CN2391932Y CN 99226950 CN99226950U CN2391932Y CN 2391932 Y CN2391932 Y CN 2391932Y CN 99226950 CN99226950 CN 99226950 CN 99226950 U CN99226950 U CN 99226950U CN 2391932 Y CN2391932 Y CN 2391932Y
Authority
CN
China
Prior art keywords
steel
ring
holding board
shaped
shaped holding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 99226950
Other languages
Chinese (zh)
Inventor
王志林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 99226950 priority Critical patent/CN2391932Y/en
Application granted granted Critical
Publication of CN2391932Y publication Critical patent/CN2391932Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model relates to a steel framework structure for a steel pipe concrete building, which comprises steel pipe concrete, steel supports and a U-shaped steel beam. The steel supports form annular steel supports and are sheathed and welded on the steel pipe concrete; each of the annular steel supports is composed of an upper annular column holder plate, a lower annular column holder plate, and four to eight connection plates; the U-shaped steel beam is respectively connected with the corresponding extending parts of the connecting plate, the upper annular column holder plate and the lower annular column holder plate which are arranged on the annular steel supports. The steel-frame structure of a whole building can be obtained by combining the annular steel supports of a plurality of standard structures. The utility model is suitable for mass production and favorable to the improvement of construction quality and shock resistance.

Description

A kind of steel frame construction of steel pipe concrete building construction
The utility model relates to a kind of steel pipe concrete building construction, refers in particular to the steel frame construction of this building construction.In the building trade, adopt the steel pipe concrete of fluid concrete and the combining structure of girder steel increasingly extensively, generally all be boring or fluting on steel pipe concrete, girder steel and steel pipe concrete linked together, perhaps girder steel is directly passed steel pipe by rod iron in patchhole or the groove or steel plate; Both require the steel pipe concrete that adopts diameter bigger, not only cause the increase of housing cost, and can weaken the intensity of steel pipe concrete, reduce whole house, building quality.
The purpose of this utility model is intended to overcome the deficiency of above-mentioned prior art, provides a kind of construction, fitting operation simple, house intensity height, and shock resistance is good, its component standardization, the steel pipe concrete building construction member that is suitable for producing in enormous quantities.
For achieving the above object, the steel supporting structure of the steel pipe concrete building construction that the utility model provides, comprise fluid concrete a plurality of steel pipe concrete, can be welded on the steel bracket on the steel pipe concrete and the U font girder steel that can be fixed between steel bracket is formed, steel bracket between steel pipe concrete and U font girder steel is a ring-shaped steel bracket, and cover is welded on the steel pipe concrete, and ring-shaped steel bracket is made up of upper ring-shaped holding board, 4~8 junction plates and lower ring-shaped holding board; One end of described U font girder steel and the corresponding extension of junction plate, upper ring-shaped holding board and lower ring-shaped holding board on the ring-shaped steel bracket are fixed together.
According to the utility model, be positioned at the ring-shaped steel bracket on the steel pipe concrete of whole building building corner part, can be by 4 junction plates, a upper ring-shaped holding board and lower ring-shaped holding board (see figure 1) that is spliced.
According to the utility model, be positioned at the ring-shaped steel bracket on the steel pipe concrete of whole building building peripheral part, can be by 6 junction plates, a upper ring-shaped holding board and lower ring-shaped holding board (see figure 3) that is spliced.
According to the utility model, be positioned at the ring-shaped steel bracket on the steel pipe concrete of whole building building mid portion, can be by 8 junction plates, a upper ring-shaped holding board and lower ring-shaped holding board (see figure 5) that is spliced.
According to the utility model, the affixed mode that constitutes described ring-shaped steel bracket and U font girder steel can adopt: the extension end face of the outer face of the junction plate of each ring-shaped steel bracket and upper ring-shaped holding board, and dock with the end face of U font girder steel, the extension of lower ring-shaped holding board exceeds the outer face of upper ring-shaped holding board and junction plate, with the end overlap joint of described U font girder steel bottom surface.
According to the utility model, the ring-shaped steel bracket of several typical constructions is applicable to whole building building different parts respectively, as long as it is made up, just can obtain the complete steel structure member of whole building building.Owing to need on steel pipe concrete, hole or operation such as fluting, help improving the structural strength that whole building is built.
Below in conjunction with several embodiment shown in the drawings, describe the utility model in detail, wherein:
Fig. 1 is a phantom drawing, illustrates a kind of embodiment of the ring-shaped steel bracket on the steel pipe concrete that is positioned at whole building building corner part;
Fig. 2 is a vertical view embodiment illustrated in fig. 1;
Fig. 3 is a phantom drawing, illustrates a kind of embodiment of the ring-shaped steel bracket on the steel pipe concrete that is positioned at whole building building peripheral part;
Fig. 4 is a vertical view embodiment illustrated in fig. 3;
Fig. 5 is a phantom drawing, illustrates a kind of embodiment of the ring-shaped steel bracket on the steel pipe concrete that is positioned at whole building building mid portion;
Fig. 6 is a vertical view embodiment illustrated in fig. 5;
Fig. 7 is a phantom drawing, illustrates the exploded view that a ring-shaped steel bracket is connected with U font girder steel.
Referring to Fig. 1, this figure illustrates the phantom drawing of a kind of embodiment of the ring-shaped steel bracket on the steel pipe concrete that is positioned at whole building building corner part, and Fig. 2 illustrates the vertical view of ring-shaped steel bracket embodiment.This ring-shaped steel bracket by upper ring-shaped holding board 3a that be arranged in parallel and lower ring-shaped holding board 3c and radially be vertically set on upper ring-shaped holding board 3a and lower ring-shaped holding board 3c between 4 junction plate 3b form (referring to Fig. 7), and cover is welded on the steel pipe concrete and is welded into one.One end of U font girder steel is fixed together with the extension end of the extension of the upper ring-shaped holding board 3a of ring-shaped steel bracket 3, two junction plate 3b and lower ring-shaped holding board 3c respectively.Its connected mode can be: the outer face of each junction plate 3b of ring-shaped steel bracket 3 is concordant with corresponding upper ring-shaped holding board 3a extension, both ends of the surface respectively with the end face of U font girder steel to welded together, the extension of its lower ring-shaped holding board 3c exceeds the outer face of two junction plate 3b, the bottom surface of U font girder steel is overlapped on the extension of lower ring-shaped holding board 3c, and with lap-joint's edge joint weld together.For the ease of assembling with strengthen bonding strength, can also a plurality of through holes be set at both clinchs, the overlap joint back is fixed together both with a plurality of bolt 5; Can also add one to two auxiliary stiffener 6 at upper ring-shaped holding board 3a and above U font girder steel one end, make whole steel frame construction more firm.
Fig. 3 is a phantom drawing, illustrate a kind of embodiment of the ring-shaped steel bracket on the steel pipe concrete that is positioned at whole building building peripheral part, Fig. 4 is the vertical view of this embodiment, this ring-shaped steel bracket by upper ring-shaped holding board 3a that be arranged in parallel and lower ring-shaped holding board 3c and radially be vertically set on upper ring-shaped holding board 3a and lower ring-shaped holding board 3c between 6 junction plate 3b form.Identical with the method for attachment of Fig. 1.
Fig. 5 is a phantom drawing, illustrates a kind of embodiment of the ring-shaped steel bracket on the steel pipe concrete that is positioned at whole building building mid portion, and Fig. 6 is the vertical view of this embodiment.This ring-shaped steel bracket is spliced by 8 identical junction plate 3b and upper ring-shaped holding board 3a, a lower ring-shaped holding board 3c, and its connected mode is identical with Fig. 1, Fig. 3.
Above-mentioned several embodiment is only for the usefulness that the utility model is described; and be not to be to restriction of the present utility model; the those of ordinary skill in relevant technologies field; under the situation that does not break away from spirit and scope of the present utility model; can also make various variations and modification; for example set up reinforcing rib etc. on each ring-shaped steel bracket, all technical schemes that are equal to also should belong to category of the present utility model, and scope of patent protection of the present utility model should be limited by each claim.

Claims (2)

1. the steel frame construction of a steel pipe concrete building construction, a plurality of steel pipe concrete by fluid concrete, the U font girder steel that can be welded on the steel bracket on the steel pipe concrete and can be fixed between steel bracket is formed, it is characterized in that: steel bracket is a ring-shaped steel bracket, and cover is welded on the steel pipe concrete, ring-shaped steel bracket is by upper ring-shaped holding board that be arranged in parallel and lower ring-shaped holding board, and 4~8 junction plates that radially are vertically set between upper ring-shaped holding board and the lower ring-shaped holding board form, an end of described U font girder steel respectively with ring-shaped steel bracket on junction plate, the corresponding extension of upper ring-shaped holding board and lower ring-shaped holding board is fixed together.
2. the steel frame construction of steel pipe concrete building construction according to claim 1, it is characterized in that: the lower ring-shaped holding board of described ring-shaped steel bracket stretches out in the end face of described upper ring-shaped holding board and described junction plate, one end of described lower ring-shaped holding board and described U font girder steel bottom surface is overlapping, and affixed by bolt or welding manner.
CN 99226950 1999-06-14 1999-06-14 Steel framework structure for steel pipe and concrete building Expired - Fee Related CN2391932Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 99226950 CN2391932Y (en) 1999-06-14 1999-06-14 Steel framework structure for steel pipe and concrete building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 99226950 CN2391932Y (en) 1999-06-14 1999-06-14 Steel framework structure for steel pipe and concrete building

Publications (1)

Publication Number Publication Date
CN2391932Y true CN2391932Y (en) 2000-08-16

Family

ID=34016561

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 99226950 Expired - Fee Related CN2391932Y (en) 1999-06-14 1999-06-14 Steel framework structure for steel pipe and concrete building

Country Status (1)

Country Link
CN (1) CN2391932Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103216722A (en) * 2013-04-08 2013-07-24 常熟建工建设集团有限公司苏州分公司 Novel universal change-over tube
CN113529943A (en) * 2021-07-21 2021-10-22 上海建工一建集团有限公司 Concrete support and lattice column connecting device and method convenient to dismantle

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103216722A (en) * 2013-04-08 2013-07-24 常熟建工建设集团有限公司苏州分公司 Novel universal change-over tube
CN113529943A (en) * 2021-07-21 2021-10-22 上海建工一建集团有限公司 Concrete support and lattice column connecting device and method convenient to dismantle

Similar Documents

Publication Publication Date Title
CN208586762U (en) Flashlight cartridge type integration assembling type steel structure column beam contact composite structure
CN2391933Y (en) Steel joint for steel structure building
US6601350B1 (en) Structure for installing a viscous vibration-damping wall and method of installing the same
CN2391932Y (en) Steel framework structure for steel pipe and concrete building
CN215976813U (en) H-shaped steel structure for bridge
CN213897534U (en) Prefabricated module connector and modular building
CN2382769Y (en) Building member of steel struture room
CN212984189U (en) Steel structure beam column connecting structure
CN2391931Y (en) Steel frame-work struture for steel pipe and concrete building
CN212926494U (en) Full-assembly type steel structure node suitable for beam column is H shaped steel
CN2700427Y (en) Perforated diaphragm plate type round column beam connection node structure
CN2345610Y (en) Prefabricated light steel truss structure
CN2360473Y (en) Steel frame structure of outer wall coner pole for steel structure building
CN2438761Y (en) Vertical column and transverse beam butt-joint structure
CN211007018U (en) Steel construction arc turning of area support
CN214657731U (en) Novel steel structure support connection structure
CN216865510U (en) Connecting assembly for house main beam and steel column
CN214364062U (en) Steel construction factory building
CN218060696U (en) Assembled steel construction foundation frame
CN2360474Y (en) Steel frame structure of steel structure building
CN211774558U (en) H-shaped steel column splicing device assembly
CN219080613U (en) Connecting node structure of steel pipe column and steel pipe beam
CN212104822U (en) Construction steel bar joint connection structure
JPS62268441A (en) Connector of steel pillar
CN217870013U (en) Assembled steel support connection component

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C53 Correction of patent for invention or patent application
COR Change of bibliographic data

Free format text: CORRECT: PATENTEE ADDRESS; FROM: ROOM 203, NO. 2, LANE 8, QUFU ROAD(WEST), ZHABEI DISTRICT, SHANGHAI CITY TO: SHANGHAI CITY, ZHABEI DISTRICT, NO.143 QUFU WEST ROAD

CP02 Change in the address of a patent holder

Address after: No. 143 West Qufu Road, Shanghai, Zhabei District

Patentee after: Wang Zhilin

Address before: Room 2, No. 8, Lane 203, West Qufu Road, Shanghai, Zhabei District

Patentee before: Wang Zhilin

C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee