DE530209C - Arrangement for the boiler feed - Google Patents

Arrangement for the boiler feed

Info

Publication number
DE530209C
DE530209C DES64135D DES0064135D DE530209C DE 530209 C DE530209 C DE 530209C DE S64135 D DES64135 D DE S64135D DE S0064135 D DES0064135 D DE S0064135D DE 530209 C DE530209 C DE 530209C
Authority
DE
Germany
Prior art keywords
water
boiler
function
flue gas
preheater
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
DES64135D
Other languages
German (de)
Inventor
Dr Waldemar Stender
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Siemens Schuckertwerke AG
Siemens Corp
Original Assignee
Siemens Schuckertwerke AG
Siemens Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Siemens Schuckertwerke AG, Siemens Corp filed Critical Siemens Schuckertwerke AG
Priority to DES64135D priority Critical patent/DE530209C/en
Application granted granted Critical
Publication of DE530209C publication Critical patent/DE530209C/en
Expired legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F22STEAM GENERATION
    • F22DPREHEATING, OR ACCUMULATING PREHEATED, FEED-WATER FOR STEAM GENERATION; FEED-WATER SUPPLY FOR STEAM GENERATION; CONTROLLING WATER LEVEL FOR STEAM GENERATION; AUXILIARY DEVICES FOR PROMOTING WATER CIRCULATION WITHIN STEAM BOILERS
    • F22D3/00Accumulators for preheated water
    • F22D3/04Accumulators for preheated water combined with steam accumulators

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Control Of Steam Boilers And Waste-Gas Boilers (AREA)

Description

Anordnung zur Kesselspeisung Es kommt vor, daß Kessel auf mehreren Wegen gespeist werden, von denen der eine durch einen Rauchgasvorwärmer führt. Die Anordnung wird dann gewöhnlich so getroffen, daß die Wasserförderung durch den Rauchgasvorwärmer in Abhängigkeit von der Wassertemperatur hinter diesem Vorwärmer selbsttätig geregelt wird. Das durch den Rauchgasvorwärmer geförderte Wasser kann beispielsweise dem Kessel unmittelbar zugeführt werden, während der Rest des Bedarfs z. B. aus einem über einen Dampfvorwärmer gespeisten - Warmwasserspeisewasserspeicher gedeckt wird. In anderem Falle verfährt man z. B. so, daß man das im Rauchgasvorwärmer vorgewärmte Wasser speichert und dieses gespeicherte Wasser bei starkem Dampfbedarf zur Speisung des Kessels benutzt, während man den Kessel in Zeiten geringen Dampfbedarfes unmittelbar mit kaltem Wasser speist.Arrangement for the boiler feed It happens that there are several boilers Ways to be fed, one of which leads through a flue gas preheater. the The arrangement is then usually made so that the water is conveyed through the flue gas preheater automatically regulated depending on the water temperature behind this preheater will. The water conveyed through the flue gas preheater can, for example, be the Boiler are supplied immediately, while the rest of the requirement z. B. from a The hot water feed water storage tank fed by a steam preheater is covered. In the other case one proceeds z. B. so that the preheated in the flue gas preheater Stores water and this stored water for feeding when there is a high demand for steam of the boiler, while the boiler is used directly in times of low steam demand feeds with cold water.

In den Fällen nun, in denen ein Speisewasserwarmwasserspeicher angeordnet ist, sei es zur Speicherung des durch den Rauchgasvorwärmer vorgewärmten Wassers, sei es zur Speicherung von warmem Wasser anderer Herkunft, kann es vorkommen, daß bei übermäßig lang andauerndem großem Dampfverbrauch alles gespeicherte warme Wasser verbraucht wird. Es tritt dann die Gefahr ein, daß der Kessel nicht genügend gespeist wird und daß sein Wassertand unter das zulässige Maß sinkt.Now in those cases in which a feed water hot water storage tank is arranged whether it is to store the water preheated by the flue gas preheater, be it for the storage of warm water of another origin, it can happen that all stored warm water in the event of excessively long steam consumption is consumed. There is then the risk that the boiler is not fed sufficiently and that its water level sinks below the permissible level.

Dieser Übelstand wird nun nach der Erfindung dadurch vermieden, daß die Einwirkung der die Fördermenge in Abhängigkeit von der Wassertemperatur hinter dem Rauchgasvorwärmer beschränkenden Temperaturmeßvor richtung bei ungenügender Förderung durch den Rauchgasvorwärmer in Abhängigkeit vom Wasserverbrauch im Kessel selbsttätig aufgehoben wird.This drawback is now avoided according to the invention in that the effect of the flow rate depending on the water temperature behind the flue gas preheater limiting Temperaturmeßvor direction with insufficient Funding through the flue gas preheater depending on the water consumption in the boiler is automatically canceled.

Die Zeichnung zeigt Beispiele der Erfindung. In den Abbildungen bedeutet i einen Dampfkessel, der das Dampfnetz :2 speist. 3 ist ein Warmwasserspeicher, q. der Rauchgasvorwärmer. Die Pumpe 5 fördert das Wasser in Abhängigkeit von der Wassertemperatur an der Stelle 6 durch den Rauchgasvorwärmer und führt es im Beispiel nach der Abb. i dem Kessel unmittelbar zu. Die Abhängigkeit ist durch die Linie 7 angedeutet. Der Rest des Wasserbedarfs wird in diesem Beispiel aus dem Speicher 3 gedeckt, dem das Wasser mit einer Pumpe 8 durch einen Dampfvorwärmer 9 zugeführt wird. Aus diesem Speicher 3 wird das Wasser durch eine Pumpe io in den Kessel i gefördert. Der Heizdampf fließt dem Dampfvorwärmer g. durch die Leitung i i zu, und zwar dann, wenn der Dampfdruck in der Leitung :2 so stark steigt, daß das Ventil 12 geöffnet wird, wobei gleichzeitig die Pumpe 8 so geregelt wird, daß eine dem Dampfvoxwärmer zuströmende Dampfmenge eine entsprechende Wassermenge erwärmt. Bei anhaltend stäxkexri Dampfverbrauch wird daher der Warmwasserspeicher 3 nicht weiter gefüllt, wohl aber wird ihm durch die Pumpe io dauernd Wasser abgenommen und in den Kessel gefördert, so daß es vorkommen kann, daß er leer wird. Die durch den Rauchgasvorwärmer strömende Wassermenge genügt aber in diesem Fall allein nicht zur Speisung des Kessels, wenn das Wasser nur so schnell durch den Rauchgasvorwärmer hindurchströmt, daß es am Punkt 6 beispielsweise annähernd die Siedetemperatur des Kessels hat. Nach der Erfindung wird deshalb die Einwirkung der bei 6 angeordneten Temperaturmeßvorrichtüngauf die Pumpe 5 in Abhängigkeit von dem zu tiefen Sinken des Schwimmers 13 im Kessel i aufgehoben, wie dies durch die Linie 14 angedeutet ist. Infolgedessen läuft die Pumpe 5 mit voller Drehzahl und fördert die erforderliche Wassermenge in den Kessel i.The drawing shows examples of the invention. In the figures means i a steam boiler that feeds the steam network: 2. 3 is a hot water tank, q. the flue gas preheater. The pump 5 promotes the water depending on the Water temperature at point 6 through the flue gas preheater and leads it in the example according to Fig. i directly to the boiler. The dependency is through the line 7 indicated. In this example, the rest of the water requirement is taken from the storage tank 3 covered, to which the water is fed with a pump 8 through a steam preheater 9 will. From this memory 3, the water is io into the boiler i by a pump promoted. The heating steam flows to the steam preheater g. through line i i to, namely when the vapor pressure in the line: 2 rises so much that the valve 12th is opened, at the same time the pump 8 is controlled so that one of the Dampfvoxwärmer incoming steam heats a corresponding amount of water. With persistent stäxkexri Steam consumption, the hot water tank 3 is therefore no longer filled, but it is water is continuously taken from him by the pump and pumped into the boiler, so that it can happen that it becomes empty. The one flowing through the flue gas preheater In this case, however, the amount of water alone is not sufficient to feed the boiler, if the water flows through the flue gas preheater only so fast that it is on Point 6, for example, has approximately the boiling point of the boiler. According to the invention is therefore the action of the temperature measuring device located at 6 on the Pump 5 canceled depending on the too low sinking of float 13 in boiler i, as indicated by line 14. As a result, the pump 5 also runs full speed and pumps the required amount of water into the boiler i.

Im Beispiel nach der Abb.2 fördert die Pumpe 15 bei schwachem Dampfbedarf das Speisewasser unmittelbar in den Kessel z, und zwar, wie durch die Linie 16 angedeutet ist, in Abhängigkeit vom Dampfdruck im Dampfnetz 2. Da dieser Druck bei sehr starkem Dampfverbrauch sinkt, arbeitet die Pumpe 15 bei starkem Dampfverbrauch nicht, und es kann daher vorkommen, daß der aus dem Rauchgasvorwärmer 4 gespeiste Warmwasserspeicher 3 leer wird, so daß dann der Wasserstand im Kessel i unter das zulässige Maß sinkt. In diesem Fall wird die Einwirkung der an der Stelle 6 angeordneten Temper aturrneßvorrichtung auf die Pumpe 5 durch den im Warmwasserspeicher angeordneten Schwimmer 13 aufgehoben. Die Abhängigkeit ist durch die Linie 14 angedeutet.In the example according to Fig. 2, the pump 15 delivers when there is a low demand for steam the feed water directly into the boiler z, as indicated by the line 16 is, depending on the steam pressure in the steam network 2. Since this pressure is very strong Steam consumption decreases, the pump 15 does not work when the steam consumption is high, and it can therefore happen that the hot water tank fed from the flue gas preheater 4 3 becomes empty, so that the water level in the boiler i then falls below the permissible level. In this case, the action of the temperature arranged at the point 6 is aturrneßvorrichtung lifted on the pump 5 by the float 13 arranged in the hot water tank. The dependency is indicated by the line 14.

Wenn der Kessel durch die beschriebenen Vorgänge wieder genügend mit Wasser gefüllt ist, könnte es vorkommen, daß der Wasserdurchfluß durch den Vorwärmer infolge des Wiedereinsetzens der Einwirkung der Temperaturme_ßvorrichtung vollkommen unterbunden wird, weil das durchfließende Wasser infolge des vorhergehenden Fehlens der Durchflußregelung in Abhängigkeit von der Wassertemperatur hinter dem Vorwärmer verhältnismäßig kalt ist. Es würde dann statt fließenden Wassers . ruhendes Wasser erwärmt, was zu Wärmestauungen und anderen Mißständen führen könnte. Zur Vermeidung dieser f_Jbelstände kann die Einrichtung so getroffen werden, daß der Wasserdurchfluß durch den Rauchgasvorwärmer nie ganz abgestellt wird. - -When the boiler is sufficiently with again through the processes described Water is filled, it could happen that the water flow through the preheater as a result of the reinsertion of the action of the temperature measuring device completely is prevented because the water flowing through as a result of the previous lack the flow control depending on the water temperature behind the preheater is relatively cold. It would then be held instead of running water. still water heated, which could lead to heat build-up and other abuses. To avoid This f_Jbelstands the device can be made so that the water flow is never completely switched off by the flue gas preheater. - -

Claims (3)

PATENT ANSPRÜcHr: i. Anordnung zur Kesselspeisung, bei der der Wasserdurchfluß durch einen Rauchgasvorwärmer in Abhängigkeit von der Wassertemperatur hinter diesem Vorwärmer selbsttätig geregelt wird, dadurch gekennzeichnet, daß bei ungenügender Förderung die Einwirkung der die Fördermenge in Abhängigkeit von der Temperatur beschränkenden Temperaturmeßvorrichtung in Abhängigkeit vom Wasserverbrauch im Kessel selbsttätig aufgehoben wird. PATENT CLAIM: i. Arrangement for the boiler feed, in which the water flow through a flue gas preheater is automatically regulated as a function of the water temperature behind this preheater, characterized in that in the event of insufficient conveyance, the action of the temperature measuring device which limits the conveyance as a function of the temperature is automatically canceled as a function of the water consumption in the boiler will. 2. Anordnung nach dem Anspruch i, dadurch gekennzeichnet, daß die Einwirkung der Temperaturmeßvorrichtung in Abhängigkeit vom Wasserstand im Kessel aufgehoben wird. 2. Arrangement according to claim i, characterized characterized in that the action of the temperature measuring device as a function is canceled by the water level in the boiler. 3. Anordnung nach dem Anspruch i, dadurch gekennzeichnet, daß die .Einwirkung der Temperaturmeßvorrichtung in Abhängigkeit vom Warmwasserstand in einem Speisewasserspeicher aufgehoben wird.3. Arrangement according to claim i, characterized characterized in that the action of the temperature measuring device as a function is canceled by the hot water level in a feed water storage tank.
DES64135D 1923-10-28 1923-10-28 Arrangement for the boiler feed Expired DE530209C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DES64135D DE530209C (en) 1923-10-28 1923-10-28 Arrangement for the boiler feed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DES64135D DE530209C (en) 1923-10-28 1923-10-28 Arrangement for the boiler feed

Publications (1)

Publication Number Publication Date
DE530209C true DE530209C (en) 1931-07-23

Family

ID=7496929

Family Applications (1)

Application Number Title Priority Date Filing Date
DES64135D Expired DE530209C (en) 1923-10-28 1923-10-28 Arrangement for the boiler feed

Country Status (1)

Country Link
DE (1) DE530209C (en)

Similar Documents

Publication Publication Date Title
DE530209C (en) Arrangement for the boiler feed
AT109784B (en) Arrangement for feeding steam boiler systems.
DE529385C (en) Arrangement for feeding steam boiler systems
DE436777C (en) Steam boiler system with heat storage
DE434282C (en) Device to prevent steam formation in flue gas preheaters
DE518763C (en) Device for feeding steam boiler systems
DE499418C (en) Steam boiler system in which excess steam is precipitated by water and the preheated water is stored
DE510713C (en) Boiler feed system with degassing of the feed water in a mixing preheater
DE429549C (en) Steam boiler system with heat storage
DE426491C (en) Steam boiler system, which is fed to compensate for the load fluctuations in the case of a reduced boiler load, and which in the case of an increased load is reduced
DE445967C (en) Steam boiler system with feed water storage tank and a container arranged between the flue gas preheater and boiler
AT97432B (en) Steam system.
DE593690C (en) Hot water heating system with a circulation pump and with displacement heat storage
DE474544C (en) Procedure to prevent the steam superheater from burning in the event of a fluctuating load in boiler systems operating with overheating
DE565389C (en) Steam system with fluctuating load and compensation through storage
DE422272C (en) High pressure steam power plant using normal boilers
DE670197C (en) High pressure storage system
DE593148C (en) Hot water heating system
DE541983C (en) Method and device for regulating the feed water flow into the intermediate container of boiler systems with a dining room storage tank
DE408050C (en) Process for the operation of steam boiler systems with constant pressure storage
DE412414C (en) Method to compensate for fluctuations in steam consumption
AT130323B (en) Steam power plant with preheating of the feed water by tap or counter-pressure steam.
AT83303B (en) Steam system with heat storage.
AT106817B (en) Boiler system with boiler water storage.
DE719640C (en) Pump hot water heating with displacement storage