EP3976888A1 - Method for repairing a damaged wind turbine foundation - Google Patents
Method for repairing a damaged wind turbine foundationInfo
- Publication number
- EP3976888A1 EP3976888A1 EP20728939.8A EP20728939A EP3976888A1 EP 3976888 A1 EP3976888 A1 EP 3976888A1 EP 20728939 A EP20728939 A EP 20728939A EP 3976888 A1 EP3976888 A1 EP 3976888A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- sections
- section
- foundation
- wind turbine
- filler material
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D37/00—Repair of damaged foundations or foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
- E02D27/425—Foundations for poles, masts or chimneys specially adapted for wind motors masts
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D13/00—Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
- F03D13/20—Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
- F03D13/22—Foundations specially adapted for wind motors
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements
- E04G23/0229—Increasing or restoring the load-bearing capacity of building construction elements of foundations or foundation walls
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F05—INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
- F05B—INDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
- F05B2230/00—Manufacture
- F05B2230/80—Repairing, retrofitting or upgrading methods
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/72—Wind turbines with rotation axis in wind direction
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/728—Onshore wind turbines
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P70/00—Climate change mitigation technologies in the production process for final industrial or consumer products
- Y02P70/50—Manufacturing or production processes characterised by the final manufactured product
Definitions
- the present disclosure relates to a method for repairing damage to a foundation of an onshore wind turbine installation, which may involve partial-replacement of regions of the foundation.
- Onshore wind turbines are supported on a concrete slab that is known as a foundation.
- a foundation typically includes a part that defines a top surface that extends above the surrounding ground level and which is adapted for fixing to a base of a wind turbine tower; this part is typically referred to as a pedestal.
- a base flange of the wind turbine tower is connected to the pedestal of the foundation either directly or by way of an adapter plate, coupled with an arrangement of grout and pre-tensioned anchor bolts.
- the concrete foundation is exposed to harsh weather conditions and is subject to high compressive and tensile loads due to the movement of the tower. These factors can lead to cracking and flaking of the concrete structure, particularly around the base of the tower where the foundation is most exposed. Although such damage is understood not to compromise the structural integrity of the foundation initially, it may mean that the foundation is vulnerable to freeze-thawing effects and so repair or replacement is desirable before the structural integrity is affected. Such issues can also occur if the compressive strength of the cured concrete is not at the required level. When inspection identifies unacceptable degradation and cracking of the foundation, a repair strategy must be employed. Currently, remedial work on surface damage may involve injecting mortar or resin into the cracks and subsequent water sealing.
- the wind turbine installation includes a wind turbine tower mounted on the foundation at a tower flange, and the foundation comprises an anchor cage embedded within a central pedestal.
- the anchor cage comprises a plurality of circumferentially spaced tensioned anchoring rods to which the tower flange is attached.
- the method comprises: identifying at least one first section of the pedestal which requires replacement; de-tensioning anchoring rods located within the first section; excavating the first section to form a cavity, wherein that cavity extends at least partially under the tower flange; filling the cavity with a filler material; allowing the filler material to cure until a predetermined strength of the filler material is achieved; and re-tensioning the de-tensioned anchoring rods located in the first section.
- the method of the invention provides a process by which the pedestal of the foundation can be repaired or at least partially replaced whilst the tower remains situated on the pedestal. This avoids the need for the wind turbine to be disassembled before the pedestal can be repaired therefore providing a saving in both time and cost. Since the pedestal can be repaired more quickly, the wind turbine can be returned to operational readiness more rapidly.
- the anchor rods Before the identified section or sections have been evacuated it is required to de-tension the anchor rods to reduce the compressive force exerted by the tower flange on the region of the pedestal that is to be replaced. In addition, it may be beneficial to de tension at least one anchoring rod located adjacent the first section.
- the method may include replacing said protection sleeves on respective anchoring rods within the cavity, before filling the cavity with filler material. This ensures that the anchoring rods do not bond with the filler material.
- the method of the invention may be used to replace a single section of the pedestal, the method may also involve the identification of a plurality of sections of the pedestal that require replacement. In such a case, the method may further include excavating more than one of the identified sections to form two or more cavities in the foundation. The two or more cavities may be spaced from one another.
- the plurality of identified sections extend about the tower flange.
- the plurality of identified sections extend about the tower flange in an annular or part-annular arrangement.
- the plurality of identified section may provide a contiguous ring-like arrangement of sections that define an underlying annular section of the pedestal that will be replaced underneath the tower flange.
- the step of identifying a first section of the pedestal that requires replacement may includes grouping the identified sections into at least first and second groups, wherein the sections in each group are associated with a set of respective identifiers, such that at least some of the sections in the first group are associated with identifiers that are in common with at least some of the sections in the second group.
- the method may include selecting a first section in the first group and selecting a first section in the second group, those first sections having a first identifier in common. Those identified first sections having a common identifier may be replaced first before moving on to replacement of other sections identified with other common identifiers during a separate working procedure.
- the excavation of a section includes water-jet excavation.
- Figure 1 is a front view of an onshore wind turbine installation to which the invention is applicable, including a wind turbine mounted to a subterranean foundation;
- Figure 2 is a detailed view of a part of the foundation show in Figure 1 ;
- Figure 3 is a perspective view of the foundation that illustrates possible wear-related degradation that may occur
- Figure 4 is a plan view of the foundation which depicts an arrangement of identified sections that extend about the pedestal of the foundation;
- FIG. 5 is a flowchart of the method of the invention.
- Figures 6 to 9 show a series of steps that correspond to the flowchart of Figure 5.
- FIG. 1 shows a wind turbine installation comprising a wind turbine 2 which in this example is a horizontal-axis wind turbine (HAWT) that includes a nacelle 6 mounted on top of a tower 8.
- the nacelle 6 supports a rotor 10 including a hub 12 and three blades 14.
- the tower 8 of the wind turbine 2 is mounted to a foundation 16 which is made of reinforced concrete and is embedded in the ground 18 in the usual way.
- a HAWT is shown here, it should be noted hat the embodiments of the invention as will be described below are also applicable to other forms of wind turbines, for example vertical axis or‘Darrieus’ type wind turbines.
- the base of the tower 8 is supported by and is affixed to the foundation 16 by a suitable fastening system.
- a suitable fastening system As the skilled person will appreciate there are various approaches to achieving this fixing, but one example will be described here for context. However, this specific example should not be taken to be limiting to the scope of the invention as defined by the claims.
- FIG. 2 shows a more detailed view of the mechanical interface between the tower 8 and the foundation 16.
- the tower 8 includes a tower base flange 20 that is secured to an upper surface 21 of an upstanding pedestal 22 of the foundation 16.
- an annular strengthening structure that is referred to as an anchor cage 24.
- Such a structure is well-known to the skilled person as a system that is conceived to transfer the loads of the wind turbine to the foundation in a more effective way. It is known for such anchor cages to be embedded within their foundation so that they are fully‘submerged’ but also where parts of the anchor cages extend beyond the concrete mass. The term‘embedded’ therefore should be interpreted accordingly.
- the anchor cage 24 includes a lower base flange or‘anchor plate’ 30, a load distribution flange 32 (which is optional) and a plurality of circumferentially spaced anchor rods 34 that extend between the lower base flange 30 and the load distribution flange 32.
- the anchor rods 34 are arranged in a pair of parallel rows.
- the load distribution flange 32 is situated at the upper surface 21 of the pedestal therefore forming an interface to which the tower base flange 20 of the wind turbine tower 8 can be connected.
- the tower base flange 20 is provided with a plurality of thru-holes (not shown in the Figures, but implied) which mate to the arrangement of the anchor rods 34.
- Respective nuts 40 are tightened over the anchor rods and tensioned appropriately to secure the tower base flange 20 in position and provide a secure anchoring point for the wind turbine.
- the embodiments of the invention propose a solution to the problems described above in which the pedestal 22 of the foundation 16 can be repaired and, indeed at least partially replaced, whilst the wind turbine tower 8 is still anchored to it.
- the inventive concept involves identification of a damaged section or multiple sections of the foundation and excavating the section(s) so as to form a respective cavity that extends below the tower base flange 20, whereinafter that cavity is filled with a suitable filler material such as grout.
- a comparatively non-destructive excavation technique is preferred such as high-pressure water jetting, as this is capable of removing concrete from the identified section whilst not affecting either reinforcing bars in the section nor the anchor rods that extend vertically through the section.
- Figure 4 illustrates a diagrammatic plan view of the foundation and is centred on the pedestal 22, thus depicting the load distribution flange 32. It should be noted that the following repair and replacement procedure is undertaken with the tower situated on the load distribution flange 32. For clarity, however, the tower is not shown in Figure 4, although its presence is implied.
- the method of the invention is started by determining the scope of repair, as shown at step 100. Although only a limited repair may be needed, the illustrated embodiment assumes that a significant repair is required such that a partial replacement of the pedestal 22 is needed.
- the pedestal 22 is divided into a section arrangement 50 comprising a plurality of sections 52 (Fig 5 - step 102). Only three of the individual sections are labelled in Figure 4.
- the arrangement of sections 52 extend about or encircle the pedestal 22 in an annular arrangement.
- the sections 52 are contiguous in the sense that one section is located so as to be adjacent to a neighbouring section and shares a common boundary with it. It will be appreciated that this type of arrangement assumes that the significant proportion of the pedestal will be replaced. However, a different arrangement would be suitable if only a part of the pedestal 22 requires remedial work.
- the section arrangement 50 could extend around a restricted arc of the pedestal 22.
- each of the sections 52 extends radially and circumferentially.
- the radial‘depth’ and the circumferential‘width’ of each section 52 is equal, although it is envisaged that this need not be the case in other arrangements as the geometry of each of the sections 52 could be determined individually.
- the section arrangement 50 and so extends from a first or ‘inner’ radius position R1 , when measured from the central axis 54 of the pedestal 22, to a second or‘outer’ radius position R2.
- the precise dimensions of the inner and outer radius positions R1 and R2 for each section may differ or they may be the same.
- the inner and outer radius positions R1 and R2 may be determined based on understanding of how extensive the damage to the pedestal may be.
- the dimensions R1 and R2 may be specified as extending a sufficient horizontal distance beyond radially inner and outer edges (32a, 32b) of the load distribution flange 32.
- each of the sections 52 has a predetermined height H, which is shown in the inset panel of Figure 4.
- the height dimension H of each section may be specified for example based on the depth of the damaged concrete. In the event that the pedestal is known to comprise a different grade of concrete, than the depth of the pedestal may be influential on the determination of the height H of the section.
- the plurality of sections 52 in the section arrangement 50 are divided into at least first and second groups.
- the section arrangement 50 comprises four groups (A-E) each containing five sections, such that the section arrangement 50 comprises twenty individual sections 52 in total.
- the sections in each group are associated with a set of respective identifiers, such that at least some of the sections in the first group are associated with identifiers that are in common with at least some of the sections in the second group.
- the identifiers are simply integer numbers (e.g. 1 , 2, 3 and 4) although in principle any appropriate identifier scheme could be used.
- the repair process can begin by identifying a first one of the sections 52 to excavate (Fig 5 - step 104). It will be appreciated from Figure 4 that the plurality of sections 52 extend at least partially under the load distribution flange 32. Therefore, before the concrete within a section 52 can be excavated, the process includes de-tensioning the anchor rods within that section (Fig 5-step 106). It will be appreciated that the anchor rods 34 are placed in tension by the action of the associated nuts 40 that are affixed to the respective anchor rods 34.
- step of de-tensioning the anchor rods 34 that are within the identified first section avoid any risk of the load distribution flange 32 from buckling.
- Figure 6 shows this step diagrammatically as the nuts 40 of the relevant anchor rods 34 are have been loosened, thereby relieving the tension in the anchor rods 34 that pass through the identified first section 52 to be excavated. It should be noted that the nuts 40 need to be loosened only slightly, although the position of the nuts 40 in Figure 6 have been exaggerated for clarity.
- the first identified section 52 can be excavated (Fig 5 - step 108).
- a first identified section having been excavated to form a cavity is shown in Figure 6 as‘60’.
- a less aggressive approach would be more optimal such as the use of a high pressure water jet device.
- water jet devices are commercially available for blast-removing concrete, but they have the advantage that they do not damage metal objects within the concrete. So, in this case a high pressure water jet device would enable maintenance personnel to excavate the identified section to create a cavity that extends underneath the load distribution flange 32 without damaging the anchor rods 34 that pass through the section or any reinforcing bars that are exposed as the concrete is blasted away.
- the process of excavating the identified section to form a cavity 60 may damage any protective sleeves (Figure 2 - 62) that are installed on the anchor rods 34.
- protective sleeves are often installed on anchor rods in order to prevent the poured concrete from bonding to the anchor rods and interfering with the tensioning process.
- Such protective sleeves 62 are typically simple plastic tubes or tape and so are easily damaged by the high pressure blasting that will be used to excavate the concrete within the section. Any protective sleeves that are damaged should therefore be replaced before the excavated section 52 is filled ( Figure 5 - step 110).
- debris removal may be achieved by the use of a suitable technique such as the use of a slurry vacuum machine.
- Figure 7 depicts the cavity 60 being filled with filler material 64 through a suitable filler nozzle 66.
- suitable formwork such as plastic, wood or metal panels, as would be known to the skilled person, should be applied around the cavity before it is filled. This will ensure that the exposed exterior form of the filled section matches the form of the sections around it.
- the filler material may take a variety of forms but in order for it to provide a suitable base to support the tower base flange 20 it is preferred that the filler material has a compressive strength that is equal to or exceeds the compressive strength of the concrete from which the foundation 16 is or should be formed. It is envisaged that a suitable filler material will be a high performance grout material that is commonly used in wind turbine foundations and which would be well-known to the skilled person. One example of which is Conbextra BB92 by Fosroc UK.
- a suitable time period is provided to allow the filler material to cure, and therefore harden to result in a section with the required compressive strength as specified ( Figure 5 - step 112).
- a suitable time period would be between 12 to 36 hours to provide a sufficient time for the grout to cure to a maturity level such that the anchor bolts can be re-tensioned.
- Figure 8 illustrates an example where two sections 52 have been excavated therefore creating a pair of cavities 60 that are spaced from each other circumferentially
- Figure 9 illustrates that pair of cavities 60 having been filled with a suitable filler material 64.
- the scenario shown in Figure 8 and 9, and particularly the relative spacing is illustrative only and is not meant to indicate a practical situation.
- simultaneous excavation does not occur in diametrically opposed positions because that can adversely affect the base tower flange.
- all of the first identified sections that is to say the sections that are identified with the same identifier #1 , are excavated, filled and allowed to cure within the same working procedure. Once all of those sections have been completed, then the process repeats by identifying the next set of sections to be excavated, filled and allowed to cure ( Figure 5 - steps 116, 118 and 120).
- the next sections to be selected for work are spaced from the previously- filled sections.
- the sections identified with the identifier #3 may be excavated, filled and cured in the next work procedure.
- the sections marked as #2 may be excavated, filled and then cured.
- the sections identified as #4 may be excavated, filled and cured.
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Paleontology (AREA)
- Mining & Mineral Resources (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Sustainable Development (AREA)
- Sustainable Energy (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- Working Measures On Existing Buildindgs (AREA)
Abstract
Description
Claims
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DKPA201970333 | 2019-05-27 | ||
| PCT/DK2020/050145 WO2020239176A1 (en) | 2019-05-27 | 2020-05-20 | Method for repairing a damaged wind turbine foundation |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| EP3976888A1 true EP3976888A1 (en) | 2022-04-06 |
Family
ID=70918170
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| EP20728939.8A Withdrawn EP3976888A1 (en) | 2019-05-27 | 2020-05-20 | Method for repairing a damaged wind turbine foundation |
Country Status (2)
| Country | Link |
|---|---|
| EP (1) | EP3976888A1 (en) |
| WO (1) | WO2020239176A1 (en) |
Family Cites Families (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE102011089522A1 (en) * | 2011-12-22 | 2013-06-27 | Wobben Properties Gmbh | Method for stabilizing a wind turbine |
| DE102012017243A1 (en) * | 2012-08-31 | 2014-03-06 | Exclutech UG (haftungsbeschränkt) | Method of attachment of outer and inner construction structure such as tiles on walls for indoor and outdoor use, involves connecting treated objects or even larger areas in long run very firmly to ground |
| AU2014100878B4 (en) * | 2014-08-05 | 2015-04-09 | McCulloch, James Peter John MR | Apparatus and method for excavating a cavity and setting an object at least partially therein |
| DE202015100932U1 (en) * | 2015-02-26 | 2015-06-10 | Wpt Nord Gmbh | Device for securing, in particular rehabilitation, of a foundation in wind turbines, as well as foundation |
| EP3411595B1 (en) * | 2016-02-05 | 2020-10-28 | Vestas Wind Systems A/S | Method of replacing anchor bolts in wind turbine foundations |
-
2020
- 2020-05-20 WO PCT/DK2020/050145 patent/WO2020239176A1/en not_active Ceased
- 2020-05-20 EP EP20728939.8A patent/EP3976888A1/en not_active Withdrawn
Also Published As
| Publication number | Publication date |
|---|---|
| WO2020239176A1 (en) | 2020-12-03 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US11555480B2 (en) | Prestressed-bolted dry-assembled segmental precast hybrid tower with grouting-free | |
| CN108474193B (en) | A METHOD OF FORMING A WIND TURBINE FOUNDATION AND RELATED SYSTEM FOR FORMING THE SAME | |
| US20110131899A1 (en) | Apparatus and method for producing a concrete foundation | |
| AU2009349932B2 (en) | Telescopic tower assembly and method | |
| US10138648B2 (en) | Tower and method for assembling tower | |
| EP3516134B1 (en) | Foundation for a windmill | |
| CN108603492A (en) | Tower sections and method utilizing segmented support plates | |
| US11274784B2 (en) | In-service repair method combining externally bonded pre-stressed FRP and polymer grouting for PCCP with broken wire | |
| CN204456167U (en) | Prestress anchoraging blower foundation | |
| CN107100192B (en) | Local reinforcing device and method for foundation ring of wind generating set | |
| CN101813069A (en) | Foundation for enabling anchoring of a wind turbine tower thereto by means of replaceable through-bolts | |
| WO2010138978A2 (en) | Fatigue resistant foundation | |
| KR102160628B1 (en) | Wind turbine structure for retrofitting spread footing in partial repowering , and construction method for the same | |
| US4731915A (en) | Machinery support and method | |
| CN108506169A (en) | A kind of Wind turbines prestressing force stay-supported pylon increases method and structure | |
| CN206768845U (en) | Prefabricated cushion cap foundation and its mounting structure | |
| CN115573376B (en) | Method for treating cracking of foundation of circular transmission tower | |
| KR101126483B1 (en) | A maintaining method of the underwater structures with fiber sheet | |
| EP3976888A1 (en) | Method for repairing a damaged wind turbine foundation | |
| CN107090841A (en) | Prefabricated cushion cap foundation, transmission tower and its construction method | |
| WO2023214094A1 (en) | Foundation for a superstructure and for a wind turbine, wind turbine with a foundation, method for forming a wind turbine foundation | |
| JP2007239283A (en) | Method of reinforcing concrete structure | |
| CN112411605A (en) | Reinforcement reinforcing method and system for foundation anchor bolt of power transmission tower | |
| CN106592622A (en) | Annular concrete based wind-driven generator foundation structure with vertical prestress | |
| CN214497526U (en) | Prefabricated hollow steel pipe concrete supporting member and inner supporting system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: UNKNOWN |
|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE |
|
| PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE |
|
| 17P | Request for examination filed |
Effective date: 20211206 |
|
| AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
| DAV | Request for validation of the european patent (deleted) | ||
| DAX | Request for extension of the european patent (deleted) | ||
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: EXAMINATION IS IN PROGRESS |
|
| 17Q | First examination report despatched |
Effective date: 20231102 |
|
| 18D | Application deemed to be withdrawn |
Effective date: 20240305 |