JP3225677B2 - Excavator hanging rope guide device - Google Patents

Excavator hanging rope guide device

Info

Publication number
JP3225677B2
JP3225677B2 JP08088693A JP8088693A JP3225677B2 JP 3225677 B2 JP3225677 B2 JP 3225677B2 JP 08088693 A JP08088693 A JP 08088693A JP 8088693 A JP8088693 A JP 8088693A JP 3225677 B2 JP3225677 B2 JP 3225677B2
Authority
JP
Japan
Prior art keywords
sheave
rope
leaving
boom
excavator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP08088693A
Other languages
Japanese (ja)
Other versions
JPH06294129A (en
Inventor
豊 小林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kobelco Construction Machinery Co Ltd
Original Assignee
Kobelco Construction Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kobelco Construction Machinery Co Ltd filed Critical Kobelco Construction Machinery Co Ltd
Priority to JP08088693A priority Critical patent/JP3225677B2/en
Publication of JPH06294129A publication Critical patent/JPH06294129A/en
Application granted granted Critical
Publication of JP3225677B2 publication Critical patent/JP3225677B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Earth Drilling (AREA)
  • Jib Cranes (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は地中に連続壁造成用等の
孔を掘削する掘削機において、掘削装置を吊持する吊り
ロープをブーム先端と掘削装置との間でガイドするロー
プガイド装置に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an excavator for excavating a hole for forming a continuous wall or the like in the ground, and a rope guide device for guiding a suspension rope for suspending the excavator between the tip of the boom and the excavator. It is about.

【0002】[0002]

【従来の技術】従来の技術を図7〜図9によって説明す
る。
2. Description of the Related Art A conventional technique will be described with reference to FIGS.

【0003】図7において、1は掘削機のベースマシン
(クレーンの本体)で、下部走行体2上に上部旋回体3
が竪軸Xまわりに旋回自在に搭載されて成り、この上部
旋回体3にブーム4が装着されている。
[0003] In FIG. 7, reference numeral 1 denotes a base machine (body of a crane) of an excavator.
Are mounted so as to be pivotable about a vertical axis X, and a boom 4 is mounted on the upper revolving unit 3.

【0004】このブーム4の先端部に2枚のアイドラシ
ーブ5と4枚のポイントシーブ6、それにブーム頂部に
1枚のリービングシーブ(折り返しガイドシーブ)7が
設けられている。
[0004] Two idler sheaves 5 and four point sheaves 6 are provided at the tip of the boom 4, and one leaving sheave (return guide sheave) 7 is provided at the top of the boom.

【0005】一方、掘削装置(電動式または油圧式)8
にはランニングブロック9が設けられ、このランニング
ブロック9に2枚のランニングシーブ10が設けられて
いる。
On the other hand, an excavator (electric or hydraulic type) 8
Is provided with a running block 9, and the running block 9 is provided with two running sheaves 10.

【0006】上部旋回体3には主巻用および補巻用両ウ
ィンチ11,12が設けられ、主巻用ウィンチ11から
引出された吊りロープ13が、図8,9に示すようにア
イドラシーブ5→ポイントシーブ6→ランニングシーブ
10→ポイントシーブ6の順で通され、ここからリービ
ングシーブ7→ポイントシーブ6で方向転換した後、ラ
ンニングシーブ10→ポイントシーブ6→アイドラシー
ブ5を経て補巻用ウィンチ12に導入される。
The upper revolving unit 3 is provided with both winches 11 and 12 for main winding and auxiliary winding. A suspension rope 13 drawn from the winch 11 for main winding is connected to an idler sheave 5 as shown in FIGS. → Point sheave 6 → running sheave 10 → point sheave 6 and then change direction at leaving sheave 7 → point sheave 6, then run sheave 10 → point sheave 6 → idler sheave 5 and make-up winch. 12 is introduced.

【0007】こうして、吊りロープ13が主巻用および
補巻用両ウィンチ11,12によって駆動され、これに
より掘削装置8が下降、上昇して地中に連続壁造成用等
の孔H(図9に示す)が掘削される。
In this manner, the suspension rope 13 is driven by both the main winding and auxiliary winding winches 11 and 12, whereby the excavator 8 descends and rises, and a hole H for forming a continuous wall or the like is formed in the ground (FIG. 9). Is excavated.

【0008】なお、このような2ドラム方式をとること
により、高深度の孔掘削が可能となる。
[0008] By employing such a two-drum system, it is possible to excavate a hole at a high depth.

【0009】[0009]

【発明が解決しようとする課題】この種の掘削機におい
ては、クレーンの本体がそのままベースマシン1として
利用されるため、クレーン作業用のロープガイド部材と
してブーム4に設けられたアイドラシーブ5およびポイ
ントシーブ6がそのまま吊りロープ13のガイドシーブ
として使用され、リービングシーブ7のみが掘削機用と
して付加される。
In this type of excavator, since the main body of the crane is used as it is as the base machine 1, the idler sheave 5 and the point provided on the boom 4 as a rope guide member for crane operation are used. The sheave 6 is used as it is as a guide sheave of the hanging rope 13, and only the leaving sheave 7 is added for the excavator.

【0010】ここで、ポイントシーブ6は、ロープの曲
げ半径を大きくしてロープ寿命を伸ばすため、できるだ
け大径とされる。
Here, the point sheave 6 is made as large as possible in order to increase the bending radius of the rope and extend the life of the rope.

【0011】一方、ランニングブロック9のランニング
シーブ10は、掘削装置8とともに孔H内に入り込むた
め、その直径寸法が孔Hの幅寸法以下とされる。
On the other hand, since the running sheave 10 of the running block 9 enters the hole H together with the excavator 8, the diameter thereof is set to be equal to or less than the width of the hole H.

【0012】このため、とくに幅の小さい孔Hを掘削す
る場合に、図9に示すようにポイントシーブ6とランニ
ングシーブ10の直径寸法a,bに差(a>b)が生
じ、このシーブ直径差により、側面から見て吊りロープ
13がこの両シーブ6,10間で下すぼまりとなる(ロ
ープ間隔cが一定とならない)。
Therefore, when a hole H having a particularly small width is excavated, a difference (a> b) occurs between the diameters a and b of the point sheave 6 and the running sheave 10, as shown in FIG. Due to the difference, the hanging rope 13 becomes narrower between the sheaves 6 and 10 when viewed from the side (the rope interval c is not constant).

【0013】こうなると、掘削中に、吊りロープ13が
孔Hの入口部分と干渉して掘削作業に支障を来すととも
に、ロープ13の摩耗、損傷が激しいものとなる。
In this case, during the excavation, the suspension rope 13 interferes with the entrance of the hole H to hinder the excavation work, and the rope 13 is severely worn and damaged.

【0014】そこで従来は、この点の対策として、図7
に示すようにポイントシーブ6とランニングブロック9
との間においてガイドブロック14をブーム4に取付
け、このガイドブロック14内に設けられた複数枚のガ
イドシーブ(図示しない)により、ポイントシーブ6の
下方でロープ間隔を絞り、同ブロック下方でロープ間隔
をランニングシーブ10の直径寸法と等しくしている。
Conventionally, as a countermeasure against this point, FIG.
Point sheave 6 and running block 9 as shown in
A guide block 14 is attached to the boom 4 between the guide block 14 and a plurality of guide sheaves (not shown) provided in the guide block 14 to reduce the rope interval below the point sheave 6 and to reduce the rope interval below the block. Is equal to the diameter dimension of the running sheave 10.

【0015】ところが、こうすると、ロープ13と孔入
口との干渉の問題は解決できるものの、新たな問題とし
て、ガイドブロック14の加入によって吊り揚程が小さ
くなる。このため、たとえば掘削機の移動時に、掘削装
置8を最大限に吊り上げても地上の障害物に当る等の問
題が生じていた。
However, although the problem of interference between the rope 13 and the hole entrance can be solved, a new problem is that the lifting height is reduced by the addition of the guide block 14. For this reason, for example, when the excavator is moved, even if the excavator 8 is lifted to the maximum, a problem such as hitting an obstacle on the ground occurs.

【0016】そこで本発明は、吊り揚程を高くとりなが
ら、吊りロープと孔入口部分との干渉を防止することが
できる掘削機のロープガイド装置を提供するものであ
る。
Accordingly, the present invention provides a rope guide device for an excavator that can prevent interference between a suspension rope and a hole entrance portion while increasing a lifting height.

【0017】[0017]

【課題を解決するための手段】請求項1の発明は、ベー
スマシンと、このベースマシンに装着されたブームと、
ウィンチから引出された吊りロープによってブームの先
端に吊持される掘削装置とを備えた掘削機において、上
記ブームの先端部に上記吊りロープが通されるポイント
シーブ、上記掘削装置に上記ポイントシーブとの間で吊
りロープが掛け回されるランニングシーブをそれぞれ左
右一対ずつ、左右方向の水平軸まわりに回転自在に設け
るとともに、上記ポイントシーブよりも下方位置におい
て、ブーム先端部の前面にリービングシーブを、前後方
向の水平軸まわりに回転自在で、かつ、側面視において
吊りロープを上記ランニングシーブとリービングシーブ
との間でほぼ鉛直状態またはロープ間隔が下広がりとな
る状態でガイドしうる位置に設けたものである。
According to a first aspect of the present invention, there is provided a base machine, a boom mounted on the base machine,
An excavator having an excavator suspended at the tip of a boom by a suspending rope pulled out from a winch, wherein a point sheave in which the suspending rope is passed through the tip of the boom, the point sheave in the excavator, A pair of running sheaves around which the hanging rope is hung is provided so as to be rotatable about a horizontal axis in the left-right direction, and at a position below the point sheave, a leaving sheave is provided on the front face of the boom tip. A rotatable rope that is rotatable around the horizontal axis in the front-rear direction, and is provided at a position where the hanging rope can be guided in a substantially vertical state or a state in which the rope interval is widened between the running sheave and the leaving sheave in a side view. It is.

【0018】請求項2の発明は、請求項1の構成におい
て、両ポイントシーブのシーブ間隔と両ランニングシー
ブのシーブ間隔とリービングシーブの直径寸法を同一と
し、かつ、リービングシーブを、正面視においてポイン
トシーブとランニングシーブを結ぶ二本の鉛直線の間に
位置させたものである。
According to a second aspect of the present invention, in the configuration of the first aspect, the sheave interval between the two point sheaves, the sheave interval between the two running sheaves, and the diameter dimension of the leaving sheave are the same, and the leaving sheave is pointed in a front view. It is located between two vertical lines connecting the sheave and the running sheave.

【0019】請求項3の発明は、請求項1または2の構
成において、リービングシーブが取付けられたリービン
グシーブフレームを、ブームに対し左右方向の水平軸を
中心として回動可能に取付けたものである。
According to a third aspect of the present invention, in the configuration of the first or second aspect, the leaving sheave frame to which the leaving sheave is attached is attached to the boom so as to be rotatable about a horizontal horizontal axis. .

【0020】請求項4の発明は、請求項3の構成におい
て、リービングシーブフレームが取付けられる取付部
を、ブーム先端部の複数個所に設けたものである。
According to a fourth aspect of the present invention, in the configuration of the third aspect, mounting portions to which the leaving sheave frame is mounted are provided at a plurality of locations at the end of the boom.

【0021】[0021]

【作用】上記構成によると、吊りロープが、ポイントシ
ーブとランニングシーブとの間でリービングシーブによ
って折り返しガイドされ、このリービングシーブとラン
ニングシーブとの間で側面視においてほぼ鉛直または下
広がり状態でガイドされる。
According to the above construction, the hanging rope is guided back by the leaving sheave between the point sheave and the running sheave, and guided substantially vertically or downwardly in a side view between the leaving sheave and the running sheave. You.

【0022】このため、ロープが下すぼまりとなる従来
のガイド構造と異なり、吊りロープが掘削孔の入口部分
と干渉するおそれがなくなる。
Therefore, unlike the conventional guide structure in which the rope is tapered downward, there is no possibility that the suspension rope interferes with the entrance of the excavation hole.

【0023】従って、ロープ間隔を絞るためのガイドブ
ロックが不要となるため、吊り揚程を高くとることがで
きる。
Accordingly, since a guide block for reducing the rope interval is not required, the lifting height can be increased.

【0024】一方、掘削機においては、掘削装置にホー
スやケーブルを取付け、これらを掘削装置とともに下
降、上昇させる場合がある。そして、この場合、掘削進
行に伴い、吊りロープにクランプを取付け、このクラン
プによりホース等を掴み保持する方式がとられる。
On the other hand, in an excavator, a hose and a cable may be attached to the excavator, and these may be lowered and raised together with the excavator. In this case, a method is adopted in which a clamp is attached to the suspension rope as the excavation progresses, and a hose or the like is grasped and held by the clamp.

【0025】このような場合、吊りロープのロープ間隔
が側面視および正面視の双方においてほぼ一定でないと
クランプを取付けることができない。
In such a case, the clamp cannot be attached unless the rope interval of the suspension rope is substantially constant in both the side view and the front view.

【0026】これに対し、請求項2の発明においては、
ロープ間隔が側面視だけでなく正面視においてもほぼ一
定となるため、クランプを吊りロープに対しいずれの位
置でも取付けることができる。
On the other hand, in the invention of claim 2,
Since the rope interval is substantially constant not only in the side view but also in the front view, the clamp can be attached to the suspension rope at any position.

【0027】また、請求項3の構成によると、ブームが
作業姿勢から倒された場合に、これに伴ってリービング
シーブが回動するため、ロープが同シーブから外れる等
のトラブルが発生するおそれがない。
According to the third aspect of the present invention, when the boom is tilted from the working posture, the leaving sheave is rotated accordingly, and there is a possibility that a trouble such as the rope coming off the sheave may occur. Absent.

【0028】さらに、請求項4の構成によると、作業時
のブーム角度等の作業条件の変化に応じてリービングシ
ーブの取付位置を変更することができる。
Further, according to the configuration of the fourth aspect, the mounting position of the leaving sheave can be changed according to a change in working conditions such as a boom angle at the time of working.

【0029】[0029]

【実施例】本発明の実施例を図1〜図6によって説明す
る。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described with reference to FIGS.

【0030】なお、以下の実施例において、図7〜図9
に示す従来技術と同一部分には同一符号を付して示し、
その重複説明を省略する。
In the following embodiment, FIGS.
The same parts as in the prior art shown in FIG.
The duplicate description is omitted.

【0031】図1〜図3に示すように、ブーム4の頂部
に左右一対のポイントシーブ6,6をポイントシーブ軸
6aまわりに回転自在に設けている。
As shown in FIGS. 1 to 3, a pair of left and right point sheaves 6, 6 are provided at the top of the boom 4 so as to be rotatable around a point sheave shaft 6a.

【0032】一方、このポイントシーブ6,6の少し下
方であるブーム先端部前面にリンク15を取付け、この
リンク15に、リービングシーブ16が取付けられたリ
ービングシーブフレーム17を、リービングシーブ16
の回転中心軸(リービングシーブ軸)16aがポイント
シーブ軸6aおよびランニングシーブ軸10aに対して
直角となる状態で、左右方向の水平軸18まわりに回動
可能に取付けている。
On the other hand, a link 15 is attached to the front face of the boom tip, which is slightly below the point sheaves 6, 6, and a leaving sheave frame 17 with a leaving sheave 16 attached thereto is attached to the link 15,
The rotation center shaft (leaving sheave shaft) 16a is perpendicular to the point sheave shaft 6a and the running sheave shaft 10a, and is mounted to be rotatable about a horizontal axis 18 in the left-right direction.

【0033】なお、リンク15は上下両端部をブーム4
に取付け、このうちリンク下端部は、クレーン作業時に
ロープエンド(ロープソケット)を止め付けるために元
々ブーム4に設けられたロープエンド止着用ブラケット
19を利用して取付けている。
The link 15 has booms 4 at both upper and lower ends.
The lower end of the link is mounted using a rope end fastening bracket 19 originally provided on the boom 4 to stop the rope end (rope socket) during crane operation.

【0034】また、シーブフレーム17の下面には、図
示しない排土ホース(場合によっては同ホースを繰り出
すホースリール)を吊持するための油圧タグライン20
が通されるタグラインシーブ21を取付けている。
On the lower surface of the sheave frame 17, a hydraulic tag line 20 for suspending a discharging hose (not shown, a hose reel for feeding the hose in some cases) is provided.
Is attached.

【0035】吊りロープ13は、図3等に示すように、
主巻用ウィンチ11からアイドラシーブ5を経て一方の
ポイントシーブ6に通され、ここから一方のランニング
シーブ10→リービングシーブ16→他方のランニング
シーブ10で折り返された後、他方のポイントシーブ
6、アイドラシーブ5経由で補巻用ウィンチ12に導入
される。
The hanging rope 13 is, as shown in FIG.
After passing from the main winding winch 11 to the one point sheave 6 via the idler sheave 5, it is turned back by one running sheave 10 → leaving sheave 16 → the other running sheave 10, and then the other point sheave 6 and idler It is introduced into the auxiliary winch 12 via the sheave 5.

【0036】ここで、ポイントシーブ6,6、ランニン
グシーブ10,10、リービングシーブ16の位置関係
等は次のように設定している。
Here, the positional relationship between the point sheaves 6 and 6, the running sheaves 10 and 10, the leaving sheave 16, and the like are set as follows.

【0037】 図2に示すように、ポイントシーブ
6,6とランニングシーブ10,10のシーブ間隔を等
しく設定し、左右相対応するシーブ同士を2本の鉛直線
L1,L2上に配置している。
As shown in FIG. 2, the sheave intervals between the point sheaves 6, 6 and the running sheaves 10, 10 are set to be equal, and the sheaves corresponding to the left and right phases are arranged on two vertical lines L1, L2. .

【0038】 図2に示すようにリービングシーブ1
6は、その直径を、ポイントシーブ6,6およびランニ
ングシーブ10,10のシーブ間隔(=正面視でのロー
プ間隔)W2と同じ寸法とし、正面視において上記二本
の鉛直線L1,L2間に配置している。
As shown in FIG. 2, the leaving sheave 1
6 has the same diameter as the sheave interval (= rope interval in a front view) W2 of the point sheaves 6, 6 and the running sheaves 10, 10, and between the two vertical lines L1, L2 in a front view. Have been placed.

【0039】 リービングシーブ16は、図1に示す
ように側面視において吊りロープ13をランニングシー
ブ10との間で鉛直状態でガイドしうる位置に取付けて
いる。
As shown in FIG. 1, the leaving sheave 16 is attached to a position where the hanging rope 13 can be guided vertically with the running sheave 10 in a side view.

【0040】このような条件設定により、吊りロープ1
3が側面視および正面視のいずれにおいても各シーブ
6,10,16間で鉛直状態でガイドされ、ロープ間隔
W1,W2が一定となる。
By setting such conditions, the hanging rope 1
3 is guided vertically between the sheaves 6, 10, 16 both in the side view and the front view, so that the rope intervals W1, W2 are constant.

【0041】従って、図9に示すように吊りロープ13
が側面視で下すぼまりにガイドされる結果、掘削時に、
掘削孔Hの入口部分に同ロープ13が干渉するという問
題がなくなるため、これを避けるためのロープガイド手
段(図7のガイドブロック14)が不要となる。このた
め、吊り揚程を高くとることができる。
Therefore, as shown in FIG.
As a result of being guided downward in side view,
Since the problem that the rope 13 interferes with the entrance portion of the excavation hole H is eliminated, a rope guide means (the guide block 14 in FIG. 7) for avoiding the problem is not required. Therefore, the lifting height can be increased.

【0042】また、正面視においてもロープ間隔W2が
一定となるため、吊りロープ13にクランプを取付けて
ホース等を掴み保持する方式をとる場合に、クランプを
いずれのロープ位置でも支障なく取付けることができ
る。
In addition, since the rope interval W2 is constant even when viewed from the front, when the clamp is attached to the hanging rope 13 to hold and hold a hose or the like, the clamp can be attached without any trouble at any rope position. it can.

【0043】さらに、ブーム4が作業姿勢から倒された
場合に、これに伴ってリービングシーブ16が水平軸1
8まわりに回動するため、同シーブ16をブーム4に固
定した場合のようにロープ13が同シーブ16から外れ
る等のトラブルが発生するおそれがない。
Further, when the boom 4 is tilted from the working position, the leaving sheave 16 is moved along the horizontal
Since it rotates around 8, there is no possibility that a trouble such as the rope 13 coming off the sheave 16 as in the case where the sheave 16 is fixed to the boom 4 will occur.

【0044】他の実施例 (I)上記実施例では、リービングシーブ16を、側面
視で吊りロープ13が鉛直にガイドされる位置に設けた
が、同シーブ16を、吊りロープ13が掘削孔入口と干
渉するおそれがなく、また吊りロープ13にクランプが
取付けられる場合にはこのクランプの取付けに支障を来
さない程度の僅かな下すぼまり状態でガイドされる位置
に設けてもよい。
Other Embodiments (I) In the above embodiment, the leaving sheave 16 is provided at a position where the hanging rope 13 is vertically guided in a side view. When the clamp is attached to the suspension rope 13, the clamp may be provided at a position where it is guided in a slightly lowered state that does not hinder the attachment of the clamp.

【0045】(II)また、クランプを用いない場合、あ
るいはクランプを伸縮式としてロープ間隔の変化に対応
できるようにした場合には、図4に示すようにリービン
グシーブ16を、側面視で吊りロープ13が下広がりに
ガイドされる位置に設けてもよい。
(II) When the clamp is not used, or when the clamp is made telescopic so as to be able to cope with a change in the distance between the ropes, as shown in FIG. 13 may be provided at a position guided downward.

【0046】さらに、図5に示すように、リービングシ
ーブ16の直径を、鉛直線L1,L2の間隔W2よりも
小さい寸法に形成し、正面視で吊りロープ13がリービ
ングシーブ16とランニングシーブ10との間で下広が
りにガイドされるようにしてもよい。
Further, as shown in FIG. 5, the diameter of the leaving sheave 16 is formed to be smaller than the distance W2 between the vertical lines L1 and L2, and the hanging rope 13 is connected to the leaving sheave 16 and the running sheave 10 in a front view. It may be made to be guided in a downward spread between.

【0047】(III)上記実施例では、ロープエンド止
着用ブラケット19の位置と、リービングシーブ16の
位置とのずれを吸収するためにこれらの間にリンク15
を介在させたが、上記両位置にずれがない条件下(ブー
ム角度、ランニングシーブ径等)では、図6に示すよう
にリービングシーブ16(シーブフレーム17)をロー
プエンド止着用ブラケット19に直接、左右方向水平軸
18を中心として回動可能に取付けてもよい。
(III) In the above embodiment, the link 15 is provided between the rope end fastening bracket 19 and the leaving sheave 16 in order to absorb the difference between the position of the bracket 19 and that of the leaving sheave 16.
Under the condition that there is no deviation between the two positions (boom angle, running sheave diameter, etc.), the leaving sheave 16 (sheave frame 17) is directly attached to the rope end fastening bracket 19 as shown in FIG. It may be mounted so as to be rotatable around the horizontal horizontal axis 18.

【0048】(IV)図6に示すように、同ブラケット1
9とは別に、ブーム先端部前側におけるブーム長さ方向
の複数個所に取付孔23…を設け、作業条件に応じてリ
ービングシーブ16の取付位置を変更しうるように構成
してもよい。
(IV) As shown in FIG.
Separately from 9, mounting holes 23 may be provided at a plurality of locations on the front side of the boom front end in the boom length direction so that the mounting position of the leaving sheave 16 can be changed according to the working conditions.

【0049】[0049]

【発明の効果】上記のように本発明によるときは、ポイ
ントシーブよりも下方位置においてブーム先端部の前面
に、リービングシーブを、前後方向の水平軸まわりに回
転自在で、かつ、側面視において吊りロープをランニン
グシーブとリービングシーブとの間でほぼ鉛直状態また
はロープ間隔が下広がりとなる状態でガイドしうる位置
に設けたから、吊りロープが掘削孔の入口部分と干渉す
るおそれがなくなる。
As described above, according to the present invention, a leaving sheave is rotatable around the horizontal axis in the front-rear direction and is suspended from the side in front of the boom tip at a position below the point sheave. Since the rope is provided at a position where it can be guided in a substantially vertical state between the running sheave and the leaving sheave or in a state where the rope interval is widened downward, there is no possibility that the suspension rope will interfere with the entrance of the excavation hole.

【0050】従って、ロープ間隔を絞るためのガイドブ
ロックが不要となるため、吊り揚程を高くとることがで
きる。
Accordingly, a guide block for narrowing the rope interval is not required, so that the lifting height can be increased.

【0051】また、請求項2の発明によると、ロープ間
隔が側面視だけでなく正面視においてもほぼ一定となる
ため、ホース等を掴み保持するクランプを吊りロープに
取付ける掘削機の場合に、クランプを吊りロープに対し
いずれの位置でも取付けることができる。
According to the second aspect of the present invention, the rope interval is substantially constant not only in a side view but also in a front view. Therefore, in the case of an excavator in which a clamp for holding and holding a hose or the like is attached to a suspension rope, Can be attached to the hanging rope at any position.

【0052】さらに、請求項3の発明によると、ブーム
が作業姿勢から倒された場合に、これに伴ってリービン
グシーブが回動するため、ロープが同シーブから外れる
等のトラブルが発生するおそれがない。
Further, according to the third aspect of the present invention, when the boom is tilted from the working posture, the leaving sheave is rotated accordingly, which may cause troubles such as the rope coming off the sheave. Absent.

【0053】さらに、請求項4の発明によると、作業時
のブーム角度(作業半径)の変化に応じてリービングシ
ーブの取付位置を変更することができる。
Further, according to the invention of claim 4, the mounting position of the leaving sheave can be changed in accordance with a change in the boom angle (work radius) during work.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施例を示す側面図である。FIG. 1 is a side view showing an embodiment of the present invention.

【図2】同正面図である。FIG. 2 is a front view of the same.

【図3】同実施例におけるロープガイド状態を説明する
ための概略斜視図である。
FIG. 3 is a schematic perspective view for explaining a rope guide state in the embodiment.

【図4】本発明の他の実施例を示す側面図である。FIG. 4 is a side view showing another embodiment of the present invention.

【図5】本発明のまた別の実施例を示す正面図である。FIG. 5 is a front view showing still another embodiment of the present invention.

【図6】本発明のさらに別の実施例を示す側面図であ
る。
FIG. 6 is a side view showing still another embodiment of the present invention.

【図7】従来技術を説明するための掘削機全体の概略側
面図である。
FIG. 7 is a schematic side view of the entire excavator for explaining the prior art.

【図8】従来技術によるロープガイド状態を示す概略斜
視図である。
FIG. 8 is a schematic perspective view showing a rope guide state according to the related art.

【図9】同側面図である。FIG. 9 is a side view of the same.

【符号の説明】[Explanation of symbols]

1 ベースマシン 4 ブーム 8 掘削装置 6 ポイントシーブ 6a ポイントシーブ軸 10 ランニングシーブ 10a ランニングシーブ軸 13 吊りロープ 16 リービングシーブ 16a リービングシーブ軸 17 リービングシーブフレーム 18 同フレーム取付用の水平軸 19 リービングシーブフレームの取付部としてのロー
プエンド止着用ブラケット 23 同取付部としての取付孔
DESCRIPTION OF SYMBOLS 1 Base machine 4 Boom 8 Excavator 6 Point sheave 6a Point sheave axis 10 Running sheave axis 10a Running sheave axis 13 Hanging rope 16 Leaving sheave 16a Leaving sheave axis 17 Leaving sheave frame 18 Horizontal axis for attaching the same frame 19 Mounting of sheave sheave frame Rope end fastening bracket as part 23 Mounting hole as mounting part

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E02F 5/02 B66C 23/66 B66D 1/36 E21B 19/02 ──────────────────────────────────────────────────続 き Continued on the front page (58) Field surveyed (Int. Cl. 7 , DB name) E02F 5/02 B66C 23/66 B66D 1/36 E21B 19/02

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 ベースマシンと、このベースマシンに装
着されたブームと、ウィンチから引出された吊りロープ
によってブームの先端に吊持される掘削装置とを備えた
掘削機において、上記ブームの先端部に上記吊りロープ
が通されるポイントシーブ、上記掘削装置に上記ポイン
トシーブとの間で吊りロープが掛け回されるランニング
シーブをそれぞれ左右一対ずつ、左右方向の水平軸まわ
りに回転自在に設けるとともに、上記ポイントシーブよ
りも下方位置において、ブーム先端部の前面にリービン
グシーブを、前後方向の水平軸まわりに回転自在で、か
つ、側面視において吊りロープを上記ランニングシーブ
とリービングシーブとの間でほぼ鉛直状態またはロープ
間隔が下広がりとなる状態でガイドしうる位置に設けた
ことを特徴とする掘削機の吊りロープガイド装置。
An excavator comprising a base machine, a boom mounted on the base machine, and an excavating device suspended at a tip of the boom by a hanging rope pulled out from a winch. A point sheave through which the suspension rope is passed, a pair of left and right running sheaves around which the suspension rope is hung between the point sheave and the excavator are provided rotatably around a horizontal axis in the left-right direction. At a position lower than the point sheave, a leafing sheave is provided at the front of the boom tip, and is rotatable around a horizontal axis in the front-rear direction, and the suspension rope is substantially vertical between the running sheave and the leafing sheave in a side view. Characterized in that it is provided at a position where it can be guided in a state or a state where the rope interval is widened downward. Hanging rope guide device for cutters.
【請求項2】 両ポイントシーブのシーブ間隔と両ラン
ニングシーブのシーブ間隔とリービングシーブの直径寸
法を同一とし、かつ、リービングシーブを、正面視にお
いてポイントシーブとランニングシーブを結ぶ二本の鉛
直線の間に位置させたことを特徴とする請求項1記載の
掘削機の吊りロープガイド装置。
2. The sheave interval between both point sheaves, the sheave interval between both running sheaves, and the diameter dimension of the leaving sheave are the same, and the leaving sheave is formed by two vertical lines connecting the point sheave and the running sheave in a front view. The suspension rope guide device for an excavator according to claim 1, wherein the suspension rope guide device is located between the suspension ropes.
【請求項3】 リービングシーブが取付けられたリービ
ングシーブフレームを、ブームに対し左右方向の水平軸
を中心として回動可能に取付けたことを特徴とする請求
項1または2記載の掘削機の吊りロープガイド装置。
3. The suspension rope of an excavator according to claim 1, wherein the leaving sheave frame to which the leaving sheave is attached is attached to the boom so as to be rotatable around a horizontal horizontal axis. Guide device.
【請求項4】 リービングシーブフレームが取付けられ
る取付部を、ブーム先端部の複数個所に設けたことを特
徴とする請求項3記載の掘削機の吊りロープガイド装
置。
4. The suspension rope guide device for an excavator according to claim 3, wherein attachment portions to which the leaving sheave frame is attached are provided at a plurality of positions at the end of the boom.
JP08088693A 1993-04-07 1993-04-07 Excavator hanging rope guide device Expired - Fee Related JP3225677B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP08088693A JP3225677B2 (en) 1993-04-07 1993-04-07 Excavator hanging rope guide device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP08088693A JP3225677B2 (en) 1993-04-07 1993-04-07 Excavator hanging rope guide device

Publications (2)

Publication Number Publication Date
JPH06294129A JPH06294129A (en) 1994-10-21
JP3225677B2 true JP3225677B2 (en) 2001-11-05

Family

ID=13730834

Family Applications (1)

Application Number Title Priority Date Filing Date
JP08088693A Expired - Fee Related JP3225677B2 (en) 1993-04-07 1993-04-07 Excavator hanging rope guide device

Country Status (1)

Country Link
JP (1) JP3225677B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011006199A (en) * 2009-06-25 2011-01-13 Hitachi Sumitomo Heavy Industries Construction Crane Co Ltd Leaving device, crane, and rope wiring method

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2755709B1 (en) * 1996-11-14 1999-02-05 Sol Comp Du DRILLING DEVICE COMPRISING A DRILLING MACHINE
JP6316225B2 (en) * 2015-02-24 2018-04-25 復建調査設計株式会社 On-site permeability test device and installation method thereof
CN111271008B (en) * 2020-03-05 2022-01-07 徐州徐工基础工程机械有限公司 Swing goose head of auxiliary pulley frame of rotary drilling rig, goose head of rotary drilling rig and rotary drilling rig
CN114278237B (en) * 2021-12-28 2023-10-20 山河智能装备股份有限公司 Self-adaptive balancing mechanism for stand column bending moment

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011006199A (en) * 2009-06-25 2011-01-13 Hitachi Sumitomo Heavy Industries Construction Crane Co Ltd Leaving device, crane, and rope wiring method

Also Published As

Publication number Publication date
JPH06294129A (en) 1994-10-21

Similar Documents

Publication Publication Date Title
CA2983835C (en) Pipelayer machine with symmetrical winches
JP3225677B2 (en) Excavator hanging rope guide device
JP3218183B2 (en) Pile driver top sheave device
JP7507711B2 (en) Earth Drill Machine
JP3606800B2 (en) Pile sheave top sheave
JP3275732B2 (en) Hydro phrase excavator
JP2860978B2 (en) Suspended excavator
JP3366602B2 (en) Front attachment support device for ground excavator
JPH0547820Y2 (en)
JP3012132B2 (en) Method and apparatus for assembling ground drill
JP2021091489A (en) Attitude control device of grab bucket and attitude control method
JP3782331B2 (en) Earth drill
JP2743349B2 (en) How to suspend sludge hose of underground excavator
JP3782324B2 (en) Earth drill
JP3250658B2 (en) Caisson excavator cable drawing equipment
JPH0355598Y2 (en)
JP3612099B2 (en) Retraction mechanism of upper device
JP2771843B2 (en) Excavator
JP2876590B2 (en) Low head crane
JP2712874B2 (en) Excavator hose suspension
JPH0635391U (en) Underground wall drilling equipment
JPS6226372B2 (en)
JP2589386Y2 (en) Hydraulic excavator equipped with winch for overhead wire collecting
JPH0441392A (en) Hook block suspension device for crane
JP2001055736A (en) Bearing device of hose for pile driver, and mounting method

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees
S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350