JP2008180016A - Self-climbing overhead crane - Google Patents

Self-climbing overhead crane Download PDF

Info

Publication number
JP2008180016A
JP2008180016A JP2007014938A JP2007014938A JP2008180016A JP 2008180016 A JP2008180016 A JP 2008180016A JP 2007014938 A JP2007014938 A JP 2007014938A JP 2007014938 A JP2007014938 A JP 2007014938A JP 2008180016 A JP2008180016 A JP 2008180016A
Authority
JP
Japan
Prior art keywords
crane
mast
climbing
self
overhead crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP2007014938A
Other languages
Japanese (ja)
Inventor
Hironori Arita
浩徳 在田
Hiroshi Tokuda
浩 徳田
Masaaki Nakanishi
正明 中西
Masaki Fuchimoto
正樹 淵本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2007014938A priority Critical patent/JP2008180016A/en
Publication of JP2008180016A publication Critical patent/JP2008180016A/en
Withdrawn legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

【課題】建物の施工に適用する天井クレーンの盛り替え作業を軽減する。
【解決手段】施工エリア1の上方を跨ぐように架設される横行ビーム5aにトロリーを走行可能に搭載してなるクレーン本体5と、クレーン本体を施工エリアの上方において走行させるべく横行ビームの両端部を走行可能に支持するとともに枠組足場2等の足場に対して固定可能な対の走行レール4と、足場に支持されて立設されてその上部に走行レールを所定間隔で昇降可能に支持するとともに走行レールを昇降させるためのクライミング用シリンダ3bを備えた複数のマスト3を具備して、セルフクライミングを可能とする。
【選択図】図2
[PROBLEMS] To reduce the work of replacing an overhead crane applied to construction of a building.
A crane main body 5 in which a trolley is movably mounted on a traversing beam 5a constructed so as to straddle the construction area 1 and both ends of the traversing beam so that the crane main body travels above the construction area. And a pair of traveling rails 4 that can be fixed to a scaffold such as the frame scaffolding 2, and are supported by the scaffolding so that the traveling rail can be moved up and down at predetermined intervals. A plurality of masts 3 having climbing cylinders 3b for raising and lowering the traveling rail are provided to enable self-climbing.
[Selection] Figure 2

Description

本発明は、建物の施工に際して設置される天井クレーン、特に施工進捗に伴ってそれ自体で漸次上方に盛り替えることのできるセルフクライミング式の天井クレーンに関する。   The present invention relates to an overhead crane installed at the time of construction of a building, and more particularly to a self-climbing overhead crane that can be gradually rearranged by itself as construction progresses.

建物の施工に際しては各種の資機材を揚重するための揚重手段が不可欠であって、大規模な建物の施工に際してはタワークレーンを設置することが最も一般的であるが、中層程度の中小規模の建物の場合にはたとえば特許文献1や特許文献2に示されるように枠組足場を利用して簡略な天井クレーンを設置することもある。
特許文献1に示されるものは、施工すべき建物の周囲に設置される枠組足場の上部に全天候型仮設上屋を架設するとともに、その下方において走行する天井クレーンを両側の枠組足場間に設置するようにしたものである。
特許文献2に示されるものは、枠組足場の要所に開口部を確保してその内側に支持部材を介して天井クレーンを配備し、開口部を通して資機材を現場内に搬出入するようにしたものである。
特開平6−146609号公報 特開2001−336289号公報
Lifting means for lifting various materials and equipment is indispensable for building construction, and tower cranes are the most common for large-scale building construction. In the case of a building of a scale, for example, as shown in Patent Document 1 and Patent Document 2, a simple overhead crane may be installed using a frame scaffold.
In Patent Document 1, an all-weather-type temporary roof is installed on the upper part of a frame scaffolding installed around a building to be constructed, and an overhead crane that travels below is installed between the frame scaffolds on both sides. It is what I did.
In the one shown in Patent Document 2, an opening is secured at a key point of the frame scaffolding, and an overhead crane is deployed through a support member on the inside, and materials and equipment are carried in and out of the site through the opening. Is.
JP-A-6-146609 JP 2001-336289 A

中小程度の規模の建物の施工に際して上記のような簡略な構成の天井クレーンを用いることは、大規模なタワークレーンを用いる場合に比べて施工効率や施工コストの改善を期待できる場合もあるが、改善すべき課題も多い。
すなわち、特許文献1〜2に示されるような従来一般の天井クレーンは、当然に施工進捗に伴って順次上方に盛り替えていく必要があるが、その盛り替えのたびにクレーン本体のみならず走行レール等も含めた設備全体を解体しては再び組み立てるという作業を繰り返す必要がある。そして、そのような盛り替え作業はたとえば電動チェーンブロック等の簡便な機材のみで実質的に手作業で行うか、あるいはそのために他のクレーンを別途用意せざるを得ず、いずれにしても天井クレーンの盛り替え作業のために多大の労務と費用を必要とするものである。
When using an overhead crane with a simple structure as described above when constructing a small or medium-sized building, it may be possible to expect improvement in construction efficiency and construction cost compared to using a large-scale tower crane. There are many issues to be improved.
In other words, the conventional general overhead cranes as shown in Patent Documents 1 and 2 naturally need to be rearranged upward as the construction progresses. It is necessary to repeat the work of disassembling and reassembling the entire equipment including rails. Then, such a reordering operation is performed by hand only with simple equipment such as an electric chain block, for example, or another crane must be prepared separately for that purpose. A large amount of labor and expense are required for the reordering work.

また、天井クレーンを仮設屋根の下方に設置したり、走行レールを枠組足場の内側に取り付けるものであることから、施工エリアの上方空間に天井クレーンの吊り代を充分を確保するためには枠組足場の所要高さを必要以上に大きくしなければならない場合もあり、それによる足場関連工事費の増大が生じる場合がある。
さらに、特許文献2に示されるものでは枠組足場に開口部を設けることから、開口部の位置では枠組足場本来の機能が失われてしまい、したがってそこには必要に応じて他の足場を適宜設けるという余分な作業も必要となる。
In addition, since the overhead crane is installed below the temporary roof and the traveling rail is attached to the inside of the frame scaffolding, the frame scaffolding is sufficient to ensure sufficient suspension for the overhead crane in the upper space of the construction area. In some cases, it may be necessary to increase the required height of the scaffold more than necessary, which may increase the construction costs related to the scaffolding.
Further, in the one shown in Patent Document 2, since an opening is provided in the frame scaffold, the original function of the frame scaffold is lost at the position of the opening. Therefore, another scaffold is appropriately provided there if necessary. This extra work is also required.

以上のことから、特許文献1〜2に示されるような天井クレーンは、中小規模の建物の施工に適用することの有用性は認められつつも現時点では広く普及するには至っておらず、有効適切な改善策が望まれているのが実情である。   From the above, overhead cranes such as those shown in Patent Documents 1 and 2 have not been widely used at the present time, although they are recognized as being useful for construction of small and medium-sized buildings. The actual situation is that various improvement measures are desired.

請求項1記載の発明は、建物の施工に際して施工エリアの周囲に設置される足場に支持されて設置され、施工進捗に伴って漸次上方に盛り替えられるセルフクライミング式の天井クレーンであって、施工エリアの上方を跨ぐように架設される横行ビームにトロリーを走行可能に搭載してなるクレーン本体と、前記クレーン本体を施工エリアの上方において走行させるべく前記横行ビームの両端部を走行可能に支持するとともに、前記足場に対して固定可能な対の走行レールと、前記足場に支持されて立設されてその上部に前記走行レールを所定間隔で昇降可能に支持するとともに、該走行レールを昇降させるためのクライミング用シリンダを備えた複数のマストを具備してなることを特徴とする。   The invention according to claim 1 is a self-climbing type overhead crane that is supported and installed on a scaffolding installed around a construction area during construction of a building, and is gradually relocated upward as construction progresses. A crane main body in which a trolley is mounted so as to be able to travel on a traverse beam laid so as to straddle the upper side of the area, and both ends of the traverse beam are supported to be able to travel so that the crane main body travels above the construction area And a pair of traveling rails that can be fixed to the scaffold, and supported by the scaffold so as to be able to move up and down at a predetermined interval on the upper portion of the traveling rail. And a plurality of masts each having a climbing cylinder.

請求項2記載の発明は、請求項1記載の発明のセルフクライミング式の天井クレーンであって、施工エリアの幅方向両側に設置された足場にマストが所定間隔で支持されて立設されて、該マストの上端部が足場上に突出し、該マストの上端部に走行レールが支持されることによって該走行レールが双方の足場の頂部において施工エリアの長手方向に沿って設置され、該走行レール間にクレーン本体が架設されることによって該クレーン本体が施工エリアの長手方向に走行する構成とされてなることを特徴とする。   The invention according to claim 2 is the self-climbing type overhead crane according to claim 1, wherein the mast is supported at predetermined intervals on the scaffolds installed on both sides in the width direction of the construction area, and is erected. The upper end of the mast protrudes on the scaffold, and the traveling rail is supported on the upper end of the mast so that the traveling rail is installed along the longitudinal direction of the construction area at the top of both scaffolds. The crane main body is constructed in such a manner that the crane main body travels in the longitudinal direction of the construction area.

請求項3記載の発明は、請求項2記載の発明のセルフクライミング式の天井クレーンであって、施工エリアの幅方向両側に設置された足場の外側に被搬送物を吊り上げるための荷取りエリアが設定され、クレーン本体として、被搬送物を荷取りエリアから建物内に取り込むための荷取り用のクレーン本体と、被搬送物を施工エリア内において搬送するための搬送用のクレーン本体とが併設され、それらクレーン本体のうち、少なくとも荷取り用のクレーン本体は、走行レールより横行ビームを吊り下げかつ横行ビームからトロリーを吊り下げて走行させるサスペンション型のクレーン本体とされて、該サスペンション型のクレーン本体の横行ビームの先端部が走行レールを越えて足場の外側に突出せしめられて荷取りエリアの上方位置までトロリーが走行可能に構成されてなることを特徴とする。   The invention according to claim 3 is the self-climbing type overhead crane according to claim 2, wherein there is a loading area for lifting the object to be transported outside the scaffolding installed on both sides in the width direction of the construction area. As a crane body, a crane body for picking up the object to be transported from the loading area into the building and a crane body for transporting the object to be transported in the construction area are provided. Among these crane main bodies, at least the crane main body for loading is a suspension type crane main body that travels with the traverse beam suspended from the traveling rail and the trolley suspended from the traverse beam. The tip of the traverse beam is projected to the outside of the scaffold over the running rail and to the upper position of the loading area. Li wherein the is is configured to be run.

請求項4記載の発明は、請求項1〜3のいずれかに記載の発明のセルフクライミング式の天井クレーンであって、マストの上部にクライミング用シリンダによって昇降可能な昇降ブラケットが装着されて該昇降ブラケットに走行レールが支持され、かつ該昇降ブラケットと足場との間には、揚重荷重を支持するためのジャーナルジャッキが介装可能とされてなることを特徴とする。   A fourth aspect of the present invention is the self-climbing overhead crane according to any one of the first to third aspects of the present invention, wherein an elevating bracket that can be moved up and down by a climbing cylinder is mounted on an upper portion of the mast. A travel rail is supported by the bracket, and a journal jack for supporting a lifting load can be interposed between the lifting bracket and the scaffold.

請求項5記載の発明は、請求項1〜4のいずれかに記載の発明のセルフクライミング式の天井クレーンであって、マストが足場に代えて施工済みの躯体に対して支持されて立設されてなることを特徴とする。   The invention according to claim 5 is the self-climbing type overhead crane according to any one of claims 1 to 4, wherein the mast is erected while being supported by a constructed frame in place of the scaffold. It is characterized by.

請求項6記載の発明は、請求項1〜5のいずれかに記載の発明のセルフクライミング式の天井クレーンであって、足場またはそれに代わる施工済みの躯体にはマストを支持するガイドフレームが設置され、該ガイドフレームにはマストを支持しつつ上下方向にスライド自在に支持するガイドローラが設けられ、マストの下部にはガイドフレームに係合する閂が着脱自在に設けられてなることを特徴とする。   A sixth aspect of the present invention is the self-climbing overhead crane according to any one of the first to fifth aspects, wherein a guide frame that supports the mast is installed on the scaffold or an already constructed frame instead. The guide frame is provided with a guide roller for supporting the mast so as to be slidable in the vertical direction, and a hook engaging with the guide frame is detachably provided at the lower part of the mast. .

本発明によれば、セルフクライミングが可能なマストを足場に組み込み、そのマストによるセルフクライミング動作によって天井クレーン全体を足場に対して上昇させて盛り替えるように構成したので、従来一般のこの種の天井クレーンのように盛り替えのたびにクレーン本体や走行レールを解体しかつ再び組み立てるといった作業を省略でき、盛り替え作業を大幅に軽減することができる。   According to the present invention, the mast capable of self-climbing is incorporated into the scaffold, and the entire overhead crane is lifted with respect to the scaffold by the self-climbing operation by the mast, so that it can be replaced. The work of disassembling and reassembling the crane body and the traveling rail every time the refilling is performed like a crane can be omitted, and the reworking work can be greatly reduced.

特に、荷取りエリアを妻側に設定してクレーン本体を施工エリアの長手方向に走行させることにより、荷取り作業と施工エリア全体にわたる搬送作業を単一のクレーン本体で効率的に実施することができる。   In particular, by setting the cargo collection area on the wife side and running the crane body in the longitudinal direction of the construction area, it is possible to efficiently carry out the cargo collection work and the conveyance work over the entire construction area with a single crane body. it can.

また、荷取り用としてサスペンション型のクレーン本体を使用することにより荷取りエリアを施工エリアの側部に設定することも可能であり、搬送用のクレーン本体との併用により施工エリア全体への搬送を支障なく行うことができる。   In addition, it is possible to set the loading area to the side of the construction area by using a suspension type crane body for loading, and use it together with the crane body for transportation to transport the entire construction area. It can be done without hindrance.

また、マストの上部に昇降ブラケットを介して走行レールを支持し、その昇降ブラケットと足場との間にジャーナルジャッキを介装することにより、揚重荷重を足場により安定に支持することができるし、大きな揚重荷重がマストに対して偏心荷重として直接作用してしまう懸念がなく、各ジャーナルジャッキの調整により走行レール全体の水平度を容易にかつ高精度で確保することができる。   In addition, by supporting the traveling rail via the lifting bracket on the upper part of the mast and interposing the journal jack between the lifting bracket and the scaffold, the lifting load can be stably supported by the scaffold, There is no concern that a large lifting load directly acts on the mast as an eccentric load, and the level of the entire running rail can be easily and accurately secured by adjusting each journal jack.

また、マストを足場に代えて施工済みの躯体に対して支持することにより、マストを設置するべき位置に足場がなくても、あるいは足場を省略しても、天井クレーンを支障なく設置することが可能である。   In addition, by supporting the mast in place of the scaffold with respect to the already constructed frame, it is possible to install the overhead crane without any trouble even if there is no scaffold at the position where the mast should be installed or the scaffold is omitted. Is possible.

さらに、マストを足場あるいは施工済みの躯体に対してガイドフレームにより支持するとともに、そのガイドフレームにはガイドローラを設け、マスト下部にはガイドフレームに係合する閂を着脱自在に設けることにより、全体の荷重をガイドフレームを介して安定に支持可能であるし、盛り替え作業時にもマストを支持しつつそのまま上昇させることができる。   Furthermore, the mast is supported by a guide frame with respect to the scaffold or the already constructed frame, a guide roller is provided on the guide frame, and a hook that engages with the guide frame is detachably provided on the lower part of the mast. The load can be stably supported via the guide frame, and can be raised as it is while supporting the mast during the refilling operation.

本発明の天井クレーンの一実施形態を図1〜図7を参照して説明する。
本実施形態の天井クレーンは、平面形状が一方向(桁行方向)に長い形態とされ、高さがたとえば10階建て程度の中層程度の建物の施工に際して適用されるものであって、図3に示すように施工エリア1の周囲に全周にわたって設置される足場を利用してそれ自体が盛り替え可能に構成されているものである。
An embodiment of the overhead crane of the present invention will be described with reference to FIGS.
The overhead crane according to the present embodiment has a planar shape that is long in one direction (girder direction), and is applied at the time of construction of a medium-rise building having a height of, for example, about 10 stories. As shown in the figure, the structure itself is configured so that it can be reordered using a scaffold installed around the construction area 1 over the entire circumference.

すなわち、建物の施工に際してはその周囲を取り囲むように仮設の足場を設置するのであるが、足場としては所定規格の建枠と布枠とブレースを主体とする枠組足場を用いて、それを施工進捗に伴って漸次上方に立ち上げていくことが最も一般的であることから、本実施形態では施工エリア1の幅方向(スパン方向)の両側に設置される枠組足場2に複数のマスト3を所定間隔で組み込み、それらマスト3の上部に走行レール4を昇降可能に設置し、両側の走行レール4間にクレーン本体5を架設することを基本としている。
そして、施工進捗に伴う枠組足場2の立ち上げに応じてマスト3を漸次上昇させていって走行レール4およびクレーン本体5をそのまま漸次上昇させていくことによって天井クレーン全体の盛り替えを行い、それにより従来のように盛り替えのたびに走行レール4やクレーン本体5を解体しかつ再び組み立てるといった作業を大幅に軽減できるものとなっている。
In other words, when constructing a building, a temporary scaffolding is installed so as to surround the surrounding area, but as a scaffolding, a framework scaffolding mainly composed of a prescribed frame, cloth frame and brace is used, and the construction progresses. Accordingly, in the present embodiment, a plurality of masts 3 are predetermined on the frame scaffold 2 installed on both sides in the width direction (span direction) of the construction area 1. Basically, the traveling rails 4 are installed at intervals above the mast 3 so as to be movable up and down, and the crane body 5 is installed between the traveling rails 4 on both sides.
Then, the mast 3 is gradually raised in accordance with the start of the frame scaffold 2 as the construction progresses, and the traveling rail 4 and the crane body 5 are gradually raised as they are, and the entire overhead crane is refilled. As a result, the operation of disassembling and reassembling the traveling rail 4 and the crane body 5 each time the refilling is performed can be greatly reduced.

マスト3は、図1〜図2に示すように角形鋼管等からなるマスト本体3aを主体として、その側部にクライミング用シリンダ3bが上向きに取り付けられ、クライミング用シリンダ3bのピストンロッド3cの先端には、マスト本体3aの上部に昇降可能に装着されている昇降ブラケット3dが連結され、クライミング用シリンダ3bの操作によりその昇降ブラケット3dをマスト本体3aに対して昇降させるようになっている。なお、クライミング用シリンダ3bの所要ストロークは少なくとも枠組足場2の1段分の高さ以上とする必要があるが、1度の盛り替え作業によって複数段の枠組足場2を立ち上げる場合にはその段数分の高さに相当する昇降ストロークを有するものとすることが好ましい。   As shown in FIGS. 1 to 2, the mast 3 is mainly composed of a mast main body 3a made of a square steel pipe or the like, and a climbing cylinder 3b is attached to the side of the mast body 3a. The upper / lower bracket 3d attached to the upper part of the mast main body 3a is connected to the upper part of the mast main body 3a, and the upper / lower bracket 3d is moved up and down with respect to the mast main body 3a by operating the climbing cylinder 3b. The required stroke of the climbing cylinder 3b needs to be at least the height of one step of the frame scaffold 2; however, when the multiple steps of the frame scaffold 2 are started up by one reworking operation, the number of steps is required. It is preferable to have a lifting stroke corresponding to the height of the minute.

枠組足場2に対するマスト3の組み込みとその支持は単管等の適宜の仮設資材を用いて適宜行えば良く、必要に応じて適宜の補強を行えば良いが、本実施形態では図2(b)、(c)に詳細を示しているように、枠組足場2の各段の建枠2a間にガイドフレーム6を設置してその中央部内側にマスト3を配置して支持するような支持機構を採用している。
その支持機構においては、ガイドフレーム6の内側にマスト本体3aを周囲から支持するガイドローラ6aが取り付けられており、そのガイドローラ6aによって常にマスト本体5aの転倒を有効に防止しつつ盛り替え作業時にはマスト本体5aをそのまま上昇させることができるものとなっている。
また、図2(c)に示すようにマスト本体5aの下端部には閂6bが着脱自在に取り付けられるようになっていて、通常時は閂6bを最下段のガイドフレーム6に係合させておくことによって天井クレーン全体の荷重をマスト本体5aから閂6a、ガイドフレーム6を介して枠組足場2により支持することができ、かつ、マスト3の盛り替えの際には閂6bを抜き取ることのみでマスト3を容易に上昇させることができるものとなっている。
The mast 3 can be incorporated into and supported by the frame scaffold 2 using an appropriate temporary material such as a single pipe, and may be appropriately reinforced as necessary. In the present embodiment, FIG. As shown in detail in (c), a support mechanism is provided in which a guide frame 6 is installed between the building frames 2a of each step of the frame scaffold 2 and the mast 3 is arranged and supported inside the center portion thereof. Adopted.
In the support mechanism, a guide roller 6a for supporting the mast body 3a from the periphery is attached to the inside of the guide frame 6, and the guide roller 6a always effectively prevents the mast body 5a from being overturned while refilling. The mast body 5a can be raised as it is.
Further, as shown in FIG. 2 (c), a collar 6b is detachably attached to the lower end portion of the mast main body 5a. Normally, the collar 6b is engaged with the lowermost guide frame 6. The load of the entire overhead crane can be supported by the frame scaffold 2 from the mast body 5a via the eave 6a and the guide frame 6, and when the mast 3 is replaced, only the eave 6b is removed. The mast 3 can be easily raised.

図1に示すように、マスト3の上端部は枠組足場2の頂部よりも上方に突出していて、そこに装着されている上記の昇降ブラケット3dには上記の走行レール4が一体に取り付けられていて、走行レールは枠組足場2の頂部に設置されるものとなっている。そして、クライミング用シリンダ3bによって昇降ブラケット3dを上昇させることにより、その昇降ブラケット3dとともに走行レール4もそのまま上昇し、走行レール4間に架設されているクレーン本体5もそのまま上昇するものとなっている。   As shown in FIG. 1, the upper end portion of the mast 3 protrudes upward from the top portion of the frame scaffold 2, and the traveling rail 4 is integrally attached to the lifting bracket 3d attached thereto. The traveling rail is installed at the top of the frame scaffold 2. Then, by raising the lifting bracket 3d by the climbing cylinder 3b, the traveling rail 4 is also lifted together with the lifting bracket 3d, and the crane body 5 installed between the traveling rails 4 is also lifted as it is. .

クレーン本体5は、図1に示すように、走行レール4間に架設された横行ビーム5aと、横行ビーム5aに沿って走行するトロリー5bからなる。
本実施形態における横行ビーム5aは、簡易な組み立て式の軽量な鋼製トラスからなる主ビーム5aaと、その下部に取り付けられてトロリー5bを走行可能に支持するI型鋼等からなるトロリービーム5abからなり、主ビーム5aaの両端部がオーバーヘッド型のサドル5cを介して走行レール4上に支持されてその長さ方向(桁行方向)に走行可能とされ、トロリー5bがトロリービーム5abの長さ方向(スパン方向)に走行しかつ主ビーム5aa上に搭載したウインチ5dの操作により昇降することによって、図3に示すように施工エリア1の妻側に設定した荷取りエリア7から各種資材を吊り上げて施工エリア1内の所望位置に効率的に搬送し得るものである。
As shown in FIG. 1, the crane body 5 includes a transverse beam 5a installed between the traveling rails 4 and a trolley 5b that travels along the transverse beam 5a.
The transverse beam 5a in the present embodiment is composed of a main beam 5aa made of a light steel truss of a simple assembly type and a trolley beam 5ab made of I-type steel or the like that is attached to the lower part of the beam 5a and supports the trolley 5b so that it can run. Both ends of the main beam 5aa are supported on the traveling rail 4 via an overhead saddle 5c so that the main beam 5aa can travel in the length direction (running direction), and the trolley 5b extends in the length direction (span of the trolley beam 5ab). 3) and lifting up and down by operating the winch 5d mounted on the main beam 5aa, the various materials are lifted from the cargo collection area 7 set on the wife side of the construction area 1 as shown in FIG. It can be efficiently transported to a desired position in 1.

なお、図1に示すように、マスト3の上部に装着した昇降ブラケット3dと枠組足場2の上面との間にはジャーナルジャッキ8が介装されて、揚重荷重が走行レール4から昇降ブラケット3d、ジャーナルジャッキ8を介して枠組足場2により支持されるようになっており、それにより揚重荷重を枠組足場2全体で安定に支持できるばかりでなく、大きな揚重荷重がマスト3に対して偏心荷重として直接作用してしまう懸念がなく、したがってマスト本体3aの強度や所要断面を節約することができるものとなっている。
また、枠組足場2の上面レベルの水平度が充分ではない場合であっても、それに対応させて個々のジャーナルジャッキ8を調整することによって走行レール4全体の水平度を容易にかつ高精度で確保することができる。
As shown in FIG. 1, a journal jack 8 is interposed between the elevating bracket 3d attached to the upper portion of the mast 3 and the upper surface of the frame scaffold 2 so that a lifting load is applied from the traveling rail 4 to the elevating bracket 3d. In addition to being supported by the frame scaffold 2 via the journal jack 8, not only can the lifting load be stably supported by the entire frame scaffold 2, but the large lifting load is eccentric with respect to the mast 3. There is no concern of acting directly as a load, and therefore the strength and required cross section of the mast body 3a can be saved.
Even if the level of the upper surface level of the frame scaffold 2 is not sufficient, the level of the entire traveling rail 4 can be easily and accurately secured by adjusting the individual journal jacks 8 correspondingly. can do.

本実施形態の天井クレーンは、マスト3がそれ自体でいわゆる尺取り虫的に作動することによってセルフクライミングによる盛り替えが可能なものであり、その盛り替え作業手順を図4〜図7に示す。   The overhead crane of the present embodiment can be changed by self-climbing when the mast 3 itself operates in a so-called scale, and the change-over operation procedure is shown in FIGS.

図4はクレーン本体5のセルフクライミングを行う直前の状態、すなわち、所定階での施工が完了して、枠組足場2を上方へ延長するための盛り替え作業とそれに伴う天井クレーンの盛り替え作業を行う段階となった状態を示している。
この状態ではマスト3を含めて天井クレーンの全体が枠組足場2に対して支持されていて、クライミング用シリンダ3bが伸張している状態で昇降ブラケット3dはマスト本体3aの最上部に位置しており、上述のように昇降ブラケット3dと枠組足場2との間にはジャーナルジャッキ8が介装されている。なお、クレーン本体5が不用意に移動しないように、横行ビーム5aを適宜位置で走行レール4に対してロックしておき、トロリー5bは横行ビーム5aに対してロックしておく。
FIG. 4 shows a state immediately before the crane main body 5 performs self-climbing, that is, a refilling operation for extending the frame scaffold 2 upward after completion of the construction on the predetermined floor and a reworking operation of the overhead crane associated therewith. It shows the state when it is time to do it.
In this state, the entire overhead crane including the mast 3 is supported by the frame scaffold 2, and the lifting bracket 3 d is positioned at the top of the mast body 3 a with the climbing cylinder 3 b extended. As described above, the journal jack 8 is interposed between the lifting bracket 3d and the frame scaffold 2. In order to prevent the crane body 5 from moving carelessly, the transverse beam 5a is locked to the traveling rail 4 at an appropriate position, and the trolley 5b is locked to the transverse beam 5a.

その状態からクライミングを行うには、まずジャーナルジャッキ8を撤去するためにクライミング用シリンダ3bを若干伸張させて昇降ブラケット3dおよび走行レール4を若干持ち上げ、ジャーナルジャッキ8を撤去した後、クライミング用シリンダ3bを縮退させて昇降ブラケット3dを引き下げ、それを枠組足場2上に直接支持して適宜連結固定する。   In order to perform climbing from this state, first, the climbing cylinder 3b is slightly extended to remove the journal jack 8, the lifting bracket 3d and the traveling rail 4 are slightly lifted, the journal jack 8 is removed, and then the climbing cylinder 3b. Is retracted, the lifting bracket 3d is pulled down, and it is directly supported on the frame scaffold 2 and connected and fixed as appropriate.

次いで、マスト本体5aの下部から閂6bを抜き取って枠組足場2によるマスト3の支持を解除し、そのマスト3の荷重を昇降ブラケット3dを介して枠組足場2の上部に預ける。
その状態でクライミング用シリンダ3bを縮退させると、ピストンロッド3cの先端部に連結されている昇降ブラケット3dが枠組足場2に対して連結固定されていることから、図5に示すようにクライミング用シリンダ3bとともにマスト本体3aが引き上げられていって枠組足場2に対して相対的に上昇していくことになる。
Next, the collar 6b is pulled out from the lower part of the mast body 5a to release the support of the mast 3 by the frame scaffold 2 and the load of the mast 3 is deposited on the upper part of the frame scaffold 2 through the lifting bracket 3d.
When the climbing cylinder 3b is retracted in this state, the climbing cylinder 3d connected to the tip of the piston rod 3c is fixedly connected to the frame scaffold 2, so that the climbing cylinder as shown in FIG. The mast main body 3a is pulled up together with 3b and rises relative to the frame scaffold 2.

各マスト本体3aをそれぞれ所定ストローク(少なくとも枠組足場2の1段分の高さに相当する距離)上昇させていき、それらマスト本体3aの下端部に閂6bを取り付けてその荷重を再び枠組足場2によって支持する。そして、全てのマスト3をその状態とした後、全てのクライミング用シリンダ3bを一斉に同期させて伸張させれば、図6に示すように枠組足場2から反力がとられて各昇降ブラケット3dが同期して一斉に押し上げられ、それにより両側の走行レール4およびそれらの間に架設されているクレーン本体5の全体が水平姿勢のままで上昇する。
そこで、図7に示すように既設の枠組足場2上に所定段数(図示例では1段のみ)の新たな枠組足場2を継ぎ足して組み立てて枠組足場2を上方に延長した後、その上部と昇降ブラケット3dの間にジャーナルジャッキ8を介装し、そのジャーナルジャッキ8を介して全体の荷重を盛り替え後の枠組足場2に預ければ、図4と同様の状態となって盛り替え作業が完了し、クレーン本体5の下方には新たに充分な吊り代が確保される。
Each mast body 3a is lifted by a predetermined stroke (at least a distance corresponding to the height of one step of the frame scaffold 2), a flange 6b is attached to the lower end of the mast body 3a, and the load is again applied to the frame scaffold 2 Support by. Then, after all the masts 3 are brought into that state, if all the climbing cylinders 3b are extended simultaneously in synchronism, a reaction force is taken from the frame scaffold 2 as shown in FIG. Are pushed up all at once in synchronism with each other, and as a result, the traveling rails 4 on both sides and the entire crane body 5 installed between them are raised in a horizontal posture.
Therefore, as shown in FIG. 7, a new frame scaffold 2 having a predetermined number of steps (only one in the illustrated example) is assembled on the existing frame scaffold 2 and assembled to extend the frame scaffold 2 upward. If a journal jack 8 is interposed between the brackets 3d and the entire load is stored in the post-replacement frame scaffold 2 via the journal jack 8, the remodeling operation is completed as in FIG. A sufficient suspension allowance is newly secured below the crane body 5.

以上のように、本実施形態の天井クレーンは、セルフクライミングが可能なマスト3を枠組足場2に組み込み、そのマスト3によるセルフクライミング動作によって天井クレーン全体をそのまま枠組足場2に対して上昇させて盛り替えるように構成したので、従来一般のこの種の天井クレーンのように盛り替えのたびにクレーン本体5や走行レール4を解体しかつ再び組み立てるといった作業を省略でき、盛り替え作業を大幅に軽減することができる。   As described above, the overhead crane according to the present embodiment incorporates the mast 3 capable of self-climbing into the frame scaffold 2 and raises the entire overhead crane as it is with respect to the frame scaffold 2 by the self-climbing operation by the mast 3. Since it is configured to be replaced, the work of disassembling and reassembling the crane body 5 and the traveling rail 4 each time when reordering is performed as in this type of conventional overhead crane can be omitted, greatly reducing the reordering work. be able to.

なお、施工完了後に枠組足場2を解体する際には、クレーン本体5、走行レール4、各マスト3の全てを解体撤去してから枠組足場2の解体撤去に着手することでも良いが、クレーン本体5のみを解体撤去してしまえば、上記と逆の手順により枠組足場2の解体撤去に並行して各マスト3および走行レール4を一斉に順次降下させていくことが可能であり、それによりそれらの解体撤去を高所で行う必要がなく地表部で容易にかつ安全に行うことができる。勿論、クレーン本体5とともに走行レール4も高所で解体撤去してしまい、各マスト3のみをそれぞれ地表部まで降下させることできる。   In addition, when dismantling the frame scaffold 2 after the completion of construction, it may be possible to start dismantling the frame scaffolding 2 after dismantling and removing all of the crane body 5, the running rail 4, and each mast 3. If only 5 is dismantled, each mast 3 and traveling rail 4 can be lowered simultaneously in parallel with the dismantling and removal of the frame scaffold 2 by the reverse procedure of the above, There is no need to dismantle and dismantle at high altitudes, and it can be done easily and safely on the surface. Of course, the traveling rail 4 as well as the crane main body 5 is dismantled and removed at a high place, and only each mast 3 can be lowered to the ground surface.

また、本実施形態の天井クレーンは、単に盛り替え作業を軽減できるばかりでなく、走行レール4を枠組足場2の頂部に支持して設置しているので、施工エリア1の上方には自ずと充分な吊り代を確保でき、したがって特許文献1〜2に示される従来のもののように吊り代を確保するがために枠組足場2の所要高さを必要以上に大きくするようなことはないし、枠組足場2の要所に荷取りのための開口部を設ける必要もなく、その点においても効率的な施工が可能である。   In addition, the overhead crane according to the present embodiment can not only reduce the refilling work but also support the traveling rail 4 on the top of the frame scaffold 2 so that it is naturally sufficient above the construction area 1. The suspension allowance can be secured, and therefore the required height of the frame scaffold 2 is not increased more than necessary to secure the suspension allowance as in the conventional ones shown in Patent Documents 1 and 2, and the frame scaffold 2 Therefore, it is not necessary to provide an opening for picking up the cargo at this important point, and efficient construction is possible in this respect.

しかも、マスト3にクライミング用シリンダ3bを備えること以外は従来一般の天井クレーンの構成部品や汎用の仮設資材をそのまま転用可能であるし、枠組足場2に対するマスト3の支持やそのための補強も簡略に行うことが可能であるから、これを設置することによるコスト増は些少で済み、タワークレーンや従来一般の天井クレーンを使用する場合に比べて施工性を大きく改善できることによる工費削減と工期短縮にを充分に図ることができる。   Moreover, except that the mast 3 is provided with the climbing cylinder 3b, the components of the conventional general overhead crane and general-purpose temporary materials can be used as they are, and the support of the mast 3 with respect to the frame scaffold 2 and the reinforcement thereof are also simplified. Because it can be done, the cost increase by installing this is insignificant, and the construction cost can be reduced and the construction period can be shortened by greatly improving the workability compared to using a tower crane or a conventional overhead crane. We can plan enough.

以上で本発明の一実施形態を説明したが、上記実施形態はあくまで好適な一例に過ぎず、本発明は上記実施形態に限定されることなくたとえば以下に列挙するような様々な設計的変形や応用が可能である。   Although one embodiment of the present invention has been described above, the above embodiment is merely a preferred example, and the present invention is not limited to the above embodiment, and various design modifications such as those listed below are possible. Application is possible.

マスト3の所要本数やその設置間隔、クライミング用シリンダ3bの昇降ストロークその他の仕様は、天井クレーン全体の規模や揚重荷重、走行レール4の長さやその部材強度、足場全体の構造やその盛り替え作業計画、その他の諸条件を考慮して、この天井クレーン全体を安定に支持しつつ安全かつ効率的な盛り替えが可能となるように適宜設定すれば良いことはいうまでもない。
上記実施形態のように各マスト3の全てにクライミング用シリンダ3bを備えることとすれば、個々のクライミング用シリンダ3bの容量は最小限で済むが、全体をバランス良く安定に昇降させることができる場合にはクライミング用シリンダ3bを一部のマスト3にのみ取り付けることでも良く、たとえば1本おきのマスト3にクライミング用シリンダ3bを設置したり、あるいは走行レール4の両端部を支持する2本のマスト3のみに大容量のクライミング用シリンダ3bを設置することも考えられる。その場合には、クライミング用シリンダ3bを取り付けていないマスト3はそれ自体によるセルフクライミングが不可能であるので、そのマスト3の上端部を走行レール4に対して連結しておいて他のマスト3により昇降させられる走行レール4を介してそのマスト3が引き上げられるようにしておけば良い。
The required number of masts 3 and their installation intervals, the climbing stroke of the climbing cylinder 3b, and other specifications are the overall size and lifting load of the overhead crane, the length of the traveling rail 4 and the strength of its members, the structure of the entire scaffold and its reordering Needless to say, considering the work plan and other various conditions, it may be set as appropriate so that safe and efficient replacement is possible while stably supporting the entire overhead crane.
If the climbing cylinders 3b are provided in all the masts 3 as in the above embodiment, the capacity of the individual climbing cylinders 3b can be minimized, but the whole can be moved up and down with good balance and stability. For example, the climbing cylinder 3b may be attached to only a part of the mast 3, for example, the climbing cylinder 3b is installed on every other mast 3, or two masts that support both ends of the running rail 4 are supported. It is also conceivable to install a large-capacity climbing cylinder 3 b only in 3. In that case, since the mast 3 to which the climbing cylinder 3b is not attached cannot perform self-climbing by itself, the upper end of the mast 3 is connected to the traveling rail 4 and the other mast 3 is connected. The mast 3 may be lifted through the traveling rail 4 that is moved up and down by the movement.

上記実施形態ではマスト3を設置して支持するための足場として最も一般的な枠組足場2を用い、通常はそれが現実的であるし最適でもあるが、本発明における足場はマスト3を組み込んで支持でき、かつ天井クレーン全体の荷重を支持できるものであれば良く、その限りにおいて足場の構造や形式は任意であって必ずしも枠組足場2を用いることに限るものではなく、地表から立設される足場のみならず施工済みの躯体から吊り支持されて設置される吊り足場に対しても同様に適用可能である。
さらに、施工するべき建物の規模や形態、足場の形式やその設置パターンによっては、マスト3を施工済みの躯体(たとえば柱や梁やスラブ)に対して設置することも考えられ、その場合にはたとえば上記実施形態におけるガイドフレーム6のような適宜の支持機構を施工済みの躯体とマスト3との間に介装して、マスト3を施工済みの躯体に対して昇降可能に支持すれば良い。そのようにマスト3を施工済みの躯体に支持することとすれば、足場がマスト3を安定に支持できない場合や、マスト3を設置するべき位置に足場を設置できない場合、あるいは足場を省略したい場合であっても、天井クレーンを支障なく設置することが可能である。
In the above embodiment, the most common framework scaffold 2 is used as a scaffold for installing and supporting the mast 3, which is usually realistic and optimal, but the scaffold in the present invention incorporates the mast 3. As long as it can support and can support the load of the entire overhead crane, the structure and form of the scaffolding are arbitrary as long as it is supported, and is not necessarily limited to the use of the frame scaffolding 2 but is erected from the ground surface. The present invention can be similarly applied not only to the scaffolding but also to the suspended scaffolding that is installed by being supported by being hung from the installed frame.
In addition, depending on the size and form of the building to be constructed, the type of scaffolding and its installation pattern, it is possible to install the mast 3 on a pre-constructed frame (for example, a column, beam or slab). For example, an appropriate support mechanism such as the guide frame 6 in the above-described embodiment may be interposed between the completed frame and the mast 3 so as to support the mast 3 so as to be movable up and down with respect to the completed frame. If the mast 3 is to be supported on the already constructed frame, the scaffold cannot support the mast 3 stably, the scaffold cannot be installed at the position where the mast 3 should be installed, or the scaffold is omitted. Even so, it is possible to install the overhead crane without hindrance.

上記実施形態におけるクレーン本体5は、オーバーヘッド型のサドル5cにより横行ビーム5aが走行レール4上を走行する形式のものとされ、そのようなオーバーヘッド型のクレーン本体5は走行範囲がマスト3により制約されることなく走行レール4上をその全長にわたって自由に走行できるものであるが、それに代えてたとえば図8に示すようにサスペンション型(懸垂型)のサドル5eにより横行ビーム5aを走行レール4より吊り下げて走行させる形式のサスペンション型のクレーン本体5も採用可能である。
但し、そのようなサスペンション型のクレーン本体5では、横行ビーム5aの先端部が走行レール4の外側に突出しているとマスト3との干渉によりその走行範囲が限定されるので、図9に示すように横行ビーム5aをマスト3の内側に納まる長さとする必要がある。
The crane body 5 in the above embodiment is of a type in which the transverse beam 5a travels on the traveling rail 4 by the overhead saddle 5c, and the traveling range of such an overhead crane body 5 is restricted by the mast 3. However, instead of this, the traverse beam 5a is suspended from the traveling rail 4 by a suspension type (suspension type) saddle 5e as shown in FIG. It is also possible to employ a suspension type crane main body 5 of a type that is driven in the manner described above.
However, in such a suspension type crane main body 5, the traveling range is limited due to interference with the mast 3 when the tip of the traverse beam 5 a protrudes outside the traveling rail 4, as shown in FIG. 9. The traverse beam 5a needs to be long enough to fit inside the mast 3.

一方、上記実施形態のようにオーバーヘッド型のクレーン本体5を施工エリア1の長手方向(桁行方向)に走行させる場合には、トロリー5bの走行範囲が両側の走行レール4間に制約されることから荷取りは妻側からしか行えず、したがって荷取りエリア7の位置は上記実施形態のように施工エリア1の妻側に設定するしかなく、側部からの荷取りは不可能である。
しかし、図8に示したようなサスペンション型のクレーン本体5を採用することにより側部からの荷取りを行うことも可能となるので、その例を図10〜図11に示す(図10〜図11においては、オーバーヘッド型のクレーン本体に符号5Aを付し、サスペンション型のクレーン本体に符号5Bを付して区別する)。
On the other hand, when the overhead crane main body 5 is caused to travel in the longitudinal direction (girder direction) of the construction area 1 as in the above embodiment, the travel range of the trolley 5b is restricted between the travel rails 4 on both sides. Unloading can be performed only from the wife side, and therefore the position of the unloading area 7 can only be set on the wife side of the construction area 1 as in the above embodiment, and unloading from the side is impossible.
However, since the suspension type crane main body 5 as shown in FIG. 8 is adopted, it is possible to carry out loading from the side, and examples thereof are shown in FIGS. 11, the overhead crane body is denoted by reference numeral 5A, and the suspension crane body is denoted by reference numeral 5B.

図10〜図11に示す実施形態は、建物の側部に設置された枠組足場2の外側に荷取りエリア7を設定し、サスペンション型のクレーン本体5Bの横行ビーム5aの先端部を枠組足場2の外側に突出させて荷取りエリア7の上方まで延長させたものである。これによれば、サスペンション型のクレーン本体5Bのトロリー5bが荷取りエリア7の上方まで走行可能であるのでそこからの荷取りを支障なく行うことができる。
但し、その場合には横行ビーム5aとマスト3との干渉によりクレーン本体5Bの走行範囲は隣接する2本のマスト3間に限定され、当然に被搬送物を施工エリア1全体にわたって搬送することができないから、上記のサスペンション型のクレーン本体5Bを主として荷取り用として使用し、その他に施工エリア1全体をカバーするための一般搬送用のクレーン本体5を併設することとする。
すなわち、荷取り用のサスペンション型のクレーン本体5Bの他に、一般搬送用として図10に示すようにオーバーヘッド型のクレーン本体5A、あるいは図11に示すようにサスペンション型のクレーン本体5Bを設置し、荷取り用のサスペンション型のクレーン本体5Bにより荷取りエリア7からの荷取りを行ってその走行可能範囲内で被搬送物を搬送して施工エリア1内に取り込んだ後、一般搬送用の他のクレーン本体5(オーバーヘッド型のクレーン本体5A、またはサスペンション型のクレーン本体5B)によってそれを所望位置にさらに搬送するように構成するのである。
そのように、荷取り用および一般搬送用の2台のクレーン本体5を併用し、それらの桁行方向の走行範囲の一部をラップさせて被搬送物の受け渡しを行うことにより、側部からの荷取りと施工領域全体にわたる搬送の両立が可能であり、敷地形状や建物形状に応じて荷取りエリア7を最適位置に設定することが可能となる。
In the embodiment shown in FIGS. 10 to 11, the loading area 7 is set outside the frame scaffold 2 installed on the side of the building, and the distal end portion of the transverse beam 5 a of the suspension type crane main body 5 </ b> B is used as the frame scaffold 2. Projecting outward and extending up to above the loading area 7. According to this, since the trolley 5b of the suspension type crane main body 5B can travel up to the upper side of the load pickup area 7, the load can be picked up without any trouble.
However, in this case, the traveling range of the crane body 5B is limited between two adjacent masts 3 due to the interference between the traverse beam 5a and the mast 3, and naturally the object to be conveyed can be conveyed over the entire construction area 1. Therefore, the suspension type crane main body 5B is mainly used for loading, and in addition, a general transport crane main body 5 for covering the entire construction area 1 is additionally provided.
That is, in addition to the suspension type crane main body 5B for loading, an overhead type crane main body 5A as shown in FIG. 10 or a suspension type crane main body 5B as shown in FIG. The suspension-type crane body 5B for loading is used to pick up the cargo from the loading area 7, transport the object to be transported within the travelable range and take it into the construction area 1, and then the other crane for general transportation. The crane main body 5 (overhead type crane main body 5A or suspension type crane main body 5B) is configured to further convey it to a desired position.
In this way, by using two crane bodies 5 for unloading and general transport together, and wrapping a part of the traveling range in the direction of traversing and delivering the object to be transported, It is possible to achieve both loading and transportation over the entire construction area, and the loading area 7 can be set to an optimum position according to the site shape and building shape.

本発明の一実施形態である天井クレーンの概略構成を示す正面図である。It is a front view which shows schematic structure of the overhead crane which is one Embodiment of this invention. 同、側面図および要部詳細を示す断面図である。It is sectional drawing which shows a side view and the principal part detail same as the above. 同、全体平面図である。FIG. 同、盛り替え作業手順を示す図である。It is a figure which shows a reordering work procedure similarly. 同、盛り替え作業手順を示す図である。It is a figure which shows a reordering work procedure similarly. 同、盛り替え作業手順を示す図である。It is a figure which shows a reordering work procedure similarly. 同、盛り替え作業手順を示す図である。It is a figure which shows a reordering work procedure similarly. 本発明の他の実施形態である天井クレーンの概略構成を示す側面図である。It is a side view which shows schematic structure of the overhead crane which is other embodiment of this invention. 同、全体平面図である。FIG. 本発明のさらに他の実施形態である天井クレーンの設置パターンを示す図である。It is a figure which shows the installation pattern of the overhead crane which is further another embodiment of this invention. 本発明のさらに他の実施形態である天井クレーンの設置パターンを示す図である。It is a figure which shows the installation pattern of the overhead crane which is further another embodiment of this invention.

符号の説明Explanation of symbols

1 施工エリア
2 枠組足場(足場)
2a 建枠
3 マスト
3a マスト本体
3b クライミング用シリンダ
3c ピストンロッド
3d 昇降ブラケット
4 走行レール
5(5A、5B) クレーン本体
5a 横行ビーム
5aa 主ビーム
5ab トロリービーム
5b トロリー
5c サドル(オーバーヘッド型)
5d ウインチ
5e サドル(サスペンション型)
6 ガイドフレーム
6a ガイドローラ
6b 閂
7 荷取りエリア
8 ジャーナルジャッキ
1 Construction area 2 Framework scaffolding (scaffolding)
2a Building frame 3Mast 3a Mast body 3b Climbing cylinder 3c Piston rod 3d Lifting bracket 4 Traveling rail 5 (5A, 5B) Crane body 5a Traverse beam 5aa Main beam 5ab Trolley beam 5b Trolley 5c Saddle (overhead type)
5d winch 5e saddle (suspension type)
6 Guide frame 6a Guide roller 6b 7 7 Unloading area 8 Journal jack

Claims (6)

建物の施工に際して施工エリアの周囲に設置される足場に支持されて設置され、施工進捗に伴って漸次上方に盛り替えられるセルフクライミング式の天井クレーンであって、
施工エリアの上方を跨ぐように架設される横行ビームにトロリーを走行可能に搭載してなるクレーン本体と、
前記クレーン本体を施工エリアの上方において走行させるべく前記横行ビームの両端部を走行可能に支持するとともに、前記足場に対して固定可能な対の走行レールと、
前記足場に支持されて立設されてその上部に前記走行レールを所定間隔で昇降可能に支持するとともに、該走行レールを昇降させるためのクライミング用シリンダを備えた複数のマストを具備してなることを特徴とするセルフクライミング式の天井クレーン。
It is a self-climbing overhead crane that is supported and installed on a scaffolding installed around the construction area during construction of the building, and that is gradually relocated upward as construction progresses,
A crane body that has a trolley mounted on a traversing beam constructed so as to straddle the construction area; and
A pair of running rails that can be fixed to the scaffolding, while supporting the both ends of the traverse beam to run the crane body above the construction area,
A plurality of masts that are supported by the scaffolding and that support the traveling rail so that the traveling rail can be raised and lowered at a predetermined interval and that have climbing cylinders for raising and lowering the traveling rail are provided. A self-climbing overhead crane characterized by
請求項1記載のセルフクライミング式の天井クレーンであって、
施工エリアの幅方向両側に設置された足場にマストが所定間隔で支持されて立設されて、該マストの上端部が足場上に突出し、該マストの上端部に走行レールが支持されることによって該走行レールが双方の足場の頂部において施工エリアの長手方向に沿って設置され、
該走行レール間にクレーン本体が架設されることによって該クレーン本体が施工エリアの長手方向に走行する構成とされてなることを特徴とするセルフクライミング式の天井クレーン。
A self-climbing overhead crane according to claim 1,
The mast is supported by standing on the scaffolds installed on both sides in the width direction of the construction area at a predetermined interval, the upper end of the mast protrudes on the scaffold, and the running rail is supported on the upper end of the mast. The running rail is installed along the longitudinal direction of the construction area at the top of both scaffolds,
A self-climbing overhead crane, wherein the crane main body is constructed between the traveling rails so that the crane main body travels in the longitudinal direction of the construction area.
請求項2記載のセルフクライミング式の天井クレーンであって、
施工エリアの幅方向両側に設置された足場の外側に被搬送物を吊り上げるための荷取りエリアが設定され、
クレーン本体として、被搬送物を荷取りエリアから建物内に取り込むための荷取り用のクレーン本体と、被搬送物を施工エリア内において搬送するための搬送用のクレーン本体とが併設され、
それらクレーン本体のうち、少なくとも荷取り用のクレーン本体は、走行レールより横行ビームを吊り下げかつ横行ビームからトロリーを吊り下げて走行させるサスペンション型のクレーン本体とされて、該サスペンション型のクレーン本体の横行ビームの先端部が走行レールを越えて足場の外側に突出せしめられて荷取りエリアの上方位置までトロリーが走行可能に構成されてなることを特徴とするセルフクライミング式の天井クレーン。
A self-climbing overhead crane according to claim 2,
A loading area is set up to lift the object to be transported outside the scaffolding installed on both sides in the width direction of the construction area.
As the crane main body, a crane main body for taking in the object to be conveyed from the loading area into the building and a crane main body for conveying the object to be conveyed in the construction area are provided.
Among these crane bodies, at least the crane body for loading is a suspension-type crane body that travels with a traverse beam suspended from a traveling rail and a trolley suspended from the traverse beam. A self-climbing overhead crane, characterized in that the tip of the traverse beam protrudes beyond the running rail and protrudes to the outside of the scaffold so that the trolley can travel to a position above the loading area.
請求項1〜3のいずれかに記載のセルフクライミング式の天井クレーンであって、
マストの上部にクライミング用シリンダによって昇降可能な昇降ブラケットが装着されて該昇降ブラケットに走行レールが支持され、かつ該昇降ブラケットと足場との間には、揚重荷重を支持するためのジャーナルジャッキが介装可能とされてなることを特徴とするセルフクライミング式の天井クレーン。
A self-climbing overhead crane according to any one of claims 1 to 3,
A lifting bracket that can be lifted and lowered by a climbing cylinder is attached to the upper part of the mast, and a traveling rail is supported by the lifting bracket, and a journal jack for supporting a lifting load is provided between the lifting bracket and the scaffold. A self-climbing overhead crane characterized by being capable of being intervened.
請求項1〜4のいずれかに記載のセルフクライミング式の天井クレーンであって、
マストが足場に代えて施工済みの躯体に対して支持されて立設されてなることを特徴とするセルフクライミング式の天井クレーン。
A self-climbing overhead crane according to any one of claims 1 to 4,
A self-climbing type overhead crane characterized in that a mast is supported and erected on a completed frame instead of a scaffold.
請求項1〜5のいずれかに記載のセルフクライミング式の天井クレーンであって、
足場またはそれに代わる施工済みの躯体にはマストを支持するガイドフレームが設置され、該ガイドフレームにはマストを支持しつつ上下方向にスライド自在に支持するガイドローラが設けられ、
マストの下部にはガイドフレームに係合する閂が着脱自在に設けられてなることを特徴とするセルフクライミング式の天井クレーン。
A self-climbing overhead crane according to any one of claims 1 to 5,
A guide frame that supports the mast is installed in the scaffolding or a frame that has been constructed in place of the scaffold, and the guide frame is provided with a guide roller that supports the mast while being slidable in the vertical direction.
A self-climbing overhead crane, wherein a hook engaging with a guide frame is detachably provided at a lower portion of the mast.
JP2007014938A 2007-01-25 2007-01-25 Self-climbing overhead crane Withdrawn JP2008180016A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007014938A JP2008180016A (en) 2007-01-25 2007-01-25 Self-climbing overhead crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007014938A JP2008180016A (en) 2007-01-25 2007-01-25 Self-climbing overhead crane

Publications (1)

Publication Number Publication Date
JP2008180016A true JP2008180016A (en) 2008-08-07

Family

ID=39724114

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007014938A Withdrawn JP2008180016A (en) 2007-01-25 2007-01-25 Self-climbing overhead crane

Country Status (1)

Country Link
JP (1) JP2008180016A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017031657A (en) * 2015-07-31 2017-02-09 株式会社大林組 Ceiling crane support device and load receiving member
CN112681144A (en) * 2020-12-21 2021-04-20 中交路桥华南工程有限公司 Self-climbing type installation method of steel cable tower
CN115402945A (en) * 2022-09-08 2022-11-29 中交路桥华南工程有限公司 Lifting and jacking integrated self-climbing crane
CN115571800A (en) * 2022-09-21 2023-01-06 广州建筑湾区智造科技有限公司 Rapid rail distribution construction method for intelligent hoisting robot to ascend stairs from self-lifting mode
CN116537111A (en) * 2023-06-01 2023-08-04 广东省水利水电第三工程局有限公司 A method for installing hydraulic prefabricated components
CN117108072A (en) * 2023-07-21 2023-11-24 中冶(上海)钢结构科技有限公司 A construction method for transposition and assembly of grid frames with large drop height and large cantilever without support and lifting

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017031657A (en) * 2015-07-31 2017-02-09 株式会社大林組 Ceiling crane support device and load receiving member
CN112681144A (en) * 2020-12-21 2021-04-20 中交路桥华南工程有限公司 Self-climbing type installation method of steel cable tower
CN112681144B (en) * 2020-12-21 2023-08-18 中交路桥华南工程有限公司 Self-climbing installation method of steel cable tower
CN115402945A (en) * 2022-09-08 2022-11-29 中交路桥华南工程有限公司 Lifting and jacking integrated self-climbing crane
CN115571800A (en) * 2022-09-21 2023-01-06 广州建筑湾区智造科技有限公司 Rapid rail distribution construction method for intelligent hoisting robot to ascend stairs from self-lifting mode
CN115571800B (en) * 2022-09-21 2025-06-24 广州建筑湾区智造科技有限公司 Rapid track laying construction method for intelligent hoisting robot to self-elevate to the building
CN116537111A (en) * 2023-06-01 2023-08-04 广东省水利水电第三工程局有限公司 A method for installing hydraulic prefabricated components
CN117108072A (en) * 2023-07-21 2023-11-24 中冶(上海)钢结构科技有限公司 A construction method for transposition and assembly of grid frames with large drop height and large cantilever without support and lifting

Similar Documents

Publication Publication Date Title
JP7568805B2 (en) Method for moving heavy objects using a heavy object moving device and a heavy object moving device
CN104652807B (en) Self-circulation construction system and method for internal climbing tower supporting steel beam in hydraulic climbing formwork system
JP6476426B2 (en) Member renewal method using lifting device
JPH0841828A (en) Bridge girder erection device
KR101287455B1 (en) System and method for launching upper structure of bridege
JP2008180016A (en) Self-climbing overhead crane
CN106917360A (en) Lift leg formula frame plate machine and its frame plate method
RU2418735C1 (en) Lifting crane system
JP5914203B2 (en) Disassembly method, disassembly assistance device
KR20130001458A (en) Rebar jig for psm box girder mould
US4274542A (en) Method for transfer of crane from tower
CN103628411B (en) Attached tower cantilevered bale handle purlin, high-altitude, mountain area crane system
JP2016142097A (en) Portable hoist unit and horizontal member dismantling method
JP2010150039A (en) Crane girder replacing method and crane girder replacing device
CN108086169B (en) Installation and lifting method of mobile formwork used in bridge construction
JP2023074170A (en) Floor slab replacement method and construction machine used therefor
JP2009007129A (en) Climbing crane
JP2007291719A (en) Heavy article erection method and apparatus
JP5894851B2 (en) Support mechanism for construction elevator mast, construction elevator, and extension method for construction elevator mast
CN207177310U (en) A kind of crane beam on rock wall for underground power house reinforcing bar is from steady structure
CN215101591U (en) A shield constructs quick-witted hoisting structure for secretly dig construction
CN110077952B (en) Building template cross-floor transportation equipment and transportation method
JP6624429B2 (en) Horizontal jib crane and construction method using the same
CN107587722A (en) A kind of advanced mounting process of crane beam on rock wall for underground power house reinforcing bar and its reinforcing bar are from steady structure
CN112111620A (en) Ball top refractory dismounting device and method for blast furnace hot blast stove

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20100406