JP2002194758A - Structure of replacement part of middle pile and replacement method - Google Patents

Structure of replacement part of middle pile and replacement method

Info

Publication number
JP2002194758A
JP2002194758A JP2000393618A JP2000393618A JP2002194758A JP 2002194758 A JP2002194758 A JP 2002194758A JP 2000393618 A JP2000393618 A JP 2000393618A JP 2000393618 A JP2000393618 A JP 2000393618A JP 2002194758 A JP2002194758 A JP 2002194758A
Authority
JP
Japan
Prior art keywords
intermediate pile
floor slab
pile
plate
replacement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2000393618A
Other languages
Japanese (ja)
Other versions
JP4464556B2 (en
Inventor
Kunihiro Ogasawara
小笠原邦洋
Yoshinao Muraki
村木由尚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2000393618A priority Critical patent/JP4464556B2/en
Publication of JP2002194758A publication Critical patent/JP2002194758A/en
Application granted granted Critical
Publication of JP4464556B2 publication Critical patent/JP4464556B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

(57)【要約】 【課題】 工期短縮を図ることを可能にした中間杭の受
替え部の構造及び受替え工法を提供することを目的とす
る。 【解決手段】 多層階の地下構造物10を貫通する中間
杭2が中床スラブ5と交差する位置に埋設具3を配置す
る。埋設具は中間杭に直交するように中間杭に取り付け
た複数枚のプレート31と、このプレートに取り付けた
多数の定着棒32で構成する。中床スラブにコンクリー
トを打設して埋設具を中床スラブに埋め込んで一体化
し、コンクリート養生後に中床スラブから下方の中間杭
を切断する。
(57) [Summary] [PROBLEMS] To provide a structure of a replacement part of an intermediate pile and a replacement method capable of shortening a construction period. SOLUTION: An embedding tool 3 is arranged at a position where an intermediate pile 2 penetrating an underground structure 10 of a multi-story floor intersects a middle floor slab 5. The burying tool is composed of a plurality of plates 31 attached to the intermediate pile so as to be orthogonal to the intermediate pile, and a number of fixing rods 32 attached to this plate. Concrete is poured into the middle floor slab, the burying tool is embedded in the middle floor slab, and integrated, and after the concrete curing, the lower intermediate pile is cut from the middle floor slab.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、中間杭の受替え部
の構造及び受替え工法に関するもので、特に地下3層の
地下駅舎などを構築する際に、下層階を早期に開放する
ために中間杭を切断する場合の中間杭の受替え部の構造
及び受替え工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a structure and a method of replacing an intermediate pile, and particularly to a method for opening a lower floor at an early stage when constructing an underground station building having three underground layers. The present invention relates to a structure of a replacement portion of a middle pile when a middle pile is cut and a replacement method.

【0002】[0002]

【従来の技術】地下構築物、特に地下3層の地下駅舎な
どを構築する場合は、駅舎開業までの工期が限られてお
り、上層階に対して地下2階、3階を先行して建築工
事、機械工事に引き渡す必要がある。一般に地下3層の
地下駅舎などの地下工事に当たっては、所定の深さまで
掘削して基礎工事を行ってから順次下層階より上層階へ
構築していく。ここで地表の覆工板を支持したり、切梁
受けに使用するために中間杭を設置している。このた
め、中間杭を受替えながら中間杭を切断し、これを撤去
してから下層階の建築工事、機械工事を行う必要があ
る。これまでの受替え工法は、図5、図6に示すように
中床スラブa上に鋼材b1、b2で井桁を組み、更にビ
ルトアップ材b3を組み込んで設置型中間杭受替え工b
を行っていた。即ち、中床スラブaのコンクリートの養
生が完了してから、中床スラブa上で鋼管柱運搬特殊台
車等を使用した鋼管柱の設置、ミニクレーンを使用した
プレキャストコンクリート壁型枠dの設置、ハンドリン
グマシンeを使用した上階床版用のプレキャストコンク
リート吊型枠fの設置等、重量物を重機によって設置し
ている。その後、中床スラブa上に設置型中間杭受替え
工bを行い、引き続き設置型中間杭受替え工bの箇所で
中間杭cを切断し、下階の中間杭cを撤去していた。
2. Description of the Related Art When constructing an underground building, in particular, an underground station building with three basements, the construction period until the opening of the station building is limited. Need to hand over to mechanical construction. In general, in underground work such as an underground station building having three basements, an excavation is performed to a predetermined depth to perform a foundation work, and then the building is sequentially constructed from a lower floor to an upper floor. Here, an intermediate pile is installed to support the lining plate on the ground surface and to use it for receiving the girder. For this reason, it is necessary to cut the intermediate pile while replacing the intermediate pile, remove it, and then perform construction work and mechanical work on the lower floor. As shown in FIG. 5 and FIG. 6, the conventional replacement method is to install a middle girder on a middle floor slab a with steel beams b1 and b2 and further incorporate a built-up material b3.
Had gone. That is, after the curing of the concrete of the middle floor slab a is completed, the installation of the steel pipe columns using the special carriage for transporting the steel pipe columns on the middle floor slab a, the installation of the precast concrete wall form d using the mini crane, Heavy objects are installed by heavy equipment such as installation of a precast concrete suspension form f for an upper floor slab using a handling machine e. Thereafter, the installation type intermediate pile replacement work b was performed on the middle floor slab a, the intermediate pile c was continuously cut at the location of the installation type intermediate pile replacement work b, and the lower floor intermediate pile c was removed.

【0003】[0003]

【本発明が解決しようとする課題】しかしながら、前記
した従来の受替え工法にあっては、次のような問題点が
ある。 <イ>井桁を組んで設置する設置型中間杭受替え工bの
大きさは2メートル四方にわたっており、このため上階
における鋼管柱、プレキャストコンクリート壁型枠dの
設置等に用いる重機の走行を阻害する。したがって、前
記したように設置型中間杭受替え工bを設置する前に上
階ではすべての重機作業を完了する必要があり、上階で
の工事が完了するまで下階を開放することができなかっ
た。 <ロ>上記のごとく上階での工事を完了してから中間杭
cを切断、撤去して下階を開放し、建築工事、機械工事
を行うため、下階の工事の開始が遅れ、工期が長くなっ
ていた。 <ハ>鋼材b1、b2で大掛かりな井桁を組み、更にビ
ルトアップ材b3を組み込んで設置型中間杭受替え工b
を行っているため、コストがかかっていた。
However, the above-mentioned conventional replacement method has the following problems. <B> The size of the installation type intermediate pile replacement b, which is to be installed by crossing the girder, is 2 meters square, so that heavy machinery used for the installation of steel pipe columns and precast concrete wall formwork d on the upper floor, etc. Inhibit. Therefore, as described above, it is necessary to complete all heavy equipment work on the upper floor before installing the installation type intermediate pile replacement b, and the lower floor can be opened until the construction on the upper floor is completed. Did not. <B> After the construction on the upper floor is completed as described above, the intermediate pile c is cut and removed, the lower floor is opened, and construction work and mechanical work are performed. Was getting longer. <C> A large-scale girder is assembled with steel materials b1 and b2, and a built-up material b3 is also incorporated to replace the installation type intermediate pile b.
And it was costly.

【0004】[0004]

【本発明の目的】本発明は上記したような従来の問題点
に鑑みて考えられたもので、工期短縮を図ることを可能
にした中間杭の受替え部の構造及び受替え工法を提供す
ることを目的とする。また本発明は、材料費等を削減
し、コストの安い中間杭の受替え部の構造及び受替え工
法を提供することを目的とする。本発明は、上記目的の
うち少なくとも一つを達成するようにしたものである。
SUMMARY OF THE INVENTION The present invention has been conceived in view of the above-mentioned conventional problems, and provides a structure and a method for replacing a middle pile which can shorten a construction period. The purpose is to: Another object of the present invention is to provide a structure of a replacement part of an intermediate pile and a replacement method which are inexpensive and reduce material costs. The present invention achieves at least one of the above objects.

【0005】[0005]

【課題を解決するための手段】上記のような目的を達成
するために、本発明の中間杭の受替え部の構造は、多層
階の地下構造物を構築する場合の中間杭の受替え工法に
おいて、多層階の地下構造物を貫通する中間杭と、前記
中間杭と中床スラブが交差する位置に配置する埋設具
と、からなり、前記埋設具は前記中間杭に直交するよう
に中間杭に取り付けた複数枚のプレートと、前記プレー
トに取り付けた多数の定着棒で構成し、前記埋設具を前
記中床スラブに埋め込んで一体化したことを特徴として
いる。以上の構成とすることで中床スラブのコンクリー
トの養生が完了すれば上層階の工事とは関係なく、中間
杭の切断、撤去し下層階を開放することができる。ま
た、本発明の中間杭の受替え工法は、前記記載の中間杭
の受替え部の構造を用いた受替え工法であって、中床ス
ラブを貫通する中間杭に複数枚のプレートを直交するよ
うに取り付け、前記プレートを前記中間杭に取り付ける
前または取り付け後に、該プレートに多数の定着棒を取
り付け、前記中床スラブにコンクリートを打設して前記
プレートと定着棒を中床スラブに埋め込んで一体化し、
コンクリート養生後に前記中床スラブから下方の中間杭
を切断して行うようになっている。
In order to achieve the above object, the structure of the replacement part of the intermediate pile of the present invention is a method of replacing the intermediate pile when constructing a multi-story underground structure. , An intermediate pile penetrating an underground structure of a multi-story floor, and an embedding tool disposed at a position where the intermediate pile and the intermediate floor slab intersect, wherein the embedding tool is orthogonal to the intermediate pile. And a plurality of fixing rods attached to the plate, and the embedding tool is embedded in the middle floor slab and integrated. With the above configuration, if the curing of the concrete of the middle floor slab is completed, the middle pile can be cut and removed to open the lower floor, regardless of the construction of the upper floor. The method for replacing an intermediate pile according to the present invention is a replacement method using the structure of the replacement part of the intermediate pile described above, wherein a plurality of plates are orthogonal to the intermediate pile penetrating the middle floor slab. Before or after attaching the plate to the intermediate pile, a large number of anchoring rods are attached to the plate, concrete is poured into the intermediate floor slab, and the plate and anchoring rod are embedded in the intermediate floor slab. Unite,
After the concrete curing, the lower intermediate pile is cut from the middle floor slab.

【0006】[0006]

【本発明の実施の形態】以下図面を参照しながら、本発
明に係る実施の形態について説明する。
Embodiments of the present invention will be described below with reference to the drawings.

【0007】<イ>全体の構成 受替え部は、中間杭2と中床スラブ5が交差する位置に
埋設具3を配置して構成する。交差する位置で中間杭2
に埋設具3を取り付け、コンクリートを打設して中間杭
2及び埋設具3を中床スラブ5と一体化する。即ち、中
床スラブ5の型枠設置後、鉄筋組みと同時に、中間杭2
に取り付けた埋設具3を中床スラブ5に埋め込んでなる
埋設型中間杭受替え部4を形成する。
<A> Overall Configuration The replacement unit is configured by arranging the burying tool 3 at a position where the intermediate pile 2 and the intermediate floor slab 5 intersect. Intermediate pile 2 at the intersection
And the intermediate pile 2 and the burying tool 3 are integrated with the middle floor slab 5 by casting concrete. That is, after the formwork of the middle floor slab 5 is installed, the intermediate pile 2
The embedding tool 3 attached to the slab 5 is embedded in the middle floor slab 5 to form a buried-type intermediate pile replacement part 4.

【0008】<ロ>中間杭 中間杭2は、H形鋼等からなる。中間杭2は、多層階の
地下構造物10(中床スラブ5)を貫通して設置してい
る。中間杭2は従来同様、地表の覆工板を支持したり、
切梁受けに使用したりするために設置しているもので、
必要に応じて複数本の中間杭2が中床スラブ5を施工す
る位置を貫通して設置されている。中間杭2と中床スラ
ブ5が交差する位置に埋設具3を接合している。
<B> Intermediate pile The intermediate pile 2 is made of H-section steel or the like. The intermediate pile 2 is installed so as to penetrate the underground structure 10 (middle floor slab 5) of the multilayered floor. The intermediate pile 2 supports the surface lining plate as before,
It is installed for use as a beam support,
As necessary, a plurality of intermediate piles 2 are installed so as to penetrate the position where the middle floor slab 5 is constructed. The embedding tool 3 is joined at a position where the intermediate pile 2 and the middle floor slab 5 intersect.

【0009】<ハ>埋設具 埋設具3は、複数枚のプレート31と、このプレート3
1に取り付けた多数の定着棒32で構成している。プレ
ート31は、矩形の鋼材等からなっている。プレート3
1には、多数の定着棒32を略等間隔に取り付けること
ができるように、取付穴31aを略等間隔に多数設け
る。定着棒32は、プレート31が打設したコンクリー
トとの間でずれることがないようにずれ止めを目的とす
るためのものである。図2から分かるように、定着棒3
2は先端部32bを大径に形成したり、あるいはフック
状に折り曲げて形成し、後端に雄ねじ32aを設けるの
が好ましい。定着棒32の雄ねじ32aをプレート31
の取付穴31aに入れ、ナット34、35をプレート3
1の両側からねじ込んでプレート31を締め付けて定着
棒32をプレート31に取り付けることができる(図2
参照)。また定着棒32は、スタッド溶接等の方法で直
接プレート31に取り付けることもできる。このように
してプレート31に多数の定着棒32を取り付ける。な
お、図2では、1枚のプレート31に定着棒32は3個
のみ示しているが、定着棒32を配置する数は設計事項
であるため、任意の数を選択することができる。
<C> Buried Tool The buried tool 3 is composed of a plurality of plates 31
It is composed of a large number of fixing rods 32 attached to one. The plate 31 is made of a rectangular steel material or the like. Plate 3
In FIG. 1, a large number of mounting holes 31a are provided at substantially regular intervals so that a large number of fixing rods 32 can be attached at substantially regular intervals. The fixing rod 32 is provided for the purpose of preventing the plate 31 from being displaced from the cast concrete. As can be seen from FIG.
It is preferable that the front end 32b is formed to have a large diameter or to be bent in a hook shape, and the rear end is provided with a male screw 32a. The external thread 32a of the fixing rod 32 is
And the nuts 34 and 35 are attached to the plate 3
2, the fixing rod 32 can be attached to the plate 31 by screwing in from both sides and tightening the plate 31 (FIG. 2).
reference). Further, the fixing rod 32 can be directly attached to the plate 31 by a method such as stud welding. Thus, a large number of fixing rods 32 are attached to the plate 31. Although only three fixing rods 32 are shown on one plate 31 in FIG. 2, the number of fixing rods 32 to be arranged is a matter of design, and any number can be selected.

【0010】多数の定着棒32を取り付けたプレート3
1を、中間杭2が中床スラブ5と交差する位置において
溶接などによって一体に接合する。図2から分かるよう
に中間杭2の幅方向に夫々プレート31を2枚づつ直交
した状態で中間杭2に接合している。したがって、8枚
のプレート31が中間杭2に接合し、全体として中間杭
2に直交する2方向へ延びるように設置される。また、
必要に応じて一方向へ延びるように4枚のプレート31
を中間杭2に接合することもできる。尚、プレート31
を中間杭2に接合してから、プレート31に定着棒32
を取り付けるようにしてもよい。
Plate 3 on which a number of fixing rods 32 are mounted
1 are integrally joined by welding or the like at a position where the intermediate pile 2 intersects with the middle floor slab 5. As can be seen from FIG. 2, the plates 31 are joined to the intermediate pile 2 in a state where two plates 31 are orthogonal to each other in the width direction of the intermediate pile 2. Therefore, the eight plates 31 are connected to the intermediate pile 2 and installed so as to extend in two directions orthogonal to the intermediate pile 2 as a whole. Also,
Four plates 31 extend in one direction as needed.
Can be joined to the intermediate pile 2. The plate 31
Is fixed to the intermediate pile 2 and then the fixing rod 32 is attached to the plate 31.
May be attached.

【0011】プレート31を中間杭2に取付けた状態で
中床スラブ5にコンクリートを打設することによって、
埋設具3は中床スラブ5に埋め込まれて一体化する。し
たがって、中間杭2は中床スラブ5と埋設具3によって
支持することができ、下階12の中間杭2を切断、撤去
して下階12を開放することができる。即ち、埋設具3
を中床スラブ5に埋め込んだ埋設型中間杭受替え部4を
構成することになる。本発明では、埋設具3を中床スラ
ブ5に埋め込んで受替え部を構成しているため、プレー
ト31を大きく形成しても重機の走行に支障がない。
By placing concrete on the middle floor slab 5 with the plate 31 attached to the intermediate pile 2,
The burying tool 3 is embedded in the middle floor slab 5 to be integrated. Therefore, the intermediate pile 2 can be supported by the middle floor slab 5 and the burying tool 3, and the lower pile 12 can be opened by cutting and removing the intermediate pile 2 on the lower floor 12. That is, the burying tool 3
Is embedded in the middle floor slab 5 to form a buried-type intermediate pile replacement unit 4. In the present invention, since the replacement part is configured by embedding the embedding tool 3 in the middle floor slab 5, even if the plate 31 is formed large, there is no problem in running the heavy machinery.

【0012】次に以上の受替え部を用いた中間杭の受替
え工法を地下鉄駅舎構築の場合について説明する。
Next, a description will be given of a method of replacing an intermediate pile using the above-described replacement section in the case of constructing a subway station building.

【0013】<イ>中間杭の建て込み(図4) 先ず周辺の地盤の崩壊を防止するために、山留壁8を構
築して山留めを行う。掘削する地盤には、中間杭2を建
て込む。中間杭2を建て込んだら、図示していないが、
切梁、腹起し等の山留支保工を水平に架設しながら所定
の深さまで掘削し、底版コンクリート7を施工する。次
いで下階12の側壁コンクリート壁14を施工し、中床
スラブ型枠13を設置し、鉄筋を配筋する。
<A> Installation of Intermediate Piles (FIG. 4) First, in order to prevent the collapse of the surrounding ground, a retaining wall 8 is constructed and retaining is performed. An intermediate pile 2 is built in the ground to be excavated. When the intermediate pile 2 is built, it is not shown,
Excavation to a predetermined depth is carried out while erection support such as cut beams and bulging is installed horizontally, and bottom slab concrete 7 is constructed. Next, the side wall concrete wall 14 of the lower floor 12 is constructed, the middle floor slab formwork 13 is installed, and reinforcing bars are arranged.

【0014】<ロ>プレートの取り付け(図2) プレート31にあけられた多数の取付穴31aに定着棒
32を取り付ける。定着棒32の雄ねじ32aをプレー
ト31の取付穴31aに入れ、ナット34、35をプレ
ート31の両側からねじ込んでプレート31を締め付け
て多数の定着棒32をプレート31に取り付ける。な
お、定着棒32をスタッド溶接等の方法で直接プレート
31に取り付けることによって、取付穴31a、雄ねじ
32a、ナット34、35を省略することができる。多
数の定着棒32を取り付けたプレート31を、中間杭2
が中床スラブ5と交差する位置において溶接などによっ
て一体に接合する。中間杭2の幅方向に夫々プレート3
1を2枚づつ直交した状態で中間杭2に接合し、8枚の
プレート31が中間杭2に直交する2方向へ延びるよう
に設置する。尚、プレート31を中間杭2に接合してか
ら、プレート31に定着棒32を取り付けるようにして
もよい。
<B> Mounting of Plate (FIG. 2) Fixing rods 32 are mounted in a number of mounting holes 31a formed in the plate 31. The male screw 32a of the fixing rod 32 is inserted into the mounting hole 31a of the plate 31, and the nuts 34 and 35 are screwed in from both sides of the plate 31, and the plate 31 is tightened. By attaching the fixing rod 32 directly to the plate 31 by a method such as stud welding, the mounting hole 31a, the male screw 32a, and the nuts 34 and 35 can be omitted. The plate 31 to which a number of fixing rods 32 are attached is
Are joined together by welding or the like at the position where they intersect with the middle floor slab 5. Plates 3 each in the width direction of the intermediate pile 2
1 are joined to the intermediate pile 2 in a state of being orthogonal to each other, and eight plates 31 are installed so as to extend in two directions orthogonal to the intermediate pile 2. The fixing rod 32 may be attached to the plate 31 after the plate 31 is joined to the intermediate pile 2.

【0015】<ハ>コンクリートの打設(図3) プレート31を中間杭2に取付けた状態で中床スラブ5
にコンクリートを打設する。プレート31及びこれに取
り付けた定着棒32からなる埋設具3は、中床スラブ5
に埋め込まれてコンクリートと一体化する。このように
して中床スラブ5と埋設具3を一体化した埋設型中間杭
受替え部4を構成し、中間杭2を埋設型中間杭受替え部
4で支持した後、中間杭2を切断、撤去して下階12を
開放する(図1参照)。中床スラブ5のコンクリート養
生後に、上階11では鋼管柱建て込み、プレキャストコ
ンクリート壁型枠設置、上階11床版用の支保工組立、
木型型枠設置と作業がつづく。
<C> Casting concrete (FIG. 3) With the plate 31 attached to the intermediate pile 2, the middle floor slab 5
Pour concrete in. The embedding tool 3 composed of the plate 31 and the fixing rod 32 attached thereto has a middle floor slab 5
Embedded in concrete and integrated with concrete. In this way, a buried-type intermediate pile replacement unit 4 in which the middle floor slab 5 and the burying tool 3 are integrated is configured, and after the intermediate pile 2 is supported by the buried-type intermediate pile replacement unit 4, the intermediate pile 2 is cut. , And the lower floor 12 is opened (see FIG. 1). After the concrete curing of the middle floor slab 5, steel pipe columns are built on the upper floor 11, precast concrete wall formwork is installed, and the shoring for the upper floor 11 slab is assembled.
Installation of wooden formwork and work continue.

【0016】<ニ>中間杭の撤去(図1) 本発明では、埋設型中間杭受替え工法を採用したこと
で、中床スラブ5のコンクリートの養生が完了すれば、
前記した上階11の作業行程に関係なく、いつでも下階
12の中間杭2を切断、撤去することが可能となった。
中間杭2を下階12の上部及び下部において切断し、撤
去する。中間杭2を撤去した後は、下階12においてホ
ーム15等を構築する。本発明では、下階12の工事と
上階11の工事を並行して行うことができ、工期短縮に
つながる。
<D> Removal of Intermediate Pile (FIG. 1) In the present invention, by adopting the buried type intermediate pile replacement method, if the curing of the concrete of the middle floor slab 5 is completed,
Irrespective of the work process of the upper floor 11, the intermediate pile 2 of the lower floor 12 can be cut and removed at any time.
The intermediate pile 2 is cut off at the upper part and lower part of the lower floor 12 and removed. After removing the intermediate pile 2, a platform 15 and the like are constructed on the lower floor 12. According to the present invention, the construction of the lower floor 12 and the construction of the upper floor 11 can be performed in parallel, which leads to a shortened construction period.

【0017】本発明による埋設型中間杭受替え工法を厚
さ40cmと薄い中床スラブ5で実施したところ、中間
杭2の作用荷重は設計値とほぼ同じ(約110トン)で
あったにもかかわらず、中床スラブ5の沈下は1mm以
下で、クラックも発生することなく予想以上に剛体であ
ることが判明した。これを従来の井桁を組み付ける設置
型中間杭受替え工法と比較すると、中床スラブ5のコン
クリート打設から下階12開放までの所要日数は、従来
の設置型中間杭受替え工法が36日であるのに対し、本
発明による埋設型中間杭受替え工法は24日と12日間
工期が短縮した。
When the buried intermediate pile replacement method according to the present invention was carried out with a thin middle floor slab 5 having a thickness of 40 cm, the applied load of the intermediate pile 2 was almost the same as the design value (about 110 tons). Regardless, the settlement of the middle floor slab 5 was 1 mm or less, and it was found that it was harder than expected without cracks. Comparing this with the conventional installation-type intermediate pile replacement method of assembling the crossbeam, the required number of days from concrete placement of the middle floor slab 5 to the opening of the lower floor 12 is 36 days for the conventional installation-type intermediate pile replacement method. In contrast, the method for replacing a buried intermediate pile according to the present invention has a shortened construction period of 24 days and 12 days.

【0018】[0018]

【本発明の効果】本発明の中間杭の受替え部の構造及び
受替え工法は、以上説明したようになるから次のような
効果を得ることができる。<イ>埋設具を中床スラブに
埋め込んで受替え部を構成しているため、重機の走行に
支障がない。したがって、従来のように中間杭受替え工
を施工する前に上階でのすべての重機作業を完了する必
要はなく、上階での工事とは関係なく下階を開放するこ
とができる。 <ロ>上記のごとく上階での工事と関係なく、コンクリ
ートの養生が完了すれば中間杭を切断、撤去して下階を
開放し、建築工事、機械工事を行うことができるため、
下階の工事の開始が早まり、工期短縮を図ることができ
る。 <ハ>プレートとこれに取り付けた定着棒からなる埋設
具を中間杭に接合してコンクリートに埋め込んで一体化
するだけのため、材料費等を削減し、コストの安い中間
杭の受替え部の構造及び受替え工法を提供することがで
きる。
According to the present invention, the structure of the replacement part of the intermediate pile and the method of replacement are as described above, and the following effects can be obtained. <A> Since the replacement part is configured by embedding the burying tool in the middle floor slab, there is no hindrance to the traveling of heavy machinery. Therefore, it is not necessary to complete all the heavy equipment work on the upper floor before constructing the intermediate pile replacement work as in the related art, and the lower floor can be opened regardless of the work on the upper floor. <B> Regardless of the construction on the upper floor as described above, once the curing of the concrete is completed, the middle pile can be cut and removed, the lower floor can be opened, and construction work and mechanical work can be performed.
The start of construction on the lower floor is hastened, and the construction period can be shortened. <C> Since the burying tool consisting of the plate and the fixing rod attached to it is simply joined to the intermediate pile and embedded in concrete and integrated, the material cost is reduced and the cost of the intermediate pile replacement part is reduced. The structure and replacement method can be provided.

【図面の簡単な説明】[Brief description of the drawings]

【図1】地下構造物に中間杭を受替えた説明図。FIG. 1 is an explanatory view in which an intermediate pile is replaced with an underground structure.

【図2】中間杭と埋設具の接合状態を示す平面図。FIG. 2 is a plan view showing a joint state between the intermediate pile and the burying tool.

【図3】中間杭と埋設具を中床スラブに埋め込んだ状態
を示す説明図。
FIG. 3 is an explanatory view showing a state in which an intermediate pile and an embedding tool are embedded in an intermediate floor slab.

【図4】地下構造物に中間杭を建て込んだ説明図。FIG. 4 is an explanatory view in which an intermediate pile is built in an underground structure.

【図5】地下構造物に中間杭を受替えた従来技術の説明
図。
FIG. 5 is an explanatory view of a conventional technique in which an intermediate pile is replaced with an underground structure.

【図6】従来の設置型中間杭受替え工の側面図。FIG. 6 is a side view of a conventional installation type intermediate pile replacement work.

【符号の説明】[Explanation of symbols]

2・・・中間杭 3・・・埋設具 31・・・プレート 32・・・定着棒 5・・・中床スラブ 10・・・地下構造物 2 ... Intermediate pile 3 ... Buried tool 31 ... Plate 32 ... Fixing rod 5 ... Intermediate floor slab 10 ... Underground structure

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】多層階の地下構造物を構築する場合の中間
杭の受替え工法において、 多層階の地下構造物を貫通する中間杭と、 前記中間杭と中床スラブが交差する位置に配置する埋設
具と、からなり、 前記埋設具は前記中間杭に直交するように中間杭に取り
付けた複数枚のプレートと、 前記プレートに取り付けた多数の定着棒で構成し、 前記埋設具を前記中床スラブに埋め込んで一体化したこ
とを特徴とする、中間杭の受替え部の構造。
An intermediate pile replacement method for constructing a multi-story underground structure, comprising: an intermediate pile penetrating the multi-story underground structure; and a middle pile intersected by a middle floor slab. The embedding tool comprises: a plurality of plates attached to the intermediate pile so as to be orthogonal to the intermediate pile; and a large number of anchoring rods attached to the plate. The structure of the replacement part of the intermediate pile, which is embedded in the floor slab and integrated.
【請求項2】請求項1に記載の中間杭の受替え部の構造
を用いた受替え工法であって、 中床スラブを貫通する中間杭に複数枚のプレートを直交
するように取り付け、 前記プレートを前記中間杭に取り付ける前または取り付
け後に、該プレートに多数の定着棒を取り付け、 前記中床スラブにコンクリートを打設して前記プレート
と定着棒を中床スラブに埋め込んで一体化し、 コンクリート養生後に前記中床スラブから下方の中間杭
を切断して行う、中間杭の受替え工法。
2. A replacement method using the structure of a replacement portion of an intermediate pile according to claim 1, wherein a plurality of plates are attached orthogonally to the intermediate pile penetrating the middle floor slab, Before or after attaching the plate to the intermediate pile, a number of anchoring rods are attached to the plate, concrete is poured into the intermediate floor slab, and the plate and anchoring rod are embedded in the intermediate floor slab and integrated, and concrete curing is performed. A method of replacing intermediate piles, which is performed by cutting the lower intermediate pile from the middle floor slab later.
JP2000393618A 2000-12-25 2000-12-25 Intermediate pile replacement method Expired - Fee Related JP4464556B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000393618A JP4464556B2 (en) 2000-12-25 2000-12-25 Intermediate pile replacement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000393618A JP4464556B2 (en) 2000-12-25 2000-12-25 Intermediate pile replacement method

Publications (2)

Publication Number Publication Date
JP2002194758A true JP2002194758A (en) 2002-07-10
JP4464556B2 JP4464556B2 (en) 2010-05-19

Family

ID=18859377

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000393618A Expired - Fee Related JP4464556B2 (en) 2000-12-25 2000-12-25 Intermediate pile replacement method

Country Status (1)

Country Link
JP (1) JP4464556B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002371570A (en) * 2001-06-15 2002-12-26 Taisei Corp How to build underground structures
CN118207874A (en) * 2024-05-21 2024-06-18 中铁二十五局集团第五工程有限公司 A subway station prefabricated panel assembly trolley

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002371570A (en) * 2001-06-15 2002-12-26 Taisei Corp How to build underground structures
JP4511080B2 (en) * 2001-06-15 2010-07-28 大成建設株式会社 Construction method of underground structure
CN118207874A (en) * 2024-05-21 2024-06-18 中铁二十五局集团第五工程有限公司 A subway station prefabricated panel assembly trolley

Also Published As

Publication number Publication date
JP4464556B2 (en) 2010-05-19

Similar Documents

Publication Publication Date Title
KR101600845B1 (en) The horizontal structural frame and the underground construction methods using it
KR20190022132A (en) Top-down method using precast-concrete colum
JP5951375B2 (en) Steel tower reinforcement structure
KR20080100740A (en) Reverse support structure of mud wall using open type plate for continuous construction of underground plywood and continuous construction method of underground plywood using the same
JP6543077B2 (en) Construction method of structure
JP2003193495A (en) Underground structure constructing method
JP2002194758A (en) Structure of replacement part of middle pile and replacement method
JPH11310928A (en) Vibration isolation reinforcing method for existing structure
JPH11140892A (en) Method for excavating ground and method for constructing underground structure using the same
JP3057466B2 (en) How to build underground structures
JP4511080B2 (en) Construction method of underground structure
JP2515227B2 (en) Installation method of cast-in-place concrete foundation and precast concrete wall slab
JPS63280153A (en) Underground inverted lining method
JPH1077644A (en) Earthquake resisting pile foundation construction method
JP3849234B2 (en) Reinforced concrete underground outer wall construction method
JP4449595B2 (en) Column-beam joint structure, method for constructing column-beam joint structure, method for constructing underground structure, and building
JP3109038B2 (en) Underground skeleton structure and construction method
JP7384755B2 (en) Core material and upper core material removal method
JP2002115324A (en) Column base unit, column integrated column base fixing foundation structure using the column base unit, and construction method therefor
JP2900840B2 (en) How to build underground structures
JP2000064314A (en) Construction method of foundation structure
JP2001164559A (en) Construction method of continuous underground wall guide wall making use of l-type precast member
JPS62244923A (en) Anchor bolt-driven precast concrete block and driving of anchor bolt
JPS63277342A (en) Reverse execution of underground story
JPH07127114A (en) Rainwater underground storage facility

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070906

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20091119

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20091124

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20100120

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20100209

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20100219

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130226

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4464556

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20160226

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees