JP2010159097A - Method of wrapping rope for elevator - Google Patents

Method of wrapping rope for elevator Download PDF

Info

Publication number
JP2010159097A
JP2010159097A JP2009000976A JP2009000976A JP2010159097A JP 2010159097 A JP2010159097 A JP 2010159097A JP 2009000976 A JP2009000976 A JP 2009000976A JP 2009000976 A JP2009000976 A JP 2009000976A JP 2010159097 A JP2010159097 A JP 2010159097A
Authority
JP
Japan
Prior art keywords
rope
hoistway
elevator
drum
counterweight
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2009000976A
Other languages
Japanese (ja)
Other versions
JP5058181B2 (en
Inventor
Munetaka Horiuchi
宗孝 堀内
Yoshito Takemori
義人 竹盛
Hiroshi Kusumi
博志 久住
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Building Systems Co Ltd
Original Assignee
Hitachi Building Systems Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Building Systems Co Ltd filed Critical Hitachi Building Systems Co Ltd
Priority to JP2009000976A priority Critical patent/JP5058181B2/en
Publication of JP2010159097A publication Critical patent/JP2010159097A/en
Application granted granted Critical
Publication of JP5058181B2 publication Critical patent/JP5058181B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

【課題】高層ビルに設置されるエレベータにも適用できる汎用性の高いエレベータのロープ掛け方法の提供。
【解決手段】釣合い錘11を昇降路1A上部に吊持する工程と、作業床8を第1の揚重機3で昇降路1A上部に吊持する工程と、支持雇21を第2の揚重機22で昇降路1A上部に吊持する工程と、ロープドラム17を最上階乗場18aに載置し、このロープドラム17から繰り出された主ロープ16を巻上機5に巻掛けて釣合い錘11に連結する工程と、ロープドラム17を移行して支持雇21に吊持する工程と、第1の揚重機3及び第2の揚重機22を駆動させて作業床8と支持雇21を同期して下降させる工程と、昇降路1A下部でロープドラム17から主ロープ16を取り外して乗りかご35に連結する工程とを含むエレベータのロープ掛け方法。
【選択図】図6
Provided is a highly versatile elevator rope hanging method applicable to an elevator installed in a high-rise building.
A process of suspending a counterweight 11 on an upper part of a hoistway 1A, a process of suspending a work floor 8 on an upper part of the hoistway 1A by a first lifting machine 3, and a support hire 21 for a second lifting machine. The rope drum 17 is placed on the uppermost floor landing 18a, and the main rope 16 drawn out from the rope drum 17 is wound around the hoisting machine 5 to the counterweight 11 The step of connecting, the step of shifting the rope drum 17 and suspending it to the support hire 21, the first lifting machine 3 and the second hoisting machine 22 being driven to synchronize the work floor 8 and the support hiring 21 An elevator rope hanging method including a step of lowering and a step of removing the main rope 16 from the rope drum 17 at the lower part of the hoistway 1A and connecting the main rope 16 to the car 35.
[Selection] Figure 6

Description

本発明は、乗りかごと釣合い錘とが釣瓶式に保持されるエレベータのロープ掛け方法に関するものである。   The present invention relates to a method for hooking an elevator rope in which a car cage and a counterweight are held in a fishing bottle type.

従来より、エレベータのロープ掛け作業は、主ロープの一端を乗りかごに連結し、昇降路頂部の機械室に設けられた巻上機を介して主ロープの他端を釣合い錘に連結することによって行われてきた。近年においては、エレベータを利用する乗客の増加に伴い、一度に多くの乗客が乗れるように乗りかごが大型化されている。そのため、エレベータには、複数本の主ロープが使用されており、各主ロープが絡む等の困難を伴い、エレベータのロープ掛け作業が従来に比して煩雑となっていた。   Traditionally, elevator rope hanging work has been done by connecting one end of the main rope to the car and connecting the other end of the main rope to the counterweight via a hoist provided in the machine room at the top of the hoistway. Has been done. In recent years, with the increase in passengers who use elevators, the size of a car has been increased so that many passengers can ride at once. For this reason, a plurality of main ropes are used for the elevator, and it is difficult to entangle the main ropes. Thus, the elevator rope-hanging operation is more complicated than before.

そこで、このような煩雑さを解消し、エレベータのロープ掛け作業の能率を向上させるために、複数本の主ロープが巻回されたロープドラムを作業床としてのかごフレームに転動可能に載置し、このかごフレームを駆動装置である仮設用巻上機で昇降させることによって、複数本の主ロープをロープドラムから繰り出させて各シーブに巻き掛けるエレベータのロープ掛け方法が提案されている(例えば、特許文献1参照)。   Therefore, in order to eliminate such complications and improve the efficiency of the elevator rope hanging work, a rope drum on which a plurality of main ropes are wound is placed on a car frame as a work floor so that it can roll. In addition, an elevator rope hooking method has been proposed in which a plurality of main ropes are unwound from a rope drum and wound around each sheave by raising and lowering the car frame with a temporary hoisting machine as a driving device (for example, , See Patent Document 1).

特開2001−302139号公報JP 2001-302139 A

ところで、最近では上記に加えて、高階床の高層ビルの建設が活発に行われており、特に、この種の高層ビルでは、上述の大型化した乗りかごのエレベータが使用される。このような高層ビルのエレベータに特許文献1に開示されたエレベータのロープ掛け方法を適用する場合、乗りかごと釣合い錘とを連結する主ロープの長さが長くなることに伴い、主ロープが巻回されたロープドラムの重さが非常に重くなる。そのため、作業床を昇降させる駆動装置として用いた仮設用巻上機では、作業床にロープドラムを転動可能に載置した状態で作業床を昇降させることができず、ロープドラムから主ロープを繰り出させることができなくなる。このように、該エレベータのロープ掛け方法は、このような高層ビルに設置されるエレベータに適用できず、汎用性が低いという問題があった。   Recently, in addition to the above, high-rise buildings with high floors are being actively constructed. In particular, in this type of high-rise buildings, the elevators of the above-described large-sized passenger cars are used. When the elevator rope hanging method disclosed in Patent Document 1 is applied to an elevator of such a high-rise building, the length of the main rope connecting the carriage and the counterweight increases, and the main rope is wound. The weight of the rope drum turned becomes very heavy. Therefore, in the temporary hoisting machine used as a drive device for raising and lowering the work floor, the work floor cannot be raised and lowered while the rope drum is movably mounted on the work floor, and the main rope is removed from the rope drum. Cannot be extended. As described above, the rope-hanging method of the elevator cannot be applied to an elevator installed in such a high-rise building, and there is a problem that versatility is low.

本発明は、このような従来技術の実情に鑑みてなされたもので、その目的は、高層ビルに設置されるエレベータにも適用できる汎用性の高いエレベータのロープ掛け方法を提供することにある。   The present invention has been made in view of the actual situation of the prior art, and an object thereof is to provide a highly versatile elevator rope hanging method that can be applied to an elevator installed in a high-rise building.

上記の目的を達成するために、本発明のエレベータのロープ掛け方法は、主ロープの一端を乗りかごに連結し、昇降路頂部の機械室に設けられた巻上機を介して前記主ロープの他端を釣合い錘に連結するエレベータのロープ掛け方法において、前記釣合い錘を前記昇降路上部に吊持する工程と、作業床を第1の揚重機のロープで前記昇降路上部に吊持する工程と、支持雇を第2の揚重機のロープで前記昇降路上部に吊持する工程と、前記主ロープが巻回されたロープドラムを上層階乗場に載置し、このロープドラムから繰り出された前記主ロープを前記巻上機に巻掛けて前記釣合い錘に連結する工程と、前記ロープドラムを前記上層階乗場から移行して前記支持雇に吊持する工程と、前記第1の揚重機及び前記第2の揚重機を駆動させて前記作業床と前記支持雇を同期して前記昇降路下部へ下降させる工程と、前記昇降路下部で前記ロープドラムから前記主ロープを取り外して前記乗りかごに連結する工程とを含むことを特徴としている。   In order to achieve the above object, the elevator rope tying method of the present invention is characterized in that one end of the main rope is connected to the car and the main rope is connected via a hoisting machine provided in the machine room at the top of the hoistway. In the elevator rope connecting method with the other end connected to the counterweight, the step of suspending the counterweight on the upper part of the hoistway and the step of suspending the work floor on the upper part of the hoistway with the rope of the first lifting machine And a process of suspending a support worker on the upper part of the hoistway with a rope of a second lifting machine, and a rope drum around which the main rope is wound was placed on the upper floor landing and fed out from this rope drum Wrapping the main rope around the hoisting machine and connecting it to the counterweight; transitioning the rope drum from the upper floor landing and suspending it to the support hire; the first lifting machine; The second hoist is driven to A step of synchronizing the work floor and the support hire to the lower part of the hoistway, and a step of removing the main rope from the rope drum and connecting to the car at the lower part of the hoistway. .

このように構成されたエレベータのロープ掛け方法では、第1の揚重機のロープ及び第2の揚重機のロープを用いて、作業床と支持雇をそれぞれ別々に吊持し、この支持雇にロープドラムを移行することにより、重いロープドラムであっても昇降させることができる。そのため、ロープドラムから繰り出された主ロープを昇降路上部に吊持された釣合い錘に巻上機を介して連結した状態で、第2の揚重機を駆動させてロープドラムを昇降路上部から昇降路下部へ下降させることにより、ロープドラムが回転して主ロープを繰り出させることができる。その際、第1の揚重機及び第2の揚重機を駆動させて作業床と支持雇を同期して昇降路下部へ下降させることにより、下降中に作業床からロープドラムを支持することができるので、ロープドラムの振動を抑え、作業員の作業時の安全性を確保することができる。このように、重量の大きなロープドラムを要する高層ビルに設置されるエレベータにも適用することができ、汎用性が高い。   In the elevator rope hanging method configured as described above, the work floor and the support hire are separately suspended using the ropes of the first and second hoisting machines, and the ropes are supported by the support hiring. By moving the drum, even a heavy rope drum can be raised and lowered. Therefore, in a state where the main rope fed from the rope drum is connected to the counterweight suspended at the upper part of the hoistway through the hoisting machine, the second hoist is driven to raise and lower the rope drum from the upper part of the hoistway. By lowering to the lower part of the road, the rope drum can rotate and the main rope can be fed out. At that time, the rope lift drum can be supported from the work floor during the descent by driving the first lifting machine and the second lifting machine and lowering the work floor and the support work to the lower part of the hoistway in synchronization. Therefore, it is possible to suppress the vibration of the rope drum and to ensure the safety during the work of the worker. Thus, it can be applied to an elevator installed in a high-rise building that requires a heavy rope drum, and is highly versatile.

本発明のエレベータのロープ掛け方法では、作業床及びロープドラムを第1の揚重機及び第2の揚重機でそれぞれ別々に吊持することにより、荷重を各揚重機に分散させたので、重いロープドラムであっても昇降させることができ、下降に伴ってロープドラムから主ロープを繰り出すことができる。その際、第1の揚重機及び第2の揚重機を駆動させて作業床と支持雇を同期して昇降路下部へ下降させることにより、下降中に作業床からロープドラムを支持することができるので、ロープドラムの振動を抑え、作業員の作業時の安全性を確保することができると共に、複数本の主ロープが絡むことを防止することができ、作業を簡便に行うことができる。このように、作業の安全性及び作業能率を高めることができると共に高層ビルに設置されるエレベータにも適用することができ、汎用性が高い。   In the elevator rope hanging method according to the present invention, the work floor and the rope drum are separately suspended by the first lifting machine and the second lifting machine, respectively, so that the load is distributed to each lifting machine. Even the drum can be raised and lowered, and the main rope can be fed out from the rope drum as it is lowered. At that time, the rope lift drum can be supported from the work floor during the descent by driving the first lifting machine and the second lifting machine and lowering the work floor and the support work to the lower part of the hoistway in synchronization. Therefore, it is possible to suppress the vibration of the rope drum and to ensure the safety of the worker when working, and to prevent the plurality of main ropes from being entangled, so that the work can be performed easily. In this way, the safety and work efficiency of work can be improved, and it can be applied to an elevator installed in a high-rise building, and is highly versatile.

本発明の実施形態例に係るエレベータのロープ掛け方法を示すフローチャートである。It is a flowchart which shows the rope hooking method of the elevator which concerns on the example of embodiment of this invention. 該ロープ掛け方法を説明する昇降路縦断面図である。It is a hoistway longitudinal cross-sectional view explaining this rope hanging method. 該ロープ掛け方法に用いられる支持雇周辺を拡大した正面図である。It is the front view to which the support employment periphery used for this rope hanging method was expanded. 該ロープ掛け方法を説明する昇降路縦断面図である。It is a hoistway longitudinal cross-sectional view explaining this rope hanging method. 該ロープ掛け方法を説明する昇降路横断面図である。It is a hoistway cross-sectional view explaining the rope hanging method. 該ロープ掛け方法を説明する昇降路縦断面図である。It is a hoistway longitudinal cross-sectional view explaining this rope hanging method. 該ロープ掛け方法を説明する昇降路縦断面図である。It is a hoistway longitudinal cross-sectional view explaining this rope hanging method.

以下、本発明に係るエレベータのロープ掛け方法を実施するための最良の形態を図に基づいて説明する。   Hereinafter, the best mode for carrying out an elevator rope hanging method according to the present invention will be described with reference to the drawings.

図1は本発明の実施形態例に係るエレベータのロープ掛け方法を示すフローチャート、図2は該ロープ掛け方法を説明する昇降路縦断面図、図3は該ロープ掛け方法に用いられる支持雇周辺を拡大した正面図、図4は該ロープ掛け方法を説明する昇降路縦断面図、図5は該ロープ掛け方法を説明する昇降路横断面図、図6は該ロープ掛け方法を説明する昇降路縦断面図、図7は該ロープ掛け方法を説明する昇降路縦断面図である。   FIG. 1 is a flowchart showing a method of hanging an elevator according to an embodiment of the present invention, FIG. 2 is a vertical sectional view of a hoistway explaining the rope hanging method, and FIG. FIG. 4 is a longitudinal sectional view of the hoistway explaining the rope hanging method, FIG. 5 is a transverse sectional view of the hoistway explaining the rope hanging method, and FIG. 6 is a hoistway longitudinal section explaining the rope hanging method. FIG. 7 is a vertical sectional view of a hoistway for explaining the rope hanging method.

図2に示すように、本発明の実施形態例に係るエレベータのロープ掛け方法は、昇降路1Aの頂部に機械室1Bを備えたエレベータに適用される。機械室1Bは、天井近傍に据付作業時等において吊点となる天井吊ビーム2と、この天井吊ビーム2に取り付けられた第1の揚重機3と、機械室1B床面に対して平行に取り付け固定されたマシンビーム4と、このマシンビーム4上に載置固定されてシーブ5aを有する巻上機5と、マシンビーム4に取り付けられた転向プーリ6とを備えている。また、図3及び図5に示すように、天井吊ビーム2は一対となっており、互いに平行に配設されている。昇降路1Aは昇降路壁に沿って互いに平行に延設された一対のガイドレール7a,7bと、この左側のガイドレール7aに案内されて昇降する作業床8とを備え、この作業床8は、第1の揚重機3を駆動させる操作装置3bを備えている。   As shown in FIG. 2, the elevator rope hanging method according to the embodiment of the present invention is applied to an elevator including a machine room 1 </ b> B at the top of the hoistway 1 </ b> A. The machine room 1B includes a ceiling hanging beam 2 that becomes a hanging point in the vicinity of the ceiling, a first lifting machine 3 attached to the ceiling hanging beam 2, and a machine room 1B parallel to the floor surface. A machine beam 4 mounted and fixed, a hoisting machine 5 mounted and fixed on the machine beam 4 and having a sheave 5a, and a turning pulley 6 mounted on the machine beam 4 are provided. Moreover, as shown in FIG.3 and FIG.5, the ceiling suspension beam 2 makes a pair, and is mutually arrange | positioned in parallel. The hoistway 1A includes a pair of guide rails 7a and 7b extending parallel to each other along the hoistway wall, and a work floor 8 which is guided by the left guide rail 7a and moves up and down. The operating device 3b for driving the first lifting machine 3 is provided.

以下、本発明の実施形態例に係るエレベータのロープ掛け方法の手順を主として図1のフローチャートを用いながら説明する。   Hereinafter, the procedure of the elevator rope hanging method according to the embodiment of the present invention will be described mainly using the flowchart of FIG.

まず、作業床8を第1の揚重機3のロープ3aで昇降路1A上部に吊持する(S1)。そして、最下階乗場(図6参照)から釣合い錘11を昇降路1A内に搬入し、組立てると共に右側のガイドレール7bに設置する(S2)。このとき、釣合い錘11は、ウェート11bを載置する釣合い錘枠11aと、この釣合い錘枠11aの上面に取り付けられた釣合い錘ソケット11cとを備えているのみであり、ウェート11bをまだ有していない。なお、手順S1と手順S2の順序は可変である。   First, the work floor 8 is suspended above the hoistway 1A by the rope 3a of the first lifting machine 3 (S1). Then, the counterweight 11 is carried into the hoistway 1A from the lowest floor landing (see FIG. 6), assembled, and installed on the right guide rail 7b (S2). At this time, the counterweight 11 only includes a counterweight frame 11a on which the weight 11b is placed and a counterweight socket 11c attached to the upper surface of the counterweight frame 11a, and still has the weight 11b. Not. Note that the order of step S1 and step S2 is variable.

次に、機械室1Bに設けられた図示しない揚重機を用い、釣合い錘11をガイドレール7bに案内させて昇降路1A上部まで揚重する。そして、図2に示すように、玉掛けワイヤ12aを介して天井吊ビーム2に取り付けられたチェーンブロック13を用い、このチェーンブロック13から垂下する玉掛けワイヤ12bを介して釣合い錘11を昇降路1A上部に吊持する(S3)。   Next, using a lifting machine (not shown) provided in the machine room 1B, the counterweight 11 is guided to the guide rail 7b and lifted up to the upper part of the hoistway 1A. Then, as shown in FIG. 2, a chain block 13 attached to the ceiling suspension beam 2 via a sling wire 12a is used, and the counterweight 11 is connected to the upper part of the hoistway 1A via a sling wire 12b hanging from the chain block 13. (S3).

次に、釣合い錘枠11aに作業床8からウェート11bを積込む(S4)。このとき、積込むウェート11bの枚数は、設置予定の乗りかご(図7参照)の定格(総)重量の半分に相当する枚数としている。   Next, the weight 11b is loaded onto the counterweight frame 11a from the work floor 8 (S4). At this time, the number of weights 11b to be loaded is a number corresponding to half of the rated (total) weight of the car (see FIG. 7) to be installed.

次に、主ロープ16を巻回したロープドラム17を最上階乗場18aにドラム廻し19を介して転動可能に載置し(S5)、ロープドラム17から主ロープ16を繰り出して機械室1Bへ引き上げる。そして、主ロープ16を巻上機5のシーブ5aに巻掛け、転向プーリ6を介して昇降路1Aへ垂下させ(S6)、釣合い錘11の釣合い錘ソケット11cに連結する(S7)。   Next, the rope drum 17 around which the main rope 16 is wound is placed on the uppermost landing 18a so as to be able to roll through the drum 19 (S5), and the main rope 16 is fed out from the rope drum 17 to the machine room 1B. Pull up. Then, the main rope 16 is wound around the sheave 5a of the hoisting machine 5, is suspended to the hoistway 1A via the turning pulley 6 (S6), and is connected to the counterweight socket 11c of the counterweight 11 (S7).

次に、図3〜図5に示すように、支持雇21を機械室1Bの一対の天井吊ビーム2に取り付けられた第2の揚重機22のロープ22aで昇降路1A上部に吊持し(S8)、ロープドラム17を最上階乗場18aから移行してこの支持雇21に回転可能に吊持する(S9)。   Next, as shown in FIGS. 3 to 5, the support worker 21 is suspended above the hoistway 1 </ b> A by the rope 22 a of the second lifting machine 22 attached to the pair of ceiling suspension beams 2 of the machine room 1 </ b> B ( In step S8, the rope drum 17 is moved from the top floor landing 18a and is rotatably suspended on the support staff 21 (S9).

ここで、第2の揚重機22は玉掛けワイヤ30を介して一対の天井吊ビーム2のいずれか一方に取り付けられ、第2の揚重機22のロープ22aは金車31及び玉掛けワイヤ30を介して他方に取り付けられる。また、支持雇21は、金車31に取り付けられる索状体23aを介して吊持される吊ビーム23と、ロープドラム17の円筒中空部に挿通されると共に、吊ビーム23にビームクランプ24を介して取り付けられた一対の吊ワイヤ25でロープドラム17を回転可能に支持する回転支持ロッド26と、この回転支持ロッド26の両端に取り付けられてロープドラム17及び一対の吊ワイヤ25の脱落を防止する脱落防止部材27とを有している。   Here, the second lifting machine 22 is attached to one of the pair of ceiling suspended beams 2 via a sling wire 30, and the rope 22 a of the second lifting machine 22 is connected via a gold wheel 31 and a sling wire 30. Attached to the other. Further, the support worker 21 is inserted into the suspension beam 23 suspended via the cord-like body 23 a attached to the gold wheel 31 and the cylindrical hollow portion of the rope drum 17, and the beam clamp 24 is attached to the suspension beam 23. A rotation support rod 26 that rotatably supports the rope drum 17 with a pair of suspension wires 25 attached thereto, and attached to both ends of the rotation support rod 26 to prevent the rope drum 17 and the pair of suspension wires 25 from falling off. And a drop-off prevention member 27.

次に、図5及び図6に示すように、作業床8上の作業員が昇降路1A上部に吊持させたロープドラム17を支持し、作業床8上の別の作業員が操作装置3bを操作して第1の揚重機3を駆動させると共に、機械室1B内にいる作業員にロープドラム17を昇降路1A下部へ下降させるように指示する。この指示を受けた機械室1B内にいる作業員は、機械室1B内に設けられた操作装置22bを操作して第2の揚重機22を駆動させ、作業床8と支持雇21を同期して昇降路1A下部へ下降させる(S10)。   Next, as shown in FIGS. 5 and 6, a worker on the work floor 8 supports the rope drum 17 suspended above the hoistway 1A, and another worker on the work floor 8 moves the operating device 3b. Is operated to drive the first lifting machine 3 and to instruct a worker in the machine room 1B to lower the rope drum 17 to the lower part of the hoistway 1A. Upon receiving this instruction, the worker in the machine room 1B operates the operating device 22b provided in the machine room 1B to drive the second lifting machine 22, and synchronizes the work floor 8 and the support worker 21. To lower the hoistway 1A (S10).

次に、昇降路1A下部でロープドラム17から主ロープ16を取り外し、ガイドレール7aに仮固定する(S11)。そして、以上の手順S5〜S11を繰り返し、必要な数の主ロープ16を設置する(S12)。   Next, the main rope 16 is removed from the rope drum 17 below the hoistway 1A and temporarily fixed to the guide rail 7a (S11). And the above procedure S5-S11 is repeated and the required number of main ropes 16 are installed (S12).

次に、図7に示すように、作業床8をガイドレール7aから取り外し、最下階乗場18bから搬出する(S13)。そして、昇降路1A下部のガイドレール7aに乗りかご受雇35aを設置し(S14)、乗りかご35を乗りかご受雇35aで受けながらガイドレール7aに係合させた状態で組立て(S15)、主ロープ16をガイドレール7aから取り外し、乗りかご35の上面に設けられたかご側ソケット35bに連結する(S16)。   Next, as shown in FIG. 7, the work floor 8 is removed from the guide rail 7a and carried out from the lowest floor landing 18b (S13). Then, the car reception 35a is installed on the guide rail 7a at the lower part of the hoistway 1A (S14), and the car 35 is assembled in a state of being engaged with the guide rail 7a while being received by the car reception 35a (S15), The main rope 16 is removed from the guide rail 7a and connected to a car-side socket 35b provided on the upper surface of the car 35 (S16).

次に、主ロープ16を乗りかご35に連結した後、チェーンブロック13を操作して釣合い錘11を吊上げ、釣合い錘11を揚重後、乗りかご受雇35aを取り外す(S17)。そして、チェーンブロック13を操作して釣合い錘11を吊下げ、主ロープ16にテンションを掛けて調整する(S18)。最後に、釣合い錘11からチェーンブロック13を取り外し、乗りかご35の低速試運転を行う(S19)。   Next, after the main rope 16 is connected to the car 35, the chain block 13 is operated to lift the counterweight 11, and after lifting the counterweight 11, the car hire 35a is removed (S17). Then, the counterweight 11 is suspended by operating the chain block 13, and the main rope 16 is tensioned and adjusted (S18). Finally, the chain block 13 is removed from the counterweight 11, and a low-speed trial operation of the car 35 is performed (S19).

このようにした本発明に係るエレベータのロープ掛け方法によれば、第1の揚重機3のロープ3a及び第2の揚重機22のロープ22aを用いて作業床8と支持雇21をそれぞれ別々に吊持し、この支持雇21にロープドラム17を移行することにより、重いロープドラム17であっても昇降させることができる。そのため、ロープドラム17から繰り出された主ロープ16を釣合い錘11に巻上機5を介して連結した状態で、第2の揚重機22を駆動させてロープドラム17を下降させることにより、ロープドラム17が回転して主ロープ16を繰り出させることができる。その際、第1の揚重機3及び第2の揚重機22を駆動させて作業床8と支持雇21を同期して昇降路1A下部へ下降させることにより、下降中に作業床8からロープドラム17を支持することができるので、ロープドラム17の振動を抑え、作業員の作業時の安全性を確保することができると共に、複数本の主ロープ16が絡むことを防止することができ、作業を簡便に行うことができる。このように、作業の安全性及び作業能率を高めることができると共に高層ビルに設置されるエレベータにも適用することができ、汎用性が高い。   According to the elevator rope hanging method according to the present invention as described above, the work floor 8 and the support worker 21 are separately provided using the rope 3a of the first lifting machine 3 and the rope 22a of the second lifting machine 22, respectively. Even if it is a heavy rope drum 17, it can be raised / lowered by suspending and transferring the rope drum 17 to this support employment 21. Therefore, in a state where the main rope 16 drawn out from the rope drum 17 is connected to the counterweight 11 via the hoisting machine 5, the second lifting machine 22 is driven to lower the rope drum 17, thereby the rope drum The main rope 16 can be fed out by rotating 17. At that time, the first lifting machine 3 and the second lifting machine 22 are driven to lower the work floor 8 and the support worker 21 synchronously to the lower part of the hoistway 1A, so that the rope drum is removed from the work floor 8 during the lowering. 17 can be supported, so that the vibration of the rope drum 17 can be suppressed, the safety of the worker can be secured, and the main ropes 16 can be prevented from being entangled. Can be performed easily. In this way, the safety and work efficiency of work can be improved, and it can be applied to an elevator installed in a high-rise building, and is highly versatile.

また、支持雇21は、回転支持ロッド26の両端に脱落防止部材27を備えているので、ロープドラム17が昇降路1A上部から昇降路1A下部へ下降する間にロープドラム17に振動が生じても、ロープドラム17及び一対の吊ワイヤ25が脱落することを防止することができ、作業員の作業時における安全性をより高めることができる。   Further, the support employer 21 is provided with drop-off prevention members 27 at both ends of the rotation support rod 26, so that the rope drum 17 vibrates while the rope drum 17 descends from the upper part of the hoistway 1A to the lower part of the hoistway 1A. In addition, it is possible to prevent the rope drum 17 and the pair of hanging wires 25 from falling off, and it is possible to further improve the safety of the worker during work.

なお、本発明の実施形態例では、図1に示すS5〜S11の手順を繰り返すことによって、複数本の主ロープ16を釣合い錘11及び乗りかご35に設けた場合について説明したが、複数のロープドラム17を第2の揚重機22で吊持し、これら複数のロープドラム17を同時に下降させて主ロープ16を繰り出させてもよい。この場合、S5〜S11の手順を繰り返す回数を減らすことができるので、作業時間を短縮することができ、作業の効率性を向上することができる。   In the embodiment of the present invention, the case where a plurality of main ropes 16 are provided on the counterweight 11 and the car 35 by repeating the steps S5 to S11 shown in FIG. 1 is described. The drum 17 may be suspended by the second lifting machine 22, and the plurality of rope drums 17 may be simultaneously lowered to feed out the main rope 16. In this case, since the frequency | count of repeating the procedure of S5-S11 can be reduced, work time can be shortened and the efficiency of work can be improved.

1A 昇降路
1B 機械室
2 天井吊ビーム
3 第1の揚重機
3a 第1の揚重機のロープ
3b,22b 操作装置
4 マシンビーム
5 巻上機
5a シーブ
6 転向プーリ
7a,7b ガイドレール
8 作業床
11 釣合い錘
11a 釣合い錘枠
11b ウェート
11c 釣合い錘ソケット
12a,12b,30 玉掛けワイヤ
13 チェーンブロック
16 主ロープ
17 ロープドラム
18a 最上階乗場
18b 最下階乗場
19 ドラム廻し
21 支持雇
22 第2の揚重機
22a 第2の揚重機のロープ
23 吊ビーム
23a 索状体
24 ビームクランプ
25 吊ワイヤ
26 回転支持ロッド
27 脱落防止手段
31 金車
35 乗りかご
35a 乗りかご受雇
35b かご側ソケット
DESCRIPTION OF SYMBOLS 1A Hoistway 1B Machine room 2 Ceiling suspended beam 3 1st lifting machine 3a 1st lifting machine rope 3b, 22b Operating device 4 Machine beam 5 Lifting machine 5a Sheave 6 Turning pulley 7a, 7b Guide rail 8 Work floor 11 Balance weight 11a Balance weight frame 11b Weight 11c Balance weight socket 12a, 12b, 30 sling wire 13 Chain block 16 Main rope 17 Rope drum 18a Top floor landing 18b Bottom floor landing 19 Drum rotation 21 Support employment 22 Second lifting machine 22a Rope of the second lifting machine 23 Suspension beam 23a Cable body 24 Beam clamp 25 Suspension wire 26 Rotation support rod 27 Fall-off prevention means 31 Money wheel 35 Ride car 35a Ride car hire 35b Car side socket

Claims (1)

主ロープの一端を乗りかごに連結し、昇降路頂部の機械室に設けられた巻上機を介して前記主ロープの他端を釣合い錘に連結するエレベータのロープ掛け方法において、
前記釣合い錘を前記昇降路上部に吊持する工程と、
作業床を第1の揚重機のロープで前記昇降路上部に吊持する工程と、
支持雇を第2の揚重機のロープで前記昇降路上部に吊持する工程と、
前記主ロープが巻回されたロープドラムを上層階乗場に載置し、このロープドラムから繰り出された前記主ロープを前記巻上機に巻掛けて前記釣合い錘に連結する工程と、
前記ロープドラムを前記上層階乗場から移行して前記支持雇に吊持する工程と、
前記第1の揚重機及び前記第2の揚重機を駆動させて前記作業床と前記支持雇を同期して前記昇降路下部へ下降させる工程と、
前記昇降路下部で前記ロープドラムから前記主ロープを取り外して前記乗りかごに連結する工程とを含むことを特徴とするエレベータのロープ掛け方法。
In the elevator rope hooking method, one end of the main rope is connected to the car and the other end of the main rope is connected to the counterweight via a hoist provided in the machine room at the top of the hoistway.
Suspending the counterweight above the hoistway;
Suspending a work floor above the hoistway with a rope of a first lifting machine;
Suspending a support hire above the hoistway with a rope of a second hoist;
Placing the rope drum around which the main rope is wound on the upper floor landing, wrapping the main rope fed out from the rope drum around the hoisting machine, and connecting to the counterweight;
Transitioning the rope drum from the upper floor landing and suspending it to the support hire,
Driving the first lifting machine and the second lifting machine to synchronize the work floor and the support hire to the lower part of the hoistway; and
Removing the main rope from the rope drum at the lower part of the hoistway and connecting it to the car.
JP2009000976A 2009-01-06 2009-01-06 How to hang an elevator rope Expired - Fee Related JP5058181B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009000976A JP5058181B2 (en) 2009-01-06 2009-01-06 How to hang an elevator rope

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009000976A JP5058181B2 (en) 2009-01-06 2009-01-06 How to hang an elevator rope

Publications (2)

Publication Number Publication Date
JP2010159097A true JP2010159097A (en) 2010-07-22
JP5058181B2 JP5058181B2 (en) 2012-10-24

Family

ID=42576585

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009000976A Expired - Fee Related JP5058181B2 (en) 2009-01-06 2009-01-06 How to hang an elevator rope

Country Status (1)

Country Link
JP (1) JP5058181B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013010580A (en) * 2011-06-28 2013-01-17 Toshiba Elevator Co Ltd Rope attaching jig

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5271043A (en) * 1975-12-11 1977-06-14 Hitachi Elevator & Service Method of putting main rope in 2 1 roping elevator
JPH06255944A (en) * 1993-03-08 1994-09-13 Hitachi Building Syst Eng & Service Co Ltd Main rope stretching method of elevator
JPH11349252A (en) * 1998-06-09 1999-12-21 Hitachi Building Systems Co Ltd Elevator installation apparatus and assembling method thereof
JP2001114484A (en) * 1999-10-18 2001-04-24 Mitsubishi Electric Corp Elevator main rope suspension method
JP2003073052A (en) * 2001-08-31 2003-03-12 Toshiba Elevator Co Ltd Rope installing method of elevator and rope guide device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5271043A (en) * 1975-12-11 1977-06-14 Hitachi Elevator & Service Method of putting main rope in 2 1 roping elevator
JPH06255944A (en) * 1993-03-08 1994-09-13 Hitachi Building Syst Eng & Service Co Ltd Main rope stretching method of elevator
JPH11349252A (en) * 1998-06-09 1999-12-21 Hitachi Building Systems Co Ltd Elevator installation apparatus and assembling method thereof
JP2001114484A (en) * 1999-10-18 2001-04-24 Mitsubishi Electric Corp Elevator main rope suspension method
JP2003073052A (en) * 2001-08-31 2003-03-12 Toshiba Elevator Co Ltd Rope installing method of elevator and rope guide device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013010580A (en) * 2011-06-28 2013-01-17 Toshiba Elevator Co Ltd Rope attaching jig

Also Published As

Publication number Publication date
JP5058181B2 (en) 2012-10-24

Similar Documents

Publication Publication Date Title
EP2403795B1 (en) Elevator arrangement and method
CN104066670B (en) Method and elevator arrangement
CN104024141A (en) Elevator arrangement and method
JP6537720B2 (en) Elevator hoist installation method
CN112566864B (en) Application method of lift extension technology of elevator
JP6969686B2 (en) How to extend the lift of a construction elevator
JP6750754B2 (en) Lifting elevator for construction work
JP2008222382A (en) Method for moving lifting device for installation
JP3807775B2 (en) How to lift the construction elevator
JP3844944B2 (en) Demolition method of construction elevator
JP5058181B2 (en) How to hang an elevator rope
JP4491110B2 (en) Elevator rope hanging method
JP5841929B2 (en) How to change the main rope of the elevator
JP2001114484A (en) Elevator main rope suspension method
JP2705534B2 (en) Elevator equipment for construction
JP5027970B2 (en) Elevator rope installation method
CN107640679A (en) The replacing options of car position adjustment hoist cable
JP2005015071A (en) Main rope replacement device of elevator
JPH0920480A (en) Method for transporting heavy load using rope type elevator and heavy load transporting device used for the method
JPH11349258A (en) Construction elevator and method of extending construction elevator up and down stroke
JP2000344440A (en) Main rope hanging work method of 2: 1 roping elevator and main rope guide device thereof
JP7804747B1 (en) Elevator shaft lifting device and elevator shaft lifting method
JPH08133634A (en) Jumping method for jump-up elevator
JP4037604B2 (en) Elevator rope replacement method
JP2003238046A (en) How to change the elevator main rope

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20100902

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120628

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120710

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120731

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150810

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 5058181

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees