JP2012092512A - Method of closing opening of impervious type revetment - Google Patents

Method of closing opening of impervious type revetment Download PDF

Info

Publication number
JP2012092512A
JP2012092512A JP2010238667A JP2010238667A JP2012092512A JP 2012092512 A JP2012092512 A JP 2012092512A JP 2010238667 A JP2010238667 A JP 2010238667A JP 2010238667 A JP2010238667 A JP 2010238667A JP 2012092512 A JP2012092512 A JP 2012092512A
Authority
JP
Japan
Prior art keywords
water
block
impervious
height
levee
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2010238667A
Other languages
Japanese (ja)
Other versions
JP5791257B2 (en
Inventor
Takashi Otsuki
貴志 大槻
Toshihiro Yamazaki
智弘 山崎
Takeshi Kanazawa
剛 金澤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toray Engineering Co Ltd
Original Assignee
Toyo Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toyo Construction Co Ltd filed Critical Toyo Construction Co Ltd
Priority to JP2010238667A priority Critical patent/JP5791257B2/en
Publication of JP2012092512A publication Critical patent/JP2012092512A/en
Application granted granted Critical
Publication of JP5791257B2 publication Critical patent/JP5791257B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

PROBLEM TO BE SOLVED: To eliminate the influence of an uplift pressure due to a tide level difference of a construction water area as much as possible when closing an opening of an impervious type revetment by an inclined dike comprising natural stones or the like.SOLUTION: On a top end face of a foundation mound 26, a first top end height H1, with which securing the water conduction cross section Ws between outside and inside of a dike at lower position than a water level at the high tide is possible, is set taking the tide level difference of the construction water area into consideration, and a first impervious structure 24 extending from the first top end height H1 to an intra-dike bottom surface part is created. While making it possible to exchange water between outside and inside of the dike through the water conduction cross section Ws, the influence of the uplift pressure passing through the foundation mound 26 from the outside of the dike and acting on the back surface of the first impervious structure 24 is suppressed as much as possible. In the following process of creating a second impervious structure extending from a second top end height H2 at a position higher than the water level at the high tide in the construction water area to the intra-dike bottom surface part, the influence of the uplift pressure from the outside of the dike is eliminated by the first impervious structure 24.

Description

本発明は、遮水型護岸の開口部締切工法に関するものである。   The present invention relates to a method for closing an opening of a water-impervious revetment.

水域における管理型廃棄物処分場等の造成には、堤内から堤外への有害物質の漏出を防ぐための高い遮水性が要求されることから、一般に、遮水型護岸が用いられる。その造成手順は、通常、図13に示されるように、枠状の護岸12を、自然石等を用いた傾斜堤、鋼製の矢板(例えば、特許文献1)、ケーソン等のコンクリート製の構造物(例えば、特許文献2)を用い、これらを延長して最終的に残った開口部14を結合して、全体を締め切る工法が採用されている。この、護岸12の開口部14の締め切りにも、図14(a)(b)に示されるように、鋼製の板16や、コンクリート製の構造物18を用いることが可能である。   In order to create a management-type waste disposal site in the water area, a high water barrier is required to prevent leakage of harmful substances from the inside of the bank to the outside of the bank. As shown in FIG. 13, the building procedure is usually a frame-shaped revetment 12, an inclined bank using natural stone, a steel sheet pile (for example, Patent Document 1), a concrete structure such as a caisson. A construction method is adopted in which an object (for example, Patent Document 2) is used, these are extended and finally the remaining opening 14 is joined, and the whole is closed. As shown in FIGS. 14A and 14B, a steel plate 16 or a concrete structure 18 can also be used for the deadline of the opening 14 of the revetment 12.

特開2002−206220号公報JP 2002-206220 A 特開2003−71401号公報Japanese Patent Laid-Open No. 2003-7401

しかしながら、護岸12の開口部14の締め切りに、鋼製の矢板16やコンクリート製の構造物18を設置する手法は、それ自体の調達に多くの時間と費用とを要するものである。又、護岸12を自然石等を用いた傾斜堤にて築造する場合には、鋼製の矢板16やコンクリート製の構造物18と、自然石等を用いた傾斜堤として築造された護岸12との接続部分の遮水構造を、別途特殊な工法で施工する必要がある。
そこで、護岸12を自然石等を用いた傾斜堤にて築造する場合には、護岸12の開口部14についても、自然石等を用いた傾斜堤により締め切ることとすれば、堤体の全体にわたる工法の共通化が図られ、種々の利点を有することとなる。一方、鋼製の矢板16やコンクリート製の構造物18を設置する手法に比べ、施工水域での工期が長くなることから、この間の潮位差に起因して、次のような問題が生じることとなる。
However, the method of installing the steel sheet pile 16 and the concrete structure 18 at the deadline of the opening 14 of the revetment 12 requires a lot of time and cost for procurement of itself. When building the revetment 12 with an inclined bank using natural stones, etc., the steel sheet pile 16 or the concrete structure 18 and the revetment 12 built as an inclined bank using natural stones, etc. It is necessary to construct the water shielding structure of the connecting part by a special method.
Therefore, when the revetment 12 is constructed with an inclined levee using natural stone, etc., if the opening 14 of the revetment 12 is also closed with an inclined levee using natural stone, the entire levee body is covered. The construction method is made common and has various advantages. On the other hand, compared to the method of installing the steel sheet pile 16 or the concrete structure 18, the construction period in the construction water area becomes longer. Become.

護岸12の堤外水位は満潮・干潮の間で変動を繰り返すが、施工水域が護岸12の延長に伴い徐々に塞がれることで内面保有水Win(図13)を有し、開口部14が締め切られるまでは、開口部14を通じて堤外と堤内との水交換が生じることとなる。従って、堤外と堤内と水交換量が制限され、図15に示されるように、堤外水位の変動、すなわち、満潮時の水位(以下、「H.W.L.」ともいう。)と干潮時の水位(以下、「L.W.L.」ともいう。)との間で繰り返される水位変動と、堤内水位の変動とに位相差が生じることとなる。そして、堤外水位が堤内水位よりも高い時には、水位差に起因する静水圧が、堤体を構成する自然石の隙間を介して、護岸12内の遮水構造体に作用する。又、堤外の波力も、同様に遮水構造体に作用する。
ここで、護岸12が自然石等を用いた傾斜堤として構築される場合には、図16に示されるように、その内部構造として遮水構造体20が設けられるが、開口部14を塞ぐ護岸12の完成前の、遮水構造体20が堤内側斜面に露出した状態では、裏面に静水圧や波力等の揚圧力Pが作用することで、遮水構造体20が浮き上がり、護岸12の遮水性を損なう恐れがある。
The water level outside the bank of the revetment 12 repeatedly fluctuates between high tide and low tide, but the construction water area gradually closes with the extension of the revetment 12, so that it has internal retained water Win (FIG. 13) and the opening 14 is closed. Until then, water exchange occurs between the outside and inside the bank through the opening 14. Therefore, the amount of water exchange between the outside of the levee and the inside of the levee is limited, and as shown in FIG. 15, the fluctuation of the water level outside the levee, that is, the water level at high tide (hereinafter also referred to as “HWL”) and at low tide. A phase difference occurs between the water level fluctuation repeated between the water level (hereinafter also referred to as “LWL.”) And the fluctuation of the water level in the levee. And when the water level outside a bank is higher than the water level in a bank, the hydrostatic pressure resulting from a water level difference acts on the impermeable structure in the revetment 12 through the gap of the natural stone which comprises a bank body. Moreover, the wave force outside the bank also acts on the impermeable structure.
Here, when the revetment 12 is constructed as an inclined bank using natural stone or the like, as shown in FIG. 16, a water-impervious structure 20 is provided as its internal structure, but the revetment that closes the opening 14 is provided. In the state where the water-impervious structure 20 is exposed on the inner slope of the bank before the completion of 12, the water-impervious structure 20 is lifted by the action of the lifting pressure P such as hydrostatic pressure and wave force on the back surface. There is a risk of impairing the water barrier.

対して、堤内水位が堤外水位よりも高い時には、内面保有水Winが遮水構造体20を堤内側傾斜面(法面部)に押し付け、堤外からの揚圧力Pに対抗することから、上記の問題は生じない。又、図16に示されるように、遮水構造体20が砕石22で覆われた後は、砕石22が錘となって、遮水構造体20は安定する。そこで、遮水構造体20の敷設以降、それが砕石22で覆われるまでの間、ポンプ等を用いて人為的に堤内水位を調整することで、遮水構造体20の浮き上がりを防ぐことも可能である。しかしながら、堤内の保有水面積が大きくなると、堤内水位の調整設備もそれに応じて大規模なものが必要となり、遮水型護岸の建設費の増大を招くことにもなる。 On the other hand, when the water level in the levee is higher than the water level outside the levee, the inner surface retained water Win presses the impermeable structure 20 against the inclined surface (slope portion) on the inner side of the levee and opposes the lifting pressure P from the outside of the levee. Does not occur. In addition, as shown in FIG. 16, after the water shielding structure 20 is covered with the crushed stone 22, the crushed stone 22 becomes a weight, and the water shielding structure 20 is stabilized. Therefore, it is possible to prevent the impermeable structure 20 from floating by artificially adjusting the water level in the levee using a pump or the like after the impermeable structure 20 is laid until it is covered with the crushed stone 22. It is. However, if the water area in the levee increases, the water level adjustment equipment in the levee will also require a large scale, which will lead to an increase in the construction cost of the impermeable bank.

本発明は、上記課題に鑑みてなされたものであり、その目的とするところは、遮水型護岸の開口部を締め切る際に、施工水域の潮位差に起因する揚圧力の影響を可能な限り排除し、自然石等を用いた傾斜堤により、遮水性の高い遮水型護岸を造成することにある。   The present invention has been made in view of the above problems, and the object of the present invention is to minimize the influence of lifting pressure caused by the tide level difference in the construction water area when closing the opening of the impermeable bank. The purpose is to create a water-impervious revetment with high water-imperviousness by using an inclined bank using natural stones.

(発明の態様)
以下の発明の態様は、本発明の構成を例示するものであり、本発明の多様な構成の理解を容易にするために、項別けして説明するものである。各項は、本発明の技術的範囲を限定するものではなく、発明を実施するための最良の形態を参酌しつつ、各項の構成要素の一部を置換し、削除し、又は、更に他の構成要素を付加したものについても、本願発明の技術的範囲に含まれ得るものである。
(Aspect of the Invention)
The following aspects of the present invention exemplify the configuration of the present invention, and will be described separately for easy understanding of various configurations of the present invention. Each section does not limit the technical scope of the present invention, and some of the components of each section are replaced, deleted, or further while referring to the best mode for carrying out the invention. Those to which the above components are added can also be included in the technical scope of the present invention.

(1)遮水型護岸の開口部締切工法であって、
開口部に隣接する自然石等を用いた傾斜堤の基礎マウンドと、共通の断面を有する基礎マウンドを造成し、
該基礎マウンドの天端面上に、施工水域の潮位差を考慮して、満潮時の水位よりも低く堤外側と堤内側との通水断面を確保可能な第1の天端高を設定し、
該第1の天端高から堤内底面部に至る遮水層を造成し、
前記遮水層の表面に錘を配置し、
該遮水層の堤内先端部を覆う変形追随性遮水材層を打設し、
前記第1の天端高以深部へと砕石を投入して、
第1の遮水構造体を造成し、
前記第1の遮水構造体の上部に、施工水域の満潮時の水位よりも高位置の第2の天端高から堤内底面部に至る第2の遮水構造体を造成する、各工程を含む遮水型護岸の開口部締切工法(請求項1)。
(1) It is a method for closing the opening of a water-proof type revetment,
The foundation mound of the slope bank using natural stone etc. adjacent to the opening and the foundation mound having a common cross section are created,
On the top surface of the foundation mound, considering the tide level difference of the construction water area, set the first top height that can secure the water cross section between the outside of the levee and the inside of the levee which is lower than the water level at high tide,
Creating a water-impervious layer from the height of the first top to the bottom of the levee;
A weight is disposed on the surface of the water shielding layer,
Placing a deformation-following water-blocking material layer covering the tip of the water-blocking layer in the levee;
Throw crushed stone into the first top and bottom deeper,
Create the first water-impervious structure,
Forming a second water-impervious structure on the upper part of the first water-impervious structure from the second top height higher than the water level at the time of high tide in the construction water area to the bottom of the levee, Including a method for closing the opening of a water-impervious revetment (claim 1).

本項に記載の遮水型護岸の開口部締切工法は、開口部においても、それと隣接する自然石等を用いた傾斜堤の基礎マウンドと、共通の断面を有する基礎マウンドを造成することで、堤体構造の一部共通化を図るものである。ここで、「自然石等」とは、自然石、砕石、コンクリートブロック等の塊片が含まれ、工区に適した大きさのものが用いられる。
又、基礎マウンドの天端面上に、施工水域の潮位差を考慮して、満潮時の水位よりも低く堤外側と堤内側との通水断面を確保可能な第1の天端高を設定し、該第1の天端高から堤内底面部に至る第1の遮水構造体を先行造成することで、時間が長く必要な底面遮水工施工時に、堤外と堤内との水交換を可能とし、潮位差を小さくしつつ、堤外から基礎マウンドを浸透して遮水層の裏面に作用する揚圧力の影響を、可能な限り小さく抑えるものである。
The opening cut-off method of the impermeable type revetment described in this section is to create a foundation mound of a sloped embankment using natural stone etc. adjacent to it and a foundation mound having a common cross section in the opening, A part of the bank structure will be shared. Here, “natural stone etc.” includes blocks of natural stone, crushed stone, concrete block, etc., and those having a size suitable for the construction area are used.
In addition, on the top surface of the foundation mound, taking into account the tide level difference of the construction water area, the first top height that can secure the water cross section between the outside of the levee and the inside of the levee is set lower than the water level at high tide. By constructing the first water-impervious structure from the height of the first top to the bottom of the levee, it is possible to exchange water between the outside of the levee and the inside of the levee at the time of bottom impermeable construction, which requires a long time. While reducing the tide level difference, the influence of the lifting pressure acting on the back surface of the impermeable layer by penetrating the foundation mound from the outside of the bank is minimized.

すなわち、第1の天端高を満潮時の水位よりも低い天端高に設定することで、第1の遮水構造体の造成中、開口部に残る通水断面を通じて堤外と堤内との水交換が生じることにより堤内水位を、堤外水位に近づけることが可能となり、潮位差が小さくなる。そして、堤外水位が堤内水位よりも高い時を除き、内面保有水が遮水層を堤内側傾斜面に押し付け、堤外から基礎マウンドを浸透して遮水層の裏面に作用する揚圧力に対抗する。一方、堤外水位が堤内水位よりも高い時には、遮水層の表面に配置する錘により、堤外から基礎マウンドを浸透して遮水層の裏面に作用する揚圧力に対抗するものとなる。
従って、遮水層の堤内先端部を覆う変形追随性遮水材層を打設する際に、遮水層の裏面に作用する揚圧力により、遮水層が破損することを防ぐことができる。以上の点を考慮し、第1の天端高は、施工水域の潮位差を考慮して、堤外水位が堤内水位よりも高い状態、すなわち、遮水層の裏面に揚圧力が作用する時間比率が可能な限り短くなるように、設定されるものである。
That is, by setting the first top height to a top height lower than the water level at high tide, the water between the outside of the levee and the inside of the levee through the cross section of water remaining in the opening during the construction of the first water shielding structure. By exchanging, it becomes possible to bring the water level inside the bank close to the water level outside the bank, and the tide level difference becomes smaller. Except when the water level outside the levee is higher than the water level inside the levee, the water retained on the inner surface presses the impermeable layer against the slanted inner surface of the levee, and penetrates the foundation mound from outside the levee and counters the lifting pressure acting on the back surface of the impermeable layer . On the other hand, when the water level outside the levee is higher than the water level inside the levee, the weight placed on the surface of the impermeable layer counteracts the lifting pressure that permeates the foundation mound from the outside of the dike and acts on the back surface of the impermeable layer.
Therefore, when the deformation followable water shielding material layer covering the tip of the water shielding layer in the bank is placed, the water shielding layer can be prevented from being damaged by the lifting pressure acting on the back surface of the water shielding layer. Considering the above points, the first top height is the time ratio in which the outside water level is higher than the water level in the levee, that is, the lifting pressure acts on the back of the impermeable layer, taking into account the tide level difference in the construction water area. Is set to be as short as possible.

更に、干潮時の水位を挟んで中間水位(以下、「M.W.L.」ともいう。図15参照。)以下の時間帯では、第1の天端高は気中となり、陸上施工が可能となる。
そして、遮水層の堤内先端部を覆うように、変形追随性遮水材層を打設することにより、第1の天端高から堤内底面部に至る範囲の遮水を完了し、以後の、施工水域の満潮時の水位よりも高位置の第2の天端高から堤内底面部に至る第2の遮水構造体を造成する工程では、堤外からの揚圧力の影響を排除するものである。
Furthermore, in the time zone below the intermediate water level (hereinafter also referred to as “M.W.L.”, see FIG. 15) across the water level at low tide, the first top height is in the air and It becomes possible.
Then, by covering the tip of the impermeable layer in the levee, by placing a deformation-following water-insulating material layer, the water shielding in the range from the first top height to the bottom surface of the levee is completed. In the process of creating the second water-blocking structure from the second top height, which is higher than the water level at the time of high tide in the construction area, to the bottom of the levee, the effect of lifting pressure from the outside of the dam is eliminated. is there.

(2)上記(1)項の、前記遮水層を造成する工程において、遮水シートを前記第1の天端高から堤内底面部に向けて敷設し、該遮水シートの敷設作業の進行に合わせて、前記錘を、前記第1の天端高から堤内底面部へと複数配置する遮水型護岸の開口部締切工法(請求項2)。
本項に記載の遮水型護岸の開口部締切工法は、遮水シートを前記第1の天端高から堤内底面部に向けて敷設し、該遮水シートの敷設作業の進行に合わせて、前記錘を、前記第1の天端高から堤内底面部へと複数配置することで、遮水シートの敷設中に、遮水シートを錘によって基礎マウンドの傾斜法面に確実に押え付ける。そして、遮水シートの裏面に揚圧力が作用することがあっても、錘によってそれに対抗し、遮水シートの浮き上がりを防ぐものである。
(2) In the step of creating the water shielding layer in the above item (1), a water shielding sheet is laid from the first top height toward the bottom surface of the levee, and the laying work of the water shielding sheet proceeds In accordance with the above, an opening closing method for a water-impervious revetment in which a plurality of weights are arranged from the first top height to the bottom surface in the bank (Claim 2).
The method for closing the opening of the water-impervious revetment described in this section is to lay the water-impervious sheet from the first top height toward the bottom surface of the levee, and according to the progress of the laying work of the water-impervious sheet, By arranging a plurality of weights from the height of the first top to the bottom of the levee, the water shielding sheet is reliably pressed against the slope of the foundation mound by the weight during the construction of the water shielding sheet. And even if lift pressure may act on the back surface of a water-impervious sheet, it opposes it with a weight and prevents the water-impervious sheet from being lifted.

(3)遮水型護岸の開口部締切工法であって、
開口部に隣接する自然石等を用いた傾斜堤の基礎マウンドと、共通の断面を有する基礎マウンドを造成し、
該基礎マウンドの天端面上に、施工水域の潮位差を考慮して、満潮時の水位よりも低く堤外側と堤内側との通水断面を確保可能な第1の天端高を設定し、
前記基礎マウンドの天端面の堤内側端部から所定距離を空けて、前記第1の天端高へ到達する高さを有する第1の法先ブロックを据付け、
前記基礎マウンドの天端面の堤内側端部と前記第1の法先ブロックとの間に、前記第1の法先ブロックの高さに合わせて裏込石の投入・均しを行い、
該裏込石を合成樹脂製ジオグリッドで押え付けた後、前記第1の天端高から堤内底面部に至る範囲に切込砕石の投入・均しを行い、
該切込砕石の投入範囲の堤内先端部から堤内側に所定距離を空けて、第2の法先ブロックを据付け、
堤内底面部の、前記第2の法先ブロックから前記切込砕石に至る範囲に、変形追随性遮水材を薄く打設し、
遮水シートを前記第1の天端高から堤内底面部に向けて敷設し、該遮水シートの敷設作業の進行に合わせて、複数の土のうを、前記第1の天端高から堤内底面部へと配置し、
前記第2の法先ブロックから前記遮水シートに至る範囲に、前記打設した変形追随性遮水材を覆うようにして変形追随性遮水材を追打設し、
前記第1の天端高から前記第2の法先ブロックに至る範囲に、前記第1の天端高まで中間砕石を投入して、前記遮水シートを前記土のうと共に埋設し、
前記第1の天端高から、施工水域の満潮時の水位よりも高位置の第2の天端高まで、前記遮水シートを接続・延長して、第1の遮水構造体を造成し、
該第1の遮水構造体を覆うようにして、前記第2の天端高から堤内底面部に至る第2の遮水構造体を造成する、各工程を含む遮水型護岸の開口部締切工法(請求項3)。
(3) It is a method of closing the opening of a water-proof type revetment,
The foundation mound of the slope bank using natural stone etc. adjacent to the opening and the foundation mound having a common cross section are created,
On the top surface of the foundation mound, considering the tide level difference of the construction water area, set the first top height that can secure the water cross section between the outside of the levee and the inside of the levee which is lower than the water level at high tide,
Installing a first tip block having a height to reach the first top end height at a predetermined distance from the ridge inner end of the top end surface of the foundation mound;
Between the ridge inner end of the top end surface of the foundation mound and the first tip block, the back stone is placed and leveled according to the height of the first tip block,
After pressing the backside stone with a synthetic resin geogrid, throwing and leveling the crushed stone in the range from the height of the first top to the bottom of the levee,
A predetermined distance from the tip of the dam in the cutting crushed stone input range to the inside of the dam, and the second method block is installed.
In the bottom of the dike, in the range from the second tip block to the crushed crushed stone, a deformation-following water shielding material is thinly placed,
A water-impervious sheet is laid from the first top edge height toward the bottom face in the levee, and a plurality of sandbags are arranged from the first top edge height to the bottom face in the levee according to the progress of the laying work of the water-proof sheet. Placed in
In the range from the second method tip block to the water-impervious sheet, the deformation-following water-insulating material is additionally placed so as to cover the placed deformation-following water-insulating material,
Into the range from the first top height to the second tip block, throw the intermediate crushed stone to the first top height, and bury the impermeable sheet with the sandbag,
The first water shielding structure is formed by connecting and extending the water shielding sheet from the first top height to the second top height which is higher than the water level at the time of high tide in the construction water area. ,
Opening deadline of the water-impervious revetment including each step for forming the second water-impervious structure that covers the first water-impervious structure and extends from the second top height to the bottom of the levee. Construction method (Claim 3).

本項に記載の遮水型護岸の開口部締切工法は、開口部においても、それと隣接する自然石等を用いた傾斜堤の基礎マウンドと、共通の断面を有する基礎マウンドを造成することで、堤体構造の一部共通化を図るものである。
又、基礎マウンドの天端面上に、施工水域の潮位差を考慮して、満潮時の水位よりも低く堤外側と堤内側との通水断面を確保可能な第1の天端高を設定し、該第1の天端高から堤内底面部に至るように遮水シートを敷設し、更に、第1の天端高から、施工水域の満潮時の水位よりも高位置の第2の天端高まで、遮水シートを接続・延長して、第1の遮水構造体を造成することで、堤外と堤内との水交換を可能としつつ、堤外から基礎マウンドを浸透して第1の遮水構造体の裏面に作用する揚圧力の影響を、可能な限り小さく抑えるものである。
The opening cut-off method of the impermeable type revetment described in this section is to create a foundation mound of a sloped embankment using natural stone etc. adjacent to it and a foundation mound having a common cross section in the opening, A part of the bank structure will be shared.
In addition, on the top surface of the foundation mound, taking into account the tide level difference of the construction water area, the first top height that can secure the water cross section between the outside of the levee and the inside of the levee is set lower than the water level at high tide. A water shielding sheet is laid from the first top to the bottom of the levee, and the second top from the first top is higher than the water level at high tide in the construction water area. By connecting and extending the impervious sheet up to the height to create the first impermeable structure, water exchange between the outside of the dike and the inside of the dike is possible, and the first mound is penetrated from the outside of the dike. The influence of the lifting pressure acting on the back surface of the water structure is minimized.

すなわち、第1の天端高を満潮時の水位低い天端高に設定することで、第1の遮水構造体の造成中、開口部に残る通水断面を通じて堤外と堤内との水交換が生じ、堤外水位が堤内水位よりも高い時を除き、内面保有水が遮水シートを堤内側傾斜面に押し付け、堤外から基礎マウンドを浸透して遮水シートの裏面に作用する揚圧力に対抗する。一方、堤外水位が堤内水位よりも高い時には、遮水シートの表面に配置する土のうにより、堤外から基礎マウンドを浸透して遮水シートの裏面に作用する揚圧力に対抗するものである。しかも、遮水シートの敷設作業の進行に合わせて、複数の土のうを、第1の天端高から堤内底面部へと配置することで、遮水シートの敷設中に、敷設が完了した範囲の遮水シートを土のうによって基礎マウンドの傾斜法面に確実に押え付ける。
そして、第2の法先ブロックから遮水シートに至る範囲に、打設した変形追随性遮水材を覆うようにして変形追随性遮水材を追打設する間に、遮水シートの裏面に揚圧力が作用することがあっても、土のうにより遮水シートの表面を押え付け、遮水シートの裏面に作用する揚圧力により、遮水シートが破損することを防ぐことができる。
That is, by setting the first top height to a low top level at the time of high tide, water exchange between the outside of the levee and the inside of the levee can be performed through the cross section of water remaining in the opening during the construction of the first water-impervious structure. Except when the water level outside the levee is higher than the water level inside the levee, the water retained on the inner surface presses the impervious sheet against the slanted inner surface of the levee and permeates the foundation mound from outside the levee and counters the lifting pressure acting on the rear surface of the impermeable sheet . On the other hand, when the water level outside the levee is higher than the water level inside the levee, the soil mound disposed on the surface of the water-impervious sheet opposes the lifting pressure that permeates the foundation mound from the outside of the dam and acts on the back surface of the water-impervious sheet. In addition, by laying a plurality of sandbags from the height of the first top to the bottom of the levee in accordance with the progress of the laying work of the water shielding sheet, the installation of the water shielding sheet is completed within the range where the laying is completed. Press the water shielding sheet firmly against the slope of the foundation mound with sandbags.
And, in the range from the second method block to the water-impervious sheet, the rear surface of the water-impervious sheet is provided while the deformable-follower water-impervious material is additionally provided so as to cover the deformed-follower water-impermeable material Even if the lifting pressure acts on the surface, the surface of the water-impervious sheet can be pressed by the sandbag, and the water-impervious sheet can be prevented from being damaged by the lifting pressure acting on the rear surface of the water-impervious sheet.

更に、干潮時の水位を挟んで中間水位以下となる時間帯では、第1の天端高は気中となり、陸上施工が可能となる。
そして、第2の法先ブロックから遮水シートに至る範囲に、打設した変形追随性遮水材を覆うようにして、変形追随性遮水材層を追打設することにより、第1の天端高から堤内底面部に至る範囲の遮水を完了し、以後の、第1の天端高から、施工水域の満潮時の水位よりも高位置の第2の天端高までの遮水層の接続・延長、及び、第1の遮水構造体を覆い堤内底面部に至る第2の遮水構造体を造成する工程では、堤外からの揚圧力の影響を排除するものである。
Furthermore, in the time zone where the water level is lower than the intermediate water level across the water level at low tide, the first top height is in the air, and land construction is possible.
And, in the range from the second method block to the water shielding sheet, the deformation following water shielding material layer is covered so as to cover the placed deformation following water shielding material. Completed the water shielding from the top to the bottom of the dam, and from the first top to the second top, which is higher than the water level at high tide in the construction area. In the step of connecting and extending the layers and forming the second water-impervious structure that covers the first water-impervious structure and reaches the bottom surface in the levee, the influence of the lifting pressure from the outside of the levee is eliminated.

(4)上記(3)項の、前記遮水シートを前記第1の天端高から堤内底面部に向けて敷設する工程において、前記遮水シートの前記第1の天端高側端部に所定幅の予備部を設け、
前記遮水シートを前記土のうと共に埋設する工程において、前記遮水シートの予備部を除く、前記第1の天端高から前記第2の法先ブロックに至る範囲に中間砕石を投入した後、該中間砕石の上面に前記遮水シートの予備部を折り返し、
前記基礎マウンドの天端面の、前記第1の法先ブロックが据え付けられた場所よりも堤外側の位置に、前記第2の天端高へ到達する高さを有する方塊ブロックを据付け、
該方塊ブロック、前記第1の法先ブロック、及び、前記基礎マウンドの天端面の堤内側端部と前記第1の法先ブロックとの間に投入された裏込石とを覆うようにして、前記方塊ブロックの高さに合わせて裏込石の再投入・均しを行い、
該再投入された裏込石を合成樹脂製ジオグリッドで押え付け、これらの上面を、前記中間砕石の上面に折り返した前記遮水シートの予備部で覆い、
前記中間砕石の上面に、前記第2の天端高に至るまで中間砕石を追加投入し、前記遮水シートの予備部の、再投入された裏込石及び前記合成樹脂製ジオグリッドの上面を覆う部分を、前記追加投入した中間砕石により埋設する遮水型護岸の開口部締切工法(請求項4)。
(4) In the step of laying the water shielding sheet in the above (3) from the first top edge height toward the bottom surface in the levee, on the first top edge high side end of the water shielding sheet Provide a spare part with a predetermined width,
In the step of burying the water shielding sheet together with the sandbag, after putting intermediate crushed stone into the range from the first top height to the second method tip block, excluding the spare part of the water shielding sheet, Fold the preliminary part of the water shielding sheet on the upper surface of the intermediate crushed stone,
A block block having a height reaching the second top end height is installed at a position outside the bank of the top end surface of the foundation mound, where the first tip block is installed.
Covering the block block, the first tip block, and the back stone placed between the ridge inner end of the top end surface of the foundation mound and the first tip block, According to the height of the block block, re-filling and leveling the backside stone,
Pressing the re-filled backside stone with a synthetic resin geogrid, and covering these top surfaces with a spare part of the water shielding sheet folded back to the top surface of the intermediate crushed stone,
The intermediate crushed stone is additionally added to the upper surface of the intermediate crushed stone until reaching the second top height, and the back-filled back stone and the upper surface of the synthetic resin geogrid of the preliminary portion of the water shielding sheet are added. A method for closing the opening of a water-impervious revetment in which a portion to be covered is buried with the additionally introduced intermediate crushed stone (Claim 4).

本項に記載の遮水型護岸の開口部締切工法は、遮水シートを前記土のうと共に埋設する工程において、遮水シートの予備部を除く、前記第1の天端高から前記第2の法先ブロックに至る範囲に中間砕石を投入した後、該中間砕石の上面に前記遮水シートの予備部を折り返し、再投入された裏込石及び合成樹脂製ジオグリッドの上面を、中間砕石の上面に折り返した遮水シートの予備部で覆うことで、施工水域の満潮時の水位よりも高位置の第2の天端高から堤内底面部に至る範囲を、第1の遮水構造体に係る遮水シートで覆い、遮水性を確保するものである。
又、遮水シートの予備部のうち、再投入された裏込石及び合成樹脂製ジオグリッドの上面を覆う部分を除く部分を、前記追加投入した中間砕石により埋設することで、遮水シートの予備部の裏面に作用する揚圧力により、遮水シートの予備部が破損することを防ぐことができる。
In the step of embedding the water-impervious type revetment described in this section, the second method from the height of the first top edge excluding the preliminary part of the water-impervious sheet in the step of burying the water-impervious sheet together with the sandbag. After the intermediate crushed stone is thrown into the range up to the previous block, the preliminary part of the water shielding sheet is folded back on the upper surface of the intermediate crushed stone, and the upper surface of the back-filled stone and the synthetic resin geogrid are placed on the upper surface of the intermediate crushed stone. By covering with the spare part of the water shielding sheet that is folded back, the range from the second crest height higher than the water level at the time of high tide in the construction water area to the bottom part of the dam is related to the first water shielding structure. It is covered with a water shielding sheet to ensure water shielding.
In addition, the portion of the spare part of the water shielding sheet, except the part that covers the top surface of the re-filled backfill stone and the synthetic resin geogrid, is buried by the additionally introduced intermediate crushed stone. It is possible to prevent the spare part of the water shielding sheet from being damaged by the lifting pressure acting on the back surface of the spare part.

(5)上記(3)、(4)項の、前記第2の遮水構造体を造成する工程において、
前記方塊ブロックの上面に上部コンクリートを打設し、
前記中間砕石の投入範囲の堤内先端部から堤内側に所定距離を空けて、第3の法先ブロックを据付け、
堤内底面部の、前記第3の法先ブロックから前記中間砕石に至る範囲に、変形追随性遮水材を打設し、
前記中間砕石を覆うようにして、前記方塊ブロックの上面から前記第3の法先ブロックに至るまで第2の遮水シートを敷設し、
前記第3の法先ブロックから前記第2の遮水シートに至る範囲に、前記打設した変形追随性遮水材を覆うようにして変形追随性遮水材を追打設し、
前記上部コンクリートから前記第3の法先ブロックに至る範囲を、砕石で被覆する遮水型護岸の開口部締切工法(請求項5)。
(5) In the step of creating the second water-impervious structure according to the items (3) and (4),
Place the upper concrete on the upper surface of the block block,
At a predetermined distance from the tip of the levee in the crushed stone input range to the inside of the dam, the third method block is installed,
In the range from the third method block to the intermediate crushed stone on the bottom of the levee, a deformation-following water-insulating material is placed,
Covering the intermediate crushed stone, laying a second water-impervious sheet from the upper surface of the block block to the third method block,
In the range from the third tip block to the second water-impervious sheet, the deformation-following water-insulating material is additionally placed so as to cover the placed deformation-following water-insulating material,
A water-blocking type revetment opening cut-off method in which the range from the upper concrete to the third method block is covered with crushed stone (Claim 5).

本項に記載の遮水型護岸の開口部締切工法は、堤内底面部の、第3の法先ブロックから中間砕石に至る範囲に、変形追随性遮水材を打設し、中間砕石を覆うようにして、方塊ブロックの上面から前記第3の法先ブロックに至るまで第2の遮水シートを敷設することで、二重の遮水シートにより確実に遮水性を有するものとなる。
又、第3の法先ブロックから第2の遮水シートに至る範囲に、打設した変形追随性遮水材を覆うようにして変形追随性遮水材を追打設し、第2の天端高から堤内底面部に至る範囲の遮水を完了するものである。その後、上部コンクリートから前記第3の法先ブロックに至る範囲を、砕石で被覆することで、第2の遮水シートを安定保持するものである。
The method for closing the opening of a water-impervious revetment described in this section covers the intermediate crushed stone by placing a deformation-following water-impervious material on the bottom of the dike in the range from the third tip block to the intermediate crushed stone. In this way, by laying the second water-impervious sheet from the upper surface of the block block to the third method block, the double water-impervious sheet ensures water impermeability.
Further, in the range from the third method block to the second impermeable sheet, the deformable followable water shielding material is additionally disposed so as to cover the deformed conformable water shielding material, and the second ceiling Water shielding in the range from the end height to the bottom of the bank is completed. Thereafter, the range from the upper concrete to the third method block is covered with crushed stone to stably hold the second water-impervious sheet.

(6)上記(5)項において、第2の遮水シートを敷設する工程において、前記遮水シートの予備部のうち、前記追加投入した中間砕石により埋設されていない部分に、第2の遮水シートの天端側端部を重ねる遮水型護岸の開口部締切工法。
本項に記載の遮水型護岸の開口部締切工法は、前記遮水シートの予備部のうち、前記追加投入した中間砕石により埋設されていない部分に、第2の遮水シートの天端側端部を重ねるようにして敷設することで、第2の天端高において、二重の遮水シートが、堤体上方から二重の遮水シートの間への、堤内の保有水又は堤外の水の浸水を防ぐものである。
(6) In the above step (5), in the step of laying the second water-impervious sheet, a portion of the spare part of the water-impervious sheet that is not buried by the additionally input intermediate crushed stone is provided in the second impervious sheet. Opening closing method for water-impervious seawalls that overlap the top edge of the water sheet.
The opening cutoff method of the water-impervious revetment described in this section is based on the top end side of the second water-impervious sheet in the spare part of the water-impervious sheet that is not embedded by the intermediate crushed stone added additionally. By laying so that the ends overlap, the double water-impervious sheet is located at the second top height from the upper part of the dam body to the space between the double water-impervious sheets. It prevents the inundation of water.

(7)上記(1)から(6)項において、施工水域の潮位変動に起因する、堤外水位の変動と、堤内水位の変動とが最小となるように、開口部幅を設定する遮水型護岸の開口部締切工法。
本項に記載の遮水型護岸の開口部締切工法は、予め、施工水域の潮位変動に起因する、堤外水位の変動と、堤内水位の変動とが最小となるように、開口部幅を設定することで、堤外と堤内との水交換を可能としつつ、堤外から基礎マウンドを浸透して第1の遮水構造体の裏面に作用する揚圧力を、可能な限り小さく抑えるものである。
(7) In the above paragraphs (1) to (6), the water-blocking type in which the opening width is set so that the fluctuation of the water level outside the bank and the fluctuation of the water level inside the bank caused by the tide level fluctuation in the construction water area are minimized. Revetment opening deadline method.
The opening cut-off method for the impermeable type revetment described in this section is to set the opening width in advance so that the fluctuation of the water level outside the bank and the fluctuation of the water level inside the bank caused by the tide level fluctuation in the construction water area are minimized. By doing so, while allowing water exchange between the outside of the bank and the inside of the bank, the lifting pressure that permeates the foundation mound from the outside of the bank and acts on the back surface of the first water shielding structure is minimized.

本発明はこのように構成したので、遮水型護岸の開口部を締め切る際に、施工水域の潮位差に起因する揚圧力の影響を可能な限り排除し、自然石等を用いた傾斜堤により、遮水性の高い遮水型護岸を造成することが可能となる。   Since the present invention is configured in this way, when closing the opening of the impermeable revetment, the influence of lifting pressure due to the tide level difference in the construction water area is eliminated as much as possible, and by using an inclined bank using natural stones, etc. It is possible to create a water-impervious revetment with high water-imperviousness.

本発明の実施の形態に係る遮水型護岸の開口部締切工法において、その中間段階で開口部に造成される、第1の天端高から堤内底面部に至る第1の遮水構造体を示す模式図である。In the opening cut-off method for a water-impervious type revetment according to an embodiment of the present invention, a first water-blocking structure is formed in the opening at an intermediate stage from the first top height to the bottom in the levee. It is a schematic diagram shown. 図1に示される開口部に造成された第1の遮水構造体の断面図を、施工水域の潮位の変化と共に示した説明図であり、(a)は満潮時、(b)は最大下げ潮時又は最大上げ潮時、(c)は干潮時を示すものである。It is explanatory drawing which showed sectional drawing of the 1st water shielding structure formed in the opening part shown by FIG. 1 with the change of the tide level of a construction water area, (a) is at high tide, (b) is the maximum low tide (C) shows the time of low tide. 本発明の実施の形態に係る、遮水型護岸の開口部締切工法を示すフローチャートである。It is a flowchart which shows the opening part deadline construction method of the impermeable type revetment based on embodiment of this invention. (a)〜(f)は、図3のS10〜S60に係る施工断面図である。(A)-(f) is construction sectional drawing concerning S10-S60 of FIG. (a)〜(f)は、図3のS70〜S100に係る施工断面図である。(A)-(f) is construction sectional drawing concerning S70-S100 of FIG. (a)〜(f)は、図3のS110〜S180に係る施工断面図である。(A)-(f) is construction sectional drawing concerning S110-S180 of FIG. (a)は図3のS10に係る作業工程を、(b)、(c)は同S20に係る作業工程を示す説明図である。(A) is an operation | work process which concerns on S10 of FIG. 3, (b), (c) is explanatory drawing which shows the work process which concerns on the same S20. (a)、(b)は図3のS30に係る作業工程を、(c)は同S40に係る作業工程を、(d)は同S50に係る作業工程を示す説明図である。(A), (b) is an explanatory view showing the work process according to S30 in FIG. 3, (c) is a work process according to S40, and (d) is an explanatory view showing the work process according to S50. (a)は図3のS60に係る作業工程を、(b)は(a)のA部拡大図である。(A) is an operation process according to S60 of FIG. 3, and (b) is an enlarged view of part A of (a). (a)は図9に係る作業工程を示すフローチャート、(b)は(a)に対応する作業工程図である。(A) is a flowchart which shows the work process which concerns on FIG. 9, (b) is a work process figure corresponding to (a). (a)は図3のS70に係る作業工程を、(b)、(c)は同S80に係る作業工程を示す説明図である。(A) is an explanatory view showing the work process according to S70 of FIG. 3, and (b), (c) are explanatory views showing the work process according to S80. (a)は図3のS90に係る作業工程を、(b)は同S100に係る作業工程を、(c)、(d)は同S110に係る作業工程を示す説明図である。(A) is a work process concerning S90 of Drawing 3, (b) is a work process concerning the same S100, (c), (d) is an explanatory view showing a work process concerning the same S110. 開口部を残した遮水型護岸の模式図である。It is a schematic diagram of the impermeable type revetment which left the opening part. (a)は、護岸の開口部の締め切りに鋼製の板を用いる場合を、(b)は同コンクリート製の構造物を用いる場合を示す説明図である。(A) is explanatory drawing which shows the case where a steel board is used for the deadline of the opening part of a revetment, (b) is the explanatory view which shows the case where the structure made from the said concrete is used. 図13に示される、開口部を残した遮水型護岸の堤外水位の変動、堤内水位の変動を示すグラフである。It is a graph which shows the fluctuation | variation of the water level outside a bank of a water-impervious type revetment which left the opening part shown in FIG. 13, and the fluctuation | variation of the water level in a bank. 遮水型護岸の開口部を、自然石等を用いた傾斜堤とした場合の問題点を示す説明図である。It is explanatory drawing which shows a problem at the time of making the opening part of a water-impervious type revetment into an inclined bank using a natural stone.

以下、本発明を実施するための最良の形態を添付図面に基づいて説明する。なお、従来技術と同一部分若しくは相当する部分については同一符号で示し、詳しい説明を省略する。
図1、図2には、本発明の実施の形態に係る遮水型護岸の開口部締切工法の中間段階で、開口部に先行造成される、第1の遮水構造体24が模式的に示されている。第1の遮水構造体24は、施工水域の潮位差を考慮して、満潮時の水位よりも低く堤外側と堤内側との通水断面Wsを確保可能な天端高(第1の天端高)H1となるように、形成される。
The best mode for carrying out the present invention will be described below with reference to the accompanying drawings. Note that the same or corresponding parts as those of the prior art are denoted by the same reference numerals, and detailed description thereof is omitted.
1 and 2 schematically show a first water-blocking structure 24 that is formed in advance in the opening at an intermediate stage of the opening-closing method of the water-blocking type revetment according to the embodiment of the present invention. It is shown. In consideration of the tide level difference in the construction water area, the first water-impervious structure 24 has a ceiling height (first heaven height) that can secure a water cross section Ws between the outside of the levee and the inside of the levee that is lower than the water level at high tide. It is formed so as to be (end height) H1.

より具体的には、第1の遮水構造体24の、第1の天端高H1は、図2(a)に示されるように、満潮時の水位(H.W.L.)では、通水断面Wsを通じて、堤外から堤内に水が流入して、堤内水位も満潮時の水位(H.W.L.)となり、図2(b)に示されるように、堤外が中間水位(M.W.L.)に低下すると、通水断面Wsを通じて、堤内から堤外に水が流出して、堤内水位も中間水位となり、以後、図2(c)に示される干潮時の水位(L.W.L.)に至る間は、第1の遮水構造体24の天端面は気中に露出し、堤内は中間水位(M.W.L.)が維持されるように、設定されるものである。
なお、第1の遮水構造体24が造成される開口部14の開口幅Lは、施工水域の潮位変動に起因する、堤外水位の変動と、堤内水位の変動との差が最小となるように設定されている。
More specifically, the first crest height H1 of the first water-impervious structure 24 is, as shown in FIG. 2 (a), at the water level at high tide (HWL): Water flows from the outside of the bank into the bank through the cross section Ws, and the water level in the bank also becomes the water level at high tide (HWL), and as shown in FIG. When the water level drops to W.L.), water flows from the inside of the dike to the outside of the dike through the water cross section Ws, and the water level in the dike also becomes an intermediate water level. Thereafter, the water level at low tide (L.L.) shown in FIG. (W.L.), the top end face of the first water-impervious structure 24 is exposed to the air, and the inside of the bank is set so that the intermediate water level (M.W.L.) is maintained. Is.
It should be noted that the opening width L of the opening 14 where the first water-impervious structure 24 is formed is such that the difference between the fluctuation of the water level outside the bank and the fluctuation of the water level inside the bank due to the tide level fluctuation in the construction water area is minimized. Is set to

ここで、本発明の実施の形態に係る、中間段階で第1の遮水構造体24が造成される工程を含む、遮水型護岸の開口部締め切り手順を説明する。なお、以下の説明では、図3のフローチャートを主に参照し、工程の進行に伴い、図1、図2、図4〜図12を適宜参照するものとする。
S0(図4(a)参照):基礎捨石(30〜100kg/個)の投入・均しを行い、開口部14に隣接する、自然石等を用いた傾斜堤の基礎マウンドと、共通の断面を有する基礎マウンド26を造成する。
S10(図4(b)参照):基礎マウンドの天端面上に、施工水域の潮位差を考慮して、満潮時の水位よりも低く堤外側と堤内側との通水断面Ws(図2(a)参照)を確保可能な第1の天端高H1を設定する。そして、基礎マウンド26の天端面の堤内側端部から所定距離を空けて、第1の天端高H1へ到達する高さを有する第1の法先ブロック28を据え付ける。第1の法先ブロック28は、1.3(m)×1.3(m)×2.0(m)の直方体であり、その据え付け作業には、図7(a)に示されるように、堤内に配置した起重機船30が用いられる。
法先ブロック28は、後工程(S20)にて施工する裏込石の捨石本均し面への飛散・こぼれ防止と、合成樹脂製ジオグリッド施工時(S30)の天端ロープ固定用に、複数設置されるものである。又、第1の法先ブロック28は、後工程(S90)において、基礎マウンド26の天端面に据え付けられる方塊ブロック70の設置位置を考慮して、それよりも基礎マウンド26の天端面の堤内側端部寄りに設置される。
Here, a procedure for closing off the opening of the water-proof type revetment including the step of forming the first water-proof structure 24 at an intermediate stage according to the embodiment of the present invention will be described. In the following description, the flowchart in FIG. 3 is mainly referred to, and FIGS. 1, 2, and 4 to 12 are appropriately referred to as the process proceeds.
S0 (see FIG. 4 (a)): foundation rubble (30-100kg / piece) is placed and leveled, and the same cross section as the foundation mound of the sloped levee using natural stone etc. adjacent to the opening 14 The foundation mound 26 having the above is created.
S10 (see FIG. 4 (b)): On the top end surface of the foundation mound, considering the tide level difference in the construction water area, the cross section Ws between the outside of the levee and the inside of the levee is lower than the water level at high tide (FIG. 2 ( a) a first top height H1 capable of ensuring (see a)) is set. Then, a first tip block 28 having a height reaching the first top end height H1 is installed at a predetermined distance from the end of the top end surface of the foundation mound 26 on the bank inner side. The first modulus block 28 is a rectangular parallelepiped of 1.3 (m) × 1.3 (m) × 2.0 (m), and the installation work is as shown in FIG. A hoist ship 30 arranged in the bank is used.
Forehead block 28 is used to prevent scattering and spillage of the back rubble stones that are to be constructed in the post-process (S20) and to fix the top end rope during the synthetic resin geogrid construction (S30). A plurality are installed. Further, the first tip block 28 is arranged in the post-step (S90) in consideration of the installation position of the block block 70 to be installed on the top end surface of the foundation mound 26. Installed near the edge.

S20(図4(c)参照):第1の法先ブロック28の据付完了後、基礎マウンド26の天端面の堤内側端部と第1の法先ブロック28との間に、第1の法先ブロック28の高さに合わせて裏込石34(1〜70kg/個)の投入・均しを行う。裏込石34の投入作業には、図7(b)に示されるように、堤外に配置されたガット船36が用いられる。又、裏込石34の均しは、図7(c)に示されるようにバックホウ38が用いられ、必要に応じ潜水士による作業も行われる。   S20 (see FIG. 4 (c)): After the installation of the first tip block 28 is completed, the first method is between the first end block 28 and the ridge inner end of the top end surface of the foundation mound 26. According to the height of the front block 28, the back stone 34 (1 to 70 kg / piece) is charged and leveled. As shown in FIG. 7B, a gut ship 36 disposed outside the bank is used for the operation of inserting the back stone 34. Further, as shown in FIG. 7C, the backhoe 38 is used for leveling the back stone 34, and a work by a diver is also performed if necessary.

S30(図4(d)参照):続いて、基礎マウンド26の天端面の堤内側端部と第1の法先ブロック28との間に、投入され均された裏込石34の上に、図8(a)に示されるように、堤内に配置した起重機船30を用いて、合成樹脂製ジオグリッド40を設置する。合成樹脂製ジオグリッド40は、筒状に形成された合成樹脂製の網の内部に、切込砕石42を充填したものであり、潮位変動による潮流や波浪の影響により、切込砕石42が洗掘、流出することを防ぐため、第1の天端高H1から所定深さに至るように、複数並列に設置される。そして、合成樹脂製ジオグリッド40により、裏込石34を押え付けた後、合成樹脂製ジオグリッド40の下方から、堤内底面部に至る範囲に切込砕石42(20〜60mm)の投入・均しを行う。合成樹脂製ジオグリッド40の間に隙間がある場合には、これらの隙間を埋めるように、第1の天端高H1から堤内底面部に至る範囲に、切込砕石42の投入・均しを行う。
切込砕石42の投入・均し作業は、図8(b)に示されるように、堤外側に配置した起重機船30にガット船36を接舷し、切込砕石42をガット船36から起重機船30に積み込み、更に堤内側に配置したバックホウ台船44へと切込砕石42を積み替えて行う。更に、必要に応じ、潜水士により均し作業を行う。
S30 (refer to FIG. 4 (d)): Subsequently, on the back-filled stone 34 that is thrown between the top end surface of the base end of the foundation mound 26 and the first tip block 28 and is smoothed, As shown in FIG. 8A, a synthetic resin geogrid 40 is installed using a hoist ship 30 arranged in a bank. The synthetic resin geogrid 40 has a cylindrical synthetic resin net filled with crushed crushed stone 42. The crushed crushed stone 42 is washed by the influence of tidal currents and waves due to tidal fluctuations. In order to prevent digging and outflow, a plurality of units are installed in parallel so as to reach a predetermined depth from the first top height H1. Then, after pressing the backing stone 34 with the synthetic resin geogrid 40, the cut crushed stone 42 (20 to 60 mm) is placed and leveled from the lower side of the synthetic resin geogrid 40 to the bottom of the levee. Do it. When there are gaps between the synthetic resin geogrids 40, the cut crushed stones 42 are placed and leveled in a range from the first top height H1 to the bottom of the bank so as to fill these gaps. Do.
As shown in FIG. 8 (b), the cutting crushed stone 42 is charged and leveled by bringing the gut ship 36 into contact with the hoisting ship 30 disposed on the outside of the bank, and the cutting crushed stone 42 from the gut ship 36 to the hoisting machine. The crushed crushed stones 42 are loaded onto the ship 30 and transferred to the backhoe carrier 44 disposed on the inner side of the bank. Furthermore, leveling work is performed by divers as necessary.

S40(図4(e)参照):切込砕石42の投入範囲の堤内先端部から堤内側に所定距離を空けて、第2の法先ブロック46を据え付ける。第2の法先ブロック46は、第1の法先ブロック28よりも小さな0.7(m)×0.7(m)×2.0(m)の直方体であり、図8(c)に示されるように、堤内側の起重機船30にて、潜水士48の指示のもとで作業を行う。第2の法先ブロック46の据え付け後、必要に応じ、後述の変形追随性遮水材(アスファルトマスチック)打設時のブロック目地間からの漏洩対策として、漏洩防止マットが敷設される。   S40 (see FIG. 4 (e)): The second tip block 46 is installed at a predetermined distance from the tip of the bank in the range where the crushed crushed stone 42 is charged to the bank. The second tip block 46 is a rectangular parallelepiped of 0.7 (m) × 0.7 (m) × 2.0 (m) smaller than the first tip block 28, and is shown in FIG. As shown, the work is performed on the hoist ship 30 inside the bank under the direction of the diver 48. After the installation of the second tip block 46, a leakage prevention mat is laid as necessary to prevent leakage from between the block joints when a deformation followable water shielding material (asphalt mastic) described later is placed.

S50(図4(e)参照):堤内底面部の、第2の法先ブロック46から切込砕石42に至る範囲に、変形追随性遮水材50を薄く打設する。図示の例では、変形追随性遮水材50の打設の厚みは、t=0.15mである。変形追随性遮水材50の打設作業は、図8(d)に示されるように、所定の温度に加熱した変形追随性遮水材50を打設バケット52に移し、堤外側の起重機船30にて打設バケット52を堤内側の台船54へと積み込む。そして、堤内側の起重機船30にて打設バケット52を吊り、潜水士48の指示により行うものである。   S50 (see FIG. 4 (e)): The deformation following water-blocking material 50 is thinly placed in a range from the second method tip block 46 to the cut crushed stone 42 on the bottom surface in the bank. In the illustrated example, the thickness of the placement of the deformation-following water-impervious material 50 is t = 0.15 m. As shown in FIG. 8 (d), the placement operation of the deformation follow-up water shielding material 50 is performed by transferring the deformation follow-up water shielding material 50 heated to a predetermined temperature to the placement bucket 52, and the hoisting ship outside the bank. At 30, the placing bucket 52 is loaded onto the trolley 54 inside the bank. Then, the driving bucket 52 is hung on the hoist ship 30 inside the bank, and is performed according to the instruction of the diver 48.

S60(図4(f)参照):第1の天端高H1から堤内底面部に向けて遮水シート56(遮水層)を敷設し、第1の天端高H1から堤内底面部に至る第1の遮水構造体24(図1、図2参照)を造成する。
この際、潮位が第1の天端高H1付近に近づくにつれ、遮水シート56の挙動は、以下のようになる。まず、下げ潮時は、潮流は堤内から堤外へ向けて発生し、遮水シート56は、傾斜堤の内側斜面に張り付くか、若しくはしわになる。一方、上げ潮時には、潮流は堤外から堤内へ向けて発生し、遮水シート56に揚圧力P(図16参照)が作用する。従って、敷設作業終了毎に、下げ潮時及び上げ潮時の潮流が遮水シート56に及ぼす影響を見極め、次の敷設作業開始までの間に遮水シート56が破損しないよう、仮養生を完了する必要がある。又、遮水シート56の敷設時以降は、遮水シート56の裏面に揚圧力Pが作用することから、これを押え付けるために、大型土のう58(有効水中重量400kg/m)を一定ピッチ(2m間隔)で、遮水シート56の敷設を完了した範囲に配置する。以上の、遮水シート56の敷設作業は、具体的には図10に示されるサブルーチンとなる。
S60 (see FIG. 4 (f)): a water shielding sheet 56 (water shielding layer) is laid from the first top height H1 toward the bottom of the bank, and reaches from the first ceiling height H1 to the bottom of the bank. A first water shielding structure 24 (see FIGS. 1 and 2) is formed.
At this time, as the tide level approaches the vicinity of the first top height H1, the behavior of the water shielding sheet 56 is as follows. First, at the time of lower tide, a tidal current is generated from the inside of the bank toward the outside of the bank, and the water shielding sheet 56 sticks to the inner slope of the inclined bank or becomes wrinkled. On the other hand, at the time of rising tide, the tide is generated from the outside of the bank to the inside of the bank, and the lifting pressure P (see FIG. 16) acts on the water shielding sheet 56. Therefore, every time the laying operation is completed, it is necessary to determine the influence of the tide during the low tide and the rising tide on the water shielding sheet 56 and complete the temporary curing so that the water shielding sheet 56 is not damaged before the next laying work starts. There is. In addition, since the lifting pressure P acts on the back surface of the water-impervious sheet 56 after the water-impervious sheet 56 is laid, a large pitch 58 (effective underwater weight 400 kg / m 2 ) is fixed at a constant pitch. It arrange | positions in the range which completed installation of the water-impervious sheet | seat 56 (2m space | interval). The above-described laying operation of the water shielding sheet 56 is specifically a subroutine shown in FIG.

S601:工場において、三層構造の遮水シート56を製作する。そして、遮水シート56の原反ロールを現場に搬入し、幅広加工を行う。この幅広加工は、現場に隣接する陸上ヤード若しくは海上の作業台船上にて、原反ロール(幅2m)を複数本(例えば15本)広げ並べて配置し、遮水シート56の長手方向の端部同士を熱溶着にて接続し(原反ロール15本の場合、幅30mとなる。)、幅広加工した遮水シート56上にブイを取り付け、浮力を確保した状態で海面上に引き出し、遮水シート56の敷設箇所に海上運搬する。
S602:幅広加工に続いて海上溶着を行う。この海上溶着は、遮水シート56の敷設箇所に海上運搬された、幅広加工した遮水シート56同士を接続するために、小型の作業台船を幅広加工した遮水シート56の間に差し込み、幅広加工した遮水シート56の端部を小型の作業台船上に人力等により引き上げ、水分を除去した後に、上記幅広加工と同様に、互いに熱溶着して接続するものである。
S601: A three-layer water-proof sheet 56 is manufactured in a factory. And the raw fabric roll of the water-impervious sheet 56 is carried in the field, and wide processing is performed. In the wide processing, a plurality of (for example, 15) rolls (for example, 15) are arranged side by side on an onshore yard or a marine work table ship adjacent to the site, and the longitudinal end portion of the water shielding sheet 56 is arranged. They are connected to each other by heat welding (in the case of 15 raw rolls, the width is 30 m), and a buoy is attached on the wide processed water-impervious sheet 56 and is pulled out on the sea surface with buoyancy secured. Transport to the place where the sheet 56 is laid.
S602: Sea welding is performed following the wide processing. This maritime weld is inserted between the impermeable sheet 56, which has been processed into a wide width, in order to connect the impermeable sheets 56, which have been transported to the sea, to the laying location of the impermeable sheet 56, The end portion of the water-impervious sheet 56 subjected to the wide processing is pulled up onto a small work table boat by human power and the like, and after moisture is removed, it is thermally welded and connected to each other in the same manner as the wide processing.

S603:海上溶着完了後、一体化した遮水シート56を海面に浮遊させた状態で、その天端側端部を第1の天端高H1(一例として、施工水域のM.W.L+1.3m、L.W.L±0.0m)に引き上げて、天端固定を行っていく。この際、遮水シート56の天端側端部を確実に位置決めするために、図9(a)(b)に示されるように、基礎マウンド26の天端面上に、山留材60を設置し、遮水シート56の天端部を、ロープ62で山留材60に固定する。更に、揚圧力Pに対抗するために、遮水シート56の天端部近傍を、敷鉄板64及びコンクリートブロック66によって、基礎マウンド26の天端面上に押え付ける。その後、大型土のう58を設置して、遮水シート56の天端部の養生を行う。   S603: After completion of the sea welding, in the state where the integrated water-impervious sheet 56 is floated on the sea surface, its top end side end is set to the first top end height H1 (for example, MW L + 1. 3m, LWL ± 0.0m), and the top end is fixed. At this time, in order to position the top end side of the water-impervious sheet 56 with certainty, as shown in FIGS. 9A and 9B, the mountain retaining material 60 is installed on the top end surface of the foundation mound 26. Then, the top end portion of the water shielding sheet 56 is fixed to the mountain retaining material 60 with the rope 62. Further, in order to counter the lifting pressure P, the vicinity of the top end portion of the water shielding sheet 56 is pressed onto the top end surface of the foundation mound 26 by the laid iron plate 64 and the concrete block 66. Thereafter, a large sandbag 58 is installed to cure the top end of the water shielding sheet 56.

S604〜S608:遮水シート56の天端部に続き、傾斜堤の法面部について、上方から下方に向けて、遮水シート56の敷設作業を進行させる。又、遮水シート56の進行に合わせて、複数の土のう58を、第1の天端高H1から堤内底面部へと配置していく。
S609:傾斜堤の法尻及び堤内底面部まで遮水シート56を敷設する。又、後工程の変形追随性遮水材50の追打設時(S70)に、遮水シート56が浮き上がる事を防ぐために、大型土のう58を法尻部に密に(堤体の延長方向に隙間なく)設置する。
以上により、遮水シート56の敷設作業が完了する。
S604 to S608: Following the top end portion of the water-impervious sheet 56, the laying operation of the water-impervious sheet 56 is advanced from the upper side to the lower side with respect to the slope portion of the inclined bank. Moreover, according to the progress of the water shielding sheet 56, a plurality of sandbags 58 are arranged from the first top height H1 to the bottom surface in the bank.
S609: The water-impervious sheet 56 is laid down to the bottom of the slope and the bottom of the bank. Further, in order to prevent the water-impervious sheet 56 from being lifted when the deformation-following water-impervious material 50 is installed in the subsequent process (S70), the large sandbag 58 is closely attached to the butt (in the extending direction of the levee body). Install without gaps.
Thus, the laying operation of the water shielding sheet 56 is completed.

S70(図5(a)参照):遮水シート56の敷設完了の後、第2の法先ブロック46から遮水シート56の法尻部に至る範囲に、打設した変形追随性遮水材50を覆うようにして、更に、変形追随性遮水材50を追打設する。図示の例では、変形追随性遮水材50の追打設の厚みは、t=0.5mである。本工程においても、変形追随性遮水材50の打設作業は、図11(a)に示されるように、所定の温度に加熱した変形追随性遮水材50を打設バケット52に移し、堤外側の起重機船30にて打設バケット52を堤内側の台船54へと積み込む。そして、堤内側の起重機船30にて打設バケット52を吊り、潜水士48の指示により行うものである。   S70 (see FIG. 5 (a)): A deformation-following water-impervious material placed in the range from the second foremost block 46 to the legal bottom of the water-impervious sheet 56 after completion of the installation of the water-impervious sheet 56 Further, a deformation following water-impervious material 50 is additionally provided so as to cover 50. In the illustrated example, the thickness of the follow-up placement of the deformation follow-up water shielding material 50 is t = 0.5 m. Also in this step, as shown in FIG. 11 (a), the placement operation of the deformation followable water shielding material 50 is performed by transferring the deformation followable water shielding material 50 heated to a predetermined temperature to the placement bucket 52, The driving bucket 52 is loaded onto the trolley 54 inside the bank by the hoisting ship 30 outside the bank. Then, the driving bucket 52 is hung on the hoist ship 30 inside the bank, and is performed according to the instruction of the diver 48.

S80(図5(b)参照):変形追随性遮水材50の追打設の完了の後、第1の天端高H1から第2の法先ブロック46に至る範囲に、第1の天端高H1まで中間砕石68(10〜60mm)を投入して、遮水シート56を含む第1の遮水構造体24(図1、図2参照)を、傾斜堤法面の大型土のう58と共に埋設する。中間砕石68の投入・均し作業は、図11(b)に示されるように、堤外側に配置した起重機船30にガット船36を接舷し、中間砕石68をガット船36から起重機船30に積み込み、更に堤内側に配置したバックホウ台船44へと中間砕石68を積み替えて行う。更に、必要に応じ、潜水士により均し作業を行う。   S80 (see FIG. 5 (b)): After the completion of the follow-up placement of the deformation followable water shielding material 50, the first ceiling is within the range from the first top height H1 to the second foremost block 46. The intermediate crushed stone 68 (10 to 60 mm) is introduced to the end height H1, and the first water-blocking structure 24 (see FIGS. 1 and 2) including the water-blocking sheet 56 is placed together with the large sandbag 58 on the slope bank slope. Buried. As shown in FIG. 11 (b), the intermediate crushed stone 68 is charged and leveled by bringing the gut ship 36 into contact with the hoist ship 30 arranged on the outside of the bank, and transferring the intermediate crushed stone 68 from the gut ship 36 to the hoist ship 30. Then, the intermediate crushed stone 68 is transferred to the backhoe carrier 44 disposed inside the bank. Furthermore, leveling work is performed by divers as necessary.

なお、第1の遮水構造体24を大型土のう58と共に埋設する工程においては、第1の天端高H1から第2の法先ブロック46に至る範囲に中間砕石68を投入する。このため、山留材60、敷鉄板64、コンクリートブロック66及び大型土のう58により基礎マウンド26の天端面上に押え付けられた、遮水シート56の天端側端部の一定幅は、基礎マウンド26の天端面に露出した状態で残されるが、この一定幅の部分が、後述する遮水シート56の予備部56aとなる。
そして、基礎マウンド26の天端面上に押え付けられた山留材60、敷鉄板64、コンクリートブロック66及び大型土のう58を、中間砕石68の投入完了後に撤去し(図5(c)参照)、中間砕石68の上面に、遮水シート56の予備部56aを折り返す。そして、折り返された予備部56aの上に、図11(c)に示されるように、堤内に配置した起重機船30を用いて、大型土のう58を設置する。そして、遮水シート56の予備部56aを中間砕石68の上面に押し付けることにより、潮流による予備部56aの破損を防止する。
In the step of burying the first water-impervious structure 24 together with the large sandbag 58, the intermediate crushed stone 68 is introduced in a range from the first top height H1 to the second method block 46. For this reason, the fixed width of the end portion on the top end side of the water-impervious sheet 56 pressed against the top end surface of the foundation mound 26 by the mountain retaining material 60, the laying iron plate 64, the concrete block 66 and the large sandbag 58 is the foundation mound. Although it remains in the state exposed to the top end surface of 26, the part of this fixed width becomes the reserve part 56a of the water-proof sheet | seat 56 mentioned later.
Then, the pile retaining material 60, the laying iron plate 64, the concrete block 66, and the large soil pad 58 pressed on the top end surface of the foundation mound 26 are removed after the completion of the insertion of the intermediate crushed stone 68 (see FIG. 5C). The preliminary portion 56 a of the water shielding sheet 56 is folded back on the upper surface of the intermediate crushed stone 68. Then, as shown in FIG. 11 (c), a large sandbag 58 is installed on the folded spare portion 56 a using the hoist ship 30 disposed in the bank. And the spare part 56a of the water-impervious sheet 56 is pressed against the upper surface of the intermediate crushed stone 68, thereby preventing the spare part 56a from being damaged by the tidal current.

S90(図5(d)参照):基礎マウンド26の天端面の、第1の法先ブロック28が据え付けられた場所よりも堤外側の位置に、第2の天端高H2へ到達する高さを有する、第1の法先ブロック28よりも大型の方塊ブロック70を据え付ける。方塊ブロック70は、2.0(m)×2.9(m)×3.0(m)の直方体であり、その据付作業は、図12(a)に示されるように、堤外側に配置した起重機船30により行われる。
S100(図5(e)参照):方塊ブロック70、第1の法先ブロック28、及び、基礎マウンド26の天端面の堤内側端部と第1の法先ブロック28との間に投入された裏込石34を覆うようにして、方塊ブロック70の高さに合わせて、裏込石34の再投入・均しを行う。なお、裏込石34の再投入・均し作業手順は、図7(b)に示される裏込石34の投入作業と同様である。
更に、再投入された裏込石34を合成樹脂製ジオグリッド40で押え付ける(図5(f)参照)。合成樹脂製ジオグリッド40の設置作業は、図12(b)に示されるように、堤内に配置した起重機船30を用いて行われる。
S90 (see FIG. 5 (d)): the height of the top end surface of the foundation mound 26 that reaches the second top end height H2 at a position outside the bank from the place where the first tip block 28 is installed. A block 70 having a size larger than the first tip block 28 is installed. The rectangular block 70 is a rectangular parallelepiped of 2.0 (m) × 2.9 (m) × 3.0 (m), and its installation work is arranged on the outside of the bank as shown in FIG. The hoist ship 30 is used.
S100 (see FIG. 5 (e)): The block block 70, the first tip block 28, and the top end face of the foundation mound 26 are inserted between the ridge inner end and the first tip block 28. The back slab 34 is recharged and leveled in accordance with the height of the block block 70 so as to cover the back slab 34. In addition, the re-input / equalization procedure of the back slab 34 is the same as that of the back slab 34 shown in FIG. 7B.
Further, the re-inserted backfill stone 34 is pressed down with a synthetic resin geogrid 40 (see FIG. 5F). As shown in FIG. 12B, the installation work of the synthetic resin geogrid 40 is performed using a hoist ship 30 disposed in the bank.

S110(図6(a)参照):中間砕石68の上面に遮水シート56の予備部56aを押し付けるための大型土のう58を、図12(c)に示されるように、堤内に配置した起重機船30を用いて撤去する。そして、再投入された裏込石34及び合成樹脂製ジオグリッド40の上面を、遮水シート56の予備部56aで覆う。
そして中間砕石68の上面に、第2の天端高H2(図2(a)参照)に至るまで中間砕石68を追加投入し、遮水シート56の予備部56aを埋設する(図6(b)参照)。中間砕石68の再投入作業は、図12(d)に示されるように、堤外側に配置した起重機船30にガット船36を接舷し、中間砕石68をガット船36から起重機船30に積み込み、更に堤内側に配置したバックホウ台船44へと中間砕石68を積み替えて行う。
S110 (see FIG. 6 (a)): a hoist ship in which a large sandbag 58 for pressing the preliminary portion 56a of the water shielding sheet 56 against the upper surface of the intermediate crushed stone 68 is disposed in the levee as shown in FIG. 12 (c). Remove with 30. Then, the top surfaces of the refilled back stone 34 and the synthetic resin geogrid 40 are covered with a spare portion 56 a of the water shielding sheet 56.
Then, the intermediate crushed stone 68 is additionally charged on the upper surface of the intermediate crushed stone 68 until the second top height H2 (see FIG. 2A) is reached, and a preliminary portion 56a of the water shielding sheet 56 is embedded (FIG. 6B). )reference). As shown in FIG. 12 (d), the intermediate crushed stone 68 is re-introduced by bringing the gut ship 36 into contact with the hoisting ship 30 disposed outside the bank and loading the intermediate crushed stone 68 from the gut ship 36 into the hoisting ship 30. Further, the intermediate crushed stone 68 is transshipped to the backhoe carrier 44 disposed on the inner side of the bank.

以上のS10〜S110の各工程は、第1の天端高H1から堤内底面部に至る第1の遮水構造体24の造成に直接的に関連するものである。この第1の遮水構造体24は、施工水域の満潮時の水位(H.W.L.)よりも高位置(一例として、K.P.+3.0mm)の第2の天端高H2(図2(a)参照)まで、接続・延長できるものである。以後は、第2の遮水構造体を造成する工程となる。第2の遮水構造体は、第1の遮水構造体24を覆うようにして、第2の天端高H2から、堤内底面部に至るものである。   The above steps S10 to S110 are directly related to the formation of the first water-blocking structure 24 from the first top height H1 to the bottom of the bank. The first water-impervious structure 24 has a second top height H2 at a higher position (for example, K.P. + 3.0 mm) than the water level (HW.L.) at high tide in the construction water area. It can be connected and extended up to (see FIG. 2A). Thereafter, the second water-impervious structure is formed. The second water-impervious structure extends from the second top height H2 to the bottom surface in the levee so as to cover the first water-impervious structure 24.

S120(図6(c)参照):方塊ブロック70の上面に、上部コンクリート72を打設する。
S130(図6(c)参照):中間砕石68の投入範囲の堤内先端部から堤内側に所定距離を空けて、第3の法先ブロック74を据付ける。第3の法先ブロック74は、第1の法先ブロック28と同じく、1.3(m)×1.3(m)×2.0(m)の直方体である。その据え付け作業は、図8(c)と同様に、堤内側の起重機船30にて、潜水士の指示のもとで作業を行う。
S120 (see FIG. 6C): The upper concrete 72 is placed on the upper surface of the block block 70.
S130 (see FIG. 6C): The third method block 74 is installed with a predetermined distance inside the bank from the tip of the bank in the range where the intermediate crushed stone 68 is charged. The third modulus block 74 is a rectangular parallelepiped of 1.3 (m) × 1.3 (m) × 2.0 (m), like the first modulus block 28. As in FIG. 8C, the installation work is performed under the instruction of a diver on the hoist ship 30 inside the bank.

S140(図6(c)参照):堤内底面部の、第3の法先ブロック74から中間砕石68に至る範囲に、変形追随性遮水材50を打設する。図示の例では、変形追随性遮水材50の打設の厚みは、t=0.15mである。変形追随性遮水材50の打設作業は、図8(d)に示されるのと同様に、所定の温度に加熱した変形追随性遮水材50を打設バケット52に移し、堤外側の起重機船30にて打設バケット52を堤内側の台船54へと積み込む。そして、堤内側の起重機船30にて打設バケット52を吊り、潜水士48の指示により行うものである。   S140 (see FIG. 6C): The deformation-following water-impervious material 50 is placed in a range from the third method tip block 74 to the intermediate crushed stone 68 on the bottom surface in the bank. In the illustrated example, the thickness of the placement of the deformation-following water-impervious material 50 is t = 0.15 m. As shown in FIG. 8D, the placement operation of the deformation follow-up water shielding material 50 is performed by transferring the deformation follow-up water shielding material 50 heated to a predetermined temperature to the placement bucket 52 and The hoisting ship 30 loads the placing bucket 52 onto the trolley 54 inside the bank. Then, the driving bucket 52 is hung on the hoist ship 30 inside the bank, and is performed according to the instruction of the diver 48.

S150(図6(d)参照):中間砕石68を覆うようにして、方塊ブロック70の上面から第3の法先ブロック74に至るまで、遮水シート56(第2の遮水シート)を敷設する。この、第2の遮水シート56は、第1の遮水構造体24に係る遮水シート56と同じものである。又、第2の遮水シート56の敷設の際、第1の遮水構造体24に係る遮水シート56の予備部56a(図9(b)参照)のうち、追加投入した中間砕石68により埋設されていない部分に、第2の遮水シート56の天端側端部を重ね合わせるようにして、敷設する。
なお、この時点では、第1の遮水構造体24が完成していることから堤内に揚圧力P(図16)が第2の遮水シート56に及ぶことはない。(図6(d)参照)。
S150 (see FIG. 6 (d)): a water shielding sheet 56 (second water shielding sheet) is laid from the upper surface of the block block 70 to the third method block 74 so as to cover the intermediate crushed stone 68. To do. The second water shielding sheet 56 is the same as the water shielding sheet 56 according to the first water shielding structure 24. In addition, when the second water-impervious sheet 56 is laid, the intermediate crushed stone 68 added in the spare part 56a (see FIG. 9B) of the water-impervious sheet 56 according to the first water-impervious structure 24 is used. The second water-impervious sheet 56 is laid in such a manner that the top end side end portion of the second water-impervious sheet 56 is superimposed on the portion that is not buried.
At this time, since the first water-impervious structure 24 is completed, the lifting pressure P (FIG. 16) does not reach the second water-impervious sheet 56 in the bank. (See FIG. 6D).

S160(図6(e)参照):第2の遮水シート56の敷設完了の後、第3の法先ブロック74から第2の遮水シート56の法尻部に至る範囲に、打設した変形追随性遮水材50を覆うようにして、更に、変形追随性遮水材50を追打設する。図示の例では、変形追随性遮水材50の追打設の厚みは、t=0.5mである。本工程においても、変形追随性遮水材50の打設作業は、図11(a)に示されるのと同様に、所定の温度に加熱した変形追随性遮水材50を打設バケット52に移し、堤外側の起重機船30にて打設バケット52を堤内側の台船54へと積み込む。そして、堤内側の起重機船30にて打設バケット52を吊り、潜水士48の指示により行うものである。   S160 (see FIG. 6 (e)): After the completion of the laying of the second water-impervious sheet 56, the second impervious sheet 56 was placed in a range from the third tip block 74 to the leg of the second impermeable sheet 56. Further, the deformation follow-up water shielding material 50 is additionally provided so as to cover the deformation follow-up water shielding material 50. In the illustrated example, the thickness of the follow-up placement of the deformation follow-up water shielding material 50 is t = 0.5 m. Also in this step, the deformation follow-up water shielding material 50 is placed in the placement bucket 52 with the deformation follow-up water shielding material 50 heated to a predetermined temperature, as shown in FIG. Then, the hoisting vessel 30 outside the bank is loaded with the placing bucket 52 onto the base ship 54 inside the bank. Then, the driving bucket 52 is hung on the hoist ship 30 inside the bank, and is performed according to the instruction of the diver 48.

S170(図6(f)参照):上部コンクリート72から第3の法先ブロック74に至る範囲を、砕石76で被覆する。これにより、第2の遮水構造体78の造成が完了する。
なお、砕石76は、中間砕石68と同じ物を用いることが出来る。又、その投入作業は、図12(d)に示されるのと同様に、外側に配置した起重機船30にガット船36を接舷し、砕石76ををガット船36から起重機船30に積み込み、更に堤内側に配置したバックホウ台船44へと砕石76を積み替えて行う。
S180:必要に応じ、第2の遮水構造体78の天端面に舗装を施し、遮水型護岸の開口部14の締切工が完了する。
S170 (see FIG. 6F): The range from the upper concrete 72 to the third method block 74 is covered with the crushed stone 76. Thereby, creation of the 2nd water-impervious structure 78 is completed.
The crushed stone 76 can be the same as the intermediate crushed stone 68. Further, as shown in FIG. 12 (d), the charging operation is performed by bringing the gut ship 36 into contact with the hoist ship 30 arranged on the outside, and loading the crushed stone 76 from the gut ship 36 into the hoist ship 30; Furthermore, the crushed stone 76 is transshipped to the backhoe carrier 44 arranged inside the bank.
S180: If necessary, the top end face of the second water-impervious structure 78 is paved, and the cut-off work for the opening 14 of the water-impervious seawall is completed.

さて、上記構成をなす本発明の実施の形態によれば、次のような作用効果を得ることが可能となる。
本発明の実施の形態に係る、遮水型護岸の開口部締切工法は、開口部14においても、それと隣接する自然石等を用いた傾斜堤の基礎マウンドと、共通の断面を有する基礎マウンド26を造成することで、堤体構造の一部共通化を図ることができる。
又、基礎マウンド26の天端面上に、施工水域の潮位差を考慮して、満潮時の水位(H.W.L.)よりも低く堤外側と堤内側との通水断面Ws(図2(a)参照)を確保可能な第1の天端高H1を設定し、第1の天端高H1から堤内底面部に至る第1の遮水構造体24を造成することで、この通水断面Wsを通じて、堤外と堤内との水交換を可能としつつ、堤外から基礎マウンド26を浸透して第1の遮水構造体24の裏面に作用する揚圧力Pの影響を、可能な限り小さく抑えることができる。また、通水断面Wsを通じて、堤内作業に供する工事用船舶の出入りも、一部可能となる。
Now, according to the embodiment of the present invention configured as described above, the following operational effects can be obtained.
According to the embodiment of the present invention, the opening cut-off method for a water-impervious revetment also includes a foundation mound 26 having a common cross section and a foundation mound of an inclined bank using natural stone or the like adjacent to the opening 14. By building the structure, a part of the bank structure can be shared.
In addition, on the top end surface of the foundation mound 26, considering the tide level difference in the construction water area, the water cross section Ws between the outside of the levee and the inside of the levee is lower than the water level at the time of high tide (HWL) (FIG. 2). By setting a first top height H1 that can ensure (see (a)) and creating a first water-blocking structure 24 from the first top height H1 to the bottom of the levee, this water flow Through the cross-section Ws, while allowing water exchange between the outside of the bank and the inside of the bank, the influence of the lifting pressure P that permeates the foundation mound 26 from the outside of the bank and acts on the back surface of the first water shielding structure 24 is minimized. be able to. In addition, it is possible to partially enter and exit the construction vessel used for the work in the bank through the water passage section Ws.

すなわち、図2に示されるように、第1の天端高H1を満潮時の水位(H.W.L.)よりも低い天端高に設定することで、第1の遮水構造体24の造成中、開口部14に残る通水断面Wsを通じて堤外と堤内との水交換が生じ、堤外水位が堤内水位よりも高い時を除き、内面保有水Winが、第1の遮水構造体24を堤内側傾斜面に押し付け、堤外から基礎マウンド26を浸透して第1の遮水構造体24の裏面に作用する揚圧力Pに対抗することができる。一方、堤外水位が堤内水位よりも高い時には、第1の遮水構造体24の表面に配置する錘(大型土のう58)により、堤外から基礎マウンドを浸透して第1の遮水構造体24の裏面に作用する揚圧力Pに対抗することができる(図9、図10参照)。
従って、第1の遮水構造体24の堤内先端部を覆う変形追随性遮水材層50を打設する際に、第1の遮水構造体24の裏面に作用する揚圧力Pにより、第1の遮水構造体24が破損することを防ぐことができる。以上の点を考慮し、第1の天端高H1は、施工水域の潮位差を考慮して、堤外水位が堤内水位よりも高い状態、すなわち、第1の遮水構造体24の裏面に揚圧力Pが作用する時間比率が可能な限り短くなるように、設定されることが望ましい。
That is, as shown in FIG. 2, the first water shielding structure 24 is set by setting the first top height H1 to a top height lower than the water level at high tide (HWL). During the formation of water, water exchange between the outside of the levee and the inside of the levee occurs through the water passage cross section Ws remaining in the opening 14, and the water retained on the inner surface Win is the first impermeable structure 24 except when the water level outside the levee is higher than the water level inside the levee. Can be pressed against the inclined surface on the inner side of the bank and penetrate the foundation mound 26 from the outside of the bank to counter the lifting pressure P acting on the back surface of the first water-blocking structure 24. On the other hand, when the water level outside the levee is higher than the water level inside the levee, the foundation mound penetrates from the outside of the dam by the weight (large sandbag 58) arranged on the surface of the first water-blocking structure 24, and the first water-blocking structure 24 It is possible to counter the lifting pressure P acting on the back surface (see FIGS. 9 and 10).
Therefore, when the deformation followable water shielding material layer 50 covering the tip of the first water shielding structure 24 in the bank is placed, the lifting pressure P acting on the back surface of the first water shielding structure 24 causes the first It is possible to prevent the one water shielding structure 24 from being damaged. Considering the above points, the first top height H1 is in a state where the water level outside the levee is higher than the water level inside the levee in consideration of the tide level difference in the construction water area, that is, on the back surface of the first impermeable structure 24. It is desirable that the time ratio during which the pressure P is applied is set to be as short as possible.

更に、堤外水位が、干潮時の水位(L.W.L.)を挟んで中間水位(M.W.L.)以下の水位となる時間帯では、第1の天端高H1は気中となり(図2参照)、陸上施工が可能となる。
そして、変形追随性遮水材層50の打設により(S70:図5(a)参照)、第1の天端高H1から堤内底面部に至る範囲の遮水を完了し、以後の、施工水域の満潮時の水位よりも高位置の第2の天端高H2から堤内底面部に至る第2の遮水構造体78(図6(f)参照)を造成する工程では、堤外からの揚圧力Pの影響を排除することができる。
Furthermore, in the time zone when the water level outside the levee falls below the intermediate water level (MWL) across the low tide level (LWL), the first top height H1 is in the air. Then (see Fig. 2), land construction is possible.
Then, by placing the deformation followable water shielding material layer 50 (S70: see FIG. 5 (a)), the water shielding in the range from the first top height H1 to the bottom of the levee is completed, and the subsequent construction In the process of creating the second water-impervious structure 78 (see FIG. 6 (f)) from the second top height H2 that is higher than the water level at the time of high tide in the water area to the bottom of the levee, The influence of the pressure P can be eliminated.

又、遮水シート56を第1の天端高H1から堤内底面部に向けて敷設し(S60:図4(f)参照)、遮水シート56の敷設作業の進行に合わせて、錘(大型土のう58)を、第1の天端高H1から堤内底面部へと複数配置することで(図9、図10参照)、遮水シート56の敷設中に、敷設が完了した範囲の遮水シート56を錘によって基礎マウンド26の傾斜法面に確実に押え付けることができる。そして、遮水シート56の敷設中に、遮水シート56の裏面に揚圧力Pが作用することがあっても、錘によってそれに対抗し、遮水シート56の浮き上がりを防ぐことができる。   Further, the water shielding sheet 56 is laid from the first top height H1 toward the bottom surface in the bank (S60: see FIG. 4 (f)), and the weight (large size) is adjusted in accordance with the progress of the laying work of the water shielding sheet 56. By arranging a plurality of sandbags 58) from the first top height H1 to the bottom surface in the bank (see FIG. 9 and FIG. 10), the water shielding sheet in the range where the laying is completed during the construction of the water shielding sheet 56 56 can be securely pressed against the inclined slope of the foundation mound 26 by the weight. And even if the lifting pressure P may act on the back surface of the water-impervious sheet 56 during the laying of the water-impervious sheet 56, it can be countered by the weight to prevent the water-impervious sheet 56 from being lifted.

又、本発明の実施の形態に係る、遮水型護岸の開口部締切工法は、遮水シート56の第1の天端高側端部に設けた所定幅の予備部56a(図5(c)、図6(a)、図9(b)参照)を、第1の遮水構造体24を大型土のう58と共に埋設する工程(S80:図5(b)参照)において、遮水シートの予備部56aを除く、第1の天端高H1から第2の法先ブロック46に至る範囲に中間砕石68を投入した後(図5(b)参照)、中間砕石68の上面に遮水シートの予備部56aを折り返し、再投入された裏込石34及び合成樹脂製ジオグリッド40の上面を、中間砕石の上面に折り返した遮水シートの予備部で覆うことで(図6(a)参照)、施工水域の満潮時の水位よりも高位置の第2の天端高H2から堤内底面部に至る範囲を、第1の遮水構造体24に係る遮水シート56で覆い、遮水性を確保することができる。又、遮水シートの予備部56aのうち、再投入された裏込石34及び合成樹脂製ジオグリッド40の上面を覆う部分を、追加投入した中間砕石68により埋設することで(図6(b)参照)、遮水シートの予備部56aの裏面に作用する揚圧力Pにより、遮水シートの予備部56aが破損することを防ぐことができる。   Further, according to the embodiment of the present invention, the method of closing the opening of the water-impervious seawall is a spare part 56a having a predetermined width provided at the first top end of the water-impervious sheet 56 (FIG. 5C). ), FIG. 6 (a) and FIG. 9 (b)), in the step of burying the first water-impervious structure 24 together with the large sandbag 58 (S80: refer to FIG. 5 (b)) After the intermediate crushed stone 68 is thrown into the range from the first top height H1 to the second method block 46, excluding the portion 56a (see FIG. 5B), a water shielding sheet is placed on the upper surface of the intermediate crushed stone 68. Folding the spare part 56a and covering the top surface of the refilled back stone 34 and the synthetic resin geogrid 40 with the spare part of the water shielding sheet folded back to the upper surface of the intermediate crushed stone (see FIG. 6A) The range from the second top height H2, which is higher than the water level at the time of high tide in the construction water area, to the bottom of the levee, Covered with a water-impervious sheet 56 according to the water-impervious structure 24 can be secured impermeability. In addition, the portion of the preliminary portion 56a of the water shielding sheet that covers the top surface of the re-inserted backfill stone 34 and the synthetic resin geogrid 40 is buried by the additionally input intermediate crushed stone 68 (FIG. 6B). )), It is possible to prevent the preliminary portion 56a of the waterproof sheet from being damaged by the lifting pressure P acting on the back surface of the preliminary portion 56a of the waterproof sheet.

又、堤内底面部の、第3の法先ブロック74から中間砕石68に至る範囲に、変形追随性遮水材を打設し(S140:図6(c)参照)、中間砕石を68覆うようにして、方塊ブロック70の上面から第3の法先ブロック74に至るまで第2の遮水シート56を敷設することで(S150:図6(d)参照)、二重の遮水シート56により、確実に遮水性を有するものとなる。   In addition, a deformation-following water-impervious material is placed in a range from the third method block 74 to the intermediate crushed stone 68 on the bottom surface in the levee (S140: see FIG. 6C) so that the intermediate crushed stone 68 is covered. Then, by laying the second water-impervious sheet 56 from the upper surface of the block block 70 to the third method block 74 (see S150: FIG. 6D), the double water-impervious sheet 56 It will surely have water barrier properties.

又、第3の法先ブロック74から第2の遮水シート56に至る範囲に、打設した変形追随性遮水材50を覆うようにして変形追随性遮水材50を追打設し(S160:図6(e)参照)、第2の天端高H2から堤内底面部に至る範囲の遮水を完了するものである。その後、上部コンクリート72から前記第3の法先ブロックに至る範囲を、砕石で被覆することで(S170:図6(f)参照)、第2の遮水シート56を安定保持することができる。   Further, in the range from the third method tip block 74 to the second water-impervious sheet 56, the deformable follow-up water shielding material 50 is additionally placed so as to cover the placed deformable follow-up water shielding material 50 ( S160: See FIG. 6 (e)), and completes the water shielding in the range from the second top height H2 to the bottom surface of the bank. Then, the range from the upper concrete 72 to the third method block is covered with crushed stone (S170: see FIG. 6F), so that the second water shielding sheet 56 can be stably held.

又、遮水シート56の予備部56aのうち、追加投入した中間砕石68により埋設されていない部分に(図6(b)参照)、第2の遮水シート56の天端側端部を重ねるようにして敷設することで(図6(d)参照)、第2の天端高において、二重の遮水シート56、56が密着し、堤体上方から二重の遮水シート56、56の間への、堤内の保有水又は堤外の水の浸水を防ぐことが可能となる。   Moreover, the top end side end part of the second water-impervious sheet 56 is overlapped with a portion of the spare part 56a of the water-impervious sheet 56 that is not buried by the additionally supplied intermediate crushed stone 68 (see FIG. 6B). By laying in this way (see FIG. 6 (d)), the double water-impervious sheets 56, 56 come into close contact with each other at the second top height, and the double water-impervious sheets 56, 56 from above the dam body. It is possible to prevent the water retained inside the bank or the water outside the bank from entering between.

12:護岸、14:開口部、 16:鋼製の板、 18:コンクリート製の構造物、22:砕石、24:第1の遮水構造体、26:基礎マウンド、28:第1の法先ブロック、34:裏込石、40:合成樹脂製ジオグリッド、42:切込砕石、46:第2の法先ブロック、50:変形追随性遮水材、56:遮水シート、56a:予備部、58:大型土のう、66:コンクリートブロック、68:中間砕石、70:方塊ブロック、72:上部コンクリート、74:第3の法先ブロック、76:砕石、78:第2の遮水構造体   12: revetment, 14: opening, 16: steel plate, 18: concrete structure, 22: crushed stone, 24: first impermeable structure, 26: foundation mound, 28: first method Block: 34: Backstone, 40: Synthetic resin geogrid, 42: Cut crushed stone, 46: Second method block, 50: Deformable water-blocking material, 56: Water-blocking sheet, 56a: Spare part 58: large sandbag, 66: concrete block, 68: intermediate crushed stone, 70: block block, 72: upper concrete, 74: third tip block, 76: crushed stone, 78: second impermeable structure

Claims (5)

遮水型護岸の開口部締切工法であって、
開口部に隣接する自然石等を用いた傾斜堤の基礎マウンドと、共通の断面を有する基礎マウンドを造成し、
該基礎マウンドの天端面上に、施工水域の潮位差を考慮して、満潮時の水位よりも低く堤外側と堤内側との通水断面を確保可能な第1の天端高を設定し、
該第1の天端高から堤内底面部に至る遮水層を造成し、
前記遮水層の表面に錘を配置し、
該遮水層の堤内先端部を覆う変形追随性遮水材層を打設し、
前記第1の天端高以深部へと砕石を投入して、
第1の遮水構造体を造成し、
前記第1の遮水構造体の上部に、施工水域の満潮時の水位よりも高位置の第2の天端高から堤内底面部に至る第2の遮水構造体を造成する、各工程を含むことを特徴とする遮水型護岸の開口部締切工法。
A method for closing the opening of a water-impervious revetment,
The foundation mound of the slope bank using natural stone etc. adjacent to the opening and the foundation mound having a common cross section are created,
On the top surface of the foundation mound, considering the tide level difference of the construction water area, set the first top height that can secure the water cross section between the outside of the levee and the inside of the levee which is lower than the water level at high tide,
Creating a water-impervious layer from the height of the first top to the bottom of the levee;
A weight is disposed on the surface of the water shielding layer,
Placing a deformation-following water-blocking material layer covering the tip of the water-blocking layer in the levee;
Throw crushed stone into the first top and bottom deeper,
Create the first water-impervious structure,
Forming a second water-impervious structure on the upper part of the first water-impervious structure from the second top height higher than the water level at the time of high tide in the construction water area to the bottom of the levee, A method of closing the opening of a water-impervious revetment, characterized by including.
前記遮水層を造成する工程において、遮水シートを前記第1の天端高から堤内底面部に向けて敷設し、該遮水シートの敷設作業の進行に合わせて、前記錘を、前記第1の天端高から堤内底面部へと複数配置することを特徴とする請求項1記載の遮水型護岸の開口部締切工法。 In the step of forming the water shielding layer, a water shielding sheet is laid from the height of the first top edge toward the bottom surface of the levee, and the weight is moved along with the progress of the laying work of the water shielding sheet. 2. The method for closing the opening portion of a water-impervious revetment according to claim 1, wherein a plurality of heights are arranged from the height of the top of 1 to the bottom of the levee. 遮水型護岸の開口部締切工法であって、
開口部に隣接する自然石等を用いた傾斜堤の基礎マウンドと、共通の断面を有する基礎マウンドを造成し、
該基礎マウンドの天端面上に、施工水域の潮位差を考慮して、満潮時の水位よりも低く堤外側と堤内側との通水断面を確保可能な第1の天端高を設定し、
前記基礎マウンドの天端面の堤内側端部から所定距離を空けて、前記第1の天端高へ到達する高さを有する第1の法先ブロックを据付け、
前記基礎マウンドの天端面の堤内側端部と前記第1の法先ブロックとの間に、前記第1の法先ブロックの高さに合わせて裏込石の投入・均しを行い、
該裏込石を合成樹脂製ジオグリッドで押え付けた後、前記第1の天端高から堤内底面部に至る範囲に切込砕石の投入・均しを行い、
該切込砕石の投入範囲の堤内先端部から堤内側に所定距離を空けて、第2の法先ブロックを据付け、
堤内底面部の、前記第2の法先ブロックから前記切込砕石に至る範囲に、変形追随性遮水材を薄く打設し、
遮水シートを前記第1の天端高から堤内底面部に向けて敷設し、該遮水シートの敷設作業の進行に合わせて、複数の土のうを、前記第1の天端高から堤内底面部へと配置し、
前記第2の法先ブロックから前記遮水シートに至る範囲に、前記打設した変形追随性遮水材を覆うようにして変形追随性遮水材を追打設し、
前記第1の天端高から前記第2の法先ブロックに至る範囲に、前記第1の天端高まで中間砕石を投入して、前記遮水シートを前記土のうと共に埋設し、
前記第1の天端高から、施工水域の満潮時の水位よりも高位置の第2の天端高まで、前記遮水シートを接続・延長して、第1の遮水構造体を造成し、
該第1の遮水構造体を覆うようにして、前記第2の天端高から堤内底面部に至る第2の遮水構造体を造成する、各工程を含むことを特徴とする遮水型護岸の開口部締切工法。
A method for closing the opening of a water-impervious revetment,
The foundation mound of the slope bank using natural stone etc. adjacent to the opening and the foundation mound having a common cross section are created,
On the top surface of the foundation mound, considering the tide level difference of the construction water area, set the first top height that can secure the water cross section between the outside of the levee and the inside of the levee which is lower than the water level at high tide,
Installing a first tip block having a height to reach the first top end height at a predetermined distance from the ridge inner end of the top end surface of the foundation mound;
Between the ridge inner end of the top end surface of the foundation mound and the first tip block, the back stone is placed and leveled according to the height of the first tip block,
After pressing the backside stone with a synthetic resin geogrid, throwing and leveling the crushed stone in the range from the height of the first top to the bottom of the levee,
A predetermined distance from the tip of the dam in the cutting crushed stone input range to the inside of the dam, and the second method block is installed.
In the bottom of the dike, in the range from the second tip block to the crushed crushed stone, a deformation-following water shielding material is thinly placed,
A water-impervious sheet is laid from the first top edge height toward the bottom face in the levee, and a plurality of sandbags are arranged from the first top edge height to the bottom face in the levee according to the progress of the laying work of the water-proof sheet. Placed in
In the range from the second method tip block to the water-impervious sheet, the deformation-following water-insulating material is additionally placed so as to cover the placed deformation-following water-insulating material,
Into the range from the first top height to the second tip block, throw the intermediate crushed stone to the first top height, and bury the impermeable sheet with the sandbag,
The first water shielding structure is formed by connecting and extending the water shielding sheet from the first top height to the second top height which is higher than the water level at the time of high tide in the construction water area. ,
A water-blocking mold comprising the steps of forming a second water-blocking structure that covers the first water-blocking structure from the height of the second top to the bottom of the levee. Revetment opening deadline method.
前記遮水シートを前記第1の天端高から堤内底面部に向けて敷設する工程において、前記遮水シートの前記第1の天端高側端部に所定幅の予備部を設け、
前記遮水シートを前記土のうと共に埋設する工程において、前記遮水シートの予備部を除く、前記第1の天端高から前記第2の法先ブロックに至る範囲に中間砕石を投入した後、該中間砕石の上面に前記遮水シートの予備部を折り返し、
前記基礎マウンドの天端面の、前記第1の法先ブロックが据え付けられた場所よりも堤外側の位置に、前記第2の天端高へ到達する高さを有する方塊ブロックを据付け、
該方塊ブロック、前記第1の法先ブロック、及び、前記基礎マウンドの天端面の堤内側端部と前記第1の法先ブロックとの間に投入された裏込石とを覆うようにして、前記方塊ブロックの高さに合わせて裏込石の再投入・均しを行い、
該再投入された裏込石を合成樹脂製ジオグリッドで押え付け、これらの上面を、前記中間砕石の上面に折り返した前記遮水シートの予備部で覆い、
前記中間砕石の上面に、前記第2の天端高に至るまで中間砕石を追加投入し、前記遮水シートの予備部の、再投入された裏込石及び前記合成樹脂製ジオグリッドの上面を覆う部分を、前記追加投入した中間砕石により埋設することを特徴とする請求項3記載の遮水型護岸の開口部締切工法。
In the step of laying the water shielding sheet from the first top end height toward the bottom surface in the levee, a preliminary portion having a predetermined width is provided at the first top end high side end of the water shielding sheet,
In the step of burying the water shielding sheet together with the sandbag, after putting intermediate crushed stone into the range from the first top height to the second method tip block, excluding the spare part of the water shielding sheet, Fold the preliminary part of the water shielding sheet on the upper surface of the intermediate crushed stone,
A block block having a height reaching the second top end height is installed at a position outside the bank of the top end surface of the foundation mound, where the first tip block is installed.
Covering the block block, the first tip block, and the back stone placed between the ridge inner end of the top end surface of the foundation mound and the first tip block, According to the height of the block block, re-filling and leveling the backside stone,
Pressing the re-filled backside stone with a synthetic resin geogrid, and covering these top surfaces with a spare part of the water shielding sheet folded back to the top surface of the intermediate crushed stone,
The intermediate crushed stone is additionally added to the upper surface of the intermediate crushed stone until reaching the second top height, and the back-filled back stone and the upper surface of the synthetic resin geogrid of the preliminary portion of the water shielding sheet are added. The method for closing the opening portion of a water-impervious type revetment according to claim 3, wherein the covering portion is buried by the additionally added intermediate crushed stone.
前記第2の遮水構造体を造成する工程において、
前記方塊ブロックの上面に上部コンクリートを打設し、
前記中間砕石の投入範囲の堤内先端部から堤内側に所定距離を空けて、第3の法先ブロックを据付け、
堤内底面部の、前記第3の法先ブロックから前記中間砕石に至る範囲に、変形追随性遮水材を打設し、
前記中間砕石を覆うようにして、前記方塊ブロックの上面から前記第3の法先ブロックに至るまで第2の遮水シートを敷設し、
前記第3の法先ブロックから前記第2の遮水シートに至る範囲に、前記打設した変形追随性遮水材を覆うようにして変形追随性遮水材を追打設し、
前記上部コンクリートから前記第3の法先ブロックに至る範囲を、砕石で被覆することを特徴とする請求項3又は4記載の遮水型護岸の開口部締切工法。
In the step of creating the second water-impervious structure,
Place the upper concrete on the upper surface of the block block,
At a predetermined distance from the tip of the levee in the crushed stone input range to the inside of the dam, the third method block is installed,
In the range from the third method block to the intermediate crushed stone on the bottom of the levee, a deformation-following water-insulating material is placed,
Covering the intermediate crushed stone, laying a second water-impervious sheet from the upper surface of the block block to the third method block,
In the range from the third tip block to the second water-impervious sheet, the deformation-following water-insulating material is additionally placed so as to cover the placed deformation-following water-insulating material,
5. The method for closing an opening portion of a water-impervious revetment according to claim 3, wherein a range from the upper concrete to the third method block is covered with crushed stone.
JP2010238667A 2010-10-25 2010-10-25 Closure method for water-impervious revetment opening Active JP5791257B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010238667A JP5791257B2 (en) 2010-10-25 2010-10-25 Closure method for water-impervious revetment opening

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010238667A JP5791257B2 (en) 2010-10-25 2010-10-25 Closure method for water-impervious revetment opening

Publications (2)

Publication Number Publication Date
JP2012092512A true JP2012092512A (en) 2012-05-17
JP5791257B2 JP5791257B2 (en) 2015-10-07

Family

ID=46386157

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010238667A Active JP5791257B2 (en) 2010-10-25 2010-10-25 Closure method for water-impervious revetment opening

Country Status (1)

Country Link
JP (1) JP5791257B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020171884A (en) * 2019-04-10 2020-10-22 東洋建設株式会社 Impervious structure, and revetment method
JP2021110197A (en) * 2020-01-15 2021-08-02 ワールドエンジニアリング株式会社 Managed revetment
JP7478060B2 (en) 2020-08-06 2024-05-02 五洋建設株式会社 Watertight structure and watertight method for connection between structures

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004181393A (en) * 2002-12-04 2004-07-02 Toyo Constr Co Ltd Water-barrier structure and water-barrier construction for maritime disposal station
JP2007016444A (en) * 2005-07-06 2007-01-25 Toa Harbor Works Co Ltd Laying method of sand preventive sheet covering slope face of rubble-stone revetment and sand preventive sheet
JP2008307433A (en) * 2007-06-12 2008-12-25 World Engineering Kk Construction method of partition revetment

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004181393A (en) * 2002-12-04 2004-07-02 Toyo Constr Co Ltd Water-barrier structure and water-barrier construction for maritime disposal station
JP2007016444A (en) * 2005-07-06 2007-01-25 Toa Harbor Works Co Ltd Laying method of sand preventive sheet covering slope face of rubble-stone revetment and sand preventive sheet
JP2008307433A (en) * 2007-06-12 2008-12-25 World Engineering Kk Construction method of partition revetment

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020171884A (en) * 2019-04-10 2020-10-22 東洋建設株式会社 Impervious structure, and revetment method
JP7292589B2 (en) 2019-04-10 2023-06-19 東洋建設株式会社 Construction method of impervious structure and revetment
JP2021110197A (en) * 2020-01-15 2021-08-02 ワールドエンジニアリング株式会社 Managed revetment
JP7329249B2 (en) 2020-01-15 2023-08-18 ワールドエンジニアリング株式会社 Managed seawall
JP7478060B2 (en) 2020-08-06 2024-05-02 五洋建設株式会社 Watertight structure and watertight method for connection between structures

Also Published As

Publication number Publication date
JP5791257B2 (en) 2015-10-07

Similar Documents

Publication Publication Date Title
JP5791257B2 (en) Closure method for water-impervious revetment opening
JP2012246670A (en) Uplift pressure-resisting underground structure
CN113266028A (en) Construction method of sea area beach section highway riprap cofferdam seepage prevention system
CN101906785B (en) Method for performing anti-seepage treatment on petroleum drilling site by adopting composite geomembrane
JP6128726B2 (en) breakwater
JP4315620B2 (en) Impermeable treatment method for managed waste landfill revetment
CN106192880B (en) The box harbour of L-type and its method of construction
JP5728206B2 (en) Construction method of partition revetment
JP4822375B2 (en) Water-blocking structure of revetment
JP7564685B2 (en) Water-impermeable structure of seawall at marine disposal site
JP7329249B2 (en) Managed seawall
JP2019073964A (en) Prevention structure for outflow of shore protecting reclamation sediment
JP6128725B2 (en) breakwater
KR20050117693A (en) Waterproof structure of the dike and construction method thereof
JP5669192B2 (en) Quay structure or revetment structure
JP7182451B2 (en) Water-shielding structure of the landfill area of the sea surface disposal site
JP2001152425A (en) Impervious structure of revetment
JP6045196B2 (en) Offshore structure
JP4482859B2 (en) Stabilization method behind the revetment
JP4701412B2 (en) Artificial tidal flat and its construction method
JPH08165652A (en) Foundation construction method of maritime structure
IL226722A (en) Method and device for laying down and tensioning an impermeable cover for hydraulic works in loose material
CN110230310A (en) A kind of method and discharge structure preventing and treating collapsible loess depression
Hawkswood et al. Foundations to precast marine structures
JP3788638B2 (en) Seabed ground protection method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20131021

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20140324

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20150204

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20150313

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20150708

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20150804

R150 Certificate of patent or registration of utility model

Ref document number: 5791257

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250