JP2004076461A JP2002239846A JP2002239846A JP2004076461A JP 2004076461 A JP2004076461 A JP 2004076461A JP 2002239846 A JP2002239846 A JP 2002239846A JP 2002239846 A JP2002239846 A JP 2002239846A JP 2004076461 A JP2004076461 A JP 2004076461A
Authority
JP
Japan
Prior art keywords
main girder
frame scaffold
floor slab
concrete floor
horizontal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2002239846A
Other languages
Japanese (ja)
Inventor
Kenji Miura
三浦 健志
Toshikatsu Hatajima
畑島 敏勝
Original Assignee
Kitagawa Iron Works Co Ltd
株式会社北川鉄工所
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kitagawa Iron Works Co Ltd, 株式会社北川鉄工所 filed Critical Kitagawa Iron Works Co Ltd
Priority to JP2002239846A priority Critical patent/JP2004076461A/en
Publication of JP2004076461A publication Critical patent/JP2004076461A/en
Pending legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To eliminate a deflective deformative of a frame scaffold 4 supporting a side form 5 of a concrete floor slab 10 from below when the concrete floor slab 10 is placed at a site in a movable form device used in the case of construction work for placing the concrete floor slab 10 on a bridge. <P>SOLUTION: The deflective deformation of the frame scaffold 4 is reduced by installing a horizontal thrusting means 9 for thrusting a side surface section of a main girder 1 to the end section of the main girder side of the frame scaffold in the horizontal direction and a vertical supporting means 12 provided between an upper flange 14 and a lower flange 15 of the main girder 1 and fixing the frame scaffold 4 to the main girder 1 by thrusting those two flanges together. <P>COPYRIGHT: (C)2004,JPO

Description

【0001】
【産業上の利用分野】
本発明は、橋梁の主桁上にコンクリート床版を現地にて打設する際に使用する移動型枠装置の構造に関するものである。
【0002】
【従来の技術】
道路や鉄道などの設置に必要な橋の構築では、橋梁の主桁上にコンクリート床版を現地にて打設する橋梁構造形式が数多く採用されている。この施工には、主桁上にコンクリート床版を現地にて打設するため、主桁のフランジ上に設けた軌条に沿って移動する移動型枠装置が用いられている。
この移動型枠装置の橋軸の直角方向から見た断面図として図3に示し、図3のA部の部分拡大図として主桁とフレーム足場の支持部を図4に示す。
【0003】
図3において橋梁は、平行に配設された2本の主桁1とその間を連結する横桁2で構成されており、コンクリート床版10は主桁間の上面およびその両外側に張り出すように現地にてコンクリート打設される。
前記のような主桁1の両外側に張り出して打設されるコンクリートを現地にて打設するための移動型枠装置には主桁1の外側までに張り出した横梁6と該横梁6の両端部に設けられた支柱8を備えた門型フレーム3が設けられている。移動型枠装置には前記門型フレーム3の支柱8によって外側端を支持され、他端を主桁1の下フランジ15の上面を走行するフレーム足場4が備えられており、該フレーム足場4は主桁1の外側に張り出すコンクリート床版10を打設するための側型枠5を下方から支持している。
【0004】
このような従来の構造では主桁1の外側に張り出す側型枠5にコンクリート床版10を打設すると、図4中に示すようにコンクリート床版10の自重Wによってフレーム足場4に曲げモーメントMが作用し、フレーム足場4はたわみ変形を起こして矢印Mの方向へ湾曲してしまい、側型枠5が内側下方に移動してコンクリート床版10の外形精度が維持できない。
【0005】
また、従来の移動型枠装置としては、特開2000‐129632号公報に記載されているように、主桁1の外側に張り出す側型枠5にかかるコンクリート床版10の荷重Wを受けるフレーム足場4に主桁1の下フランジ15の上面に突き当ててフレーム足場4を支持する支持ジャッキを設けて、主桁1の下フランジ15へフレーム足場4にかかる垂直方向の荷重を支持させている。
【0006】
しかし、この構造では垂直方向の荷重を支持する支持ジャッキの下部が主桁1の下フランジ15のみを突き当てて、支持ジャッキの上部は固定されていないために垂直方向下向きの荷重は支持できるが、水平力やフレーム足場4にかかる曲げモーメントMが作用すると支持ジャッキは転倒してしまい、荷重を主桁1に伝えることは困難であり、フレーム足場4のたわみ変形による側型枠5の移動を防ぐことはできない。
【0007】
このため、フレーム足場4のたわみ変形による側型枠5の移動を見越してコンクリート打設前にあらかじめ側型枠5の位置を上方に設置しておき、コンクリートを打設してコンクリート床版10の自重Wにより側型枠5が下方に移動したときにコンクリート床版10が所望の外形となるように事前に側型枠5の設置調整が行なわれていた。しかし、この方法での調整量は作業者の経験や感覚により決定されており、やはりコンクリート床版10の外形は高精度には維持できない。
【0008】
【発明が解決しようとする課題】
したがって、本発明は前記問題点を鑑み、コンクリート床版10を現地にて打設する際に移動型枠装置のフレーム足場4のたわみ変形を解消する移動型枠装置を提供することを目的とする。
【0009】
【課題を解決するための手段】
上記の課題を解決するため、本発明は、橋梁にコンクリート床版を敷設する施工時に使用し、主桁の両外側に張り出した横梁と該横梁の両端部に支柱が備えられた門型フレームを有する移動型枠装置において、前記支柱と主桁に支持されており主桁外側部のコンクリート床版の側型枠を下方から支持するフレーム足場が、主桁の側面部を水平方向に押圧する水平押圧手段と、主桁の上フランジと下フランジの間に設けられてこれら二つのフランジを共に押圧することでフレーム足場と主桁を固定する垂直支持手段を備えることを特徴とする。
【0010】
【発明の実施の形態】
本発明の実施例を図を用いて説明する。
図1は本発明の移動型枠装置の橋軸の直角方向から見た断面図を示し、図2は図1中のB部部分拡大図である主桁1とフレーム足場4の支持部を示す。
図1において、二つの主桁1の間に横桁2が配置され、これらの上方にコンクリート床版10を現地にて打設する。そのため、主桁1の左右両側に張り出す外側に側型枠5が取り付けられている。この側型枠5を支持し、移動させるために主桁上へ設けた軌条に沿って移動する移動型枠装置が設けられている。
【0011】
移動型枠装置は、主桁上の軌条を走行する駆動台車7を備え、駆動台車7に支持されて水平方向に主桁1の両外側までに及ぶ片持ち梁構造で外側に張り出した横梁6と該横梁6の外側両端部に垂直に降ろされた支柱8を備えた門型フレーム3を設けている。支柱8は側型枠5を支えるために側型枠5の下方に設けられたフレーム足場4の外側端部を支持している。フレーム足場4の主桁側の端部は主桁1の下フランジ15の上面を移動可能になされており、垂直支持手段12が備えられている。
図2に示されるように、垂直支持手段12は垂直状態でフレーム足場4の端部に固定された垂直ジャッキ13を主桁1の上フランジ14と下フランジ15の間に備えている。
垂直ジャッキ13を伸長することによって主桁1の上フランジ14を下方から、下フランジ15を上方からそれぞれ押圧して、垂直支持手段12の上下両端部を主桁1に固定させて、フレーム足場4にかかるコンクリート床版10の自重Wを主桁1に支持させる。
【0012】
また、フレーム足場4には曲げモーメントMに対向する水平方向への作用力を発生させる水平押圧手段9として水平ジャッキ11が水平方向にフレーム足場4へ固定されている。
水平押圧手段9である水平ジャッキ11は伸長すると主桁外側の側面部を押圧するように設けられており、水平ジャッキ11を伸長させることによりフレーム足場4から主桁1の側面部を押圧する。
【0013】
次に本発明の作用を説明する。
図2に示すように、コンクリート床版10を現地にて打設する際に移動型枠装置を打設位置へ移動させた後、主桁1の上フランジ14と下フランジ15の間に設けられた垂直ジャッキ13を伸長させて主桁1の上フランジ14と下フランジ15をそれぞれ押圧して垂直作用力V1、V2を発生させる。
垂直支持手段12は前記垂直作用力V1、V2により垂直ジャッキ13の上下両端部を押圧し、主桁1とフレーム足場4を固定することにより、水平力や曲げモーメントMが作用しても垂直支持手段12が転倒することなく固定を維持し、フレーム足場4にかかるコンクリート床版10の自重Wを確実に主桁1へ伝えることができる。
【0014】
さらに、水平押圧手段9としてフレーム足場4へ水平に設けられた水平ジャッキ11を伸長させて主桁1の外側の側面部を押圧する。水平ジャッキ11はフレーム足場4へ固定されているので、押圧による反力がフレーム足場4に作用してフレーム足場4へ外向きの水平作用力Pを発生させる。
フレーム足場4に作用した外向きの水平作用力Pは現地にて打設されたコンクリート床版10の自重Wにより生じる下向きの曲げモーメントMに対向する水平作用力として作用し、フレーム足場4にかかる曲げモーメントMによる水平力を抑えて、曲げモーメントMによって発生するフレーム足場4のたわみ変形を低減させる。
【0015】
前記実施例では水平押圧手段9や垂直支持手段12は水平ジャッキ11、垂直ジャッキ13を使用しているが、他にも油圧シリンダなどの作動式のものを用いても同様な効果を得ることができる。
また、水平押圧手段9は主桁1の側面部を直接に押圧しているが、押圧による主桁1の変形に考慮して主桁1の側面部に押圧受け部材を設け、直接に主桁1の側面部を押圧しないような構造としても良い。
【0016】
本発明では、垂直支持手段12が上下両端部で主桁1の上フランジ14と下フランジ15をそれぞれ押圧することで、水平力や曲げモーメントMが作用してもフレーム足場4と主桁1との固定が維持されてフレーム足場4にかかるコンクリート床版の自重Wを確実に主桁1へ伝達できる。
さらに、水平押圧手段9がフレーム足場4にかかる曲げモーメントMによる水平力に対向する水平作用力Pを発生させることで、フレーム足場4にかかる水平力を抑えて、曲げモーメントMによるフレーム足場4の変形を低減できる。
これら2つの作用によって、コンクリート床版10の自重Wによる垂直力とコンクリート床版10の自重Wから発生する曲げモーメントMによる水平力がフレーム足場4にかかる場合でも、フレーム足場4のたわみ変形を抑えることができる。
【0017】
【発明の効果】
以上述べたように本発明によれば、コンクリート床版10の自重Wによるフレーム足場4のたわみ変形を抑えてコンクリートを打設するので、コンクリート床版10の形状を高精度に維持でき、これによりコンクリート強度の安定したコンクリート床版10を得ることができる。
また、フレーム足場4のたわみ変形が抑えられてフレーム足場4を支持する門型フレーム3の強度が低減されるので移動型枠装置の軽量化が可能となり、主桁1にかかる荷重が小さくなり主桁1の変形を抑えることができる。
【図面の簡単な説明】
【図1】本発明の移動型枠装置の橋軸の直角方向から見た断面図
【図2】図1中のB部部分拡大図
【図3】従来の移動型枠装置の橋軸の直角方向から見た断面図
【図4】図3中のA部部分拡大図
【符号の説明】
1 主桁
3 門型フレーム
4 フレーム足場
5 側型枠
9 水平押圧手段
10 コンクリート床版
11 水平ジャッキ
12 垂直支持手段
13 垂直ジャッキ
[0001]
[Industrial applications]
TECHNICAL FIELD The present invention relates to a structure of a movable form device used for placing a concrete slab on a main girder of a bridge on site.
[0002]
[Prior art]
In the construction of bridges required for installation of roads, railways, etc., many types of bridge structures in which concrete slabs are cast locally on the main girder of the bridge are used. In this construction, a movable form device that moves along a rail provided on a flange of the main girder is used in order to cast a concrete floor slab on the main girder.
FIG. 3 is a cross-sectional view of the movable form device as viewed from a direction perpendicular to the bridge axis, and FIG. 4 is a partially enlarged view of a portion A in FIG.
[0003]
In FIG. 3, the bridge is composed of two main girders 1 arranged in parallel and a horizontal girder 2 connecting the main girders, and the concrete floor slab 10 extends over the upper surface between the main girders and on both outer sides thereof. Concrete will be cast on site.
The movable formwork apparatus for placing concrete projecting out on both sides of the main girder 1 on both sides of the main girder 1 includes a cross beam 6 extending to the outside of the main girder 1 and both ends of the cross beam 6. There is provided a portal frame 3 having a column 8 provided in the section. The movable form device is provided with a frame scaffold 4 whose outer end is supported by a column 8 of the portal frame 3 and whose other end runs on the upper surface of the lower flange 15 of the main girder 1. A side formwork 5 for placing a concrete floor slab 10 projecting outside the main girder 1 is supported from below.
[0004]
In such a conventional structure, when the concrete floor slab 10 is cast on the side formwork 5 projecting outside the main girder 1, the bending moment is applied to the frame scaffold 4 by the weight W of the concrete floor slab 10, as shown in FIG. M acts and the frame scaffold 4 bends and bends in the direction of the arrow M, and the side formwork 5 moves inward and downward, so that the external accuracy of the concrete floor slab 10 cannot be maintained.
[0005]
Further, as a conventional movable form device, as described in Japanese Patent Application Laid-Open No. 2000-129632, a frame which receives a load W of a concrete floor slab 10 on a side form 5 projecting outside a main girder 1. A support jack for supporting the frame scaffold 4 by abutting the scaffold 4 against the upper surface of the lower flange 15 of the main girder 1 is provided, so that the lower flange 15 of the main girder 1 supports a vertical load applied to the frame scaffold 4. .
[0006]
However, in this structure, the lower part of the support jack supporting the vertical load abuts only the lower flange 15 of the main girder 1 and the upper part of the support jack is not fixed, so that the vertical downward load can be supported. When the horizontal force or the bending moment M applied to the frame scaffold 4 acts, the support jack falls down, and it is difficult to transmit the load to the main girder 1. It cannot be prevented.
[0007]
For this reason, in anticipation of the movement of the side formwork 5 due to the deformation of the frame scaffold 4, the position of the side formwork 5 is set up beforehand before the concrete is cast, and the concrete is cast into the concrete floor slab 10. The installation and adjustment of the side formwork 5 has been performed in advance so that the concrete floor slab 10 has a desired outer shape when the side formwork 5 moves downward by its own weight W. However, the amount of adjustment in this method is determined based on the experience and feeling of the worker, and the outer shape of the concrete floor slab 10 cannot be maintained with high accuracy.
[0008]
[Problems to be solved by the invention]
Accordingly, the present invention has been made in view of the above problems, and has as its object to provide a movable formwork device that eliminates the bending deformation of the frame scaffold 4 of the movable formwork device when the concrete slab 10 is cast on site. .
[0009]
[Means for Solving the Problems]
In order to solve the above-described problems, the present invention provides a portal frame which is used at the time of laying a concrete floor slab on a bridge, and has a cross beam projecting to both outer sides of a main girder and columns provided at both ends of the cross beam. In the movable formwork apparatus having the above, the frame scaffolding supported by the column and the main girder and supporting the side formwork of the concrete floor slab on the outer side of the main girder from below presses the side part of the main girder horizontally. It is characterized by comprising a pressing means and a vertical support means provided between the upper flange and the lower flange of the main girder and pressing the two flanges together to fix the frame scaffold to the main girder.
[0010]
BEST MODE FOR CARRYING OUT THE INVENTION
An embodiment of the present invention will be described with reference to the drawings.
FIG. 1 is a sectional view of the movable formwork device of the present invention as viewed from a direction perpendicular to the bridge axis. FIG. 2 is a partially enlarged view of a part B in FIG. .
In FIG. 1, a horizontal girder 2 is arranged between two main girders 1, and a concrete floor slab 10 is cast on the upper side thereof. Therefore, the side formwork 5 is attached to the outside of the main girder 1 on the left and right sides. A movable form device is provided which moves along a rail provided on the main girder to support and move the side form 5.
[0011]
The movable form device includes a driving bogie 7 that travels on a rail on the main girder, and is supported by the driving bogie 7 and extends laterally outwardly in a cantilever structure extending to both outer sides of the main girder 1. And a portal frame 3 having columns 8 vertically lowered at both outer ends of the cross beam 6. The column 8 supports the outer end of the frame scaffold 4 provided below the side formwork 5 to support the side formwork 5. The end of the frame scaffold 4 on the main girder side is movable on the upper surface of the lower flange 15 of the main girder 1, and is provided with vertical support means 12.
As shown in FIG. 2, the vertical support means 12 includes a vertical jack 13 fixed to an end of the frame scaffold 4 in a vertical state between the upper flange 14 and the lower flange 15 of the main girder 1.
By extending the vertical jack 13, the upper flange 14 of the main girder 1 is pressed from below and the lower flange 15 is pressed from above, so that the upper and lower ends of the vertical support means 12 are fixed to the main girder 1, and the frame scaffold 4 , The weight W of the concrete floor slab 10 is supported by the main girder 1.
[0012]
A horizontal jack 11 is horizontally fixed to the frame scaffold 4 as horizontal pressing means 9 for generating a horizontal acting force opposing the bending moment M.
The horizontal jack 11 as the horizontal pressing means 9 is provided so as to press the side portion outside the main girder when extended. The horizontal jack 11 is extended to press the side portion of the main girder 1 from the frame scaffold 4.
[0013]
Next, the operation of the present invention will be described.
As shown in FIG. 2, when the movable formwork device is moved to the casting position when the concrete floor slab 10 is cast on site, the movable slab is provided between the upper flange 14 and the lower flange 15 of the main girder 1. The vertical jack 13 is extended to press the upper flange 14 and the lower flange 15 of the main girder 1 to generate vertical acting forces V1 and V2.
The vertical support means 12 presses the upper and lower ends of the vertical jack 13 by the vertical acting forces V1 and V2, and fixes the main girder 1 and the frame scaffold 4, so that the vertical supporting means 12 is supported even when a horizontal force or bending moment M is applied. The means 12 can maintain the fixing without falling down, and the weight W of the concrete slab 10 on the frame scaffold 4 can be transmitted to the main girder 1 without fail.
[0014]
Further, the horizontal jack 11 provided horizontally to the frame scaffold 4 as the horizontal pressing means 9 is extended to press the side surface outside the main girder 1. Since the horizontal jack 11 is fixed to the frame scaffold 4, a reaction force due to the pressing acts on the frame scaffold 4 to generate an outward horizontal acting force P on the frame scaffold 4.
The outward horizontal acting force P acting on the frame scaffold 4 acts as a horizontal acting force opposing the downward bending moment M generated by the weight W of the concrete floor slab 10 cast on site, and acts on the frame scaffold 4. The horizontal force caused by the bending moment M is suppressed, and the bending deformation of the frame scaffold 4 generated by the bending moment M is reduced.
[0015]
In the above embodiment, the horizontal pressing means 9 and the vertical supporting means 12 use the horizontal jack 11 and the vertical jack 13, but the same effect can be obtained by using an actuating type such as a hydraulic cylinder. it can.
The horizontal pressing means 9 directly presses the side of the main girder 1. However, in consideration of the deformation of the main girder 1 due to the pressing, a pressing receiving member is provided on the side of the main girder 1, and the main girder 1 is directly provided. A structure that does not press the side surface portion 1 may be used.
[0016]
In the present invention, the vertical supporting means 12 presses the upper flange 14 and the lower flange 15 of the main girder 1 at the upper and lower ends, respectively, so that the frame scaffold 4 and the main girder 1 can be moved even when a horizontal force or a bending moment M acts. Is maintained, and the weight W of the concrete slab on the frame scaffold 4 can be reliably transmitted to the main girder 1.
Further, the horizontal pressing means 9 generates a horizontal acting force P opposing the horizontal force due to the bending moment M applied to the frame scaffold 4, thereby suppressing the horizontal force applied to the frame scaffold 4 and causing the frame scaffold 4 to be restrained by the bending moment M. Deformation can be reduced.
By these two actions, even when the vertical force due to the weight W of the concrete floor slab 10 and the horizontal force due to the bending moment M generated from the weight W of the concrete floor slab 10 are applied to the frame scaffold 4, the bending deformation of the frame scaffold 4 is suppressed. be able to.
[0017]
【The invention's effect】
As described above, according to the present invention, concrete is poured while suppressing the deformation of the frame scaffold 4 due to its own weight W of the concrete floor slab 10, so that the shape of the concrete floor slab 10 can be maintained with high accuracy. A concrete floor slab 10 with stable concrete strength can be obtained.
In addition, since the bending deformation of the frame scaffold 4 is suppressed and the strength of the portal frame 3 supporting the frame scaffold 4 is reduced, the weight of the movable form device can be reduced, and the load applied to the main girder 1 can be reduced. The deformation of the girder 1 can be suppressed.
[Brief description of the drawings]
FIG. 1 is a cross-sectional view of a movable formwork device of the present invention viewed from a direction perpendicular to a bridge axis. FIG. 2 is an enlarged view of a portion B in FIG. 1 FIG. FIG. 4 is an enlarged cross-sectional view of a portion A in FIG.
DESCRIPTION OF SYMBOLS 1 Main girder 3 Gate type frame 4 Frame scaffold 5 Side formwork 9 Horizontal pressing means 10 Concrete floor slab 11 Horizontal jack 12 Vertical support means 13 Vertical jack

Claims (1)

  1. 橋梁にコンクリート床版を敷設する施工時に使用し、主桁の両外側に張り出した横梁と該横梁の両端部に支柱が備えられた門型フレームを有する移動型枠装置において、前記支柱と主桁に支持されており主桁外側部のコンクリート床版の側型枠を下方から支持するフレーム足場が、主桁の側面部を水平方向に押圧する水平押圧手段と、主桁の上フランジと下フランジの間に設けられてこれら二つのフランジを共に押圧することでフレーム足場と主桁を固定する垂直支持手段を備えることを特徴とする移動型枠装置。A movable formwork apparatus which is used at the time of laying a concrete floor slab on a bridge and has a cross beam which protrudes on both outer sides of a main girder and a portal frame provided with struts at both ends of the cross girder, wherein the support and the main girder are provided. A frame scaffolding, which is supported on the side of the concrete girder outside of the main girder and supports the side formwork of the concrete floor slab from below, presses the side part of the main girder horizontally, and upper and lower flanges of the main girder. A movable formwork device comprising vertical support means provided between the two to press the two flanges together to fix the frame scaffold and the main girder.
JP2002239846A 2002-08-20 2002-08-20 Movable form device Pending JP2004076461A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002239846A JP2004076461A (en) 2002-08-20 2002-08-20 Movable form device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002239846A JP2004076461A (en) 2002-08-20 2002-08-20 Movable form device

Publications (1)

Publication Number Publication Date
JP2004076461A true JP2004076461A (en) 2004-03-11

Family

ID=32022828

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002239846A Pending JP2004076461A (en) 2002-08-20 2002-08-20 Movable form device

Country Status (1)

Country Link
JP (1) JP2004076461A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009062768A (en) * 2007-09-07 2009-03-26 Maeda Corp Bracket timbering of form for overhanging section, and method of constructing concrete overhanging section
CN106012843A (en) * 2016-05-23 2016-10-12 中交第航务工程局有限公司 Integral horizontal-movement construction method for single scaffolds
CN111576223A (en) * 2020-05-12 2020-08-25 陕西中立检测鉴定有限公司 Main tower lower cross beam support pre-pressing device and pre-pressing method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009062768A (en) * 2007-09-07 2009-03-26 Maeda Corp Bracket timbering of form for overhanging section, and method of constructing concrete overhanging section
CN106012843A (en) * 2016-05-23 2016-10-12 中交第航务工程局有限公司 Integral horizontal-movement construction method for single scaffolds
CN111576223A (en) * 2020-05-12 2020-08-25 陕西中立检测鉴定有限公司 Main tower lower cross beam support pre-pressing device and pre-pressing method thereof

Similar Documents

Publication Publication Date Title
JP2008088782A (en) Cantilever overhang erection method of corrugated steel plate web bridge
JP2006077521A (en) Bridge constructing apparatus
JP5179804B2 (en) Mobile suspension support
JP2006022595A (en) Main pilot girder, main girder structure for erection of box girder bridge and erection method of the box girder bridge
JP4329535B2 (en) Mobile work vehicle for overhanging slabs
JP2010048060A (en) Construction method of structure
KR20090126957A (en) Pre-loading apparatus for upper structure unit of a bridge and bending method of upper structure unit using thereof
JP2008274586A (en) Pillar head construction method
JP5053589B2 (en) How to build a bridge girder
JP2007315077A (en) Construction method for corrugated steel web bridge using girder wagon
JP2004076461A (en) Movable form device
JP2010095898A (en) Trussed setting beam
JP2008274638A (en) Corrugated steel plate web bridge erection device and corrugated steel plate web bridge erection method
JP5106989B2 (en) Corrugated steel web bridge erection device and corrugated steel web bridge erection method
JP2006112179A (en) Bridge girder installing method
JP2001146718A (en) Bridge floor slab projection moving and supporting structure
JP6509096B2 (en) Extension method
JP4033871B2 (en) How to build a bridge girder
JP2005264607A (en) Construction method for overhang slab of viaduct and precast concrete board for overhang slab
JP3830362B2 (en) Overhang construction method of PC box girder bridge
JP2009097197A (en) Method of constructing pillar head
JP2009287286A (en) Support for overhanging floor slab
KR102206783B1 (en) Temporary Fixing System for Prestressed Concrete Spliced Girder Bridge and Construction method using thereof
JP3065916B2 (en) Equipment for moving formwork for floor concrete
JP2020183678A (en) Box girder construction method and construction system

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050812

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070713

A131 Notification of reasons for refusal