JP2693699B2 - Ceiling mounting structure - Google Patents
Ceiling mounting structureInfo
- Publication number
- JP2693699B2 JP2693699B2 JP5134774A JP13477493A JP2693699B2 JP 2693699 B2 JP2693699 B2 JP 2693699B2 JP 5134774 A JP5134774 A JP 5134774A JP 13477493 A JP13477493 A JP 13477493A JP 2693699 B2 JP2693699 B2 JP 2693699B2
- Authority
- JP
- Japan
- Prior art keywords
- ceiling
- view
- lower chord
- base panel
- ceiling base
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000002184 metal Substances 0.000 claims description 29
- 239000000463 material Substances 0.000 claims description 15
- 241000473391 Archosargus rhomboidalis Species 0.000 claims 1
- 238000010276 construction Methods 0.000 description 9
- 230000037431 insertion Effects 0.000 description 6
- 238000003780 insertion Methods 0.000 description 6
- 238000009434 installation Methods 0.000 description 2
- 238000005192 partition Methods 0.000 description 2
- 238000009435 building construction Methods 0.000 description 1
- 239000002893 slag Substances 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
Landscapes
- Joining Of Building Structures In Genera (AREA)
- Building Environments (AREA)
Description
【0001】[0001]
【産業上の利用分野】この発明は、天井取付構造に関す
るものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a ceiling mounting structure.
【0002】[0002]
【従来の技術】従来、屋根裏の下の2階の天井を施工す
る場合、屋根トラスの下方に配置する天井下地パネル
は、建物上棟工事終了後の大工工事にて、吊金具および
吊木等を用いて吊り固定していた。2. Description of the Related Art Conventionally, in the case of constructing a ceiling on the second floor under the attic, the ceiling base panel placed below the roof truss is equipped with hanging metal fittings and hanging trees in carpentry work after the completion of the building ridge construction. It was suspended and fixed.
【0003】[0003]
【発明が解決しようとする課題】従来の天井取付構造
は、上記のように建物上棟工事終了後の大工工事にて天
井下地パネルを取付けていたので、大工工事に手間がか
かるという問題点があった。したがって、この発明の目
的は、大工工事の省力化を図った天井取付構造を提供す
ることである。The conventional ceiling mounting structure has a problem that the carpentry work is troublesome because the ceiling base panel is mounted in the carpentry work after the completion of the building upper building work as described above. Was. Therefore, an object of the present invention is to provide a ceiling mounting structure that saves labor in carpentry work.
【0004】[0004]
【課題を解決するための手段】この発明の天井取付構造
は、建物の天井に複数の区画が形成されるように、屋根
トラスの下弦材とこの下弦材に直交するように架設され
た横架材とが縦横に組まれ、各区画のコーナ付近の前記
下弦材または横架材に取付部を有する吊金物を固着し、
前記区画に対応するように天井下地パネルを枠組みする
とともに、この天井下地パネルの枠内の入隅部に火打ち
金物を取付け、この火打ち金物を前記取付部にビス止め
したことを特徴とするものである。The ceiling mounting structure of the present invention has a roof so that a plurality of compartments are formed on the ceiling of a building.
It is erected so that it is orthogonal to the lower chord of the truss and this lower chord.
The horizontal crossing material and the horizontal crossing material are assembled vertically and horizontally, and the hanging metal article having the mounting portion is fixed to the lower chord material or the horizontal crossing material near the corner of each section ,
Frame the ceiling base panel to correspond to the compartment
At the same time, a flint metal fitting is attached to an inside corner portion of the frame of the ceiling base panel, and the flint metal fitting is screwed to the attachment portion.
【0005】[0005]
【作用】この発明の構成によれば、屋根トラスの下弦材
に直交するように横架材を架設し、かつ枠組みされた天
井下地パネルの枠内の入隅部に火打ち金物を取付け、こ
の火打ち金物を屋根トラスの下弦材または横架材に固着
した吊金物の取付部にビス止めしたので、上棟工事の終
了段階で天井下地パネルの取付けを完成させることがで
きる。また、建物の天井に複数の区画が形成されるよう
に、屋根トラスの下弦材とこの下弦材に直交するように
架設された横架材とが縦横に組まれ、各区画のコーナ付
近の下弦材または横架材に取付部を有する吊金物を固着
したので、天井に対する吊金物の位置が決まるととも
に、天井の周囲および内部に一様に吊金物を配置するこ
とができる。このため、複数の区画に及ぶ大きな天井下
地パネルでも安定した状態で吊持できる。また、天井下
地パネルは上記区画に対応するように枠組みされ、その
枠内の入隅部に火打ち金物を取付けたので、天井下地パ
ネルが所定の取付位置に配置されると、火打ち金物と吊
金物の位置が対応し取付部にビス止めする作業が容易に
できる。 According to the structure of the present invention, a horizontal member is erected so as to be orthogonal to the lower chord member of the roof truss, and a struck metal fitting is attached to the corner of the frame of the framed ceiling base panel. Since the metal fittings were screwed to the attachment parts of the hanging hardware fixed to the lower chord material or the horizontal material of the roof truss, the installation of the ceiling base panel can be completed at the end stage of the upper building construction. Also, make sure that multiple partitions are formed on the ceiling of the building.
So that it is orthogonal to the lower chord of the roof truss and this lower chord
Horizontally installed materials are assembled vertically and horizontally, with corners for each section
Fasten hanging hardware with mounting part to nearby lower chord or horizontal material
As a result, the position of the hanging hardware relative to the ceiling is decided.
The hanging hardware evenly around and inside the ceiling.
Can be. For this reason, under a large ceiling that spans multiple compartments
Even the ground panel can be hung in a stable state. Also under the ceiling
The ground panel is framed to correspond to the above section,
Since a metal fitting was attached to the inside corner of the frame,
Once the flannel is in place, it will
Corresponds to the position of the metal object, making it easy to screw on the mounting part
it can.
【0006】[0006]
【実施例】この発明の一実施例の天井取付構造を図1な
いし図27に基づいて説明する。この天井取付構造で
は、建物の屋根裏に架設された屋根トラス1の下方に枠
組みされた天井下地パネル31が配置され、この天井下
地パネル31が屋根トラス1側に取付けられる。図8は
その建物の平面図であり、A部を図1、B部を図2、C
部を図3、D部を図4、E部を図5、F部を図6、G部
を図7にそれぞれ示した。FIG. 1 shows a ceiling mounting structure according to an embodiment of the present invention.
This will be explained based on FIG. 27. This ceiling mounting structureso
Is below the roof truss 1 installed in the attic of the building.frame
The assembled ceiling base panel 31 is placed under this ceiling
The ground panel 31 is attached to the roof truss 1 side.FIG. 8
It is a top view of the building, A part is FIG. 1, B part is FIG. 2, C
Part is FIG. 3, part D is FIG. 4, part E is FIG. 5, part F is FIG. 6, part G is
ToEach is shown in FIG. 7.
【0007】また、図10に示すように、建物の天井に
複数の区画が形成されるように、屋根トラス1の下弦材
1aと、この下弦材1aに直交するように架設された横
架材2とが受金物3を用いて縦横に組まれている。下弦
材1aおよび横架材2は上向き溝形の部材である。受金
物3は、図11に示すように、ねじ挿通孔3aを有する
L形の金物で、その垂直片3bの上端および下端を屈曲
させてある。そして、この上端に形成された引っ掛け部
3dを下弦材1aのフランジに引っ掛けて垂直片3bを
ねじ(図示せず)により固定し、横架材2の端部を受金
物3の水平片3cの上に載せて同様にねじ4により固定
している。Also, as shown in FIG. 10, the ceiling of the building is
Lower chord of roof truss 1 so that multiple compartments are formed
1a and a laterally erected transversely to the lower chord member 1a
The frame 2 and the receiving material 3 are vertically and horizontally assembled. The lower chord member 1a and the horizontal member 2 are upward grooved members. As shown in FIG. 11, the metal receiving object 3 is an L-shaped metal object having a screw insertion hole 3a, and an upper end and a lower end of a vertical piece 3b thereof are bent. Then, the hook portion 3d formed at the upper end is hooked on the flange of the lower chord member 1a to fix the vertical piece 3b with a screw (not shown) , and the end portion of the horizontal member 2 of the horizontal piece 3c of the receiving object 3 is fixed. It is placed on the top and is similarly fixed by the screw 4.
【0008】つぎに、図8における各部の詳細について
説明する。図1に示すA部は、外壁パネル5の近傍を示
し、屋根パネル6の枠6aを受ける屋根金物7が外壁パ
ネル5の上端に固定してある。枠6aには図13に示す
ような受金物8が取付けられる。この受金物8は、略L
形で垂直片8bの上部の半分は切除され、残部に切欠き
部8dが設けてある。水平片8cにはねじ挿通孔8aが
設けてある。そして、図12に示すように、切欠き部8
dを枠6aの下フランジにかち込み、一端が屋根トラス
1に接合された横架材2の他端を水平片8cの上に載せ
てねじ4により固定している。このように架設された横
架材2の下部に吊金物9を介して天井下地パネル31が
吊持される。Next, details of each part in FIG. 8 will be described. The A portion shown in FIG. 1 shows the vicinity of the outer wall panel 5, and a roof metal fitting 7 for receiving the frame 6a of the roof panel 6 is fixed to the upper end of the outer wall panel 5. A receiving object 8 as shown in FIG. 13 is attached to the frame 6a. This receipt 8 is approximately L
In the shape, the upper half of the vertical piece 8b is cut off, and a cutout portion 8d is provided in the remaining portion. The horizontal piece 8c is provided with a screw insertion hole 8a. Then, as shown in FIG. 12, the notch 8
d is pushed into the lower flange of the frame 6a, and the other end of the horizontal member 2 whose one end is joined to the roof truss 1 is placed on the horizontal piece 8c and fixed by the screw 4. The ceiling base panel 31 is hung from the lower portion of the horizontal member 2 thus constructed via the hanging hardware 9.
【0009】天井下地パネル31は、図8および図9に
示すように前記区画に対応するように枠組みされ、枠内
の四隅に火打ち金物14が取付けられる。この火打ち金
物14には、状況に応じて使用される複数のビス挿通孔
14a…が設けられる。吊金物9は、図14に示すよう
に、略ハット形で、下向きに開口した溝形部10と、こ
の溝形部10の両垂下片にスライド自在にねじ等の固着
具12により連結した一対のL形部11,11とからな
る。L形部11の水平片にはビス挿通孔11aが設けら
れて取付部11bとなる。溝形部10の中央には取付孔
10aが設けられる。The ceiling base panel 31 is shown in FIGS. 8 and 9.
As shown, it is framed so as to correspond to the above-mentioned compartment, and the fire metal 14 is attached to the four corners of the frame. A plurality of screw insertion holes 14a, which are used depending on the situation, are provided in the flint metal article 14. As shown in FIG. 14, the hanging hardware 9 is substantially hat-shaped, and has a pair of downwardly opening groove portions 10 and slidably connected to both hanging pieces of the groove portions 10 by fasteners 12 such as screws. And L-shaped parts 11 and 11. The horizontal piece of the L-shaped portion 11 is provided with a screw insertion hole 11a and serves as a mounting portion 11b. A mounting hole 10a is provided at the center of the groove portion 10.
【0010】この場合、天井下地パネル31の取付けに
際しては、図1、図15および図16に示すように、吊
金物9を横架材2の下部にボルト等の固着具15で固定
し、両側の取付部11b,11bを隣接する天井下地パ
ネル31,31の火打ち金物14,14にビス16…で
固定している。図2に示すB部では、4つの天井下地パ
ネル31…のコーナ部が集まる位置で、屋根トラス1の
下弦材1aに横架材2が直交する位置に対応する。天井
下地パネル31の施工時には、図17および図18に示
すように、吊金物9を屋根トラス1の下弦材1aの下部
に固着具15で固定し、両側の取付部11b,11bを
図1と同様に火打ち金物14,14にビス16…で固定
している。In this case, when mounting the ceiling base panel 31, as shown in FIGS . 1, 15 and 16, the hanging hardware 9 is fixed to the lower portion of the horizontal member 2 with a fixing tool 15 such as a bolt, and both sides are fixed. The mounting portions 11b and 11b of the above are fixed to the flint metal articles 14 and 14 of the adjacent ceiling base panels 31 and 31 with screws 16. In the portion B shown in FIG. 2, the corner portions of the four ceiling base panels 31 ... Are gathered and correspond to the position where the horizontal member 2 is orthogonal to the lower chord member 1a of the roof truss 1. At the time of constructing the ceiling base panel 31, as shown in FIGS. 17 and 18, the hanging hardware 9 is fixed to the lower part of the lower chord member 1a of the roof truss 1 with the fastener 15, and the mounting portions 11b and 11b on both sides are as shown in FIG. Similarly, it is fixed to the slag hardware 14, 14 with screws 16.
【0011】図3に示すC部では、B部と同様に4つの
天井下地パネル31…のコーナ部が集まる位置である
が、柱32が介在するために(図6参照)一組の天井下
地パネル31,31が間隔をおいて配設される。この場
合、B部と同様の施工で天井下地パネル31が取付けら
れるが、図19および図20に示すように、火打ち金物
14,14の間隔が大きくなるためビス16で固定する
際に使用するビス挿通孔14aが異なる。In the C portion shown in FIG. 3, the corner portions of the four ceiling underlayer panels 31 are gathered like the B portion, but since the pillars 32 are interposed (see FIG. 6), a set of ceiling underlayers is formed. The panels 31, 31 are arranged at intervals. In this case, the ceiling base panel 31 is attached by the same construction as that of the part B, but as shown in FIGS. 19 and 20, the interval between the fire metal fittings 14, 14 becomes large, and therefore the screw used when fixing with the screw 16. The insertion holes 14a are different.
【0012】図4に示すD部は、B部の屋根トラス1の
端部が位置する外壁パネル5の近傍を示している。外壁
パネル5の上端に屋根トラス受金物17が固定され、こ
れに屋根トラス1の端部が支持されている。天井下地パ
ネル31の施工はB部と同様である。図5に示すE部
は、C部の屋根トラス1の一端部が位置する外壁パネル
5の近傍を示している。図21および図22に示すよう
に、D部と同様に外壁パネル5の上端に屋根トラス受金
物17が固定され、これに屋根トラス1の端部が支持さ
れている。天井下地パネル31の施工はC部と同様であ
る。The D portion shown in FIG. 4 shows the vicinity of the outer wall panel 5 where the end portion of the roof truss 1 of the B portion is located. A roof truss bracket 17 is fixed to the upper end of the outer wall panel 5, and an end portion of the roof truss 1 is supported by the roof truss bracket 17. The construction of the ceiling base panel 31 is the same as that of the part B. The E section shown in FIG. 5 shows the vicinity of the outer wall panel 5 where one end of the roof truss 1 of the C section is located. As shown in FIGS. 21 and 22, the roof truss bracket 17 is fixed to the upper end of the outer wall panel 5 similarly to the section D, and the end of the roof truss 1 is supported thereby. The construction of the ceiling base panel 31 is the same as that of the C part.
【0013】図6に示すF部は、C部の屋根トラス1の
他端部が位置する柱32の近傍で4つの天井下地パネル
31…のコーナ部が集まる位置を示している。図23お
よび図24に示すように、この柱32には十字形に4方
向に配設される屋根トラス1の端部が固定される。ま
た、柱32が介在するため各天井下地パネル31…は間
隔をおいて配設される。この場合の施工は、C部および
E部と同様である。The F portion shown in FIG. 6 shows a position where the corner portions of the four ceiling base panels 31 ... Collect near the pillar 32 where the other end of the roof truss 1 of the C portion is located. As shown in FIGS. 23 and 24, the ends of the roof truss 1 arranged in four directions in a cross shape are fixed to the columns 32. Further, since the pillars 32 are interposed, the ceiling base panels 31 ... Are arranged at intervals. The construction in this case is the same as that of the C part and the E part.
【0014】図7に示すG部は、外壁パネル5のコーナ
部を示し、コーナ用屋根受金物18が外壁パネル5の上
端に固定してある。コーナ用屋根受金物18には吊金物
19が取付けられる。この吊金物19は、図27に示す
ように、コ字形の金物で、上片にブレース取付孔19
a、下片にビス挿通孔19bが設けてある。施工時には
図25および図26に示すように、ブレース20の端部
を吊金物19の上片に固定し、火打ち金物14を吊金物
19の下片に固定して天井下地パネル31を取付ける。A G portion shown in FIG. 7 shows a corner portion of the outer wall panel 5, and a roof member 18 for a corner is fixed to an upper end of the outer wall panel 5. A hanging hardware 19 is attached to the corner roof hardware 18. As shown in FIG. 27, the hanging hardware 19 is a U-shaped hardware and has a brace mounting hole 19 on the upper piece.
a, a screw insertion hole 19b is provided in the lower piece. At the time of construction, as shown in FIG. 25 and FIG. 26, the end of the brace 20 is fixed to the upper piece of the hanging hardware 19, the flint metal fitting 14 is fixed to the lower piece of the hanging hardware 19, and the ceiling base panel 31 is attached.
【0015】また、本実施例とは異なるが、図8におい
て、H部、I部、J部、火打ち金物14を介しないで天
井下地パネル31が吊持される。図28に示すH部で
は、屋根金物33の位置に図31に示すような吊金物2
1が取付けられる。この吊金物21は、屋根パネル22
の枠の下フランジにかち込まれる切欠き部21aが上部
に設けられ、天井下地パネル31に取付けられる取付部
21bが下部にれ設けられる。図29に示すI部では、
図32に示すような吊金物23が取付けられる。この吊
金物23は、屋根トラス1の下弦材1aまたは横架材2
のフランジに引っ掛けられる引っ掛け部23aと、この
引っ掛け部23aに対してスライド自在に連結され天井
下地パネル31に取付けられる取付部23bとからな
る。図30に示すJ部では、取付部23b′の形状が異
なる図32と同様の吊金物23′が使用される。Although different from the present embodiment, in FIG. 8, the ceiling base panel 31 is suspended without the H portion, the I portion, the J portion, and the metal hammer 14 being interposed. In the H part shown in FIG. 28, the hanging hardware 2 as shown in FIG.
1 is attached. This hanging hardware 21 is a roof panel 22.
A notch 21a that is cut into the lower flange of the frame is provided in the upper portion, and a mounting portion 21b attached to the ceiling base panel 31 is provided in the lower portion. In part I shown in FIG. 29,
A hanging piece 23 as shown in FIG. 32 is attached. The hanging hardware 23 is a lower chord member 1a or a horizontal member 2 of the roof truss 1.
And a mounting portion 23b slidably connected to the hanging portion 23a and mounted on the ceiling base panel 31. In the J section shown in FIG. 30, a hanging piece 23 'similar to that in FIG. 32 is used, in which the shape of the mounting portion 23b' is different.
【0016】以上のようにこの実施例では、屋根トラス
1の下弦材1aに直交するように横架材2を架設し、か
つ枠組みされた天井下地パネル31の枠内の入隅部に火
打ち金物14を取付け、この火打ち金物14を屋根トラ
ス1の下弦材1aまたは横架材2に固着した吊金物9の
取付部11bにビス止めしたので、上棟工事の終了段階
で天井下地パネル31の取付けを完成させることができ
る。また、図8に示すように、建物の天井に複数の区画
が形成されるように、屋根トラス1の下弦材1aとこの
下弦材1aに直交するように架設された横架材2とが縦
横に組まれ、各区画のコーナ付近の下弦材1aまたは横
架材2に取付部11bを有する吊金物9を固着したの
で、天井に対する吊金物9の位置が決まるとともに、天
井の周囲および内部に一様に吊金物9を配置することが
できる。このため、複数の区画に及ぶ大きな天井下地パ
ネル31でも安定した状態で吊持できる。また、図9に
示すように、天井下地パネル31は上記区画に対応する
ように枠組みされ、その枠内の入隅部に火打ち金物14
を取付けたので、天井下地パネル31が所定の取付位置
に配置されると、火打ち金物14と吊金物9の位置が対
応し取付部11bにビス止めする作業が容易にできる。
また、吊金物23の取付部23bがスライド自在である
ため、天井下地パネル31の取付後の天井高さ調整が可
能になる。また、火打ち金物14を用いずに直接天井下
地パネル31に固着する吊金物21,23には、切欠き
部21a、引っ掛け部23aが設けてあり、固着具を使
用しないので施工が容易になる。As described above, in this embodiment, the horizontal member 2 is erected so as to be orthogonal to the lower chord member 1a of the roof truss 1, and the flint metal fittings are provided at the corners in the frame of the ceiling base panel 31 framed. 14 is attached, and this flint metal 14 is screwed to the attachment portion 11b of the hanging metal 9 fixed to the lower chord member 1a or the horizontal member 2 of the roof truss 1, so that the ceiling base panel 31 is attached at the end stage of the upper ridge construction. Can be completed. In addition, as shown in FIG.
And the lower chord member 1a of the roof truss 1
The horizontal bridge member 2 which is erected so as to be orthogonal to the lower chord member 1a is vertically
The lower chords 1a that are assembled horizontally and are located near the corners of each section or horizontally
The hanging hardware 9 having the mounting portion 11b is fixed to the frame material 2.
The position of the hanging hardware 9 with respect to the ceiling is determined, and
It is possible to arrange the hanging hardware 9 uniformly around and inside the well.
it can. For this reason, a large ceiling base pad covering multiple partitions
Even the flannel 31 can be hung in a stable state. Also, in FIG.
As shown, the ceiling base panel 31 corresponds to the above section.
It is framed like this, and the metal fittings 14
Since the ceiling base panel 31 has been installed,
When it is arranged in the
Accordingly, it is possible to easily perform the work of screwing to the mounting portion 11b.
Further, since the mounting portion 23b of the hanging hardware 23 is slidable, it is possible to adjust the ceiling height after mounting the ceiling base panel 31. Further, the hanging hardwares 21 and 23 that are directly fixed to the ceiling base panel 31 without using the flint metal fitting 14 are provided with the cutout portions 21a and the hook portions 23a, and since the fixing tool is not used, the construction is facilitated.
【0017】[0017]
【発明の効果】この発明の天井取付構造によれば、屋根
トラスの下弦材に直交するように横架材を架設し、かつ
枠組みされた天井下地パネルの枠内の入隅部に火打ち金
物を取付け、この火打ち金物を屋根トラスの下弦材また
は横架材に固着した吊金物の取付部にビス止めしたの
で、上棟工事の終了段階で天井下地パネルの取付けを完
成させることができる。したがって、上棟工事終了後の
大工工事の施工の省力化を図ることができる。また、建
物の天井に複数の区画が形成されるように、屋根トラス
の下弦材とこの下弦材に直交するように架設された横架
材とが縦横に組まれ、各区画のコーナ付近の下弦材また
は横架材に取付部を有する吊金物を固着したので、天井
に対する吊金物の位置が決まるとともに、天井の周囲お
よび内部に一様に吊金物を配置することができる。この
ため、複数の区画に及ぶ大きな天井下地パネルでも安定
した状態で吊持できる。また、天井下地パネルは上記区
画に対応するように枠組みされ、その枠内の入隅部に火
打ち金物を取付けたので、天井下地パネルが所定の取付
位置に配置されると、火打ち金物と吊金物の位置が対応
し取付部にビス止めする作業が容易にできる。 According to the ceiling mounting structure of the present invention, a horizontal member is erected so as to be orthogonal to the lower chord member of the roof truss, and a flint is provided at the corner of the frame of the ceiling base panel. Since the flint metal fittings were attached to the lower truss members of the roof truss or the attachment members of the hanging metal members fixed to the horizontal members with screws, it is possible to complete the installation of the ceiling base panel at the end of the construction of the upper wing. Therefore, it is possible to save labor in carpentry work after the completion of the upper building work. Also,
Roof truss so that multiple compartments are formed on the ceiling of the object
Lower chord material and a horizontal bridge installed so as to be orthogonal to this lower chord material
Timber and wood are assembled vertically and horizontally, and the lower chord material near the corners of each section
Is attached to the horizontal member with the hanging hardware, so the ceiling
The position of the hanging hardware relative to the
Also, the hanging hardware can be uniformly arranged inside. this
Therefore, it is stable even for large ceiling base panels that span multiple sections
It can be hung in a closed state. In addition, the ceiling base panel is the above
It is framed so as to correspond to the drawing, and fire is applied to the corners inside the frame.
Since the metal fittings are attached, the ceiling base panel is installed in the specified
When placed in position, the position of fire metal and hanging metal objects correspond
The work of fixing screws to the mounting part can be done easily.
【図1】この発明の一実施例で図8のA部の一部破断分
解斜視図である。FIG. 1 is a partially cutaway exploded perspective view of a portion A of FIG. 8 according to an embodiment of the present invention.
【図2】図8のB部の分解斜視図である。FIG. 2 is an exploded perspective view of a B part in FIG.
【図3】図8のC部の分解斜視図である。FIG. 3 is an exploded perspective view of a C portion of FIG.
【図4】図8のD部の分解斜視図である。FIG. 4 is an exploded perspective view of a D part of FIG.
【図5】図8のE部の分解斜視図である。5 is an exploded perspective view of a portion E of FIG.
【図6】図8のF部の分解斜視図である。FIG. 6 is an exploded perspective view of a portion F of FIG.
【図7】図8のG部の分解斜視図である。7 is an exploded perspective view of a G part in FIG.
【図8】吊金物の取付位置を示す平面図である。FIG. 8 is a plan view showing a mounting position of a hanging hardware.
【図9】天井下地パネルの平面図である。FIG. 9 is a plan view of a ceiling base panel.
【図10】屋根トラスと横架材の連結構造を示す分解斜
視図である。FIG. 10 is an exploded perspective view showing a connecting structure of a roof truss and a horizontal member.
【図11】受金物の斜視図である。FIG. 11 is a perspective view of a receiving object.
【図12】図1において横架材の取付説明図である。FIG. 12 is an explanatory view for attaching the horizontal member in FIG. 1.
【図13】別の受金物の斜視図である。FIG. 13 is a perspective view of another receiving object.
【図14】吊金物の斜視図である。FIG. 14 is a perspective view of a hanging piece.
【図15】A部の断面側面図である。FIG. 15 is a sectional side view of a portion A.
【図16】A部の平面図である。FIG. 16 is a plan view of part A.
【図17】B部の断面側面図である。FIG. 17 is a sectional side view of a B part.
【図18】B部の平面図である。FIG. 18 is a plan view of a B part.
【図19】C部の断面側面図である。FIG. 19 is a sectional side view of a C portion.
【図20】C部の平面図である。FIG. 20 is a plan view of a C portion.
【図21】E部の断面側面図である。FIG. 21 is a sectional side view of an E portion.
【図22】E部の平面図である。FIG. 22 is a plan view of an E portion.
【図23】F部の断面側面図である。FIG. 23 is a sectional side view of an F portion.
【図24】F部の平面図である。FIG. 24 is a plan view of an F portion.
【図25】G部の断面側面図である。FIG. 25 is a sectional side view of a G part.
【図26】G部の平面図である。FIG. 26 is a plan view of a G part.
【図27】別の吊金物の斜視図である。FIG. 27 is a perspective view of another hanging piece.
【図28】図8のH部の斜視図である。28 is a perspective view of an H part in FIG. 8. FIG.
【図29】図8のI部の斜視図である。29 is a perspective view of a portion I of FIG. 8. FIG.
【図30】図8のJ部の斜視図である。30 is a perspective view of a J portion of FIG. 8. FIG.
【図31】図28で示された吊金物の斜視図である。FIG. 31 is a perspective view of the hanging hardware shown in FIG. 28.
【図32】図29で示された吊金物の斜視図である。32 is a perspective view of the hanging hardware shown in FIG. 29. FIG.
1 屋根トラス 2 横架材 9 吊金物 11b 取付部 14 火打ち金物 31 天井下地パネル 1 Roof truss 2 Horizontal material 9 Hanging hardware 11b Mounting part 14 Fire metal fitting 31 Ceiling base panel
Claims (1)
うに、屋根トラスの下弦材とこの下弦材に直交するよう
に架設された横架材とが縦横に組まれ、各区画のコーナ
付近の前記下弦材または横架材に取付部を有する吊金物
を固着し、前記区画に対応するように天井下地パネルを
枠組みするとともに、この天井下地パネルの枠内の入隅
部に火打ち金物を取付け、この火打ち金物を前記取付部
にビス止めしたことを特徴とする天井取付構造。1. A plurality of compartments are formed on a ceiling of a building.
Sea bream, so that it is orthogonal to the lower chord of the roof truss and this lower chord
The horizontal materials installed on the
Secure a hanging metal piece having an attachment part to the lower chord member or horizontal member in the vicinity, and attach the ceiling base panel so as to correspond to the section.
As well as a framework, the ceiling mounting structure, characterized in that the mounting of the angle brace hardware into internal corner portion of the frame of the roof underlying panels were screwed the angle brace hardware into the mounting portion.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP5134774A JP2693699B2 (en) | 1993-06-04 | 1993-06-04 | Ceiling mounting structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP5134774A JP2693699B2 (en) | 1993-06-04 | 1993-06-04 | Ceiling mounting structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH06346546A JPH06346546A (en) | 1994-12-20 |
JP2693699B2 true JP2693699B2 (en) | 1997-12-24 |
Family
ID=15136254
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP5134774A Expired - Fee Related JP2693699B2 (en) | 1993-06-04 | 1993-06-04 | Ceiling mounting structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2693699B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9376812B2 (en) | 2014-08-19 | 2016-06-28 | Charles Porter | Ceiling panel mounting system |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107949219B (en) * | 2017-12-20 | 2023-05-16 | 无锡优耐特能源科技有限公司 | Mounting plate fixing piece |
JP7229831B2 (en) * | 2019-03-28 | 2023-02-28 | 大和ハウス工業株式会社 | Arrangement structure of the ceiling base panel frame |
CN116464305B (en) * | 2023-06-19 | 2023-09-26 | 山西八建集团有限公司 | Accurate assembly device based on field conversion truss installation |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0342173U (en) * | 1989-08-31 | 1991-04-22 | ||
JPH04189948A (en) * | 1990-11-26 | 1992-07-08 | Naka Ind Ltd | Ceiling structure |
-
1993
- 1993-06-04 JP JP5134774A patent/JP2693699B2/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9376812B2 (en) | 2014-08-19 | 2016-06-28 | Charles Porter | Ceiling panel mounting system |
Also Published As
Publication number | Publication date |
---|---|
JPH06346546A (en) | 1994-12-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2693699B2 (en) | Ceiling mounting structure | |
JP3606986B2 (en) | Inner balcony having a truss unit as a superstructure and its construction method | |
JP2557161B2 (en) | Roof unit with parapet | |
JPH0728241Y2 (en) | balcony | |
JP3180144B2 (en) | Panel mounting structure | |
JP2892197B2 (en) | House closet structure and construction method | |
JPH0726487Y2 (en) | Eave ceiling mounting structure | |
JPH078699Y2 (en) | Eave ceiling support structure | |
JPH078696Y2 (en) | Eave ceiling mounting structure | |
JPH0130491Y2 (en) | ||
JP3810869B2 (en) | Entrance fence unit and its mounting method | |
JPH0728243Y2 (en) | Flower box | |
JPH0326223Y2 (en) | ||
JPH0337320Y2 (en) | ||
JP3037195B2 (en) | Eave ceiling mounting structure | |
JPH0752824Y2 (en) | Connection structure between front eaves and diagonal eaves | |
JP2537341Y2 (en) | Building ceiling joist fastening structure and joist receiving bracket | |
JPS5811856Y2 (en) | Base material for wall panel installation | |
JPH0533422A (en) | Eave soffit attaching structure | |
JP2612142B2 (en) | Ceiling mounting structure | |
JPS5923125Y2 (en) | Exterior wall mounting structure | |
JP2702872B2 (en) | Bay window floor panel mounting structure | |
JPH0327692B2 (en) | ||
JP2022076538A (en) | Entrance porch | |
JPS6092561A (en) | Enlarged part structure of house |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 19970826 |
|
LAPS | Cancellation because of no payment of annual fees |