JP3544534B2 - Tunnel section widening method - Google Patents

Tunnel section widening method Download PDF

Info

Publication number
JP3544534B2
JP3544534B2 JP2001228224A JP2001228224A JP3544534B2 JP 3544534 B2 JP3544534 B2 JP 3544534B2 JP 2001228224 A JP2001228224 A JP 2001228224A JP 2001228224 A JP2001228224 A JP 2001228224A JP 3544534 B2 JP3544534 B2 JP 3544534B2
Authority
JP
Japan
Prior art keywords
tunnel
widening
section
tunnel lining
constructed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2001228224A
Other languages
Japanese (ja)
Other versions
JP2003041882A (en
Inventor
兵次 中村
正男 増野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pacific Consultants Co Ltd
Original Assignee
Pacific Consultants Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pacific Consultants Co Ltd filed Critical Pacific Consultants Co Ltd
Priority to JP2001228224A priority Critical patent/JP3544534B2/en
Publication of JP2003041882A publication Critical patent/JP2003041882A/en
Application granted granted Critical
Publication of JP3544534B2 publication Critical patent/JP3544534B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

【0001】
【発明の属する技術分野】
この発明は例えば地下道路或いは地下鉄、下水道等を構成するトンネルの施工方法に関し、特にトンネルの一部区間に待避、分岐、合流等のための断面拡幅部を簡素に構築することを可能としたトンネル断面拡幅工法を提案しようとするものである。
【0002】
【従来の技術】
従来よりトンネル工事には一般にシールド工法が取られている。シールド工法は一旦シールド機を掘削進路上に設置してしまえば、シールド機が掘進し、トンネル覆工も構築してしまうため、地上に影響を与えることなくトンネルを構築することができることから、同一径が連続したトンネルを構築するには優れた工法である。
これに対し、例えば地下道路の分岐合流部では図7及び図8に示すように、本線トンネル1の車線数に加えて減速車線又は加速車線を構築するための拡幅トンネル2が必要になる。トンネルの分岐合流部におけるトンネル断面の拡幅は、従来の施工技術では本線トンネルを含めた開削工法により構築している。
【0003】
本線トンネル1と、拡幅トンネル2とを含む全体を開削する場合、幅が数10メートル、長さが約数100メートルに達するため、施工に必要な占有幅及び占有面積が広くなることから、周辺環境に与える影響が大きく、施工における重要な課題であった。
このため、開削工法で施工する範囲を可能な限り縮小し、シールド工法を応用したトンネル断面拡幅工法が考えられている。図9はその一例を示す。図9に示す例では主シールド機3により本線トンネル1を掘進し、拡幅区間の始端位置に立抗4を構築し、この立坑4を通じて側部シールド機5A、5Bを地下に降ろし、この側部シールド機5A、5Bを主シールド機3の両側に装着する。主シールド機3の両側に側部シールド機5A、5Bを装着した複合シールド機により拡幅区間を掘進し、拡幅トンネル2を構築する。拡幅区間の終端位置には再び立抗を形成し、この立抗を通じて側部シールド機5A、5Bを地下から撤去する。
【0004】
【発明が解決しようとする課題】
現状のトンネル拡幅工法は、欠点として以下の事項が挙げられる。
(1)拡幅断面をシールド機で一括施工する場合、拡幅断面の端部に立抗を設けてシールド機の組立て及び改造を行うため、この部分には大規模な開削工事を伴う。
(2)トンネル断面幅の大きなシールド機で掘進するため、トンネル土被りが小さいと地表面に地盤沈下などの影響を及ぼす可能性が高くなる。
【0005】
(3)シールド機の組立て及び改造には大規模な施工設備が必要になるため、立抗上部(一般に公道)を長期間占有し、地上への影響が大きい。
(4)地中でトンネル断面を拡大する場合には大規模な地盤改良工事を伴うため、施工に要する日数及び費用が多くかかる。
(5)道路トンネルの分岐合流部を構築するにはトンネル断面の拡幅工法の他に分岐のための施工技術が必要となる。
この発明の目的は地上への影響を小さくし、大規模な開削工事を伴うことなく、拡幅部を構築することができるトンネル断面拡幅工法を提案するものである。
【0006】
【課題を解決するための手段】
この発明の請求項1では、本線トンネルの一部区間に拡幅トンネルを設けるトンネル断面拡幅工法において、拡幅トンネルを構築すべき位置に、この拡幅トンネルに接して構築されるべき本線トンネル覆工の、構築仮想位置に向って開口面が配置され、断面がほぼコ字状の拡幅トンネル覆工を構築すると共に、この拡幅トンネル覆工の上床版及び下床版の先端に接してシールド工法により本線トンネル覆工を構築するトンネル断面拡幅工法を提案する。
【0007】
この発明の請求項2では、請求項1記載のトンネル断面拡幅工法において、拡幅トンネル覆工は開削工法により構築され、コ字状断面の開口面を塞ぐ仮壁を開口面より内側に仮設し、上床版と下床版を結合する支保材の役割を持たせるとともにこの仮壁の外側に土砂を埋め戻して本線トンネル覆工を構築するトンネル断面拡幅工法を提案する。
この発明の請求項3では、請求項1記載のトンネル断面拡幅工法において、拡幅トンネル覆工はシールド工法により構築され、拡幅トンネル覆工の構築と共に開口面から内側に開口面を塞ぐ仮壁を構築し、上床版と下床版を結合する支保材の役割を持たせるとともにこの仮壁の外側に土砂を埋め戻して本線トンネル覆工を構築するトンネル断面拡幅工法を提案する。
【0008】
この発明の請求項4では、請求項1、2、3記載のトンネル断面拡幅工法の何れかにおいて、本線トンネル覆工を構築するための施工は、拡幅トンネル覆工を構成する上床版及び下床版の双方の先端の一部を切削範囲に含むシールド工法により施工するトンネル断面拡幅工法を提案する
【0009】
更に、一方の側部が開口されたコ字状断面を持つ拡幅トンネル覆工を構築し、このコ字状断面を持つ拡幅トンネル覆工の開口面に接触させて本線トンネル覆工を構築するから、本線トンネルと拡幅トンネルとの接合を簡素に達することができる
【0010】
【発明の実施の形態】
図1乃至図6にこの発明によるトンネル断面拡幅工法の一実施例を示す。この実施例では拡幅トンネル覆工を開削工法によって構築した場合を示す。
つまり、図1に示すように、拡幅トンネル覆工11の幅に相当する間隙を隔てて2連の土留め壁12−12を形成する。土留め壁12−12で囲まれた部分の土砂を掘り出し、その底部に断面がほぼコ字状の拡幅トンネル覆工11を構築する。拡幅トンネル覆工11の形状は本線トンネル覆工が構築されると仮想される面側が開口されたほぼコ字状の断面形状を有する。また開口面側が漸次外広となる形状とし、この形状により円筒状の本線トンネル覆工との接合強度を高める構造とした場合を示す。
【0011】
拡幅トンネル覆工11の内部には仮壁13を形成する。更に、拡幅トンネル覆工11の上床版11Aと下床版11Bのそれぞれの外側にスライドフード14を装着する。このスライドフード14は拡幅トンネル覆工11に形成した長孔等を通じて拡幅トンネル覆工11の内部から本線トンネルが構築される側に向って自由にスライド操作ができるように構成される。
拡幅トンネル覆工11及び仮壁13、スライドフード14が装着された状態で土留め壁12−12を撤去し、拡幅トンネル覆工11の上部に土砂を埋め戻す(図2参照)。10は埋め戻した土砂を示す。このとき、拡幅トンネル覆工11の仮壁13と開口面で囲まれる部分にも土砂10を充填する。
【0012】
土砂を埋め戻し拡幅トンネル覆工11を土砂の中に埋設した状態で、拡幅トンネル覆工11の開口面に接触する位置にシールド機を掘進させる。図3にその様子を示す。図3に示す破線15はシールド機掘削線を示す。シールド機は拡幅トンネル覆工11の上床版11Aと下床版11Bの先端の一部を切削しながら掘進する。このためには上床版11Aと下床版11Bの先端には鉄筋類を含まない施工を施す。このように上床版11A及び下床版11Bの先端部分を切削しながら本線トンネル覆工16を構築することにより、図4に示すように本線トンネル覆工16と拡幅トンネル覆工11とを可及的に接近させて構築することができ、特に本線トンネル覆工16と拡幅トンネル覆工11との間が大きく離れ、その間隙部分から土砂が崩落する事故が発生することを回避することができる。
【0013】
に拡幅トンネル覆工11の上床版11Aと下床版11Bのそれぞれの外側にスライドフード14を設けているから、本線トンネル覆工16が構築された位置ではスライドフード14を本線トンネル覆工16側に移動させ、スライドフード14により本線トンネル覆工16と拡幅トンネル覆工11との間に発生するわずかな間隙も遮蔽することができる
図5にその詳細を示す。本線トンネル覆工16の外周にはシールド工法で施される裏込め注入材17が配置される。スライドフード14を本線トンネル覆工16に向って移動させることにより、スライドフード14の先端は裏込め注入材17の層に突き刺さる。この状態でスライドフード14に内蔵した注入管から地盤改良剤を注入し、スライドフード14と裏込め注入材17との接合部分の土砂を地盤改良(固形化)し、拡幅トンネル覆工11の上床版11Aと下床版11Bと本線トンネル覆工16との間の間隙部分を防水構造とする。図5に示す18は地盤改良剤により固形化された防水処理部を示す。
【0014】
スライドフード14により応急的に防水処理部18を得るのと平行して、拡幅トンネル覆工11に設けた仮壁13と、拡幅トンネル覆工11で囲まれた本線トンネル覆工16のセグメント16A(図6に点線で示す)を撤去し、拡幅トンネル覆工11と本線トンネル覆工16との間を恒久的に結合する工事を施工することにより図6に示す本線トンネル1と拡幅トンネル2が互に連通したトンネルを得ることができる。
以上は拡幅トンネル覆工11を開削工法により構築した場合を説明したが、拡幅トンネル覆工11をシード工法により構築することもできる。シールド工法により拡幅トンネル覆工11を構築する場合には掘進面を拡幅トンネルの断面形状に設定したシールド機を用意し、掘進と同時に周辺にセグメントを張り巡らす。この場合、拡幅トンネル覆工11と共に仮壁13を構築することにより地中で図2に示した拡幅トンネル覆工11と仮壁13とを構築することができる。図2に示した状態が構築された後の工法は図3乃至図5に示した工法と同じであるから、ここではこれ以上の説明は省略する。
【0015】
【発明の効果】
以上説明したように、この発明によれば予め断面形状がほぼコ字状の拡幅トンネル覆工11を構築して用意し、この拡幅トンネル覆工11の開口面に沿って本線トンネル覆工16をシールド工法により構築し、本線トンネル覆工16の一部を撤去して拡幅トンネルと本線トンネルとを連通させて拡幅部を構築したから、簡単な工事でトンネルに拡幅部を設けることができる。特に、拡幅トンネル覆工11を開削工法で構築する場合は幅が約10メートル程度、長さが数100メートル程度であるから、従来の開削工法と比較して小さい開削面積で済ませることができるため、地上への影響を小さくすることができる。また、長さが約数100メートル程度の拡幅トンネルを構築する場合に、シールド工法で構築することも考えられるが、わずかな区間をシールド機を用いて構築するより開削工法を採った方が工費を安価に済ませることができる。
【図面の簡単な説明】
【図1】この発明によるトンネル断面拡幅工法の初期工程の一例を説明するための断面図。
【図2】図1に示した工程の次の工程を説明するための断面図。
【図3】図2に示した工程の次の工程を説明するための断面図。
【図4】図3に示した工程により本線トンネル覆工が構築された状況を説明するための断面図。
【図5】図4に示した状況で施される防水処理の工程を説明するための断面図。
【図6】この発明の工法により構築された本線トンネルと拡幅トンネルの完成状況を説明するための断面図。
【図7】トンネルの一部区間に拡幅部が必要になる実例を説明するための断面図。
【図8】図7に示したA−A線上の断面図。
【図9】従来のトンネル断面拡幅工法を説明するための斜視図。
【符号の説明】
1 本線トンネル
2 拡幅トンネル
11 拡幅トンネル覆工
11A 上床版
11B 下床版
12 土留め壁
13 仮壁
14 スライドフード
15 シールド機掘削線
16 本線トンネル覆工
17 裏込め注入材
18 防水処理部
[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a method of constructing a tunnel constituting, for example, an underground road, a subway, a sewer, and the like, and more particularly to a tunnel capable of simply constructing a widened section for evacuation, branching, merging, etc. in a part of the tunnel. It is intended to propose a section widening method.
[0002]
[Prior art]
Conventionally, tunnel construction has generally employed a shield method. The shield method is the same because once the shield machine is installed on the excavation path, the shield machine will excavate and construct the tunnel lining, so the tunnel can be constructed without affecting the ground. This is an excellent method for constructing a tunnel with a continuous diameter.
On the other hand, for example, as shown in FIG. 7 and FIG. 8, in addition to the number of lanes of the main road tunnel 1, a widening tunnel 2 for constructing a deceleration lane or an acceleration lane is required at a branch junction of an underground road. The widening of the tunnel cross section at the branch junction of the tunnel is constructed by the open-cutting method including the main line tunnel in the conventional construction technology.
[0003]
When digging the whole, including the main tunnel 1 and the widening tunnel 2, the width reaches several tens of meters and the length reaches approximately several hundred meters, so the occupied width and occupied area required for construction are increased, It had a significant impact on the environment and was an important issue in construction.
For this reason, a tunnel section widening method using a shield method has been considered, in which the area to be constructed by the open-cut method is reduced as much as possible. FIG. 9 shows an example. In the example shown in FIG. 9, the main tunnel 1 is dug by the main shield machine 3, a pier 4 is constructed at the start end position of the widening section, and the side shield machines 5A and 5B are lowered to the underground through the pit 4. The shield machines 5A and 5B are mounted on both sides of the main shield machine 3. The widened section is dug by the composite shield machine in which the side shield machines 5A and 5B are mounted on both sides of the main shield machine 3, and the wide tunnel 2 is constructed. A stand is formed again at the end position of the widening section, and the side shield machines 5A and 5B are removed from underground through the stand.
[0004]
[Problems to be solved by the invention]
The current tunnel widening method has the following disadvantages as disadvantages.
(1) When collectively constructing the widened cross section with a shield machine, a large-scale open-cutting work is involved in assembling and remodeling the shield machine by providing a stand at the end of the widened cross section.
(2) Since the tunnel is excavated by a shield machine having a large tunnel section width, if the tunnel cover is small, there is a high possibility that the ground surface will have an influence such as land subsidence.
[0005]
(3) Since large-scale construction equipment is required for assembling and remodeling the shield machine, it occupies the upper part of the pier (generally, a public road) for a long time, and has a large influence on the ground.
(4) When the tunnel section is expanded underground, large-scale ground improvement work is required, so that the number of days and costs required for the construction are large.
(5) In order to construct a branch junction of a road tunnel, a construction technique for branching is required in addition to a method of widening a tunnel section.
An object of the present invention is to propose a tunnel section widening method capable of constructing a widened portion with a reduced influence on the ground and without large-scale excavation work.
[0006]
[Means for Solving the Problems]
According to claim 1 of the present invention, in the tunnel section widening method of providing a widened tunnel in a partial section of the main tunnel, a main line tunnel lining to be constructed in contact with the widened tunnel is provided at a position where the widened tunnel is to be constructed. An opening surface is arranged toward the virtual construction position, and a wide-width tunnel lining with a substantially U-shaped cross section is constructed, and the main line tunnel is in contact with the top and bottom floor slabs of this wide-width tunnel lining by a shield method. We propose a tunnel section widening method to construct lining.
[0007]
According to a second aspect of the present invention, in the tunnel section widening method according to the first aspect, the widening tunnel lining is constructed by an open-cutting method, and a temporary wall that closes an opening surface of the U-shaped cross section is temporarily provided inside the opening surface, We propose a method of widening the tunnel section, which has the role of a supporting material to join the upper and lower slabs, and bury the earth and sand outside the temporary wall to construct the main line tunnel lining.
According to a third aspect of the present invention, in the widening method of the tunnel section according to the first aspect, the widening tunnel lining is constructed by a shield method, and together with the construction of the widening tunnel lining, a temporary wall that closes the opening surface from the opening surface to the inside is constructed. Then, we propose a method of widening the tunnel cross section, which has the role of a supporting material to join the upper and lower slabs, and bury the earth and sand outside the temporary wall to construct the main line tunnel lining.
[0008]
According to claim 4 of the present invention, in any of the tunnel section widening methods according to claims 1, 2, and 3, the construction for constructing the main line tunnel lining includes the upper floor slab and the lower floor constituting the widening tunnel lining. This paper proposes a tunnel section widening method that uses a shield method that includes both ends of the plate in the cutting area .
[0009]
Furthermore, a wide-width tunnel lining having a U-shaped cross section with one side opened is constructed, and the main line tunnel lining is constructed by making contact with the opening surface of the wide-width tunnel lining having the U-shaped cross section. Thus, the junction between the main tunnel and the widening tunnel can be easily achieved .
[0010]
BEST MODE FOR CARRYING OUT THE INVENTION
1 to 6 show one embodiment of the tunnel section widening method according to the present invention. This embodiment shows a case where the widening tunnel lining is constructed by the open-cutting method.
That is, as shown in FIG. 1, two continuous retaining walls 12-12 are formed with a gap corresponding to the width of the widened tunnel lining 11. The earth and sand in a portion surrounded by the retaining walls 12-12 is dug, and a widened tunnel lining 11 having a substantially U-shaped cross section is constructed at the bottom thereof. The shape of the widened tunnel lining 11 has a substantially U-shaped cross-sectional shape in which a virtual side is opened when the main line tunnel lining is constructed. Further, a case is shown in which the opening surface side is gradually widened outward, and the structure is such that the bonding strength with the cylindrical main line tunnel lining is enhanced by this shape.
[0011]
A temporary wall 13 is formed inside the widening tunnel lining 11. Further, slide hoods 14 are mounted on the outer sides of the upper deck 11A and the lower deck 11B of the widening tunnel lining 11, respectively. The slide hood 14 is configured such that the slide hood 14 can be freely slid from the inside of the widened tunnel lining 11 to the side where the main line tunnel is constructed through a long hole or the like formed in the widened tunnel lining 11.
The retaining wall 12-12 is removed with the widening tunnel lining 11, the temporary wall 13, and the slide hood 14 attached thereto, and the sand is buried in the upper portion of the widening tunnel lining 11 (see FIG. 2). Numeral 10 indicates backfilled earth and sand. At this time, the portion surrounded by the temporary wall 13 and the opening surface of the widening tunnel lining 11 is also filled with the earth and sand 10.
[0012]
With the earth and sand backfilled and the widening tunnel lining 11 buried in the earth and sand, the shield machine is excavated to a position in contact with the opening surface of the widening tunnel lining 11. FIG. 3 shows this state. A broken line 15 shown in FIG. 3 indicates a shield machine excavation line. The shield machine excavates while cutting a part of the tip of the upper deck 11A and the lower deck 11B of the widening tunnel lining 11. For this purpose, the tops of the upper slab 11A and the lower slab 11B are subjected to construction that does not include reinforcing bars. By constructing the main line tunnel lining 16 while cutting the end portions of the upper floor slab 11A and the lower floor slab 11B in this way, the main line tunnel lining 16 and the widening tunnel lining 11 can be formed as shown in FIG. In particular, it is possible to avoid that the main line tunnel lining 16 and the widening tunnel lining 11 are largely separated from each other, and that an accident in which the earth and sand collapses from the gap portion occurs.
[0013]
Since further the have a sliding hood 14 is provided on each outer side of the top floor plate 11A and the lower deck 11B of expansion width tunnel lining 11, main tunnel lining slides hood 14 is at a position where the main line tunnel lining 16 is constructed 16, the slide hood 14 can also shield a slight gap generated between the main line tunnel lining 16 and the widening tunnel lining 11.
FIG. 5 shows the details. On the outer periphery of the main line tunnel lining 16, a backfill injection material 17 applied by a shield method is arranged. By moving the slide hood 14 toward the main line tunnel lining 16, the tip of the slide hood 14 pierces the layer of the backfill material 17. In this state, a soil improvement agent is injected from an injection pipe built in the slide hood 14, and the soil at the joint between the slide hood 14 and the backfilling material 17 is ground improved (solidified), and the upper floor of the widening tunnel lining 11 is laid. The gap between the plate 11A, the lower deck 11B, and the main line tunnel lining 16 has a waterproof structure. Reference numeral 18 shown in FIG. 5 denotes a waterproofing portion solidified by the ground improving agent.
[0014]
In parallel with obtaining the waterproofing portion 18 by the slide hood 14 in an emergency, the temporary wall 13 provided on the widened tunnel lining 11 and the segment 16A of the main line tunnel lining 16 surrounded by the widened tunnel lining 11 ( 6 (represented by a dotted line in FIG. 6), and a construction for permanently connecting the widening tunnel lining 11 and the main tunnel lining 16 is carried out, whereby the main tunnel 1 and the widening tunnel 2 shown in FIG. You can get a tunnel that communicates with.
Although the case where the widening tunnel lining 11 is constructed by the open-cutting method has been described above, the widening tunnel lining 11 can also be constructed by the seeding method. When constructing the widening tunnel lining 11 by the shield method, a shield machine whose excavation surface is set to the cross-sectional shape of the widening tunnel is prepared, and segments are spread around the excavation simultaneously with excavation. In this case, by constructing the temporary wall 13 together with the widening tunnel lining 11, the widening tunnel lining 11 and the temporary wall 13 shown in FIG. 2 can be constructed underground. Since the construction method after the state shown in FIG. 2 is constructed is the same as the construction method shown in FIGS. 3 to 5, further description is omitted here.
[0015]
【The invention's effect】
As described above, according to the present invention, the widened tunnel lining 11 having a substantially U-shaped cross section is constructed and prepared in advance, and the main line tunnel lining 16 is formed along the opening surface of the widened tunnel lining 11. Since the widening part is constructed by the shield method, a part of the main line tunnel lining 16 is removed, and the widening tunnel and the main line tunnel are connected to each other, the widening part can be provided in the tunnel by simple construction. In particular, when the widening tunnel lining 11 is constructed by the open-cutting method, since the width is about 10 meters and the length is about several 100 meters, the cut-off area can be reduced compared to the conventional open-cut method. , The influence on the ground can be reduced. In addition, when constructing a wide tunnel with a length of about several hundred meters, it is conceivable to construct with a shield method, but it is more costly to adopt open cut method than to construct a small section using a shield machine. Can be done at low cost.
[Brief description of the drawings]
FIG. 1 is a sectional view for explaining an example of an initial step of a tunnel section widening method according to the present invention.
FIG. 2 is a sectional view for explaining a step subsequent to the step shown in FIG. 1;
FIG. 3 is a sectional view for explaining a step subsequent to the step shown in FIG. 2;
FIG. 4 is a cross-sectional view for explaining a state where the main line tunnel lining has been constructed by the process shown in FIG. 3;
FIG. 5 is a cross-sectional view for explaining a waterproofing process performed in the situation shown in FIG. 4;
FIG. 6 is a cross-sectional view for explaining a completed state of the main line tunnel and the widening tunnel constructed by the method of the present invention.
FIG. 7 is a sectional view for explaining an actual example in which a widened portion is required in a partial section of a tunnel.
FIG. 8 is a sectional view taken along the line AA shown in FIG. 7;
FIG. 9 is a perspective view for explaining a conventional tunnel section widening method.
[Explanation of symbols]
1 Main Line Tunnel 2 Widening Tunnel 11 Widening Tunnel Lining 11A Upper Floor Slab 11B Lower Floor Slab 12 Retaining Wall 13 Temporary Wall 14 Slide Hood 15 Shield Machine Drilling Line 16 Main Line Tunnel Lining 17 Backfill Injection Material 18 Waterproofing Section

Claims (4)

本線トンネルの一部区間に拡幅トンネルを設けるトンネル断面拡幅工法において、
拡幅トンネルを構築すべき位置に、この拡幅トンネルに接して構築されるべき本線トンネル覆工の、構築仮想位置に向って開口面が配置され、断面がほぼコ字状の拡幅トンネル覆工を構築すると共に、この拡幅トンネル覆工の上床版及び下床版の先端に接してシールド工法により本線トンネル覆工を構築することを特徴とするトンネル断面拡幅工法。
In the tunnel cross-section widening method of installing a widening tunnel in a section of the main line tunnel,
At the position where the widening tunnel is to be constructed, the opening surface of the main line tunnel lining to be built in contact with this widening tunnel is arranged toward the virtual construction position, and the widening tunnel lining with a substantially U-shaped cross section is constructed A tunnel cross-section widening method comprising constructing a main line tunnel lining by a shield method in contact with the top and bottom floor slabs of the widening tunnel lining.
請求項1記載のトンネル断面拡幅工法において、上記拡幅トンネル覆工は開削工法により構築され、コ字状断面の開口面を塞ぐ仮壁を開口面より内側に仮設し、上床版と下床版を結合する支保材の役割を持たせるとともにこの仮壁の外側に土砂を埋め戻して本線トンネル覆工を構築することを特徴とするトンネル断面拡幅工法。2. The tunnel section widening method according to claim 1, wherein the widening tunnel lining is constructed by an open-cutting method, and a temporary wall closing the opening surface of the U-shaped cross section is temporarily provided inside the opening surface, and the upper floor slab and the lower floor slab are combined. A tunnel cross-section widening method characterized by having a role as a supporting material to be joined and constructing a main line tunnel lining by burying earth and sand outside the temporary wall. 請求項1記載のトンネル断面拡幅工法において、上記拡幅トンネル覆工はシールド工法により構築され、拡幅トンネル覆工の構築と共に開口面から内側に開口面を塞ぐ仮壁を構築し、上床版と下床版を結合する支保材の役割を持たせるとともにこの仮壁の外側に土砂を埋め戻して本線トンネル覆工を構築することを特徴とするトンネル断面拡幅工法。2. The tunnel cross-section widening method according to claim 1, wherein the widening tunnel lining is constructed by a shield method, and a temporary wall for closing the opening surface from the opening surface to the inside is constructed together with the construction of the widening tunnel lining. A tunnel cross-section widening method characterized by having a role of a supporting material for joining the plates and constructing a main line tunnel lining by burying earth and sand outside the temporary wall. 請求項1、2、3記載のトンネル断面拡幅工法の何れかにおいて、上記本線トンネル覆工を構築するための施工は、上記拡幅トンネル覆工を構成する上床版及び下床版の双方の先端の一部を切削範囲に含むシールド工法により施工することを特徴とするトンネル断面拡幅工法。In any of the tunnel cross-section widening methods according to claims 1, 2, and 3, the construction for constructing the main line tunnel lining is performed at both ends of an upper floor slab and a lower floor slab constituting the widening tunnel lining. A tunnel cross-section widening method characterized by being constructed by a shield method that partially covers the cutting area.
JP2001228224A 2001-07-27 2001-07-27 Tunnel section widening method Expired - Fee Related JP3544534B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001228224A JP3544534B2 (en) 2001-07-27 2001-07-27 Tunnel section widening method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001228224A JP3544534B2 (en) 2001-07-27 2001-07-27 Tunnel section widening method

Publications (2)

Publication Number Publication Date
JP2003041882A JP2003041882A (en) 2003-02-13
JP3544534B2 true JP3544534B2 (en) 2004-07-21

Family

ID=19060766

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001228224A Expired - Fee Related JP3544534B2 (en) 2001-07-27 2001-07-27 Tunnel section widening method

Country Status (1)

Country Link
JP (1) JP3544534B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5005604B2 (en) * 2008-04-04 2012-08-22 新日本製鐵株式会社 Tunnel structure
KR101560527B1 (en) * 2015-06-25 2015-10-14 함정아 Construction method for tunneling
CN112814695B (en) * 2021-02-02 2024-04-12 上海隧道工程有限公司 Emergency stop belt for shield method submarine highway tunnel and construction method thereof

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0765454B2 (en) * 1989-05-09 1995-07-19 建設省土木研究所長 Tunnel part expansion shield construction method and its equipment, and induction segment piece related thereto
JP2816397B2 (en) * 1990-06-29 1998-10-27 清水建設株式会社 Method of expanding and reducing diameter of tunnel
JP2942874B2 (en) * 1990-11-02 1999-08-30 清水建設株式会社 How to join tunnels
JP3567401B2 (en) * 1996-06-07 2004-09-22 清水建設株式会社 Large section tunnel and its construction method

Also Published As

Publication number Publication date
JP2003041882A (en) 2003-02-13

Similar Documents

Publication Publication Date Title
JP4881555B2 (en) Construction method of underground structure
JPH035600A (en) Construction method for shield tunnel branches and joints and temporary bulkhead construction equipment for branches and joints
JP4205615B2 (en) How to construct a confluence of shield tunnels
JP3893056B2 (en) Construction method of underground structure
JP3544534B2 (en) Tunnel section widening method
JP4888725B2 (en) Tunnel construction method
JP4074214B2 (en) Shield excavation machine and ground excavation method using the same
JP2594863B2 (en) Underground tunnel widening method and branching / merging section construction method
JP3765048B2 (en) How to build a tunnel
JPH11152986A (en) Protection method for shielding excavation in section covered with thin soil layer
JP2004211361A (en) Branch junction construction method of shield tunnel
JP3908978B2 (en) Junction structure and junction construction method for large-section tunnel segments
JP4303512B2 (en) Construction method of large section tunnel
JP2003148086A (en) Construction method of junction of tunnel
JP4303511B2 (en) Construction method of large section tunnel
KR102649959B1 (en) Longitudinal and lateral integration structure of pile and structure manufactured using the same
JP4349570B2 (en) Construction method of division box and underground level crossing
JPH04309692A (en) Underground space construction method
JP4322688B2 (en) Construction method of large section tunnel
JP4185401B2 (en) Construction method of large section tunnel using divided box
KR101620787B1 (en) underground excavation construction method
JP4397797B2 (en) Construction method of underground structure
JP3567399B2 (en) Large section tunnel and its construction method
JP2003206697A (en) Construction method for underground structures
JP2840122B2 (en) Shield excavator and tunnel construction method using the shield excavator

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20031209

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040206

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040309

RD01 Notification of change of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7426

Effective date: 20040402

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040402

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080416

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090416

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100416

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100416

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110416

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110416

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120416

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130416

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees