CN2850874Y - Super long roof high altitude tile-making tower - Google Patents

Super long roof high altitude tile-making tower Download PDF

Info

Publication number
CN2850874Y
CN2850874Y CN 200520044913 CN200520044913U CN2850874Y CN 2850874 Y CN2850874 Y CN 2850874Y CN 200520044913 CN200520044913 CN 200520044913 CN 200520044913 U CN200520044913 U CN 200520044913U CN 2850874 Y CN2850874 Y CN 2850874Y
Authority
CN
China
Prior art keywords
steel wire
intermediate mesh
mesh framework
tripods
vata
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 200520044913
Other languages
Chinese (zh)
Inventor
石永红
范江民
杨献生
刘大恩
李志芬
李功满
胡东
韩雪英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
Industrial Kiln Engineering Co Ltd Shanghai No5 Metallurgical Construction
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Industrial Kiln Engineering Co Ltd Shanghai No5 Metallurgical Construction filed Critical Industrial Kiln Engineering Co Ltd Shanghai No5 Metallurgical Construction
Priority to CN 200520044913 priority Critical patent/CN2850874Y/en
Application granted granted Critical
Publication of CN2850874Y publication Critical patent/CN2850874Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model discloses a high altitude tile pressing gauntry with an over-long roof, which is composed of a walking chassis, a middle grid framework, two tripods, a steel wire cable, a lapping machine, a tamping machine, etc., wherein the walking chassis is provided with H-shaped steel rails, south wheels, north wheels, east wheels and west wheels; the lapping machine is arranged on the lower part of the middle grid framework; the tamping machine is arranged on the top of the middle grid framework; the two tripods are respectively arranged on the top of the middle grid framework and the top of a steel roof gutter of another roof which is corresponding to the middle grid framework; both ends of the steel wire cable are respectively fixed on the two tripods; the steel wire cable is provided with a plurality of suspended cableway conveying devices. If the utility model is adopted, the vertical transportation, the horizontal transportation, the manufacture and the processing of roof tiles can be integrated into one body.

Description

The high pneumatics Vata of over-long roof frame
Technical field
The utility model relates to the tile press pylon, is specifically related to the high pneumatics Vata of over-long roof frame.
Background technology
Along with the raising that building roof waterproof is required, the hidden roofing tile is extensive use of in industrial construction, also promote simultaneously the flourish of large span factory building, so long yardstick roofing tile just is not designed person's favor and generally selects for use, can only carry out the method for vertical transport traditionally with crane, can not carry out the transportation of over-long roof watt with the method, another kind method is veneer reeling machine to be hung press watt and lay roofing tile on the support with the roof double altitudes again, the transportation of this method colored steel volume must be leaned on crane, not very convenient equally, and the total defectiveness of joint of the roofing tile of laying like this, restrict the development of roofing tile length, also just restricted the development of large span factory building.
Summary of the invention
Technical problem to be solved in the utility model is to overcome the deficiencies in the prior art, provides a kind of and can and make construction equipment--the high pneumatics Vata of the over-long roof frame that processing combines together roofing tile vertical transport and level transportation,
For solving the problems of the technologies described above, the utility model is achieved by the following technical solutions.
The high pneumatics Vata of a kind of over-long roof frame, comprise walking chassis, intermediate mesh framework, a pair of tripod, flexible steel wire, veneer reeling machine and forming press etc., described walking chassis is provided with H shaped steel rail and is provided with the north and south driving wheel and the thing driving wheel, described veneer reeling machine is located at intermediate mesh framework bottom, and described forming press is located at intermediate mesh framework top; Two tripods are located at the steel gutter top that intermediate mesh framework top reaches the another side roofing corresponding with the intermediate mesh framework respectively; Described flexible steel wire two ends are separately fixed on described two tripods, and described flexible steel wire is provided with some suspension type cableway conveyers.
The high pneumatics Vata of above-mentioned over-long roof frame also is provided with lowering or hoisting gear and the two-way transfer of taking turns on the wherein said walking chassis.
The high pneumatics Vata of above-mentioned over-long roof frame, wherein said intermediate mesh framework are twin-well posture body of the tower, and its top is the overhanging type operating platform.
The high pneumatics Vata of above-mentioned over-long roof frame, the suspension type cableway conveyer on the wherein said flexible steel wire is the steel pipe suspension bracket, and the horizontal bottom of this suspension bracket is provided with the rubber sleeve roller, and top is provided with the circular arc wire cableway.
The high pneumatics Vata of this over-long roof of the present utility model frame possesses stability, reliability: adopt twin-well posture body of the tower, the overhanging type operating platform; Possess mobility and turning to property: adopt the rail mounted mobile device, the two-way transfer of taking turns; Possesses height-adjustable performance: adopt trolley type to move up and down device; Possesses the long-distance transportation of over-long roof watt: adopt suspension type cableway conveyer.
Description of drawings
Fig. 1 is a structural representation of the present utility model;
Fig. 2 is a walking chassis structure schematic diagram of the present utility model;
Fig. 3 is tripod of the present utility model and flexible steel wire structural representation;
Fig. 4 is a steel pipe hanger structure schematic diagram of the present utility model.
The specific embodiment
The utility model is described in further detail below in conjunction with drawings and embodiments:
The high pneumatics Vata of over-long roof frame among Fig. 1, Fig. 2, Fig. 3, comprise walking chassis 1, intermediate mesh framework 3, two tripods 51,52, flexible steel wire 6, veneer reeling machine 2 and forming presses 4 etc., described walking chassis 1 is provided with H shaped steel rail 11, promptly constitute by thing track and north and south track, which is provided with north and south driving wheel 12 and thing driving wheel 13, also be provided with lowering or hoisting gear 14 and the two-way transfer 15 of taking turns, wherein lowering or hoisting gear adopts hydraulic method; Intermediate mesh framework 3 is a twin-well posture body of the tower, and its top is the overhanging type operating platform; Described veneer reeling machine 2 is located at intermediate mesh framework 3 bottoms, and described forming press 4 is located at intermediate mesh framework 3 tops; Two tripods 51,52 are located at steel gutter 8 tops that intermediate mesh framework 3 tops reach the another side roofing corresponding with the intermediate mesh framework respectively; Described flexible steel wire 6 two ends are separately fixed on described two tripods 51,52, described flexible steel wire 6 is provided with some suspension type cableway conveyers 7, this device is the steel pipe suspension bracket, the horizontal bottom of this suspension bracket is provided with rubber sleeve roller 71, and top is provided with circular arc wire cableway 72 (see figure 4)s.
When the laying of carrying out large span factory building roof watt, the high pneumatics Vata of over-long roof of the present utility model frame is carried out installation in position according to desired size, on the thing track, operate earlier, when beginning to construct, by veneer reeling machine 2 end of colored steel volume is sent into the forming press 4 at intermediate mesh framework 3 tops earlier, be pressed into required form by forming press 4, and export suspension type cableway conveyer 7 on the flexible steel wire 6 to, suspension type cableway conveyer 7 is the steel pipe suspension bracket, they are evenly arranged on flexible steel wire, the rubber sleeve roller 71 of the bottom that this suspension bracket is horizontal makes the transmission of contour plate 9 level and smooth, but the circular arc wire cableway 72 on top makes contour plate 9 long-distance transportations.When constructing, by jack 3 of mid-level net lattices are pushed up certain altitude earlier, the thing track is extracted out if will commutate, carrying out the track of North and South direction then installs, jack is got back to original position, carries out the constructing operation of south-north direction, and reciprocal operation is got back to east-west direction and carried out the installation of contour plate die mould.

Claims (4)

1, the high pneumatics Vata of a kind of over-long roof frame is made of walking chassis, intermediate mesh framework, two tripods, flexible steel wire, veneer reeling machine and forming presses etc., it is characterized in that described walking chassis is provided with H shaped steel rail and is provided with the north and south driving wheel and the thing driving wheel; Described veneer reeling machine is located at intermediate mesh framework bottom, and described forming press is located at intermediate mesh framework top; Two tripods are located at the steel gutter top that intermediate mesh framework top reaches the another side roofing corresponding with the intermediate mesh framework respectively; Described flexible steel wire two ends are separately fixed on described two tripods, and described flexible steel wire is provided with some suspension type cableway conveyers.
2, the high pneumatics Vata of over-long roof according to claim 1 frame is characterized in that, also is provided with lowering or hoisting gear and the two-way transfer of taking turns on the described walking chassis.
3, the high pneumatics Vata of over-long roof according to claim 1 frame is characterized in that, described intermediate mesh framework is a twin-well posture body of the tower, and its top is the overhanging type operating platform.
4, the high pneumatics Vata of over-long roof according to claim 1 frame is characterized in that, the suspension type cableway conveyer on the described flexible steel wire is the steel pipe suspension bracket, and the horizontal bottom of this suspension bracket is provided with the rubber sleeve roller, and top is provided with the circular arc wire cableway.
CN 200520044913 2005-09-09 2005-09-09 Super long roof high altitude tile-making tower Expired - Lifetime CN2850874Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200520044913 CN2850874Y (en) 2005-09-09 2005-09-09 Super long roof high altitude tile-making tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200520044913 CN2850874Y (en) 2005-09-09 2005-09-09 Super long roof high altitude tile-making tower

Publications (1)

Publication Number Publication Date
CN2850874Y true CN2850874Y (en) 2006-12-27

Family

ID=37584841

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200520044913 Expired - Lifetime CN2850874Y (en) 2005-09-09 2005-09-09 Super long roof high altitude tile-making tower

Country Status (1)

Country Link
CN (1) CN2850874Y (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102912948A (en) * 2012-11-05 2013-02-06 天门双菱百变钢构有限责任公司 Color steel tile station adapting conveyor
CN103233559A (en) * 2013-01-04 2013-08-07 森特士兴集团股份有限公司 System and method for transporting roof board in air
CN104763109A (en) * 2015-04-13 2015-07-08 中冶建工集团有限公司 Quick construction method for pressed bottom tile of large-span steel structure factory building roof
CN105442761A (en) * 2014-09-29 2016-03-30 上海宝钢工业技术服务有限公司 Wind resistant rack of roofing color steel plate
CN106193476A (en) * 2015-05-05 2016-12-07 五冶集团上海有限公司 A kind of concealed roofing tile mounting platform

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102912948A (en) * 2012-11-05 2013-02-06 天门双菱百变钢构有限责任公司 Color steel tile station adapting conveyor
CN102912948B (en) * 2012-11-05 2017-03-29 天门双菱百变钢构有限责任公司 Color steel tile station is adapted to conveyer
CN103233559A (en) * 2013-01-04 2013-08-07 森特士兴集团股份有限公司 System and method for transporting roof board in air
CN103233559B (en) * 2013-01-04 2015-11-18 森特士兴集团股份有限公司 A kind of roof panel high-altitude transmission system and method
CN105442761A (en) * 2014-09-29 2016-03-30 上海宝钢工业技术服务有限公司 Wind resistant rack of roofing color steel plate
CN104763109A (en) * 2015-04-13 2015-07-08 中冶建工集团有限公司 Quick construction method for pressed bottom tile of large-span steel structure factory building roof
CN104763109B (en) * 2015-04-13 2017-01-25 中冶建工集团有限公司 Quick construction method for pressed bottom tile of large-span steel structure factory building roof
CN106193476A (en) * 2015-05-05 2016-12-07 五冶集团上海有限公司 A kind of concealed roofing tile mounting platform

Similar Documents

Publication Publication Date Title
CN2850874Y (en) Super long roof high altitude tile-making tower
CN103216109B (en) Construction method of track gauge variation block slippage of long span spatial composite roof truss
CN201010842Y (en) Tyre type span-variable multifunctional rail laying machine
CN110510527A (en) A kind of installation system and its construction method of high slope variable cross-section side slope prefabricated section
CN203213623U (en) Slide guiding and rectifying device
CN201666012U (en) Lift-type movable work shed
CN206144559U (en) Portable mining lifting support that fixes
CN210177913U (en) Slidable wall color plate mounting device
CN209603182U (en) A kind of adjustable die system of pipe gallery automatic control section
CN202400794U (en) Folding type movable lifter
CN208684247U (en) A kind of prefabricated subsection hanging apparatus
CN205934730U (en) Installation device of wave form steel web
CN201809856U (en) Double-layered movable steel frame ceiling
CN210887594U (en) Motorized modular building structure
CN201276408Y (en) Precast beam mobile device
CN212403204U (en) Building construction lifting device
CN1120274C (en) Pile pressing machine
CN206545219U (en) Airport roof photovoltaic bracket basis and airport roof photovoltaic support structure
CN206256382U (en) It is a kind of to suspend purlin car in midair for the triangle that Wavelike steel webplate is installed
CN201678395U (en) Movable elevator
CN213679518U (en) Asynchronous cradle with gantry crane
CN203637830U (en) Large-tonnage transporting trolley capable of converting load distribution
CN2863975Y (en) Automatic plastering machine
CN214081933U (en) Bamboo winding piping lane stripper
CN204620761U (en) Muffler bend molding apparatus

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: MCC5 GROUP CORPORATION LIMITED (SHANGHAI)

Free format text: FORMER OWNER: INDUSTRIAL KILN ENGINEERING CO., LTD., SHANGHAI NO.5 METALLURGICAL CONSTRUCTION

Effective date: 20110609

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 201900 NO. 5, KEDONG ROAD, GUOYUAN, BAOSHAN DISTRICT, SHANGHAI TO: 201900 NO. 2501, TIELI ROAD, BAOSHAN DISTRICT, SHANGHAI

TR01 Transfer of patent right

Effective date of registration: 20110609

Address after: 201900 Shanghai city Baoshan District Tieli Road No. 2501

Patentee after: MCC5 Group Corporation Limited (Shanghai)

Address before: 201900, No. 5, G East Road, orchard, Shanghai, Baoshan District

Patentee before: Industrial Kiln Engineering Co., Ltd., Shanghai No.5 Metallurgical Construction

CX01 Expiry of patent term

Expiration termination date: 20150909

Granted publication date: 20061227

EXPY Termination of patent right or utility model