JP2004218267A - Construction method of columnar structure made of pressurized and dehydrated ready mixed concrete - Google Patents
Construction method of columnar structure made of pressurized and dehydrated ready mixed concrete Download PDFInfo
- Publication number
- JP2004218267A JP2004218267A JP2003006576A JP2003006576A JP2004218267A JP 2004218267 A JP2004218267 A JP 2004218267A JP 2003006576 A JP2003006576 A JP 2003006576A JP 2003006576 A JP2003006576 A JP 2003006576A JP 2004218267 A JP2004218267 A JP 2004218267A
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- water
- mixed concrete
- ready
- ready mixed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Abstract
Description
【0001】
【発明の属する技術分野】
本発明は生コンクリートを加圧脱水した柱状構造物の構築方法に係り、特に、従来の透水性型枠を使用し、普通の流動性コンクリートを打設するが、早期強度を発現するコンクリートとなる柱状構造物の構築方法に関する。
【0002】
【従来の技術】
今までの柱状構造物(例えば橋脚)の構築は、主筋やフープ筋などの鉄筋を組み立てて、ベニヤ合板や鋼鈑等による型枠支保工を組み立ててから、型枠内に生コンクリートを打設することにより構築していた。通常は、生コンクリートを打設後、3日程度の養生を行ってから型枠を解体している。
【0003】
型枠を解体してもよいコンクリート強度は、土木学会のコンクリート標準示方書(平成8年制定)によると、橋脚の場合は5.0N/mm2である。通常のコンクリートでは材齢1日で、ほぼ脱型可能な5.0N/mm2に達するが、脱型は安全をみて3〜5日後に行うことが多い。
【0004】
また、密実なコンクリートを形成する方法として、生コンクリートを透水性の袋内に打設して、打設圧を利用してスランプがほぼ0に近い密実な袋詰コンクリートを形成する例があるが、この袋詰コンクリートを積み重ねる例は、橋脚としては強度的に無理があった。(例えば、特許文献1参照)。
【0005】
【特許文献1】
特開2000−144740号公報
【0006】
【発明が解決しようとする課題】
しかしながら、上記従来の橋脚構築方法には、次のような問題があった。
(1)型枠に用いられるベニヤ合板は資源消費の問題があり、熱帯雨林の保護などの環境面から使用を抑制しなければならない。
(2)型枠の脱型までに数日を要し、工期短縮のネックとなっていた。
(3)従来のコンクリート硬化方式では、コンクリートの表面に余剰水およびブリージングが生じやすい。
(4)レイタンスの発生により、コンクリートの打ち継ぎに悪影響を与える恐れがあった。
(5)レイタンス処理も工期短縮のネックとなっていた。
【0007】
本発明の目的は、型枠のベニヤ合板を省略して熱帯材型枠の使用量を削減し、かつ、コンクリート構造物の製作工期を短縮し、かつ、コンクリートの余剰水およびブリージングと、レイタンスの発生が少ない橋脚の構築方法を提供することである。
【0008】
【課題を解決するための手段】
上記目的を達成するために、本発明の生コンクリートを加圧脱水した柱状構造物(例えば橋脚)の構築方法は、柱状構造物の生コンクリート打設部に、生コンクリート中の水分を透過する透水性型枠を設置し、次いで、打設したコンクリートを加圧脱水してコンクリート製柱状構造物を構築することを特徴とするものである。
【0009】
本発明によれば、生コンクリートを打設後すぐに加圧を行い、水分を排出することにより、コンクリートは自立できる程度の状態になる。また、早期強度の発現が早く、早期に型枠を脱型することが可能になる。加圧脱水することにより、生コンクリートの表面には余剰水も生じず、ブリージングによるレイタンスの発生も少なく、コンクリートの打ち継ぎの処理工程は短縮できる。
【0010】
【発明の実施の形態】
以下、本発明の実施の形態を、図面を参照して説明する。図1は、本発明工法のために採用された透水性型枠の一例である。図(a)は平面図、図(b)は正面図である。
【0011】
図1に示すように、本工法の一実施形態では、コンクリート中の水分を透過する透水性シート1を生コンクリート打設部側に設置し、透水性シート1を支持する網状体2を外側に設置してなる透水性型枠3を用いる。
【0012】
透水性シート1としては、水分を透過し、コンクリート分は透過させない性能を有する布製シートを使用する。布製シートはナイロン製の糸を編み込んだもので、水分は透過するが、セメントやコンクリート分は漏洩しない性質を備えている。
【0013】
この透水性シート1内に打設された生コンクリートを加圧すると、コンクリート分は漏洩せず、コンクリート中の水分が排出される。そのため、スランプが、ほぼ0cmの密実な自立性コンクリートを早期に形成できる。
【0014】
加圧脱水によって透水性シート1が外側にふくらむのを防ぐために、透水性シート1の外側に網状体2としてエキスパンドメタルを設置している。エキスパンドメタル以外にも、ラス網、グレーチング、パンチングメタル等が使用できる。また、網状以外にも、格子状など、透水性シート1のはらみを抑制するように支持できるものであればよい。
【0015】
さらに、型枠全体としての形状、図1では平面形状、を保持するために、L型鋼や平鋼鈑などの鋼材4で枠組みを構成し、このような鋼製枠組みによって、型枠としての十分な強度を維持している。
【0016】
図1に示した透水性型枠3の据付方法は、従来の鋼製型枠(メタルフォーム)と同様である。透水性型枠3は、あらかじめ工場や作業場で製作され、透水性シート1と例えばエキスパンドメタル5を、L型鋼等の鋼材4で補強して形成されている。
【0017】
加圧脱水を行ったコンクリートの材料試験データによると、材齢24時間での圧縮強度は、
▲1▼ 加圧力0.25kgf/cm2 で9.72N/mm2
▲2▼ 加圧力0.5kgf/cm2 で10.11N/mm2
▲3▼ 加圧力1.0kgf/cm2 で11.06N/mm2
であった。
【0018】
無加圧の場合、材齢24時間では3.0〜5.0N/mm2 、材齢3日では7〜11.0N/mm2 程度である。加圧脱水させることにより、生コンクリートの表面には余剰な水およびブリージングが生じることがなく、コンクリートの打ち継ぎに悪影響を与えるレイタンスの発生が少ない。レイタンス処理も通常の施工に比較して短時間で容易に済む。
【0019】
このように、生コンクリート打設後すぐに加圧を行えば、コンクリートは、スランプがほぼ0cmの自立できる程度の状態になる。また、早期強度の発現が早く、早期に型枠を脱型できる。早期に型枠が脱型できることにより、作業工程が早まることになる。
【0020】
また、透水性型枠として、透水性シートを型枠の内側にセットした鋼材による枠組み、あるいはポーラスな型枠を使用することにより、透水性シートの目からは生コンクリート余剰水を積極的に排水することにより、気泡等を除去でき、コンクリートの強度が増加する。
【0021】
さらに、生コンクリートの充填具合も目視で確認でき、表面のジャンカが皆無となる。また、生コンクリート打設後に加圧を行うことにより、早期にコンクリート強度が発現し、工期の短縮となる。
【0022】
以下、型枠等の各要素についての考察を行うと、
〔型枠〕
▲1▼ 透水性型枠は軽い方がよい。生コンクリート打設後に加圧するので、通常よりも頑丈にする必要がある。
【0023】
▲2▼ 合板だと軽くてよいが、排水性が悪い。型枠自体が強度的に弱いので、補強として支保工を組む必要がある。
【0024】
▲3▼ 型枠に使用する合板は、資源消費の問題がある。熱帯雨林の保護を目的とすると、合板を使用しない工法の方がよい。
【0025】
▲4▼ 型枠は大判として、クレーンで建て込むようにする。
【0026】
▲5▼ 型枠と支保工と足場が一体となった大判でもよい。
【0027】
▲6▼ 型枠1案:合板のかわりにラス網を使用する。ラス網だと排水性がよい。桟木のかわりに補強の鋼製プレートやL型鋼(アングル)を使用する。
【0028】
▲7▼ 型枠2案:ポーラスコンクリート板(プレキャストコンクリート板など)を使用する。
【0029】
〔鉄筋〕
▲1▼ 主筋1案:主鉄筋はH型鋼を代用して、最初に組み立てておく。あるいは順次組み上げてもよい。最初に組み立てができれば施工的に有利と思われる。鉄筋を組み立てる場合、材料費はH型鋼に比較して安価であるが、組立人件費、工期は不利である。
【0030】
▲2▼ 主筋2案:どうしても鉄筋で組み立てる場合は、在来の工法と同様にコンクリート打設後に、順次組み立ててあがっていく。
【0031】
▲3▼ フープ筋については、型枠1案のラス網の場合は、在来の工法と同様の組立となる。なお、型枠2案のプレキャストコンクリート板を使用する場合は、事前にフープ筋を組み込んだ板を作成しておくことができる。
【0032】
〔加圧方法〕
▲1▼ 加圧方式1案:機械的な加圧は反力がとりにくいので、重力を利用する方法がよい。水袋を使って加圧の重しとする。加圧後は排水を行う。水袋への水の供給は、ポンプあるいは水道ホースとする。
【0033】
上記方法によれば、打設した生コンクリートの上に蓋をし、水用の袋を載せて袋の中に水を供給し、重しとして生コンクリートを加圧する。加圧後の除荷は水を排水することによるので簡単である。しかし、ハイピアで、大量の水の供給に時間を要する場合、または大きい加圧力が必要な場合は、既設躯体にアンカーを設置して反力とし機械的な加圧を行う。
【0034】
▲2▼ 加圧方式2案:均しコンクリート打設時にアンカーをセットしておき、このアンカーを反力として加圧する方法もある。例えば、ケーソン工法のように橋脚を構築できるし、また、後述するように、本発明方法をケーソン工法に適用できる。
【0035】
〔コンクリート最終形〕
▲1▼ 型枠1案のラス網の場合は、柱状構造物(例えば橋脚)が、所定の高さまでコンクリート打設が終わり、型枠を脱型した後に透水性シートを取り除いて、通常のコンクリート面を露出させる。
【0036】
▲2▼ 型枠2案の場合は、PCa板(プレキャストコンクリート板)そのままの仕上がりとなる。
【0037】
次に、各作業手順を説明すると、
<透水性型枠の上昇作業>
(エキスパンドメタル型枠の場合)
(1)鉄筋を組み立てる。
(2)型枠を組み立てる。
(3)生コンクリートを型枠内へ打設する。
(4) 加圧装置をセットする。
(5)生コンクリートを加圧脱水する。
(6)型枠が脱型できる箇所は脱型する。
(7) 繰り返し、所定の高さまでコンクリートを打設する。
(8) 型枠を脱型する。
(9) コンクリートの表面の布をはがし取る。
【0038】
(ポーラスコンクリート板の場合)
(1)鉄筋を組み立てる。
(2)ポーラスコンクリート板(埋め込み型枠)を組み立てる。
(3)生コンクリートを型枠内へ打設する。
(4)加圧装置をセットする。
(5)生コンクリートを加圧脱水する。
(6) 繰り返し、所定の高さまでコンクリートを打設する。
【0039】
次に、図2〜図4を参照して、透水性型枠に透水性型枠3を用いた柱状構造物(橋脚)構築方法の施工順序を説明する。下記のように、(a)〜(d)をくりかえして橋脚のコンクリートを打ち継いでいく。
【0040】
(a)まず、図2に示すように、鉄筋26を組み立てる。次に透水性型枠3を組み立てる。なお、符号の24は足場、25は昇降装置、27は昇降階段である。
【0041】
(b)次に、図3に示すように、生コンクリート10を打設して天端を被覆養生した後、水袋を載置する蓋28を設置する。なお、符号の20はPCa版の例示したものである。
【0042】
(c)次いで、図4に示すように、蓋28の上に水袋29を載置する。水袋に水を注水し、その重量で生コンクリートを加圧し、生コンクリート中の水分を排水する。なお、符号の30は排水が飛散しないように立ち上げた壁枠である。
(d)次いで、水荷重を撤去し、水袋29と蓋28を除去する。
【0043】
なお、生コンクリートを加圧する荷重は、水袋によるもの以外に、鉄塊やコンクリートブロックなどをカウンタとして蓋28の上に載置してもよい。また、既設躯体にアンカーをとる場合は、蓋28の上からジャッキで加圧し、生コンクリート中の水分を排水すればよい。
【0044】
次に、ケーソン工法を例にしてジャツキで加圧する方法を説明する。図5、図6は、本発明方法をケーソン工法に適用した場合の説明図である。図5に示すように、前述の図1に符号3で示した透水性型枠40を用いて、周壁コンクリート41を打設する。打設した生コンクリートの上に蓋42をして、地表面43から深く設置したアンカー44に反力をとって、油圧ジャッキ45により生コンクリートを加圧し脱水する。
【0045】
次いで、図6に示すように、コンクリートの打設終了後、従来と同様に、コンクリートの強度が出たら加圧梁46を設置し、アンカー44に反力をとって、油圧ジャッキ45により、躯体を地表面43から沈下させる。本例によれば、アンカー44を生コンクリート脱水用の荷重に兼用できる。
【0046】
【発明の効果】
上述のとおり本発明によれば、型枠のベニヤ合板を省略して工期を短縮し、かつ、コンクリートの余剰水およびブリージングと、レイタンスの発生が少ない柱状構造物(橋脚)の構築方法が得られる。
【図面の簡単な説明】
【図1】本発明方法における透水性型枠の一例を示す平面図および正面図である。
【図2】透水性型枠を用いた橋脚構築方法の施工順序を示す説明図である。
【図3】透水性型枠を用いた橋脚構築方法の施工順序を示す説明図である。
【図4】透水性型枠を用いた橋脚構築方法の施工順序を示す説明図である。
【図5】本発明方法をケーソン工法に適用した場合の加圧脱水方法の説明図である。
【図6】本発明方法をケーソン工法に適用した場合の加圧脱水方法の説明図である。
【符号の説明】
1 透水性シート
2 網状体
3 透水性型枠
4 鋼材
5 エキスパンドメタル
10 生コンクリート
26 鉄筋
28 蓋
29 水袋
40 透水性型枠
41 周壁コンクリート
42 蓋
44 アンカー
45 油圧ジャッキ
46 加圧梁[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a method of constructing a columnar structure obtained by dehydrating ready-mixed concrete under pressure, and in particular, using a conventional water-permeable form, casting ordinary fluid concrete, but resulting in concrete exhibiting early strength. The present invention relates to a method for constructing a columnar structure.
[0002]
[Prior art]
Up to now, columnar structures (for example, piers) are constructed by assembling reinforcing bars such as main bars and hoop bars, assembling a formwork support with veneer plywood, steel plate, etc., and then pouring ready-mixed concrete into the formwork. It was built by doing. Usually, after placing the ready-mixed concrete, the mold is dismantled after curing for about three days.
[0003]
According to the Concrete Standards Specification of the Japan Society of Civil Engineers (established in 1996), the concrete strength at which the formwork may be dismantled is 5.0 N / mm 2 for piers. With ordinary concrete, the material reaches 5.0 N / mm 2 at the age of one day, which can be almost removed. However, removal is often performed after 3 to 5 days for safety.
[0004]
Further, as a method of forming solid concrete, there is an example in which raw concrete is poured into a water-permeable bag, and a slump close to 0 is formed by using the driving pressure. However, the case of stacking the bagged concrete was unreasonable in terms of strength as a pier. (For example, see Patent Document 1).
[0005]
[Patent Document 1]
JP 2000-144740 A
[Problems to be solved by the invention]
However, the above-mentioned conventional pier construction method has the following problems.
(1) The veneer plywood used for the formwork has a problem of resource consumption, and its use must be suppressed from an environmental aspect such as protection of a tropical rain forest.
(2) It took several days to release the formwork, which was a bottleneck in shortening the construction period.
(3) In the conventional concrete hardening method, surplus water and breathing easily occur on the surface of concrete.
(4) Due to the occurrence of latencies, there is a possibility that the jointing of concrete may be adversely affected.
(5) Laittance treatment has also been a bottleneck in shortening the construction period.
[0007]
An object of the present invention is to omit the veneer plywood of the form, reduce the amount of tropical timber form used, and shorten the construction period of the concrete structure, and to reduce the excess water and breathing of the concrete and the latencies. It is an object of the present invention to provide a method for constructing a bridge pier with a low occurrence.
[0008]
[Means for Solving the Problems]
In order to achieve the above object, a method for constructing a columnar structure (for example, a bridge pier) of the present invention in which ready-mixed concrete is depressurized and dewatered is provided by a method of permeating water in the ready-mixed concrete to a portion of the columnar structure where the ready-mixed concrete is cast. A concrete formwork is installed, and then the poured concrete is dehydrated under pressure to construct a concrete columnar structure.
[0009]
ADVANTAGE OF THE INVENTION According to this invention, pressurization is performed immediately after casting concrete, and water is discharged | emitted, and concrete will be in the state which can stand on its own. In addition, the early development of the strength is early, and the mold can be released from the mold early. By performing pressure dehydration, surplus water is not generated on the surface of the ready-mixed concrete, latencies due to breathing are reduced, and the process of jointing concrete can be shortened.
[0010]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings. FIG. 1 is an example of a water-permeable mold used for the method of the present invention. FIG. 1A is a plan view, and FIG. 1B is a front view.
[0011]
As shown in FIG. 1, in one embodiment of the present construction method, a water-permeable sheet 1 permeable to moisture in concrete is installed on the ready-cast concrete placing portion side, and a
[0012]
As the water-permeable sheet 1, a cloth sheet having a performance of transmitting moisture and not transmitting concrete is used. The cloth sheet is made by knitting a nylon thread, and has a property of transmitting moisture but not leaking cement or concrete.
[0013]
When the fresh concrete poured into the water permeable sheet 1 is pressurized, the concrete component does not leak and the water in the concrete is discharged. Therefore, the slump can quickly form a solid freestanding concrete of almost 0 cm.
[0014]
In order to prevent the water permeable sheet 1 from bulging outward due to pressure dehydration, an expanded metal is installed as a
[0015]
Further, in order to maintain the shape of the entire formwork, that is, the plane shape in FIG. 1, the form is constituted by a
[0016]
The installation method of the water
[0017]
According to the material test data of concrete subjected to pressure dehydration, the compressive strength at the age of 24 hours is
▲ 1 ▼ in pressure 0.25kgf / cm 2 9.72N / mm 2
( 2 ) 10.11 N / mm 2 at a pressure of 0.5 kgf / cm 2
▲ 3 ▼ in pressure 1.0kgf / cm 2 11.06N / mm 2
Met.
[0018]
For pressureless, the age of 24 hours 3.0~5.0N / mm 2, in the age of 3 days, about 7~11.0N / mm 2. By performing pressure dehydration, surplus water and breathing do not occur on the surface of the ready-mixed concrete, and the occurrence of latencies that adversely affect the jointing of concrete is reduced. Laittance processing can be completed easily in a short time as compared with ordinary construction.
[0019]
In this way, if the pressurization is performed immediately after placing the ready-mixed concrete, the concrete is in a state in which the slump is almost 0 cm and can stand alone. In addition, the early development of the strength is early, and the mold can be released from the mold early. By being able to release the mold at an early stage, the work process is sped up.
[0020]
In addition, by using a steel frame in which a permeable sheet is set inside the form or a porous form as the permeable form, the fresh water surplus water is actively drained from the eyes of the permeable sheet. By doing so, air bubbles and the like can be removed, and the strength of concrete increases.
[0021]
Furthermore, the degree of filling of the ready-mixed concrete can be visually confirmed, and there is no junka on the surface. In addition, by applying pressure after placing the ready-mixed concrete, concrete strength is developed early and the construction period is shortened.
[0022]
In the following, considering each element such as formwork,
(Form)
{Circle around (1)} The water-permeable formwork should be light. Since the pressure is applied after placing the ready-mixed concrete, it must be stronger than usual.
[0023]
(2) Plywood can be light, but drainage is poor. Since the form itself is weak in strength, it is necessary to construct a support as reinforcement.
[0024]
(3) Plywood used for formwork has a problem of resource consumption. For protection of the rainforest, a construction method that does not use plywood is better.
[0025]
(4) The formwork should be large and built with a crane.
[0026]
(5) A large format in which the formwork, the shoring and the scaffolding are integrated may be used.
[0027]
(6) Form 1 proposal: Use a lath net instead of plywood. A lath net has good drainage. Instead of piers, use reinforced steel plates or L-shaped steel (angle).
[0028]
(7)
[0029]
(Rebar)
(1) Main rebar 1 plan: The main rebar is replaced with H-section steel and assembled first. Alternatively, they may be assembled sequentially. If it can be assembled first, it will be advantageous in terms of construction. When assembling a reinforcing bar, the material cost is lower than that of the H-section steel, but the assembly labor cost and the construction period are disadvantageous.
[0030]
(2)
[0031]
{Circle around (3)} Regarding the hoop streak, in the case of the lath net of one formwork, the assembly is the same as the conventional method. In addition, when using the precast concrete board of the two formwork, a board incorporating hoop streaks can be prepared in advance.
[0032]
(Pressurization method)
{Circle around (1)} Proposed pressurization method 1: Mechanical pressurization is difficult to take a reaction force, so a method using gravity is preferred. Use a water bag to apply pressure. After pressurization, drain water. The supply of water to the water bag shall be a pump or a water hose.
[0033]
According to the above method, a lid is placed on the poured ready-mixed concrete, a bag for water is placed, water is supplied into the bag, and the ready-mixed concrete is pressed as a weight. Unloading after pressurization is simple because the water is drained. However, when it takes a long time to supply a large amount of water, or when a large pressing force is required in a high pier, an anchor is installed on the existing building to provide a reaction force to perform mechanical pressurization.
[0034]
{Circle around (2)} Pressing
[0035]
[Concrete final form]
{Circle around (1)} In the case of the lath net of one formwork, the columnar structure (for example, a bridge pier) is finished casting concrete to a predetermined height, and after removing the formwork, remove the water-permeable sheet and remove the ordinary concrete. Expose the surface.
[0036]
{Circle around (2)} In the case of two mold forms, the PCa plate (precast concrete plate) is finished as it is.
[0037]
Next, each work procedure will be described.
<Ascent work of permeable formwork>
(In case of expanded metal formwork)
(1) Assemble the rebar.
(2) Assemble the formwork.
(3) Pour ready-mixed concrete into the formwork.
(4) Set the pressure device.
(5) The ready-mixed concrete is dewatered under pressure.
(6) The part where the mold can be removed is removed.
(7) Concrete is repeatedly poured to a predetermined height.
(8) Remove the mold.
(9) Peel off the cloth on the concrete surface.
[0038]
(For porous concrete plate)
(1) Assemble the rebar.
(2) Assemble a porous concrete plate (embedded formwork).
(3) Pour ready-mixed concrete into the formwork.
(4) Set the pressure device.
(5) The ready-mixed concrete is dewatered under pressure.
(6) Repeatedly cast concrete up to the specified height.
[0039]
Next, with reference to FIG. 2 to FIG. 4, a construction order of a columnar structure (pier) construction method using the water-
[0040]
(A) First, as shown in FIG. 2, the reinforcing
[0041]
(B) Next, as shown in FIG. 3, after the ready-
[0042]
(C) Next, a
(D) Next, the water load is removed, and the
[0043]
The load for pressing the ready-mixed concrete may be placed on the
[0044]
Next, a method of applying pressure with a jack will be described using the caisson method as an example. 5 and 6 are explanatory diagrams when the method of the present invention is applied to the caisson method. As shown in FIG. 5, the surrounding
[0045]
Next, as shown in FIG. 6, after the concrete has been poured, the
[0046]
【The invention's effect】
ADVANTAGE OF THE INVENTION As mentioned above, according to this invention, the construction method of shortening a construction period by omitting the veneer plywood of a formwork, and producing the surplus water and breathing of concrete, and generating less latencies is obtained. .
[Brief description of the drawings]
FIG. 1 is a plan view and a front view showing an example of a water-permeable mold in the method of the present invention.
FIG. 2 is an explanatory diagram showing a construction order of a pier construction method using a water-permeable form.
FIG. 3 is an explanatory view showing a construction order of a pier construction method using a water-permeable formwork.
FIG. 4 is an explanatory diagram showing a construction order of a pier construction method using a water-permeable formwork.
FIG. 5 is an explanatory view of a pressure dehydration method when the method of the present invention is applied to the caisson method.
FIG. 6 is an explanatory diagram of a pressure dehydration method when the method of the present invention is applied to the caisson method.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Water-
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003006576A JP2004218267A (en) | 2003-01-15 | 2003-01-15 | Construction method of columnar structure made of pressurized and dehydrated ready mixed concrete |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003006576A JP2004218267A (en) | 2003-01-15 | 2003-01-15 | Construction method of columnar structure made of pressurized and dehydrated ready mixed concrete |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2004218267A true JP2004218267A (en) | 2004-08-05 |
Family
ID=32896902
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003006576A Pending JP2004218267A (en) | 2003-01-15 | 2003-01-15 | Construction method of columnar structure made of pressurized and dehydrated ready mixed concrete |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2004218267A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006083564A (en) * | 2004-09-15 | 2006-03-30 | Sogo Concrete Service:Kk | Foundation constructing method, pressurizing device for use in the constructing method, and continuous footing or mat foundation constructed by the constructing method |
CN108086154A (en) * | 2017-12-19 | 2018-05-29 | 安徽省交通控股集团有限公司 | A kind of gradient function concrete towers rod structure and its construction method |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS594755A (en) * | 1982-06-28 | 1984-01-11 | 株式会社大林組 | Slide type frame apparatus for casting concrete structure |
JPS6448965A (en) * | 1987-08-17 | 1989-02-23 | Sumitomo Cement Co | Unburned tile and manufacture thereof |
JPH03275865A (en) * | 1990-02-13 | 1991-12-06 | I C D Kenchiku Sekkei Jimusho:Kk | Form for concrete-casting |
JPH0492052A (en) * | 1990-08-03 | 1992-03-25 | Achilles Corp | Application of excess water draining type mold |
JPH1088795A (en) * | 1996-09-18 | 1998-04-07 | Norio Shinya | Water permeable form |
JPH11131436A (en) * | 1997-10-30 | 1999-05-18 | Toshinori Toyoda | Consolidating construction method of bottom mud of lake and marsh |
JP2000144740A (en) * | 1998-11-04 | 2000-05-26 | Zenitaka Corp | Caisson type pile method making use of packed concrete |
-
2003
- 2003-01-15 JP JP2003006576A patent/JP2004218267A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS594755A (en) * | 1982-06-28 | 1984-01-11 | 株式会社大林組 | Slide type frame apparatus for casting concrete structure |
JPS6448965A (en) * | 1987-08-17 | 1989-02-23 | Sumitomo Cement Co | Unburned tile and manufacture thereof |
JPH03275865A (en) * | 1990-02-13 | 1991-12-06 | I C D Kenchiku Sekkei Jimusho:Kk | Form for concrete-casting |
JPH0492052A (en) * | 1990-08-03 | 1992-03-25 | Achilles Corp | Application of excess water draining type mold |
JPH1088795A (en) * | 1996-09-18 | 1998-04-07 | Norio Shinya | Water permeable form |
JPH11131436A (en) * | 1997-10-30 | 1999-05-18 | Toshinori Toyoda | Consolidating construction method of bottom mud of lake and marsh |
JP2000144740A (en) * | 1998-11-04 | 2000-05-26 | Zenitaka Corp | Caisson type pile method making use of packed concrete |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006083564A (en) * | 2004-09-15 | 2006-03-30 | Sogo Concrete Service:Kk | Foundation constructing method, pressurizing device for use in the constructing method, and continuous footing or mat foundation constructed by the constructing method |
JP4618413B2 (en) * | 2004-09-15 | 2011-01-26 | 株式会社総合コンクリートサービス | Foundation construction method, pressure device used in the construction method, and fabric foundation or solid foundation produced by the construction method |
CN108086154A (en) * | 2017-12-19 | 2018-05-29 | 安徽省交通控股集团有限公司 | A kind of gradient function concrete towers rod structure and its construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106592426B (en) | The construction method of transverse prestress overall with reinforced concrete bridge deck plate prefab-form system | |
CN103615053B (en) | Monolithic reinforced concrete structure post empiricism engineering method | |
CN109968520A (en) | A kind of production method of precast plate girder | |
CN110424605A (en) | A kind of steel bar girder composite floor | |
CN107905424A (en) | Full prefabricated band splicing groove unidirectional harden structure, making and assembly method | |
JP2004218267A (en) | Construction method of columnar structure made of pressurized and dehydrated ready mixed concrete | |
CN112411560A (en) | Step-by-step rapid construction method for beam plate structure of support body system in deep and large foundation pit | |
CN104131635B (en) | Method and platform for constructing peripheral shear wall of prefabricated staircase | |
CN109457718A (en) | A kind of isolated footing casting craft | |
CN212176547U (en) | Building floor bathroom falls board construction template device in building | |
CN104234432B (en) | Shed deckhead construction method | |
JP3237530B2 (en) | Method of manufacturing precast concrete member for wall construction | |
CN110965769A (en) | Building floor bathroom falls board construction template device in building | |
CN206477251U (en) | Transverse prestress overall with reinforced concrete bridge deck plate prefab-form system | |
CN216865221U (en) | Bearing platform adopting combined prefabricated ceramsite plate | |
CN114922054B (en) | Continuous rigid frame bridge prestressed steel concrete bearing platform structure and construction method thereof | |
CN101280607B (en) | Cast-in-situ rib laminated floor slab | |
JP2007039948A (en) | Foundation construction method and foundation | |
CN109024650A (en) | A kind of construction method on basis | |
JP2770604B2 (en) | Underground outer wall waterproofing method | |
CN102261146B (en) | Cast-in-place rib laminated floor slab | |
CN1959015B (en) | Shuttering component | |
CN110284650A (en) | A kind of production method of assembled cavity floor | |
KR20090127789A (en) | Method for prestressing concrete girder using temporary loading and method for constructing bridge using thereof | |
CN108729581A (en) | A kind of concrete frame and light-steel roofing connection structure and method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
RD04 | Notification of resignation of power of attorney |
Free format text: JAPANESE INTERMEDIATE CODE: A7424 Effective date: 20040507 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20040512 |
|
RD02 | Notification of acceptance of power of attorney |
Free format text: JAPANESE INTERMEDIATE CODE: A7422 Effective date: 20050215 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20050215 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050331 |
|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20060110 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060120 |
|
RD02 | Notification of acceptance of power of attorney |
Free format text: JAPANESE INTERMEDIATE CODE: A7422 Effective date: 20060120 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20060120 |
|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20060110 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20080124 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20080205 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080407 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20080812 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20081014 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20081118 |