JP2006106829A - Apparatus and program for production scheduling - Google Patents

Apparatus and program for production scheduling Download PDF

Info

Publication number
JP2006106829A
JP2006106829A JP2004288512A JP2004288512A JP2006106829A JP 2006106829 A JP2006106829 A JP 2006106829A JP 2004288512 A JP2004288512 A JP 2004288512A JP 2004288512 A JP2004288512 A JP 2004288512A JP 2006106829 A JP2006106829 A JP 2006106829A
Authority
JP
Japan
Prior art keywords
load
resources
order
resource
date
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP2004288512A
Other languages
Japanese (ja)
Inventor
Akira Sakurai
陽 桜井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Toshiba Digital Solutions Corp
Original Assignee
Toshiba Corp
Toshiba Solutions Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp, Toshiba Solutions Corp filed Critical Toshiba Corp
Priority to JP2004288512A priority Critical patent/JP2006106829A/en
Publication of JP2006106829A publication Critical patent/JP2006106829A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a production scheduling apparatus, etc. capable of efficiently allocating resources. <P>SOLUTION: The apparatus includes a PERT calculation means 52 for executing PERT calculation which calculates forward paths and backward paths with the respective number of resources ranging from the number of minimally required resources to the number of maximally required resources for each order in the process of an arbitrary number of resources; a loading processing means 53 for extracting the result of the PERT calculation calculated at the maximally required number of resources through the forward path for each order, and based on the extracted PERT calculation result for loading so as not to exceed the maximally required resources per unit time, and for calculating the number of mean required resources per unit time in a scheduling object period; and a load distribution processing means 34 for distributing the load so as not to exceed the mean requested resources in the past direction. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

本発明は、製品を製造するために、最小必要資源数と最大必要資源数との間の所定の資源数で作業が実行される任意資源数工程において、単位時間ごとに必要な資源数を平準化し、最適な資源数を算出する生産スケジューリング装置および生産スケジューリングプログラムに関する。   The present invention equalizes the required number of resources per unit time in an arbitrary number of resources process in which work is performed with a predetermined number of resources between the minimum required resource count and the maximum required resource count to manufacture a product. The present invention relates to a production scheduling apparatus and a production scheduling program that calculate the optimal number of resources.

昨今、工場のライン作業などにおける製品の製造において、製造される製品品目や、その製品品目に利用する資源の割付が、コンピュータによって行われている。ここで「資源」とは、穴明機、研磨機などの製造機器はもちろんのこと、作業員なども含まれる。オーダ(製造製品の注文)が入力されると、コンピュータは、オーダされた製品を納期内に納められるように、資源の作業時間および製造対象の製品品目を割り付け、いつ、何を製造するかを決定する。   In recent years, in the manufacture of products in factory line work or the like, the product items to be manufactured and the resources used for the product items are allocated by a computer. Here, “resources” include not only manufacturing equipment such as drilling machines and polishing machines but also workers. When an order (manufactured product order) is entered, the computer allocates the resource working time and the product item to be manufactured so that the ordered product can be delivered within the due date, and when and what to manufacture. decide.

この資源の割付は、アクティビティと呼ばれる時間単位ごとに行われる。このアクティビティは、製造装置の稼働時間や作業員のシフト時間などに応じて、例えば、1時間または1日などの時間が予め設定される。資源の割付においては、このアクティビティと、製造装置または作業員などの資源と、そのアクティビティにその資源を利用する負荷が関連づけられる。ここで負荷とは、このアクティビティにその資源を利用する製品品目(あるいはオーダ)である。   This resource allocation is performed for each time unit called an activity. For this activity, a time such as one hour or one day is preset according to the operating time of the manufacturing apparatus, the shift time of the worker, and the like. In resource allocation, this activity is associated with a resource such as a manufacturing apparatus or a worker, and a load that uses the resource is associated with the activity. Here, the load is a product item (or order) that uses the resource for this activity.

このとき、例えば作業員などは、その調達人数に応じて資源数を任意に変更しやすい。しかし、作業員の雇用状況を考慮すると、なるべく同じ人数を継続して調達することが人員配置の手続上の便宜等の観点から好ましい。また、製造装置などにおいても、その資源数を任意に変更できる場合でも、なるべく同じ数で継続して調達することが好ましい。   At this time, for example, a worker or the like can easily change the number of resources arbitrarily according to the number of procurement personnel. However, in consideration of the employment situation of workers, it is preferable from the viewpoint of convenience in personnel allocation procedures to continuously procure the same number as possible. In addition, even in a manufacturing apparatus or the like, even when the number of resources can be arbitrarily changed, it is preferable to continuously procure as much as possible.

従って、資源の割付においては、アクティビティにおける負荷を平準化することにより、必要となる資源数を平準化することが求められている。   Therefore, in the resource allocation, it is required to level the number of necessary resources by leveling the load in the activity.

例えば、操業制約の多い他品種工程においても実用的な精算計画を作成する工程負荷調整装置がある(例えば、特許文献1参照)。この特許文献1記載の装置においては、工程情報メモリ、製品情報メモリに格納させた数量を用いて、工程ごとに山積を行い、結果を作業割付テーブルに登録する。負荷山崩は、最も負荷の大きいセグメントを山崩対象とし、セグメントが作業割付可能機関の端に、該当する製品の作業を移動する。作業割付テーブルの全セグメントの負荷が登録された工程能力以下になるまで繰り返す。   For example, there is a process load adjustment device that creates a practical payment plan even in other types of processes with many operational restrictions (see, for example, Patent Document 1). In the apparatus described in Patent Document 1, a pile is made for each process using the quantities stored in the process information memory and the product information memory, and the result is registered in the work allocation table. In the load collapse, the segment with the largest load is targeted for the collapse, and the segment moves the work of the corresponding product to the end of the work assignable engine. Repeat until the load of all segments in the work allocation table is less than the registered process capability.

また、資源の一括調達の時間間隔等に合わせて必要資源の山積値をなるだけ一定に保つ工程計画の自動作成を行う工程計画作成支援方法がある(例えば、特許文献2参照)。この特許文献2においては、作業に要する全期間を複数に区分する区分期間を入力し、作業工程データを用い演算処理によって区分期間に対して資源の量を平準化する。
特開2004−46308号公報 特開平8−255196号公報
In addition, there is a process plan creation support method that automatically creates a process plan that keeps the peak value of necessary resources as constant as possible in accordance with the time interval for batch procurement of resources (see, for example, Patent Document 2). In this patent document 2, a division period for dividing the entire period required for work into a plurality of parts is input, and the amount of resources is leveled with respect to the division period by arithmetic processing using work process data.
JP 2004-46308 A JP-A-8-255196

しかし、これらの特許文献1においては、スケジューリングの開始時点から全ての製品を生産開始したとして、負荷の山積を行い、最も負荷の大きいセグメントを山崩の対象として納期の余裕などを考慮してセグメントを移動させる。この特許文献1に記載の方法においては、山積の開始地点は全て同じになっており、セグメントを移動させる場合に、未来方向に移動させることになる。この場合、納期を遵守できない場合も発生してしまうおそれがある。   However, in these Patent Documents 1, assuming that all products have been produced from the start of scheduling, the load is piled up, and the segment with the largest load is targeted for the landslide and the segments are considered in consideration of the delivery time margin. Move. In the method described in Patent Document 1, the starting points of the piles are all the same, and when moving a segment, it is moved in the future direction. In this case, there may be a case where the delivery date cannot be observed.

また、特許文献2に記載の方法においては、1つのオーダに対する負荷の平準化を可能としているが、複数のオーダに対して負荷を平準化することはできない。   Moreover, in the method described in Patent Document 2, it is possible to level the load for one order, but it is not possible to level the load for a plurality of orders.

このような状況を鑑み、例えば複数のオーダに対してアクティビティにおける負荷を平準化することにより、効率よく資源を割り付ける方法が求められている。   In view of such a situation, there is a demand for a method for efficiently allocating resources by, for example, leveling loads in activities for a plurality of orders.

本発明の目的は、効率よく資源を割り付けることのできる生産スケジューリング装置および生産スケジューリングプログラムを提供することである。   The objective of this invention is providing the production scheduling apparatus and production scheduling program which can allocate a resource efficiently.

上記課題を解決するために、本発明の第1の特徴は、製品品目を製造するために、最小必要資源数と最大必要資源数との間の所定の資源数で作業が実行される任意資源数工程において、単位時間ごとに必要な資源数を平準化し、最適な資源数を算出する生産スケジューリング装置に関する。即ち本発明の第1の特徴に係る生産スケジューリング装置は、製品品目、製造数量、開始可能日および納期を含むオーダ情報と、この製品品目を製造する任意資源数工程で利用される資源名、最小必要資源数、最大必要資源数、単位時間に基づく作業効率が関連づけられた作業工程情報とが記憶される記憶手段と、記憶手段からオーダ情報および作業工程情報とを読み出して、スケジューリングの対象となるオーダのオーダ情報、およびこのオーダ情報に含まれる製品品目に関連づけられた作業工程情報を抽出して、スケジュールデータとして記憶手段に記憶するスケジュールデータ取込手段と、記憶手段からスケジュールデータを読み出し、オーダごとに任意資源数工程において最小必要資源数から最大必要資源数の間のそれぞれの資源数でフォワードパスおよびバックワードパスを算出するPERT計算を実行し、オーダごとに、任意資源数工程における、納期を守る最小必要資源数と最小必要資源数における余裕日数、納期を守る最大必要資源数と最大必要資源数における余裕日数、および最早開始可能日と最遅開始可能日と最遅完了日を算出して、PERT計算結果として記憶手段に記憶するPERT計算手段と、記憶手段からPERT計算結果を読み出して、オーダごとにバックワードパスで最大必要資源数で計算されたPERT計算結果を抽出し、抽出されたPERT計算結果に基づいて単位時間ごとに最大必要資源数を越えない様に負荷山積を行って負荷山積結果として記憶手段に記憶するとともに、スケジューリングの対象となる期間における単位時間あたりの平均必要資源数を算出し、負荷山積結果として記憶手段に記憶する負荷山積処理手段と、記憶手段からPERT計算結果および負荷山積結果を読み出し、PERT計算結果におけるオーダごとの最小必要資源数および最大必要資源数に基づいて過去の方向に平均必要資源数を越えないように負荷山崩を行って、負荷山崩結果として記憶手段に記憶する負荷山崩処理手段とを備える。
ここで、「記憶手段」とは、ハードディスクなどの記憶装置や、RAMなどである。
In order to solve the above-mentioned problem, a first feature of the present invention is that an arbitrary resource whose work is executed with a predetermined number of resources between the minimum number of required resources and the maximum number of required resources to manufacture a product item. The present invention relates to a production scheduling apparatus that equalizes the number of necessary resources per unit time and calculates an optimum number of resources in several processes. That is, the production scheduling apparatus according to the first feature of the present invention includes order information including a product item, a production quantity, a start date and a delivery date, a resource name used in an arbitrary resource number process for producing the product item, a minimum Storage means for storing work process information associated with the required resource count, maximum required resource count, and work efficiency based on unit time, and order information and work process information are read from the storage means, and are subject to scheduling. The order information of the order and the work process information associated with the product item included in the order information are extracted and stored in the storage means as schedule data, the schedule data is read from the storage means, and the order is read out. Each resource number between the minimum required resource number and the maximum required resource number in the arbitrary resource number process for each Execute PERT calculation to calculate the forward path and backward path, and for each order, in the arbitrary resource count process, the minimum required number of resources to protect the delivery date, the number of days required for the minimum required resource count, the maximum required number of resources to protect the delivery date and the maximum PERT calculation means for calculating the number of days required, the earliest start possible date, the latest start possible date, and the latest completion date, and storing them in the storage means as PERT calculation results, and reading the PERT calculation results from the storage means For each order, the PERT calculation result calculated with the maximum required number of resources is extracted in the backward path, and the load pile is performed so that the maximum required number of resources is not exceeded per unit time based on the extracted PERT calculation result. The result is stored in the storage means as the load pile result, and the average per unit time in the period to be scheduled Calculate the required number of resources and store the load pile processing result in the storage means as the load pile result, read the PERT calculation result and the load pile result from the storage means, and read the PERT calculation result in the minimum necessary resource number and the maximum necessary resource for each order. Load hill-climbing processing means for performing load hill-climbing so as not to exceed the average required number of resources in the past direction based on the number, and storing the load hill-climbing result in the storage means.
Here, the “storage means” is a storage device such as a hard disk, a RAM, or the like.

このような本発明によれば、まず最も厳しい後ろ倒しの条件で負荷山積を行い、平均必要資源数を越えないように過去方向に負荷山崩を行うを行うことにより、納期を遵守しつつ、資源数を平準化することができる。   According to the present invention as described above, the load pile is first performed under the most severe postponement conditions, and the load collapse is performed in the past direction so as not to exceed the average required number of resources. Numbers can be leveled.

本発明の第2の特徴は、コンピュータに、製品品目を製造するために、最小必要資源数と最大必要資源数との間の所定の資源数で作業が実行される任意資源数工程において、単位時間ごとに必要な資源数を平準化し、最適な資源数を算出させる生産スケジューリングプログラムに関する。即ち本発明の第2の特徴に係る生産スケジューリングプログラムは、 記憶手段から、製品品目、製造数量、開始可能日および納期を含むオーダ情報と、この製品品目を製造する任意資源数工程で利用される資源名、最小必要資源数、最大必要資源数、単位時間に基づく作業効率が関連づけられた作業工程情報とを読み出し、スケジューリングの対象となるオーダが記憶されたオーダ情報、およびこのオーダ情報に含まれる製品品目に関連づけられた作業工程情報とを抽出して、スケジュールデータとして記憶手段に記憶するスケジュールデータ取込手段と、記憶手段からスケジュールデータを読み出し、オーダごとに任意資源数工程において最小必要資源数から最大必要資源数の間のそれぞれの資源数でフォワードパスおよびバックワードパスを算出するPERT計算を実行し、オーダごとに、任意資源数工程における、納期を守ることのできる最小必要資源数と最小必要資源数における余裕日数、納期を守ることのできる最大必要資源数と最大必要資源数における余裕日数、および最早開始可能日と最遅開始可能日と最遅完了日を算出して、PERT計算結果として記憶手段に記憶するPERT計算手段と、記憶手段からPERT計算結果を読み出して、オーダごとにバックワードパスで最大必要資源数で計算されたPERT計算結果を抽出し、抽出されたPERT計算結果に基づいて単位時間ごとに最大必要資源数を越えない様に負荷山積を行って負荷山積結果として記憶手段に記憶するとともに、スケジューリングの対象となる期間における単位時間あたりの平均必要資源数を算出し、負荷山積結果として記憶手段に記憶する負荷山積処理手段と、記憶手段からPERT計算結果および負荷山積結果とを読み出し、PERT計算結果におけるオーダごとの最小必要資源数および最大必要資源数に基づいて過去の方向に平均必要資源数を越えないように負荷山崩を行って、負荷山崩結果として記憶手段に記憶する負荷山崩処理手段とをコンピュータに実行させる。   The second feature of the present invention is that, in order to produce a product item in a computer, in an arbitrary resource number process in which an operation is performed with a predetermined number of resources between the minimum required resource number and the maximum required resource number. The present invention relates to a production scheduling program that equalizes the number of necessary resources every hour and calculates the optimum number of resources. That is, the production scheduling program according to the second feature of the present invention is used in the ordering information including the product item, the production quantity, the startable date and the delivery date from the storage means, and the arbitrary resource number process for producing the product item. Reads work process information associated with work efficiency based on resource name, minimum required resource number, maximum required resource number, and unit time, order information in which the order to be scheduled is stored, and included in this order information The work process information associated with the product item is extracted and stored in the storage means as schedule data, and the schedule data fetching means is read out, and the schedule data is read out from the storage means. Forward path and backward with each resource number between 1 and the maximum required resource number For each order, the minimum required number of resources that can meet the delivery date, the number of days required for the minimum required number of resources, the maximum number of required resources that can meet the delivery date, and The PERT calculation means for calculating the margin days in the maximum required number of resources, the earliest start possible date, the latest start possible date and the latest completion date and storing them in the storage means as the PERT calculation results, and the PERT calculation results from the storage means Read and extract the PERT calculation result calculated with the maximum required number of resources in the backward path for each order, and based on the extracted PERT calculation result, calculate the load pile so as not to exceed the maximum required number of resources per unit time And store it in the storage means as the load pile result, and the average number of required resources per unit time in the period to be scheduled And the load pile processing means for storing the load pile result in the storage means, the PERT calculation result and the load pile result are read from the storage means, and the minimum required resource number and the maximum required resource number for each order in the PERT calculation result are read. Based on this, load collapse is performed so as not to exceed the average number of required resources in the past direction, and the computer executes load load collapse processing means for storing the load collapse result in the storage means.

本発明によれば、効率よく資源を割り付けることのできる生産スケジューリング装置および生産スケジューリングプログラムを提供することができる。   ADVANTAGE OF THE INVENTION According to this invention, the production scheduling apparatus and production scheduling program which can allocate a resource efficiently can be provided.

次に、図面を参照して、本発明の実施の形態を説明する。以下の図面の記載において、同一または類似の部分には同一または類似の符号を付している。   Next, embodiments of the present invention will be described with reference to the drawings. In the following description of the drawings, the same or similar parts are denoted by the same or similar reference numerals.

(最良の実施の形態)
図1に示すように、本発明の最良の実施の形態に係る生産スケジューリング装置1は、中央処理制御装置101および記憶装置107を備えているコンピュータに所定のソフトウェアプログラムが実行されることによって実現される。本発明の最良の実施の形態に係る生産スケジューリング装置1は、製品品目を製造するために、最小必要資源数と最大必要資源数との間の所定の資源数で作業が実行される任意資源数工程において、アクティビティ(単位時間)ごとに必要な資源数を平準化し、最適な資源数を算出する。本発明の最良の実施の形態においては、1アクティビティを1日として説明する。ここで本発明の最良の実施の形態において任意資源数工程とは、所定の製品を製造するための作業工程フローにおいて、作業員などの資源数を任意に決定できる工程のことである。例えば、1人でも3人でも作業可能である工程を任意資源数工程と呼ぶ。この任意資源数工程において、1人で作業した場合と3人で作業した場合とでは、製品の製造に必要な日数が異なる。本発明の最良の実施の形態においては、例えば顧客からの注文(オーダ)に応じて製品を生産する受注生産方式において、顧客から入力されたオーダ情報に基づいて、製品品目を製造するための資源を割り当てる。このオーダ情報は、例えば、顧客からの注文単位で採番されたオーダ識別子に、顧客名、注文する製品品目、数量、納期などが関連づけられる。本発明の最良の実施の形態においては、特に複数のオーダについて、納期を守りつつ、任意資源数工程における資源数を平準化することのできる生産スケジューリング装置1を説明する。
(Best Embodiment)
As shown in FIG. 1, the production scheduling apparatus 1 according to the preferred embodiment of the present invention is realized by executing a predetermined software program on a computer having a central processing control apparatus 101 and a storage apparatus 107. The The production scheduling apparatus 1 according to the preferred embodiment of the present invention is an arbitrary resource number in which work is executed with a predetermined resource number between the minimum necessary resource number and the maximum required resource number in order to manufacture a product item. In the process, the number of necessary resources is leveled for each activity (unit time), and the optimum number of resources is calculated. In the best mode of the present invention, one activity is described as one day. Here, in the best embodiment of the present invention, the arbitrary resource number step is a step in which the number of resources such as workers can be arbitrarily determined in a work process flow for manufacturing a predetermined product. For example, a process in which one or three people can work is called an arbitrary resource number process. In this arbitrary resource number process, the number of days required for manufacturing a product differs depending on whether the work is performed by one person or three persons. In the best mode of the present invention, for example, in a build-to-order manufacturing method for producing a product in response to an order (order) from a customer, a resource for producing a product item based on order information input from the customer Assign. In the order information, for example, a customer name, a product item to be ordered, a quantity, a delivery date, and the like are associated with an order identifier numbered in an order from a customer. In the preferred embodiment of the present invention, a production scheduling apparatus 1 capable of leveling the number of resources in an arbitrary number of resources process while keeping a delivery date especially for a plurality of orders will be described.

(生産スケジューリング装置のハードウェア構成図)
図2に示すように、本発明の最良の実施の形態に係る生産スケジューリング装置1は、中央処理制御装置101、ROM(Read Only Memory)102、RAM(Random Access Memory)103および入出力インタフェース109が、バス110を介して接続されている。入出力インタフェース109には、入力装置104、表示装置105、通信制御装置106、記憶装置107およびリムーバブルディスク108が接続されている。
(Hardware configuration diagram of production scheduling device)
As shown in FIG. 2, the production scheduling apparatus 1 according to the preferred embodiment of the present invention includes a central processing control device 101, a ROM (Read Only Memory) 102, a RAM (Random Access Memory) 103, and an input / output interface 109. Are connected via a bus 110. An input device 104, a display device 105, a communication control device 106, a storage device 107, and a removable disk 108 are connected to the input / output interface 109.

中央処理制御装置101は、入力装置104からの入力信号に基づいてROM102から生産スケジューリング装置1を起動するためのブートプログラムを読み出して実行し、更に記憶装置107に記憶されたオペレーティングシステムを読み出す。更に中央処理制御装置101は、入力装置104や通信制御装置106などの入力信号に基づいて、各種装置の制御を行ったり、RAM103や記憶装置107などに記憶されたプログラムおよびデータを読み出してRAM103にロードするとともに、RAM103から読み出されたプログラムのコマンドに基づいて、データの計算または加工など、後述する一連の処理を実現する処理装置である。   The central processing control device 101 reads and executes a boot program for starting the production scheduling device 1 from the ROM 102 based on an input signal from the input device 104, and further reads an operating system stored in the storage device 107. Further, the central processing control device 101 controls various devices based on input signals from the input device 104, the communication control device 106, etc., and reads programs and data stored in the RAM 103, the storage device 107, etc., into the RAM 103. A processing device that loads and implements a series of processing described later, such as data calculation or processing, based on a program command read from the RAM 103.

入力装置104は、操作者が各種の操作を入力するキーボード、マウスなどの入力デバイスにより構成されており、操作者の操作に基づいて入力信号を作成し、入出力インタフェース109およびバス110を介して中央処理制御装置101に送信される。表示装置105は、CRT(Cathode Ray Tube)ディスプレイや液晶ディスプレイなどであり、中央処理制御装置101からバス110および入出力インタフェース109を介して表示装置105において表示させる出力信号を受信し、例えば中央処理制御装置101の処理結果などを表示する装置である。通信制御装置106は、LANカードやモデムなどの装置であり、生産スケジューリング装置1をインターネットやLANなどの通信ネットワークに接続する装置である。通信制御装置106を介して通信ネットワークと送受信したデータは入力信号または出力信号として、入出力インタフェースおよびバス110を介して中央処理制御装置101に送受信される。   The input device 104 includes input devices such as a keyboard and a mouse through which an operator inputs various operations. The input device 104 generates an input signal based on the operation of the operator, and inputs via the input / output interface 109 and the bus 110. It is transmitted to the central processing control apparatus 101. The display device 105 is a CRT (Cathode Ray Tube) display, a liquid crystal display, or the like, and receives an output signal to be displayed on the display device 105 from the central processing control device 101 via the bus 110 and the input / output interface 109. It is a device that displays the processing result of the control device 101 and the like. The communication control device 106 is a device such as a LAN card or a modem, and is a device that connects the production scheduling device 1 to a communication network such as the Internet or a LAN. Data transmitted / received to / from the communication network via the communication control device 106 is transmitted / received to / from the central processing control device 101 via the input / output interface and the bus 110 as an input signal or an output signal.

記憶装置107は半導体記憶装置や磁気ディスク装置であって、中央処理制御装置101で実行されるプログラムやデータが記憶されている。リムーバブルディスク108は、光ディスクやフレキシブルディスクのことであり、ディスクドライブによって読み書きされた信号は、入出力インタフェース109およびバス110を介して中央処理制御装置101に送受信される。   The storage device 107 is a semiconductor storage device or a magnetic disk device, and stores programs and data executed by the central processing control device 101. The removable disk 108 is an optical disk or a flexible disk, and signals read / written by the disk drive are transmitted / received to / from the central processing control apparatus 101 via the input / output interface 109 and the bus 110.

本発明の最良の実施の形態に係る生産スケジューリング装置1の記憶装置107には、オーダ情報記憶部21、作業工程フロー情報記憶部22、作業工程情報記憶部23、資源グループ情報記憶部24、資源情報記憶部25、スケジュールデータ記憶部31、PERT計算結果記憶部32、負荷山積結果記憶部33、負荷山崩結果記憶部34、資源別スケジュール結果記憶部41、オーダ別スケジュール結果記憶部42が記憶されるとともに、生産スケジューリングプログラムが記憶される。この生産スケジューリングプログラムが生産スケジューリング装置1の中央処理制御装置101に読み込まれ実行されることによって、図1に示すようなスケジュールデータ取込手段51、PERT計算手段52、負荷山積処理手段53、負荷山崩処理手段54、スケジュール結果出力手段55が生産スケジューリング装置1に実装される。   The storage device 107 of the production scheduling apparatus 1 according to the preferred embodiment of the present invention includes an order information storage unit 21, a work process flow information storage unit 22, a work process information storage unit 23, a resource group information storage unit 24, a resource An information storage unit 25, a schedule data storage unit 31, a PERT calculation result storage unit 32, a load pile result storage unit 33, a load landslide result storage unit 34, a resource-specific schedule result storage unit 41, and an order-specific schedule result storage unit 42 are stored. In addition, a production scheduling program is stored. When this production scheduling program is read and executed by the central processing control device 101 of the production scheduling device 1, the schedule data fetching means 51, PERT calculation means 52, load pile processing means 53, load load collapse as shown in FIG. A processing unit 54 and a schedule result output unit 55 are mounted on the production scheduling apparatus 1.

図1および図2において、本発明の最良の実施の形態に係る生産スケジューリング装置1を説明したが、1つのハードウェア上に実装される必要はない。例えば、オーダ情報記憶部21、作業工程フロー情報記憶部22、作業工程情報記憶部23、資源グループ情報記憶部24、資源情報記憶部25は、生産スケジューリング装置1に内蔵された記憶装置107に記憶されている必要はなく、例えば生産管理システムなどの異なるハードウェアに実装された記憶装置に記憶され、通信制御装置などを介して生産スケジューリング装置1に読み出されても良い。また、記憶装置107に記憶された各データは、RAM103などの記憶装置に記憶されても良い。具体的には、スケジュールデータ記憶部31、PERT計算結果記憶部32、負荷山積結果記憶部33、負荷山崩結果記憶部34などの、中央処理制御装置101において実現された各手段によって出力される一時ファイルは、RAM103に記憶されても良い。   1 and 2, the production scheduling apparatus 1 according to the preferred embodiment of the present invention has been described. However, it is not necessary to be mounted on one piece of hardware. For example, the order information storage unit 21, work process flow information storage unit 22, work process information storage unit 23, resource group information storage unit 24, and resource information storage unit 25 are stored in the storage device 107 built in the production scheduling apparatus 1. For example, it may be stored in a storage device mounted on different hardware such as a production management system and read to the production scheduling device 1 via a communication control device or the like. Each data stored in the storage device 107 may be stored in a storage device such as the RAM 103. Specifically, temporary data output by each means realized in the central processing control device 101 such as the schedule data storage unit 31, the PERT calculation result storage unit 32, the load pile result storage unit 33, and the load hill collapse result storage unit 34. The file may be stored in the RAM 103.

(生産スケジューリング装置の概説)
次に、図1および図3を参照して、本発明の最良の実施の形態に係る生産スケジューリング装置1の概略を説明する。
(Outline of production scheduling equipment)
Next, an outline of the production scheduling apparatus 1 according to the preferred embodiment of the present invention will be described with reference to FIG. 1 and FIG.

まず、ステップS101において、スケジュールデータ取込手段51は、スケジュールデータの作成処理を行う。ここでは、オーダ情報記憶部21などからスケジューリングの対象となるオーダと、そのオーダに含まれる製品品目に関する作業工程フロー情報、作業工程情報、資源グループ情報、資源情報などを抽出し、スケジュールデータ記憶部31に記憶する。ステップS102において、全てのスケジュールデータが読み込まれたことが確認されると、ステップS103に進む。   First, in step S101, the schedule data fetching means 51 performs a process for creating schedule data. Here, an order to be scheduled is extracted from the order information storage unit 21 and the like, and work process flow information, work process information, resource group information, resource information, etc. relating to the product items included in the order are extracted, and a schedule data storage unit 31. When it is confirmed in step S102 that all schedule data has been read, the process proceeds to step S103.

ステップS103において、PERT(Program Evaluation and Review Technique)計算手段52は、オーダごとに任意資源数工程において最小必要資源数から最大必要資源数の間のそれぞれの資源数でフォワードパスおよびバックワードパスを算出するPERT計算を実行し、オーダごとに、任意資源数工程における、納期を守ることのできる最小必要資源数と最小必要資源数における余裕日数、納期を守ることのできる最大必要資源数と最大必要資源数における余裕日数、および最早開始可能日と最早完了日と最遅開始可能日と最遅完了日などを算出して、PERT計算結果記憶部32に記憶する。ステップS104において全てのオーダについてPERT計算が行われたことが確認されると、ステップS105に進む。   In step S103, PERT (Program Evaluation and Review Technique) calculating means 52 calculates a forward path and a backward path with each resource number between the minimum required resource number and the maximum required resource number in an arbitrary resource number process for each order. For each order, the minimum required number of resources that can meet the delivery date, the number of days required for the minimum required number of resources, the maximum required number of resources that can meet the delivery date, and the maximum required resource The marginal number of days, the earliest start possible date, the earliest completion date, the latest start possible date, the latest completion date, and the like are calculated and stored in the PERT calculation result storage unit 32. If it is confirmed in step S104 that PERT calculation has been performed for all orders, the process proceeds to step S105.

ここで、PERT計算とは、例えば複数の製造工程を経て製品を生産するための生産計画において、アクティビティごとに日程管理や工程管理を行う手法である。PERT計算では、例えば1アクティビティを1日にした場合、所定の生産計画について予め定められた着手日と完了日(納期)に基づいて、その生産計画における製品を製造するための個々の製造工程について着手日や完了日などの工程計画を決定する。このとき、完了日を基準として個々の製造工程の完了日を逆算して決められた工程計画はバックワードパスと呼ばれ、生産計画の完了日を厳守するためにはこれより遅れることが許されない最遅の工程計画である。一方、着手日を基準として個々の製造工程の着手日を計算して求められた工程計画はフォワードパスと呼ばれ、これ以上早く製造することが許されない最早の工程計画である。また、バックワードパスにおける最初の製造工程の着手日が、生産計画において予め定められた着手日と同じ場合、或いはフォワードパスにおける最終の製造工程の完了日が、生産計画において予め定められた完了日と同じ場合、その工程計画はクリティカルパスと呼ばれ、余裕日がないことを示す。本発明の最良の実施の形態においては、任意資源数工程においては、資源数に応じてその工程に必要なアクティビティ数が異なるので、任意資源数のそれぞれに応じてPERT計算される。   Here, PERT calculation is a method of performing schedule management and process management for each activity in a production plan for producing a product through a plurality of manufacturing processes, for example. In PERT calculation, for example, when one activity is set to one day, each manufacturing process for manufacturing a product in the production plan based on a predetermined start date and completion date (delivery date) for a predetermined production plan. Determine the process plan such as start date and completion date. At this time, the process plan determined by calculating back the completion date of each manufacturing process based on the completion date is called a backward pass, and it is not allowed to be late to strictly observe the completion date of the production plan. This is the latest process plan. On the other hand, the process plan obtained by calculating the start date of each manufacturing process on the basis of the start date is called a forward pass, and is the earliest process plan that is not allowed to manufacture any earlier. In addition, when the start date of the first manufacturing process in the backward pass is the same as the start date determined in advance in the production plan, or the completion date of the final manufacturing process in the forward pass is the completion date determined in advance in the production plan The process plan is called a critical path, indicating that there are no spare days. In the preferred embodiment of the present invention, in the arbitrary resource number process, since the number of activities required for the process differs depending on the number of resources, PERT calculation is performed for each of the arbitrary resource numbers.

ステップS105において、負荷山積処理手段53は、記憶装置107からPERT計算結果記憶部32を読み出して、オーダごとにバックワードパスで最大必要資源数で計算されたPERT計算結果を抽出し、抽出されたPERT計算結果に基づいてアクティビティごとに最大必要資源数を越えない様に負荷山積を行って負荷山積結果記憶部33に記憶するとともに、スケジューリングの対象となる期間におけるアクティビティあたりの平均必要資源数を算出し、負荷山積結果記憶部33に記憶する。ステップS106において全てのオーダについて負荷山積処理が行われたことが確認されると、ステップS107に進む。   In step S105, the load pile processing means 53 reads the PERT calculation result storage unit 32 from the storage device 107, and extracts and extracts the PERT calculation result calculated with the maximum required number of resources in the backward path for each order. Based on the PERT calculation result, a load pile is calculated for each activity so as not to exceed the maximum necessary resource number, and is stored in the load pile result storage unit 33, and an average necessary resource number per activity during the period to be scheduled is calculated. And stored in the load pile result storage unit 33. When it is confirmed in step S106 that load pile processing has been performed for all orders, the process proceeds to step S107.

ステップS107において、負荷山崩処理手段54は、記憶装置107からPERT計算結果記憶部32および負荷山積結果記憶部33とを読み出し、PERT計算結果におけるオーダごとの最小必要資源数および最大必要資源数に基づいて過去の方向に平均必要資源数を越えないように負荷山崩を行って、負荷山崩結果記憶部34に記憶する。ステップS108において全てのオーダについて負荷山崩処理が行われたことが確認されると、ステップS109に進む。   In step S107, the load collapse processing unit 54 reads the PERT calculation result storage unit 32 and the load pile result storage unit 33 from the storage device 107, and based on the minimum required resource number and the maximum required resource number for each order in the PERT calculation result. Then, load collapse is performed so as not to exceed the average required number of resources in the past direction, and the result is stored in the load collapse result storage unit 34. If it is confirmed in step S108 that the load leveling process has been performed for all orders, the process proceeds to step S109.

ステップS109において、スケジュール結果出力手段55は、記憶装置107から負荷山崩結果記憶部34を読み出して、資源ごとおよびアクティビティごとに資源に割り当てられたオーダを関連づけて資源別スケジュール結果記憶部41に記憶し、オーダごとに割り当てられた資源と納期予定とを関連づけてオーダ別スケジュール結果記憶部42に記憶する。   In step S109, the schedule result output means 55 reads the load devastating result storage unit 34 from the storage device 107, associates the order assigned to the resource for each resource and for each activity, and stores it in the resource-specific schedule result storage unit 41. The resource allocated for each order is associated with the delivery schedule and stored in the order-specific schedule result storage unit 42.

このように、本発明の最良の実施の形態に係る生産スケジューリング装置1は、予め、各オーダについてバックワードパスおよびフォワードパスを算出し、納期を守ることのできる最早開始可能日、最遅開始可能日および最遅完了日を算出する。   As described above, the production scheduling apparatus 1 according to the best embodiment of the present invention calculates the backward path and the forward path for each order in advance and can start the earliest possible start date and the latest start possible date. Calculate the date and latest completion date.

次に、納期を守るための最も厳しい後ろ倒しの条件で負荷山積を実行するとともに、平均必要資源数を算出する。更に、PERT計算で計算された情報に基づいて、平均必要資源数を越えない様に過去方向に負荷山崩を行う。   Next, load piles are executed under the strictest postponement conditions to keep the delivery date, and the average required number of resources is calculated. Further, based on the information calculated by PERT calculation, load collapse is performed in the past direction so as not to exceed the average required number of resources.

これにより、本発明の最良の実施の形態に係る生産スケジューリング装置1は、まず最も厳しい後ろ倒しの条件で負荷山積を行い、平均必要資源数を越えないように過去方向に負荷山崩を行うことにより、納期を遵守しつつ、資源数を平均必要資源数以内に収まるように平準化することができる。   As a result, the production scheduling apparatus 1 according to the best embodiment of the present invention first performs load accumulation under the most severe postponement conditions, and performs load collapse in the past direction so as not to exceed the average required number of resources. The number of resources can be leveled within the average required number of resources while complying with the delivery date.

(生産スケジューリング装置の詳説)
次に、図1を参照して、本発明の最良の実施の形態に係る生産スケジューリング装置1の各データおよび各手段について詳述する。
(Detailed explanation of production scheduling equipment)
Next, with reference to FIG. 1, each data and each means of the production scheduling apparatus 1 which concerns on the best embodiment of this invention are explained in full detail.

オーダ情報記憶部21は、図4に示すように、オーダ識別子ごとに、オーダされた製品品目、製造数量、着手可能日、納期などが関連づけられて記憶されている。このオーダ情報記憶部21は、顧客から入力されたオーダに基づいて、生産計画の対象となる製品品目および製造数量についてのみが記載されても良い。ここで、着手可能日は、製造するための部品の調達日や資源の納入日などによって、製品の製造に関する全ての情報を扱う生産管理システムにおいて決定され、本発明の最良の実施の形態に係る生産スケジューリング装置によって資源の割付可能な日である。また納期は、客先への製品の納入リードタイムなどを考慮した納期であって、本発明の最良の実施の形態に係る生産スケジューリング装置が目標とする納期である。   As shown in FIG. 4, the order information storage unit 21 stores the ordered product item, production quantity, available start date, delivery date, and the like in association with each other. The order information storage unit 21 may describe only the product item and the production quantity that are the targets of the production plan based on the order input from the customer. Here, the available start date is determined in the production management system that handles all information related to the manufacture of the product, depending on the date of procurement of the parts to be manufactured and the date of delivery of the resources, and is related to the best mode of the present invention. It is a day when resources can be allocated by the production scheduling device. The delivery date is a delivery date considering the delivery lead time of the product to the customer, and is the delivery date targeted by the production scheduling apparatus according to the best mode of the present invention.

作業工程フロー情報記憶部22は、図5に示すように、製品品目ごとに、この製品目を製造するために必要な工程が順番に関連づけられている。   As shown in FIG. 5, the work process flow information storage unit 22 associates the processes necessary for manufacturing the product item in order for each product item.

作業工程情報記憶部23は、図6に示すように、製品品目および当該製品品目を製造するために必要な工程ごとに、使用する資源名、資源数(例;機械の台数、人員数)、所定時間あたりの作業効率が関連づけられて記憶されている。この作業効率は、アクティビティあたりの作業個数で表されることが好ましい。ここで、「包装工程」の様に、資源数が「1〜5人」と設定されている工程を、本発明の最良の実施の形態において任意資源数工程と定義する。ここで、最小の資源数である「1人」が最小必要資源数であり、「5人」が最大必要資源数である。この任意資源数工程においては、資源数に応じてこの工程に必要とするアクティビティが異なる。具体的には、図6に示した例では、作業効率が「200個/1人日」である。この条件において1000個の製品を製造する場合、包装人員1人および1アクティビティ(1日)あたり200個を作業することができるので、包装人員を1人にするとこの包装工程には5日を要し、包装人員を5人にすると、この包装工程には1日を要す。このような任意資源数工程においては、納期や他の資源と考慮して、任意の資源数を指定して作業することができる。   As shown in FIG. 6, the work process information storage unit 23 stores the name of the resource used, the number of resources (eg, the number of machines, the number of personnel) for each product item and each process necessary for manufacturing the product item, The work efficiency per predetermined time is associated and stored. This work efficiency is preferably represented by the number of work per activity. Here, a process in which the number of resources is set to “1 to 5 people” as in the “packaging process” is defined as an arbitrary resource number process in the best embodiment of the present invention. Here, “1 person”, which is the minimum number of resources, is the minimum required resource number, and “5 persons” is the maximum required resource number. In this arbitrary resource number process, the activity required for this process differs depending on the number of resources. Specifically, in the example shown in FIG. 6, the work efficiency is “200 pieces / person day”. If 1000 products are manufactured under these conditions, it is possible to work with 1 packaging person and 200 pieces per activity (1 day), so if one packaging person is used, this packaging process takes 5 days. However, if the number of packaging personnel is five, this packaging process takes one day. In such an arbitrary resource number process, it is possible to specify an arbitrary number of resources in consideration of delivery date and other resources.

資源グループ情報記憶部24は、図7に示すように、工程ごとに使用可能な資源の保有数と、その資源名が関連づけられている。   As shown in FIG. 7, the resource group information storage unit 24 associates the number of resources that can be used for each process with the resource name.

資源情報記憶部25には、図8に示すように、資源名ごとおよびアクティビティごとにそのスケジュールが記憶されている。図8に示す例においては、包装人員それぞれについて、一日ごとにその包装人員の稼働状況(出勤状況)が関連づけられている。包装人員が出勤しない日は、オーダを割り当てることができない制約条件となる。   As shown in FIG. 8, the resource information storage unit 25 stores the schedule for each resource name and each activity. In the example shown in FIG. 8, the operating status (attendance status) of the packaging personnel is associated with each packaging personnel every day. On days when packaging personnel do not work, there is a constraint that orders cannot be assigned.

スケジュールデータ取込手段51は、記憶装置107からオーダ情報記憶部21、作業工程フロー情報記憶部22、作業工程情報記憶部23、資源グループ情報記憶部24、資源情報記憶部25などを読み出して、スケジューリングの対象となるオーダのオーダ情報と、オーダ情報に含まれる製品品目に関連づけられた作業工程フロー情報、作業工程情報、資源グループ情報、資源情報などを抽出して、スケジュールデータ記憶部31に記憶する。オーダ情報記憶部21、作業工程フロー情報記憶部22、作業工程情報記憶部23、資源グループ情報記憶部24、資源情報記憶部25などの情報は、生産管理システムなどの上位システムから、インタフェースを経由して提示されたり、管理者端末などの端末の入力手段から情報が設定されても良い。これらの情報は、外部から記憶装置107に格納され、スケジューリングの対象となるオーダに関するデータが抽出され、そのデータ全てをスケジュールデータ記憶部31として記憶装置107等のメモリに全て取り込み、本処理全てが終了するまで保持される。このスケジュールデータ記憶部31は、RAM103に備えられても良い。   The schedule data fetching means 51 reads the order information storage unit 21, work process flow information storage unit 22, work process information storage unit 23, resource group information storage unit 24, resource information storage unit 25, etc. from the storage device 107, The order information of the order to be scheduled and the work process flow information, work process information, resource group information, resource information, etc. associated with the product item included in the order information are extracted and stored in the schedule data storage unit 31. To do. Information such as the order information storage unit 21, work process flow information storage unit 22, work process information storage unit 23, resource group information storage unit 24, resource information storage unit 25, etc. is sent from an upper system such as a production management system via an interface. Or information may be set from input means of a terminal such as an administrator terminal. These pieces of information are stored in the storage device 107 from the outside, data related to the order to be scheduled is extracted, all of the data is taken into the memory such as the storage device 107 as the schedule data storage unit 31, and all this processing is performed. Holds until finished. The schedule data storage unit 31 may be provided in the RAM 103.

PERT計算手段52は、記憶装置107からスケジュールデータ記憶部31を読み出し、オーダごとに任意資源数工程において最小必要資源数から最大必要資源数の間のそれぞれの資源数でフォワードパスおよびバックワードパスを算出するPERT計算を実行し、オーダごとに、任意資源数工程における、納期を守ることのできる最小必要資源数と最小必要資源数における余裕日数、および納期を守ることのできる最大必要資源数と最大必要資源数における余裕日数、および最早開始可能日、最早完了日、最遅開始可能日および最遅完了日などを算出して、PERT計算結果記憶部32に記憶する。   The PERT calculation means 52 reads the schedule data storage unit 31 from the storage device 107, and performs a forward path and a backward path with each resource number between the minimum required resource number and the maximum required resource number in an arbitrary resource number process for each order. Execute the PERT calculation to calculate the minimum required number of resources that can meet the delivery date, the number of days required for the minimum required resource number, and the maximum required number of resources that can meet the delivery date and the maximum for each order. The margin days in the required number of resources, the earliest start possible date, the earliest completion date, the latest start possible date, the latest completion date, and the like are calculated and stored in the PERT calculation result storage unit 32.

このPERT計算手段52は、例えば図9に示すような処理を行う。
ステップS201において、PERT計算手段は、記憶装置107に展開されたスケジュールデータ記憶部31から、オーダごとに取り出す。ここで、ステップS202において既にスケジュールデータ記憶部31の全てのオーダが取り込まれていた(EOF:End of File)と判断された場合、ステップS208に進む。
This PERT calculation means 52 performs a process as shown in FIG. 9, for example.
In step S <b> 201, the PERT calculation unit extracts each order from the schedule data storage unit 31 expanded in the storage device 107. If it is determined in step S202 that all orders in the schedule data storage unit 31 have already been taken in (EOF: End of File), the process proceeds to step S208.

ステップS203において、ステップS201で抽出されたオーダに関連づけられた作業工程フロー情報および資源情報を抽出する。ここで、この作業工程フロー情報において、複数の資源数が関連づけられた任意資源数工程が含まれている場合、ステップS204において、変数「R」を最小必要資源数として設定し、ステップS205において、このRにおけるフォワードパスおよびバックワードパスによるPERT計算を実行する。   In step S203, the work process flow information and resource information associated with the order extracted in step S201 are extracted. Here, in the work process flow information, when an arbitrary resource number process associated with a plurality of resource numbers is included, in step S204, the variable “R” is set as the minimum required resource number. In step S205, The PERT calculation by the forward path and backward path in R is executed.

次に、ステップS206において「R」をインクリメントし、ステップS207において「R」と最大必要資源数を比較する。「R」が最大必要資源数以下の場合、再びステップS205に戻りPERT計算を実行する。   Next, “R” is incremented in step S206, and “R” is compared with the maximum required resource number in step S207. If “R” is less than or equal to the maximum required number of resources, the process returns to step S205 again to execute PERT calculation.

ステップS207において「R」が最大必要資源数を越える場合、ステップS201に戻り、新たにオーダを抽出する。   If “R” exceeds the maximum required resource number in step S207, the process returns to step S201 to newly extract an order.

このPERT計算が終了した後、ステップS208においてPERT計算手段52は、納期を守れなかった計算パターンを削除する。   After the PERT calculation is completed, in step S208, the PERT calculation means 52 deletes the calculation pattern that failed to meet the delivery date.

このように、PERT計算手段52は、オーダごとに、最小必要資源数から最大必要資源数のそれぞれについてPERT計算を実行して、納期を守ることのできる最小必要資源数と最小必要資源数における余裕日数、および納期を守ることのできる最大必要資源数と最大必要資源数における余裕日数、および最早開始可能日、最早完了日、最遅開始可能日および最遅完了日を算出し、その結果をPERT計算結果記憶部32として記憶装置107等の記憶手段に全て取り込み、本処理全てが終了するまで保持される。例えば、このPERT計算結果記憶部32は、RAM103に備えられても良い。   In this way, the PERT calculation means 52 executes PERT calculation for each of the minimum required resource number to the maximum required resource number for each order, and the margin in the minimum required resource number and the minimum required resource number that can meet the delivery date. Calculate the number of days, the maximum number of required resources that can meet the delivery date, the number of days in the maximum required number of resources, the earliest start possible date, the earliest completion date, the latest start possible date, and the latest completion date, and PERT All of the calculation results are stored in the storage unit such as the storage device 107 as the calculation result storage unit 32 and held until all the processes are completed. For example, the PERT calculation result storage unit 32 may be provided in the RAM 103.

次に、図10ないし図13を参照して、本発明の最良の実施の形態に係る生産スケジューリング装置1のPERT計算手段52の処理について説明する。この図10ないし図13は、図6に示した作業工程に従ってPERT計算されている。   Next, processing of the PERT calculation means 52 of the production scheduling apparatus 1 according to the preferred embodiment of the present invention will be described with reference to FIGS. 10 to 13 are PERT calculated in accordance with the work process shown in FIG.

図10および図11においては、フォワードパスによりPERT計算を行っている。フォワードパスによるPERT計算においては、納期を守れる最小必要資源数および最大必要資源数、最早開始可能日、最早完了日、余裕日数が算出される。ここで、穴明工程、研磨工程のそれぞれの作業効率は、図6に示した例によれば1000個/1日であるので、製品を1000個製造する場合、それぞれ一日の作業日数を要する。
図10においては、3月1日が開始可能日であって3月10日が納期である場合で、包装工程を開始できる最早開始可能日は穴明工程、研磨工程を考慮して3月3日になる。最小必要資源数である1人で作業した場合、3月7日に作業は完了し、納期である3月10日までの余裕日数は3日となる。最大必要資源数である5人で作業した場合、3月3日に作業は完了し、納期である3月10日までの余裕日数は7日となる。図10に示した例においては、任意資源数工程において、指定されたいずれの資源数においても納期を守ることができるので、最小必要資源数は1人でこのときの余裕日数は3日となり、最大必要資源数は5人でこのときの余裕日数は7日となる。また、最大必要資源数の最早開始可能日は3月3日、最早完了日は3月3日となり、最小必要資源数の最早開始可能日は3月3日、最早完了日は3月7日になる。
図11においては、3月1日が開始可能日であって3月5日が納期である場合で、包装工程を開始できる最早開始可能日は穴明工程、研磨工程を考慮して3月3日になる。最小必要資源数である1人で作業した場合、3月7日に作業は完了することになり、納期である3月5日を過ぎてしまう。資源数を2で作業した場合、3月5日に作業は完了し、納期である3月5日までの余裕日数は0日(クリティカルパス)となる。最大必要資源数である5人で作業した場合、3月3日に作業は完了し、納期である3月5日までの余裕日数は2日となる。最大必要資源数である5人で作業した場合、3月3日に作業は完了し、納期である3月5日までの余裕日数は2日となる。図11に示した例においては、任意資源数工程において、指定された資源数のうち2人以上であるときに納期を守ることができるので、最小必要資源数は2人でこのときの余裕日数は0日となり、最大必要資源数は5人でこのときの余裕日数は2日となる。また、最大必要資源数の最早開始可能日は3月3日、最早完了日は3月3日となり、最小必要資源数の最早開始可能日は3月3日、最早完了日は3月5日になる。
10 and 11, PERT calculation is performed by the forward path. In PERT calculation by the forward path, the minimum required resource number and the maximum required resource number that can meet the delivery date, the earliest start possible date, the earliest completion date, and the spare days are calculated. Here, the work efficiency of each of the drilling process and the polishing process is 1000 pieces / day according to the example shown in FIG. 6. Therefore, when 1000 products are manufactured, each work day requires one work day. .
In FIG. 10, when March 1 is the start date and March 10 is the delivery date, the earliest start date when the packaging process can be started is March 3 in consideration of the drilling process and the polishing process. It will be a day. When one person who is the minimum required number of resources is working, the work is completed on March 7, and the remaining days until March 10, which is the delivery date, is three days. When working with 5 people, which is the maximum required number of resources, the work will be completed on March 3, and the remaining days until March 10, which is the delivery date, will be 7 days. In the example shown in FIG. 10, in the arbitrary resource number process, since the delivery date can be maintained for any specified number of resources, the minimum required number of resources is one person and the spare days at this time is 3 days. The maximum required number of resources is 5, and the spare days at this time are 7 days. The earliest possible start date of the maximum required number of resources is March 3, the earliest completion date is March 3, the earliest possible start date of the minimum required number of resources is March 3, and the earliest completion date is March 7. become.
In FIG. 11, when March 1 is the start date and March 5 is the delivery date, the earliest start date when the packaging process can be started is March 3 in consideration of the drilling process and the polishing process. It will be a day. When one person who is the minimum required number of resources works, the work is completed on March 7, and the delivery date of March 5 is passed. When the number of resources is 2, the work is completed on March 5, and the number of days left until March 5, which is the delivery date, is 0 (critical path). When working with 5 people, which is the maximum required number of resources, the work is completed on March 3, and the remaining days until March 5, which is the delivery date, is 2 days. When working with 5 people, which is the maximum required number of resources, the work is completed on March 3, and the remaining days until March 5, which is the delivery date, is 2 days. In the example shown in FIG. 11, in the arbitrary resource number process, the delivery date can be maintained when the number of specified resources is 2 or more, so the minimum required number of resources is 2 people and the number of days allowed at this time Is 0 days, the maximum required number of resources is 5, and the number of spare days at this time is 2 days. The earliest possible start date of the maximum required number of resources is March 3, the earliest completion date is March 3, the earliest possible start date of the minimum required number of resources is March 3, and the earliest completion date is March 5. become.

図12および図13においては、バックワードパスによりPERT計算を行っている。バックワードパスによるPERT計算においては、納期を守れる最小必要資源数および最大必要資源数、最遅開始可能日、最遅完了日、余裕日数が算出される。ここで、穴明工程、研磨工程のそれぞれの作業効率は、図6に示した例によれば1000個/1日であるので、製品を1000個製造する場合、それぞれ一日の作業日数を要する。
図12においては、3月1日が開始可能日であって3月10日が納期である場合で、包装工程を終了する最遅完了日は3月10日になる。最小必要資源数である1人で作業した場合、3月6日に作業を開始することになるので、穴明工程、研磨工程を考慮したこの作業フローの開始可能日である3月1日までの余裕日数は3日となる。最大必要資源数である5人で作業した場合、3月10日に作業を開始することになるので、穴明工程、研磨工程を考慮したこの作業フローの開始可能日である3月1日までの余裕日数は7日となる。図12に示した例においては、任意資源数工程において、指定されたいずれの資源数においても納期を守ることができるので、最小必要資源数は1人でこのときの余裕日数は3日となり、最大必要資源数は5人でこのときの余裕日数は7日となる。また、最大必要資源数の最遅開始可能日は3月10日、最遅完了日は3月10日となり、最小必要資源数の最遅開始可能日は3月6日、最遅完了日は3月10日になる。
図13においては、3月1日が開始可能日であって3月5日が納期である場合で、包装工程を終了する最遅完了日は3月5日になる。最小必要資源数である1人で作業した場合、2月27日(閏年ではない場合であり、閏年の場合には2月28日)に作業を開始することになるので、穴明工程、研磨工程を考慮したこの作業フローの開始可能日である3月1日より過去になってしまう。資源数を2で作業した場合、3月3日に作業を開始することになるので、穴明工程、研磨工程を考慮したこの作業フローの開始可能日である3月1日までの余裕日数は0日(クリティカルパス)となる。最大必要資源数である5人で作業した場合、3月5日に作業を開始することになるので、穴明工程、研磨工程を考慮したこの作業フローの開始可能日である3月1日までの余裕日数は2日となる。図13に示した例においては、任意資源数工程において、指定されたいずれの資源数のうち2人以上であるときに納期を守ることができるので、最小必要資源数は2人でこのときの余裕日数は0日(クリティカルパス)となり、最大必要資源数は5人でこのときの余裕日数は2日となる。また、最大必要資源数の最遅開始可能日は3月3日、最遅完了日は3月5日となり、最小必要資源数の最遅開始可能日は3月3日、最遅完了日は3月5日になる。
12 and 13, PERT calculation is performed by a backward path. In PERT calculation by the backward pass, the minimum required resource number and the maximum required resource number that can meet the delivery date, the latest start possible date, the latest completion date, and the extra days are calculated. Here, the work efficiency of each of the drilling process and the polishing process is 1000 pieces / day according to the example shown in FIG. 6. Therefore, when 1000 products are manufactured, each work day requires one work day. .
In FIG. 12, when March 1 is the startable date and March 10 is the delivery date, the latest completion date for ending the packaging process is March 10. When working with one person, the minimum required number of resources, work will start on March 6th, so until March 1st, which is the start date of this work flow considering the drilling and polishing processes The surplus days will be 3 days. When working with 5 people, the maximum required number of resources, work will start on March 10th, so until March 1st, the start date of this work flow considering the drilling and polishing processes The extra days will be 7 days. In the example shown in FIG. 12, in the arbitrary resource number process, since the delivery date can be maintained for any specified number of resources, the minimum required number of resources is one person and the spare days at this time is three days. The maximum required number of resources is 5, and the spare days at this time are 7 days. Also, the latest possible start date of the maximum required number of resources is March 10th, the latest completion date is March 10th, the latest possible start date of the minimum required number of resources is March 6th, the latest completed date is March 10th.
In FIG. 13, when March 1 is the startable date and March 5 is the delivery date, the latest completion date for ending the packaging process is March 5. When working with one person, which is the minimum required number of resources, work will start on February 27 (if it is not a leap year and February 28 if it is a leap year), so the drilling process, polishing It will be past from March 1st, which is the date when this work flow can be started in consideration of the process. When working with 2 resources, work will start on March 3, so the number of days left until March 1, which is the start date of this work flow considering the drilling process and polishing process, is Day 0 (critical path). When working with the maximum required number of 5 people, work will start on March 5th, so until March 1st, which is the start date of this work flow considering the drilling and polishing processes The surplus days will be 2 days. In the example shown in FIG. 13, in the arbitrary resource number process, since the delivery date can be observed when there are two or more of the specified number of resources, the minimum required number of resources is 2 people at this time. The spare days are 0 days (critical path), the maximum required number of resources is 5, and the spare days at this time is 2 days. Also, the latest possible start date of the maximum required number of resources is March 3 and the latest completion date is March 5. The latest possible start date of the minimum required number of resources is March 3 and the latest complete date is It will be March 5th.

これらのPERT計算結果に基づいて、図14に示すようなデータがPERT計算結果記憶部32に記憶される。PERT計算結果記憶部32には、所定の資源(ここでは作業員)について、オーダごとにPERTの計算結果が記憶される。図14(a)には、オーダごとのフォワードパスによるPERT計算結果である、納期を守れる最小必要資源数および最大必要資源数、最早開始可能日、最早完了日、余裕日数がPERT計算結果記憶部32aに記憶されている。図14(b)には、オーダごとのバックワードパスによるPERT計算によるPERT計算結果である、納期を守れる最小必要資源数および最大必要資源数、最遅開始可能日、最遅完了日、余裕日数がに記憶される。そのほか、最小必要資源数から最大必要資源数までのそれぞれの計算パターンもPERT計算結果記憶部32に記憶される。図14(a)に示す例において最早開始可能日と最早完了日が、図14(b)に示す例において最遅開始可能日と最遅完了日が同一であるが、これは、調達可能な資源数を最大限に利用した場合に一日で各オーダの作業が完了するためである。例えば、調達可能な資源数を最大限利用しても複数日要する場合、最早開始可能日から最早完了日の日数は複数日となり、最遅開始可能日から最遅完了日の日数は複数日となる。   Based on these PERT calculation results, data as shown in FIG. 14 is stored in the PERT calculation result storage unit 32. The PERT calculation result storage unit 32 stores the PERT calculation result for each order for a predetermined resource (in this case, a worker). FIG. 14 (a) shows the PERT calculation result storage unit that is the PERT calculation result by the forward path for each order, and includes the minimum necessary resource number and the maximum required resource number, the earliest start date, the earliest completion date, and the spare days that can meet the delivery date 32a. FIG. 14B shows the result of PERT calculation by PERT calculation using the backward pass for each order, the minimum required resource number and the maximum required resource number that can meet the delivery date, the latest start possible date, the latest completion date, and the extra days. Is memorized. In addition, each calculation pattern from the minimum required resource number to the maximum required resource number is also stored in the PERT calculation result storage unit 32. In the example shown in FIG. 14 (a), the earliest start possible date and the earliest completion date are the same, and in the example shown in FIG. 14 (b), the latest start possible date and the latest completion date are the same. This is because each order can be completed in one day when the number of resources is maximized. For example, if multiple days are required even if the maximum number of resources that can be procured is used, the number of days from the earliest start possible date to the earliest completion date is multiple days, and the date from the latest start possible date to the latest completion date is multiple days. Become.

負荷山積処理手段53は、記憶装置107からPERT計算結果記憶部32を読み出して、オーダごとにバックワードパスで最大必要資源数で計算されたPERT計算結果を抽出し、最遅開始可能日から最遅完了日の間で、アクティビティごとに、最大必要資源数を越えない様に負荷山積を行って負荷山積結果記憶部33に記憶するとともに、スケジューリングの対象となる期間における平均必要資源数を算出し、負荷山積結果記憶部33に記憶する。   The load pile processing means 53 reads the PERT calculation result storage unit 32 from the storage device 107, extracts the PERT calculation result calculated with the maximum required number of resources in the backward path for each order, and extracts the PERT calculation result from the latest possible start date. During the late completion date, for each activity, a load pile is performed so as not to exceed the maximum required resource number, and the load pile result storage unit 33 is stored, and an average necessary resource number in the period to be scheduled is calculated. And stored in the load pile result storage unit 33.

この負荷山積処理手段53は、例えば図15に示すような処理を行う。
まず、ステップS301において、PERT計算結果記憶部32を読み出し、オーダごとにバックワードパスで最大必要資源数で計算された計算結果を抽出する。次に、ステップS302においてステップS301で抽出されたオーダを1件取り出す。このとき、取り出すべきオーダがない場合、ステップS305に進む。
The load pile processing means 53 performs a process as shown in FIG. 15, for example.
First, in step S301, the PERT calculation result storage unit 32 is read, and a calculation result calculated with the maximum required number of resources is extracted for each order by a backward path. Next, in step S302, one order extracted in step S301 is taken out. At this time, if there is no order to be taken out, the process proceeds to step S305.

ステップS303においてオーダを取り出すと、ステップS304において、最遅開始可能日から最遅完了日の範囲で、負荷山積を行う。これにより、オーダごとに許される最も遅いスケジュールを設定することができる。この結果は、逐次、負荷山積結果記憶部33に記憶される。   When the order is taken out in step S303, load accumulation is performed in step S304 in the range from the latest possible start date to the latest completed date. As a result, the latest schedule allowed for each order can be set. This result is sequentially stored in the load pile result storage unit 33.

ステップS304において負荷山積が行われると、ステップS302に戻り次のオーダを抽出する。   When the load pile is performed in step S304, the process returns to step S302 to extract the next order.

このように、ステップS301で抽出された全てのオーダについて、負荷山積されると、ステップS305において、平均必要資源数を算出する。具体的には、アクティビティが日単位である場合、スケジュールの対象となるスケジュール終了日(最も遅い日に割り付けられたオーダの最遅完了日)からスケジュール開始日(或いは現在日)を減算して、アクティビティ数(日数)を算出する。一方、オーダ単位での最大必要資源数を積算し、総負荷量を算出する。このように算出された総負荷量をアクティビティ数で除算して、アクティビティ単位の平均必要資源数を算出する。算出された平均必要資源数は、負荷山積結果記憶部33に記憶される。   As described above, when all the orders extracted in step S301 are loaded, the average required number of resources is calculated in step S305. Specifically, if the activity is daily, subtract the schedule start date (or current date) from the schedule end date (latest completion date of the order assigned to the latest date), Calculate the number of activities (days). On the other hand, the total required amount is calculated by integrating the maximum required number of resources in order units. The total load amount calculated in this way is divided by the number of activities to calculate the average required number of resources for each activity. The calculated average required resource number is stored in the load pile result storage unit 33.

ここで、図16を参照して、負荷山積結果の一例を説明する。図16は、図14(b)に示した結果を参照して作成される。具体的には、オーダAは最遅完了日が3月4日であるので、3月4日に最大必要資源数である3の負荷を山積する。オーダBは最遅完了日が3月5日であるので、3月5日に最大必要資源数である1の負荷を山積する。オーダCは最遅完了日が3月6日であるので、3月6日に最大必要資源数である2の負荷を山積する。オーダDは最遅完了日が3月7日であるので、3月7日に最大必要資源数である5の負荷を山積する。オーダEは最遅完了日が3月8日であるので、3月8日に最大必要資源数である3の負荷を山積する。図16に示す様な負荷山積された結果が、負荷山積結果記憶部33に記憶される。   Here, an example of the load pile result will be described with reference to FIG. FIG. 16 is created with reference to the result shown in FIG. Specifically, since the latest completion date of the order A is March 4, the load of 3 which is the maximum required number of resources is piled up on March 4. Since order B has the latest completion date of March 5, the load of 1 which is the maximum required number of resources is piled up on March 5. Since the latest completion date of the order C is March 6, the load of 2 which is the maximum necessary resource number is piled up on March 6. Since the latest completion date of the order D is March 7, the load of 5 which is the maximum required number of resources is piled up on March 7. Since the latest completion date of the order E is March 8, the load of 3 which is the maximum required number of resources is piled up on March 8. The result of the load pile as shown in FIG. 16 is stored in the load pile result storage unit 33.

負荷山崩処理手段54は、記憶装置107からPERT計算結果記憶部32および負荷山積結果記憶部33を読み出し、PERT計算結果に含まれる最遅完了日から最早開始可能日に過去の方向に平均必要資源数を越えないように負荷山崩を行って、負荷山崩結果記憶部34に記憶する。   The load landslide processing means 54 reads the PERT calculation result storage unit 32 and the load pile result storage unit 33 from the storage device 107, and average required resources in the past direction from the latest completion date included in the PERT calculation result to the earliest start possible date. Load collapse is performed so as not to exceed the number, and the result is stored in the load collapse result storage unit 34.

具体的には、負荷山崩処理手段54は、オーダごとのPERT計算結果について割付優先順位の高いオーダから順に抽出して、最大必要資源数の負荷量で空き負荷を探索し、最大必要資源数と必要平均資源数とを比較する。ここで、必要平均資源数で割付可能であって既に割付済みのオーダの負荷を過去方向に移動可能である場合、割付済みのオーダを過去方向に移動させて移動後の空き負荷に抽出されたオーダの負荷を割り当て、既に割付済みのオーダの負荷を過去方向に移動可能でない場合、空き負荷に抽出されたオーダの負荷を割り当てる。一方、必要平均資源数で割付不可能であって平均必要資源数を越えた負荷を最遅完了日から最早開始日の過去方向へ移動可能である場合、平均必要資源数を越えた負荷を最遅完了日から最早開始日の範囲で過去方向へ移動し、平均必要資源数を越えた負荷を最遅完了日から最早開始日の範囲で過去方向へ移動可能でない場合、最大必要資源数にて割付を行う。   Specifically, the load erosion processing means 54 extracts the PERT calculation results for each order in order from the order with the highest allocation priority, searches for a free load with the load amount of the maximum required resource number, Compare the required average number of resources. Here, if it is possible to assign with the required average number of resources and the load of the already assigned order can be moved in the past direction, the assigned order is moved in the past direction and extracted to the free load after the move. When an order load is assigned and the already assigned order load cannot be moved in the past direction, the extracted order load is assigned to the free load. On the other hand, if the load that cannot be allocated with the required average number of resources and the load that exceeds the average required number of resources can be moved from the latest completion date to the past start date, the load that exceeds the average required number of resources is maximized. If the load that exceeds the average required number of resources moves in the past direction from the latest completion date to the earliest start date, and if it is not possible to move in the past direction from the latest completion date to the earliest start date, the maximum required resource number Perform allocation.

この負荷山崩処理手段54は、例えば図17に示すような処理を行う。
まず、ステップS401において、余裕日数の少ない順など、優先的に資源を割り付けるオーダ順にソートする。図17に示す例では余裕日数の少ない順に山崩を行うが、顧客の優先順位など外部から与えられたそのほかのパラメータに従って、優先的に資源を割り付けるオーダ順にソートされても良い。
The load hillside processing means 54 performs processing as shown in FIG. 17, for example.
First, in step S401, sorting is performed in the order in which resources are preferentially allocated, such as the order with the fewest days. In the example shown in FIG. 17, the hills are crushed in the order of few days, but they may be sorted in the order in which resources are preferentially allocated according to other parameters given from the outside such as customer priority.

次に、ステップS402においてステップS401でソートされたオーダから優先順位の高い順にオーダを1件取り出す。オーダを取り出すことができなければ、全てのオーダについて山崩を行ったとして処理を終了する。   Next, in step S402, one order is extracted from the order sorted in step S401 in descending order of priority. If the order cannot be taken out, it is determined that all the orders have been crushed and the process is terminated.

一方、ステップS402においてオーダを1件取り出すと、最遅完了日から最早開始日の範囲で最大必要資源数にて空き負荷を探索する。ここでは、最大必要資源数にて空き負荷を探索することにより、そのオーダが最短(縦軸:能力最大、横軸:期間最小)の期間で作業を完了できるかを評価する。   On the other hand, when one order is taken out in step S402, the available load is searched with the maximum number of required resources in the range from the latest completion date to the earliest start date. Here, it is evaluated whether or not the work can be completed in a period in which the order is the shortest (vertical axis: maximum capacity, horizontal axis: minimum period) by searching for a free load with the maximum required number of resources.

ステップS405において、最大必要資源数で算出された最遅完了日に、負荷山積処理手段53で算出された平均必要資源数以下で、負荷が割り付けられているか否かを判定する。   In step S405, it is determined whether or not a load is allocated below the average required resource number calculated by the load pile processing means 53 on the latest completion date calculated by the maximum required resource number.

ステップS405において、平均必要資源数以下で割付られていない場合、ステップS406において、最遅完了日から最早開始日の範囲で、平均必要資源数を越えた負荷を移動させることが可能であるか否かを判定する。負荷を移動できない場合、ステップS407において、最遅完了日を基点に最早開始日の方向へ最大必要資源数の負荷で配置を行う。この場合、最大必要資源数が平均必要資源数を越えることになるが、最大必要資源数を割り付けることにより、納期を守ることができる。一方、負荷を移動できる場合、ステップS408において、平均必要資源数を越えた負荷を、最遅完了日から最早開始日の範囲で過去方向へ山崩を行い、探索された空き負荷にステップS402で取り出されたオーダの負荷を割り当てる。このとき、平均必要資源数を越えないように負荷は移動される。このとき、平均必要資源数を越えた負荷を連続したアクティビティに割り付けるか、連続しないアクティビティに割り付けても良いかなどの割付条件が、外部からパラメータとして入力されても良い。   If it is determined in step S405 that the allocation is not less than the average required resource number, in step S406, it is possible to move the load exceeding the average required resource number in the range from the latest completion date to the earliest start date. Determine whether. If the load cannot be moved, in step S407, placement is performed with the maximum required number of resources in the direction of the earliest start date with the latest completion date as the base point. In this case, the maximum required resource number exceeds the average required resource number, but the delivery date can be kept by assigning the maximum required resource number. On the other hand, if the load can be moved, in step S408, the load exceeding the average required number of resources is crushed in the past direction in the range from the latest completion date to the earliest start date, and the searched free load is extracted in step S402. Assign the load of the ordered order. At this time, the load is moved so as not to exceed the average required number of resources. At this time, an assignment condition such as whether a load exceeding the average required resource number may be assigned to a continuous activity or a non-continuous activity may be input as a parameter from the outside.

ステップS405において平均必要資源数以下で割り付けられた場合、ステップS409において、既に割り付けられたオーダの負荷は、そのオーダの割付可能範囲で過去方向に負荷を移動できるか否かを判定する。負荷を移動できる場合、ステップS410において、既に割り付けられたオーダの負荷を過去方向に移動させ、移動によって発生した空き負荷に、ステップS402で取り出されたオーダの負荷を割り当てる。一方、負荷を移動できない場合、最遅完了日の空き負荷に、ステップS402で取り出されたオーダの負荷を割り当てる。   In the case where the allocation is less than the average required number of resources in step S405, it is determined in step S409 whether the load of the already allocated order can move the load in the past direction within the range in which the order can be allocated. When the load can be moved, in step S410, the load of the already assigned order is moved in the past direction, and the load of the order taken out in step S402 is assigned to the empty load generated by the movement. On the other hand, if the load cannot be moved, the load of the order extracted in step S402 is assigned to the empty load on the latest completion date.

図16に示した具体的な負荷山積の処理結果に基づいて、負荷山崩を説明する。図16に示した例で負荷山崩処理手段54は、余裕日数に基づいて、オーダBおよびオーダC、オーダA、オーダD、オーダEの順にソートする。   The load landslide will be described based on the processing result of the specific load pile shown in FIG. In the example shown in FIG. 16, the load landslide processing means 54 sorts in the order of order B and order C, order A, order D, and order E based on the number of days.

まず、オーダBおよびオーダCについては、余裕日数が0日なので、負荷山積処理手段53によって山積された状態で、図18に示すようにそれぞれの最遅完了日に負荷が山積される。   First, as for order B and order C, since the number of days is 0, the load is piled up on the latest completion date as shown in FIG.

次に、オーダDについては、負荷山積処理手段53によって最遅完了日である3月7日に5つの負荷が山積されているが、山積された負荷が平均必要資源数である3を越えるため、負荷山崩処理手段54は、図19に示すように過去の方向に負荷を移動させる。このとき、負荷山崩処理手段54は、最遅完了日から最早開始可能日まで過去の方向に遡って空き負荷を探索する。具体的には、このオーダDは、図16に示すように、最早開始可能日が3月5日であるので、3月5日から3月7日までの間で負荷を割り当てることができる。平均必要資源数を越える2つの負荷について、まず、一日過去に遡った3月6日に空き負荷があるか否かを探索する。この3月6日には、オーダCによって2つの負荷が割り付けられているが、平均必要資源数までに1つの空き負荷があるので、3月6日の1つの空き負荷に、オーダDを割り当てる。更に一日過去に遡った3月5日に空き負荷があるか否かを探索する。この3月5日には、オーダBによって1つの負荷が割り付けられているが、平均必要資源数までに2つの空き負荷があるので、3月5日の1つの空き負荷に、オーダDを割り当てる。このように処理することにより、オーダDの負荷が、平均必要資源数を越えない様に、最遅完了日から最早開始可能日までに割り付けられる。   Next, for order D, five loads are piled up on March 7 which is the latest completion date by the load pile processing means 53, but the piled loads exceed 3 which is the average required number of resources. The load landslide processing means 54 moves the load in the past direction as shown in FIG. At this time, the load landslide processing means 54 searches for a free load retroactively from the latest completion date to the earliest start possible date. Specifically, as shown in FIG. 16, the order D can be assigned a load between March 5 and March 7 because the earliest startable date is March 5. For two loads exceeding the average required number of resources, first, it is searched whether there is a free load on March 6 that goes back one day in the past. On March 6, two loads are assigned by order C. However, since there is one free load up to the average required number of resources, order D is assigned to one free load on March 6. . Further, a search is made as to whether or not there is an idle load on March 5 that goes back one day in the past. On March 5th, one load is assigned by order B. Since there are two free loads up to the average required number of resources, order D is assigned to one free load on March 5th. . By processing in this way, the load of the order D is allocated from the latest completion date to the earliest start possible date so as not to exceed the average required number of resources.

次に、オーダAについては、負荷山積処理手段53によって最遅完了日である3月4日に3つの負荷が山積されているが、山積された負荷が平均必要資源数である「3」を越えないため、図20に示すように最遅完了日に負荷が山積される。   Next, for order A, three loads are piled up on March 4th, which is the latest completion date, by the load pile processing means 53, but the piled load is “3”, which is the average number of required resources. Since it does not exceed, loads are piled up on the latest completion date as shown in FIG.

次に、オーダEについては、負荷山積処理手段53によって最遅完了日である3月8日に3つの負荷が山積されているが、山積された負荷が平均必要資源数である「3」を越えないため、最遅完了日に負荷が山積される。ここで負荷山崩処理手段54は、既に割付済みの負荷を割付可能範囲で過去方向に移動可能であるか否かを検証する。ここで、オーダAの最早開始可能日が3月1日であり、オーダEよりオーダAの方が納期に余裕がないので、図21に示すように、オーダAに関する負荷を3月3日に移動させ、オーダAの負荷の移動で空き負荷になった3月4日にオーダEの負荷を移動させる。   Next, for order E, three loads are piled up on March 8th, which is the latest completion date, by the load pile processing means 53, but the piled loads are set to “3”, which is the average required number of resources. Since it does not exceed, the load is piled up on the latest completion date. Here, the load landslide processing means 54 verifies whether or not the load that has already been allocated can be moved in the past direction within the allocation range. Here, the earliest possible start date of order A is March 1, and order A has less time for delivery than order E. Therefore, as shown in FIG. The load of the order E is moved on March 4 when the load of the order A has become a free load.

このような負荷山崩処理を行うことにより、平均必要資源数を越えないように過去方向に負荷山崩を行うことにより、納期を遵守しつつ、資源数を平準化することができる。   By performing such a load collapse process, by performing a load collapse in the past direction so as not to exceed the average required number of resources, the number of resources can be leveled while observing the delivery date.

スケジュール結果出力手段55は、記憶装置107から負荷山崩結果記憶部34を読み出して、資源ごとおよび単位時間ごとに資源に割り当てられたオーダを関連づけて資源別スケジュール結果記憶部41に記憶し、オーダごとに割り当てられた資源と納期予定とを関連づけてオーダ別スケジュール結果記憶部42に記憶する。   The schedule result output means 55 reads the load devastating result storage unit 34 from the storage device 107, associates the orders assigned to the resources for each resource and unit time, and stores them in the resource-specific schedule result storage unit 41, for each order. The resource assigned to the item and the delivery schedule are associated with each other and stored in the order-specific schedule result storage unit 42.

このスケジュール結果出力手段55においては、オーダ順、工程順、納期順、余裕日数の少ない順といった条件をパラメータ等で指定して出力しても良い。この資源別スケジュール結果記憶部41およびオーダ別スケジュール結果記憶部42は、生産管理システム等の上位システムへデータ送信されて生産管理システムで保存されても良いし、生産管理システムなどで任意のフォーマットで提示されても良い。このとき、スケジュール結果は、ガントチャート等を用いて提示されても良い。   In the schedule result output means 55, conditions such as order order, process order, delivery date order, and order with few days of allowance may be designated and output by parameters. The resource-specific schedule result storage unit 41 and the order-specific schedule result storage unit 42 may be transmitted to a higher-level system such as a production management system and stored in the production management system, or in an arbitrary format by the production management system or the like. May be presented. At this time, the schedule result may be presented using a Gantt chart or the like.

上述したように、本発明の最良の実施の形態に係る生産スケジューリング装置1は、まず最も厳しい後ろ倒しの条件で負荷山積を行い、平均必要資源数を越えないように過去方向に負荷山崩を行うことにより、納期を遵守しつつ、資源数を平準化することができる。資源数を平準化することにより、例えば作業員を同じメンバーで長期的に雇用することができるので、新たな雇用が発生しないので、作業員の教育や雇用に関する余計なコストが発生しない。また、同じ作業員に継続して作業させることにより、この作業員の習熟度を高めることができ、不良品の減少や歩留まりの向上などの品質に関わる効果が期待される。   As described above, the production scheduling apparatus 1 according to the best embodiment of the present invention first performs load accumulation under the most severe postponement conditions, and performs load collapse in the past direction so as not to exceed the average required number of resources. As a result, the number of resources can be leveled while observing the delivery date. By leveling the number of resources, for example, workers can be hired for the long term by the same member, so that no new employment is generated, so there is no extra cost related to worker education or employment. Further, by allowing the same worker to continue working, the proficiency level of this worker can be increased, and effects related to quality such as reduction of defective products and improvement of yield are expected.

(その他の実施の形態)
上記のように、本発明の最良の実施の形態によって記載したが、この開示の一部をなす論述および図面はこの発明を限定するものであると理解すべきではない。この開示から当業者には様々な代替実施の形態、実施例および運用技術が明らかとなる。
(Other embodiments)
As described above, the present invention has been described according to the best mode for carrying out the invention. However, it should not be understood that the description and drawings constituting a part of this disclosure limit the present invention. From this disclosure, various alternative embodiments, examples, and operational techniques will be apparent to those skilled in the art.

本発明はここでは記載していない様々な実施の形態等を含んでも構わない。従って、本発明の技術的範囲は上記の説明から妥当な特許請求の範囲に係る発明特定事項によってのみ定められる。   The present invention may include various embodiments not described herein. Therefore, the technical scope of the present invention is defined only by the invention specifying matters according to the scope of claims reasonable from the above description.

本発明の最良の実施の形態に係る生産スケジューリング装置の機能ブロック図。The functional block diagram of the production scheduling apparatus which concerns on the best embodiment of this invention. 本発明の最良の実施の形態に係る生産スケジューリング装置のハードウェア構成図。The hardware block diagram of the production scheduling apparatus which concerns on the best embodiment of this invention. 本発明の最良の実施の形態に係る生産スケジューリング装置の主な処理を説明するフローチャート。The flowchart explaining the main processes of the production scheduling apparatus which concerns on the best embodiment of this invention. 本発明の最良の実施の形態に係るオーダ情報記憶部のデータ構造とデータの一例を説明する図。The figure explaining an example of the data structure and data of the order information storage part which concerns on the best embodiment of this invention. 本発明の最良の実施の形態に係る作業工程フロー情報記憶部のデータ構造とデータの一例を説明する図。The figure explaining an example of the data structure and data of the work process flow information storage part which concerns on the best embodiment of this invention. 本発明の最良の実施の形態に係る作業工程情報記憶部のデータ構造とデータの一例を説明する図。The figure explaining the data structure and example of data of the work process information storage part which concerns on the best embodiment of this invention. 本発明の最良の実施の形態に係る資源グループ情報記憶部のデータ構造とデータの一例を説明する図。The figure explaining an example of the data structure and data of the resource group information storage part which concerns on the best embodiment of this invention. 本発明の最良の実施の形態に係る資源情報記憶部のデータ構造とデータの一例を説明する図。The figure explaining an example of the data structure of the resource information storage part which concerns on the best embodiment of this invention, and data. 本発明の最良の実施の形態に係るPERT計算手段のフローチャートの一例。An example of the flowchart of the PERT calculation means based on the best embodiment of this invention. 本発明の最良の実施の形態に係るPERT計算処理手段において、フォワードパスにより行われるPERT計算を説明する図。(その1)The figure explaining PERT calculation performed by a forward path in the PERT calculation processing means which concerns on the best embodiment of this invention. (Part 1) 本発明の最良の実施の形態に係るPERT計算処理手段において、フォワードパスにより行われるPERT計算を説明する図。(その2)The figure explaining PERT calculation performed by a forward path in the PERT calculation processing means which concerns on the best embodiment of this invention. (Part 2) 本発明の最良の実施の形態に係るPERT計算処理手段において、バックワードパスにより行われるPERT計算を説明する図。(その1)The figure explaining PERT calculation performed by a backward path | pass in the PERT calculation process means which concerns on the best embodiment of this invention. (Part 1) 本発明の最良の実施の形態に係るPERT計算処理手段において、バックワードパスにより行われるPERT計算を説明する図。(その2)The figure explaining PERT calculation performed by a backward path | pass in the PERT calculation process means which concerns on the best embodiment of this invention. (Part 2) 本発明の最良の実施の形態に係るPERT計算結果記憶部のデータ構造とデータの一例を説明する図。The figure explaining an example of the data structure and data of the PERT calculation result storage part which concerns on the best embodiment of this invention. 本発明の最良の実施の形態に係る負荷山積処理手段のフローチャートの一例。An example of the flowchart of the load pile processing means which concerns on the best embodiment of this invention. 本発明の最良の実施の形態に係る負荷山積処理手段による処理結果の一例。An example of the processing result by the load pile processing means which concerns on the best embodiment of this invention. 本発明の最良の実施の形態に係る負荷山崩処理手段のフローチャートの一例。An example of the flowchart of the load landslide processing means which concerns on the best embodiment of this invention. 本発明の最良の実施の形態に係る負荷山崩処理手段による処理結果の一例。(その1)An example of the processing result by the load landslide processing means which concerns on the best embodiment of this invention. (Part 1) 本発明の最良の実施の形態に係る負荷山崩処理手段による処理結果の一例。(その2)An example of the processing result by the load landslide processing means which concerns on the best embodiment of this invention. (Part 2) 本発明の最良の実施の形態に係る負荷山崩処理手段による処理結果の一例。(その3)An example of the processing result by the load landslide processing means which concerns on the best embodiment of this invention. (Part 3) 本発明の最良の実施の形態に係る負荷山崩処理手段による処理結果の一例。(その4)An example of the processing result by the load landslide processing means which concerns on the best embodiment of this invention. (Part 4)

符号の説明Explanation of symbols

1…生産スケジューリング装置
21…オーダ情報記憶部
22…作業工程フロー情報記憶部
23…作業工程情報記憶部
24…資源グループ情報記憶部
25…資源情報記憶部
31…スケジュールデータ記憶部
32…PERT計算結果記憶部
33…負荷山積結果記憶部
34…負荷山崩結果記憶部
41…資源別スケジュール結果記憶部
42…オーダ別スケジュール結果記憶部
51…スケジュールデータ取込手段
52…PERT計算手段
53…負荷山積処理手段
54…負荷山崩処理手段
55…スケジュール結果出力手段
101…中央処理制御装置
102…ROM
103…RAM
104…入力装置
105…表示装置
106…通信制御装置
107…記憶装置
108…リムーバブルディスク
109…入出力インタフェース
110…バス
DESCRIPTION OF SYMBOLS 1 ... Production scheduling apparatus 21 ... Order information storage part 22 ... Work process flow information storage part 23 ... Work process information storage part 24 ... Resource group information storage part 25 ... Resource information storage part 31 ... Schedule data storage part 32 ... PERT calculation result Storage unit 33 ... Load pile result storage unit 34 ... Load landslide result storage unit 41 ... Resource-specific schedule result storage unit 42 ... Order-specific schedule result storage unit 51 ... Schedule data fetching means 52 ... PERT calculation means 53 ... Load pile processing means 54 ... Load-climbing processing means 55 ... Schedule result output means 101 ... Central processing control device 102 ... ROM
103 ... RAM
104 ... Input device 105 ... Display device 106 ... Communication control device 107 ... Storage device 108 ... Removable disk 109 ... Input / output interface 110 ... Bus

Claims (8)

製品品目を製造するために、最小必要資源数と最大必要資源数との間の所定の資源数で作業が実行される任意資源数工程において、単位時間ごとに必要な資源数を平準化し、最適な資源数を算出する生産スケジューリング装置において、
製品品目、製造数量、開始可能日および納期を含むオーダ情報と、この製品品目を製造する任意資源数工程で利用される資源名、最小必要資源数、最大必要資源数、前記単位時間に基づく作業効率が関連づけられた作業工程情報とが記憶される記憶手段と、
前記記憶手段から前記オーダ情報および前記作業工程情報とを読み出して、スケジューリングの対象となるオーダのオーダ情報、およびこのオーダ情報に含まれる製品品目に関連づけられた作業工程情報を抽出して、スケジュールデータとして前記記憶手段に記憶するスケジュールデータ取込手段と、
前記記憶手段から前記スケジュールデータを読み出し、前記オーダごとに前記任意資源数工程において最小必要資源数から最大必要資源数の間のそれぞれの資源数でフォワードパスおよびバックワードパスを算出するPERT計算を実行し、前記オーダごとに、前記任意資源数工程における、納期を守る最小必要資源数と前記最小必要資源数における余裕日数、納期を守る最大必要資源数と前記最大必要資源数における余裕日数、および最早開始可能日と最遅開始可能日と最遅完了日を算出して、PERT計算結果として前記記憶手段に記憶するPERT計算手段と、
前記記憶手段からPERT計算結果を読み出して、前記オーダごとにバックワードパスで最大必要資源数で計算されたPERT計算結果を抽出し、抽出された前記PERT計算結果に基づいて前記単位時間ごとに前記最大必要資源数を越えない様に負荷山積を行って負荷山積結果として前記記憶手段に記憶するとともに、スケジューリングの対象となる期間における前記単位時間あたりの平均必要資源数を算出し、前記負荷山積結果として前記記憶手段に記憶する負荷山積処理手段と、
前記記憶手段から前記PERT計算結果および前記負荷山積結果を読み出し、前記PERT計算結果における前記オーダごとの前記最小必要資源数および前記最大必要資源数に基づいて過去の方向に前記平均必要資源数を越えないように負荷山崩を行って、負荷山崩結果として前記記憶手段に記憶する負荷山崩処理手段
とを備えることを特徴とする生産スケジューリング装置。
In order to manufacture product items, the number of resources required per unit time is leveled and optimized in an arbitrary resource count process where work is performed with a predetermined resource count between the minimum required resource count and the maximum required resource count. In the production scheduling device that calculates the number of resources,
Order information including product item, production quantity, start date and delivery date, resource name, minimum required resource number, maximum required resource number, work based on the unit time used in the arbitrary resource number process for manufacturing this product item Storage means for storing work process information associated with efficiency;
The order information and the work process information are read from the storage means, and the order information of the order to be scheduled and the work process information associated with the product item included in the order information are extracted, and the schedule data Schedule data fetching means stored in the storage means as
Read the schedule data from the storage means, and execute PERT calculation for calculating the forward path and the backward path with the respective resource numbers between the minimum required resource number and the maximum required resource number in the arbitrary resource number process for each order. For each order, the minimum required number of resources for protecting the delivery date, the number of days for the minimum required number of resources, the maximum number of required resources for protecting the delivery date, the number of days for the maximum required number of resources, and the earliest PERT calculation means for calculating a startable date, the latest startable date, and the latest completion date, and storing them in the storage means as a PERT calculation result;
The PERT calculation result is read from the storage means, and the PERT calculation result calculated with the maximum required number of resources in the backward path is extracted for each order, and the unit time is calculated based on the extracted PERT calculation result. A load pile is performed so as not to exceed the maximum required resource number, and the load pile result is stored in the storage means, and the average required resource number per unit time in a period to be scheduled is calculated, and the load pile result Load pile processing means stored in the storage means as
The PERT calculation result and the load pile result are read from the storage means, and the average required resource number is exceeded in the past direction based on the minimum required resource number and the maximum required resource number for each order in the PERT calculation result. A load scheduling process unit that performs load collapse so as not to be stored and stores the result in the storage unit as a load collapse result.
前記記憶手段から前記負荷山崩結果を読み出して、前記資源ごとおよび前記単位時間ごとに前記資源に割り当てられた前記オーダが関連づけた資源別スケジュール結果と、前記オーダごとに割り当てられた前記資源と納期予定とが関連づけられたオーダ別スケジュール結果とを前記記憶手段に記憶するスケジュール結果出力手段
を更に備えることを特徴とする請求項1記載の生産スケジューリング装置。
Reading the load collapse result from the storage means, and the resource-specific schedule result associated with the order assigned to the resource for each resource and for each unit time, the resource assigned for each order, and the delivery schedule The production scheduling apparatus according to claim 1, further comprising: a schedule result output unit that stores, in the storage unit, an order-by-order schedule result associated with.
前記負荷山積処理手段は、前記記憶手段から前記PERT計算結果を読み出して、前記オーダごとにバックワードパスで最大必要資源数で計算されたPERT計算結果を抽出し、前記最遅開始可能日から前記最遅完了日の間で、前記単位時間ごとに、前記最大必要資源数を越えない様に負荷山積を行って負荷山積結果として前記記憶手段に記憶するとともに、スケジューリングの対象となる期間における平均必要資源数を算出し、前記負荷山積結果として前記記憶手段に記憶し、
前記負荷山崩処理手段は、前記記憶手段から前記PERT計算結果および前記負荷山積結果を読み出し、前記PERT計算結果に含まれる前記最遅完了日から前記最早開始可能日に過去の方向に前記平均必要資源数を越えない様に負荷山崩を行って、負荷山崩結果として前記記憶手段に記憶する
ことを特徴とする請求項1または2記載の生産スケジューリング装置。
The load pile processing means reads the PERT calculation result from the storage means, extracts the PERT calculation result calculated with the maximum required number of resources in the backward path for each order, and starts the latest start date During the latest completion date, a load pile is performed for each unit time so as not to exceed the maximum required number of resources, and the load pile result is stored in the storage means, and the average necessary for the period to be scheduled Calculate the number of resources, and store it in the storage means as the load pile result,
The load landslide processing means reads the PERT calculation result and the load pile result from the storage means, and the average required resource in the past direction from the latest completion date included in the PERT calculation result to the earliest startable date The production scheduling apparatus according to claim 1 or 2, wherein load collapse is performed so as not to exceed a number, and the result of load collapse is stored in the storage means.
前記負荷山崩処理手段は、前記オーダごとのPERT計算結果について割付優先順位の高いオーダから順に抽出して、
前記最大必要資源数の負荷量で空き負荷を探索し、前記最大必要資源数と前記必要平均資源数とを比較するとともに、
前記必要平均資源数で割付可能であって既に割付済みのオーダの負荷を過去方向に移動可能である場合、前記割付済みのオーダを過去方向に移動させて抽出されたオーダの負荷を移動後の空き負荷に割り当て、前記既に割付済みのオーダの負荷を過去方向に移動可能でない場合、抽出されたオーダの負荷を空き負荷に割り当てるとともに、
前記必要平均資源数で割付不可能であって前記平均必要資源数を越えた負荷を前記最遅完了日から前記最早開始日の過去方向へ移動可能である場合、前記平均必要資源数を越えた負荷を前記最遅完了日から前記最早開始日の範囲で過去方向へ移動し、前記平均必要資源数を越えた負荷を前記最遅完了日から前記最早開始日の範囲で過去方向へ移動可能でない場合、前記最大必要資源数にて割付を行う
ことを特徴とする請求項3記載の生産スケジューリング装置。
The load landslide processing means extracts the PERT calculation result for each order in order from the order of higher allocation priority,
Search for a free load with the load amount of the maximum required resource number, compare the maximum required resource number with the required average resource number,
If it is possible to allocate the required average number of resources and move the already allocated order load in the past direction, move the allocated order in the past direction and move the extracted order load If the load of the already assigned order is not movable in the past direction, the load of the extracted order is assigned to the free load.
When the load that cannot be allocated with the required average number of resources and exceeds the average required number of resources can be moved from the latest completion date to the past of the earliest start date, the average required number of resources is exceeded. The load is moved in the past direction from the latest completion date to the earliest start date, and the load exceeding the average required resource number is not movable in the past direction from the latest completion date to the earliest start date The production scheduling apparatus according to claim 3, wherein allocation is performed based on the maximum required resource number.
コンピュータに、製品品目を製造するために、最小必要資源数と最大必要資源数との間の所定の資源数で作業が実行される任意資源数工程において、単位時間ごとに必要な資源数を平準化し、最適な資源数を算出させる生産スケジューリングプログラムにおいて、
記憶手段から、製品品目、製造数量、開始可能日および納期を含むオーダ情報と、この製品品目を製造する任意資源数工程で利用される資源名、最小必要資源数、最大必要資源数、前記単位時間に基づく作業効率が関連づけられた作業工程情報とを読み出し、スケジューリングの対象となるオーダが記憶されたオーダ情報、およびこのオーダ情報に含まれる製品品目に関連づけられた作業工程情報とを抽出して、スケジュールデータとして前記記憶手段に記憶するスケジュールデータ取込手段と、
前記記憶手段から前記スケジュールデータを読み出し、前記オーダごとに前記任意資源数工程において最小必要資源数から最大必要資源数の間のそれぞれの資源数でフォワードパスおよびバックワードパスを算出するPERT計算を実行し、前記オーダごとに、前記任意資源数工程における、納期を守ることのできる最小必要資源数と前記最小必要資源数における余裕日数、納期を守ることのできる最大必要資源数と前記最大必要資源数における余裕日数、および最早開始可能日と最遅開始可能日と最遅完了日を算出して、PERT計算結果として前記記憶手段に記憶するPERT計算手段と、
前記記憶手段からPERT計算結果を読み出して、前記オーダごとにバックワードパスで最大必要資源数で計算されたPERT計算結果を抽出し、抽出された前記PERT計算結果に基づいて前記単位時間ごとに前記最大必要資源数を越えない様に負荷山積を行って負荷山積結果として前記記憶手段に記憶するとともに、スケジューリングの対象となる期間における前記単位時間あたりの平均必要資源数を算出し、前記負荷山積結果として前記記憶手段に記憶する負荷山積処理手段と、
前記記憶手段から前記PERT計算結果および前記負荷山積結果とを読み出し、前記PERT計算結果における前記オーダごとの前記最小必要資源数および前記最大必要資源数に基づいて過去の方向に前記平均必要資源数を越えないように負荷山崩を行って、負荷山崩結果として前記記憶手段に記憶する負荷山崩処理手段
とをコンピュータに実行させることを特徴とする生産スケジューリングプログラム。
In order to manufacture product items on a computer, the required number of resources is leveled per unit time in an arbitrary number of resources process in which work is executed with a predetermined number of resources between the minimum required resource count and the maximum required resource count. In a production scheduling program that calculates the optimal number of resources,
From the storage means, order information including product item, production quantity, start date and delivery date, resource name, minimum required resource number, maximum required resource number used in the arbitrary resource number process for manufacturing this product item, the unit The work process information associated with the work efficiency based on the time is read out, the order information in which the order to be scheduled is stored, and the work process information associated with the product item included in the order information are extracted. Schedule data fetching means for storing the schedule data in the storage means;
Read the schedule data from the storage means, and execute PERT calculation for calculating the forward path and the backward path with the respective resource numbers between the minimum required resource number and the maximum required resource number in the arbitrary resource number process for each order. For each order, the minimum required number of resources that can meet the delivery date, the number of days required for the minimum required number of resources, the maximum required number of resources that can meet the delivery date, and the maximum required number of resources PERT calculation means for calculating the number of days in the table, the earliest startable date, the latest startable date, and the latest completion date, and storing them in the storage means as a PERT calculation result;
The PERT calculation result is read from the storage means, and the PERT calculation result calculated with the maximum required number of resources in the backward path is extracted for each order, and the unit time is calculated based on the extracted PERT calculation result. A load pile is performed so as not to exceed the maximum required resource number, and the load pile result is stored in the storage means, and the average required resource number per unit time in a period to be scheduled is calculated, and the load pile result Load pile processing means stored in the storage means as
The PERT calculation result and the load pile result are read from the storage means, and the average required resource number is determined in the past direction based on the minimum required resource number and the maximum required resource number for each order in the PERT calculation result. A production scheduling program characterized by causing a computer to execute a load landslide so as not to exceed the load landscaping and storing the load landslide processing means stored in the storage means as a load landslide result.
前記記憶手段から前記負荷山崩結果を読み出して、前記資源ごとおよび前記単位時間ごとに前記資源に割り当てられた前記オーダが関連づけた資源別スケジュール結果と、前記オーダごとに割り当てられた前記資源と納期予定とが関連づけられたオーダ別スケジュール結果とを前記記憶手段に記憶するスケジュール結果出力手段
を更にコンピュータに実行させることを特徴とする請求項5記載の生産スケジューリングプログラム。
Reading the load collapse result from the storage means, and the resource-specific schedule result associated with the order assigned to the resource for each resource and for each unit time, the resource assigned for each order, and the delivery schedule The production scheduling program according to claim 5, further causing the computer to execute schedule result output means for storing in the storage means the order-specific schedule result associated with.
前記負荷山積処理手段は、前記記憶手段から前記PERT計算結果を読み出して、前記オーダごとにバックワードパスで最大必要資源数で計算されたPERT計算結果を抽出し、前記最遅開始可能日から前記最遅完了日の間で、前記単位時間ごとに、前記最大必要資源数を越えない様に負荷山積を行って負荷山積結果として前記記憶手段に記憶するとともに、スケジューリングの対象となる期間における平均必要資源数を算出し、前記負荷山積結果として前記記憶手段に記憶し、
前記負荷山崩処理手段は、前記記憶手段から前記PERT計算結果および前記負荷山積結果を読み出し、前記PERT計算結果に含まれる前記最遅完了日から前記最早開始可能日に過去の方向に前記平均必要資源数を越えない様に負荷山崩を行って、負荷山崩結果として前記記憶手段に記憶する
ことを特徴とする請求項5または6記載の生産スケジューリングプログラム。
The load pile processing means reads the PERT calculation result from the storage means, extracts the PERT calculation result calculated with the maximum required number of resources in the backward path for each order, and starts the latest start date During the latest completion date, a load pile is performed for each unit time so as not to exceed the maximum required number of resources, and the load pile result is stored in the storage means, and the average necessary for the period to be scheduled Calculate the number of resources, and store it in the storage means as the load pile result,
The load landslide processing means reads the PERT calculation result and the load pile result from the storage means, and the average required resource in the past direction from the latest completion date included in the PERT calculation result to the earliest startable date 7. The production scheduling program according to claim 5, wherein load collapse is performed so as not to exceed a number, and a load collapse result is stored in the storage means.
前記負荷山崩処理手段は、前記オーダごとのPERT計算結果について割付優先順位の高いオーダから順に抽出して、
前記最大必要資源数の負荷量で空き負荷を探索し、前記最大必要資源数と前記必要平均資源数とを比較するとともに、
前記必要平均資源数で割付可能であって既に割付済みのオーダの負荷を過去方向に移動可能である場合、前記割付済みのオーダを過去方向に移動させて移動後の空き負荷に抽出されたオーダの負荷を割り当て、前記既に割付済みのオーダの負荷を過去方向に移動可能でない場合、空き負荷に抽出されたオーダの負荷を割り当てるとともに、
前記必要平均資源数で割付不可能であって前記平均必要資源数を越えた負荷を前記最遅完了日から前記最早開始日の過去方向へ移動可能である場合、前記平均必要資源数を越えた負荷を前記最遅完了日から前記最早開始日の範囲で過去方向へ移動し、前記平均必要資源数を越えた負荷を前記最遅完了日から前記最早開始日の範囲で過去方向へ移動可能でない場合、前記最大必要資源数にて割付を行う
ことを特徴とする請求項7記載の生産スケジューリングプログラム。

The load landslide processing means extracts the PERT calculation result for each order in order from the order of higher allocation priority,
Search for a free load with the load amount of the maximum required resource number, compare the maximum required resource number with the required average resource number,
If the load of the already allocated order can be moved in the past direction and can be allocated with the required average number of resources, the order extracted in the free load after movement by moving the allocated order in the past direction If the load of the already assigned order is not movable in the past direction, the load of the extracted order is assigned to the free load, and
When the load that cannot be allocated with the required average number of resources and exceeds the average required number of resources can be moved from the latest completion date to the past of the earliest start date, the average required number of resources is exceeded. The load is moved in the past direction from the latest completion date to the earliest start date, and the load exceeding the average required resource number is not movable in the past direction from the latest completion date to the earliest start date In this case, the production scheduling program according to claim 7, wherein the allocation is performed with the maximum required number of resources.

JP2004288512A 2004-09-30 2004-09-30 Apparatus and program for production scheduling Withdrawn JP2006106829A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004288512A JP2006106829A (en) 2004-09-30 2004-09-30 Apparatus and program for production scheduling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004288512A JP2006106829A (en) 2004-09-30 2004-09-30 Apparatus and program for production scheduling

Publications (1)

Publication Number Publication Date
JP2006106829A true JP2006106829A (en) 2006-04-20

Family

ID=36376537

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004288512A Withdrawn JP2006106829A (en) 2004-09-30 2004-09-30 Apparatus and program for production scheduling

Country Status (1)

Country Link
JP (1) JP2006106829A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011221923A (en) * 2010-04-13 2011-11-04 Kobe Steel Ltd Schedule creation method and schedule creation program and schedule creation device
JP2019179338A (en) * 2018-03-30 2019-10-17 パナソニックIpマネジメント株式会社 Preparation schedule creating method and preparation schedule creating device
CN112116189A (en) * 2019-06-21 2020-12-22 株式会社日立制作所 Production plan drafting support system

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011221923A (en) * 2010-04-13 2011-11-04 Kobe Steel Ltd Schedule creation method and schedule creation program and schedule creation device
JP2019179338A (en) * 2018-03-30 2019-10-17 パナソニックIpマネジメント株式会社 Preparation schedule creating method and preparation schedule creating device
JP7108830B2 (en) 2018-03-30 2022-07-29 パナソニックIpマネジメント株式会社 Preparation plan creation method and preparation plan creation device
CN112116189A (en) * 2019-06-21 2020-12-22 株式会社日立制作所 Production plan drafting support system
JP2021002203A (en) * 2019-06-21 2021-01-07 株式会社日立製作所 Production plan drafting support system
JP7178966B2 (en) 2019-06-21 2022-11-28 株式会社日立製作所 Production planning support system

Similar Documents

Publication Publication Date Title
JP6025154B2 (en) System, method and program for managing a project
JP4736651B2 (en) Production planning method and production planning system for mixed orders and expected production
JP5134601B2 (en) Production schedule creation device
JP6832829B2 (en) Inventory management device and inventory management method
US6795742B1 (en) Production management method in a plurality of production lines
JP5958227B2 (en) Process management system
US20070117230A1 (en) Computer readable storage medium for work-in-process schedules
WO2012026056A1 (en) Process design/production planning device
JP2019117454A (en) Production planning support system
JP6338077B2 (en) Equipment plan support system, equipment plan support method and program
JP5439275B2 (en) Information processing apparatus, cost forecast calculation method, and cost forecast calculation program
JP6695673B2 (en) Plan generation device and plan generation method
JP7314043B2 (en) PRODUCTION PLANNING SUPPORT SYSTEM AND PRODUCTION PLANNING SUPPORT METHOD
JP2006106829A (en) Apparatus and program for production scheduling
JP2021163324A (en) Line configuration plan device
JPH0773244A (en) Method and device for determining input order of working object product to production line, method and device for determining personnel placement to production line
TWI784311B (en) Management device, management system, and management program
JP6005535B2 (en) Production plan creation device, production plan creation method, and production plan creation program
JP2006244470A (en) Delivery date reply system, delivery date reply method, and delivery date reply program
JP5810040B2 (en) Production schedule creation device and production schedule creation method
US20110106417A1 (en) Path Planning in a Warehouse
JP3853649B2 (en) Production management support system, method, apparatus, and program
JP5857580B2 (en) Work information management apparatus and program
JP5696010B2 (en) Production schedule creation device and production schedule creation method
JP7265762B2 (en) Agricultural Work Information Processing Program, Agricultural Work Information Processing Method, and Agricultural Work Information Processing Device

Legal Events

Date Code Title Description
A300 Application deemed to be withdrawn because no request for examination was validly filed

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20071204