JP3664815B2 - Roof dome construction method - Google Patents

Roof dome construction method Download PDF

Info

Publication number
JP3664815B2
JP3664815B2 JP17453896A JP17453896A JP3664815B2 JP 3664815 B2 JP3664815 B2 JP 3664815B2 JP 17453896 A JP17453896 A JP 17453896A JP 17453896 A JP17453896 A JP 17453896A JP 3664815 B2 JP3664815 B2 JP 3664815B2
Authority
JP
Japan
Prior art keywords
roof
tension ring
dome
roof dome
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP17453896A
Other languages
Japanese (ja)
Other versions
JPH1018496A (en
Inventor
和利 林
厚志 磯田
某行 馬場
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Heavy Industries Ltd
Original Assignee
Mitsubishi Heavy Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Heavy Industries Ltd filed Critical Mitsubishi Heavy Industries Ltd
Priority to JP17453896A priority Critical patent/JP3664815B2/en
Publication of JPH1018496A publication Critical patent/JPH1018496A/en
Application granted granted Critical
Publication of JP3664815B2 publication Critical patent/JP3664815B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、屋根付き球技場,競技場,テーマパーク,多目的施設建屋等の屋根を形成する屋根ドームの建設工法に関する。
【0002】
【従来の技術】
従来、屋根ドームの建設工法としては、例えば図7に示すように、地上レベルにて外周部即ち屋根ドーム底面の水平方向変形を制限するテンションリング101を架設し、その後タワークレーン,クローラクレーン等を用いて屋根シェル(骨組屋根トラス)102を順次中心部に向かって組み立てて行き、最終的に全体の屋根ドーム100を組み立てた後に屋根ドーム100の全体架構をセンターホールジャッキ等のリフトアップ機103で建屋周壁104上にリフトアップするものがある。
【0003】
【発明が解決しようとする課題】
ところが、従来の工法で屋根ドームを建設した場合、屋根の自重により屋根形状が変形するために、屋根シェルに軸力だけでなく曲げモーメントが発生し、屋根シェル部材の必要とする断面性能が大きくなる。この結果、屋根シェル部材の重量が増大し、屋根ドームのみならず建屋全体の建設工費が増大するという問題点があった。
【0004】
また、屋根形状の変形を抑えようとする場合、従来の工法ではテンションリングの断面積を上げる必要が生じ、テンションリングの重量が増大し、上記と同様に屋根ドームのみならず建屋全体の建設工費が増大する。
【0005】
屋根ドームの規模が大きくなればなるほど、屋根の自重による屋根形状の変形が大きくなるので、上記のような傾向はより大きくなる。
【0006】
そこで、本発明の目的は、屋根シェル部材の必要とする断面性能を抑制して屋根シェルの重量低減が図れる屋根ドームの建設工法を提供することにある。
【0007】
【課題を解決するための手段】
前記目的を達成するために本発明に係る屋根ドームの建設工法は、屋根ドームのうち、屋根形状が曲面シェル形状である屋根ドームを建設する際に、屋根ドーム底面の水平方向変形を制限するテンションリングに同テンションリングに埋設したケーブルを用いてプレストレスを導入し、プレストレスを導入したテンションリングを用いて屋根ドームの変形を抑えることを特徴とする。
【0008】
[作用]
本発明に係る屋根ドームの建設工法によれば、屋根ドームの自重によりテンションリングに発生する力は常に引張り力であるため、先に導入したプレストレス(圧縮力)が自重による引張り力の一部を相殺し、テンションリングに発生する引張り力を低減することができる。例えば図5に示すように、このプレストレスによって発生する逆曲げモーメントが屋根シェルの自重による曲げモーメントを相殺し、屋根シェルに発生する曲げモーメントを低減することができる。
【0009】
【発明の実施の形態】
以下、本発明に係る屋根ドームの建設工法を実施例により詳細に説明する。
【0010】
「実施例」
図1は本建設工法が適用された大型屋根ドームの平面図、図2は同じく側断面図、図3は張力ケーブルを有したテンションリングの断面図、図4は同じく工程図である。
【0011】
図1及び図2に示すように、屋根ドームにおいて、荷重を受け持つ主構造は、屋根シェル1とテンションリング2に大きく分類される。
【0012】
前記テンションリング2の内部には、図3に示すように、テンションリング2にプレストレス4を導入するためのケーブル3が複数本埋設されている。
【0013】
本建設工法では、図4に示すように、先ず地上レベルにてテンションリング2を組み立て、次に外周部から順次中心部に向かって屋根シェル1を組み立てる(架設ステップ1参照)。この組立は複数箇所に設けた架設ベント11と、図示しないトラッククレーン,クローラクレーン等の重機を利用して、各ジョイント位置の測定を実施しながら行い、また屋根仕上げ材取付用の母屋材を仮固定しておく。さらに、後で屋根仕上げ材を取り付ける際に使用する吊り足場を取り付ける。
【0014】
次に、テンションリング2に埋設されたケーブル3をジャッキで引張り、ケーブル3に張力を与え、テンションリング2にプレストレス(圧縮力)を与える。テンションリング2にプレストレスを与える工程では屋根ドームに強制変形を与えることでもあるので、テンションリング2だけでなく、屋根シェル部材にも大きな局部応力が発生しないよう十分な測量、精度管理に基づき実施される(架設ステップ2参照)。
【0015】
テンションリング2にプレストレスを与える工法として、架設ステップ1において、屋根シェル1とテンションリング2を接合する前に、予めテンションリング2にプレストレスを導入する方法もある。この場合の施工手順は、架設ステップ1において屋根シェル1の組立を行い、架設ステップ2において屋根シェル1をジャッキアップした後に屋根シェル1とテンションリング2を接合することとなる。図6にジャッキアップにより屋根シェル1に変形を与えてテンションリング2と接合する概念を示す。
【0016】
テンションリング2にプレストレスを導入した後、架設ベント11を解体し、屋根ドーム自体が自重を受け持つようにする(架設ステップ3参照)。この架設ステップ3においても、施工中に屋根シェル部材に大きな局部応力が発生しないよう十分な測量、精度管理に基づき実施される。
【0017】
次に、建屋周壁12上に屋根ドーム全体をリフトアップするウィンチ13と架台14を設置し、全体ブロックを吊り上げて建屋周壁12上に固定する(架設ステップ4参照)。母屋材の調整及び本固定はプレストレス導入の影響回避やリフトアップ重量の低減等のため、全体ブロックのリフトアップ後に行う。母屋材の本固定完了後、屋根仕上げ材を架設する。
【0018】
【発明の効果】
以上説明したように本発明によれば、テンションリングの断面積を増大させることなく、屋根形状の変形を抑えることが可能となる。屋根の変形を抑えることにより、屋根の変形によって屋根シェルに生じる曲げモーメントを抑えることができ、屋根シェル部材の必要とする断面性能を抑えることが可能となる。この結果、屋根シェルの重量低減ができ、屋根ドームのみならず建屋全体の建設工費を大幅に低減することが可能となる。
【図面の簡単な説明】
【図1】本発明の一実施例に係る屋根ドームの平面図である。
【図2】同じく側断面図である。
【図3】同じく張力ケーブルを有したテンションリングの断面図である。
【図4】本発明に係る屋根ドームの建設手順を示す説明図である。
【図5】本発明の効果を示す曲げモーメント図である。
【図6】ジャッキアップにより屋根シェルに強制変形を与える方法の説明図である。
【図7】従来の建設工法を示す説明図である。
【符号の説明】
1 屋根シェル
2 テンションリング
3 ケーブル
11 架設ベント
12 建屋周壁
13 ウィンチ
14 架台
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a construction method of a roof dome that forms a roof of a covered ball game field, a stadium, a theme park, a multipurpose facility building, or the like.
[0002]
[Prior art]
Conventionally, as a construction method of a roof dome, for example, as shown in FIG. 7, a tension ring 101 for restricting horizontal deformation of the outer peripheral portion, that is, the bottom surface of the roof dome, is erected on the ground level, and then a tower crane, a crawler crane, The roof shell (frame roof truss) 102 is sequentially assembled toward the center, and finally the entire roof dome 100 is assembled, and then the entire frame of the roof dome 100 is lifted by a lift-up machine 103 such as a center hole jack. Some lift up on the surrounding wall 104 of the building.
[0003]
[Problems to be solved by the invention]
However, when the roof dome is constructed by the conventional method, the roof shape is deformed by the weight of the roof, so that not only the axial force but also the bending moment is generated in the roof shell, and the cross-sectional performance required for the roof shell member is large. Become. As a result, there is a problem that the weight of the roof shell member increases, and the construction cost of the entire building increases as well as the roof dome.
[0004]
Also, when trying to suppress the deformation of the roof shape, the conventional construction method requires an increase in the cross-sectional area of the tension ring, which increases the weight of the tension ring. Increase.
[0005]
As the scale of the roof dome increases, the above-described tendency increases because the deformation of the roof shape due to the weight of the roof increases.
[0006]
Then, the objective of this invention is providing the construction method of the roof dome which can aim at the weight reduction of a roof shell by suppressing the cross-sectional performance which a roof shell member requires.
[0007]
[Means for Solving the Problems]
In order to achieve the above object, the roof dome construction method according to the present invention includes a tension that restricts horizontal deformation of the bottom surface of the roof dome when a roof dome having a curved shell shape is constructed. Prestress is introduced into the ring by using a cable embedded in the tension ring, and the deformation of the roof dome is suppressed by using the prestressed tension ring.
[0008]
[Action]
According to the construction method of the roof dome according to the present invention, the force generated in the tension ring by the weight of the roof dome is always a tensile force, so that the prestress (compression force) introduced earlier is a part of the tensile force by the own weight. And the tensile force generated in the tension ring can be reduced. For example, as shown in FIG. 5, the reverse bending moment generated by the prestress cancels the bending moment due to the weight of the roof shell, and the bending moment generated in the roof shell can be reduced.
[0009]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, the construction method of the roof dome according to the present invention will be described in detail with reference to examples.
[0010]
"Example"
FIG. 1 is a plan view of a large roof dome to which the present construction method is applied, FIG. 2 is a sectional side view, FIG. 3 is a sectional view of a tension ring having a tension cable, and FIG.
[0011]
As shown in FIGS. 1 and 2, the main structure responsible for loads in the roof dome is roughly classified into a roof shell 1 and a tension ring 2.
[0012]
As shown in FIG. 3, a plurality of cables 3 for introducing prestress 4 into the tension ring 2 are embedded in the tension ring 2.
[0013]
In this construction method, as shown in FIG. 4, first, the tension ring 2 is assembled on the ground level, and then the roof shell 1 is assembled from the outer peripheral portion toward the central portion in sequence (see erection step 1). This assembly is carried out while measuring each joint position by using construction vents 11 provided at a plurality of locations and heavy machinery such as a truck crane and a crawler crane (not shown), and a roof building material for attaching a roof finishing material is temporarily installed. Keep it fixed. In addition, a suspension scaffold that will be used later when attaching the roof finish is attached.
[0014]
Next, the cable 3 embedded in the tension ring 2 is pulled with a jack, tension is applied to the cable 3, and prestress (compression force) is applied to the tension ring 2. In the process of pre-stressing the tension ring 2, the roof dome is also forced to be deformed. Therefore, it is implemented based on sufficient surveying and accuracy control so that not only the tension ring 2 but also the roof shell member does not generate large local stress. (See erection step 2).
[0015]
As a method of applying prestress to the tension ring 2, there is a method in which prestress is introduced into the tension ring 2 before the roof shell 1 and the tension ring 2 are joined in the erection step 1. In the construction procedure in this case, the roof shell 1 is assembled in the erection step 1 and the roof shell 1 is jacked up in the erection step 2 and then the roof shell 1 and the tension ring 2 are joined. FIG. 6 shows a concept of joining the tension ring 2 by deforming the roof shell 1 by jacking up.
[0016]
After introducing prestress into the tension ring 2, the erection vent 11 is disassembled so that the roof dome itself takes charge of its own weight (see erection step 3). This erection step 3 is also performed based on sufficient surveying and accuracy control so that a large local stress is not generated on the roof shell member during construction.
[0017]
Next, a winch 13 and a pedestal 14 for lifting the entire roof dome are installed on the building peripheral wall 12, and the entire block is lifted and fixed on the building peripheral wall 12 (see erection step 4). The main building is adjusted and fixed after the entire block is lifted to avoid the effects of introducing prestress and reduce the lift-up weight. After the main fixing of the main building is completed, the roof finishing material will be installed.
[0018]
【The invention's effect】
As described above, according to the present invention, the deformation of the roof shape can be suppressed without increasing the cross-sectional area of the tension ring. By suppressing the deformation of the roof, the bending moment generated in the roof shell by the deformation of the roof can be suppressed, and the cross-sectional performance required for the roof shell member can be suppressed. As a result, the weight of the roof shell can be reduced, and the construction cost of the entire building as well as the roof dome can be significantly reduced.
[Brief description of the drawings]
FIG. 1 is a plan view of a roof dome according to an embodiment of the present invention.
FIG. 2 is a side sectional view of the same.
FIG. 3 is a cross-sectional view of a tension ring similarly having a tension cable.
FIG. 4 is an explanatory view showing a construction procedure of a roof dome according to the present invention.
FIG. 5 is a bending moment diagram showing the effect of the present invention.
FIG. 6 is an explanatory diagram of a method for applying a forced deformation to the roof shell by jacking up.
FIG. 7 is an explanatory view showing a conventional construction method.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Roof shell 2 Tension ring 3 Cable 11 Construction vent 12 Building surrounding wall 13 Winch 14 Mounting stand

Claims (1)

屋根ドームのうち、屋根形状が曲面シェル形状である屋根ドームを建設する際に、屋根ドーム底面の水平方向変形を制限するテンションリングに同テンションリングに埋設したケーブルを用いてプレストレスを導入し、プレストレスを導入したテンションリングを用いて屋根ドームの変形を抑えることを特徴とする屋根ドームの建設工法。When constructing a roof dome having a curved shell shape among the roof dome, a prestress is introduced using a cable embedded in the tension ring to a tension ring that restricts horizontal deformation of the bottom surface of the roof dome, A roof dome construction method characterized by suppressing deformation of the roof dome using a pre-stressed tension ring.
JP17453896A 1996-07-04 1996-07-04 Roof dome construction method Expired - Lifetime JP3664815B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17453896A JP3664815B2 (en) 1996-07-04 1996-07-04 Roof dome construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17453896A JP3664815B2 (en) 1996-07-04 1996-07-04 Roof dome construction method

Publications (2)

Publication Number Publication Date
JPH1018496A JPH1018496A (en) 1998-01-20
JP3664815B2 true JP3664815B2 (en) 2005-06-29

Family

ID=15980296

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17453896A Expired - Lifetime JP3664815B2 (en) 1996-07-04 1996-07-04 Roof dome construction method

Country Status (1)

Country Link
JP (1) JP3664815B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185188A (en) * 2019-06-04 2019-08-30 中国十九冶集团有限公司 Large-span reticulated shell installation method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113323138A (en) * 2021-06-01 2021-08-31 华电重工股份有限公司 Truss structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185188A (en) * 2019-06-04 2019-08-30 中国十九冶集团有限公司 Large-span reticulated shell installation method

Also Published As

Publication number Publication date
JPH1018496A (en) 1998-01-20

Similar Documents

Publication Publication Date Title
JP6831714B2 (en) Tower crane foundation and tower crane
JP3664815B2 (en) Roof dome construction method
JPH06101274A (en) Method of constructing roof of cable dome
JP3426339B2 (en) Construction method of large building with dome roof
JPH1077749A (en) Roof constructing method for tower-shaped structure
JP3215059B2 (en) Construction method of tower-like structure roof
JPH108626A (en) Construction method of roof dome
JPH10325182A (en) Construction method of dome-shaped roof
JP2529067B2 (en) Crane flexible climbing method
JP3939237B2 (en) How to construct a girder frame
JP6917720B2 (en) How to build a composite suspended structure
JPH10184015A (en) Method for constructing roof dome
CN110552542A (en) Construction method of conical building structure
JP2858891B2 (en) Construction method of large span dome roof
JP2001059271A (en) Construction method of dome-like roof
JP3017461B2 (en) Construction method of the inspection walkway inside the tower
JP2994205B2 (en) Structural assembly method
JP6814717B2 (en) How to install horizontal members and how to build a building frame
JPH0718743A (en) Construction method for large span domelike roof
JP3506022B2 (en) How to build a dome roof
JP2000045542A (en) Foundation base isolation method for existing structure
JP3110876B2 (en) Dome roof and construction method
JP4698184B2 (en) Climbing crane support method and support jig
JP2696486B2 (en) Building construction method
JPH1162089A (en) Construction method for shell type dome roof

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040824

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20041019

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20041220

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050308

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050330

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080408

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090408

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100408

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110408

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130408

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140408

Year of fee payment: 9

EXPY Cancellation because of completion of term