JP3487201B2 - Construction method of underwater tunnel and underwater excavator - Google Patents

Construction method of underwater tunnel and underwater excavator

Info

Publication number
JP3487201B2
JP3487201B2 JP35015398A JP35015398A JP3487201B2 JP 3487201 B2 JP3487201 B2 JP 3487201B2 JP 35015398 A JP35015398 A JP 35015398A JP 35015398 A JP35015398 A JP 35015398A JP 3487201 B2 JP3487201 B2 JP 3487201B2
Authority
JP
Japan
Prior art keywords
box
tunnel
excavator
ground
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP35015398A
Other languages
Japanese (ja)
Other versions
JP2000170187A (en
Inventor
久夫 今藤
隆 三井
雄一 芳野
忍 高橋
清一郎 滝沢
茂希 本間
秀夫 田中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP35015398A priority Critical patent/JP3487201B2/en
Publication of JP2000170187A publication Critical patent/JP2000170187A/en
Application granted granted Critical
Publication of JP3487201B2 publication Critical patent/JP3487201B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】この発明は、陸上の製作ヤー
ドでプレキャスト方式で予め製作されたトンネル函体エ
レメント(以下「函体」という)を複数、互いに接合し
ながら水底の地盤面下に設置して水底トンネルを構築す
る水底トンネルの構築工法及びこの工法で使用される水
底掘進機に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention is to install a plurality of tunnel box elements (hereinafter referred to as "boxes") prefabricated by a precast method in an onshore production yard while connecting them to each other below the ground surface of the water bottom. TECHNICAL FIELD The present invention relates to a construction method of a subsea tunnel for constructing a subsea tunnel and a submersible machine used in this construction method.

【0002】[0002]

【従来の技術】これまで、海底トンネル等のように水面
下で連続するトンネルを構築する方法として、沈埋トン
ネル工法が一般に知られている。沈埋トンネル工法は、
函体を基礎工事の終了した計画地点まで曳航し、そして
そこで函体の沈設と接合をおこなって水底に連続するト
ンネルを構築しようとするものである。
2. Description of the Related Art Up to now, a submerged tunnel method has been generally known as a method for constructing a continuous tunnel under the surface of water such as an undersea tunnel. The submerged tunnel method is
The purpose is to tow the box to the planned site where the foundation work has been completed, and then to sunk and join the box to construct a continuous tunnel at the bottom of the water.

【0003】しかし、このような構築工法では、計画地
点で浚渫などの基礎工事を行う必要があるほか、函体の
製作ヤードから計画地点まで函体を一個一個曳航する必
要があるため、その間度々航路を塞いでしまう等の課題
があった。
However, in such a construction method, it is necessary to carry out foundation work such as dredging at the planned point, and it is necessary to tow each box from the box production yard to the planned point. There were problems such as blocking the route.

【0004】この発明は、以上の課題を解決するために
なされたもので、特に主航路上の船舶の往来を妨げず
に、水底トンネルの施工をきわめて効率的に行えるよう
にした水底トンネルの構築工法および水底掘進機を提供
することを目的とする。
The present invention has been made in order to solve the above problems, and in particular, the construction of a submarine tunnel that enables extremely efficient construction of a submarine tunnel without hindering the movement of ships on the main route. The purpose is to provide a construction method and a submersible machine.

【0005】[0005]

【課題を解決するための手段】請求項1記載の水底トン
ネルの構築工法は、水底の地盤を掘進しつつ、掘進後の
地盤上に複数の函体を互いに接合しながら設置して水底
トンネルを構築する水底トンネルの構築工法において、
複数の新設函体を水中に沈め、既設函体上を先頭の既設
函体までスライドさせた後、先頭の既設函体の前に順に
設置して連続するトンネルを構築することを特徴とする
ものである。
A water bottom ton according to claim 1.
The construction method of the flannel is a construction method of a subsea tunnel in which a subsea tunnel is constructed by digging the submerged ground and installing a plurality of boxes on the submerged ground while joining each other.
Plural new boxes are submerged in water, and the top of the existing box is already installed.
It is characterized in that after sliding to the box, it is installed in order in front of the existing box at the top to build a continuous tunnel.

【0006】 請求項2記載の水底トンネルの構築工法
は、請求項1記載の水底トンネルの構築工法において、
前記複数の函体は、函体の上端部にガイドレール、函体
の下端部にガイド溝を設けてあり、互いに係合し掘進方
向にスライド可能であることを特徴とするものである。
The construction method of the undersea tunnel according to claim 2 is the construction method of the undersea tunnel according to claim 1, wherein
The plurality of boxes includes a guide rail and a box at the upper end of the box.
A guide groove is provided at the lower end of the
It is characterized in that it can slide in the direction.

【0007】 請求項3記載の水底掘進機は、水底の地
盤を掘進しつつ、掘進後の地盤上に複数の函体を互いに
接合しながら設置して水底トンネルを構築する際に使用
される水底掘進機において、新設函体を上から収納しテ
ール部から掘進後の地盤上に出せるように上端部とテー
ル部が開口する函状をなし、先端部に水底の地盤を掘進
する掘進手段を、テール部に前進するための推進ジャッ
キを、上端部に前記新設函体を引っ張って既設函体上を
先頭の既設函体までスライドさせるウィンチをそれぞれ
備えてなるを特徴とするものである。
A submarine excavator according to claim 3 is used for constructing a submarine tunnel by excavating a submerged ground and installing a plurality of boxes on the submerged ground while being joined to each other. In the excavator, a new box is housed from the top, and the upper part and the tail part are opened so that the tail part can be put out on the ground after the excavation.
The excavation means to move it to the tail section.
Gently pull the new box on the upper end to
Each winch that slides to the top existing box
It is characterized by being prepared.

【0008】[0008]

【発明の実施の形態】図1は海底トンネルの一例を示
し、図において、複数の函体1を海底の地盤面下の比較
的浅い位置に互いに接合しながら設置することにより海
底トンネルAが構築されている。また、こうして構築さ
れた海底トンネルAの両端は別途に構築されたトンネル
Bに接続され、トンネルBを介して地上と結ばれてい
る。
BEST MODE FOR CARRYING OUT THE INVENTION FIG. 1 shows an example of a submarine tunnel. In the figure, a submarine tunnel A is constructed by arranging a plurality of boxes 1 at relatively shallow positions below the ground surface of the sea floor while joining them. Has been done. Further, both ends of the submarine tunnel A thus constructed are connected to a separately constructed tunnel B, and are connected to the ground through the tunnel B.

【0009】函体1は地上の製作ヤードでRC構造、P
C構造、SRC構造、または鋼板型枠の中にコンクリー
トを打設する鋼・コンクリート合成構造などによって構
築されている。
The box 1 is an RC structure, P
It is constructed by a C structure, an SRC structure, or a steel / concrete composite structure in which concrete is placed in a steel plate form.

【0010】また、各函体1と海底地盤6との間には主
に函体1を安定させるために裏込めモルタルまたは砂2
等が所定の厚さに充填されている。図2と図3はこの海
底トンネルAの構築で使用される水底掘進機で、掘進機
3は函体1を収納できるように函状をなし、また函体1
を上から収納しテール部から後方に出せるように上端部
とテール部がともに開口している。
Further, backfilling mortar or sand 2 is mainly provided between each box 1 and the seabed 6 to stabilize the box 1.
Etc. are filled to a predetermined thickness. 2 and 3 show a submarine excavator used in the construction of the subsea tunnel A. The excavator 3 has a box shape so that the box 1 can be housed therein.
The upper end and the tail are both open so that the can be stowed from the top and pulled out from the tail.

【0011】また、先端側に海底の地盤を前に掘り進む
ための掘削手段として面板4と掘削土を後方に排出する
スクリューコンベアー(図省略)を、テール部に推進手
段として面板4で地盤を掘りながら前進するための推進
ジャッキ5をそれぞれ備えている。
Further, a face plate 4 and a screw conveyor (not shown) for discharging the excavated soil to the rear as excavation means for digging the ground on the seabed forward at the tip side, and a face plate 4 as propulsion means for digging the ground at the tail portion. While being equipped with each of the propulsion jacks 5 for moving forward.

【0012】なお、掘削手段としては、特に海底地盤6
が砂シルト層の場合、他に例えば図5(a)に図示する
ように掘削翼7と排泥ポンプ8を備え、掘削翼7で掘削
した掘削土と海水とを攪拌し、泥水化した後排泥ポンプ
8で後方に流体排出するようにしたもの、また図5
(b)に図示するようにアースドリル9とコンクリート
ポンプ10を備え、アースドリル9で掘削した掘削土を
コンクリートポンプ10によって原形に近い状態で後方
にパイプ排出するようにしたもの等でもよく、要する
に、海底地盤6を連続して掘進し、同時に掘削土を後方
に排出できる構成のものであればよい。
As the excavation means, especially the seabed 6
Is a sand silt layer, the excavation blade 7 and the mud pump 8 are additionally provided as shown in FIG. 5 (a), and the excavated soil excavated by the excavation blade 7 and seawater are agitated to make muddy water. A device in which the fluid is discharged backward by the sludge pump 8, and FIG.
As shown in (b), an earth drill 9 and a concrete pump 10 may be provided, and the excavated soil excavated by the earth drill 9 may be discharged backward by the concrete pump 10 in a state close to the original shape. Any structure may be used as long as it can continuously excavate the seabed 6 and simultaneously discharge the excavated soil backward.

【0013】また、掘進機3の先端側の上端部にはウィ
ンチ11が、そして掘進機3内にはリフト12がそれぞ
れ設置されている。ウィンチ11は、海底の地盤面下に
互いに接合しながら連続して設置されている函体1(以
下「既設函体1」という)の上を、新たに設置される函
体1(以下「新設函体1」という)を主航路の水域より
外側の水域(岸寄りの水域)から反対側の岸の方にスラ
イドさせて移送する際に、新設函体1を反対側の岸の方
向に引っ張るために使用されるものである。
A winch 11 is installed at the upper end of the excavator 3 on the tip side, and a lift 12 is installed in the excavator 3. The winch 11 is installed on the box 1 (hereinafter referred to as "existing box 1") that is continuously installed while being joined to each other under the ground surface of the seabed (hereinafter referred to as "newly installed"). When sliding the "Box 1") from the water area outside the waterway of the main route (water area near the shore) to the opposite shore, pull the new case 1 toward the opposite shore. Is used for.

【0014】 なおこの場合、新設函体1のスライドを
スムーズに行えるように、例えば図4に図示するよう
に、新設函体1の上端部に新設函体1の軸方向に連続す
るガイドレール13を突設する一方、新設函体1の下端
部にガイドレール13にスライド自在に係合するガイド
溝14を新設函体1の軸方向に連続して形成するものと
する。
In this case, slide the new box 1
For smooth operation , for example, as shown in FIG. 4, a guide rail 13 continuous in the axial direction of the new box 1 is provided on the upper end of the new box 1 while the lower end of the new box 1 is projected. The guide groove 14 slidably engaged with the guide rail 13 is formed continuously in the axial direction of the new case 1.

【0015】こうすることで、新設函体1を移送する際
の新設函体1の横ずれを阻止できて新設函体1をきわめ
てスムーズに掘進機3側に移送することができる。な
お、全ての函体1を設置し終えたらガイドレール13は
撤去し、ガイド溝14は裏込めモルタル2で完全に埋め
るものとする。
By doing so, the lateral displacement of the new box 1 when the new box 1 is transferred can be prevented, and the new box 1 can be transferred extremely smoothly to the machine 3 side. Note that the guide rails 13 are removed after the installation of all the boxes 1, and the guide grooves 14 are completely filled with the backfill mortar 2.

【0016】リフト12は、ウィンチ11によって掘進
機3の上まで移送されてきた新設函体1を掘進機3内に
降ろすために使用されるもので、新設函体1を載せる複
数の受け昇降装置16を備えて構成されている。
The lift 12 is used to lower the new box 1 transferred to the top of the excavator 3 by the winch 11 into the excavator 3, and a plurality of receiving and elevating devices for mounting the new box 1 thereon. 16 is provided.

【0017】受け昇降装置16は、掘進機3内の両側部
に掘削機3上端部から底部まで昇降自在に複数突設され
ている。なお、掘進機3は函体1を収納できるように函
状に形成され、周囲からの土圧に対処できる構造になっ
ている。
A plurality of receiving and elevating devices 16 are provided on both sides of the excavator 3 so as to be vertically movable from the upper end to the bottom of the excavator 3. In addition, the excavator 3 is formed in a box shape so that the box body 1 can be stored therein, and has a structure capable of coping with earth pressure from the surroundings.

【0018】また、掘進機3の内側部と底部には新設函
体1が摩擦抵抗を受けないで移動しやすいように複数の
コロ(またはタイヤ)17が取り付けられている。さら
に、掘進機3は掘進中、左右および上下に自由に蛇行で
きる中折れ機構18を備え、函体1の緩やかなカーブま
たは不陸に自由に対応できるよになっている。こうして
構成された掘進機3はさらに、バラスト水を利用して自
由に浮力調整を行えるようにもなっている。
A plurality of rollers (or tires) 17 are attached to the inside and bottom of the excavator 3 so that the new box 1 can be easily moved without receiving frictional resistance. Further, the excavator 3 is provided with a center folding mechanism 18 which can meander freely left and right and up and down during the excavation so that it can freely cope with a gentle curve or unevenness of the box 1. The excavator 3 configured in this manner is further adapted to freely adjust the buoyancy by using ballast water.

【0019】このような構成において、次にこの発明に
係る水底トンネルの構築工法を順に説明する(図6〜図
8参照)。 (1) 最初に、海底トンネルAの発進基地側に発進用土
留め壁19を構築する(図6(a)参照)。発進用土留
め壁19は施工中、船舶の往来を妨げないように船舶が
頻繁に行き来する主航路の水域より外側の水域(岸寄り
の水域)に構築するものとする。
Next, the construction method of the underwater tunnel according to the present invention having such a structure will be described in order (see FIGS. 6 to 8). (1) First, the starting earth retaining wall 19 is constructed on the starting base side of the undersea tunnel A (see FIG. 6A). The earth retaining wall 19 for start-up is to be constructed in a water area outside the water area of the main route where the ship frequently travels (water area near the shore) so as not to hinder the traffic of the ship during construction.

【0020】また、発進用土留め壁19は例えば、鋼管
矢板を多数打ち込む等して構築し、また発進用土留め壁
19の裏側地盤20を地盤改良する。 (2) 次に、主航路の水域より外側の水域(岸寄りの水
域)内で、発進用土留め壁19の主航路側の海底地盤を
浚渫船21によって所定範囲に渡って掘り下げる(図6
(b)参照)。
The starting earth retaining wall 19 is constructed by, for example, driving in a plurality of steel sheet piles, and the back ground 20 of the starting earth retaining wall 19 is improved. (2) Next, within the water area outside the water area of the main channel (water area near the shore), the seabed ground on the main channel side of the starting earth retaining wall 19 is dug down over a predetermined range by the dredger 21 (Fig. 6).
(See (b)).

【0021】また、掘り下げた底部(根切り底)に必要
に応じて鋼管杭などからなる基礎杭22を打ち込み、そ
してその上に基礎コンクリート23を打設する(図6
(c)参照)。 (3) 次に、主航路の水域より外側の水域(岸寄りの水
域)内で、基礎コンクリート23の上に掘進機3を沈設
する(図7(a)参照)。また、掘進機3内に最初の函
体1aを沈設する。
If necessary, a foundation pile 22 such as a steel pipe pile is driven into the dug bottom (root cutting bottom), and a foundation concrete 23 is placed thereon (FIG. 6).
(See (c)). (3) Next, the excavator 3 is sunk on the foundation concrete 23 in a water area outside the water area of the main channel (water area near the shore) (see FIG. 7 (a)). Further, the first box 1a is sunk in the excavator 3.

【0022】その際、掘進機3はクレーン船15で吊
り、バラスト水で浮力を調整しながら沈め、基礎コンク
リート23の上に設置する。また、函体1aもクレーン
船15で吊り、バラスト水で浮力を調整しながら掘進機
3の上まで沈め、リフト12の受け昇降装置16の上に
載せる。そして、リフト12を操作して函体1aをさら
に掘進機3内の底部まで沈める。 (4) 次に、面板4で地盤を掘削しながら、最初の函体
1aを反力受けに推進ジャッキ5を作動させることによ
り、掘進機3を前進させて函体1aの一個分の距離を掘
り進む。
At this time, the excavator 3 is hung by the crane ship 15, sunk while adjusting the buoyancy with ballast water, and installed on the foundation concrete 23. Further, the box body 1a is also hung by the crane ship 15, sunk to the top of the excavator 3 while adjusting the buoyancy with ballast water, and placed on the receiving and elevating device 16 of the lift 12. Then, the lift 12 is operated to further sink the box 1a to the bottom of the excavator 3. (4) Next, while excavating the ground with the face plate 4, the propulsion jack 5 is operated by receiving the reaction force from the first box 1a to advance the excavator 3 to move the distance for one box 1a. Dig in.

【0023】掘進機3で函体一個分の距離を掘進するこ
とにより、掘進機3内の函体1aは掘進機3が前進する
のと相反して推進ジャッキ5によって掘進機3のテール
部から後方の海底地盤6の上に押し出され、掘進機3内
は空になる。
By excavating a distance corresponding to one box with the machine 3, the box 1a in the machine 3 is moved from the tail of the machine 3 by the propulsion jack 5 contrary to the case where the machine 3 advances. It is pushed onto the seabed 6 at the rear, and the inside of the excavator 3 becomes empty.

【0024】なお、掘進機3は推進ジャッキ5を複数備
えていることから、この推進ジャッキ5を適当に操作す
ることにより掘進機3の向き(掘進方向)を変え、また
姿勢制御を行う。 (5) 次に、海底地盤6の上に押し出された函体1aと
地盤との間に裏込めモルタルまたは砂2などを充填して
函体1aを安定させる。 (6) 次に、主航路の水域より外側の水域(岸寄りの水
域)内で、二番目に設置される函体1bをクレーン船1
5で吊り、最初の函体1aと同様にバラスト水で浮力を
調整しながら沈め、函体1aの上に載せる(図7(b)
参照)。 (7) 次に、二番目の函体1bにウィンチ11のワイヤ
ー11aを繋ぐ。そして、ウィンチ11で函体1bを、
掘進機3側に引っ張って函体1aの上を掘進機3側に移
送し、リフト12の受け昇降装置16の上に載せる。次
に、リフト12を操作して函体1bを掘進機3内の底ま
で沈める。 (8) 次に再び、面板4で地盤を掘削しながら、函体1
bを反力受けに推進ジャッキ5を作動させることによ
り、掘進機3を前進させてさらに函体一個分の距離を掘
り進む。
Since the excavator 3 is provided with a plurality of propulsion jacks 5, the direction (excavation direction) of the excavator 3 is changed and the attitude is controlled by appropriately operating the propulsion jacks 5. (5) Next, backfill mortar or sand 2 is filled between the box 1a extruded onto the seabed 6 and the ground to stabilize the box 1a. (6) Next, in the water area outside the water area of the main route (water area near the shore), install the second box 1b installed in the crane ship 1
5 and sunk while adjusting the buoyancy with ballast water in the same way as the first box 1a, and put it on the box 1a (Fig. 7 (b)).
reference). (7) Next, connect the wire 11a of the winch 11 to the second box 1b. Then, use the winch 11 to move the box 1b
It is pulled to the excavator 3 side, transferred on the box 1a to the excavator 3 side, and placed on the receiving and elevating device 16 of the lift 12. Next, the lift 12 is operated to sink the box 1b to the bottom inside the excavator 3. (8) Next, again while excavating the ground with the face plate 4, the box 1
By operating the propulsion jack 5 by receiving b as a reaction force, the excavator 3 is advanced to further dig a distance of one box.

【0025】掘進機3で函体一個分の距離を掘進するこ
とにより、掘進機3内の函体1bは掘進機3のテール部
から後方の海底地盤の上に押し出され、掘進機3内は空
になる。 (9) 次に、海底地盤6の上に押し出された函体1bと
地盤との間に裏込めモルタルまたは砂2などを充填して
函体1bを安定させる。また、最初の函体1aと函体1
bを接合する。 (10) 以下同様にして、掘進機3で海底地盤6を掘り進
みながら、必要数の函体1c、函体1d,……を掘進後
の海底地盤6の上に互いに接合しながら順に設置する。 (11) こうして、構築された海底トンネルAの到達側に
最後の函体1nを設置したら、掘進機3の掘進手段を切
り離して回収し、函状をなす本体部分はそのまま海底に
残す。そして、函状をなす本体部分は地上に通じるトン
ネルBとの継手部を施工するための外枠として利用する
(図8(b)参照)。なお、本体部分も回収して残りの
区間を在来の沈埋工法で施工してもよい。
By excavating a distance of one box with the excavator 3, the box 1b in the excavator 3 is pushed out from the tail portion of the excavator 3 onto the rear seabed ground, and the inside of the excavator 3 is Become empty. (9) Next, backfill mortar or sand 2 is filled between the box 1b extruded on the seabed 6 and the ground to stabilize the box 1b. Also, the first box 1a and the box 1
Join b. (10) Similarly, while excavating the submarine ground 6 with the excavator 3, a required number of boxes 1c, 1d, ... Are sequentially installed on the subseabed 6 after excavation while being joined to each other. . (11) After the last box 1n is installed on the arrival side of the constructed submarine tunnel A in this manner, the excavation means of the excavator 3 is separated and recovered, and the box-shaped main body portion is left as it is on the seabed. The box-shaped main body portion is used as an outer frame for constructing a joint portion with the tunnel B leading to the ground (see FIG. 8B). In addition, the main body part may be recovered and the remaining section may be constructed by a conventional burial method.

【0026】こうして、海底トンネルAが構築される。
なお、トンネルAの終端部分は主航路の水域より外側の
水域(反対側の岸寄りの水域)内で終わるように施工す
るものとする。また、既設函体1の両側と上は完全に埋
め戻すものとする。
In this way, the submarine tunnel A is constructed.
In addition, the end portion of the tunnel A shall be constructed so as to end within the water area outside the water area of the main route (water area near the opposite shore). In addition, both sides and the top of the existing box 1 are completely backfilled.

【0027】[0027]

【発明の効果】この発明は以上説明した構成からなり、
特に主航路の水域より外側の水域から掘り始め、主航路
の水域の下を反対側の岸に向かって掘り進み、これと並
行して主航路の水域より外側の水域で新設函体を沈め、
主航路水域下の既設函体の上を先頭の既設函体まで移送
した後、先頭の既設函体の前に設置することにより、掘
進開始側の岸から反対側の岸まで複数の新設函体を順に
設置して水底トンネルを構築するため、主航路水域内の
船舶の往来を全く妨げることなく、水底トンネルの施工
をきわめて効率的に行うことができる。
The present invention has the configuration described above,
In particular, start digging from the water area outside the water area of the main channel, proceed under the water area of the main channel toward the opposite shore, and in parallel with this, sunk the new box in the water area outside the water area of the main channel,
After transferring the existing box above the existing box under the waterway of the main route and installing it in front of the existing box at the front, multiple new boxes can be installed from the shore on the excavation start side to the shore on the opposite side. Since the submarine tunnels are sequentially installed to construct the submarine tunnel, the submarine tunnel can be constructed very efficiently without obstructing the traffic of ships in the main channel area.

【0028】また、水底のごく浅い部分を、函体を埋め
られる程度のごく限られたスペースを掘り進むことで、
掘削土量を大幅に減らすことができてコストの大幅な削
減が図れる。
By digging a very shallow part of the water bottom into a very limited space where the box can be buried,
The amount of excavated soil can be greatly reduced and the cost can be significantly reduced.

【図面の簡単な説明】[Brief description of drawings]

【図1】海底トンネルの一例を示す側面図である。FIG. 1 is a side view showing an example of an undersea tunnel.

【図2】海底トンネルを構築する際に使用される掘進機
の側面図である。
FIG. 2 is a side view of an excavator used when constructing an undersea tunnel.

【図3】図2におけるイ−イ線断面図である。3 is a cross-sectional view taken along the line EE in FIG.

【図4】既設函体の上を新設函体を移送する状態を示す
断面図である。
FIG. 4 is a cross-sectional view showing a state in which the new box is transferred over the existing box.

【図5】(a),(b)は掘進手段の他の例を示す掘進
機の一部断面図である。
5A and 5B are partial cross-sectional views of an excavator showing another example of excavating means.

【図6】(a)〜(c)は海底トンネルの施工方法を示
す工程図である。
6A to 6C are process drawings showing a method of constructing a submarine tunnel.

【図7】(a),(b)は海底トンネルの施工方法を示
す工程図である。
7 (a) and 7 (b) are process drawings showing a method for constructing a submarine tunnel.

【図8】(a),(b)は海底トンネルの施工方法を示
す工程図である。
8 (a) and 8 (b) are process drawings showing a method of constructing a submarine tunnel.

【符号の説明】[Explanation of symbols]

1 函体(トンネル函体エレメント) 2 裏込めモルタルまたは砂 3 掘進機 4 面板 5 推進ジャッキ 6 海底地盤 7 掘削翼 8 排泥ポンプ 9 アースドリル 10 コンクリートポンプ 11 ウィンチ 11a ワイヤー 12 リフト 13 ガイドレール 14 ガイド溝 15 クレーン船 16 受け昇降装置 17 コロ(またはタイヤ) 18 中折れ機構 19 発進用土留め壁 20 裏側地盤(地盤改良部) 21 浚渫船 22 基礎杭 23 基礎コンクリート 1 Box (Tunnel Box Element) 2 Backfill mortar or sand 3 excavator 4 face plates 5 propulsion jack 6 seabed 7 excavation wings 8 Sludge pump 9 Earth drill 10 concrete pump 11 winch 11a wire 12 lift 13 Guide rail 14 Guide groove 15 crane ships 16 Receiver lifting device 17 roller (or tire) 18 Center folding mechanism 19 Start retaining wall 20 Backside ground (ground improvement section) 21 dredger 22 Foundation pile 23 Foundation concrete

───────────────────────────────────────────────────── フロントページの続き (72)発明者 高橋 忍 東京都港区元赤坂1丁目2番7号 鹿島 建設株式会社内 (72)発明者 滝沢 清一郎 東京都港区元赤坂1丁目2番7号 鹿島 建設株式会社内 (72)発明者 本間 茂希 東京都港区元赤坂1丁目3番8号 鹿島 建設株式会社東京支店内 (72)発明者 田中 秀夫 東京都港区元赤坂1丁目2番7号 鹿島 建設株式会社内 (56)参考文献 実開 平5−96198(JP,U) (58)調査した分野(Int.Cl.7,DB名) E02D 29/07 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Shinobu Takahashi 1-2-7 Moto-Akasaka, Minato-ku, Tokyo Within Kashima Construction Co., Ltd. (72) Seiichiro Takizawa 1-2-7 Moto-Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. (72) Inventor Shigeki Honma 1-3-8 Moto-Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. Tokyo Branch (72) Inventor Hideo Tanaka 1-2-7 Moto-Akasaka, Minato-ku, Tokyo No. within Kashima Construction Co., Ltd. (56) References: Kaihei 5-96198 (JP, U) (58) Fields investigated (Int.Cl. 7 , DB name) E02D 29/07

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 水底の地盤を掘進しつつ、掘進後の地盤
上に複数の函体を互いに接合しながら設置して水底トン
ネルを構築する水底トンネルの構築工法において、複数
の新設函体を水中に沈め、既設函体上を先頭の既設函体
までスライドさせた後、先頭の既設函体の前に順に設置
して連続するトンネルを構築することを特徴とする水底
トンネルの構築工法。
1. A while excavation of the water bottom of the ground, in the construction method of the undersea tunnel to build undersea tunnel installed while joining together a plurality of box-body on the ground after excavation, more
The new box of is submerged in the water, the top of the existing box on top of the existing box
A construction method for a subsea tunnel characterized by constructing a continuous tunnel by sliding it to the front and installing it in front of the existing box at the top.
【請求項2】 前記複数の函体は、函体の上端部にガイ
ドレール、函体の下端部にガイド溝を設けてあり、互い
に係合し掘進方向にスライド可能であることを特徴とす
る請求項1記載の水底トンネルの構築工法。
2. A plurality of boxes are provided at the upper end of the box.
There are guide grooves at the bottom of the rail and box,
It is characterized in that it is engaged with and can slide in the direction of excavation.
The method for constructing a subsea tunnel according to claim 1,
【請求項3】 水底の地盤を掘進しつつ、掘進後の地盤
上に複数の函体を互いに接合しながら設置して水底トン
ネルを構築する際に使用される水底掘進機において、新
設函体を上から収納しテール部から掘進後の地盤上に出
せるように上端部とテール部が開口する函状をなし、
端部に水底の地盤を掘削する掘進手段を、テール部に前
進するための推進ジャッキを、上端部に前記新設函体を
引っ張って既設函体上を先頭の既設函体までスライドさ
せるウィンチをそれぞれ備えてなることを特徴とする水
底掘進機。
3. A submarine excavator used for constructing a subsea tunnel by excavating a submerged ground and installing a plurality of boxes on the submerged ground while joining them to each other. It forms a box-shape opening upper end portion and the tail portion so accommodated from above put out on the ground after excavation from the tail part, previously
An excavation means for excavating the bottom of the water at the end,
A propelling jack for advancing the new box at the upper end.
Pull and slide on the existing box to the top existing box.
Water that is equipped with each winch
Bottom excavator.
JP35015398A 1998-12-09 1998-12-09 Construction method of underwater tunnel and underwater excavator Expired - Fee Related JP3487201B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP35015398A JP3487201B2 (en) 1998-12-09 1998-12-09 Construction method of underwater tunnel and underwater excavator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP35015398A JP3487201B2 (en) 1998-12-09 1998-12-09 Construction method of underwater tunnel and underwater excavator

Publications (2)

Publication Number Publication Date
JP2000170187A JP2000170187A (en) 2000-06-20
JP3487201B2 true JP3487201B2 (en) 2004-01-13

Family

ID=18408594

Family Applications (1)

Application Number Title Priority Date Filing Date
JP35015398A Expired - Fee Related JP3487201B2 (en) 1998-12-09 1998-12-09 Construction method of underwater tunnel and underwater excavator

Country Status (1)

Country Link
JP (1) JP3487201B2 (en)

Also Published As

Publication number Publication date
JP2000170187A (en) 2000-06-20

Similar Documents

Publication Publication Date Title
JP4687713B2 (en) Construction method and equipment for tunnels submerged on the seabed
JP7357517B2 (en) Pipe construction method using propulsion method
JP3487201B2 (en) Construction method of underwater tunnel and underwater excavator
JPH0462230A (en) Setting construction for underground structure
KR100931918B1 (en) Underwater tunneling method using internal and external hydraulic pressure difference
CN109537632B (en) Submarine tunnel construction method
WO2018133745A1 (en) Pipe jacking tunneling device for underwater tunnels and construction method thereof
JP3917146B2 (en) Laying method and removing method of lining plate in open shield method
JP7303756B2 (en) Open shield machine and tunnel construction method
US4643613A (en) Underwater trenching and pipe-laying devices
WO2018133748A1 (en) Construction ship for underwater tunnel and construction method therefor
JP4148047B2 (en) Open shield machine
JPH08338022A (en) Method for movable type cut and cover earth-retaining construction and device therefor
JP2849822B2 (en) Underground diaphragm wall excavation method and its equipment
JP2000220158A (en) Construction method of underwater tunnel
JP3926818B2 (en) Installation method of concrete box
JP3360906B2 (en) Drilling method for buried undersea pipe
JP3473915B2 (en) Small diameter pipe burial method
JP3069822B2 (en) Installation method of intake water discharge pipe
JP2802837B2 (en) Submerged tunnel installation method
KR20180067826A (en) excavator using propulsion of caisson, and excavation method using the same
CN115928709A (en) Pushing structure suitable for continuous wall constructed by pushing method
JPH11141272A (en) Excavation method and excavator for bedrock shaft and inclined shaft in steel pipe laying construction
JPH0428044B2 (en)
JPS6140996A (en) Method of construction of water-bottom tunnel, etc.

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20030930

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091031

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121031

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees