JP2006183779A - Baseless construction method for buried pipe - Google Patents

Baseless construction method for buried pipe Download PDF

Info

Publication number
JP2006183779A
JP2006183779A JP2004377883A JP2004377883A JP2006183779A JP 2006183779 A JP2006183779 A JP 2006183779A JP 2004377883 A JP2004377883 A JP 2004377883A JP 2004377883 A JP2004377883 A JP 2004377883A JP 2006183779 A JP2006183779 A JP 2006183779A
Authority
JP
Japan
Prior art keywords
buried pipe
trench
buried
positioning device
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2004377883A
Other languages
Japanese (ja)
Inventor
Masahiro Hirata
平田昌宏
Ken Nishina
仁科憲
Satoru Sasase
笹瀬悟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NAKAKEN
Original Assignee
NAKAKEN
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NAKAKEN filed Critical NAKAKEN
Priority to JP2004377883A priority Critical patent/JP2006183779A/en
Publication of JP2006183779A publication Critical patent/JP2006183779A/en
Pending legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a baseless construction method for a buried pipe omitting foundation work, and not needing segmentation of back filling and rolling compaction of back filling material. <P>SOLUTION: In the construction method, trench digging is carried out, and the buried pipe is laid in a trench. It is characterized by that the buried pipe is positioned and installed in a separated state from a trench bottom face, and slurry stabilized treated soil is filled at once in the trench until a whole circumference of the buried pipe is hidden. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

本発明は、埋設管の無基礎工法に関するものである。   The present invention relates to a foundationless construction method for buried pipes.

従来より、水道管、ガス管、下水管、信号ケーブル用鞘管、ファイバケーブル等の管(以下「埋設管」とする)を地中に埋設する工法は、地表を開削して管を埋設するトレンチ工法が広く知られている。   Conventionally, the method of embedding pipes such as water pipes, gas pipes, sewage pipes, sheath pipes for signal cables, fiber cables (hereinafter referred to as “buried pipes”) in the ground is to cut the ground surface and bury the pipes. The trench method is widely known.

図4に基づいて一般的なトレンチ工法を説明する。
最初に土留め掘削を行った後、砂などの骨材を層状に布設し、その後締め固めて基礎層20を形成して基礎拵えをする。(図4A)
次に基礎層20に埋設管6を吊り込んで設置し、(図4B)埋設管6の周りに砂を埋め戻し、十分に締め固めて巻立層21を形成する。(図4C)
そして最後に切梁11を撤去しつつ、良質土を埋め戻して埋立層22を形成するものである。(図4D)
A general trench construction method will be described with reference to FIG.
After the earth retaining excavation is first performed, an aggregate such as sand is laid in layers, and then the foundation layer 20 is formed by compaction to prepare the foundation. (FIG. 4A)
Next, the buried pipe 6 is suspended and installed in the foundation layer 20 (FIG. 4B), the sand is backfilled around the buried pipe 6, and the wound layer 21 is formed by sufficiently compacting. (Fig. 4C)
Finally, the cut beam 11 is removed and the good quality soil is backfilled to form the landfill layer 22. (Fig. 4D)

前記した従来のトレンチ工法にあっては、以下のような問題を抱えていた。
<1>地盤が軟弱な場合、基礎層20の締め固め作業が困難となるため、施工そのものが非常に困難となる。
<2>地盤が軟弱な場合、掘削に伴うリバウンドにより地盤が膨張し、埋設管6を所定の位置に設置しても、埋め戻し作業時に、膨張した地盤が再び圧縮され、沈下するため、埋設管6も沈下してしまう。
<3>骨材および砂は透水性材料であるため、埋設管の設置場所が河川敷や堤防敷きの場合、施工の許可がおりにくい。
<4>埋め戻し後の土留壁の引き抜き作業で埋め戻し材がゆるみ、埋め戻し部分及び周囲の路面の沈下が発生する。
<5>従来は複数回にわたって埋め戻し作業を行うため、工期が長期化する。
<6>転圧作業が必要なため、騒音公害などの問題が起こる。
The conventional trench method described above has the following problems.
<1> When the ground is soft, it is difficult to compact the foundation layer 20, and therefore the construction itself is very difficult.
<2> When the ground is soft, the ground expands due to rebound from excavation, and even if the buried pipe 6 is installed at a predetermined position, the expanded ground is compressed and sinks again during the backfilling operation. The tube 6 will also sink.
<3> Since aggregate and sand are water-permeable materials, it is difficult to permit construction when the location of the buried pipe is a riverbed or a bank.
<4> The backfilling material is loosened by the work of pulling out the retaining wall after backfilling, and settlement of the backfilled part and the surrounding road surface occurs.
<5> Conventionally, since the backfilling operation is performed a plurality of times, the construction period is prolonged.
<6> Since rolling work is required, problems such as noise pollution occur.

上記のような課題を解決するために、本発明の第1発明は、トレンチ掘削し、トレンチ内に埋設管を敷設して埋め戻す工法であって、埋設管をトレンチ底面より離隔させた状態で位置決めを行って設置し、トレンチ内にスラリー化安定処理土を埋設管の全周が隠れるまで一度に充填することを特徴とするものである。   In order to solve the above-described problems, the first invention of the present invention is a method of excavating a trench, laying a buried pipe in the trench, and filling it back, with the buried pipe separated from the bottom of the trench. Positioning is performed, and the slurry-stabilized soil is filled in the trench at a time until the entire circumference of the buried pipe is hidden.

また、本発明の第2発明は、本発明の第1発明に記載の埋設管の無基礎工法において、位置決め装置を設置して埋設管の浮き上がりを防止することを特徴とするものである。   According to a second aspect of the present invention, in the non-foundation method for the buried pipe according to the first aspect of the present invention, a positioning device is installed to prevent the buried pipe from being lifted.

また、本発明の第3発明は、本発明の第2発明に記載の埋設管の無基礎工法において、上記位置決め装置が取り外し自在であることを特徴とするものである。   According to a third aspect of the present invention, in the non-foundation method for the buried pipe according to the second aspect of the present invention, the positioning device is detachable.

また、本発明の第4発明は、本発明の第2乃至第3発明のいずれかに記載の埋設管の無基礎工法において、前記位置決め装置は、一端を埋設管と接続する縦杆と、縦杆の他端と交差させて接続した横断杆と、からなり、位置決め装置から反力を得て埋設管の浮き上がりを防止することを特徴とするものである。
According to a fourth aspect of the present invention, in the non-foundation method for an embedded pipe according to any one of the second to third aspects of the present invention, the positioning device includes a vertical hook that connects one end to the embedded pipe, It is characterized by comprising crossing rivets crossed and connected to the other end of the ridge, and obtaining a reaction force from the positioning device to prevent the buried pipe from being lifted.

本発明の埋設管の無基礎工法は、上記した課題を解決するための手段により、次のような効果を得ることができる。
<1>埋設管に位置決め装置を取り付けて浮力に対抗し得るように位置決めすることにより、トレンチ内の埋め戻しにスラリー化安定処理土を使用することが可能となる。したがって、流動性に優れたスラリー化安定処理土を一度にトレンチ全域に効率よく、しかも隅々まで充填することができ、施工性が改善される。
<2>土留壁の撤去後にできた隙間にもスラリー化安定処理土が充填されて硬化するため、地盤の沈下がほとんど発生しない。
<3>位置決め装置は単純な機構で取扱性がよく、設置及び撤去が容易で転用が可能であるため、経済性が高い。
The non-foundation method for the buried pipe of the present invention can obtain the following effects by means for solving the above-described problems.
<1> By attaching a positioning device to the buried pipe and positioning it so as to resist buoyancy, it becomes possible to use the slurry-stabilized soil for backfilling in the trench. Therefore, the slurry-stabilized soil excellent in fluidity can be efficiently filled into the entire trench at a time, and can be filled to every corner, thereby improving the workability.
<2> Since the slurried and stabilized soil is filled and hardened in the gap formed after the removal of the retaining wall, subsidence of the ground hardly occurs.
<3> The positioning device is simple and easy to handle, easy to install and remove, and can be diverted, so it is highly economical.

以下、図面を参照しながら本発明の実施の形態について説明する。   Hereinafter, embodiments of the present invention will be described with reference to the drawings.

<1>位置決め装置
まず、本発明で使用する主要な装置について説明する。(図1)
位置決め装置5は、縦杆3と横断杆4からなり、縦杆3は、下端に埋設管6と接続する埋設管保持部31を有し、横断杆4は、ねじ式、ピン式等の長手方向への伸縮を可能とする公知の長さ調節機構41と、両端にエッジを形成するスパイク42を有する。
縦杆3と横断杆4は垂直クランプ等の接続具8を介して交差するように接続するものとする。
<1> Positioning device First, main devices used in the present invention will be described. (Figure 1)
The positioning device 5 includes a vertical rod 3 and a cross rod 4, and the vertical rod 3 has an embedded tube holding portion 31 connected to the embedded tube 6 at the lower end, and the horizontal rod 4 is a screw type, a pin type or the like It has a known length adjusting mechanism 41 that enables expansion and contraction in the direction, and spikes 42 that form edges at both ends.
The vertical rod 3 and the transverse rod 4 are connected so as to cross each other via a connecting tool 8 such as a vertical clamp.

<2>開削工程
土留壁2を地中に打設し土留壁2で囲まれた領域を形成する。上記領域は両側の土留壁2に沿って細長く形成されており、掘削を行ってトレンチ1を形成する。上記トレンチ1は埋設管6を設置することのできる深さに掘削されており、土留壁2には、H型鋼などの線材を用いた腹起(ここでは図示せず。)をボルトなどで取り付け、切梁11の両端を腹起に押圧するように取り付ける。
<2> Cutting process The retaining wall 2 is placed in the ground to form a region surrounded by the retaining wall 2. The said area | region is formed elongate along the earth retaining wall 2 of both sides, and excavation is performed and the trench 1 is formed. The trench 1 is excavated to such a depth that a buried pipe 6 can be installed, and an abdomen (not shown here) using a wire such as H-shaped steel is attached to the retaining wall 2 with a bolt or the like. Attach both ends of the beam 11 so as to press against the abdomen.

<3>埋設管の敷設
トレンチ1の底面から離隔した状態で埋設管6を敷設する。敷設方法には、トレンチ底面に土嚢91を敷き、その上に埋設管6を敷設する。(図2A)
<3> Laying the buried pipe The buried pipe 6 is laid in a state separated from the bottom surface of the trench 1. In the laying method, a sandbag 91 is laid on the bottom of the trench, and the buried pipe 6 is laid thereon. (FIG. 2A)

<4>横断杆の設置
スパイク42は、横断杆4の両端にエッジをもって形成され、トレンチ1の土留壁の隙間の地山にスパイク42をそれぞれ手ハンマーで打ち込む。その後、横断杆4に設けた長さ調節機構41を用いて、横断杆4を長手方向に伸張し、スパイク42を地山に押圧させ固定する。
また、横断杆4は、埋設管6の長手方向に沿って、一定の間隔で設置することで、位置決めをより効果的に行うことができる。
<4> Installation of Crossing Spikes The spikes 42 are formed with edges at both ends of the crossing scissors 4, and the spikes 42 are respectively driven by hand hammers into the ground of the gap between the retaining walls of the trench 1. Then, using the length adjusting mechanism 41 provided on the crossing bar 4, the crossing bar 4 is extended in the longitudinal direction, and the spike 42 is pressed against the ground and fixed.
In addition, the transverse rods 4 can be positioned more effectively by installing them at regular intervals along the longitudinal direction of the buried pipe 6.

<5>縦杆の設置及び埋設管の固定
縦杆3を、直交クランプなどの接続具8を用いて前記横断杆4と交差するように設置する。縦杆3の下端に設けられた埋設管保持部31と埋設管6とを固定する。このときに、埋設管6がトレンチ1の底面10に接触しないようにする。
縦杆3と埋設管6との固定には、縦杆3の埋設管保持部31を埋設管6とを結束材32を用いて固定するなど、周知の取り付け方法を採用するものとする。
<5> Installation of vertical gutter and fixing of buried pipe The vertical gutter 3 is installed so as to intersect with the crossing gutter 4 using a connecting tool 8 such as an orthogonal clamp. The buried pipe holding portion 31 and the buried pipe 6 provided at the lower end of the vertical rod 3 are fixed. At this time, the buried pipe 6 is prevented from contacting the bottom surface 10 of the trench 1.
For fixing the vertical gutter 3 and the buried pipe 6, a well-known attachment method such as fixing the buried pipe holding portion 31 of the vertical gutter 3 to the buried pipe 6 using a binding material 32 is adopted.

なお、埋設管6をクレーン等でトレンチ1内に吊りこんだまま縦杆3と接続することにより、土嚢91を敷設せずに埋設管6をトレンチの底面10から離隔して敷設することもできる。   In addition, by connecting the buried pipe 6 to the vertical fence 3 while being suspended in the trench 1 with a crane or the like, the buried pipe 6 can be laid away from the bottom surface 10 of the trench without laying the sandbag 91. .

<6>埋め戻し工程
埋設管6が十分に位置決めされた後、埋め戻しを行う。このとき、埋設管6をトレンチ1の底部10に接触させないように設置するために用いた土嚢91は、埋め戻しの前に、取り除いても放置しておいてもよい。
埋め戻しにはスラリー化安定処理土7を用いる。(図2B) 上記スラリー化安定処理土7は、流動性に富み、自硬性があるため小さな隙間にも充填され硬化し、路面の沈下がほとんど発生しないため、振動による締め固めや、ローラによる転圧が不要となり、施工期間の短縮につながる。
<6> Backfilling process After the buried pipe 6 is sufficiently positioned, backfilling is performed. At this time, the sandbag 91 used for installing the buried pipe 6 so as not to contact the bottom portion 10 of the trench 1 may be removed or left before being backfilled.
Slurry stabilized soil 7 is used for backfilling. (Fig. 2B) The slurry-stabilized soil 7 is rich in fluidity and self-hardening, so it fills and cures even in small gaps and hardly sinks the road surface. No pressure is required, leading to a shortened construction period.

スラリー化安定処理土7は、埋設管6とトレンチ1の底部10との間の隙間にも充填される。埋設管6とトレンチ1の底部10との間の隙間にスラリー化安定処理土7が充填されると、埋設管6は浮力を受ける。しかし、埋設管6に接続された位置決め装置5により、埋設管6は浮力に抵抗し、埋設管6はずれずに強固に位置決めがなされる。   The slurry-stabilized soil 7 is also filled in the gap between the buried pipe 6 and the bottom 10 of the trench 1. When the slurrying stabilized soil 7 is filled in the gap between the buried pipe 6 and the bottom 10 of the trench 1, the buried pipe 6 receives buoyancy. However, the buried pipe 6 resists buoyancy by the positioning device 5 connected to the buried pipe 6, and the buried pipe 6 is firmly positioned without being displaced.

上記の埋め戻し作業は、従来の工法のように埋め戻しを段階的に行わずとも、埋設管6の位置決めが強固になされ、締め固めの作業も不要となるため、上記スラリー化安定処理土7を埋設管6の全周が隠れるまで、一度に充填することができ、施工期間を短縮することができる。   In the above-described backfilling operation, the buried pipe 6 is firmly positioned and the compaction work is not required even if the backfilling is not performed stepwise as in the conventional construction method. Can be filled at a time until the entire circumference of the buried pipe 6 is hidden, and the construction period can be shortened.

<7>解体撤去工程
土留壁2、切梁11の取り外しは、スラリー化安定処理土7を埋め戻した直後からある程度硬化するまでの間であればいつでもよく、位置決め装置5の取り外しはスラリー化安定処理土7がある程度硬化し、スラリー化安定処理土7の浮力に埋設管6が耐えうる程度になった後に行う。(図2)
上記条件で土留壁2、切梁11の取り外しを行えば、処理土は土留壁2の引き抜き後の隙間にも充填され硬化するため、従来の工法で問題とされた引き抜き後の路面の沈下を防止することができる。
取り外した土留壁2、位置決め装置5、切梁11は、転用することができ、経済性を高くすることができる。
<7> Demolition and removal process The retaining wall 2 and the cut beam 11 can be removed at any time from immediately after the slurry-stabilized soil 7 is backfilled until it is hardened to some extent. The treatment is performed after the treated soil 7 has hardened to some extent and the buried pipe 6 can withstand the buoyancy of the slurry-stabilized treated soil 7. (Figure 2)
If the retaining wall 2 and the cut beam 11 are removed under the above conditions, the treated soil is filled and hardened in the gaps after the retaining wall 2 is pulled out. Can be prevented.
The removed retaining wall 2, the positioning device 5, and the cut beam 11 can be diverted, and the economy can be increased.

第2の実施例として杭9をトレンチ1の底部に打設して埋設管6を両側から挟むようにしたり(図3)、杭9に替えて土嚢を設置してもよい。
本例にあっては、杭9が埋設管6の水平方向の移動を拘束するため、埋設管6をより強固に位置決めできる。
As a second embodiment, the pile 9 may be placed on the bottom of the trench 1 to sandwich the buried pipe 6 from both sides (FIG. 3), or a sandbag may be installed instead of the pile 9.
In this example, since the pile 9 restrains the horizontal movement of the buried pipe 6, the buried pipe 6 can be positioned more firmly.

第3の実施例として、横断杆4の両端部を地上の路盤に固定して取り付けることもできる。本例にあっては、埋設管6が受ける浮力の反力を地上の路盤からとることができ、埋設管6の浮き上がりが防止できる。
As a 3rd Example, the both ends of the crossing fence 4 can also be fixed and attached to a ground roadbed. In this example, the reaction force of the buoyancy received by the buried pipe 6 can be taken from the ground roadbed, and the buried pipe 6 can be prevented from rising.

本発明の埋設菅の無基礎工法の実施例の工程図。The process drawing of the Example of the non-foundation construction method of the buried paddle of this invention. 本発明の埋設菅の無基礎工法の実施例の断面図。Sectional drawing of the Example of the non-foundation construction method of the buried paddle of this invention. 本発明の埋設菅の無基礎工法の他の実施例の断面図。Sectional drawing of the other Example of the non-foundation construction method of the buried paddle of this invention. 従来のトレンチ工法の工程図Process diagram of conventional trench method

符号の説明Explanation of symbols

1・・・トレンチ
10・・底部
11・・切梁
2・・・土留壁
3・・・縦杆
31・・埋設管保持部
32・・結束材
4・・・横断杆
41・・長さ調節機構
42・・スパイク
5・・・位置決め装置
6・・・埋設管
7・・・スラリー化安定処理土
8・・・接続具
9・・・杭
91・・土嚢
20・・基礎層
21・・巻立層
22・・埋立層
DESCRIPTION OF SYMBOLS 1 ... Trench 10 ... Bottom 11 ... Cut beam 2 ... Retaining wall 3 ... Vertical fence 31 ... Embedded pipe holding part 32 ... Bundling material 4 ... Crossing fence 41 ... Length adjustment Mechanism 42 ... Spike 5 ... Positioning device 6 ... Buried pipe 7 ... Slurry stabilized soil 8 ... Connecting tool 9 ... Pile 91 ... Sandbag 20 ... Base layer 21 ... Winding Standing layer 22 ... Landfill layer

Claims (4)

トレンチ掘削し、トレンチ内に埋設管を敷設して埋め戻す工法であって、
埋設管をトレンチ底面より離隔させた状態で位置決めを行って設置し、
トレンチ内にスラリー化安定処理土を埋設管の全周が隠れるまで一度に充填することを特徴とする埋設管の無基礎工法。
It is a method of excavating a trench, laying a buried pipe in the trench and backfilling,
Position and install the buried pipe away from the bottom of the trench,
A non-foundation method for buried pipes, characterized in that a slurry-stabilized soil is filled in a trench at a time until the entire circumference of the buried pipe is hidden.
請求項1に記載の埋設管の無基礎工法において、位置決め装置を設置して埋設管の浮き上がりを防止することを特徴とする、
埋設管の無基礎工法。
In the foundationless construction method of the buried pipe according to claim 1, a positioning device is installed to prevent the buried pipe from being lifted up.
No foundation method for buried pipes.
請求項2に記載の埋設管の無基礎工法において、上記位置決め装置が取り外し自在であることを特徴とする埋設管の無基礎工法。
The non-foundation method for buried pipe according to claim 2, wherein the positioning device is detachable.
請求項2乃至3のいずれかに記載の埋設管の無基礎工法において、前記位置決め装置は、一端を埋設管と接続する縦杆と、縦杆の他端と交差させて接続した横断杆と、からなり、位置決め装置から反力を得て埋設管の浮き上がりを防止することを特徴とする、
埋設管の無基礎工法。
In the non-foundation method of the buried pipe according to any one of claims 2 to 3, the positioning device includes a vertical gutter that connects one end to the buried pipe, and a cross gutter that is connected to intersect the other end of the vertical gutter. Characterized in that the embedded pipe is prevented from rising by obtaining a reaction force from the positioning device,
No foundation method for buried pipes.
JP2004377883A 2004-12-27 2004-12-27 Baseless construction method for buried pipe Pending JP2006183779A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004377883A JP2006183779A (en) 2004-12-27 2004-12-27 Baseless construction method for buried pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004377883A JP2006183779A (en) 2004-12-27 2004-12-27 Baseless construction method for buried pipe

Publications (1)

Publication Number Publication Date
JP2006183779A true JP2006183779A (en) 2006-07-13

Family

ID=36737030

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004377883A Pending JP2006183779A (en) 2004-12-27 2004-12-27 Baseless construction method for buried pipe

Country Status (1)

Country Link
JP (1) JP2006183779A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015036499A (en) * 2013-08-14 2015-02-23 国立大学法人 東京大学 Method and jig for preventing lift of underground burial structure
JP2016173141A (en) * 2015-03-17 2016-09-29 株式会社水道技術開発機構 Pipe movement prevention device and fixing method of fluid pipeline system
JP2016188494A (en) * 2015-03-30 2016-11-04 大成建設株式会社 Tube sewer construction method and underground flow channel

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015036499A (en) * 2013-08-14 2015-02-23 国立大学法人 東京大学 Method and jig for preventing lift of underground burial structure
JP2016173141A (en) * 2015-03-17 2016-09-29 株式会社水道技術開発機構 Pipe movement prevention device and fixing method of fluid pipeline system
JP2016188494A (en) * 2015-03-30 2016-11-04 大成建設株式会社 Tube sewer construction method and underground flow channel

Similar Documents

Publication Publication Date Title
CN106013191B (en) Environment-friendly type grass planting Concrete Highway protective slope structure and construction method
CN103958780B (en) The method for forming cementing retaining wall
KR20100068597A (en) A shoring method using arch plate pile and h-pile
KR101065017B1 (en) A shoring method using arch plate pile and H-Pile
KR101793037B1 (en) Construction method of permanent wall with retaining wall combined PHC pile and steel pipe
KR100618597B1 (en) Cast in place concrete pile using vibro magnetic shovel hammer, and the construction method of this
KR20090007826A (en) Process of blocking water penetration and blocking earth collapsing by using impermeable wall without strut
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
JP3893056B2 (en) Construction method of underground structure
JP4485006B2 (en) Construction method for underground structures
KR100989984B1 (en) Bult-in timbering roof type tunnel method
CN106917331B (en) Water-stopping reinforced roadbed structure for deep-buried karst region and construction method thereof
JP2006183779A (en) Baseless construction method for buried pipe
KR20190072213A (en) Method Of Ground Half-Openning For Tunnel Excavation
KR200296444Y1 (en) Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method
KR20170035321A (en) Retaining wall construction method and retaining wall structure by the method
JP4761052B2 (en) Precast box culvert excavation method without margin
KR102149709B1 (en) Deformation prevention method of files for retaining wall of underground
KR102625776B1 (en) Construction method of CIP retaining wall with improved water protection and ground subsidence prevention function
CN109763518A (en) A kind of construction method of basement post-pouring zone
KR200297427Y1 (en) Retaining Pile for Retaining Wall Engineer
KR102610909B1 (en) Method and structure of steel pipe propulsion using anchor installation inside steel pipe to prevent sinking
JPH07300845A (en) Preventive method against liquefaction of underground linear structure
JP3841679B2 (en) Ground improvement method
JP3612524B2 (en) Septic tank installation and construction method