on the operation of the operation unit 14. Based on the setting, the test communication control unit 16 transmits a test start signal from the composite panel 4 to the housing information panel 1 of the designated dwelling unit (S19). At this time, the display unit 13 causes the display control unit 17 to display a sensor unit test screen. Here, the designation of the dwelling unit may be a dwelling unit number determined in advance as described above, and the fire detectors 3 connected to the housing information panel 1 are numbered sequentially from 1 and tested. Designate the number assigned to the fire detector 3 to perform.
[0032]
Next, when the communication unit 11 of the housing information panel 1 of the designated residence receives the test start signal from the composite panel 4, the test execution unit 12 of the housing information panel 1 is connected to the housing information panel 1 and designated fire detection. The operation test is performed on the device 3, and the result is stored in the storage unit 12a provided in the test execution unit 12 (S20). When the test communication control unit 16 of the composite panel 4 transmits a test result transmission request signal from the composite panel 4 to the housing information panel 1 of the designated dwelling unit (S21), the communication unit 11 of the housing information panel 1 of the designated dwelling unit is tested. The test result of the designated sensor stored in the storage unit 12a of the execution unit 12 is transmitted to the composite board 4 (S22), and the composite board 4 shows the test result received by the test communication control unit 16 as shown in FIG. Then, it is displayed on the display unit 13 via the display control unit 17 (S23).
[0033]
When the composite panel 4 receives the test result from the designated sensor of the designated dwelling unit, the test setting unit 15 performs a remote test on the fire sensor 3 of the same dwelling unit or another dwelling unit by the operation unit 14. The test unit continuation or termination based on the operation is set (S24), and if the test continuation of the fire detector 3 of the same dwelling unit or another dwelling unit is set, the process returns to the above-described step S19. When the remote test of the fire detector 3 of either the same unit or another unit is not continued, that is, when the remote test of the sensor unit is ended, a test end signal is transmitted to the housing information panel 1 of the designated unit. (S25), canceling the remote test mode for the housing information panel 1, the designated fire detector 3 and the composite panel 4 of the designated residence, and returning the apartment house system 10 (designated fire detector 3 of the designated residence) to the fire monitoring mode. The normal fire occurrence monitoring screen is displayed on the display unit 13 via the display control unit 17.
[0034]
In this way, between the housing information panel 1 and the composite panel 4 of each dwelling unit connected via the communication control line L1, each housing information panel 1 is connected via the communication control line (signal line) L3. Because the remote test of the fire detector 3 was performed, there was no need for inspection workers to go to the front door of each dwelling unit as in the past, and it was easy to fire even in apartments with a large number of dwelling units in a short time. A fire alarm system equipped with a remote test system for the fire detector 3 capable of performing a remote test of the sensor 3 can be obtained. Further, since the remote test can be controlled by the composite panel 4, it is possible to arbitrarily set the remote test instruction, that is, to set all dwelling units, dwelling units or sensor units, and the fire detector 3 is easy to use. A fire alarm facility equipped with a remote test system can be obtained.
[0035]
In the above-described embodiment, the case where the test operation for each fire detector 3 is started by transmitting a test start signal from the composite panel 4 to the house information panel 1 is described. The test information may be activated, or a test switch (not shown) may be provided as an input means on the surface of the house information panel 1 so that the test operation is activated by operating the test switch. Furthermore, a test switch or the like may be provided in a place where the door phone 2 is difficult to see in the appearance, and an operation input may be performed to the house information panel 1 from the outside by the test switch.
[0036]
【The invention's effect】
As described above, the fire alarm system according to the present invention includes a housing information panel installed in each dwelling unit, a fire detector installed in each dwelling unit and connected to the housing information panel, each dwelling unit, It is equipped with a composite panel that controls alarms from telephone calls and fire detectors in the control room and common entrance, and remote test control means is provided on the composite panel to remotely operate the fire detectors of each dwelling unit. Therefore, it is possible to obtain a fire alarm facility that can easily perform a remote test of a fire detector in a short time even in an apartment house with a large number of units.
[0037]
In the fire alarm facility according to the present invention, when the remote test control means is instructed to perform a remote test, the housing information panel is provided to the fire detectors of all dwelling units, the fire detectors of the designated dwelling units or the designated fire detectors of the designated dwelling units. Because the operation test is performed through the machine, there is no need for inspection workers to go to the front door of each dwelling unit, and remote testing of fire detectors can be easily done in a short time even in apartments with many dwelling units. A fire alarm facility capable of performing the above can be obtained.
[0038]
The fire alarm facility according to the present invention is provided with a display means and an operation means on the composite panel, and the remote test control means is a fire detector for all dwelling units, a fire sensor for designated dwelling units or The operation test is performed on the designated fire detector of the designated residence through the housing information panel, and the result of the behavior test is displayed on the display means, so the setting of the remote test instruction, that is, all the residences, the unit of residence or the unit of sensor Can be arbitrarily set, and the results of the operation test can be grasped in one place, so that a fire alarm facility that is easy to use can be obtained.
[0039]
In the fire alarm facility according to the present invention, the remote test control means sets the start or end of the operation test based on the operation of the operation means, or the remote test instruction for any dwelling unit, dwelling unit or sensor unit. A test setting unit, a test communication control unit for transmitting and receiving a communication signal including a test start signal or an end signal and a signal of an operation test result based on the setting of the test setting unit, and the setting of the test setting unit and the test communication control unit Since the display control unit for controlling the display on the display means based on the result of the operation test from the above is provided, the same effect as described above can be obtained.
[0040]
In the fire alarm facility according to the present invention, the housing information panel is an operation test for a fire detector and a communication unit that transmits and receives a communication signal including a test start signal or an end signal with the composite panel and a signal of an operation test result. When the communication unit receives a remote test instruction from the composite panel, the test execution unit executes an operation test on the fire detector based on the remote test instruction. It is possible to obtain a fire alarm facility that can easily perform a remote test of a sensor in a short time.
[0041]
The fire alarm system according to the present invention includes a housing information board installed in each dwelling unit, a fire detector installed in each dwelling unit and connected to the housing information board, each dwelling unit, a control room, and a common unit. It is equipped with a composite panel that controls calls from the entrance and alarms from fire detectors, and a test control means is provided on the housing information panel of each dwelling unit to perform an operation test of the fire sensor connected to the housing information panel. It is a thing.
The test control means performs an operation test of the fire detector when there is a remote test instruction from the composite board or a test input by an input means provided on the house information board.
Furthermore, the test control means, when there is a designation of a fire detector for performing an operation test, together with a remote test instruction from the composite panel or a test input by the input means of the housing information panel, An operation test is performed.
In this way, because the house information panel is equipped with a test control means for testing the fire detector, it is not necessary for the inspection operator to carry the external tester as in the past, and the test information is input to the house information panel. If it carries out, the fire alarm equipment which can perform the remote test of a fire detector easily can be obtained.
[Brief description of the drawings]
FIG. 1 is a system diagram showing a configuration of a shared housing system to which the present invention is applied.
FIG. 2 is a block diagram of a main part of the embodiment of the present invention.
FIG. 3 is a flowchart showing the operation of the exemplary embodiment of the present invention.
FIG. 4 is a diagram showing a screen during a remote test of the display unit according to the embodiment of the present invention.
FIG. 5 is a diagram showing a screen during a full dwelling test of the display unit according to the embodiment of the present invention.
FIG. 6 is a diagram showing a screen during a dwelling unit test of the display unit according to the embodiment of the present invention.
FIG. 7 is a diagram showing another screen at the time of the dwelling unit test of the display unit according to the embodiment of the present invention.
FIG. 8 is a diagram showing a screen during a sensor unit test of the display unit according to the embodiment of the present invention.
FIG. 9 is a diagram showing another screen during the sensor unit test of the display unit according to the embodiment of the present invention.
FIG. 10 is a system diagram showing a configuration of a conventional apartment house system.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Housing information board, 3 Fire detector, 4 Composite board, 10 Apartment house system, 11 Communication part, 12 Test execution part, 12a Memory | storage part, 13 Display part, 14 Operation part, 15 Test setting part, 16 Test communication control part , 17 Display control part, L1-L6 Communication control line.

Claims (3)

共同住戸の各住戸にそれぞれ設置された住宅情報盤と、
前記各住戸内にそれぞれ設置され前記住宅情報盤に接続された火災感知器と、
前記各住戸、管理室および共同玄関における通話および前記火災感知器からの警報を制御する複合盤とを備えてなり、
前記複合盤に、表示手段と、操作手段と、前記各住戸の火災感知器の動作試験を遠隔操作により行う遠隔試験制御手段を設け
前記住宅情報盤に、前記複合盤との試験開始信号または終了信号および動作試験の結果の信号を含む通信信号を送受信する通信部と、前記火災感知器に対して動作試験を実行し、該動作試験の結果を格納する記憶部を有する試験実行部とを設け、
前記住宅情報盤は、
前記通信部が前記複合盤からの遠隔試験の指示を受けると、前記試験実行部が前記遠隔試験の指示に基づいて前記火災感知器に対して動作試験を実行して、動作試験の結果を前記記憶部に格納し、
前記通信部が前記複合盤から動作試験の結果の送信要求信号を受信すると、前記記憶部に格納された動作試験の結果を前記複合盤に送信し、
前記複合盤の前記遠隔試験制御手段は、
前記操作手段による遠隔試験の指示に基づいて全住戸の火災感知器、指定住戸の火災感知器または指定住戸の指定火災感知器に対し前記住宅情報盤を介して動作試験を行わせ、
前記住宅情報盤に動作試験の結果の送信要求信号を送信し、
前記住宅情報盤から受信した該動作試験の結果を、前記表示手段に表示させる
ことを特徴とする火災報知設備。
A housing information board installed in each dwelling unit,
Fire detectors installed in each dwelling unit and connected to the housing information panel,
Each of the dwelling units, the management room and the common entrance, and a composite panel for controlling the alarm from the fire detector,
The composite panel is provided with display means, operation means, and remote test control means for performing an operation test of the fire detector of each dwelling unit by remote operation ,
A communication unit that transmits / receives a communication signal including a test start signal or an end signal with the composite panel and a signal of an operation test result to the housing information panel, and an operation test is performed on the fire detector, and the operation A test execution unit having a storage unit for storing test results;
The housing information board
When the communication unit receives a remote test instruction from the composite panel, the test execution unit executes an operation test on the fire detector based on the remote test instruction, and the result of the operation test is obtained. Stored in the storage unit,
When the communication unit receives an operation test result transmission request signal from the composite panel, the operation test result stored in the storage unit is transmitted to the composite panel,
The remote test control means of the composite panel is:
Based on the remote test instructions by the operation means, let the fire detectors of all the dwelling units, the fire detectors of the designated dwelling units or the designated fire detectors of the designated dwelling units perform an operation test via the housing information panel,
Send a transmission request signal of the result of the operation test to the house information board,
The fire alarm facility characterized in that the result of the operation test received from the housing information panel is displayed on the display means .
記各住戸の住宅情報盤に、該住宅情報盤に接続された前記火災感知器の動作試験を行わせる試験制御手段を設け、前記試験制御手段は、前記複合盤から遠隔試験の指示または住宅情報盤に設けられた入力手段による試験入力があったときに、前記火災感知器の動作試験を行うことを特徴とする請求項記載の火災報知設備。 Before SL residential information panel of each dwelling unit, the test control means for causing the operation test of the fire detector connected to the housing information panel provided, said test control means, an instruction or residential remote testing from the composite board when there is testing input by the input means provided on the information panel, fire alarm system according to claim 1, characterized in that the operation test of the fire detector. 前記試験制御手段は、前記複合盤からの遠隔試験の指示または住宅情報盤の入力手段による試験入力とともに、動作試験を行わせる火災感知器の指定があったときに、該指定火災感知器に対して動作試験を行うことを特徴とする請求項記載の火災報知設備。 Said test control means, with a test input by the input means of instructions or residential information panel for remote testing from the composite panel, when there is specified fire detector to perform the operation test, with respect to the designated fire detector The fire alarm system according to claim 2 , wherein an operation test is performed.
JP2002285317A 2002-09-30 2002-09-30 Fire alarm system Expired - Fee Related JP3968652B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002285317A JP3968652B2 (en) 2002-09-30 2002-09-30 Fire alarm system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002285317A JP3968652B2 (en) 2002-09-30 2002-09-30 Fire alarm system

Publications (2)

Publication Number Publication Date
JP2004118805A JP2004118805A (en) 2004-04-15
JP3968652B2 true JP3968652B2 (en) 2007-08-29

Family

ID=32278654

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002285317A Expired - Fee Related JP3968652B2 (en) 2002-09-30 2002-09-30 Fire alarm system

Country Status (1)

Country Link
JP (1) JP3968652B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100643791B1 (en) * 2004-06-30 2006-11-10 삼성물산 주식회사 Complementary Apartment Fire Alarm System
JP5016945B2 (en) * 2007-02-23 2012-09-05 パナソニック株式会社 Fire alarm system
JP2009217592A (en) * 2008-03-11 2009-09-24 Panasonic Electric Works Co Ltd Radio system
KR101393517B1 (en) 2012-12-18 2014-05-14 주식회사 하이맥스 Remote checking system for smoke detector and device thereof
JP7055987B2 (en) * 2019-01-23 2022-04-19 竹中エンジニアリング株式会社 Control terminal and security system

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3295207B2 (en) * 1993-12-28 2002-06-24 能美防災株式会社 Fire alarm system
JPH08153295A (en) * 1994-11-26 1996-06-11 Hochiki Corp Disaster prevention monitoring system
JP3843419B2 (en) * 1999-03-31 2006-11-08 能美防災株式会社 Intercom system
JP2002083390A (en) * 2000-09-08 2002-03-22 Tokyo Gas Co Ltd Fire alarm system and its inspection method
JP2003296839A (en) * 2002-04-05 2003-10-17 Hochiki Corp Disaster prevention monitoring equipment for apartment buildings
JP3957600B2 (en) * 2002-09-20 2007-08-15 ニッタン株式会社 Fire receiver

Also Published As

Publication number Publication date
JP2004118805A (en) 2004-04-15

Similar Documents

Publication Publication Date Title
JP3661620B2 (en) Apartment house management system with earthquake notification function
JP3968652B2 (en) Fire alarm system
JP3653994B2 (en) Security intercom device and alarm monitoring system provided with the same
JP7496007B2 (en) Fire alarm system
JP3463234B2 (en) Apartment house alarm monitoring integrated system
JP2023138786A (en) Fire alarm facilities
JP3843419B2 (en) Intercom system
JPH11161884A (en) Apartment house integrated alarm/monitoring board
JPH1145390A (en) Multiple dwelling house system with emergency broadcasting line
JP3906401B2 (en) Intercom system
JP3883345B2 (en) Apartment house management system
JP4789528B2 (en) Fire alarm system for apartment houses
JP3273306B2 (en) Alarm monitoring / integration panel for multiple dwelling units and alarm monitoring / integrating system for multiple dwelling units using the same
JP3906411B2 (en) Residential information board monitoring device
JP3899451B2 (en) Vehicle security system
JP3122825B2 (en) Housing information panel
JP2002251679A (en) Disaster prevention monitoring panel
JP3678125B2 (en) Alert monitoring panel for apartment houses
JP2004171385A (en) Alarm and monitoring system for apartment house
JPS6336495A (en) Housing information system
JPH07123165A (en) Monitor controller
JPS6336497A (en) Housing information system testing equipment
JPH07129874A (en) Apartment housing management system
JPH0328108B2 (en)
JP2000331269A (en) Apartment house monitoring call system

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050926

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20061226

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070109

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070309

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070515

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070523

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110615

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110615

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120615

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130615

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees