JP2002061498A - Method for constructing top slab section of reinforced concrete structure - Google Patents

Method for constructing top slab section of reinforced concrete structure

Info

Publication number
JP2002061498A
JP2002061498A JP2000245344A JP2000245344A JP2002061498A JP 2002061498 A JP2002061498 A JP 2002061498A JP 2000245344 A JP2000245344 A JP 2000245344A JP 2000245344 A JP2000245344 A JP 2000245344A JP 2002061498 A JP2002061498 A JP 2002061498A
Authority
JP
Japan
Prior art keywords
top slab
top plate
slab
reinforced concrete
concrete structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2000245344A
Other languages
Japanese (ja)
Other versions
JP3721505B2 (en
Inventor
Tadashi Saiki
正 齋木
Yasuyuki Sato
泰幸 佐藤
Hiroyuki Yamauchi
裕之 山内
Kazuhiko Koshida
和彦 越田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2000245344A priority Critical patent/JP3721505B2/en
Publication of JP2002061498A publication Critical patent/JP2002061498A/en
Application granted granted Critical
Publication of JP3721505B2 publication Critical patent/JP3721505B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a method by which the top slab section of a reinforced concrete structure can be constructed with good workability and workers are not forced to work in unnatural postures for a long time at the time of performing reinforcing bar arrangement even when the arrangement is performed at a narrow place covered with sheet piles, etc. SOLUTION: The top slab section 15 of a tunnel is constructed in such a way that upper and lower reinforcing bars 20 and 22 are arranged at prescribed positions and supported by a suspended frame 19 extended downward from a pipe roof 2 which is provided in advance above the top slab section. Then the bottom form and side forms of the top slab section are respectively assembled and concrete is placed in the spaces formed of the forms.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、鉄筋コンクリート
構造物の頂版部の施工方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a slab of a reinforced concrete structure.

【0002】[0002]

【従来の技術】図5は、例えば地下道形成用として用い
られる鉄筋コンクリート製トンネルの頂版部の施工方法
を示すものである。ここで示すトンネル100は、中央
に車道101、この車道101の左右に歩道102A,
102Bがそれぞれ形成されるものである。トンネル1
00の床版部103及び外壁104及び内壁105のそ
れぞれの高さ方向中間部までは、既にコンクリートが打
設されている。残された内外壁104,105の上側部
分並びに頂版部106の施工方法について説明すると、
まず、車道101及び歩道102A,102Bとなる箇
所に足場兼用の支保工107を組み立てる(図5
(イ))。その後、内壁105の上側部分となる所定箇
所に埋設用の鉄筋108を配置する(図5(ロ))。
2. Description of the Related Art FIG. 5 shows a method of constructing a top plate portion of a reinforced concrete tunnel used for forming an underpass, for example. The tunnel 100 shown here has a roadway 101 in the center and sidewalks 102A on the left and right sides of the roadway 101.
102B are respectively formed. Tunnel 1
Concrete has already been poured into the floor slab 103, the outer wall 104, and the inner wall 105 in the middle in the height direction. The method of constructing the upper portions of the remaining inner and outer walls 104 and 105 and the top plate 106 will be described.
First, a shoring 107 which is also used as a scaffold is assembled at a location to be a road 101 and sidewalks 102A and 102B (FIG. 5).
(I)). After that, a reinforcing bar 108 for embedding is arranged at a predetermined location which is to be an upper portion of the inner wall 105 (FIG. 5B).

【0003】次に、頂版部106の底型枠109、内壁
の型枠110、及び外壁の内側型枠111をそれぞれ組
み立てるとともに、それら型枠109,110,111
を前記支保工107で支持する(図5(ハ))。次い
で、外壁104の上側部分となる所定箇所並びに頂版部
106の所定箇所にそれぞれ埋設用の鉄筋112を配置
し(図5(ニ))、その後外壁の外側型枠113を組み
立てる(図5(ホ))。そして、それら型枠109,1
10,111,113内にコンクリートを打設し、これ
により頂版部106等をつくるのである。
Next, a bottom mold 109 of the top plate 106, a mold 110 of the inner wall, and an inner mold 111 of the outer wall are assembled, and the molds 109, 110, 111 are assembled.
Is supported by the support 107 (FIG. 5C). Next, embedding rebars 112 are arranged at predetermined locations on the upper side of the outer wall 104 and at predetermined locations on the top plate 106, respectively (FIG. 5 (d)), and then the outer formwork 113 of the outer wall is assembled (FIG. 5 ( E)). And, those molds 109, 1
Concrete is poured into 10, 111 and 113, thereby forming the top plate 106 and the like.

【0004】[0004]

【発明が解決しようとする課題】上記した従来の鉄筋コ
ンクリート構造物の頂版部の施工方法にあっては、次の
問題があった。すなわち、構造物の上方及び側方がそれ
ぞれ開放された通常の工事現場では、上記の施工方法を
支障なく採用できるが、例えば線路下のトンネルや地下
街を構築する際のように、上方と左右両側とが矢板11
4等で囲まれた狭隘な箇所で上述した従来の底型枠を組
んだ後に配筋を行う施工方法を採用しようとすると(図
5(ニ)中1点鎖線参照)と、型枠109,110,1
11と矢板114とで囲まれる狭い空間115内で、頂
版部106内に埋設される上筋及び下筋からなる主筋の
運搬作業、並びにそれら主筋の設置作業を行わなければ
ならず、作業性が悪く、作業時間が長引いてしまうとい
う問題が生じる。また、作業者は、上述の型枠109,
110,111と矢板114とで囲まれる狭い空間11
5内で、腰を曲げる無理な姿勢での作業を強いられるこ
ととなり、通常の環境下での作業に比べて早期に疲労感
を覚えてしまうという問題も生じる。
However, the above-mentioned conventional method for constructing the top plate of a reinforced concrete structure has the following problems. In other words, in a normal construction site where the upper and side surfaces of the structure are open, the above construction method can be adopted without any trouble.However, for example, when constructing a tunnel under the track or an underground mall, both the upper side and the left and right sides are used. And the sheet pile 11
When the above-described conventional construction method of assembling the bottom formwork in a narrow place surrounded by 4 or the like and then performing the reinforcing arrangement (see the one-dot chain line in FIG. 5D) is adopted, the formwork 109, 110,1
In the narrow space 115 surrounded by the sheet 11 and the sheet pile 114, the work of transporting the main reinforcements including the upper reinforcement and the lower reinforcement buried in the top plate portion 106 and the operation of installing the main reinforcements must be performed. And the work time is prolonged. In addition, the operator can use the above-described form
Narrow space 11 surrounded by 110, 111 and sheet pile 114
In 5, the user is forced to work in an unreasonable posture to bend his / her waist, which causes a problem that the user feels fatigue earlier than in a normal environment.

【0005】本発明は、上記事情に鑑みてなされたもの
で、その目的とするところは、上方が矢板等で囲まれた
狭隘な箇所であっても、配筋を行う際の作業性を良好に
保って作業時間の短縮化が図れ、かつ作業者が無理な姿
勢で長時間の作業を強いられることがない鉄筋コンクリ
ート構造物の頂版部の施工方法を提供することにある。
The present invention has been made in view of the above circumstances, and has as its object to improve the workability in arranging reinforcing bars even when the upper part is a narrow part surrounded by a sheet pile or the like. It is an object of the present invention to provide a method of constructing a top plate portion of a reinforced concrete structure which can shorten the working time while keeping the work time, and does not force the worker to work for a long time in an unreasonable posture.

【0006】[0006]

【課題を解決するための手段】前記課題を解決するため
の本発明の請求項1にかかる発明は、鉄筋コンクリート
構造物の頂版部を施工するにあたり、前記頂版部につい
て内部に埋設される鉄筋を所定位置に配置し、次いで、
前記頂版部の底型枠及び側型枠をそれぞれ組み立てると
ともにそれら型枠を支保工で支持し、次いで、それら型
枠内にコンクリートを打設して頂版部をつくることを特
徴としている。請求項2にかかる発明は、前記頂版部の
上方に予め支持体を設け、該支持体から下方に延びる吊
架台によって前記頂版部の鉄筋を吊り支持することを特
徴としている。請求項3にかかる発明は、前記頂版部の
底型枠を組み立てた後、前記支持体から下方に延びる吊
架台を撤去し、頂版部の前記鉄筋の位置調整を行った
後、型枠内にコンクリートを打設して頂版部をつくるこ
とを特徴としている。請求項4にかかる発明は、前記支
持体が、複数のパイプを並列に配置してなるパイプルー
フであることを特徴としている。
According to a first aspect of the present invention for solving the above-mentioned problems, when a top plate portion of a reinforced concrete structure is constructed, a reinforcing bar embedded inside the top plate portion is provided. In place, then
It is characterized in that the bottom mold and the side mold of the top slab are respectively assembled and supported by shoring, and then the top slab is made by casting concrete into the molds. The invention according to claim 2 is characterized in that a support is provided in advance above the top plate portion, and the reinforcing bar of the top plate portion is suspended and supported by a suspension base extending downward from the support. The invention according to claim 3 is that, after assembling the bottom formwork of the top plate portion, removing the suspension base extending downward from the support, adjusting the position of the reinforcing bar of the top plate portion, and then forming the formwork. It is characterized by casting concrete inside to make the top slab. The invention according to claim 4 is characterized in that the support is a pipe roof in which a plurality of pipes are arranged in parallel.

【0007】本発明によれば、コンクリート製構造物の
頂版部を施工するにあたり、型枠を組み立てる前に、先
に頂版部について配筋作業を行うものであるから、配筋
作業は下側の広い空間を利用して行うことができ、した
がって、たとえ構造物の上方に予め矢板等が配されてい
る場合であっても、配筋を行う際の良好な作業性が確保
できる。
According to the present invention, when constructing the top slab of the concrete structure, the arranging work is first performed on the top slab before assembling the formwork. The work can be performed using a wide space on the side, and therefore, even when a sheet pile or the like is previously arranged above the structure, good workability in performing the arrangement of the reinforcing bars can be ensured.

【0008】[0008]

【発明の実施の形態】以下、図面に基づいて本発明の実
施の形態を示す。図1は本発明にかかる鉄筋コンクリー
ト構造物である、線路下の地下道形成用のトンネルを作
る場合の施工途中の側面図、図2は同トンネルを作る場
合の施工途中の正面図である。これらの図において、符
号1は線路下のこれから作ろうとする地下道形成用のト
ンネル、2はトンネル1を作る場合の土留め用のパイプ
ルーフである。パイプルーフ2は、多数の鋼管2aを正
面から見て門型となるように地盤中に圧入されて形成さ
れるものであり、このパイプルーフ2によって地盤を支
えることで、天端の崩落を防ぎながら、内部のトンネル
掘削が可能となる。また、図2において3はパイプルー
フ2を受ける受桁、4,…は受桁3を介してパイプルー
フ2を受ける受杭である。
Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 is a side view of a reinforced concrete structure according to the present invention, in which a tunnel for forming an underpass under a track is being constructed, and FIG. 2 is a front view of the reinforced concrete structure, in which the tunnel is being constructed. In these figures, reference numeral 1 denotes a tunnel for forming an underground passage to be made below the track, and reference numeral 2 denotes a pipe roof for retaining the soil when the tunnel 1 is made. The pipe roof 2 is formed by press-fitting a large number of steel pipes 2a into the ground so as to form a gate shape when viewed from the front. The pipe roof 2 supports the ground to prevent the top end from collapsing. However, tunnel excavation inside is possible. In FIG. 2, reference numeral 3 denotes a girder receiving the pipe roof 2, and 4,...

【0009】上記トンネル1は、中央に車道10、車道
10の左右に歩道11A,11Bがそれぞれ形成され
る。なお、ここでは、トンネル1の床版部12及び外壁
13及び内壁14のそれぞれの高さ方向中間部までは、
既にコンクリートが打設されている。
In the tunnel 1, a road 10 is formed in the center, and sidewalks 11A and 11B are formed on the left and right of the road 10, respectively. In this case, up to the intermediate portions in the height direction of the floor slab portion 12, the outer wall 13, and the inner wall 14 of the tunnel 1,
Concrete has already been cast.

【0010】残された内外壁14,13の上側部分及び
頂版部15の施工方法について図3,図4を参照しなが
ら説明する。まず、車道10及び歩道11A,11Bと
なる箇所に足場兼用の支保工17を組み立てる(図3
(イ))。この場合、支保工17は、頂版部15の下端
面15aの位置まで作るのではなく、同下端面15aと
の間に所定の隙間18をあけた状態で所定高さまで作
る。
A method of applying the remaining upper portions of the inner and outer walls 14 and 13 and the top plate portion 15 will be described with reference to FIGS. First, a shoring 17 which is also used as a scaffold is assembled at a location to be the road 10 and the sidewalks 11A and 11B (FIG. 3).
(I)). In this case, the shoring 17 is not formed up to the position of the lower end surface 15a of the top plate portion 15, but is formed up to a predetermined height with a predetermined gap 18 provided between the support plate 17 and the lower end surface 15a.

【0011】次に、パイプルーフ2から下方に延びるス
テー19aを介して吊架台19を組み立てる(図3
(ロ))。その後、頂版部15の上筋20を所定位置に
配置し、該上筋21を前記吊架台19によって支持する
(図3(ハ))。次に、外壁13の上側部分となる所定
箇所に埋設用の鉄筋21を配置し(図3(ニ))、その
後、頂版部15の下筋22を所定位置に配置するととも
に、図示せぬ腹筋間に幅止筋を掛け渡し、これにより頂
版部15の配筋全体を仮止めする(図3(ホ))。
Next, the suspension base 19 is assembled via a stay 19a extending downward from the pipe roof 2 (FIG. 3).
(B)). Thereafter, the upper streak 20 of the top plate 15 is arranged at a predetermined position, and the upper streak 21 is supported by the suspension base 19 (FIG. 3C). Next, a reinforcing bar 21 for embedding is arranged at a predetermined location that is to be the upper portion of the outer wall 13 (FIG. 3D). Thereafter, the lower streaks 22 of the top plate 15 are arranged at a predetermined position, and are not shown. A width stop is stretched between the abdominal muscles, thereby temporarily fixing the entire arrangement of the top plate 15 (FIG. 3E).

【0012】次に、内壁14の上側部分となる所定箇所
に埋設用の鉄筋23を配置する(図4(ヘ))。その
後、最初に組み立てた支保工17と頂版部の下端面15
aとの間の隙間18を埋めるように、前記支保工17の
上側に2次的な支保工17aを組み立てる(図4
(ト))。さらに、頂版部の底型枠24、内壁14の左
右両側型枠25、25、外壁の内側型枠26をそれぞれ
組み立て、それら型枠24,25,26を前記支保工1
7,17aで支持する(図4(チ))。
Next, a reinforcing bar 23 for embedding is arranged at a predetermined location on the upper side of the inner wall 14 (FIG. 4 (f)). Thereafter, the first assembled support 17 and the lower end face 15 of the top plate portion are formed.
a secondary supporter 17a is assembled on the upper side of the supporter 17 so as to fill the gap 18 between the supporter 17 and the supporter 17 (FIG. 4).
(G)). Further, the bottom formwork 24 of the top slab, the left and right formworks 25 and 25 of the inner wall 14, and the inner formwork 26 of the outer wall are assembled respectively, and these formworks 24, 25 and 26 are attached to the support 1
7, 17a (FIG. 4 (h)).

【0013】次に、頂版部15の配筋を支持していた吊
架台19を撤去し、それらフリーになった配筋に対し
て、型枠24に対する相対的な位置、並びに鉄筋同士の
相互間隔を含めた最終的な位置調整を行う(図4
(リ))
Next, the suspension gantry 19 supporting the reinforcing bars of the top plate 15 is removed, and the positions of the free reinforcing bars relative to the formwork 24 and the mutual connection of the reinforcing bars are reduced. Perform final position adjustment including the interval (Fig. 4
(Re))

【0014】その後、外壁の外側型枠27を組み立てる
(図4(ヌ))。次に、それら型枠24,25,26,
27内にコンクリートを打設し、所定期間養生した後
に、型枠24,25,26,27並びに支保工等を撤去
する。以上の工程によって、トンネルの残された内外壁
14,13の上側部分及び頂版部15をつくるのであ
る。
Thereafter, the outer formwork 27 of the outer wall is assembled (FIG. 4 (N)). Next, those molds 24, 25, 26,
Concrete is poured into the inside 27, and after curing for a predetermined period, the formwork 24, 25, 26, 27, the shoring and the like are removed. Through the steps described above, the upper portions of the inner and outer walls 14, 13 where the tunnel is left and the top plate 15 are formed.

【0015】上述した鉄筋コンクリート構造物の頂版部
の施工方法によれば、頂版部15の底型枠24等を組み
立てる前に、先に頂版部15について配筋作業を行うも
のであるから、該配筋作業は前記底型枠24が配される
箇所よりも下側の広い空間を利用して行うことができ、
したがって、この例のようにたとえ該構造物の上方に予
めパイプルーフ2が配されて配筋箇所の上方に作業空間
がとれない場合であっても、良好な配筋作業性を確保す
ることができる。このため、上方に作業空間がとれない
場合であっても、従来の先に頂版部の型枠24を組み立
てその後に配筋作業を行う施工方法を採用する場合に比
べて、工期の大幅な短縮化が可能となる。
According to the above-described method for constructing the top slab of the reinforced concrete structure, the reinforcing work is first performed on the top slab 15 before assembling the bottom formwork 24 and the like of the top slab 15. The reinforcing work can be performed using a wide space below the place where the bottom formwork 24 is arranged,
Therefore, even in the case where the pipe roof 2 is previously arranged above the structure and a work space cannot be taken above the arrangement location as in this example, it is possible to ensure good arrangement workability. it can. For this reason, even when the working space cannot be taken upward, the construction period is much longer than in the case of adopting the construction method of assembling the formwork 24 of the top slab first and then performing the reinforcing work. Shortening is possible.

【0016】また、頂版部15についての配筋作業は、
底型枠24が配される箇所よりも下側の広い空間を利用
して行うことができる。具体的には、作業者は足場を兼
ねた支保工17の中間位置に足をかけて行う起立姿勢で
配筋作業を行うことができる。このため、従来例で説明
した、腰を曲げて行う無理な姿勢での作業は図3(i)
で示す最終的な配筋調整だけに止まる。この結果、作業
者の肉体的な負担は従来の施工方法を採用する場合に比
べて各段に軽減される。
The bar arrangement work for the top plate 15 is as follows.
It can be performed using a wide space below the place where the bottom formwork 24 is arranged. Specifically, the worker can perform the rebar arrangement work in a standing posture in which the worker places his foot on the intermediate position of the supporter 17 also serving as a scaffold. For this reason, the work in an unreasonable posture performed by bending the waist as described in the conventional example is shown in FIG.
It only stops at the final bar arrangement shown by. As a result, the physical burden on the worker is reduced in each step as compared with the case where the conventional construction method is adopted.

【0017】また、上記したように頂版部の底型枠24
を、配筋作業の後であって最終的にコンクリートを打設
する前に組み立てる施工方法であるから、底型枠24の
表面に鉄筋やスケール等のゴミが溜まりにくく、したが
って、従来通常行っていたコンクリート打設前の型枠表
面の清掃作業が不要になる。
Further, as described above, the bottom formwork 24 of the top plate portion is formed.
Is a construction method of assembling after the reinforcing work and before the concrete is finally poured, and it is difficult for dust such as reinforcing bars and scales to collect on the surface of the bottom formwork 24. The cleaning work of the formwork surface before the concrete is poured becomes unnecessary.

【0018】なお、本発明は上述の実施の形態に限られ
ることなく、発明の趣旨を逸脱しない範囲で適宜設計変
更可能である。例えば、上述の実施の形態では、本発明
を、線路下のトンネルの頂版部を施工する場合を例に挙
げて説明したが、勿論、これに限られることなく、例え
ば地下街の頂版部等他の鉄筋コンクリート構造物の頂版
部を作る場合にも、本発明が適用可能であることは言う
までもない。
It should be noted that the present invention is not limited to the above-described embodiment, and can be appropriately designed and modified without departing from the spirit of the invention. For example, in the above-described embodiment, the present invention has been described by exemplifying a case where a top plate portion of a tunnel under a track is constructed. However, the present invention is not limited to this. It goes without saying that the present invention can be applied to the case of making a top plate portion of another reinforced concrete structure.

【0019】[0019]

【発明の効果】請求項1にかかる発明では、頂版部の底
型枠等を組み立てる前に、先に頂版部について配筋作業
を行うものであるから、配筋作業は底型枠等が配される
箇所よりも下側の広い空間を利用して行うことができ、
もって、良好な配筋作業性を確保することができ、配筋
箇所の上方に作業空間がとれない場合に、底型枠等を組
み立てた後に配筋作業を行う従来の施工方法を採用する
のに比べて、工期の大幅な短縮化が可能となる。また、
頂版部を作る上での作業者が腰を曲げて行う無理な姿勢
での作業は全工程のごく一部に止めることができ、した
がって、作業者の肉体的な負担は従来の施工方法を採用
する場合に比べて各段に軽減される。さらに、頂版部の
底型枠等を、配筋作業の後であって最終的にコンクリー
トを打設する前に組み立てる施工方法であるから、底型
枠の表面に鉄筋やスケール等のゴミが溜まりにくく、通
常行っていたコンクリート打設前の型枠表面の清掃作業
が不要になる。また、頂版部の上方に予め支持体を設
け、該支持体から下方に延びる吊架台によって頂版部の
鉄筋を吊り支持するようにすれば、頂版部の型枠を組み
立てる前の頂版部の鉄筋支持を、下方に作業空間を残し
たまま行うことができ、当該配筋作業並びに後工程で行
う型枠作業を、良好な作業性を確保しつつ進めることが
できる。また、頂版部の底型枠を組み立てた後、前支持
体から下方に延びる吊架台を撤去し、頂版部の鉄筋の位
置調整を行うようにすれば、型枠と配筋間の相対的な位
置誤差を最終的に修正することができる。さらに、支持
体を、複数のパイプを並列に配置してなるパイプルーフ
とすれば、既存のパイプルーフを有効利用することがで
き、部品点数の削減ならびにコストを低減することがで
きる。
According to the first aspect of the present invention, before the bottom formwork or the like of the top slab is assembled, the reinforcing work is performed on the top slab first. Can be performed using a large space below the place where
Therefore, it is possible to ensure good workability of rebar arrangement, and when the work space cannot be secured above the rebar arrangement part, adopt the conventional construction method of performing rebar arrangement work after assembling the bottom formwork and the like. The construction period can be greatly shortened compared to Also,
The work in an unreasonable posture, in which the worker bends the waist when making the top slab, can be stopped in only a small part of the entire process, so the physical burden of the worker is reduced by the conventional construction method. It is reduced to each stage as compared with the case of adoption. Furthermore, since this is a construction method in which the bottom formwork of the top slab is assembled after the rebar work and before the concrete is finally cast, dust such as reinforcing bars and scales may be found on the surface of the bottom formwork. It hardly accumulates, and the work of cleaning the surface of the formwork before concrete casting, which is usually performed, becomes unnecessary. Further, if a support is provided in advance above the top plate portion and the reinforcing bar of the top plate portion is suspended and supported by a suspension base extending downward from the support, the top plate before assembling the formwork of the top plate portion. The reinforcing bar can be supported with the work space left below, and the reinforcing work and the formwork performed in the post-process can be performed while securing good workability. Also, after assembling the bottom formwork of the top slab, if the suspension base extending downward from the front support is removed and the position of the reinforcing bar of the top slab is adjusted, the relative distance between the formwork and the reinforcing bars can be adjusted. The final position error can be finally corrected. Furthermore, if the support is a pipe roof in which a plurality of pipes are arranged in parallel, the existing pipe roof can be effectively used, and the number of parts and the cost can be reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明にかかる鉄筋コンクリート構造物であ
る、線路下の地下道形成用のトンネルを作る場合の施工
途中の側面図である。
FIG. 1 is a side view of a reinforced concrete structure according to the present invention, which is in the middle of construction when a tunnel for forming an underpass under a railway track is formed.

【図2】 同トンネルを作る場合の施工途中の正面図で
ある。
FIG. 2 is a front view in the middle of construction when making the tunnel.

【図3】 同トンネルの頂版部等の施工方法の工程を説
明する側面図である。
FIG. 3 is a side view for explaining steps of a method for constructing a top plate portion and the like of the tunnel.

【図4】 同トンネルの頂版部等の施工方法の工程を説
明する側面図である。
FIG. 4 is a side view for explaining the steps of the method for constructing the top plate and the like of the tunnel.

【図5】 従来の鉄筋コンクリート構造物の頂版部の施
工方法の工程を説明する側面図である。
FIG. 5 is a side view illustrating steps of a conventional method of constructing a top slab of a reinforced concrete structure.

【符号の説明】[Explanation of symbols]

1 トンネル 2 パイプルーフ(支持体) 12 床版部 13 外壁 14 内壁 15 頂版部 17 支保工 19 吊架台 19a ステー 20 頂版部の上筋 22 頂版部の下筋 24 頂版部の底型枠 25 内壁の側型枠 26 外壁の内側型枠 27 外壁の外側型枠(頂版部の側型枠) DESCRIPTION OF SYMBOLS 1 Tunnel 2 Pipe roof (support) 12 Slab part 13 Outer wall 14 Inner wall 15 Top slab part 17 Support 19 Suspension stand 19a Stay 20 Top slab top streak 22 Top slab bottom streak 24 Bottom mold of top slab Frame 25 Side form of inner wall 26 Inner form of outer wall 27 Outside form of outer wall (side form of top slab)

フロントページの続き (72)発明者 山内 裕之 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 越田 和彦 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 Fターム(参考) 2D054 AB05 AC15 AD23 2D055 BB03 CA06 DA01 GA07 KB08Continuing from the front page (72) Inventor Hiroyuki Yamauchi 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Corporation (72) Inventor Kazuhiko Koshida 1-2-3 Shibaura, Minato-ku, Tokyo Shimizu Corporation F term (reference) 2D054 AB05 AC15 AD23 2D055 BB03 CA06 DA01 GA07 KB08

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 鉄筋コンクリート構造物の頂版部を施工
するにあたり、 前記頂版部について内部に埋設される鉄筋を所定位置に
配置し、 次いで、前記頂版部の底型枠及び側型枠をそれぞれ組み
立てるとともにそれら型枠を支保工で支持し、 次いで、それら型枠内にコンクリートを打設して頂版部
をつくることを特徴とする鉄筋コンクリート構造物の頂
版部の施工方法。
When constructing a top slab of a reinforced concrete structure, a reinforcing bar embedded inside the top slab is disposed at a predetermined position, and then a bottom formwork and a side formwork of the top slab are removed. A method of constructing a slab portion of a reinforced concrete structure, comprising assembling each of the slabs and supporting the slabs with supports, and then casting concrete into the slabs to form a slab portion.
【請求項2】 前記頂版部の上方に予め支持体を設け、
該支持体から下方に延びる吊架台によって前記頂版部の
鉄筋を吊り支持することを特徴とする請求項1記載の鉄
筋コンクリート構造物の頂版部の施工方法。
2. A support is provided in advance above the top plate portion,
The method according to claim 1, wherein the reinforcing bar of the top slab is suspended and supported by a suspension base extending downward from the support.
【請求項3】 前記頂版部の底型枠を組み立てた後、前
記支持体から下方に延びる吊架台を撤去し、頂版部の前
記鉄筋の位置調整を行った後、型枠内にコンクリートを
打設して頂版部をつくることを特徴とする請求項2記載
の鉄筋コンクリート構造物の頂版部の施工方法。
3. After assembling the bottom formwork of the top slab, the suspension base extending downward from the support is removed, and the position of the reinforcing bar in the top slab is adjusted. 3. The method for constructing a top plate of a reinforced concrete structure according to claim 2, wherein the top plate is formed by casting.
【請求項4】 前記支持体は、複数のパイプを並列に配
置してなるパイプルーフであることを特徴とする請求項
2または3記載の鉄筋コンクリート構造物の頂版部の施
工方法。
4. The method according to claim 2, wherein the support is a pipe roof in which a plurality of pipes are arranged in parallel.
JP2000245344A 2000-08-11 2000-08-11 Construction method of top plate part of reinforced concrete structure Expired - Fee Related JP3721505B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000245344A JP3721505B2 (en) 2000-08-11 2000-08-11 Construction method of top plate part of reinforced concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000245344A JP3721505B2 (en) 2000-08-11 2000-08-11 Construction method of top plate part of reinforced concrete structure

Publications (2)

Publication Number Publication Date
JP2002061498A true JP2002061498A (en) 2002-02-28
JP3721505B2 JP3721505B2 (en) 2005-11-30

Family

ID=18735888

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000245344A Expired - Fee Related JP3721505B2 (en) 2000-08-11 2000-08-11 Construction method of top plate part of reinforced concrete structure

Country Status (1)

Country Link
JP (1) JP3721505B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112377216A (en) * 2020-11-12 2021-02-19 招商局重庆交通科研设计院有限公司 Small-angle construction method based on pipe shed in drill jumbo tunnel
CN113931661A (en) * 2021-11-02 2022-01-14 中铁二十四局集团有限公司 Secondary lining template device suitable for large-span cavity dome and construction method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102877858B (en) * 2012-09-26 2015-07-01 安徽理工大学 Reinforcing method for crushed top plate of coal face

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112377216A (en) * 2020-11-12 2021-02-19 招商局重庆交通科研设计院有限公司 Small-angle construction method based on pipe shed in drill jumbo tunnel
CN113931661A (en) * 2021-11-02 2022-01-14 中铁二十四局集团有限公司 Secondary lining template device suitable for large-span cavity dome and construction method
CN113931661B (en) * 2021-11-02 2023-10-27 中铁二十四局集团有限公司 Secondary lining template device suitable for large-span chamber dome and construction method

Also Published As

Publication number Publication date
JP3721505B2 (en) 2005-11-30

Similar Documents

Publication Publication Date Title
KR20090030716A (en) Joint structure for connecting slurry wall and girder/slab and method for constructing girder/slab of underground structures using the same
JP2011157720A (en) Method for constructing railway reinforced concrete rigid-frame structure viaduct
JP4611113B2 (en) Integrated construction method of pile and column
JP2004232328A (en) Structure of half precast type arch culvert and its construction method
JP2769936B2 (en) Construction method of beams and slabs in underground skeleton construction
JP3721505B2 (en) Construction method of top plate part of reinforced concrete structure
KR100640244B1 (en) Method for constructing underground slabs and walls using erection piles without preliminary wall-attached supports
JP6855296B2 (en) Building foundation structure and its construction method
EP0054026A1 (en) Lost formwork for use when casting concrete floors.
JP3644606B2 (en) Installation method of formwork support in reverse placement method
JP3578414B2 (en) Construction method of reinforced concrete retaining wall
JP2002147194A (en) Reinforcing bar-shuttering framing method
JP2000129633A (en) Erection method for bridge floor slab
KR200183137Y1 (en) Precast concrete segment for arch type culvert
KR100694762B1 (en) Method for constructing underground slabs and walls without preliminary wall-attached supports
JP7453837B2 (en) Reinforcement structure and reinforcement construction method for concrete structures
JPH0988348A (en) Method for constructing foundation beam
JP2004360266A (en) Structure and construction method for floor post base part
JP3055754U (en) Large culvert by combination of precast concrete
KR20220153333A (en) Floor frame support system for flat slab in top-down method
JP2023022563A (en) Concrete wall construction method
JPH08144402A (en) Hollow precast concrete member for wall
JP3041754U (en) Half precast slab
JPH03271465A (en) Method of construction for placing slab with manhole
JPH07247594A (en) Architectural method by use of pc member

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050516

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050524

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050720

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050816

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050831

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees