JP2000303694A - Frame and method for unloading members - Google Patents

Frame and method for unloading members

Info

Publication number
JP2000303694A
JP2000303694A JP11115953A JP11595399A JP2000303694A JP 2000303694 A JP2000303694 A JP 2000303694A JP 11115953 A JP11115953 A JP 11115953A JP 11595399 A JP11595399 A JP 11595399A JP 2000303694 A JP2000303694 A JP 2000303694A
Authority
JP
Japan
Prior art keywords
unloading
construction site
members
diagonal
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP11115953A
Other languages
Japanese (ja)
Inventor
Toshiyuki Fukushima
敏之 福島
Yohei Watanabe
洋平 渡辺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sekisui House Ltd
Original Assignee
Sekisui House Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sekisui House Ltd filed Critical Sekisui House Ltd
Priority to JP11115953A priority Critical patent/JP2000303694A/en
Publication of JP2000303694A publication Critical patent/JP2000303694A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To easily and promptly unload members from a member carrying vehicle in the construction field where a mobile crane means cannot enter, by using a temporary member unloading frame which is made up of a hoist machine for hoisting a beam and members, and a diagonal member. SOLUTION: A beam 1 is externally protruded from an external scaffolding 4 so as to be rotated on a vertical axis, at a side edge of the external scaffolding 4. The beam 1 houses therein a trolley in a movable manner, and a hoist machine 2 is linked to the trolley, whereby the hoist machine 2 is moved along the beam 1 together with the trolley. A round steel diagonal member 3 is stretched between a free end, i.e., an external end, of the beam and a standing pole 4. The lower end of the diagonal member 3 is connected to the external end of the beam 1, and the upper end of the diagonal member 3 is connected to the standing pole 41 by pin joint, whereby the diagonal member 3 can be rotated on the vertical axis at the side edge of the external scaffolding 4 together with the beam 1. Thus, unloading of members from a member carrying vehicle or movement of the hoisted members from an upper location can be facilitated.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、建物の施工現場
に仮設されて、部材運搬車から部材を荷降しするのに用
いられる架構、ならびに該部材荷降し用架構を用いて部
材運搬車から部材を荷降しする方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a frame temporarily installed at a construction site of a building and used for unloading members from a member carrier, and a member carrier using the member unloading frame. And a method of unloading a member from a vehicle.

【0002】[0002]

【従来の技術・発明が解決しようとする課題】従来、建
物の施工現場において、トラック等の部材運搬車から部
材を荷降しするには、一般に、クレーン車等の移動式揚
重手段が用いられている。しかしながら、現場によって
は、上記のような移動式揚重手段が敷地付近に進入でき
ない場合もある。このような場合には、部材運搬車から
部材を人力によって荷降しする以外にないため、作業に
多大な労力および時間を要していた。建物を構成する部
材には、例えば形鋼よりなる梁材では単品重量が100
kg以上にも及ぶなど、概して多大な重量を有するもの
が多く、これらを人力によって荷降しするとなると、作
業者に対する肉体的負担が非常に大きくなり、また1部
材ずつ荷降しせざるを得ないため作業時間が長大とな
る。さらに、荷降し作業に長時間を要すると、それだけ
部材運搬車による道路占有時間が長くなって交通障害を
生じることともなる。
2. Description of the Related Art Conventionally, at a construction site of a building, a mobile lifting means such as a crane truck is generally used to unload a member from a member carrier such as a truck. Have been. However, depending on the site, the mobile lifting means as described above may not be able to enter the vicinity of the site. In such a case, there is no other way than to unload the members from the member transporter by human power, so that much work and time are required for the operation. For a member constituting a building, for example, a beam made of shaped steel has a single item weight of 100.
Most of them have a large weight, such as over kg, and if they are to be unloaded manually, the physical burden on the worker becomes very large, and the members must be unloaded one by one. Work time is lengthened. Furthermore, if the unloading operation requires a long time, the occupation time of the road by the member transporter becomes longer, which may cause a traffic obstacle.

【0003】本発明は、上記の点に鑑み、移動式揚重手
段が進入できないような施工現場においても、部材運搬
車から部材を容易かつ迅速に荷降しすることが可能な部
材荷降し手段および部材荷降し方法を提供することを目
的とするものである。
In view of the above, the present invention has been made in consideration of the above circumstances, and has been made in view of the above-described problems. Accordingly, even at a construction site where mobile lifting means cannot enter, a member unloading member can be easily and quickly unloaded from a member carrier. It is an object of the present invention to provide means and a member unloading method.

【0004】[0004]

【課題を解決するための手段】上記目的を達成するため
になされたこの発明の請求項1に記載の部材荷降し用架
構は、建物の施工現場において部材運搬車から部材を荷
降しするために仮設される部材荷降し用架構であって、
前記施工現場における仮設構造物から外方へ突設された
ビームと、前記ビームに配設されて部材の吊り上げを行
う巻上機と、前記ビームの外側端部と前記仮設構造物の
上部との間に架設された斜材と、を備えることを特徴と
するものである。
According to a first aspect of the present invention, there is provided a member unloading frame for unloading a member from a member carrier at a building construction site. A temporary member unloading frame for
A beam protruding outward from the temporary structure at the construction site, a hoisting machine arranged on the beam to lift a member, and an outer end of the beam and an upper part of the temporary structure. And a diagonal member installed between them.

【0005】また、この発明の請求項2に記載の部材荷
降し用架構は、前記請求項1に記載の部材荷降し用架構
において、前記ビームおよび斜材が、仮設構造物側端部
で鉛直方向の軸を中心に回動し得るように該仮設構造物
に接合されていることを特徴とするものである。
According to a second aspect of the present invention, there is provided a member unloading frame according to the first aspect, wherein the beam and the diagonal member are provided at an end of the temporary structure. And is joined to the temporary structure so as to be rotatable about a vertical axis.

【0006】また、この発明の請求項3に記載の部材荷
降し用架構は、前記請求項1または2に記載の部材荷降
し用架構において、前記巻上機がビームに沿って移動し
得るように設けられていることを特徴とするものであ
る。
According to a third aspect of the present invention, there is provided a member unloading frame according to the first or second aspect, wherein the hoist moves along a beam. It is characterized by being provided to obtain.

【0007】また、この発明の請求項4に記載の部材荷
降し方法は、建物の施工現場において部材運搬車から部
材を荷降しする方法であって、前記請求項1乃至3に記
載の部材荷降し用架構のビームを前記部材運搬車の上方
の位置に配置する第1行程と、前記部材運搬車に積載さ
れた部材を、前記ビームの巻上機により吊り上げる第2
行程と、前記部材を部材運搬車の上方の位置から移動さ
せて前記施工現場に降ろす第3行程と、を含むことを特
徴とするものである。
According to a fourth aspect of the present invention, there is provided a member unloading method for unloading a member from a member carrier at a building construction site. A first step of arranging a beam of a member unloading frame at a position above the member transporter, and a second step of lifting a member loaded on the member transporter by a beam hoist.
And a third step of moving the member from a position above the member carrier and lowering the member at the construction site.

【0008】また、この発明の請求項5に記載の部材荷
降し方法は、前記請求項4に記載の部材荷降し方法にお
いて、前記第3行程において、前記ビームおよび斜材を
回動させて部材を水平方向に移動させ、この後該部材を
施工現場に降ろすことを特徴とするものである。
According to a fifth aspect of the present invention, there is provided a member unloading method according to the fourth aspect, wherein the beam and the diagonal member are rotated in the third stroke. The member is moved in the horizontal direction, and then the member is lowered to the construction site.

【0009】また、この発明の請求項6に記載の部材荷
降し方法は、前記請求項4に記載の部材荷降し方法にお
いて、前記第3行程において、前記巻上機をビームに沿
って前記仮設構造物側へ移動させ、この後該部材を施工
現場に降ろすことを特徴とするものである。
In the member unloading method according to a sixth aspect of the present invention, in the member unloading method according to the fourth aspect, the hoisting machine is moved along the beam in the third step. The member is moved to the temporary structure side, and then the member is lowered to a construction site.

【0010】また、この発明の請求項7に記載の部材荷
降し方法は、前記請求項4に記載の部材荷降し方法にお
いて、前記第3行程において、前記巻上機をビームに沿
って前記仮設構造物側へ移動させ、ついで、該ビームお
よび斜材を回動させて水平方向に移動させ、この後、前
記部材を施工現場に降ろすことを特徴とするものであ
る。
According to a seventh aspect of the present invention, there is provided a member unloading method according to the fourth aspect, wherein the hoist is moved along the beam in the third step. The beam and the diagonal member are moved horizontally by rotating the beam and the diagonal member, and then the member is lowered to a construction site.

【0011】なお、この発明において、「施工現場にお
ける仮設構造物」とは、施工現場に仮設された構造物で
あってビームおよび斜材による荷重の少なくとも一部を
支持し得るものを意味し、例えば該施工現場に仮設され
た足場や、該足場とは別個に立設された塔状物、柱状物
等の構造物が含まれるものとする。
In the present invention, the term "temporary structure at a construction site" means a structure temporarily constructed at a construction site and capable of supporting at least a part of a load caused by beams and diagonal members. For example, a scaffold temporarily provided at the construction site or a structure such as a tower or a column which is provided separately from the scaffold is included.

【0012】また、「巻上機」とは、電動式、手動式等
を問わず、部材の吊り上げが可能な機器を広汎に意味
し、例えばウインチ、ホイスト、チェーンブロック等が
いずれも包含されるものとする。
The term "winding machine" broadly refers to a device capable of lifting a member, regardless of whether it is an electric type or a manual type, and includes, for example, winches, hoists, and chain blocks. Shall be.

【0013】[0013]

【発明の実施の形態】以下、本発明の実施形態を例示
し、図面に基づいて具体的に説明する。図1および図2
には、本発明の一実施形態に係る部材荷降し用架構が示
されている。同図に示す部材荷降し用架構F1は、ビー
ム1と、巻上機2と、斜材3とを備えるものとなってい
る。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, embodiments of the present invention will be exemplified and specifically described with reference to the drawings. 1 and 2
1 shows a member unloading frame according to an embodiment of the present invention. The member unloading frame F1 shown in FIG. 1 includes a beam 1, a hoist 2, and a diagonal member 3.

【0014】上記部材荷降し用架構F1は、建物の施工
現場に仮設された外部足場4に付設されている。該外部
足場4は、単管パイプから構成された本足場となってお
り、図2に示すように、建築予定の建物の占有スペース
(以下、建物スペースと称す)Sの両側面および裏側面
に沿って上面視コの字形状に組み立てられている。該外
部足場4の両側部は、施工現場の敷地Lの前側端(前面
道路R側端)近傍まで延びている。
The frame F1 for unloading members is attached to an external scaffold 4 temporarily provided at a construction site of a building. The external scaffold 4 is a main scaffold composed of a single pipe, and as shown in FIG. It is assembled in a U-shape as viewed from above. Both side portions of the external scaffold 4 extend to near the front end (front road R side end) of the site L of the construction site.

【0015】上記外部足場4の上部には、図1に示すよ
うに、天井クレーン5が架設されている。該天井クレー
ン5は、特願平11−21198号に開示されているも
のと基本的に同様のものであり、平行な2条のサイドレ
ール51と、両サイドレール51に直交するようにして
架設されたガーダーレール52とで構成され、該ガーダ
ーレール52には部材を吊り上げるためのウインチ53
が保持されている(なお図1ではガーダーレール52の
一方端部における構成のみを示しているが、他方端部に
おける構成も同様である)。上記外部足場4における複
数の建地41の上端には、それぞれ建物スペースS側方
向へ延出するブラケット42が配設されており、これら
複数のブラケット42の先端部には、前記サイドレール
51の複数箇所が支持されている。これにより、該サイ
ドレール51が桁行方向に沿って架設されている。上記
サイドレール51は、外部足場4の前方(前面道路R側
方向)へやや突出するように架設されている。
As shown in FIG. 1, an overhead crane 5 is installed above the external scaffold 4. The overhead crane 5 is basically the same as that disclosed in Japanese Patent Application No. 11-21198, and is constructed so that two parallel side rails 51 and two side rails 51 are orthogonal to each other. And a girder rail 52 which is provided with a winch 53 for lifting members.
(Note that FIG. 1 shows only the configuration at one end of the girder rail 52, but the configuration at the other end is also the same). Brackets 42 extending toward the building space S are respectively provided at the upper ends of the plurality of buildings 41 in the external scaffold 4. Multiple locations are supported. Thereby, the side rail 51 is erected along the row direction. The side rail 51 is provided so as to slightly protrude in front of the external scaffold 4 (toward the front road R).

【0016】上記サイドレール51およびガーダーレー
ル52は、いずれも、下面の一部がスリット状に開放さ
れた中空状の金属(アルミ、鉄等)よりなる型材となっ
ており、それぞれ内部にトロリ(図示せず)が走行自在
に収容され、両端がエンド部材(図示せず)により閉塞
される構成となっている。上記ガーダーレール52の両
端部は、サイドレール51内のトロリに連結されてお
り、また、前記ウインチ53は、ガーダーレール52内
のトロリに連結されている。これにより、上記ガーダー
レール52はサイドレール51の長さ方向に沿って移動
自在であるとともに、ウインチ53はガーダーレール5
2の長さ方向に沿って移動自在となっている。
Each of the side rails 51 and the girder rails 52 is formed of a hollow metal (aluminum, iron, or the like) whose lower surface is partially opened in a slit shape. (Not shown) is accommodated so that it can run freely, and both ends are closed by end members (not shown). Both ends of the girder rail 52 are connected to a trolley in the side rail 51, and the winch 53 is connected to a trolley in the girder rail 52. Thus, the girder rail 52 can be freely moved along the length direction of the side rail 51, and the winch 53 is connected to the girder rail 5
2 is movable along the length direction.

【0017】上記天井クレーン5によれば、部材を建物
スペースS内の任意の位置へ搬送することが可能である
ので、これにより部材を揚重しながら建物の施工を効率
よく行うことができる。さらに、上記天井クレーン5
は、現場完結式のものであるため、移動式揚重手段が進
入できないような現場において特に有用であり、また足
場を利用して簡便に設置することができる等の利点を有
する。
According to the overhead crane 5, the members can be transported to an arbitrary position in the building space S, so that the building can be efficiently constructed while lifting the members. Furthermore, the above-mentioned overhead crane 5
Since it is a site-completed type, it is particularly useful in a site where mobile lifting means cannot enter, and has advantages such as being easily installed using a scaffold.

【0018】上記外部足場4において建物スペースSの
一方側面に沿って配設された複数の建地41のうち、前
側端に位置する建地41には、図1に示すように、部材
荷降し用架構F1のビーム1が接合されている。該ビー
ム1は、前記天井クレーン5のガーダーレール52と同
一の部材よりなり、内部には同様にトロリ(図示せず)
が走行自在に収容されている。該トロリには巻上機2が
連結されており、該トロリとともにビーム1に沿って移
動し得るようになっている。該巻上機2は、前記ガーダ
ーレール52のウインチ53と同様のウインチとなって
いる。
As shown in FIG. 1, a member 41 located at the front end of the plurality of buildings 41 arranged along one side of the building space S on the external scaffold 4 has a member unloading structure. The beam 1 of the bridge frame F1 is joined. The beam 1 is made of the same member as the girder rail 52 of the overhead crane 5 and has a trolley (not shown) inside.
Are movably accommodated. A hoist 2 is connected to the trolley so that it can move along the beam 1 with the trolley. The hoist 2 is a winch similar to the winch 53 of the girder rail 52.

【0019】上記ビーム1の一方端は、ヒンジを備える
クランプ6を介して、上記建地41にピン接合されてお
り、図1中の矢印A1で示すように、該建地41の長さ
方向に沿って延びる軸を中心に回動し得るようになって
いる。即ち、該ビーム1は、上記外部足場4側端部で鉛
直方向の軸を中心に回動し得るように、該外部足場4か
ら外方へ突設されている。
One end of the beam 1 is pin-joined to the building 41 via a clamp 6 having a hinge, and as shown by an arrow A1 in FIG. Can be rotated about an axis extending along the center. That is, the beam 1 is protruded outward from the external scaffold 4 so as to be able to rotate around a vertical axis at the end of the external scaffold 4 side.

【0020】上記ビーム1は、前面道路Rの外側端縁
部、即ち施工現場の敷地Lから遠い側の端縁部近傍まで
水平に延びている。また、該ビーム1は、上記建地41
の中間の高さ位置に接合されており、巻上機2が、部材
を積載した状態の部材運搬車(図1には図示せず)に抵
触することなく移動し得る程度の高さに架設されてい
る。これにより、該ビーム1は、前面道路R上(即ち荷
降し可能な位置)に停車した部材運搬車の上方の位置に
配置し得るようになっている。
The beam 1 extends horizontally to the outer edge of the front road R, that is, to the vicinity of the edge farther from the site L of the construction site. In addition, the beam 1
And the hoisting machine 2 is erected at such a height that the hoisting machine 2 can move without contacting a member carrier (not shown in FIG. 1) in a state where the members are loaded. Have been. Thereby, the beam 1 can be arranged at a position above the member carrier stopped on the front road R (that is, a position where the beam can be unloaded).

【0021】上記ビーム1の自由端、即ち外側端と前記
建地41の上端との間には、丸鋼よりなる斜材3が架設
されており、該斜材3により、ビーム1の外側端部が外
部足場4の上部に支持されている。該斜材3の下端はビ
ーム1の外側端に接合され、上端は、前記ビーム1の場
合と同様に、建地41にピン接合されており、これによ
り、該斜材3は、ビーム1とともに、外部足場4側端部
で鉛直方向の軸を中心に回動し得る構成となっている。
上記のようにビーム1の外側端部と外部足場4の上部と
の間に斜材3を架設することにより、該ビーム1を底辺
とする直角三角形状の骨組構造が構成されており、これ
により、該ビーム1が外部足場4に安定して支持される
ようになっている。
Between the free end of the beam 1, that is, the outer end, and the upper end of the building 41, a diagonal member 3 made of round steel is erected. The part is supported on the upper part of the external scaffold 4. The lower end of the diagonal member 3 is joined to the outer end of the beam 1, and the upper end is pinned to the building 41 as in the case of the beam 1, whereby the diagonal member 3 is joined together with the beam 1. The outer scaffold 4 is configured to be rotatable around a vertical axis at its end.
As described above, the diagonal member 3 is erected between the outer end of the beam 1 and the upper part of the external scaffold 4 to form a right-angled triangular frame structure having the beam 1 as a base. The beam 1 is stably supported by the external scaffold 4.

【0022】上記斜材3の中間部には、ターンバックル
胴31が配設されており、これにより、必要に応じ該斜
材3を長さ調節して緊張し得るようになっている。
A turnbuckle cylinder 31 is provided at an intermediate portion of the diagonal member 3 so that the length of the diagonal member 3 can be adjusted and tensioned as required.

【0023】以下、上記部材荷降し用架構F1を用いて
部材を荷降しする手順を順次説明する。
The procedure for unloading the members using the member unloading frame F1 will be described below.

【0024】1.配置行程(第1行程) まず、図3に示すように、上記部材荷降し用架構F1の
ビーム1を部材運搬車Tの上方の位置に配置する。
1. Arrangement Step (First Step) First, as shown in FIG. 3, the beam 1 of the member unloading frame F1 is arranged at a position above the member carrier T.

【0025】このとき、上記部材運搬車Tを前面道路R
上に停車してから、ビーム1を回動して該部材運搬車T
の上方の位置に配置するか、あるいは、ビーム1を回動
して前面道路R上に配置してから、該ビーム1の下方の
位置に部材運搬車Tを進入させ停車するようにすればよ
い。
At this time, the member carrier T is connected to the front road R
After stopping above, the beam 1 is turned to rotate the member carrier T
, Or the beam 1 is rotated and arranged on the front road R, and then the member carrier T enters the position below the beam 1 and stops. .

【0026】2.吊り上げ行程(第2行程) ついで、図4に示すように、上記部材運搬車Tに積載さ
れた部材Mを、前記ビーム1の巻上機2により吊り上げ
る。
2. Lifting Stroke (Second Stroke) Next, as shown in FIG. 4, the member M loaded on the member transporter T is lifted by the hoist 2 of the beam 1.

【0027】このとき、部材Mは、部材運搬車T上で予
め一括して玉掛けしておくようにし、積載された全ての
部材Mを、1度の吊り上げで一括して吊り上げるように
する。
At this time, the members M are previously slung collectively on the member transport vehicle T, and all the stacked members M are lifted collectively by one lifting.

【0028】3.部材移動行程(第3行程) この後、図5(a)、(b)に示すように、上記部材M
を部材運搬車Tの上方の位置から移動させて施工現場に
降ろす。
3. Member moving stroke (third stroke) Thereafter, as shown in FIGS. 5A and 5B, the member M
Is moved from a position above the member carrier T and is lowered to the construction site.

【0029】このとき、図5(a)中の矢印A3で示す
ように、上記巻上機2をビーム1に沿って外部足場4側
へ移動させ、ついで、図5(b)中の矢印A4で示すよ
うに、該ビーム1および斜材3を回動させて外部足場4
側へ水平に移動させ、この後、前記部材Mを施工現場に
降ろすようにするとよい。これによれば、部材Mをビー
ム1の回動軸に近い位置に寄せた状態で該ビーム1を回
動させるので、該ビーム1の自由端側にかかる荷重が小
となり、その分、該ビーム1を小さな力で回動させるこ
とができる。
At this time, as shown by an arrow A3 in FIG. 5A, the hoist 2 is moved to the external scaffold 4 along the beam 1, and then, an arrow A4 in FIG. As shown by the arrow, the beam 1 and the diagonal member 3 are rotated to
The member M may be moved horizontally to the side, and then the member M may be lowered to the construction site. According to this, since the beam 1 is rotated in a state where the member M is moved to a position close to the rotation axis of the beam 1, the load applied to the free end side of the beam 1 becomes small, and the beam is accordingly reduced. 1 can be rotated with a small force.

【0030】また、このとき、部材運搬車Tの上方に吊
り上げた部材Mを水平方向に移動させる前に、該部材運
搬車Tを先にビーム1の下方の位置から別の場所へ移動
させておくようにすると、後の作業が行いやすい。
At this time, before the member M suspended above the member carrier T is moved in the horizontal direction, the member carrier T is first moved from a position below the beam 1 to another place. If you keep it, later work will be easier.

【0031】以上の第1乃至第3の行程により、部材運
搬車Tから部材Mを荷降しすることができる。該部材M
は、敷地Lにおける建物スペースSの前に仮置してお
き、前記天井クレーン5により1部材ずつ揚重して建物
の施工を行うようにする。前記したように、外部足場4
は敷地Lの前側端近傍まで延びており、また天井クレー
ン5のサイドレール51は該外部足場4の前方へやや突
出するように架設されているので、上記のようにして仮
置された部材Mは上記天井クレーン5により直上から吊
り上げることができる。
The member M can be unloaded from the member carrier T by the first to third steps described above. The member M
Are temporarily placed in front of the building space S on the site L, and the building is constructed by lifting the members one by one by the overhead crane 5. As mentioned above, the external scaffold 4
Extends to the vicinity of the front end of the site L, and the side rail 51 of the overhead crane 5 is erected so as to protrude slightly in front of the external scaffold 4. Can be lifted from directly above by the overhead crane 5.

【0032】上述のように、上記部材荷降し用架構F1
は、施工現場に仮設された外部足場4から外方へ突設さ
れたビーム1と、該ビーム1に配設されて部材Mの吊り
上げを行う巻上機2と、該ビーム1の外側端部と外部足
場4の上部との間に架設された斜材3とから構成されて
いるので、該部材荷降し用架構F1を用いることによ
り、クレーン車等の移動式揚重手段が進入できないよう
な施工現場においても、人力による荷降し作業によるこ
となく、部材運搬車Tから部材Mを容易かつ迅速に荷降
しすることができる。
As described above, the member unloading frame F1
A beam 1 protruding outward from an external scaffold 4 temporarily provided at a construction site, a hoisting machine 2 disposed on the beam 1 to lift a member M, and an outer end of the beam 1 And the upper part of the external scaffold 4 and the diagonal member 3, so that the mobile unloading means such as a crane truck cannot enter by using the member unloading frame F1. Even at a simple construction site, it is possible to easily and quickly unload the member M from the member transport vehicle T without resorting to manual unloading work.

【0033】即ち、上記部材荷降し用架構F1のビーム
1を部材運搬車Tの上方の位置に配置し(第1行程)、
ついで、上記部材運搬車Tに積載された部材Mを、上記
ビーム1の巻上機2により吊り上げ(第2行程)、この
後、上記部材Mを部材運搬車Tの上方の位置から移動さ
せて施工現場に降ろす(第3行程)ようにすることで、
部材運搬車Tからの部材Mの荷降しを容易かつ迅速に行
うことができる。
That is, the beam 1 of the member unloading frame F1 is arranged at a position above the member carrier T (first stroke),
Next, the member M loaded on the member transporter T is lifted by the hoisting machine 2 for the beam 1 (second stroke). Thereafter, the member M is moved from a position above the member transporter T. By dropping it to the construction site (3rd stroke)
The unloading of the member M from the member transport vehicle T can be performed easily and quickly.

【0034】さらに、上記部材荷降し用架構F1におい
ては、上記ビーム1および斜材3が、外部足場4側端部
で鉛直方向の軸を中心に回動し得るように該外部足場4
に接合されているので、このビーム1および斜材3の回
動動作により、前記第1行程において該ビーム1を部材
運搬車Tの上方の位置に容易に配置し得るとともに、前
記第3行程において部材Mを部材運搬車Tの上方の位置
から容易に移動させることができる。
Further, in the member loading / unloading frame F1, the beam 1 and the diagonal member 3 are rotated so that the beam 1 and the diagonal member 3 can rotate around a vertical axis at the end of the frame 4 on the side of the external scaffold 4.
Since the beam 1 and the diagonal member 3 rotate, the beam 1 can be easily arranged at a position above the member carrier T in the first stroke, and the beam 1 and the diagonal member 3 can be easily arranged in the third stroke. The member M can be easily moved from a position above the member carrier T.

【0035】さらにまた、上記巻上機2がビーム1に沿
って移動し得るように設けられているので、この巻上機
2の移動動作により、前記第3行程において部材Mを部
材運搬車Tの上方の位置から容易に移動させることがで
きる。
Further, since the hoisting machine 2 is provided so as to be movable along the beam 1, the moving operation of the hoisting machine 2 causes the member M to move the member M in the third stroke. Can be easily moved from a position above the.

【0036】また、上記部材荷降し用架構F1は、構成
部材の点数も少なく全体的に簡単な構成となっており、
また外部足場4を利用して容易に設置することができ
る。さらに、ビーム1および巻上機2として、天井クレ
ーン5の構成要素と同一のものを用いることができる。
Further, the frame F1 for unloading members has a simple structure as a whole with a small number of components.
In addition, it can be easily installed using the external scaffold 4. Further, the same components as those of the overhead crane 5 can be used as the beam 1 and the hoisting machine 2.

【0037】さらにまた、上記ビーム1の長さが、荷降
し可能な位置にある部材運搬車Tの上方の位置に配置す
ることが可能な程度の短尺に設定され、そのスパンが小
となっているので、その分揚重可能な重量が大となって
おり、したがって1度の吊り上げで多数の部材を一括し
て吊り上げることができる。ここに示す例では、前記し
たように、該ビーム1として天井クレーン5のガーダー
レール52と同一のレール材が用いられているが、該天
井クレーン5のガーダーレール52が例えば10m程度
の長さとして用いられる場合には、該ガーダーレール5
2により揚重可能な最大重量は250kg程度である。
これに対し、該ビーム1が例えば3m程度の長さとして
用いられる場合には、該ビーム1により揚重可能な最大
重量は1t程度である。部材1点当たりの重量は前記し
たように例えば100kg程度であるから、上記ビーム
1によれば、部材運搬車Tに積載された部材Mを、1部
材ずつではなく、ある程度一括して吊り上げることがで
きる。さらにこの場合、該部材Mの総重量が1t以下程
度であれば、積載された全ての部材Mを、1度の吊り上
げで一括して吊り上げることができる。
Furthermore, the length of the beam 1 is set to be short enough to allow the beam 1 to be disposed above the member carrier T at a position where the beam can be unloaded, and its span is reduced. As a result, the weight that can be lifted is large, so that a large number of members can be lifted at one time by one lifting. In the example shown here, as described above, the same rail material as the girder rail 52 of the overhead crane 5 is used as the beam 1, but the girder rail 52 of the overhead crane 5 has a length of, for example, about 10 m. If used, the girder rail 5
The maximum weight that can be lifted by 2 is about 250 kg.
On the other hand, when the beam 1 is used with a length of, for example, about 3 m, the maximum weight that can be lifted by the beam 1 is about 1 t. As described above, the weight per member is, for example, about 100 kg. Therefore, according to the beam 1, the members M loaded on the member transport vehicle T can be lifted to some extent collectively instead of one by one. it can. Further, in this case, if the total weight of the members M is about 1 t or less, all the stacked members M can be lifted at once by one lifting.

【0038】以上に例示した実施形態には、様々な変更
を加えることが可能である。例えば、図6に示す部材荷
降し用架構F2のように、ビーム1を回動させずに使用
位置に固定したままで用いる構成としてもよい。この場
合、部材移動行程(第3行程)においては、図6中の矢
印A5で示すように、巻上機2を該ビーム1に沿って外
部足場4側へ移動させ、この後部材Mを該ビーム1の外
部足場4側端部の下方に降ろすようにする。またこの場
合、上記部材荷降し用架構F2は、荷降し作業の前後
で、外部足場4の建地41に着脱するようにすればよ
い。
Various modifications can be made to the embodiment exemplified above. For example, like the member unloading frame F2 shown in FIG. 6, the beam 1 may be used without being rotated and fixed at the use position. In this case, in the member moving stroke (third stroke), the hoist 2 is moved along the beam 1 to the external scaffold 4 as shown by an arrow A5 in FIG. The beam 1 is lowered below the end of the external scaffold 4. Further, in this case, the member unloading frame F2 may be attached to and detached from the building 41 of the external scaffold 4 before and after the unloading operation.

【0039】上記図6に示す態様によれば、ビーム1な
いし斜材3を建地41にピン接合する必要はなく、その
分細部を簡略化することができる。
According to the embodiment shown in FIG. 6, there is no need to pin-join the beam 1 or the diagonal member 3 to the building 41, and the details can be simplified accordingly.

【0040】あるいは、例えば、図7に示す部材荷降し
用架構F3のように、巻上機2をビーム1に沿って移動
させずに、部材運搬車の上方に配置し得る位置に固定し
たままで用いる構成としてもよい。この場合、部材移動
行程(第3行程)においては、図7中の矢印A6で示す
ように、ビーム1および斜材3を回動させて部材Mを水
平方向に移動させ、この後該部材Mを施工現場に降ろす
ようにする。
Alternatively, for example, as in a member unloading frame F3 shown in FIG. 7, the hoisting machine 2 is not moved along the beam 1, but is fixed to a position where it can be arranged above the member carrier. It may be configured to be used as it is. In this case, in the member moving stroke (third stroke), the beam M and the diagonal member 3 are rotated to move the member M in the horizontal direction, as shown by an arrow A6 in FIG. To the construction site.

【0041】上記図7に示す態様によれば、ビーム1と
してレールを用いる必要はなく、その分構成を簡略化す
ることができる。
According to the embodiment shown in FIG. 7, it is not necessary to use a rail as the beam 1, and the configuration can be simplified accordingly.

【0042】また、例えば、前記外部足場4とは別個に
適宜な塔状物、柱状物等を立設し、これらを仮設構造物
として、ビーム1の一部を支持させるようにしてもよい
(図示せず)。これによれば、部材荷降し用架構を任意
の位置に設けることができる。
Further, for example, an appropriate tower or column may be erected separately from the external scaffold 4 and may be used as a temporary structure to support a part of the beam 1 ( Not shown). According to this, the member unloading frame can be provided at an arbitrary position.

【0043】また、巻上機2として、例えばチェーンブ
ロック等を用いるようにしてもよく、これによれば、部
材荷降し用架構の設置コストを低減することができる。
Further, for example, a chain block or the like may be used as the hoisting machine 2, whereby the installation cost of the member unloading frame can be reduced.

【0044】また、斜材3としては、丸鋼以外にも例え
ばワイヤーロープ、アングル等の任意の線材ないし棒材
を用いることができる。
As the diagonal member 3, any wire or bar such as a wire rope or an angle can be used other than the round steel.

【0045】[0045]

【発明の効果】以上のように、この発明の請求項1に記
載の部材荷降し用架構は、施工現場における仮設構造物
から外方へ突設されたビームと、前記ビームに配設され
て部材の吊り上げを行う巻上機と、前記ビームの外側端
部と前記仮設構造物の上部との間に架設された斜材とを
備えるものであるので、該部材荷降し用架構を用いるこ
とにより、クレーン車等の移動式揚重手段が進入できな
いような施工現場においても、人力による荷降し作業に
よることなく、部材運搬車から部材を容易かつ迅速に荷
降しすることができる。
As described above, the member unloading frame according to the first aspect of the present invention is provided with a beam projecting outward from a temporary structure at a construction site, and a beam provided on the beam. And a diagonal member installed between the outer end of the beam and the upper part of the temporary structure, so that the member unloading frame is used. Accordingly, even at a construction site where mobile lifting means such as a crane truck cannot enter, it is possible to easily and quickly unload members from the member transporter without using a manual unloading operation.

【0046】さらに、前記ビームは、荷降し可能な位置
にある部材運搬車の上方の位置に配置することが可能な
程度の短尺のものとすることができるので、該ビームの
スパンを小とすることができる。このため、該ビームを
同一材で長尺のものとした場合に比して、揚重可能な重
量を増大させることができるので、1度の吊り上げで多
数の部材を一括して吊り上げることができる。したがっ
て、部材運搬車から部材を1部材ずつ吊り上げる場合に
比して、作業効率を大幅に向上させることができ、部材
運搬車による道路占有時間も大幅に短縮されて交通障害
も生じ難くなる。
Further, since the beam can be so short that it can be arranged above the member carrier at a position where it can be unloaded, the span of the beam can be reduced. can do. For this reason, the liftable weight can be increased as compared with the case where the beam is made of the same material and is long, so that a large number of members can be lifted at one time by one lifting. . Therefore, as compared with the case where members are lifted one by one from the member transporter, the work efficiency can be greatly improved, the time occupied by the member transporter on the road is significantly reduced, and traffic obstacles are less likely to occur.

【0047】さらに加えて、この発明の請求項2に記載
の部材荷降し用架構によれば、前記ビームおよび斜材
が、仮設構造物側端部で鉛直方向の軸を中心に回動し得
るように該仮設構造物に接合されているので、このビー
ムおよび斜材の回動動作により、該ビームを部材運搬車
の上方の位置に容易に配置し得るとともに、部材運搬車
から吊り上げた部材を該部材運搬車の上方の位置から容
易に移動させることができる。
In addition, according to the member unloading frame according to the second aspect of the present invention, the beam and the diagonal member rotate around the vertical axis at the end of the temporary structure. Since the beam and the diagonal member are rotated so as to obtain the beam, the beam can be easily arranged at a position above the member carrier, and the member lifted from the member carrier can be obtained. Can be easily moved from a position above the member carrier.

【0048】さらに加えて、この発明の請求項3に記載
の部材荷降し用架構によれば、前記巻上機がビームに沿
って移動し得るように設けられているので、この巻上機
の移動動作により、部材運搬車から吊り上げた部材を該
部材運搬車の上方の位置から容易に移動させることがで
きる。
[0048] In addition, according to the member unloading frame according to the third aspect of the present invention, the hoist is provided so as to be movable along the beam. By the moving operation, the member lifted from the member carrier can be easily moved from a position above the member carrier.

【0049】また、この発明の請求項4に記載の部材荷
降し方法は、前記請求項1乃至3に記載の部材荷降し用
架構のビームを部材運搬車の上方の位置に配置する第1
行程と、前記部材運搬車に積載された部材を、前記ビー
ムの巻上機により吊り上げる第2行程と、前記部材を部
材運搬車の上方の位置から移動させて前記施工現場に降
ろす第3行程とを含むものであるので、部材運搬車から
の部材の荷降しを容易かつ迅速に行うことができる。
According to a fourth aspect of the present invention, there is provided a member unloading method, wherein the beam of the member unloading frame according to any one of the first to third aspects is arranged at a position above the member transport vehicle. 1
A second step of lifting the members loaded on the member transporter by the beam hoist; and a third step of moving the members from a position above the member transporter and lowering the members on the construction site. Therefore, the member can be easily and quickly unloaded from the member carrier.

【0050】さらに加えて、この発明の請求項5に記載
の部材荷降し方法によれば、前記第3行程において、前
記ビームおよび斜材を回動させて部材を水平方向に移動
させ、この後該部材を施工現場に降ろすようにするの
で、このビームおよび斜材の回動動作により、部材を該
部材運搬車の上方の位置から容易に移動させることがで
きる。
In addition, according to the member unloading method according to the fifth aspect of the present invention, in the third step, the beam and the diagonal member are rotated to move the member in the horizontal direction. Since the member is later lowered to the construction site, the member can be easily moved from a position above the member carrier by the turning operation of the beam and the diagonal member.

【0051】さらにまた、この発明の請求項6に記載の
部材荷降し方法によれば、前記第3行程において、前記
巻上機をビームに沿って前記仮設構造物側へ移動させ、
この後該部材を施工現場に降ろすようにするので、この
巻上機の移動動作により、部材を該部材運搬車の上方の
位置から容易に移動させることができる。
Further, according to the member unloading method according to claim 6 of the present invention, in the third step, the hoist is moved along the beam to the temporary structure side,
Thereafter, the member is lowered to the construction site, so that the member can be easily moved from a position above the member carrier by the moving operation of the hoisting machine.

【0052】さらにまた、この発明の請求項7に記載の
部材荷降し方法によれば、前記第3行程において、前記
巻上機をビームに沿って前記仮設構造物側へ移動させ、
ついで、該ビームおよび斜材を回動させて水平方向に移
動させ、この後、前記部材を施工現場に降ろすようにす
るので、部材をビームの回動軸に近い位置に寄せた状態
で該ビームを回動させることになり、したがって該ビー
ムの自由端側にかかる荷重が小となって、その分該ビー
ムを小さな力で回動させることができる。
Further, according to the member unloading method according to claim 7 of the present invention, in the third step, the hoist is moved along the beam to the temporary structure side,
Next, the beam and the diagonal member are rotated to move in the horizontal direction, and thereafter, the member is lowered to the construction site. Therefore, the member is moved to a position close to the rotation axis of the beam. Therefore, the load applied to the free end side of the beam is reduced, and the beam can be rotated with a correspondingly small force.

【図面の簡単な説明】[Brief description of the drawings]

【図1】実施形態に係る部材荷降し用架構を示す斜視
図。
FIG. 1 is a perspective view showing a member unloading frame according to an embodiment.

【図2】図1の概略平面図。FIG. 2 is a schematic plan view of FIG.

【図3】実施形態に係る部材荷降し方法における配置行
程(第1行程)を示す模式図。
FIG. 3 is a schematic diagram showing an arrangement process (first process) in the member unloading method according to the embodiment.

【図4】実施形態に係る部材荷降し方法における吊り上
げ行程(第2行程)を示す模式図。
FIG. 4 is a schematic diagram showing a lifting process (second stroke) in the member unloading method according to the embodiment.

【図5】実施形態に係る部材荷降し方法における部材移
動行程(第3行程)を示す模式図。
FIG. 5 is a schematic diagram showing a member moving process (third process) in the member unloading method according to the embodiment.

【図6】他の実施形態に係る部材荷降し用架構を示す斜
視図。
FIG. 6 is a perspective view showing a member unloading frame according to another embodiment.

【図7】他の実施形態に係る部材荷降し用架構を示す斜
視図。
FIG. 7 is a perspective view showing a member unloading frame according to another embodiment.

【符号の説明】[Explanation of symbols]

1 ビーム 2 巻上機 3 斜材 4 外部足場(仮設構造物) F1 部材荷降し用架構 DESCRIPTION OF SYMBOLS 1 Beam 2 Hoist 3 Diagonal material 4 External scaffold (temporary structure) F1 Frame for unloading members

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】 建物の施工現場において部材運搬車から
部材を荷降しするために仮設される部材荷降し用架構で
あって、 前記施工現場における仮設構造物から外方へ突設された
ビームと、 前記ビームに配設されて部材の吊り上げを行う巻上機
と、 前記ビームの外側端部と前記仮設構造物の上部との間に
架設された斜材と、を備えることを特徴とする部材荷降
し用架構。
Claims: 1. A member unloading frame temporarily provided for unloading a member from a member carrier at a construction site of a building, the frame being protruded outward from a temporary structure at the construction site. Beam, a hoisting machine arranged on the beam to lift a member, and a diagonal member installed between an outer end of the beam and an upper part of the temporary structure, For unloading components.
【請求項2】 前記ビームおよび斜材が、仮設構造物側
端部で鉛直方向の軸を中心に回動し得るように該仮設構
造物に接合されていることを特徴とする請求項1に記載
の部材荷降し用架構。
2. The temporary structure according to claim 1, wherein the beam and the diagonal member are joined to the temporary structure so as to be rotatable around a vertical axis at a side end of the temporary structure. A frame for unloading members as described in the above.
【請求項3】 前記巻上機がビームに沿って移動し得る
ように設けられていることを特徴とする請求項1または
2に記載の部材荷降し用架構。
3. The frame for unloading members according to claim 1, wherein the hoist is provided so as to be movable along a beam.
【請求項4】 建物の施工現場において部材運搬車から
部材を荷降しする方法であって、 前記請求項1乃至3に記載の部材荷降し用架構のビーム
を前記部材運搬車の上方の位置に配置する第1行程と、 前記部材運搬車に積載された部材を、前記ビームの巻上
機により吊り上げる第2行程と、 前記部材を部材運搬車の上方の位置から移動させて前記
施工現場に降ろす第3行程と、を含むことを特徴とする
部材荷降し方法。
4. A method for unloading a member from a member carrier at a construction site of a building, wherein the beam of the member unloading frame according to claim 1 is disposed above the member carrier. A second step of lifting a member loaded on the member transporter by the beam hoist; and moving the member from a position above the member transporter to the construction site. And a third step of unloading the member.
【請求項5】 前記第3行程において、前記ビームおよ
び斜材を回動させて部材を水平方向に移動させ、この後
該部材を施工現場に降ろすことを特徴とする請求項4に
記載の部材荷降し方法。
5. The member according to claim 4, wherein, in the third step, the member is moved in a horizontal direction by rotating the beam and the diagonal member, and thereafter, the member is lowered to a construction site. Unloading method.
【請求項6】 前記第3行程において、前記巻上機をビ
ームに沿って前記仮設構造物側へ移動させ、この後該部
材を施工現場に降ろすことを特徴とする請求項4に記載
の部材荷降し方法。
6. The member according to claim 4, wherein, in the third step, the hoist is moved along the beam to the temporary structure, and then the member is lowered to a construction site. Unloading method.
【請求項7】 前記第3行程において、前記巻上機をビ
ームに沿って前記仮設構造物側へ移動させ、ついで、該
ビームおよび斜材を回動させて水平方向に移動させ、こ
の後、前記部材を施工現場に降ろすことを特徴とする請
求項4に記載の部材荷降し方法。
7. In the third step, the hoist is moved along the beam to the temporary structure side, and then the beam and the diagonal member are rotated to move in the horizontal direction. The member unloading method according to claim 4, wherein the member is unloaded to a construction site.
JP11115953A 1999-04-23 1999-04-23 Frame and method for unloading members Pending JP2000303694A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11115953A JP2000303694A (en) 1999-04-23 1999-04-23 Frame and method for unloading members

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11115953A JP2000303694A (en) 1999-04-23 1999-04-23 Frame and method for unloading members

Publications (1)

Publication Number Publication Date
JP2000303694A true JP2000303694A (en) 2000-10-31

Family

ID=14675244

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11115953A Pending JP2000303694A (en) 1999-04-23 1999-04-23 Frame and method for unloading members

Country Status (1)

Country Link
JP (1) JP2000303694A (en)

Similar Documents

Publication Publication Date Title
JP2008248664A (en) Hoisting method of curtain wall
WO2015152235A1 (en) Method for manufacturing crane and system for mounting superstructure of crane
JP2819990B2 (en) Hoist type tower crane
JPH06272389A (en) Temporary unloading stage
JPH09302919A (en) Transfer platform for columnar body
JP2000303694A (en) Frame and method for unloading members
CN213925880U (en) Steel case composite beam bridge segment section and decking setting device
JPH05147884A (en) Dismountable jib crane
JP2001213584A (en) Large-scale elevation stage and lifting method and reversely driving technique using the same
JP6393954B2 (en) Crane overhead structure system and crane manufacturing method
JPH09240988A (en) Assembling method of bridge crane
JP2000303696A (en) Frame and method for unloading members
CN117513764B (en) Sliding method with installation position lower than sliding rail
JP2833439B2 (en) Hoist type tower crane
JPH0328066Y2 (en)
JPH10167668A (en) Vertical and horizontal transporting device and its operation
JP2000053375A (en) Vertical carrier system corresponding to slewing overhead crane
KR0139129B1 (en) Lifting device and method in carrage
JP3100574B2 (en) Suspended scaffold and its erection method
CN117513764A (en) Sliding method with installation position lower than sliding rail
SU1017657A1 (en) Bridge crane and method of mounting same
JPH07315740A (en) Carrying out method for escalator truss
JPS58784B2 (en) Method for lifting and lowering construction materials using framework scaffolding
JP2567560B2 (en) Bridge construction method using precast girders
JP3306336B2 (en) Passenger conveyor installation equipment

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040604

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060208

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060214

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20060613