DE20218701U1 - Method for securing wire baskets in retaining wall with mesh panels attached to the baskets and buried in the infill behind the baskets - Google Patents

Method for securing wire baskets in retaining wall with mesh panels attached to the baskets and buried in the infill behind the baskets

Info

Publication number
DE20218701U1
DE20218701U1 DE20218701U DE20218701U DE20218701U1 DE 20218701 U1 DE20218701 U1 DE 20218701U1 DE 20218701 U DE20218701 U DE 20218701U DE 20218701 U DE20218701 U DE 20218701U DE 20218701 U1 DE20218701 U1 DE 20218701U1
Authority
DE
Germany
Prior art keywords
grid
wall according
gabion wall
baskets
gabion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
DE20218701U
Other languages
German (de)
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to DE20218701U priority Critical patent/DE20218701U1/en
Publication of DE20218701U1 publication Critical patent/DE20218701U1/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0208Gabions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0241Retaining or protecting walls comprising retention means in the backfill the retention means being reinforced earth elements

Abstract

A method for securely anchoring wire baskets, filled with material, and stacked to form a retaining wall, has mesh panels attached to the baskets and positioned into the infill behind the stacked baskets. The mesh panels are attached as each basket layer is placed in position and covered with the infill. The length of the panels can be selected by clipping several panels together, to span the width of the infill.

Description

Der Beschreibungstext wurde nicht elektronisch erfaßt The description text was not recorded electronically  

Der Beschreibungstext wurde nicht elektronisch erfaßt The description text was not recorded electronically  

Der Beschreibungstext wurde nicht elektronisch erfaßt The description text was not recorded electronically  

Der Beschreibungstext wurde nicht elektronisch erfaßt The description text was not recorded electronically  

Der Beschreibungstext wurde nicht elektronisch erfaßt The description text was not recorded electronically  

Der Beschreibungstext wurde nicht elektronisch erfaßtThe description text was not recorded electronically

Claims (16)

1. Gabionenwand aus mindestens einem Gitterkorb für Füllmateri­ al, wie Natursteine, Kunststeine, Glaskörper oder anderes Füll­ material, mit Seitenwänden und einem Boden, an dem minde­ stens eine in einen Aushubraum ragende Gittermatte befestigt ist, dadurch gekennzeichnet, daß der Gitterkorb (5, 6) mindestens ein zwischen dem Boden (11, 12) und seinem oberen Rand an­ geordnetes Zwischengitter (21, 22) zum Anschluß für wenig­ stens eine weitere Gittermatte (28, 29) aufweist.1. gabion wall from at least one mesh basket for filling material, such as natural stones, artificial stones, vitreous bodies or other filling material, with side walls and a floor to which at least one mesh mat projecting into an excavation space is fastened, characterized in that the mesh basket ( 5 , 6 ) at least one between the bottom ( 11 , 12 ) and its upper edge to arranged intermediate grille ( 21 , 22 ) for connection for least least another grid mat ( 28 , 29 ). 2. Gabionenwand nach Anspruch 1, dadurch gekennzeichnet, daß das Zwischengitter (21, 22) über die dem Aushubraum (2) zugewandte Rückwand (8, 10) des Git­ terkorbes (5, 6) ragt.2. Gabion wall according to claim 1, characterized in that the intermediate grid ( 21 , 22 ) on the excavation space ( 2 ) facing rear wall ( 8 , 10 ) of the lattice basket ( 5 , 6 ) protrudes. 3. Gabionenwand nach Anspruch 1 oder 2, dadurch gekennzeichnet, daß das Zwischengitter (21, 22) mit einem vorderen Rand (26, 26') an einer Frontwand (7, 9) des Gitterkorbes (5, 6) befestigt ist.3. gabion wall according to claim 1 or 2, characterized in that the intermediate grid ( 21 , 22 ) with a front edge ( 26 , 26 ') on a front wall ( 7 , 9 ) of the grid basket ( 5 , 6 ) is attached. 4. Gabionenwand nach einem der Ansprüche 1 bis 3, dadurch gekennzeichnet, daß das Zwischengitter (21, 22) mit seinem vorderen Rand (26, 26') in die Frontwand (7, 9) einge­ hängt ist. 4. gabion wall according to one of claims 1 to 3, characterized in that the intermediate grid ( 21 , 22 ) with its front edge ( 26 , 26 ') in the front wall ( 7 , 9 ) is suspended. 5. Gabionenwand nach einem der Ansprüche 1 bis 4, dadurch gekennzeichnet, daß der vordere Rand (26, 26') des Zwischengitters (21, 22) durch hakenförmig ausgebildete Enden von Gitterstäben (23) gebildet ist.5. Gabion wall according to one of claims 1 to 4, characterized in that the front edge ( 26 , 26 ') of the intermediate grid ( 21 , 22 ) is formed by hook-shaped ends of bars ( 23 ). 6. Gabionenwand nach einem der Ansprüche 1 bis 5, dadurch gekennzeichnet, daß der rückwärtige Rand (25, 25') des Zwischengitters (21, 22) durch schlaufenartig ausgebildete Enden der Gitterstäbe (23) gebildet ist.6. Gabion wall according to one of claims 1 to 5, characterized in that the rear edge ( 25 , 25 ') of the intermediate grid ( 21 , 22 ) is formed by loop-shaped ends of the bars ( 23 ). 7. Gabionenwand nach einem der Ansprüche 1 bis 6, dadurch gekennzeichnet, daß das Zwischengitter (21, 22) mit seinem vorderen Rand (26, 26') in einen Querstab (27) der Frontwand (7, 9) des Gitterkorbes (5, 6) eingehängt ist.7. gabion wall according to one of claims 1 to 6, characterized in that the intermediate grid ( 21 , 22 ) with its front edge ( 26 , 26 ') in a cross bar ( 27 ) of the front wall ( 7 , 9 ) of the mesh basket ( 5 , 6 ) is attached. 8. Gabionenwand nach einem der Ansprüche 1 bis 7, dadurch gekennzeichnet, daß der dem vorderen Rand (26, 26') benachbarte Querstab (24) des Zwischengitters (21, 22) von dem dem rückwärtigen Rand (25, 25') benachbarten Querstab (24) einen Abstand hat, der kleiner ist als die Breite (b) des Git­ terkorbes (5, 6).8. Gabion wall according to one of claims 1 to 7, characterized in that the cross bar ( 24 ) adjacent to the front edge ( 26 , 26 ') of the intermediate grid ( 21 , 22 ) from the cross bar adjacent to the rear edge ( 25 , 25 ') ( 24 ) has a distance which is smaller than the width (b) of the grid basket ( 5 , 6 ). 9. Gabionenwand nach einem der Ansprüche 1 bis 8, dadurch gekennzeichnet, daß die Gittermatte (14 bis 16; 28, 29) an beiden Rändern schlaufenförmig ausgebildete Enden (19, 20) aufweist.9. Gabion wall according to one of claims 1 to 8, characterized in that the grid mat ( 14 to 16 ; 28 , 29 ) has loop-shaped ends ( 19 , 20 ) on both edges. 10. Gabionenwand nach einem der Ansprüche 1 bis 9, dadurch gekennzeichnet, daß die mit den Zwischengittern (21, 22) verbundenen Gittermatten (28, 29) auf gleicher Höhe und fluchtend zu diesen liegen. 10. Gabion wall according to one of claims 1 to 9, characterized in that the grid mats ( 28 , 29 ) connected to the intermediate grids ( 21 , 22 ) are at the same height and in alignment with them. 11. Gabionenwand nach einem der Ansprüche 1 bis 10, dadurch gekennzeichnet, daß das Zwischengitter (21, 22) und die mit ihm verbundene Gittermatte (28, 29) über ein Verbin­ dungsteil miteinander verbunden sind.11. Gabion wall according to one of claims 1 to 10, characterized in that the intermediate grid ( 21 , 22 ) and the grid mat ( 28 , 29 ) connected to it are connected to one another via a connecting part. 12. Gabionenwand nach Anspruch 11, dadurch gekennzeichnet, daß das Verbindungsteil als Stab aus­ gebildet ist, der durch die schlaufenförmigen Enden (20, 20') des Zwischengitters (21, 22) und die mit diesen fluchtenden schlaufenförmigen Enden (25, 25') der Gittermatte (28, 29) ge­ steckt ist.12. Gabion wall according to claim 11, characterized in that the connecting part is formed as a rod, through the loop-shaped ends ( 20 , 20 ') of the intermediate grid ( 21 , 22 ) and the loop-shaped ends ( 25 , 25 ') aligned with them the grid mat ( 28 , 29 ) is inserted ge. 13. Gabionenwand nach Anspruch 11 oder 12, dadurch gekennzeichnet, daß das Verbindungsteil gleich aus­ gebildet ist wie die Verbindungsteile, mit denen die Wände (7 bis 10), und der Boden (11, 12, 13) der Gitterkörbe (5, 6) mit­ einander verbunden sind.13. Gabion wall according to claim 11 or 12, characterized in that the connecting part is formed from the same as the connecting parts with which the walls ( 7 to 10 ), and the bottom ( 11 , 12 , 13 ) of the mesh baskets ( 5 , 6 ) are connected to each other. 14. Gabionenwand nach einem der Ansprüche 1 bis 13, dadurch gekennzeichnet, daß das Zwischengitter (21, 22) aus einander kreuzenden Quer- und Längsdrähten (23, 24) besteht.14. Gabion wall according to one of claims 1 to 13, characterized in that the intermediate grid ( 21 , 22 ) consists of intersecting transverse and longitudinal wires ( 23 , 24 ). 15. Gabionenwand nach einem der Ansprüche 1 bis 14, dadurch gekennzeichnet, daß das Zwischengitter (21, 22) und/oder die Gittermatte (14 bis 16; 28, 29) eine Vielzahl von in Längs- und/oder Querrichtung hintereinander liegenden Gitter­ öffnungen aufweist.15. Gabion wall according to one of claims 1 to 14, characterized in that the intermediate grid ( 21 , 22 ) and / or the grid mat ( 14 to 16 ; 28 , 29 ) a plurality of grid openings lying one behind the other in the longitudinal and / or transverse direction having. 16. Gabionenwand nach Anspruch 15, dadurch gekennzeichnet, daß die Gitteröffnungen des Zwi­ schengitters (21, 22) in Längsrichtung größere Erstreckung ha­ ben als in Querrichtung.16. Gabion wall according to claim 15, characterized in that the lattice openings of the inter mediate lattice ( 21 , 22 ) in the longitudinal direction have greater extension than in the transverse direction.
DE20218701U 2002-11-25 2002-11-25 Method for securing wire baskets in retaining wall with mesh panels attached to the baskets and buried in the infill behind the baskets Expired - Lifetime DE20218701U1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE20218701U DE20218701U1 (en) 2002-11-25 2002-11-25 Method for securing wire baskets in retaining wall with mesh panels attached to the baskets and buried in the infill behind the baskets

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE20218701U DE20218701U1 (en) 2002-11-25 2002-11-25 Method for securing wire baskets in retaining wall with mesh panels attached to the baskets and buried in the infill behind the baskets

Publications (1)

Publication Number Publication Date
DE20218701U1 true DE20218701U1 (en) 2003-02-13

Family

ID=7977569

Family Applications (1)

Application Number Title Priority Date Filing Date
DE20218701U Expired - Lifetime DE20218701U1 (en) 2002-11-25 2002-11-25 Method for securing wire baskets in retaining wall with mesh panels attached to the baskets and buried in the infill behind the baskets

Country Status (1)

Country Link
DE (1) DE20218701U1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1925742A1 (en) 2006-11-24 2008-05-28 Konrad Lehrhuber Wall made of panels and posts limiting a volume to be filled
EP1898005A3 (en) * 2006-09-06 2009-01-28 Johann Stoll Gabion element for constructing supporting walls or similar
DE102012205484A1 (en) * 2012-04-03 2013-10-10 Gesellschaft für geotechnische Systeme Hoy und Nüssler GmbH Embankment structure for use in reinforced soil system, has air-side supporting wall formed from set of gabions, and rear anchorages designed as metal wire lattice, which is connected with gabions by connecting element
DE102013011770A1 (en) * 2013-07-09 2015-01-15 vgs Ingenieure Dr. Köhler & Kirschstein GmbH Support device for supporting soil and reinforced soil with such a support device
EP1712687B1 (en) * 2005-04-11 2016-08-31 Jochen Schüssler Retaining apparatus

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1712687B1 (en) * 2005-04-11 2016-08-31 Jochen Schüssler Retaining apparatus
EP1898005A3 (en) * 2006-09-06 2009-01-28 Johann Stoll Gabion element for constructing supporting walls or similar
EP1925742A1 (en) 2006-11-24 2008-05-28 Konrad Lehrhuber Wall made of panels and posts limiting a volume to be filled
DE102012205484A1 (en) * 2012-04-03 2013-10-10 Gesellschaft für geotechnische Systeme Hoy und Nüssler GmbH Embankment structure for use in reinforced soil system, has air-side supporting wall formed from set of gabions, and rear anchorages designed as metal wire lattice, which is connected with gabions by connecting element
DE102013011770A1 (en) * 2013-07-09 2015-01-15 vgs Ingenieure Dr. Köhler & Kirschstein GmbH Support device for supporting soil and reinforced soil with such a support device

Similar Documents

Publication Publication Date Title
DE50104528C5 (en) gabion
EP2050331A1 (en) Vegetated gabion
DE4208964C3 (en) Steep embankment
DE20112447U1 (en) Holding frame for presenting goods, objects or the like.
EP1426521B1 (en) Facade for walls
DE20218701U1 (en) Method for securing wire baskets in retaining wall with mesh panels attached to the baskets and buried in the infill behind the baskets
EP4192226A1 (en) Greenable wall element
EP2894274B1 (en) Facade cladding gabion
DE202008010662U1 (en) gabion
DE20100569U1 (en) Seating
DE3612506C1 (en) Lagging mat for face support
DE102017100392A1 (en) To build a wall provided gabion and fall protection
DE8326632U1 (en) Lattice set to form an embankment fortification
EP0534346A1 (en) Vegetative soundbarrier, composed of a number of frame parts
EP3767054B1 (en) Gabion-basket structure
DE4409538A1 (en) Device for constructing slopes, preferably in which plants can be grown
DE202012103825U1 (en) Device for fixing a grid mat to a post or a wall
DE3803121A1 (en) Cultivation element
DE202007004127U1 (en) Plantable herb spiral has wall made of mesh spiral with radially inner, outer spirals with radially inner and outer spiral panels, between which space is defined that can be filled with bulk material, anchorage elements at both spiral ends
DE102006041880A1 (en) Stone basket element for erecting retaining walls or the like
DE512590C (en) Braided basket
DE202011052161U1 (en) gabion
DE3618653A1 (en) Plantable noise protection wall
WO2000019023A1 (en) Covering for a sloping surface or a support for a sloping surface and an accompanying structural element
DE1484071B1 (en) Method for fastening a plate-shaped body made of vitreous silicon oxide on a supporting substructure

Legal Events

Date Code Title Description
R207 Utility model specification

Effective date: 20030320

R150 Term of protection extended to 6 years

Effective date: 20060207

R157 Lapse of ip right after 6 years

Effective date: 20090603