JP2012077463A - Balcony unit, assembly method of balcony unit, jig, and hanging method of building unit - Google Patents

Balcony unit, assembly method of balcony unit, jig, and hanging method of building unit Download PDF

Info

Publication number
JP2012077463A
JP2012077463A JP2010221289A JP2010221289A JP2012077463A JP 2012077463 A JP2012077463 A JP 2012077463A JP 2010221289 A JP2010221289 A JP 2010221289A JP 2010221289 A JP2010221289 A JP 2010221289A JP 2012077463 A JP2012077463 A JP 2012077463A
Authority
JP
Japan
Prior art keywords
balcony unit
unit
balcony
building
piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2010221289A
Other languages
Japanese (ja)
Other versions
JP5538169B2 (en
Inventor
Takahiro Minamino
貴洋 南野
Takahiro Shimabukuro
孝博 島袋
Kazuharu Mori
和晴 森
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Daiwa House Industry Co Ltd
Original Assignee
Daiwa House Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daiwa House Industry Co Ltd filed Critical Daiwa House Industry Co Ltd
Priority to JP2010221289A priority Critical patent/JP5538169B2/en
Publication of JP2012077463A publication Critical patent/JP2012077463A/en
Application granted granted Critical
Publication of JP5538169B2 publication Critical patent/JP5538169B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

PROBLEM TO BE SOLVED: To provide a balcony unit which can be easily assembled to a skeleton of a building body, its assembly method, a jig, and a hanging method of a building unit.SOLUTION: The balcony unit can be assembled to the skeleton of the building body and is projected to the outer side of the skeleton when assembled to the skeleton. The balcony unit includes a balcony unit side girth piece, which is connected with a set of skeleton side girth pieces provided on the skeleton so as to be arranged straight with a gap in-between to function as a girth in the skeleton together with the set of skeleton side girth pieces. The balcony unit is assembled to the skeleton by connecting the balcony unit side girth piece with each of the set of skeleton side girth pieces in a state that it is positioned in the gap.

Description

本発明は、建物本体の躯体に組み付け可能なバルコニーユニット、及び、その組み付け方法に係り、特に、躯体に組み付けられたときに躯体の外側に張り出すバルコニーユニット、及び、その組み付け方法に関する。また、本発明は、建物本体の躯体に組み付けられる建物用ユニットを吊るための治具、及び、当該治具を用いて建物用ユニットを吊る吊り方法に関する。   The present invention relates to a balcony unit that can be assembled to a housing of a building body, and an assembling method thereof, and more particularly to a balcony unit that projects to the outside of the housing when assembled to the housing, and an assembling method thereof. The present invention also relates to a jig for suspending a building unit to be assembled to a housing of a building body, and a suspension method for suspending a building unit using the jig.

建物本体の躯体に組み付け可能な建物用ユニットの一例として、建物本体の躯体に組み付けられたときに該躯体の外側に張り出すバルコニーユニットは、既に知られている。かかるバルコニーユニットは、建物のバルコニー部を構成する各種部品を予め組み立ててユニット化したものであり、建設現場へ搬送されて当該現場にて建物本体に組み付けられる(例えば、特許文献1参照)。   As an example of a building unit that can be assembled to a building body, a balcony unit that protrudes outside the building when it is assembled to the building body is already known. Such a balcony unit is a unit in which various parts constituting a balcony part of a building are assembled in advance, and is transported to a construction site and assembled to the building body at the site (for example, see Patent Document 1).

特開2001−11936号公報JP 2001-11936 A

ただし、従来のバルコニーユニットについては、建物本体の躯体に組み付けられる前段階で、バルコニー部の構成部品のうち、骨組み(フレーム)等のみがユニット化されているものが多く、当該ユニットを先ず建物本体の躯体に組み付けてから、その後、建設現場においてバルコニー部の床板や外壁等を取り付ける作業を別途要していた。そこで、建設現場での作業を軽減することで施工の迅速化・簡略化を図るために、床板や外壁等をも組み立てた状態までユニット化されたバルコニーユニットを予め準備しておくことも考えられる。   However, with regard to conventional balcony units, many of the components of the balcony portion are unitized only in the framework (frame), etc., before being assembled to the building body frame. After that, it was necessary to separately attach the floor plate and the outer wall of the balcony at the construction site. Therefore, in order to speed up and simplify the construction by reducing the work at the construction site, it is also possible to prepare a balcony unit that has been unitized up to the state where the floorboard and outer wall are also assembled. .

しかしながら、このようなバルコニーユニットを建物本体の躯体に組み付けるためには、例えば、躯体に組み付け後のバルコニーユニットを取り囲むような足場等を架設する等して建物本体の外側に作業スペースを確保しておく必要がある。その一方で、作業スペースを確保しづらい環境(特に、住宅が密集している地域)では、バルコニーユニットを建物本体の躯体に組み付ける作業を建物本体の外側で行うことが困難となる。   However, in order to assemble such a balcony unit in the building body frame, for example, a work space is secured outside the building body by, for example, building a scaffold or the like surrounding the balcony unit after being assembled in the frame. It is necessary to keep. On the other hand, in an environment where it is difficult to secure a work space (particularly in an area where houses are densely populated), it is difficult to perform the work of assembling the balcony unit on the housing of the building body outside the building body.

本発明は、上記の問題に鑑みてなされたものであり、その目的は、建物本体の躯体に容易に組み付けることが可能なバルコニーユニット、および、バルコニーユニットを容易に建物本体の躯体に組み付けるための組み付け方法を提供することにある。   The present invention has been made in view of the above-described problems, and an object of the present invention is to provide a balcony unit that can be easily assembled to a building main body, and a balcony unit to be easily assembled to a building main body. It is to provide an assembly method.

前記課題は、本発明のバルコニーユニットによれば、建物本体の躯体に組み付け可能で、該躯体に組み付けられたときに該躯体の外側に張り出すバルコニーユニットであって、バルコニーユニット側胴差片を有し、該バルコニーユニット側胴差片が、隙間を隔てて直線状に並ぶように前記躯体に設けられた一組の躯体側胴差片と連結して、該一組の躯体側胴差片とともに前記躯体において胴差として機能し、前記バルコニーユニット側胴差片が前記隙間内に位置した状態で前記一組の躯体側胴差片の各々と連結されることによって、前記躯体に組み付けられることにより解決される。
本発明のバルコニーユニットについては、建物本体の躯体に組み付けるにあたり、先ず、躯体に設けられた一組の躯体側胴差片の間に設けられた隙間にバルコニーユニット側胴差片を位置させる。これにより、バルコニーユニット側胴差片と各躯体側胴差片との接合作業(換言すると、バルコニーユニットの建物本体の躯体への組み付け作業)が建物本体の内側から行えるようになる。この結果、建物本体の外側で作業スペースを確保しづらい環境であっても、バルコニーユニットを建物本体の躯体に容易に組み付けることが可能となる。
According to the balcony unit of the present invention, the object is a balcony unit that can be assembled to a housing of a building body and projects outside the housing when assembled to the housing. The balcony unit side torso piece is connected to a set of torso side torso pieces provided on the case so as to be arranged in a straight line with a gap therebetween, and the set of torso side torso pieces In addition, it functions as a trunk difference in the casing, and is assembled to the casing by being connected to each of the pair of casing side trunk difference pieces in a state where the balcony unit side trunk difference piece is located in the gap. It is solved by.
Regarding the balcony unit of the present invention, when assembling to the housing of the building main body, first, the balcony unit side trunk piece is positioned in a gap provided between a pair of housing side trunk pieces provided on the cabinet. Thereby, the joining operation | work (in other words, the assembly | attachment operation | work to the housing of a building main body of a balcony unit) of a balcony unit side body differential piece and each housing side body differential piece can be performed now from the inside of a building main body. As a result, even in an environment where it is difficult to secure a work space outside the building body, the balcony unit can be easily assembled to the housing of the building body.

また、上記のバルコニーユニットにおいて、該バルコニーユニットは、前記バルコニーユニット側胴差片と、該バルコニーユニット側胴差片が固定されたフレームとを有し、前記バルコニーユニットが前記躯体に組み付けられる前の段階で、前記バルコニーユニットは、前記フレームに支持される床板と、該床板が支持される側とは反対側で前記フレームに支持される軒天板と、前記床板の周囲に配置され、前記床板とともに前記バルコニーユニット内の空間を仕切る外壁と、前記空間内の液状水を前記空間の外側に向けて排出するための排水機構とのうち、少なくともいずれか一つを更に有することとしてもよい。
かかる構成であれば、バルコニーユニットの構成要素として当該ユニットに組み込まれている部品が多ければ多いほど、バルコニーユニットを建物本体の躯体に組み付けた後に当該バルコニーユニット周りで行う作業が軽減する。これにより、建物本体の外側に作業スペースを確保する必要性が緩和される結果、建物本体の外側に作業スペースを要さずにバルコニーユニットを建物本体の躯体に容易に組み付けられる、という本発明の効果がより有効に奏されることになる。
Further, in the above balcony unit, the balcony unit includes the balcony unit side torso piece and a frame to which the balcony unit side torso piece is fixed, and before the balcony unit is assembled to the casing. The balcony unit is disposed around the floor board, the floor board supported by the frame, the eaves board supported by the frame on the side opposite to the side on which the floor board is supported, and the floor board. At least one of an outer wall that partitions the space in the balcony unit and a drainage mechanism that discharges liquid water in the space toward the outside of the space may be further included.
With such a configuration, the more parts that are incorporated in the unit as a component of the balcony unit, the less work that is performed around the balcony unit after the balcony unit is assembled to the housing of the building body. As a result, the necessity of securing the work space outside the building body is alleviated. As a result, the balcony unit can be easily assembled to the building body without requiring work space outside the building body. The effect will be more effective.

さらに、建物本体の躯体に組み付けたときに該躯体の外側に張り出すバルコニーユニットを、前記躯体に組み付ける組み付け方法であって、(A)隙間を隔てて直線状に並ぶように設けられた一組の躯体側胴差片を備えた前記躯体と、前記一組の躯体側胴差片と連結し、該一組の躯体側胴差片とともに前記躯体において胴差として機能するバルコニーユニット側胴差片を備えた前記バルコニーユニットと、をそれぞれ準備する工程と、(B)前記一組の躯体側胴差片が並ぶ方向と交差するように前記躯体に設けられた梁部材、の長手方向の一端部が前記隙間に臨んだ状態にあるときに、前記梁部材を傾けて該梁部材の姿勢を、前記長手方向が水平方向に沿った第一姿勢から、前記一端部が前記長手方向の他端部よりも上方に位置した第二姿勢に切り替える工程と、(C)前記姿勢が前記第二姿勢であるときに、前記一端部に前記バルコニーユニット側胴差片を固定する工程と、(D)前記一端部に前記バルコニーユニット側胴差片を固定した後に、前記一端部に固定された前記バルコニーユニット側胴差片が前記隙間内に位置して前記一組の躯体側胴差片に挟まれるように、前記姿勢を前記第二姿勢から前記第一姿勢に戻す工程と、(E)前記一組の躯体側胴差片に挟まれた前記バルコニーユニット側胴差片を、前記一組の躯体側胴差片の各々に連結する工程と、を有するバルコニーユニットの組み付け方法も実現可能である。
かかる方法によれば、上述したように、バルコニーユニットの建物本体の躯体への組み付け作業を建物本体の内側から行えるようになる。また、当該組み付け作業を行っている間、バルコニーユニット各部と建物本体側の部材との干渉を容易に回避することが可能である。
Furthermore, it is an assembling method for assembling a balcony unit projecting outside the housing when it is assembled to the housing of the building body to the housing, and (A) a set provided so as to be linearly arranged with a gap between them. The housing provided with the housing side torso piece, and the pair of housing side torso pieces, together with the set of housing side torso pieces, function as a torso difference in the housing. And (B) one end portion in the longitudinal direction of a beam member provided on the housing so as to intersect with the direction in which the pair of housing-side body differential pieces are arranged. When the beam member is in a state of facing the gap, the beam member is inclined to change the posture of the beam member from the first posture in which the longitudinal direction is along the horizontal direction, and the one end portion is the other end portion in the longitudinal direction. 2nd posture located above A step of switching, (C) a step of fixing the balcony unit side trunk piece to the one end when the posture is the second position, and (D) the balcony unit side trunk piece to the one end. After fixing the posture, the posture is changed from the second posture so that the balcony unit side trunk piece fixed to the one end is positioned in the gap and is sandwiched between the pair of housing side trunk pieces. Returning to the first posture; and (E) connecting the balcony unit side torso piece sandwiched between the set of housing side torso pieces to each of the set of torso body torso pieces. A method for assembling a balcony unit having the above can also be realized.
According to this method, as described above, the work of assembling the balcony unit to the housing of the building body can be performed from the inside of the building body. Further, during the assembly operation, it is possible to easily avoid interference between each part of the balcony unit and members on the building body side.

また、上記のバルコニーユニットの組み付け方法において、前記梁部材を傾けて前記姿勢を前記第一姿勢から前記第二姿勢に切り替える工程では、前記一端部が前記他端部よりも上方に位置するように前記一端部を持ち上げ、前記姿勢を前記第二姿勢から前記第一姿勢に戻す工程では、前記長手方向が前記水平方向に沿うように前記一端部を落下させることとしてもよい。
かかる手順により、バルコニーユニットの組み付け作業をより容易に行うことが可能となる。
Further, in the above assembling method of the balcony unit, in the step of tilting the beam member and switching the posture from the first posture to the second posture, the one end is positioned above the other end. In the step of lifting the one end and returning the posture from the second posture to the first posture, the one end may be dropped so that the longitudinal direction is along the horizontal direction.
Such a procedure makes it possible to more easily perform the assembling work of the balcony unit.

さらに、建物本体の躯体に組み付けられる建物用ユニットを吊るための治具であって、前記躯体に設けられた躯体側胴差片と連結して該躯体側胴差片とともに前記躯体において胴差として機能する建物用ユニット側胴差片が前記建物用ユニットの後端部に備えられているときに、前記建物用ユニット側胴差片と係合する係合部と、該係合部を長手方向の一端部において支持し、前記係合部が前記建物用ユニット側胴差片に係合した際に前記長手方向が前記建物用ユニットの前後方向に沿う支持部材と、前記治具が取り付けられた前記建物用ユニットを吊る際の吊り位置を規定し、前記長手方向に沿って移動することにより、該長手方向において前記吊り位置を調整するための吊り位置調整機構と、を備える治具も実現可能である。
かかる治具によれば、建物用ユニットを建物本体の躯体に組み付けるにあたり、当該建物用ユニットの吊り位置の調整を簡易に行えるようになる結果、建物用ユニットの吊り作業を適切に行うことが可能になる。
Furthermore, it is a jig for suspending a building unit to be assembled to the building body frame, and is connected to the body side trunk difference piece provided in the case and as a body difference in the case together with the body side trunk difference piece. When a functioning building unit side trunk piece is provided at the rear end of the building unit, an engaging portion that engages with the building unit side trunk piece, and the engaging portion in the longitudinal direction A supporting member along which the longitudinal direction runs in the front-rear direction of the building unit and the jig are attached when the engaging portion engages with the building unit side trunk piece. A jig provided with a suspension position adjusting mechanism for adjusting the suspension position in the longitudinal direction by defining the suspension position when suspending the building unit and moving along the longitudinal direction can be realized. It is.
According to such a jig, when the building unit is assembled to the housing of the building body, the suspension position of the building unit can be easily adjusted, so that the building unit can be properly suspended. become.

また、上記の治具において、前記係合部と前記支持部材と前記吊り位置調整機構とをそれぞれ一組ずつ備えるとともに、一方の前記吊り位置調整機構と他方の前記吊り位置調整機構とを連結する連結部材を更に備え、一方の前記吊り位置調整機構と他方の前記吊り位置調整機構には、それぞれ、前記建物用ユニットを吊る際に用いる吊具を取り付けるために、取付け穴が形成されていることとしてもよい。
かかる構成であれば、建物用ユニットを二点吊りすることが可能となり、当該建物用ユニットの吊り姿勢を安定させることが可能になる。
In the above jig, the engagement portion, the support member, and the suspension position adjustment mechanism are each provided in one set, and one of the suspension position adjustment mechanism and the other suspension position adjustment mechanism are connected to each other. A connecting member is further provided, and one mounting position is formed in each of the suspension position adjustment mechanism and the other suspension position adjustment mechanism in order to attach a hanging tool used when hanging the building unit. It is good.
With this configuration, the building unit can be suspended at two points, and the suspension posture of the building unit can be stabilized.

また、上記の治具において、前記建物用ユニット側胴差片がH型鋼を有するときに、一方の前記係合部と他方の前記係合部は、それぞれ鉤状で、前記H型鋼のフランジの端部に引掛かることによって前記H型鋼に係合することとしてもよい。
かかる構成であれば、建物用ユニット側胴差片に治具の係合部を簡易に係合させ、かつ、その係合状態を安定させることが可能になる。
In the above jig, when the building unit side differential piece has H-shaped steel, one of the engaging portions and the other engaging portion are respectively bowl-shaped, and the flange of the H-shaped steel It is good also as engaging with the said H-shaped steel by hooking on an edge part.
With this configuration, it is possible to easily engage the engaging portion of the jig with the building unit side trunk difference piece and to stabilize the engaged state.

また、上記の治具において、前記吊り位置調整機構を前記長手方向に沿って移動させるための駆動機構を有し、前記駆動機構は、中心軸方向が前記長手方向に沿った状態で前記支持部材に回転自在に支持され、前記中心軸方向の一端部に備えられた被操作部が操作されることによって回転する回転ねじ体と、該回転ねじ体が挿入され、該回転ねじ体の回転によって前記中心軸方向に沿って移動するナットと、を有し、前記吊り位置調整機構は、前記ナットが固定されており、前記回転ねじ体の回転による前記ナットの移動に伴って前記長手方向に沿ってスライドするスライド部材を有することとしてもよい。
かかる構成であれば、吊り位置の調整をより容易に行うことが可能になる。
Further, the jig includes a drive mechanism for moving the suspension position adjusting mechanism along the longitudinal direction, and the drive mechanism is configured so that the support member is in a state where a central axis direction is along the longitudinal direction. A rotating screw body that is rotatably supported by the operated portion provided at one end in the central axis direction, and the rotating screw body is inserted, and the rotating screw body rotates to rotate the rotating screw body. A nut that moves along a central axis direction, and the suspension position adjusting mechanism has the nut fixed thereto, along the longitudinal direction along with the movement of the nut by the rotation of the rotating screw body. It is good also as having a slide member which slides.
With this configuration, the suspension position can be adjusted more easily.

さらに、建物本体の躯体に組み付けられて建物の一部をなす建物用ユニットであって、前記躯体に設けられた躯体側胴差片と連結して該躯体側胴差片とともに前記躯体において胴差として機能する建物用ユニット側胴差片を後端部に有する建物用ユニットを、治具を用いて吊る吊り方法であって、前記建物用ユニット側胴差片と係合する係合部と、該係合部を長手方向の一端部において支持する支持部材と、前記治具が取り付けられた前記建物用ユニットを吊る際の吊り位置を規定し、前記長手方向に沿って移動可能な吊り位置調整機構と、を備える前記治具を前記建物用ユニットに取り付ける工程と、前記吊り位置を調整する工程と、を有し、前記治具を前記建物用ユニットに取り付ける工程では、前記長手方向が前記建物用ユニットの前後方向に沿うように前記係合部を前記建物用ユニット側胴差片に係合し、前記吊り位置を調整する工程では、前記吊り位置調整機構を前記長手方向に沿って移動させることにより、該長手方向において前記吊り位置を調整する建物用ユニットの吊り方法も実現可能である。
かかる方法によれば、上述した構成の治具を用いるため、建物用ユニットの吊り位置の調整を簡易に行えて当該建物用ユニットを適切に吊ることが可能になる。
Furthermore, the building unit is a part of a building assembled to the building body frame, and is connected to the body side torso piece provided on the body and is connected to the body side torso piece together with the body side torso piece. A building unit having a building unit side trunk piece that functions as a rear end portion using a jig, and an engagement portion that engages with the building unit side trunk piece; A support member that supports the engaging portion at one end in the longitudinal direction, and a suspension position adjustment that defines a suspension position when the building unit to which the jig is attached is suspended and is movable along the longitudinal direction. A step of attaching the jig to the building unit, and a step of adjusting the suspension position, and in the step of attaching the jig to the building unit, the longitudinal direction is the building. In front of the unit In the step of engaging the engaging unit with the building unit side trunk difference piece along the direction and adjusting the hanging position, by moving the hanging position adjusting mechanism along the longitudinal direction, A method of suspending a building unit that adjusts the suspension position in the longitudinal direction can also be realized.
According to this method, since the jig having the above-described configuration is used, it is possible to easily adjust the suspension position of the building unit and appropriately suspend the building unit.

本発明のバルコニーユニットによれば、建物本体への組み付け作業を該建物本体の内側で行うことが可能になる。この結果、建物本体の外側で作業スペースを確保しづらい環境であっても、バルコニーユニットを建物本体の躯体に容易に組み付けることが可能となる。   According to the balcony unit of the present invention, it is possible to perform the assembling work on the building body inside the building body. As a result, even in an environment where it is difficult to secure a work space outside the building body, the balcony unit can be easily assembled to the housing of the building body.

建物1の模式側面図である。1 is a schematic side view of a building 1. FIG. バルコニー部3の斜視図である。3 is a perspective view of a balcony unit 3. FIG. 建物本体2の躯体20を示す模式斜視図である。2 is a schematic perspective view showing a housing 20 of the building body 2. FIG. 図3Aに記されたX−X断面を示す図である。It is a figure which shows the XX cross section described by FIG. 3A. 本実施形態のバルコニーユニット10の斜視図である。It is a perspective view of the balcony unit 10 of this embodiment. 本実施形態のバルコニーユニット10の組立手順図(第一図)である。It is an assembly procedure figure (1st figure) of the balcony unit 10 of this embodiment. 本実施形態のバルコニーユニット10の組立手順図(第二図)である。It is an assembly procedure figure (2nd figure) of the balcony unit 10 of this embodiment. 本実施形態のバルコニーユニット10の組立手順図(第三図)である。It is an assembly procedure figure (3rd figure) of the balcony unit 10 of this embodiment. 本実施形態のバルコニーユニット10の組立手順図(第四図)である。It is an assembly procedure figure (4th figure) of the balcony unit 10 of this embodiment. 本実施形態のバルコニーユニット10の組立手順図(第五図)である。It is an assembly procedure figure (figure 5) of the balcony unit 10 of this embodiment. 本実施形態のバルコニーユニット10の組立手順図(第六図)である。It is an assembly procedure figure (6th figure) of the balcony unit 10 of this embodiment. 本実施形態のバルコニーユニット10の組立手順図(第七図)である。It is an assembly procedure figure (7th figure) of the balcony unit 10 of this embodiment. 本実施形態のバルコニーユニット10の組立手順図(第八図)である。It is an assembly procedure figure (FIG. 8) of the balcony unit 10 of this embodiment. バルコニーユニット10の組み付け手順を示す流れ図である。It is a flowchart which shows the assembly | attachment procedure of the balcony unit. 図7(A)〜図7(D)は、バルコニーユニット10の組み付け作業の各過程を示す模式図である。FIG. 7A to FIG. 7D are schematic views showing each process of the assembling work of the balcony unit 10. 被操作梁22aと隙間との位置関係を示す図である。It is a figure which shows the positional relationship of the to-be-operated beam 22a and a clearance gap. 被操作梁22aの姿勢の切り替えを行うための機構を示す図である。It is a figure which shows the mechanism for switching the attitude | position of the to-be-operated beam 22a. 治具30の正面図である。3 is a front view of a jig 30. FIG. 図10におけるY−Y断面図である。It is YY sectional drawing in FIG. 治具30が取り付けられた状態のバルコニーユニット10を示す図である。It is a figure which shows the balcony unit 10 in the state to which the jig | tool 30 was attached. 係合部31と上側フランジ部15aとの係合状態を示す図である。It is a figure which shows the engagement state of the engaging part 31 and the upper side flange part 15a. 図14(A)及び図14(B)は、治具30を用いたバルコニーユニット10の吊り作業に関する手順を示す図である。FIG. 14A and FIG. 14B are diagrams showing a procedure related to the hanging work of the balcony unit 10 using the jig 30.

<<建物1の全体構成例>>
本実施形態のバルコニーユニット10を説明するにあたり、当該バルコニーユニット10を用いて完成される建物1の全体構成例について、図1、図2、図3A及び図3Bを参照しながら説明する。図1は、建物1の全体構成例を示しており、具体的には建物1の模式側面図である。図2は、バルコニー部3の斜視図である。図3Aは、建物本体2の躯体20を示しており、具体的には躯体20中の基本構成要素(いわゆる軸組み)を示す模式斜視図である。図3Bは、図3Aに記されたX−X断面を示す図である。
<< Example of overall structure of building 1 >>
In describing the balcony unit 10 of the present embodiment, an example of the overall configuration of the building 1 completed using the balcony unit 10 will be described with reference to FIGS. 1, 2, 3A, and 3B. FIG. 1 shows an example of the overall configuration of a building 1, specifically a schematic side view of the building 1. FIG. 2 is a perspective view of the balcony unit 3. FIG. 3A shows the housing 20 of the building body 2, and is a schematic perspective view specifically showing basic components (so-called shaft assembly) in the housing 20. FIG. 3B is a diagram illustrating a cross section taken along line XX in FIG. 3A.

上記の各図には建物1の前後方向が、矢印にて示されている。なお、以下の説明では、建物1の前後方向においてバルコニー部3が張り出している側を前側(正面側とも言う)と、その反対側を後側と呼ぶこととする。   In the above figures, the front-rear direction of the building 1 is indicated by arrows. In the following description, the side where the balcony 3 projects in the front-rear direction of the building 1 is referred to as a front side (also referred to as a front side), and the opposite side is referred to as a rear side.

本実施形態の建物1は、図1に示すように、建物本体2と、該建物本体2の外側に張り出すバルコニー部3を有する。ここで、建物本体2とは、建物1の主要部分をなし、バルコニー部3以外の部分を意味する。   As shown in FIG. 1, the building 1 of the present embodiment includes a building main body 2 and a balcony portion 3 that protrudes outside the building main body 2. Here, the building body 2 is a main part of the building 1 and means a part other than the balcony part 3.

バルコニー部3は、図1及び図2に示すように、床部3a、該床部3aの周囲に配置された外壁部3b、床部3aの裏側に配置された軒天部3c、及び、バルコニー内空間に侵入した雨水等の液状水を排水するための排水部3dを有している。排水部3dは、図1に示すように、床部3aと軒天部3cの間に形成された排水ライン3eを有する。そして、バルコニー内空間の液状水は、床部3aの天端に形成された排水口3f(図2参照)から、排水ライン3eを通じて排水される。なお、排水ライン3eの下流端部は、建物本体2側に取り付けられた建物本体側樋2aの内空間に連通している。   As shown in FIGS. 1 and 2, the balcony 3 includes a floor 3a, an outer wall 3b arranged around the floor 3a, an eaves 3c arranged on the back side of the floor 3a, and a balcony. It has a drainage part 3d for draining liquid water such as rainwater that has entered the interior space. As shown in FIG. 1, the drainage part 3d has the drainage line 3e formed between the floor part 3a and the eaves-top part 3c. And the liquid water of the space in a balcony is drained through the drain line 3e from the drain port 3f (refer FIG. 2) formed in the top end of the floor part 3a. In addition, the downstream end part of the drainage line 3e is connected to the internal space of the building main body side wall 2a attached to the building main body 2 side.

なお、バルコニー部3の前後方向は建物1の前後方向に対応しており、当該方向において、建物1の正面に位置する側がバルコニー部3の前側となり、その反対側(すなわち、建物本体2に位置する側)がバルコニー部3の後側となる。   Note that the front-rear direction of the balcony 3 corresponds to the front-rear direction of the building 1, and in this direction, the side located in front of the building 1 is the front side of the balcony 3, and the opposite side (ie, the position on the building body 2) The side to be) is the rear side of the balcony 3.

建物本体2は、骨組みとしての躯体20を有する。躯体20は、図3A及び図3Bに示すように、上階と下階との境界位置に胴差21と複数の床梁22とを有する。胴差21は、水平方向に沿う梁部材であり、建物1が完成した時点で略矩形状に配置されて建物本体2の躯体20の外周をなす。複数の床梁22の各々は、その長手方向が建物1の前後方向に沿うように設けられる梁部材であり、胴差21に包囲された状態で該胴差21とともに上階の土台をなす。なお、本実施形態において、胴差21をなす部材は、鋼材(具体的にはH型鋼)である。   The building body 2 has a housing 20 as a framework. As shown in FIGS. 3A and 3B, the frame 20 includes a trunk difference 21 and a plurality of floor beams 22 at the boundary position between the upper floor and the lower floor. The trunk difference 21 is a beam member along the horizontal direction, and is arranged in a substantially rectangular shape when the building 1 is completed, and forms the outer periphery of the housing 20 of the building body 2. Each of the plurality of floor beams 22 is a beam member provided such that the longitudinal direction thereof is along the front-rear direction of the building 1, and forms the foundation of the upper floor together with the trunk difference 21 while being surrounded by the trunk difference 21. In the present embodiment, the member forming the trunk difference 21 is a steel material (specifically, H-shaped steel).

<<バルコニーユニット10の構成例>>
次に、本実施形態のバルコニーユニット10の構成例について図4及び図5A〜図5Gを参照しながら説明する。図4は、本実施形態のバルコニーユニット10の斜視図である。図5A〜図5Hは、本実施形態のバルコニーユニット10の組立手順図であり、バルコニーユニット10の組立状態は図5Aから図5Hへと遷移する。
<< Configuration example of balcony unit 10 >>
Next, the structural example of the balcony unit 10 of this embodiment is demonstrated, referring FIG.4 and FIG.5A-FIG.5G. FIG. 4 is a perspective view of the balcony unit 10 of the present embodiment. 5A to 5H are assembly procedure diagrams of the balcony unit 10 of the present embodiment, and the assembly state of the balcony unit 10 transitions from FIG. 5A to FIG. 5H.

図4には、バルコニーユニット10の前後方向、幅方向及び上下方向が、それぞれ矢印にて示されている。なお、バルコニーユニット10の前後方向はバルコニー部3の前後方向に相当し、バルコニーユニット10の前側は建物1の完成時点でバルコニー部3の前側に相当し、同様にバルコニーユニット10の後側はバルコニー部3の後側に相当する。   In FIG. 4, the front-rear direction, the width direction, and the up-down direction of the balcony unit 10 are indicated by arrows. The front-rear direction of the balcony unit 10 corresponds to the front-rear direction of the balcony unit 3, the front side of the balcony unit 10 corresponds to the front side of the balcony unit 3 when the building 1 is completed, and similarly the rear side of the balcony unit 10 is the balcony. This corresponds to the rear side of the portion 3.

本実施形態のバルコニーユニット10は、建物本体2の躯体20に組み付けられて最終的にバルコニー部3を構成するためのものである。つまり、バルコニーユニット10は、建物本体2の躯体20に組み付け可能であり、躯体20に組み付けられたときに該躯体20の外側に張り出すものである。   The balcony unit 10 of the present embodiment is for assembling the balcony unit 3 after being assembled to the housing 20 of the building body 2. In other words, the balcony unit 10 can be assembled to the housing 20 of the building body 2 and protrudes outside the housing 20 when assembled to the housing 20.

そして、本実施形態のバルコニーユニット10は、建物本体2の躯体20に組み付けられる前の段階で、バルコニー部3の構成要素の大部分を組み込んでいる。つまり、本実施形態では、バルコニー部3を構成する部品のうち、略全ての部品がバルコニーユニット10として一体化されている。かかる状態のバルコニーユニット10は、組立工場で製作されるものであり、建設現場まで搬送された後に、当該現場にて事前に構築されている建物本体2の躯体20に組み付けられる。   And the balcony unit 10 of this embodiment has incorporated most of the components of the balcony part 3 in the step before assembling | attaching to the housing 20 of the building main body 2. FIG. In other words, in the present embodiment, substantially all of the components constituting the balcony unit 3 are integrated as the balcony unit 10. The balcony unit 10 in such a state is manufactured at an assembly factory, and after being transported to a construction site, the balcony unit 10 is assembled to the housing 20 of the building body 2 that has been constructed in advance at the site.

以下、本実施形態のバルコニーユニット10に関して、建物本体2の躯体20に組み付けられる前段階で備えられている要素を説明する。本実施形態のバルコニーユニット10は、図4及び図5A〜図5Hに示すように、床ユニット11と、外壁12と、軒天板13と、排水機構としての排水ユニット14とを構成要素として有している。   Hereinafter, regarding the balcony unit 10 of the present embodiment, elements provided in the previous stage of being assembled to the housing 20 of the building body 2 will be described. As shown in FIGS. 4 and 5A to 5H, the balcony unit 10 of the present embodiment includes a floor unit 11, an outer wall 12, an eaves top plate 13, and a drainage unit 14 as a drainage mechanism as constituent elements. is doing.

床ユニット11は、建物1が完成した時点でバルコニー部3の床部3aをなすものであり、図5A〜図5Cに示すように、フレームとしての床フレーム11aと、床板11bとを有している。   The floor unit 11 forms the floor 3a of the balcony 3 when the building 1 is completed. As shown in FIGS. 5A to 5C, the floor unit 11 includes a floor frame 11a as a frame and a floor plate 11b. Yes.

床フレーム11aは、鋼材からなり、バルコニーユニット10の幅方向に沿って複数(本実施形態では2個)並んだ略矩形状の床支持部11cと、床支持部11c間の接合位置から上方に向かって延出する中間アーム11dとを有する。また、床フレーム11aには、該床フレーム11aの前面、左側面及び右側面を覆うように板金状の桁11eが取り付けられている。なお、この桁11eの下端部は床支持部11cの下端よりも幾分下方に位置している(例えば、図5C及び図5D参照)。また、当該下端部には、外壁12を支持するための外壁支持部材11fが取り付けられている(例えば、図5F参照)。   The floor frame 11a is made of a steel material, and has a substantially rectangular floor support portion 11c arranged in a plurality (two in this embodiment) along the width direction of the balcony unit 10 and a joint position between the floor support portions 11c and upward. And an intermediate arm 11d extending toward the center. Further, a sheet metal-like beam 11e is attached to the floor frame 11a so as to cover the front surface, the left side surface, and the right side surface of the floor frame 11a. Note that the lower end of the girder 11e is located somewhat below the lower end of the floor support 11c (see, for example, FIGS. 5C and 5D). In addition, an outer wall support member 11f for supporting the outer wall 12 is attached to the lower end portion (see, for example, FIG. 5F).

床板11bは、バルコニーユニット10の床天井をなし、床フレーム11a(より具体的には床支持部11c)にネジ止めで固定されて支持されている。なお、本実施形態の床板11bは、図5Bに示すように、床支持部11cごとに分割された防水パンである。このように床板11bが分割可能な構成になっていることにより、バルコニーユニット10の幅に関する自由度が高まり、多くのバリエーションに対応することが可能になる。一方、図5Bに示すように、各防水パンの後側の隅部には、上述した排水口3fが形成されている。   The floor board 11b forms the floor ceiling of the balcony unit 10, and is fixed to the floor frame 11a (more specifically, the floor support portion 11c) by screws and supported. In addition, the floor board 11b of this embodiment is a waterproof pan divided | segmented for every floor support part 11c, as shown to FIG. 5B. Since the floor plate 11b is configured to be split in this way, the degree of freedom regarding the width of the balcony unit 10 is increased, and it is possible to cope with many variations. On the other hand, as shown in FIG. 5B, the drain port 3f described above is formed at the corner on the rear side of each waterproof pan.

外壁12は、床板11bの周囲(具体的には、バルコニーユニット10の前面、左側面及び右側面)に配置され、該床板11bとともにバルコニーユニット10内の空間(図4において記号Sにて示す)を仕切るパネル状部材である。この外壁12は、建物1が完成した時点でバルコニー部3の外壁部3bをなす。そして、床板11bと外壁12により区画された空間Sは、建物1が完成した時点でバルコニー内空間をなすことになる。外壁12は、上述した外壁支持部材11fにより支持される。具体的に説明すると、外壁支持部材11fの上端部には、図5Fに示すように、外壁12を差し込むための差込溝11gが形成されている。外壁12は、この差込溝11gに差し込まれ、さらに外壁支持部材11fにピン止めされることによって、該外壁支持部材11fに支持されるようになる。   The outer wall 12 is disposed around the floor plate 11b (specifically, the front surface, the left side surface, and the right side surface of the balcony unit 10), and the space in the balcony unit 10 together with the floor plate 11b (indicated by symbol S in FIG. 4). It is a panel-shaped member which partitions off. The outer wall 12 forms the outer wall portion 3b of the balcony portion 3 when the building 1 is completed. The space S partitioned by the floor board 11b and the outer wall 12 forms a space in the balcony when the building 1 is completed. The outer wall 12 is supported by the outer wall support member 11f described above. Specifically, as shown in FIG. 5F, an insertion groove 11g for inserting the outer wall 12 is formed at the upper end portion of the outer wall support member 11f. The outer wall 12 is inserted into the insertion groove 11g and further pinned to the outer wall support member 11f, thereby being supported by the outer wall support member 11f.

なお、図5Hに示すように、本実施形態に係る外壁12は、その上端部に手摺12aを備えた構成となっているが、当該手摺12aを有しない外壁12であっても良い。   As shown in FIG. 5H, the outer wall 12 according to the present embodiment is configured to include the handrail 12a at the upper end portion thereof, but may be the outer wall 12 that does not have the handrail 12a.

軒天板13は、床板11bが支持される側とは反対側で床フレーム11aに支持される板状部材であり、建物1が完成した時点で軒天部3cをなす。本実施形態では、軒天板13の前後方向一端部がアングル(不図示)を介して床支持部11cに支持されている。   The eaves top plate 13 is a plate-like member supported by the floor frame 11a on the side opposite to the side on which the floor plate 11b is supported, and forms the eaves top part 3c when the building 1 is completed. In the present embodiment, one end portion in the front-rear direction of the eaves top plate 13 is supported by the floor support portion 11c via an angle (not shown).

排水ユニット14は、建物1が完成した時点で排水部3dをなすものであり、上記空間S内の液状水を該空間Sの外側に向けて排出するための機構である。排水ユニット14は、図5Dに示すように、排水栓ソケット14aと、バルコニーユニット側樋14bとを有する。排水栓ソケット14aは、床板11bに形成された排水口3fと、バルコニーユニット側樋14bとの間に設けられた継手部材である。なお、本実施形態では、排水栓ソケット14aと、バルコニーユニット側樋14bの一部とが、床板11bと軒天板13との間に配置された状態でバルコニーユニット10に設けられている。   The drainage unit 14 forms the drainage section 3d when the building 1 is completed, and is a mechanism for discharging liquid water in the space S toward the outside of the space S. As shown in FIG. 5D, the drainage unit 14 includes a drain plug socket 14a and a balcony unit side wall 14b. The drain plug socket 14a is a joint member provided between the drain port 3f formed in the floor board 11b and the balcony unit side wall 14b. In the present embodiment, the drain plug socket 14a and a part of the balcony unit side wall 14b are provided in the balcony unit 10 in a state of being disposed between the floor plate 11b and the eaves top plate 13.

以上のように、本実施形態に係るバルコニーユニット10は、建物1の完成段階でバルコニー部3を構成する部品の略全てを有している。さらに、本実施形態に係るバルコニーユニット10は、図4に示すように、上述の部品に加えて、更にバルコニーユニット側胴差片15を有している。   As described above, the balcony unit 10 according to the present embodiment has substantially all of the components that constitute the balcony unit 3 at the completion stage of the building 1. Furthermore, as shown in FIG. 4, the balcony unit 10 according to the present embodiment further includes a balcony unit side trunk piece 15 in addition to the above-described components.

バルコニーユニット側胴差片15は、バルコニーユニット10が建物本体2の躯体20に組み付けられたときに、該躯体20において胴差21の一部として機能する部材である。本実施形態のバルコニーユニット側胴差片15は、その中央部にH型鋼を有し、端部には略箱状の鋼材を有している。すなわち、本実施形態では、建物1が完成した段階で建物本体2の躯体20の一部として機能する断片部材が、バルコニーユニット10が躯体20に組み付けられる前の段階でバルコニーユニット10側に取り付けられていることになる。そして、バルコニーユニット側胴差片15は、図4に示すように、その長手方向がバルコニーユニット10の幅方向に沿った状態で、バルコニーユニット10の後端部に位置している。なお、本実施形態では、バルコニーユニット側胴差片15が、床フレーム11aよりも後側に位置した状態で該床フレーム11aに固定されている。   The balcony unit side trunk difference piece 15 is a member that functions as a part of the trunk difference 21 in the casing 20 when the balcony unit 10 is assembled to the casing 20 of the building body 2. The balcony unit side trunk piece 15 of the present embodiment has an H-shaped steel at the center and a substantially box-shaped steel material at the end. That is, in this embodiment, the fragment member that functions as a part of the housing 20 of the building body 2 when the building 1 is completed is attached to the balcony unit 10 side before the balcony unit 10 is assembled to the housing 20. Will be. And the balcony unit side trunk | drum differential piece 15 is located in the rear-end part of the balcony unit 10 in the state in which the longitudinal direction followed the width direction of the balcony unit 10, as shown in FIG. In addition, in this embodiment, the balcony unit side trunk | drum difference piece 15 is being fixed to this floor frame 11a in the state located behind the floor frame 11a.

ここで、バルコニーユニット側胴差片15は、図3B中、ハッチングが施された部分に相当する。かかる部分が、建物本体2の躯体20に組み付けられる前のバルコニーユニット10に取り付けられている。換言すると、バルコニーユニット10が組み付けられる前の躯体20は、胴差21のうちの一部(具体的には、上記したハッチング部分)を欠いている。つまり、バルコニーユニット10が組み付けられる前の躯体20には、一組の躯体側胴差片21a、21bが隙間を隔てて直線状に並ぶように設けられていることになる。   Here, the balcony unit-side trunk difference piece 15 corresponds to a hatched portion in FIG. 3B. Such a portion is attached to the balcony unit 10 before being assembled to the housing 20 of the building body 2. In other words, the housing 20 before the balcony unit 10 is assembled lacks a part of the trunk difference 21 (specifically, the hatched portion described above). That is, a pair of housing-side trunk difference pieces 21a and 21b are provided on the housing 20 before the balcony unit 10 is assembled so as to be arranged in a straight line with a gap.

より具体的に説明すると、一組の躯体側胴差片21a、21bは、バルコニーユニット側胴差片15と同種の鋼材であり、バルコニーユニット10が組み付けられる前の躯体20において、後にバルコニーユニット側胴差片15が入り込むだけの隙間を空けて並んでいる。なお、一組の躯体側胴差片21a、21bが並ぶ方向とは、水平方向に沿い、かつ、建物本体2の前後方向(建物1が完成したときの前後方向)と交差する方向である。   More specifically, the pair of housing side trunk piece 21a, 21b is the same kind of steel as the balcony unit side trunk piece 15, and in the housing 20 before the balcony unit 10 is assembled, They are lined up with a gap enough for the torso piece 15 to enter. Note that the direction in which the pair of frame-side trunk differential pieces 21a and 21b are arranged is a direction along the horizontal direction and intersecting the front-rear direction of the building body 2 (the front-rear direction when the building 1 is completed).

そして、バルコニーユニット10が躯体20に組み付けられる際に、バルコニーユニット側胴差片15が上記隙間内に位置して一組の躯体側胴差片21a、21bの間に入り込み、最終的に一組の躯体側胴差片21a、21bの各々とボルト止め等により連結される。この結果、バルコニーユニット側胴差片15と一組の躯体側胴差片21a、21bとが一本化し、バルコニーユニット側胴差片15が躯体20において一組の躯体側胴差片21a、21bとともに胴差21として機能するようになる。また、当該作業の完了を以って、バルコニーユニット10が躯体20に組み付けられることになる。   And when the balcony unit 10 is assembled | attached to the housing 20, the balcony unit side trunk | drum difference piece 15 is located in the said clearance gap, and penetrates between one set of casing side trunk | drum difference pieces 21a and 21b, and finally one set. Are connected to each of the housing-side body differential pieces 21a and 21b by bolting or the like. As a result, the balcony unit side torso piece 15 and the pair of housing side torso pieces 21a and 21b are unified, and the balcony unit side torso piece 15 is a set of housing side torso pieces 21a and 21b. At the same time, it functions as the trunk difference 21. Moreover, the balcony unit 10 is assembled | attached to the housing 20 by the completion of the said operation | work.

上記の構成を有するバルコニーユニット10は、例えば、組立工場にて図5Aから図5Hの手順で組み立てられた後に、上記バルコニーユニット側胴差片15を所定箇所に取り付けられることにより完成される。そして、完成したバルコニーユニット10は、建設現場に向けて搬送され、当該現場にて建物本体2の躯体20(正確には、バルコニーユニット10が組み付けられる前の躯体20)に組み付けられる。これにより、建設現場での作業量を効果的に減らすことが可能になる。   The balcony unit 10 having the above-described configuration is completed, for example, by assembling the balcony unit side trunk piece 15 at a predetermined position after being assembled in the assembly factory according to the procedure of FIGS. 5A to 5H. And the completed balcony unit 10 is conveyed toward a construction site, and is assembled | attached to the housing 20 of the building main body 2 (to be exact, the housing 20 before the balcony unit 10 is assembled) in the said site. As a result, the amount of work on the construction site can be effectively reduced.

<<本実施形態のバルコニーユニット10の有効性について>>
上述したように、本実施形態のバルコニーユニット10には、建物1が完成した段階で建物本体2の躯体20の一部として機能する部材(具体的には、バルコニーユニット側胴差片15)が、建物本体2の躯体20に組み付けられる前の時点で備えられている。これにより、建物本体2の躯体20に容易に組み付けることが可能なバルコニーユニット10が実現される。以下、本実施形態のバルコニーユニット10の有効性について説明する。
<< Effectiveness of Balcony Unit 10 of this Embodiment >>
As described above, the balcony unit 10 according to the present embodiment has a member (specifically, the balcony unit side trunk piece 15) that functions as a part of the housing 20 of the building body 2 when the building 1 is completed. It is provided at the time before being assembled to the housing 20 of the building body 2. Thereby, the balcony unit 10 which can be easily assembled | attached to the housing 20 of the building main body 2 is implement | achieved. Hereinafter, the effectiveness of the balcony unit 10 of the present embodiment will be described.

すなわち、発明が解決しようとする課題の項で説明したように、従来、バルコニーユニット10を建物本体2の躯体20に組み付けるためには、建物本体2の外側に作業スペースを確保しなければならなかった。これは、従来、バルコニーユニット10側の部材と、建物本体2の躯体20側の部材との取り合い(例えば、接合作業)を建物本体2の外側で行う必要があったためである。かかる事情により、従来では、住宅密集地などの作業スペースを確保しづらい環境におけるバルコニーユニット10の組み付け作業を行うことが困難となっていた。   That is, as described in the section of the problem to be solved by the invention, conventionally, in order to assemble the balcony unit 10 to the housing 20 of the building body 2, a work space must be secured outside the building body 2. It was. This is because, conventionally, it has been necessary to perform the engagement (for example, joining work) between the member on the balcony unit 10 side and the member on the housing 20 side of the building body 2 on the outside of the building body 2. Under such circumstances, conventionally, it has been difficult to assemble the balcony unit 10 in an environment where it is difficult to secure a work space such as a densely populated house.

これに対して、本実施形態では、建物1が完成した段階で建物本体2の躯体20の一部として機能する部材がバルコニーユニット10側に備えられている。また、バルコニーユニット10が組み付けられる前の建物本体2の躯体20には、バルコニーユニット側胴差片15を収容するためのスペースとして、一組の躯体側胴差片21a、21bの間に隙間が設けられている。そして、バルコニーユニット10を躯体20に組み付けるにあたり、上記隙間にバルコニーユニット側胴差片15を嵌め込む。当該隙間に嵌め込まれたバルコニーユニット側胴差片15は、その一部が建物本体2の内側に臨んだ(露出した)状態となる。これにより、バルコニーユニット10側の部材と、建物本体2の躯体20側の部材との取り合いを建物本体2の内側で行うことが可能となる。   On the other hand, in this embodiment, the member which functions as a part of the housing 20 of the building main body 2 when the building 1 is completed is provided on the balcony unit 10 side. In addition, in the housing 20 of the building main body 2 before the balcony unit 10 is assembled, a space is provided between the pair of housing-side torso pieces 21a and 21b as a space for accommodating the balcony unit-side torso piece 15. Is provided. And when attaching the balcony unit 10 to the housing 20, the balcony unit side trunk | drum difference piece 15 is engage | inserted in the said clearance gap. The balcony unit side trunk piece 15 fitted in the gap is in a state where a part thereof faces (exposed) to the inside of the building body 2. Thereby, the member on the balcony unit 10 side and the member on the housing 20 side of the building main body 2 can be engaged inside the building main body 2.

以上のように、本実施形態では、バルコニーユニット10の組み付け作業を建物本体2の内側で行うことが可能である。したがって、建物本体2の外側に作業スペースを確保する必要がなくなり、住宅密集地などにおいてもスムーズにバルコニーユニット10の組み付け作業を行うことが可能となる。そして、本実施形態のバルコニーユニット10の組み付け作業は、上記の如く建物本体2の内側で行える結果、従来の組み付け作業よりも容易に行えるのである。   As described above, in the present embodiment, the assembly work of the balcony unit 10 can be performed inside the building body 2. Therefore, it is not necessary to secure a work space outside the building body 2, and the assembly work of the balcony unit 10 can be performed smoothly even in densely populated houses. And the assembly | attachment operation | work of the balcony unit 10 of this embodiment can be performed more easily than the conventional assembly | attachment operation | work as a result of being able to perform inside the building main body 2 as mentioned above.

さらに、本実施形態のバルコニーユニット10は、建物1の完成段階でバルコニー部3を構成する部品の略全てを有している。これにより、上述した効果がより有効に奏される。分かり易く説明すると、本実施形態では、建物1が完成した段階で建物本体2の躯体20の一部として機能する部材(具体的には、バルコニーユニット側胴差片15)がバルコニーユニット10側に備えられていることにより、建物本体2の外側に作業スペースを要さずにバルコニーユニット10の組み付け作業を行うことが可能である。ここで、建物1の完成段階でバルコニー部3を構成する部品が、建物本体2の躯体20に組み付けられる前のバルコニーユニット10に予め組み込まれていれば、建設現場においてバルコニー部3を完成させるための作業が軽減される。つまり、当該作業を行うためのスペースをバルコニーユニット10周り(すなわち、建本体2の外側)に確保する必要性も緩和される。この結果、建物本体2の外側に作業スペースを要さずにバルコニーユニット10を建物本体2の躯体20に容易に組み付けられるという効果が、より有効に奏される。   Furthermore, the balcony unit 10 of the present embodiment has substantially all of the components that constitute the balcony unit 3 when the building 1 is completed. Thereby, the effect mentioned above is show | played more effectively. If it explains clearly, in this embodiment, the member (specifically, the balcony unit side trunk piece 15) which functions as a part of the housing 20 of the building main body 2 at the stage when the building 1 is completed is on the balcony unit 10 side. By being provided, it is possible to perform the assembling work of the balcony unit 10 without requiring a work space outside the building body 2. Here, in order to complete the balcony part 3 at the construction site, if the parts constituting the balcony part 3 at the completion stage of the building 1 are preliminarily incorporated in the balcony unit 10 before being assembled to the housing 20 of the building body 2. Work is reduced. That is, the need to secure a space for performing the work around the balcony unit 10 (that is, outside the building body 2) is also alleviated. As a result, the effect that the balcony unit 10 can be easily assembled to the housing 20 of the building body 2 without requiring a work space outside the building body 2 is more effectively achieved.

なお、本実施形態では、建物1の完成段階でバルコニー部3を構成する部品の略全てが予め組み込まれているバルコニーユニット10について説明したが、当該構成はあくまでも一例に過ぎない。バルコニーユニット10は、バルコニーユニット側胴差片15と当該バルコニーユニット側胴差片15が固定された床フレーム11aとを有し、躯体20に組み付けられる前の段階で、床板11bと外壁12と軒天板13と排水ユニット14とのうち、少なくともいずれか一つを更に有している構成であれば良い。   In addition, although this embodiment demonstrated the balcony unit 10 in which almost all the parts which comprise the balcony part 3 in the completion stage of the building 1 were integrated previously, the said structure is only an example to the last. The balcony unit 10 includes a balcony unit-side trunk piece 15 and a floor frame 11a to which the balcony unit-side trunk piece 15 is fixed, and before being assembled to the housing 20, the floor plate 11b, the outer wall 12, and the eaves. Any configuration that further includes at least one of the top plate 13 and the drainage unit 14 may be used.

次に、本実施形態のバルコニーユニット10を建物本体2の躯体20に組み付ける方法について、図6と図7(A)〜図7(D)を参照しながら説明する。図6は、バルコニーユニット10の組み付け手順を示す流れ図である。図7(A)〜図7(D)は、バルコニーユニット10の組み付け作業の各過程を示す模式図である。なお、図7(A)〜図7(D)においては、図を分かり易くするために、バルコニーユニット10のスケールやセットボルト16の突出量等が実際のものと異なっている。   Next, a method for assembling the balcony unit 10 of the present embodiment to the housing 20 of the building body 2 will be described with reference to FIGS. 6 and 7A to 7D. FIG. 6 is a flowchart showing an assembling procedure of the balcony unit 10. FIG. 7A to FIG. 7D are schematic views showing each process of the assembling work of the balcony unit 10. 7A to 7D, the scale of the balcony unit 10 and the protruding amount of the set bolt 16 are different from the actual ones for easy understanding of the drawings.

<<バルコニーユニット10の組み付け作業>>
バルコニーユニット10の組み付け方法は、以下に説明する組み付け作業において実践されるものである。当該組付け作業は、図6に示すように、上記構成のバルコニーユニット10、及び、バルコニーユニット10を受け入れる状態にある躯体20をそれぞれ準備する工程から始まる(S001)。その後、後述する被操作梁22aを傾けて該被操作梁22aの姿勢を切り替える工程(S002)と、該被操作梁22aの長手方向一端部にバルコニーユニット側胴差片15を固定する工程(S003)と、固定されたバルコニーユニット側胴差片15が所定位置に位置するように該被操作梁22aの姿勢を再び切り替える工程(S004)と、当該所定位置に位置したバルコニーユニット側胴差片15を上述した一組の躯体側胴差片21a、21bの各々に連結する工程(S005)と、を経てバルコニーユニット10の組み付け作業が完了する。以下、各工程について詳述する。
<< Assembly work of balcony unit 10 >>
The method of assembling the balcony unit 10 is practiced in the assembling work described below. As shown in FIG. 6, the assembling work starts from a step of preparing the balcony unit 10 having the above-described configuration and the housing 20 in a state of receiving the balcony unit 10 (S001). Thereafter, a step of tilting the operated beam 22a (to be described later) to switch the posture of the operated beam 22a (S002), and a step of fixing the balcony unit side trunk piece 15 to one longitudinal end of the operated beam 22a (S003). ), The step of switching the attitude of the operated beam 22a again so that the fixed balcony unit side trunk piece 15 is located at a predetermined position (S004), and the balcony unit side trunk piece 15 located at the predetermined position. The assembly operation of the balcony unit 10 is completed through the step (S005) of connecting the above to the above-described one set of the body-side trunk difference pieces 21a and 21b. Hereinafter, each process is explained in full detail.

<バルコニーユニット10及び躯体20を準備する工程S001>
本工程S001は、バルコニーユニット10の組み付け作業に際して、バルコニーユニット側胴差片15を備えた状態のバルコニーユニット10を、組立工場から建設現場まで搬送する工程である。本実施形態のバルコニーユニット10において、該バルコニーユニット10が有するバルコニーユニット側胴差片15の所定箇所には、セットボルト16が取り付けられている(例えば、図7(B)参照)。このセットボルト16は、バルコニーユニット10が建物本体2の躯体20に組み付けられる際に、該躯体20に形成された係合穴23a(係合穴23aについては後述する)に係合するものであり、その下端部がバルコニーユニット側胴差片15の下端から幾分突出した状態で該バルコニーユニット側胴差片15に取り付けられている。なお、本実施形態におけるセットボルト16の突出量は、約40mmである。
<Step S001 for Preparing Balcony Unit 10 and Housing 20>
This step S001 is a step of transporting the balcony unit 10 with the balcony unit side trunk piece 15 from the assembly factory to the construction site when the balcony unit 10 is assembled. In the balcony unit 10 of the present embodiment, a set bolt 16 is attached to a predetermined portion of the balcony unit-side trunk piece 15 of the balcony unit 10 (see, for example, FIG. 7B). When the balcony unit 10 is assembled to the housing 20 of the building body 2, the set bolt 16 is engaged with an engagement hole 23a formed in the housing 20 (the engagement hole 23a will be described later). The lower end portion of the balcony unit side body differential piece 15 is attached to the balcony unit side body differential piece 15 in a state where it protrudes somewhat from the lower end of the balcony unit side body differential piece 15. In addition, the protrusion amount of the set bolt 16 in this embodiment is about 40 mm.

一方、本工程では、バルコニーユニット10の準備と同様に、建物本体2の躯体20の準備を行う。ここで、躯体20については、バルコニーユニット10を組み付けられる状態となっている必要がある。具体的に説明すると、バルコニーユニット10の準備完了時において、建物本体2の躯体20には、一組の躯体側胴差片21a、21bと、複数の床梁22が備えられている。そして、一組の躯体側胴差片21a、21bの間には、バルコニーユニット側胴差片15が入り込むだけの隙間が形成されている。換言すると、バルコニーユニット10の組み付け作業に際して、一組の躯体側胴差片21a、21bは、上記隙間を隔てて直線状に並んでいる状態にある。   On the other hand, in this step, the housing 20 of the building body 2 is prepared in the same manner as the preparation of the balcony unit 10. Here, the casing 20 needs to be in a state in which the balcony unit 10 can be assembled. More specifically, when the preparation of the balcony unit 10 is completed, the housing 20 of the building body 2 is provided with a pair of housing-side trunk difference pieces 21 a and 21 b and a plurality of floor beams 22. A gap is formed between the pair of housing-side trunk differential pieces 21a and 21b so that the balcony unit-side trunk differential piece 15 enters. In other words, when the balcony unit 10 is assembled, the pair of housing-side trunk difference pieces 21a and 21b are in a state of being linearly arranged with the gap therebetween.

さらに、バルコニーユニット10が建物本体2の躯体20に組み付けられる前において、複数の床梁22の一については、その長手方向一端部が隙間に臨んだ状態にある。すなわち、図8に示すように、バルコニーユニット10が組み付けられる前の躯体20では、一の床梁22が、一組の躯体側胴差片21a、21bが並ぶ方向において該躯体側胴差片21a、21bの間に位置し、当該一の床梁22の長手方向一端(前端)が、建物本体2の前後方向において上記隙間の脇(一組の躯体側胴差21a、21bの各々の後端位置と略同じ位置)に位置している。以下、長手方向一端部が隙間に臨むように備えられた床梁22を被操作梁22aと呼ぶ。当然ながら、被操作梁22aは、一組の躯体側胴差片21a、21bが並ぶ方向と交差するように躯体20に設けられた梁部材の一例である。図8は、被操作梁22aと隙間との位置関係を示す図である。   Furthermore, before the balcony unit 10 is assembled to the housing 20 of the building body 2, one of the plurality of floor beams 22 is in a state where one end in the longitudinal direction faces the gap. That is, as shown in FIG. 8, in the frame 20 before the balcony unit 10 is assembled, one floor beam 22 is connected to the frame side trunk piece 21a in the direction in which the pair of frame side trunk pieces 21a and 21b are arranged. , 21b, and one longitudinal end (front end) of the one floor beam 22 is located beside the gap in the front-rear direction of the building body 2 (the rear end of each pair of housing side trunk differences 21a, 21b). Position). Hereinafter, the floor beam 22 provided so that one end portion in the longitudinal direction faces the gap is referred to as an operated beam 22a. Naturally, the operated beam 22a is an example of a beam member provided on the casing 20 so as to intersect with a direction in which the pair of casing-side trunk difference pieces 21a and 21b are arranged. FIG. 8 is a diagram showing the positional relationship between the operated beam 22a and the gap.

また、隙間の直下には、バルコニーユニット10が建物本体2の躯体20に組み付けられる際にバルコニーユニット側胴差片15を受ける受け部材23が設けられており、当該受け部材23の上端部には係合穴23aが形成されている。ここで、受け部材23とは、例えば、躯体20において胴差21よりも下方に位置する横架部材、間柱又は管柱若しくは外壁材である。   Also, immediately below the gap, a receiving member 23 is provided that receives the balcony unit side trunk piece 15 when the balcony unit 10 is assembled to the housing 20 of the building body 2. An engagement hole 23a is formed. Here, the receiving member 23 is, for example, a horizontal member, an intermediate column, a pipe column, or an outer wall member that is positioned below the trunk difference 21 in the housing 20.

以上の状況の下、準備されたバルコニーユニット10は、建物本体2の躯体20の所定位置に組み付けるために吊り上げられる。そして、吊り上げられたバルコニーユニット10は、その前端が後端よりも上方に位置した姿勢(具体的には、セットボルト16の突出量に応じた分だけ上方に位置した姿勢)を維持しながら、上記の所定位置に向けて移動される。なお、バルコニーユニット10の吊り方法、及び、バルコニーユニット10を吊る際に用いられる治具30については後に詳述する。   Under the above circumstances, the prepared balcony unit 10 is lifted to be assembled at a predetermined position of the housing 20 of the building body 2. Then, the suspended balcony unit 10 maintains the posture in which the front end is located above the rear end (specifically, the posture located above the amount corresponding to the protruding amount of the set bolt 16) It is moved toward the predetermined position. The method for hanging the balcony unit 10 and the jig 30 used when hanging the balcony unit 10 will be described in detail later.

<被操作梁22aの姿勢を切り替える工程S002>
本工程S002は、被操作梁22aの長手方向一端部が隙間に臨んだ状態にあるときに、被操作梁22aを傾けて被操作梁22aの姿勢を切り替える工程である。具体的に説明すると、本工程S002が実行される前の段階で、被操作梁22aは、その長手方向一端部が隙間に臨んでおり、かつ、その長手方向が水平方向に沿っている状態にある。かかる状態にある被操作梁22aの姿勢を、以降、第一姿勢と呼ぶ。その後、本工程S002の実行により、被操作梁22aは、その長手方向一端部が長手方向他端部よりも上方に位置した状態になるように傾けられる。かかる状態にある被操作梁22aの姿勢を、以降、第二姿勢と呼ぶ。なお、本実施形態における第二姿勢とは、セットボルト16の突出量に応じた分だけ、被操作梁22aの長手方向一端(前端)が長手方向他端(後端)よりも上方に位置した状態の姿勢である。
<Step S002 for switching the posture of the operated beam 22a>
This step S002 is a step of switching the posture of the operated beam 22a by tilting the operated beam 22a when one end in the longitudinal direction of the operated beam 22a faces the gap. More specifically, in the stage before this step S002 is executed, the operated beam 22a has one end in the longitudinal direction facing the gap, and the longitudinal direction is in the horizontal direction. is there. Hereinafter, the posture of the operated beam 22a in this state is referred to as a first posture. Thereafter, by the execution of this step S002, the operated beam 22a is tilted so that one end portion in the longitudinal direction is positioned higher than the other end portion in the longitudinal direction. Hereinafter, the posture of the operated beam 22a in this state is referred to as a second posture. In the present embodiment, the second posture is such that one end (front end) in the longitudinal direction of the operated beam 22a is positioned above the other end (rear end) in the longitudinal direction by an amount corresponding to the protruding amount of the set bolt 16. It is the posture of the state.

以下、被操作梁22aの姿勢を上記の如く切り替えるための具体的手順について図9を参照しながら説明する。図9は、被操作梁22aの姿勢の切り替えを行うための機構を示す図である。   Hereinafter, a specific procedure for switching the posture of the operated beam 22a as described above will be described with reference to FIG. FIG. 9 is a diagram showing a mechanism for switching the posture of the operated beam 22a.

本工程S002を行うにあたり、まず、図9に示すように、被操作梁22aの長手方向一端部の下方位置に、若干の空間を設けて、被操作梁22aの長手方向と交差する方向に長い単管40を敷設する。この際、単管40は、建物本体2の躯体20に設けられた支持部材40aにより支持される。次に、この単管40と被操作梁22aの長手方向一端部との間に、梁受部材としてのジャッキ41を据え付ける。このジャッキ41は、単管40側に備え付けられた留め具41aにより固定支持される。これにより、被操作梁22aの長手方向一端部がジャッキ41に支持されるようになる。その後、ジャッキ41の操作により、被操作梁22aの長手方向一端部が持ち上がり、被操作梁22aが傾けられる。この結果、図7(A)に示すように、被操作梁22aの姿勢が第一姿勢から第二姿勢に切り替わり、その後、被操作梁22aの長手方向一端部がジャッキ41に支持され続ける間、上記姿勢が第二姿勢に維持されることになる。   In performing this step S002, first, as shown in FIG. 9, a slight space is provided at a position below one end portion in the longitudinal direction of the operated beam 22a and is long in a direction intersecting with the longitudinal direction of the operated beam 22a. A single pipe 40 is laid. At this time, the single tube 40 is supported by a support member 40 a provided in the housing 20 of the building body 2. Next, a jack 41 as a beam receiving member is installed between the single tube 40 and one end in the longitudinal direction of the operated beam 22a. The jack 41 is fixedly supported by a fastener 41a provided on the single tube 40 side. Thereby, the longitudinal direction one end part of the to-be-operated beam 22a comes to be supported by the jack 41. FIG. Thereafter, the operation of the jack 41 raises one longitudinal end of the operated beam 22a, and the operated beam 22a is tilted. As a result, as shown in FIG. 7A, the position of the operated beam 22a is switched from the first position to the second position, and thereafter, one end in the longitudinal direction of the operated beam 22a is continuously supported by the jack 41. The posture is maintained in the second posture.

以上のような手順により本工程002が実行される。なお、本工程002の実行時期については、バルコニーユニット10の吊り上げ前であっても、吊り上げ後であってもよい。また、上述した単管40及びジャッキ41の設置作業、及び、当該ジャッキ41の操作は建物本体2の内側で行うことが可能である。   This step 002 is executed by the procedure as described above. Note that the execution time of this step 002 may be before the balcony unit 10 is lifted or after it is lifted. Further, the installation work of the single pipe 40 and the jack 41 and the operation of the jack 41 can be performed inside the building body 2.

<被操作梁22aにバルコニーユニット側胴差片15を固定する工程S003>
本工程S003は、被操作梁22aの姿勢を第一姿勢から第二姿勢に切り替える工程S003の後に行われ、姿勢が第二姿勢にある状態の被操作梁22aの長手方向一端部に、吊り上げられた状態のバルコニーユニット側胴差片15を固定する工程である。
<Step S003 of fixing the balcony unit side trunk piece 15 to the operated beam 22a>
This step S003 is performed after the step S003 for switching the posture of the operated beam 22a from the first posture to the second posture, and is lifted to one end in the longitudinal direction of the operated beam 22a in a state where the posture is in the second posture. This is a step of fixing the balcony unit side trunk piece 15 in a state of being damaged.

本実施形態では、本工程S003の実行に際して、吊り上げられたバルコニーユニット10の姿勢(吊り姿勢)が、セットボルト16の突出量に応じた分だけ、バルコニーユニット10の前端が後端よりも上方に位置するように調整されている。他方、被操作梁22aの姿勢は、セットボルト16の突出量に応じた分だけ、該被操作梁22aの長手方向一端部が長手方向他端部よりも上方に位置するように調整されている。換言すると、本実施形態では、図7(B)に示すように、バルコニーユニット10の傾き具合と同程度に、被操作梁22aが傾けられることになる。この結果、被操作梁22aの長手方向一端部にバルコニーユニット側胴差片15を固定するための作業(例えば、ボルト等による接合作業)が円滑に行われるようになる。そして、本工程S003が完了すると、バルコニーユニット10が、バルコニーユニット側胴差片15を介して被操作梁22aに連結された状態となる(例えば、図7(C)参照)。   In the present embodiment, when executing this step S003, the balcony unit 10 is lifted so that the front end of the balcony unit 10 is higher than the rear end by an amount corresponding to the protruding amount of the set bolt 16. It is adjusted to be positioned. On the other hand, the posture of the operated beam 22a is adjusted so that one end in the longitudinal direction of the operated beam 22a is positioned higher than the other end in the longitudinal direction by an amount corresponding to the protruding amount of the set bolt 16. . In other words, in this embodiment, as shown in FIG. 7B, the operated beam 22a is tilted to the same extent as the inclination of the balcony unit 10. As a result, an operation for fixing the balcony unit side trunk piece 15 to one end portion in the longitudinal direction of the operated beam 22a (for example, a joining operation using a bolt or the like) is smoothly performed. And if this process S003 is completed, the balcony unit 10 will be in the state connected with the to-be-operated beam 22a via the balcony unit side trunk piece 15 (for example, refer FIG.7 (C)).

<被操作梁22aの姿勢を再び切り替える工程S004>
本工程S004は、被操作梁22aの長手方向一端部にバルコニーユニット側胴差片15を固定した後に実行され、被操作梁22aの姿勢を第二姿勢から第一姿勢に戻す工程である。本工程S004により、被操作梁22aの長手方向一端部に固定されたバルコニーユニット側胴差片15が、一組の躯体側胴差片21a、21bの間の隙間内に位置し、当該一組の躯体側胴差片21a、21bに挟まれるようになる。すなわち、本工程S004は、被操作梁22aの操作を通じて、バルコニーユニット側胴差片15が一組の躯体側胴差片21a、21bの間の隙間内に配置されるように、当該バルコニーユニット側胴差片15及び当該バルコニーユニット側胴差片15が備えられたバルコニーユニット10を移動させる工程である。
<Step S004 for switching the attitude of the operated beam 22a again>
This step S004 is a step that is executed after the balcony unit side trunk piece 15 is fixed to one longitudinal end portion of the operated beam 22a, and returns the posture of the operated beam 22a from the second posture to the first posture. By this step S004, the balcony unit side trunk difference piece 15 fixed to one end in the longitudinal direction of the operated beam 22a is located in the gap between the pair of frame side trunk difference pieces 21a and 21b. Are sandwiched between the body-side trunk differential pieces 21a and 21b. That is, this step S004 is performed on the balcony unit side so that the balcony unit side trunk piece 15 is disposed in the gap between the pair of housing side trunk pieces 21a and 21b through the operation of the operated beam 22a. This is a step of moving the balcony unit 10 provided with the trunk difference piece 15 and the balcony unit side trunk difference piece 15.

以下、被操作梁22aの姿勢を第二姿勢から第一姿勢に復帰させるための具体的手順について説明する。   Hereinafter, a specific procedure for returning the posture of the operated beam 22a from the second posture to the first posture will be described.

被操作梁22aの長手方向一端部にバルコニーユニット側胴差片15が固定された後、ジャッキ41の操作によって、上記長手方向一端部を自重によって落下させる。この結果、被操作梁22aの長手方向が水平方向に沿うようになる(すなわち、被操作梁22aの姿勢が第一姿勢に復帰する)。この過程において、被操作梁22aの長手方向一端部に固定されたバルコニーユニット側胴差片15は、一組の躯体側胴差片21a、21bの間の隙間内に位置するようになる。さらに、バルコニーユニット側胴差片15が隙間内に位置する際に、当該バルコニーユニット側胴差片15に取り付けられたセットボルト16が、隙間の直下に設けられた受け部材23の係合穴23aに係合するようになる(図7(D)参照)。   After the balcony unit side trunk piece 15 is fixed to one end portion in the longitudinal direction of the beam to be operated 22a, the one end portion in the longitudinal direction is dropped by its own weight by the operation of the jack 41. As a result, the longitudinal direction of the operated beam 22a is aligned with the horizontal direction (that is, the attitude of the operated beam 22a returns to the first attitude). In this process, the balcony unit side trunk difference piece 15 fixed to one end portion in the longitudinal direction of the operated beam 22a comes to be positioned in a gap between the pair of body side trunk difference pieces 21a and 21b. Further, when the balcony unit side trunk piece 15 is positioned in the gap, the set bolt 16 attached to the balcony unit side trunk piece 15 is engaged with the engagement hole 23a of the receiving member 23 provided immediately below the gap. (See FIG. 7D).

このように、本実施形態では、被操作梁22aの姿勢の切り替えにより、バルコニーユニット側胴差片15は所定の位置に配置されるようになる。換言すると、被操作梁22aの長手方向一端部にバルコニーユニット側胴差片15を固定する工程S003では、被操作梁22aの姿勢を第一姿勢に復帰させたときにバルコニーユニット側胴差片15が上記の隙間内に位置でき、かつ、上記のセットボルト16が係合穴23aに係合できるように、バルコニーユニット側胴差片15の所定箇所を被操作梁22aの長手方向一端部に固定させることになる。   Thus, in this embodiment, the balcony unit side trunk difference piece 15 comes to be arrange | positioned in a predetermined position by switching the attitude | position of the to-be-operated beam 22a. In other words, in the step S003 for fixing the balcony unit side trunk piece 15 to one end in the longitudinal direction of the operated beam 22a, the balcony unit side trunk piece 15 when the attitude of the operated beam 22a is returned to the first position. Is fixed at one end in the longitudinal direction of the operated beam 22a so that the set bolt 16 can be engaged with the engagement hole 23a. I will let you.

そして、隙間内に位置したバルコニーユニット側胴差片15は当該隙間を埋め、受け部材23による支持を受けつつ、鉛直方向において一組の躯体側胴差片21a、21bと同じ高さに位置するようになる。なお、本工程S004の完了後、上述した単管40及びジャッキ41は建物本体2の躯体20から取り外されることとなる。   And the balcony unit side trunk difference piece 15 located in the gap is positioned at the same height as the pair of frame side trunk difference pieces 21a and 21b in the vertical direction while filling the gap and receiving the support by the receiving member 23. It becomes like this. In addition, after completion of this process S004, the single pipe 40 and the jack 41 mentioned above will be removed from the housing 20 of the building main body 2. FIG.

<バルコニーユニット側胴差片15を躯体側胴差片21a、21bに連結する工程S005>
本工程S005は、その前の工程S004において一組の躯体側胴差片21a、21bと同じ高さに位置するようになったバルコニーユニット側胴差片15を、前記一組の躯体側胴差片21a、21bの各々と連結する工程である。本工程S005により、バルコニーユニット側胴差片15は、建物本体2の躯体20において一組の躯体側胴差片21a、21bとともに胴差21の一部として機能するようになる。そして、本工程S005の完了を以って、バルコニーユニット10の組み付け作業が完了する。
<Step S005 for Connecting Balcony Unit Side Body Difference Piece 15 to Housing Side Body Difference Pieces 21a and 21b>
In this step S005, the balcony unit side torso piece 15 that is positioned at the same height as the pair of case side torso pieces 21a and 21b in the previous step S004 is replaced with the set of body side torso pieces. This is a step of connecting to each of the pieces 21a, 21b. By this process S005, the balcony unit side trunk difference piece 15 comes to function as a part of the trunk difference 21 together with the pair of casing side trunk difference pieces 21a and 21b in the casing 20 of the building body 2. And the assembly | attachment operation | work of the balcony unit 10 is completed by completion of this process S005.

<<本実施形態のバルコニーユニット10の組み付け方法の有効性について>>
上述したように、本実施形態のバルコニーユニット10の組み付け方法では、一組の躯体側胴差片21a、21bの間の隙間に長手方向一端部が臨んだ状態にある一の床梁22(すなわち、被操作梁22a)を傾けて、床梁22の姿勢を第一姿勢から第二姿勢に切り替え、当該姿勢が第二姿勢であるときに、前記長手方向一端部にバルコニーユニット側胴差片15を固定する。その後、バルコニーユニット側胴差片15が固定された床梁22の姿勢を第一姿勢に戻すことにより、バルコニーユニット側胴差片15が上記の隙間内に位置して一組の躯体側胴差片21a、21bに挟まれるようになる。
<< Effectiveness of Assembling Method of Balcony Unit 10 of this Embodiment >>
As described above, in the method for assembling the balcony unit 10 of the present embodiment, one floor beam 22 (i.e., one end in the longitudinal direction faces the gap between the pair of frame-side trunk difference pieces 21a and 21b) (i.e. The beam 22a) is tilted to switch the posture of the floor beam 22 from the first posture to the second posture. When the posture is the second posture, the balcony unit side trunk piece 15 is placed at one end in the longitudinal direction. To fix. Thereafter, by returning the posture of the floor beam 22 to which the balcony unit side torso piece 15 is fixed to the first position, the balcony unit side torso piece 15 is located in the gap and the pair of housing side torso pieces are set. It comes to be sandwiched between the pieces 21a and 21b.

以上の組み付け方法により、バルコニーユニット10を建物本体2の躯体20に組み付けるための一連の作業が建物本体2の内側から行えるようになる。さらに、当該組み付け作業を行っている間、バルコニーユニット10の各部と建物本体2側の部材との干渉を容易に回避することが可能となる。   With the above assembling method, a series of operations for assembling the balcony unit 10 to the housing 20 of the building body 2 can be performed from the inside of the building body 2. Furthermore, it is possible to easily avoid interference between each part of the balcony unit 10 and the member on the building body 2 side during the assembly operation.

具体的に説明すると、バルコニーユニット10を建物本体2の躯体20に組み付けるためには、バルコニーユニット側胴差片15を一組の躯体側胴差片21a、21bの間の隙間に嵌め込む必要がある。ここで、上記の床梁22(すなわち、被操作梁22aに相当する床梁22)が正位置に配置された状態のままでバルコニーユニット側胴差片15を上記隙間に嵌め込もうとすると、当該床梁22にバルコニーユニット側胴差片15が衝突し易くなってしまう。   More specifically, in order to assemble the balcony unit 10 to the housing 20 of the building body 2, it is necessary to fit the balcony unit-side torso piece 15 into a gap between the pair of body-side torso pieces 21a and 21b. is there. Here, when the above-mentioned floor beam 22 (that is, the floor beam 22 corresponding to the operated beam 22a) is placed in the normal position and the balcony unit side trunk piece 15 is to be fitted into the gap, The balcony unit side trunk piece 15 easily collides with the floor beam 22.

これに対し、本実施形態では、バルコニーユニット側胴差片15を一組の躯体側胴差片21a、21bの間の隙間に嵌め込むにあたり、先ず、被操作梁22aを傾けて、該被操作梁22aの長手方向一端部にバルコニーユニット側胴差片15を固定する。これにより、上述した衝突の危険性を回避することが可能になる。そして、バルコニーユニット側胴差片15が固定された状態の被操作梁22aについて、その姿勢を元の姿勢に復帰させる(すなわち、正位置に戻す)ことにより、バルコニーユニット側胴差片15を上記隙間に嵌め込むことが比較的容易になる。   On the other hand, in this embodiment, when the balcony unit side trunk piece 15 is fitted into the gap between the pair of housing side trunk pieces 21a and 21b, first, the manipulated beam 22a is tilted to perform the manipulation. The balcony unit side trunk piece 15 is fixed to one end portion of the beam 22a in the longitudinal direction. Thereby, it becomes possible to avoid the danger of the collision mentioned above. And about the to-be-operated beam 22a of the state to which the balcony unit side trunk piece 15 was fixed, the attitude | position is returned to the original attitude | position (namely, it returns to a normal position), The balcony unit side trunk piece 15 is made into the above-mentioned It becomes relatively easy to fit in the gap.

さらに、本実施形態では、被操作梁22aの姿勢を第一姿勢から第二姿勢に切り替えるにあたり、被操作梁22aの長手方向一端部を持ち上げることとし、また、上記の姿勢を第二姿勢から元の第一姿勢に戻すにあたり、持ち上げた長手方向一端部を自重にて落下させることとしている。このような単純な手順により、本実施形態では、バルコニーユニット10の組み付け作業をより容易に行うことが可能となる。   Furthermore, in the present embodiment, when switching the posture of the operated beam 22a from the first posture to the second posture, one end in the longitudinal direction of the operated beam 22a is lifted, and the above posture is restored from the second posture. In returning to the first posture, the lifted one end in the longitudinal direction is dropped by its own weight. According to such a simple procedure, in the present embodiment, it is possible to more easily perform the assembling work of the balcony unit 10.

<<バルコニーユニット10を吊るための治具30について>>
前述したように、バルコニーユニット10を建物本体2の躯体20に組み付けるにあたり、該バルコニーユニット10をクレーン等によって吊り上げる必要がある。この際、バルコニーユニット10の各部に損傷を与えず、かつ、安定した吊り姿勢を維持することが求められる。また、バルコニーユニット10の吊り姿勢については、比較的容易に調整できることが望ましい。本実施形態では、上記の課題を解決するために、以降に説明する治具30を用いたバルコニーユニット10の吊り方法を採用している。以下、当該治具30の構成例、及び、当該治具30を用いたバルコニーユニット10の吊り方法について説明する。
<< About the jig 30 for hanging the balcony unit 10 >>
As described above, when the balcony unit 10 is assembled to the housing 20 of the building body 2, the balcony unit 10 needs to be lifted by a crane or the like. At this time, it is required to maintain a stable hanging posture without damaging each part of the balcony unit 10. Moreover, it is desirable that the hanging posture of the balcony unit 10 can be adjusted relatively easily. In the present embodiment, in order to solve the above-described problem, a method of hanging the balcony unit 10 using the jig 30 described below is employed. Hereinafter, a configuration example of the jig 30 and a method of hanging the balcony unit 10 using the jig 30 will be described.

<<治具30の構成例について>>
先ず、本実施形態に係る治具30に関して、その構成例を図10〜図12に基づいて説明する。図10は、治具30の正面図であり、図11は、図10におけるY−Y断面図である。図12は、治具30が取り付けられた状態のバルコニーユニット10を示す図である。図11には後述する支持プレート32の長手方向が、図12にはバルコニーユニット10の前後方向が、それぞれ矢印にて示されている。なお、以下の説明では、支持プレート32の長手方向において係合部31が取り付けられている側を固定端側とも呼び、その反対側を自由端側とも呼ぶ。
<< Regarding Configuration Example of Jig 30 >>
First, a configuration example of the jig 30 according to the present embodiment will be described with reference to FIGS. 10 is a front view of the jig 30, and FIG. 11 is a YY cross-sectional view in FIG. FIG. 12 is a diagram illustrating the balcony unit 10 with the jig 30 attached thereto. 11, the longitudinal direction of the support plate 32 to be described later is indicated by arrows, and in FIG. 12, the longitudinal direction of the balcony unit 10 is indicated by arrows. In the following description, the side on which the engaging portion 31 is attached in the longitudinal direction of the support plate 32 is also called a fixed end side, and the opposite side is also called a free end side.

本実施形態の治具30は、建物本体2の躯体20に組み付けられるバルコニーユニット10を吊るためのものであり、図10および図11に示すように、当該治具30を正面から見たときに、係合部31、支持プレート32、吊り位置調整機構33及び駆動機構34を左右それぞれに備えている(換言すると、係合部31、支持プレート32、吊り位置調整機構33及び駆動機構34をそれぞれ一組ずつ備えている)。また、左右の吊り位置調整機構33の間には、当該左右の吊り位置調整機構33を連結している連結部材35が備えられている。以下、治具30の各構成要素について説明する。なお、一組ずつ備えられている構成要素(すなわち、係合部31、支持プレート32、吊り位置調整機構33及び駆動機構34)については、左右対称の構成となっているので、以下では一方の構成についてのみ説明するものとする。   The jig 30 of the present embodiment is for suspending the balcony unit 10 assembled to the housing 20 of the building body 2, and as shown in FIGS. 10 and 11, when the jig 30 is viewed from the front. , The engaging portion 31, the support plate 32, the suspension position adjustment mechanism 33, and the drive mechanism 34 are provided on the left and right sides (in other words, the engagement portion 31, the support plate 32, the suspension position adjustment mechanism 33, and the drive mechanism 34 are provided respectively). One set each). Further, a connecting member 35 that connects the left and right suspension position adjustment mechanisms 33 is provided between the left and right suspension position adjustment mechanisms 33. Hereinafter, each component of the jig 30 will be described. In addition, about the component (namely, the engaging part 31, the support plate 32, the suspension position adjustment mechanism 33, and the drive mechanism 34) provided one by one, since it is a right-and-left symmetrical structure, below, Only the configuration will be described.

係合部31は、本実施形態の治具30をバルコニーユニット10に取り付ける際にバルコニーユニット側胴差片15と係合するものである。この係合部31の形状は、上方から見たときに略矩形状であり、側方から見たときに横向きJの字状となっている。すなわち、本実施形態の係合部31は、鉤状となっており、バルコニーユニット側胴差片15に引掛けることが可能である。   The engaging part 31 engages with the balcony unit-side trunk piece 15 when the jig 30 of this embodiment is attached to the balcony unit 10. The shape of the engaging portion 31 is a substantially rectangular shape when viewed from above, and is a laterally J-shaped when viewed from the side. That is, the engaging portion 31 of the present embodiment has a bowl shape and can be hooked on the balcony unit side trunk piece 15.

より具体的に説明すると、本実施形態のバルコニーユニット側胴差片15は、前述したように中央部にH型鋼を有し、2つのフランジ部(すなわち、上側フランジ部15a及び下側フランジ部15b)がバルコニーユニット10の上下方向に並ぶようにバルコニーユニット10に備えられている。また、バルコニーユニット側胴差片15は、バルコニーユニット10の後端部に備えられている。かかるバルコニーユニット側胴差片15に対して、係合部31は、図13に示すように、バルコニーユニット側胴差片15たるH型鋼に備えられた上側フランジ部15aの端部に引掛かることにより、H型鋼と係合するようになる。なお、係合部31とバルコニーユニット側胴差片15との係合状態を保持する上で、係合部31とバルコニーユニット側胴差片15とをボルト止めすることとしてもよい。図13は、係合部31と上側フランジ部15aとの係合状態を示す図である。   More specifically, the balcony unit side trunk piece 15 of the present embodiment has an H-shaped steel at the center as described above, and has two flange portions (that is, an upper flange portion 15a and a lower flange portion 15b). ) Are arranged in the balcony unit 10 so as to be arranged in the vertical direction of the balcony unit 10. Moreover, the balcony unit side trunk piece 15 is provided at the rear end of the balcony unit 10. As shown in FIG. 13, the engaging portion 31 is hooked to the end portion of the upper flange portion 15 a provided in the H-shaped steel as the balcony unit side trunk piece 15 with respect to the balcony unit side trunk piece 15. As a result, the H-shaped steel is engaged. In addition, it is good also as bolting the engaging part 31 and the balcony unit side trunk | drum difference piece 15 in maintaining the engagement state of the engaging part 31 and the balcony unit side trunk | drum differential piece 15. FIG. FIG. 13 is a diagram showing an engaged state between the engaging portion 31 and the upper flange portion 15a.

支持プレート32は、その長手方向の一端部(固定端部)において上記係合部31を支持している金属板であり、支持部材の一例である。この支持プレート32は、側面から見たときに略横向きL字状となっており、前記係合部31の上端面から立ち上がった後に略垂直に曲がって延出している。なお、本実施形態では、図10に示すように、係合部31の上端面のうち、支持プレート32が立設されている部分の両脇に、当該支持プレート32の強度を補強するための補強リブ39が立設されている。   The support plate 32 is a metal plate that supports the engaging portion 31 at one end portion (fixed end portion) in the longitudinal direction, and is an example of a support member. The support plate 32 is substantially L-shaped when viewed from the side, and extends from the upper end surface of the engaging portion 31 so as to bend substantially vertically. In the present embodiment, as shown in FIG. 10, the strength of the support plate 32 is reinforced on both sides of the portion of the upper end surface of the engaging portion 31 where the support plate 32 is erected. Reinforcing ribs 39 are erected.

そして、係合部31がバルコニーユニット側胴差片15に係合されることにより本実施形態の治具30がバルコニーユニット10に取り付けられると、支持プレート32の長手方向は、バルコニーユニット10の前後方向に沿い、かつ、バルコニーユニット側胴差片15の長手方向と略直交するようになる(図12参照)。   And when the jig | tool 30 of this embodiment is attached to the balcony unit 10 by engaging the engaging part 31 with the balcony unit side trunk | drum differential piece 15, the longitudinal direction of the support plate 32 is the front and back of the balcony unit 10. Along the direction, it becomes substantially orthogonal to the longitudinal direction of the balcony unit side trunk piece 15 (see FIG. 12).

吊り位置調整機構33は、治具30が取り付けられたバルコニーユニット10を吊る際の吊り位置を規定するものである。さらに、吊り位置調整機構33は、治具30がバルコニーユニット10に取り付けられた状態において、支持プレート32の長手方向に沿って移動することが可能である。この移動により、当該長手方向において前記吊り位置を調整することが可能になる。すなわち、吊り位置調整機構33は、治具30が取り付けられたバルコニーユニット10を吊る際の吊り位置を、支持プレート32の長手方向(換言すると、バルコニーユニット10の前後方向)において調整するためのものである。   The suspension position adjusting mechanism 33 defines a suspension position when the balcony unit 10 to which the jig 30 is attached is suspended. Furthermore, the suspension position adjusting mechanism 33 can move along the longitudinal direction of the support plate 32 in a state where the jig 30 is attached to the balcony unit 10. By this movement, the suspension position can be adjusted in the longitudinal direction. That is, the suspension position adjusting mechanism 33 is for adjusting the suspension position when the balcony unit 10 to which the jig 30 is attached is suspended in the longitudinal direction of the support plate 32 (in other words, the front-rear direction of the balcony unit 10). It is.

吊り位置調整機構33は、図10に示すように、連結部材35の両端に配置されており、スライド部材36と被固定部37とシャックル取付け部38とを有する。より詳しく説明すると、連結部材35は、支持プレート32の長手方向と交差する方向に長い梁状の金属体であり、その両端には、スライド部材36、被固定部37及びシャックル取付け部38(すなわち、吊り位置調整機構33)が一組ずつ備えられている。なお、連結部材35は、その長さが調整できるように伸縮自在の構成であってもよい。   As shown in FIG. 10, the suspension position adjusting mechanism 33 is disposed at both ends of the connecting member 35, and includes a slide member 36, a fixed portion 37, and a shackle mounting portion 38. More specifically, the connecting member 35 is a beam-like metal body that is long in the direction intersecting the longitudinal direction of the support plate 32, and has a slide member 36, a fixed portion 37, and a shackle mounting portion 38 (that is, a shackle mounting portion 38) The suspension position adjusting mechanism 33) is provided one by one. In addition, the connection member 35 may be configured to be stretchable so that the length thereof can be adjusted.

スライド部材36は、正面から見たときにU字状の金属製枠体であり、一対の側壁36aと底壁36bとを有する。スライド部材36の上端部には、被固定部37が一対の側壁36aの間に挟み込まれた状態で固定されている。また、スライド部材36の中央部には、上述の支持プレート32が一対の側壁36aの間に挟み込まれた状態で配置されている。そして、スライド部材36は、支持プレート32に案内されながら、当該支持プレート32の長手方向に沿ってスライドすることが可能である。なお、側壁36aと底壁36bと支持プレート32により仕切られる空間には、ガイドローラ36cが配置されている。このガイドローラ36cは、その周面が支持プレート32の下端面に摺擦するように回転し、スライド部材36の移動を補助する役目を担っている。   The slide member 36 is a U-shaped metal frame when viewed from the front, and has a pair of side walls 36a and a bottom wall 36b. A fixed portion 37 is fixed to the upper end portion of the slide member 36 while being sandwiched between a pair of side walls 36a. Further, the above-described support plate 32 is disposed in the center of the slide member 36 in a state of being sandwiched between the pair of side walls 36a. The slide member 36 can slide along the longitudinal direction of the support plate 32 while being guided by the support plate 32. A guide roller 36c is disposed in a space partitioned by the side wall 36a, the bottom wall 36b, and the support plate 32. The guide roller 36 c rotates so that its peripheral surface rubs against the lower end surface of the support plate 32, and plays a role of assisting the movement of the slide member 36.

被固定部37は、略三角形状の金属板であり、上記のスライド部材36に取り付けられており、かつ、連結部材35の端部にボルト止めにより固定されている。シャックル取付け部38は、略矩形状の金属板であり、上記被固定部37の上端部にボルト止めにより固定されている。そして、このシャックル取付け部38には、シャックル50(例えば、図14(B)参照)を取り付けるために、取付け穴38aが形成されている。当該シャックル50は、バルコニーユニット10を吊る際に用いる吊具の一例である。そして、上記の取付け穴38aの形成位置が上述の吊り位置となる。   The fixed portion 37 is a substantially triangular metal plate, is attached to the slide member 36, and is fixed to the end of the connecting member 35 by bolting. The shackle attachment portion 38 is a substantially rectangular metal plate, and is fixed to the upper end portion of the fixed portion 37 by bolting. An attachment hole 38a is formed in the shackle attachment portion 38 in order to attach a shackle 50 (for example, see FIG. 14B). The shackle 50 is an example of a hanging tool used when hanging the balcony unit 10. And the formation position of said attachment hole 38a turns into the above-mentioned hanging position.

以上のような構成の吊り位置調整機構33は、シャックル取付け部38に形成された取付け穴38aを備えるとともに、支持プレート32の長手方向に沿って移動することが可能である。具体的には、スライド部材36が支持プレート32の長手方向に沿ってスライドすることにより、当該スライド部材36と被固定部37とシャックル取付け部38が一体的に支持プレート32の長手方向に沿って移動する。これにより、支持プレート32に対する吊り位置調整機構33の相対位置を変化させることが可能となる。つまり、取付け穴38aの形成位置、すなわち、吊り位置を支持プレート32の長手方向に変化させることが可能となる。   The suspension position adjustment mechanism 33 having the above-described configuration includes an attachment hole 38 a formed in the shackle attachment portion 38 and can move along the longitudinal direction of the support plate 32. Specifically, when the slide member 36 slides along the longitudinal direction of the support plate 32, the slide member 36, the fixed portion 37, and the shackle mounting portion 38 are integrally formed along the longitudinal direction of the support plate 32. Moving. Thereby, the relative position of the suspension position adjustment mechanism 33 with respect to the support plate 32 can be changed. That is, the formation position of the attachment hole 38 a, that is, the hanging position can be changed in the longitudinal direction of the support plate 32.

駆動機構34は、吊り位置調整機構33を支持プレート32の長手方向に沿って移動させるためのものであり、図10及び図11に示すように、回転ねじ体としてのボールねじ34aとナット34bとを有する。   The drive mechanism 34 is for moving the suspension position adjusting mechanism 33 along the longitudinal direction of the support plate 32. As shown in FIGS. 10 and 11, a ball screw 34a and a nut 34b as a rotating screw body are provided. Have

ボールねじ34aは、支持プレート32の上方に配置され、支持プレート32の長手方向一端(自由端側の端)から長手方向他端(固定端側の端)まで亘る長さを有する。このボールねじ34aは、中心軸方向が支持プレート32の長手方向に沿った状態で支持プレート32に回転自在に支持されている。そして、ボールねじ34aの中心軸方向一端部(支持プレート32の長手方向において固定端側の端部)には、操作者によって操作される被操作部34cが形成されている。この被操作部34cが例えばインパクトレンチを用いて操作されることにより、上記のボールねじ34aがその中心軸を中心に回転する。なお、ボールねじ34aは、正転方向及び反転方向の何れの方向にも回転可能である。   The ball screw 34a is disposed above the support plate 32 and has a length extending from one end in the longitudinal direction (end on the free end side) of the support plate 32 to the other end in the longitudinal direction (end on the fixed end side). The ball screw 34 a is rotatably supported by the support plate 32 in a state where the central axis direction is along the longitudinal direction of the support plate 32. An operated portion 34c that is operated by an operator is formed at one end in the central axis direction of the ball screw 34a (an end on the fixed end side in the longitudinal direction of the support plate 32). When the operated portion 34c is operated using, for example, an impact wrench, the ball screw 34a rotates about its central axis. The ball screw 34a can be rotated in either the forward direction or the reverse direction.

ナット34bは、上記のボールねじ34aを挿通させるための貫通穴を有している。このナット34bは、当該貫通穴にてボールねじ34aが挿入されてボールねじ34aに螺合した状態で、上述のスライド部材36に固定されている。具体的に説明すると、図11に示すように、ナット34bは、支持プレート32の上方位置にあり、スライド部材36が備える一対の側壁36aの間に挟まれた位置にて側壁36aに固定されている。   The nut 34b has a through hole through which the ball screw 34a is inserted. The nut 34b is fixed to the above-described slide member 36 in a state in which the ball screw 34a is inserted into the through hole and screwed into the ball screw 34a. Specifically, as shown in FIG. 11, the nut 34 b is located above the support plate 32 and is fixed to the side wall 36 a at a position sandwiched between a pair of side walls 36 a included in the slide member 36. Yes.

そして、ナット34bは、当該ナット34bに挿入されたボールねじ34aが回転すると(より正確にはナット34bに対して相対的に回転すると)、ボールねじ34aの中心軸に沿って移動する。なお、上述したように、ボールねじ34aは正転方向及び反転方向の何れにも回転可能であり、ボールねじ34aが正転方向に回転すると、ナット34bは中心軸方向の一端から他端に向かう向きに移動し、ボールねじ34aが反転方向に回転すると、他端から一端に向かう向きに移動する。なお、ナット34bがボールねじ34aから脱落するのを防止する上で、ボールねじ34aの端部に係止部材(ストッパ)34dが設けられていることが望ましい。   The nut 34b moves along the central axis of the ball screw 34a when the ball screw 34a inserted into the nut 34b rotates (more precisely, when the ball 34a rotates relative to the nut 34b). As described above, the ball screw 34a can rotate in either the forward direction or the reverse direction, and when the ball screw 34a rotates in the forward direction, the nut 34b moves from one end to the other end in the central axis direction. When the ball screw 34a rotates in the reverse direction, it moves in the direction from the other end to the one end. In order to prevent the nut 34b from falling off the ball screw 34a, it is desirable that a locking member (stopper) 34d is provided at the end of the ball screw 34a.

以上のような構成の駆動機構34では、ボールねじ34aの被操作部34cが操作されることにより、ボールねじ34aがナット34bに対して相対的に回転し、これにより、当該ナット34bがボールねじ34aの中心軸方向に沿って移動する。これに伴って、ナット34bが固定されたスライド部材36が支持プレート32の長手方向に沿って移動する。この結果、スライド部材36を含む吊り位置調整機構33全体が上記長手方向に沿って移動するようになる(換言すると、支持プレート32に対する吊り位置調整機構33の相対位置が変化するようになる)。そして、上述したように、吊り位置調整機構33の移動により、最終的に吊り位置が支持プレート32の長手方向に沿って調整されることになる。   In the drive mechanism 34 configured as described above, the operated portion 34c of the ball screw 34a is operated, whereby the ball screw 34a rotates relative to the nut 34b, whereby the nut 34b is moved to the ball screw. It moves along the direction of the central axis of 34a. Accordingly, the slide member 36 to which the nut 34 b is fixed moves along the longitudinal direction of the support plate 32. As a result, the entire suspension position adjustment mechanism 33 including the slide member 36 moves along the longitudinal direction (in other words, the relative position of the suspension position adjustment mechanism 33 with respect to the support plate 32 changes). As described above, the suspension position is finally adjusted along the longitudinal direction of the support plate 32 by the movement of the suspension position adjustment mechanism 33.

<<治具30を用いたバルコニーユニット10の吊り方法について>>
次に、本実施形態のバルコニーユニット10を、上記構成の治具30を用いて吊る吊り方法について説明する。当該吊り方法は、以下に説明する吊り作業において実践される。以降、図14(A)及び図14(B)を参照しながら、当該吊り作業について説明する。図14(A)及び図14(B)は、治具30を用いたバルコニーユニット10の吊り作業に関する手順を示す図である。
<< About the hanging method of the balcony unit 10 using the jig 30 >>
Next, a hanging method for hanging the balcony unit 10 of the present embodiment using the jig 30 having the above-described configuration will be described. The suspension method is practiced in the suspension work described below. Hereinafter, the suspension work will be described with reference to FIGS. 14 (A) and 14 (B). FIG. 14A and FIG. 14B are diagrams showing a procedure related to the hanging work of the balcony unit 10 using the jig 30.

バルコニーユニット10の吊り作業を行うにあたり、先ず、図12に示す状態となるように、上述した治具30をバルコニーユニット10に取り付ける。具体的に説明すると、左右にそれぞれ設けられた支持プレート32の長手方向がバルコニーユニット10の前後方向に沿うように、治具30の係合部31をバルコニーユニット側胴差片15に係合させる。より詳しく説明すると、前述したように、本実施形態の係合部31は、鉤状であり、バルコニーユニット側胴差片15の中央部に設けられたH型鋼の、上側フランジ部15aの端部に引掛けて当該H型鋼に係合される。この係合作業が完了した時点で、支持プレート32の長手方向がバルコニーユニット10の前後方向に沿うように、治具30がバルコニーユニット10に取り付けられることになる。この際、支持プレート32を含む治具30の略全体がバルコニーユニット10の内側(バルコニーユニット10内の空間Sの中)に配置されるようになる(図12参照)。   When the balcony unit 10 is suspended, first, the jig 30 described above is attached to the balcony unit 10 so as to be in the state shown in FIG. More specifically, the engaging portion 31 of the jig 30 is engaged with the balcony unit-side trunk piece 15 so that the longitudinal direction of the support plates 32 provided on the left and right sides is along the front-rear direction of the balcony unit 10. . More specifically, as described above, the engaging portion 31 of the present embodiment has a bowl shape, and is an end portion of the upper flange portion 15a of the H-shaped steel provided in the central portion of the balcony unit side trunk piece 15. Is engaged with the H-shaped steel. When this engagement operation is completed, the jig 30 is attached to the balcony unit 10 so that the longitudinal direction of the support plate 32 is along the front-rear direction of the balcony unit 10. At this time, substantially the entire jig 30 including the support plate 32 is disposed inside the balcony unit 10 (in the space S in the balcony unit 10) (see FIG. 12).

なお、バルコニーユニット10への治具30の取付け作業は、通常、当該バルコニーユニット10を架台51の上で静置させた状態で行われる。なお、当該取付け作業に際して、上述のセットボルト16を、バルコニーユニット側胴差片15の下端から幾分突出した状態でバルコニーユニット側胴差片15に取り付けることとしてもよい。   In addition, the attachment operation | work of the jig | tool 30 to the balcony unit 10 is normally performed in the state which left the said balcony unit 10 on the mount frame 51. FIG. In addition, it is good also as attaching the above-mentioned set bolt 16 to the balcony unit side trunk piece 15 in the state which protruded from the lower end of the balcony unit side trunk piece 15 somewhat in the case of the said attachment operation | work.

次に、治具30の左右にそれぞれ設けられた吊り位置調整機構33の、シャックル取付け部38にシャックル50を取り付ける。すなわち、本実施形態では、バルコニーユニット10を二点吊り方式で吊り上げることになる。換言すると、本実施形態では、治具30が取り付けられたバルコニーユニット10を吊る際の吊り位置が、バルコニーユニット10の幅方向において2箇所存在することになる。   Next, the shackle 50 is attached to the shackle attachment portion 38 of the suspension position adjusting mechanism 33 provided on each of the left and right sides of the jig 30. That is, in this embodiment, the balcony unit 10 is lifted by a two-point hanging method. In other words, in this embodiment, there are two hanging positions in the width direction of the balcony unit 10 when hanging the balcony unit 10 to which the jig 30 is attached.

その後、各吊り位置調整機構33に対応する駆動機構34を用いて、当該各吊り位置調整機構33の位置、すなわち、各吊り位置を調整する。具体的に説明すると、インパクトレンチによりボールねじ34aを回転させて、ナット34bをボールねじ34aの中心軸方向に沿って移動させる。これにより、当該ナット34bが固定されているスライド部材36と、被固定部材37と、シャックル取付け部38とが一体的に支持プレート32の長手方向に沿って移動するようになる。この結果、吊り位置が、支持プレート32の長手方向、すなわち、バルコニーユニット10の前後方向において調整されることとなる。   Thereafter, using the drive mechanism 34 corresponding to each suspension position adjustment mechanism 33, the position of each suspension position adjustment mechanism 33, that is, each suspension position is adjusted. More specifically, the ball screw 34a is rotated by an impact wrench, and the nut 34b is moved along the central axis direction of the ball screw 34a. As a result, the slide member 36 to which the nut 34 b is fixed, the fixed member 37, and the shackle mounting portion 38 are integrally moved along the longitudinal direction of the support plate 32. As a result, the hanging position is adjusted in the longitudinal direction of the support plate 32, that is, in the front-rear direction of the balcony unit 10.

以上のような吊り位置の調整作業を行うことにより、バルコニーユニット10を吊り上げたときの吊り姿勢を調整することが可能になる。分かり易く説明すると、吊り位置の調整により、当該吊り位置とバルコニーユニット10の重心位置(正確には、治具30が取り付けられた状態のバルコニーユニット10の重心位置)との相対位置関係が変化する。この結果、バルコニーユニット10を吊り上げたときの吊り姿勢を調整することが可能となる。特に、本実施形態では、吊り位置をバルコニーユニット10の前後方向において調整することから、上記の吊り姿勢を調整することは、吊られた状態にあるバルコニーユニット10の傾き(より詳しくは、水平方向に対するバルコニーユニット10の前後方向の傾き)を調整することになる。   By performing the adjustment operation of the hanging position as described above, it is possible to adjust the hanging posture when the balcony unit 10 is lifted. To explain in an easy-to-understand manner, the relative positional relationship between the suspension position and the gravity center position of the balcony unit 10 (more precisely, the gravity center position of the balcony unit 10 with the jig 30 attached) is changed by adjusting the suspension position. . As a result, it is possible to adjust the hanging posture when the balcony unit 10 is lifted. In particular, in the present embodiment, since the suspension position is adjusted in the front-rear direction of the balcony unit 10, the above-described suspension posture is adjusted by the inclination of the balcony unit 10 in a suspended state (more specifically, in the horizontal direction). The inclination of the balcony unit 10 with respect to the front / rear direction) is adjusted.

なお、上記吊り位置の調整は、一先ず、バルコニーユニット10が架台51上に静置している段階で大まかに行われる。この段階の調整は、いわゆる地切りの段階(バルコニーユニット10を吊り上げて架台51から離間させる段階)で、バルコニーユニット10の吊り姿勢が所定の姿勢に極力近づくように行われる。その後、シャックル50にフック52を掛けて、治具30を介してバルコニーユニット10を吊り上げる。そして、地切り後に、上記と同様の手順にて吊り位置を微調整する。この微調整により、バルコニーユニット10の吊り姿勢は、その前端が後端よりもセットボルト16の突出量に応じた分だけ上方に位置するように調整される(図7(B)参照)。   The adjustment of the hanging position is roughly performed at the stage where the balcony unit 10 is still on the gantry 51. The adjustment at this stage is performed so that the hanging posture of the balcony unit 10 approaches a predetermined posture as much as possible at the so-called ground cutting stage (the stage where the balcony unit 10 is lifted and separated from the gantry 51). Thereafter, the hook 52 is hung on the shackle 50 and the balcony unit 10 is lifted through the jig 30. After the ground cutting, the hanging position is finely adjusted in the same procedure as described above. By this fine adjustment, the hanging posture of the balcony unit 10 is adjusted so that the front end thereof is positioned above the rear end by an amount corresponding to the protruding amount of the set bolt 16 (see FIG. 7B).

上記の如くバルコニーユニット10の吊り姿勢が調整されることにより、バルコニーユニット10の組み付け作業の項で説明したように、バルコニーユニット10の傾き具合と同程度に傾けられた被操作梁22aに対して、バルコニーユニット側胴差片15を円滑に固定することが可能になる。   By adjusting the hanging posture of the balcony unit 10 as described above, as described in the section of the assembling work of the balcony unit 10, the operated beam 22a tilted to the same degree as the balcony unit 10 is tilted. The balcony unit side trunk piece 15 can be fixed smoothly.

<<本実施形態の治具30及び当該治具30を用いたバルコニーユニット10の吊り方法の有効性について>>
本実施形態の治具30及び当該治具30を用いたバルコニーユニット10の吊り方法により、バルコニーユニット10の吊り位置の調整を簡易に行えるようになる。この結果、バルコニーユニット10の吊り作業を適切に行うことが可能になる。
<< Effectiveness of the jig 30 of this embodiment and the method of hanging the balcony unit 10 using the jig 30 >>
The hanging position of the balcony unit 10 can be easily adjusted by the jig 30 of the present embodiment and the method of hanging the balcony unit 10 using the jig 30. As a result, the balcony unit 10 can be properly suspended.

具体的に説明すると、従来の治具では、上記吊り位置を調整するために、例えば、バルコニーユニットに対する治具の取付け位置を切り替えることとしていた。この結果、吊り位置の調整作業に手間を要し、また、バルコニーユニットの各部を傷付けるおそれがあった。さらに、従来の治具を用いてバルコニーユニットを吊り上げた場合、上記の如く治具の取付け位置を切り替えて吊り位置を調整することから、バルコニーユニットを吊り上げている間に吊り位置を調整することが困難であった。   If it demonstrates concretely, in the conventional jig | tool, in order to adjust the said hanging position, it was supposed to switch the attachment position of the jig | tool with respect to a balcony unit, for example. As a result, it takes time to adjust the hanging position, and there is a risk of damaging each part of the balcony unit. Furthermore, when the balcony unit is lifted using a conventional jig, the hanging position is adjusted by switching the mounting position of the jig as described above, so that the hanging position can be adjusted while the balcony unit is lifted. It was difficult.

これに対して、本実施形態の治具30であれば、治具30側に設けられている吊り位置調整機構33を支持プレート32の長手方向に沿って移動させることにより、当該吊り位置を調整することが可能である。これにより、従来と比較して、吊り位置の調整を簡易に行うことが可能となる。また、かかる構成により、バルコニーユニット10を吊り上げている間にも吊り位置の調整を行うことが可能となる。さらに、本実施形態の治具30は、バルコニーユニット10に設けられたバルコニーユニット側胴差片15に係合部31を係合させることで取り付けられるため、バルコニーユニット10の各部の損傷を回避することも可能である。   On the other hand, in the case of the jig 30 of the present embodiment, the suspension position is adjusted by moving the suspension position adjustment mechanism 33 provided on the jig 30 side along the longitudinal direction of the support plate 32. Is possible. Thereby, compared with the past, it becomes possible to easily adjust the hanging position. Also, with this configuration, it is possible to adjust the hanging position while the balcony unit 10 is being lifted. Furthermore, since the jig 30 according to the present embodiment is attached by engaging the engagement unit 31 with the balcony unit-side trunk piece 15 provided in the balcony unit 10, damage to each part of the balcony unit 10 is avoided. It is also possible.

また、本実施形態の治具30は、連結部材35の両端に、係合部31と支持プレート32と吊り位置調整機構33と駆動機構34とを、それぞれ一組ずつ備えており、一方の吊り位置調整機構33と他方の吊り位置調整機構33には、それぞれ、シャックル50を取り付けるための取付け穴38aが形成されていることとした。しかし、かかる構成に限定されるものではなく、例えば、係合部31と支持プレート32と吊り位置調整機構33と駆動機構34とを一つずつ有する構成(すなわち、一点吊り形式の構成)であってもよい。ただし、本実施形態の構成であれば、バルコニーユニット10を二点吊りすることが可能となり、バルコニーユニット10の吊り姿勢を安定させることが可能になる。   Further, the jig 30 of the present embodiment is provided with one set of each of the engaging portion 31, the support plate 32, the suspension position adjusting mechanism 33, and the drive mechanism 34 at both ends of the connecting member 35. The position adjustment mechanism 33 and the other suspension position adjustment mechanism 33 are each provided with an attachment hole 38a for attaching the shackle 50. However, the present invention is not limited to such a configuration. For example, the configuration includes one engagement portion 31, one support plate 32, one suspension position adjustment mechanism 33, and one drive mechanism 34 (that is, a one-point suspension configuration). May be. However, with the configuration of the present embodiment, the balcony unit 10 can be suspended at two points, and the suspension posture of the balcony unit 10 can be stabilized.

また、本実施形態の治具30では、各係合部31が鉤状となっていることとした。そして、本実施形態のように、バルコニーユニット側胴差片15がH型鋼を有するときに、各係合部31は、当該H型鋼のフランジ部15a、15bの端部に引掛かることによって当該H型鋼に係合することとなっている。しかし、係合部31は上記の形状に限定されるものでなく、バルコニーユニット側胴差片15に係合可能である限り、如何なる形状であってもよい。ただし、本実施形態の構成であれば、バルコニーユニット側胴差片15に係合部31を容易に係合させ、かつ、その係合状態を安定させることが可能となる。   Moreover, in the jig | tool 30 of this embodiment, it was decided that each engaging part 31 was hook shape. And when the balcony unit side trunk | drum 15 has H type steel like this embodiment, each engaging part 31 is said H by hooking on the edge part of the flange parts 15a and 15b of the said H type steel. Engage with the steel. However, the engaging portion 31 is not limited to the above-described shape, and may have any shape as long as it can engage with the balcony unit side trunk piece 15. However, if it is the structure of this embodiment, it will become possible to engage the engagement part 31 with the balcony unit side trunk | drum difference piece 15, and to stabilize the engagement state.

さらに、本実施形態の治具30は、吊り位置調整機構33を支持プレート32の長手方向に沿って移動させるための駆動機構34を有することとした。また、当該駆動機構34は、ボールねじ34aとナット34bを有し、ボールねじ34aは、その末端部に形成された被操作部34cが操作されることにより、支持プレート32の長手方向に沿った中心軸を中心にして回転し、ナット34bは、ボールねじ34aの回転によってその中心軸方向に沿って移動する。これにより、ナット34bが固定されたスライド部材36が支持プレート32の長手方向に沿ってスライドし、当該スライド部材36を含む吊り位置調整機構33全体が、前記長手方向に沿って移動することとした。   Furthermore, the jig 30 of the present embodiment has a drive mechanism 34 for moving the suspension position adjusting mechanism 33 along the longitudinal direction of the support plate 32. The drive mechanism 34 has a ball screw 34a and a nut 34b. The ball screw 34a is operated along the longitudinal direction of the support plate 32 by operating an operated portion 34c formed at the end thereof. The nut 34b rotates along the central axis, and the nut 34b moves along the direction of the central axis by the rotation of the ball screw 34a. Thereby, the slide member 36 to which the nut 34b is fixed slides along the longitudinal direction of the support plate 32, and the entire suspension position adjusting mechanism 33 including the slide member 36 moves along the longitudinal direction. .

しかし、かかる構成に限定されるものではなく、吊り位置調整機構33を支持プレート32の長手方向に沿って移動させるものである限り、上記の構成とは異なる他の駆動機構34であってもよい。また、駆動機構34が治具30の構成要素でなくともよい。ただし、本実施形態の吊り位置調整機構33であれば、吊り位置の調整をより容易に行うことが可能になる。   However, the present invention is not limited to this configuration, and may be another drive mechanism 34 different from the above configuration as long as the suspension position adjustment mechanism 33 is moved along the longitudinal direction of the support plate 32. . Further, the drive mechanism 34 may not be a component of the jig 30. However, the suspension position adjustment mechanism 33 of the present embodiment makes it possible to adjust the suspension position more easily.

詳しく説明すると、本実施形態では、比較的簡易な操作(具体的には、ボールねじ34aの被操作部34cを操作すること)により、吊り位置調整機構33の移動、すなわち、吊り位置の調整が行える。さらに、本実施形態の治具30をバルコニーユニット10に取り付けた状態において、被操作部34cは、バルコニーユニット10の後側を向くことになる。これにより、バルコニーユニット10を建物本体2の躯体20に組み付ける段階で、吊り位置の微調整(すなわち、バルコニーユニット10の吊り姿勢の微調整)が必要になれば、上記操作を建物本体2の内側から行うことも可能となる。   More specifically, in the present embodiment, movement of the suspension position adjusting mechanism 33, that is, adjustment of the suspension position is performed by a relatively simple operation (specifically, by operating the operated portion 34c of the ball screw 34a). Yes. Furthermore, in a state where the jig 30 of the present embodiment is attached to the balcony unit 10, the operated portion 34 c faces the rear side of the balcony unit 10. Accordingly, if fine adjustment of the hanging position (that is, fine adjustment of the hanging posture of the balcony unit 10) is required at the stage where the balcony unit 10 is assembled to the housing 20 of the building main body 2, the above operation is performed inside the building main body 2. It is also possible to do from.

<<その他の実施形態>>
上記の実施形態には、主として本発明のバルコニーユニット10及び当該バルコニーユニット10の組み付け方法、並びに、バルコニーユニット10を吊る際の治具30及び当該治具30を用いてバルコニーユニット10を吊る吊り方法について説明した。しかし、上記の実施形態は、本発明の理解を容易にするためのものであり、本発明を限定するものではない。本発明は、その趣旨を逸脱することなく、変更、改良され得ると共に、本発明にはその等価物が含まれることはもちろんである。また、上述した材質や形状等は本発明の効果を発揮させるための一例に過ぎず、本発明を限定するものではない。
<< Other Embodiments >>
In the above embodiment, the balcony unit 10 of the present invention, the method of assembling the balcony unit 10, the jig 30 for hanging the balcony unit 10, and the method of hanging the balcony unit 10 using the jig 30 are mainly described. Explained. However, the above embodiment is for facilitating the understanding of the present invention, and does not limit the present invention. The present invention can be changed and improved without departing from the gist thereof, and the present invention includes the equivalents thereof. Further, the above-described materials, shapes, and the like are merely examples for exhibiting the effects of the present invention, and do not limit the present invention.

また、本発明に係る治具30の用途は、バルコニーユニット10を吊ることに限定されるものではない。建物本体2の躯体20に組み付けられて建物1の一部をなす建物用ユニットであって、当該躯体20に設けられた躯体側胴差片21a(21b)と連結して当該躯体側胴差片21a(21b)とともに前記躯体20において胴差21として機能する建物用ユニット側胴差片を後端部に有する建物用ユニット、を吊る際にも上記治具30は有効である。上記の建物用ユニットの一例としては、バルコニーユニット10のほか、建物1の内装を構成するユニット(例えば、バス設備ユニットやキッチン設備ユニット)、建物1の居住面積を拡張するための拡張ユニットが挙げられる。   Moreover, the use of the jig 30 according to the present invention is not limited to suspending the balcony unit 10. A building unit that is assembled to the housing 20 of the building body 2 and forms a part of the building 1, and is connected to the housing-side trunk piece 21 a (21 b) provided in the housing 20. The jig 30 is also effective when suspending a building unit having a building unit side trunk piece that functions as the trunk difference 21 in the housing 20 together with 21a (21b). As an example of the above-mentioned unit for building, in addition to the balcony unit 10, a unit (for example, a bath equipment unit or a kitchen equipment unit) constituting the interior of the building 1 and an expansion unit for expanding the living area of the building 1 can be cited. It is done.

1 建物、2 建物本体、2a 建物本体側樋、3 バルコニー部、3a 床部、
3b 外壁部、3c 軒天部、3d 排水部、3e 排水ライン、3f 排水口、
10 バルコニーユニット、11 床ユニット、11a 床フレーム(フレーム)、
11b 床板、11c 床支持部、11d 中間アーム、11e 桁、
11f 外壁支持部材、11g 差込溝、12 外壁、12a 手摺、
13 軒天板、14 排水ユニット(排水機構)、14a 排水栓ソケット、
14b バルコニーユニット側樋、
15 バルコニーユニット側胴差片、15a 上側フランジ部、15b 下側フランジ部、
16 セットボルト、20 躯体、21 胴差、21a,21b 躯体側胴差片、
22 床梁、22a 被操作梁(梁部材)、23 受け部材、23a 係合穴、
30 治具、31 係合部、32 支持プレート(支持部材)、
33 吊り位置調整機構、
34 駆動機構、34a ボールねじ(回転ねじ体)、34b ナット、34c 被操作部、
34d 係止部材、35 連結部材、
36 スライド部材、36a 側壁、36b 底壁、36c ガイドローラ
37 被固定部、38 シャックル取付け部、38a 取付け穴、39 補強リブ、
40 単管、40a 支持部材、41 ジャッキ、41a 留め具、
50 シャックル(吊具)、51 架台、52 フック、S 空間
1 building, 2 building body, 2a side of building body, 3 balcony, 3a floor,
3b outer wall part, 3c eaves top part, 3d drainage part, 3e drainage line, 3f drainage port,
10 balcony unit, 11 floor unit, 11a floor frame (frame),
11b floor board, 11c floor support, 11d intermediate arm, 11e girder,
11f outer wall support member, 11g insertion groove, 12 outer wall, 12a handrail,
13 rooftops, 14 drainage unit (drainage mechanism), 14a drainage socket,
14b Balcony unit side,
15 balcony unit side torso piece, 15a upper flange part, 15b lower flange part,
16 set bolts, 20 housing, 21 torso, 21a, 21b torso side torso piece,
22 floor beam, 22a beam to be operated (beam member), 23 receiving member, 23a engagement hole,
30 jigs, 31 engaging parts, 32 support plates (support members),
33 Hanging position adjustment mechanism,
34 drive mechanism, 34a ball screw (rotary screw body), 34b nut, 34c operated part,
34d locking member, 35 connecting member,
36 slide member, 36a side wall, 36b bottom wall, 36c guide roller 37 fixed portion, 38 shackle mounting portion, 38a mounting hole, 39 reinforcing rib,
40 single tube, 40a support member, 41 jack, 41a fastener,
50 Shackles (51), 51 mounts, 52 hooks, S space

Claims (9)

建物本体の躯体に組み付け可能であり、該躯体に組み付けられたときに該躯体の外側に張り出すバルコニーユニットであって、
バルコニーユニット側胴差片を有し、
該バルコニーユニット側胴差片は、隙間を隔てて直線状に並ぶように前記躯体に設けられた一組の躯体側胴差片と連結して、該一組の躯体側胴差片とともに前記躯体において胴差として機能し、
前記バルコニーユニット側胴差片が前記隙間内に位置した状態で前記一組の躯体側胴差片の各々と連結されることによって、前記躯体に組み付けられることを特徴とするバルコニーユニット。
A balcony unit that can be assembled to the housing of the building body and projects outside the housing when assembled to the housing,
It has a balcony unit side torso piece,
The balcony unit side torso piece is connected to a pair of case side torso pieces provided on the case so as to be arranged in a straight line with a gap therebetween, and together with the set of torso side torso pieces, the casing Functions as a torso
The balcony unit is assembled to the casing by being connected to each of the pair of casing-side trunk differential pieces in a state where the balcony unit-side trunk differential piece is positioned in the gap.
請求項1に記載のバルコニーユニットにおいて、
該バルコニーユニットは、前記バルコニーユニット側胴差片と、該バルコニーユニット側胴差片が固定されたフレームとを有し、
前記バルコニーユニットが前記躯体に組み付けられる前の段階で、前記バルコニーユニットは、
前記フレームに支持される床板と、
該床板が支持される側とは反対側で前記フレームに支持される軒天板と、
前記床板の周囲に配置され、前記床板とともに前記バルコニーユニット内の空間を仕切る外壁と、
前記空間内の液状水を前記空間の外側に向けて排出するための排水機構とのうち、少なくともいずれか一つを更に有することを特徴とするバルコニーユニット。
The balcony unit according to claim 1,
The balcony unit has the balcony unit side torso piece and a frame to which the balcony unit side torso piece is fixed,
In a stage before the balcony unit is assembled to the housing, the balcony unit is
A floorboard supported by the frame;
An eaves top plate supported by the frame on the side opposite to the side on which the floor plate is supported;
An outer wall that is disposed around the floor board and partitions the space in the balcony unit together with the floor board;
The balcony unit further comprising at least one of a drainage mechanism for discharging liquid water in the space toward the outside of the space.
建物本体の躯体に組み付けたときに該躯体の外側に張り出すバルコニーユニットを、前記躯体に組み付ける組み付け方法であって、
隙間を隔てて直線状に並ぶように設けられた一組の躯体側胴差片を備えた前記躯体と、前記一組の躯体側胴差片と連結し、該一組の躯体側胴差片とともに前記躯体において胴差として機能するバルコニーユニット側胴差片を備えた前記バルコニーユニットと、
をそれぞれ準備する工程と、
前記一組の躯体側胴差片が並ぶ方向と交差するように前記躯体に設けられた梁部材、の長手方向の一端部が前記隙間に臨んだ状態にあるときに、前記梁部材を傾けて前記梁部材の姿勢を、前記長手方向が水平方向に沿った第一姿勢から、前記一端部が前記長手方向の他端部よりも上方に位置した第二姿勢に切り替える工程と、
前記姿勢が前記第二姿勢であるときに、前記一端部に前記バルコニーユニット側胴差片を固定する工程と、
前記一端部に前記バルコニーユニット側胴差片を固定した後に、前記一端部に固定された前記バルコニーユニット側胴差片が前記隙間内に位置して前記一組の躯体側胴差片に挟まれるように、前記姿勢を前記第二姿勢から前記第一姿勢に戻す工程と、
前記一組の躯体側胴差片に挟まれた前記バルコニーユニット側胴差片を、前記一組の躯体側胴差片の各々に連結する工程と、
を有することを特徴とするバルコニーユニットの組み付け方法。
A method for assembling a balcony unit that projects to the outside of the housing when assembled to the housing of the building body,
The housing provided with a set of housing side torso pieces provided so as to be arranged in a straight line with a gap, and the set of housing side torso pieces connected to the set of housing side torso pieces. And the balcony unit including a balcony unit side torso piece that functions as a torso in the casing,
Preparing each of the above,
When one end in the longitudinal direction of the beam member provided on the casing so as to intersect with the direction in which the pair of casing-side body differential pieces intersects, the beam member is inclined. Switching the posture of the beam member from a first posture in which the longitudinal direction is along the horizontal direction to a second posture in which the one end is positioned above the other end in the longitudinal direction;
When the posture is the second posture, fixing the balcony unit side trunk piece to the one end,
After fixing the balcony unit side trunk piece to the one end, the balcony unit side trunk piece fixed to the one end is located in the gap and is sandwiched between the pair of housing side trunk pieces. Returning the posture from the second posture to the first posture,
Connecting the balcony unit side torso piece sandwiched between the set of torso side torso pieces to each of the set of torso side torso pieces;
The assembly method of the balcony unit characterized by having.
請求項3に記載のバルコニーユニットの組み付け方法において、
前記梁部材を傾けて前記姿勢を前記第一姿勢から前記第二姿勢に切り替える工程では、
前記一端部が前記他端部よりも上方に位置するように前記一端部を持ち上げ、
前記姿勢を前記第二姿勢から前記第一姿勢に戻す工程では、
前記長手方向が前記水平方向に沿うように前記一端部を落下させることを特徴とするバルコニーユニットの組み付け方法。
In the assembly method of the balcony unit of Claim 3,
In the step of tilting the beam member and switching the posture from the first posture to the second posture,
Lifting the one end so that the one end is positioned above the other end,
In the step of returning the posture from the second posture to the first posture,
The method of assembling a balcony unit, wherein the one end is dropped so that the longitudinal direction is along the horizontal direction.
建物本体の躯体に組み付けられる建物用ユニットを吊るための治具であって、
前記躯体に設けられた躯体側胴差片と連結して該躯体側胴差片とともに前記躯体において胴差として機能する建物用ユニット側胴差片が前記建物用ユニットの後端部に備えられているときに、前記建物用ユニット側胴差片と係合する係合部と、
該係合部を長手方向の一端部において支持し、前記係合部が前記建物用ユニット側胴差片に係合した際に前記長手方向が前記建物用ユニットの前後方向に沿う支持部材と、
前記治具が取り付けられた前記建物用ユニットを吊る際の吊り位置を規定し、前記長手方向に沿って移動することにより、前記長手方向において前記吊り位置を調整するための吊り位置調整機構と、
を備えることを特徴とする治具。
A jig for suspending a building unit to be assembled to the building body frame,
A building unit side trunk piece that is connected to a case side trunk piece provided in the case and functions as a trunk difference in the case together with the case side trunk piece is provided at the rear end of the building unit. An engaging portion that engages with the building unit side trunk difference piece,
The engagement portion is supported at one end portion in the longitudinal direction, and when the engagement portion engages with the building unit side trunk piece, the support member extends along the front-rear direction of the building unit;
A suspension position adjusting mechanism for adjusting the suspension position in the longitudinal direction by defining a suspension position when hanging the building unit to which the jig is attached and moving along the longitudinal direction;
A jig characterized by comprising:
請求項5に記載の治具において、
前記係合部と前記支持部材と前記吊り位置調整機構とをそれぞれ一組ずつ備えるとともに、
一方の前記吊り位置調整機構と他方の前記吊り位置調整機構とを連結する連結部材を更に備え、
一方の前記吊り位置調整機構と他方の前記吊り位置調整機構には、それぞれ、前記建物用ユニットを吊る際に用いる吊具を取り付けるために、取付け穴が形成されていることを特徴とする治具。
The jig according to claim 5,
Each of the engagement portion, the support member, and the suspension position adjustment mechanism are provided as a set,
A connection member that connects the one suspension position adjustment mechanism and the other suspension position adjustment mechanism;
A mounting hole is formed in each of the suspension position adjustment mechanism and the other suspension position adjustment mechanism in order to attach a hanging tool used when hanging the building unit. .
請求項6に記載の治具において、
前記建物用ユニット側胴差片がH型鋼を有するときに、
一方の前記係合部と他方の前記係合部は、それぞれ鉤状で、前記H型鋼のフランジの端部に引掛かることによって前記H型鋼に係合することを特徴とする治具。
The jig according to claim 6, wherein
When the building unit side trunk piece has H-shaped steel,
One said engaging part and the said other engaging part are hook-shaped, respectively, The jig | tool engaged with the said H-shaped steel by hooking on the edge part of the flange of the said H-shaped steel.
請求項5乃至請求項7のいずれか一項に記載の治具において、
前記吊り位置調整機構を前記長手方向に沿って移動させるための駆動機構を有し、
前記駆動機構は、
中心軸方向が前記長手方向に沿った状態で前記支持部材に回転自在に支持され、前記中心軸方向の一端部に備えられた被操作部が操作されることによって回転する回転ねじ体と、
該回転ねじ体が挿入され、該回転ねじ体の回転によって前記中心軸方向に沿って移動するナットと、を有し、
前記吊り位置調整機構は、
前記ナットが固定されており、前記回転ねじ体の回転による前記ナットの移動に伴って前記長手方向に沿ってスライドするスライド部材を有することを特徴とする治具。
In the jig according to any one of claims 5 to 7,
A drive mechanism for moving the suspension position adjustment mechanism along the longitudinal direction;
The drive mechanism is
A rotating screw body that is rotatably supported by the support member in a state in which the central axis direction is along the longitudinal direction, and that is rotated by operating an operated portion provided at one end of the central axis direction;
The rotating screw body is inserted, and the nut moves along the central axis direction by the rotation of the rotating screw body,
The hanging position adjusting mechanism is
A jig, wherein the nut is fixed, and has a slide member that slides along the longitudinal direction as the nut moves due to rotation of the rotary screw body.
建物本体の躯体に組み付けられて建物の一部をなす建物用ユニットであって、前記躯体に設けられた躯体側胴差片と連結して該躯体側胴差片とともに前記躯体において胴差として機能する建物用ユニット側胴差片を後端部に有する建物用ユニットを、治具を用いて吊る吊り方法であって、
前記建物用ユニット側胴差片と係合する係合部と、該係合部を長手方向の一端部において支持する支持部材と、前記治具が取り付けられた前記建物用ユニットを吊る際の吊り位置を規定し、前記長手方向に沿って移動可能な吊り位置調整機構と、を備える前記治具を前記建物用ユニットに取り付ける工程と、
前記吊り位置を調整する工程と、を有し、
前記治具を前記建物用ユニットに取り付ける工程では、前記長手方向が前記建物用ユニットの前後方向に沿うように前記係合部を前記建物用ユニット側胴差片に係合し、
前記吊り位置を調整する工程では、前記吊り位置調整機構を前記長手方向に沿って移動させることにより、前記長手方向において前記吊り位置を調整することを特徴とする建物用ユニットの吊り方法。
A building unit that is assembled to a building body and forms a part of the building. The unit is connected to the body-side body difference piece provided in the body and functions as a body difference in the body together with the body-side body difference piece. A building unit having a building unit side trunk piece at the rear end is hung using a jig,
An engaging portion that engages with the building unit side trunk piece, a support member that supports the engaging portion at one end in the longitudinal direction, and a suspension when the building unit to which the jig is attached is suspended. A step of defining a position and attaching the jig to the building unit, the suspension position adjusting mechanism being movable along the longitudinal direction;
Adjusting the suspension position, and
In the step of attaching the jig to the building unit, the engagement portion is engaged with the building unit side trunk piece so that the longitudinal direction is along the front-rear direction of the building unit,
In the step of adjusting the suspension position, the suspension position adjustment mechanism is moved along the longitudinal direction to adjust the suspension position in the longitudinal direction.
JP2010221289A 2010-09-30 2010-09-30 Balcony unit, method for assembling balcony unit, jig, and method for hanging building unit Expired - Fee Related JP5538169B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010221289A JP5538169B2 (en) 2010-09-30 2010-09-30 Balcony unit, method for assembling balcony unit, jig, and method for hanging building unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010221289A JP5538169B2 (en) 2010-09-30 2010-09-30 Balcony unit, method for assembling balcony unit, jig, and method for hanging building unit

Publications (2)

Publication Number Publication Date
JP2012077463A true JP2012077463A (en) 2012-04-19
JP5538169B2 JP5538169B2 (en) 2014-07-02

Family

ID=46238029

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010221289A Expired - Fee Related JP5538169B2 (en) 2010-09-30 2010-09-30 Balcony unit, method for assembling balcony unit, jig, and method for hanging building unit

Country Status (1)

Country Link
JP (1) JP5538169B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2021004462A (en) * 2019-06-25 2021-01-14 大和ハウス工業株式会社 Overhanging panel unit and overhanging panel structure

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61165434A (en) * 1985-01-17 1986-07-26 積水ハウス株式会社 Drain apparatus of floor protruded from outer wall
JPH03241129A (en) * 1990-02-15 1991-10-28 Sekisui Chem Co Ltd Prefabricated dwelling house with balcony
JPH04366242A (en) * 1991-06-12 1992-12-18 Natl House Ind Co Ltd Supporting structure for balcony
JPH07268964A (en) * 1994-03-30 1995-10-17 Sekisui Chem Co Ltd Unit building
JPH11280141A (en) * 1998-03-27 1999-10-12 Sekisui House Ltd Fitting structure of balcony floor unit
JP2006112131A (en) * 2004-10-15 2006-04-27 Taisei Corp Execution method of outer wall panel and mounting structure of outer wall panel

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61165434A (en) * 1985-01-17 1986-07-26 積水ハウス株式会社 Drain apparatus of floor protruded from outer wall
JPH03241129A (en) * 1990-02-15 1991-10-28 Sekisui Chem Co Ltd Prefabricated dwelling house with balcony
JPH04366242A (en) * 1991-06-12 1992-12-18 Natl House Ind Co Ltd Supporting structure for balcony
JPH07268964A (en) * 1994-03-30 1995-10-17 Sekisui Chem Co Ltd Unit building
JPH11280141A (en) * 1998-03-27 1999-10-12 Sekisui House Ltd Fitting structure of balcony floor unit
JP2006112131A (en) * 2004-10-15 2006-04-27 Taisei Corp Execution method of outer wall panel and mounting structure of outer wall panel

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2021004462A (en) * 2019-06-25 2021-01-14 大和ハウス工業株式会社 Overhanging panel unit and overhanging panel structure
JP7329770B2 (en) 2019-06-25 2023-08-21 大和ハウス工業株式会社 Overhang panel unit and overhang panel structure

Also Published As

Publication number Publication date
JP5538169B2 (en) 2014-07-02

Similar Documents

Publication Publication Date Title
JP2007170130A (en) Construction machine
US8646557B2 (en) Construction machine
JP5538169B2 (en) Balcony unit, method for assembling balcony unit, jig, and method for hanging building unit
JP4316161B2 (en) Power plant construction method
JP6186155B2 (en) Exterior wall panel mounting device and exterior wall panel mounting method
JP5189962B2 (en) Curtain wall structure
CN217379218U (en) Box plate type steel structure
JP7157577B2 (en) Ceiling frame suspension structure
JP2022157576A (en) Panel mounting bracket, panel mounting structure and panel mounting method
JP5824378B2 (en) Structure for reinforcing horizontal members of building and method for reinforcing horizontal members
JP7278131B2 (en) External wall panel installation method
JP6904633B2 (en) Self-weight receiver for lightweight cellular concrete panels
JP4691202B1 (en) Building reinforcement structure
JP2024053097A (en) Building unit manufacturing line and manufacturing method
JP2008240287A (en) Supporting structure of roof panel
JP6542315B2 (en) Rail-like member
JP2008280732A (en) Structure and construction method for mounting external wall panel
JP2019157530A (en) Unit building and unit building method
JP3204632U (en) Toilet frame device, toilet cover and toilet
JP2024023048A (en) Connection jig and building construction method using the connection jig
JP2010270480A (en) Construction method for double skin curtain wall
CN105464262A (en) Wall surface framework connection board and application node structure thereof
JP2017020210A (en) Building outer wall structure
JPH0210222Y2 (en)
JP3980384B2 (en) Floor expansion joint device

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20130830

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20140317

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140408

R150 Certificate of patent or registration of utility model

Ref document number: 5538169

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140428

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees