CN2389292Y - Electricity generating apparatus composed of butt joined refuse incinerator and old generating equipment - Google Patents

Electricity generating apparatus composed of butt joined refuse incinerator and old generating equipment Download PDF

Info

Publication number
CN2389292Y
CN2389292Y CN99248360U CN99248360U CN2389292Y CN 2389292 Y CN2389292 Y CN 2389292Y CN 99248360 U CN99248360 U CN 99248360U CN 99248360 U CN99248360 U CN 99248360U CN 2389292 Y CN2389292 Y CN 2389292Y
Authority
CN
China
Prior art keywords
boiler
power generation
old
garbage
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN99248360U
Other languages
Chinese (zh)
Inventor
高卫东
黄享华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN99248360U priority Critical patent/CN2389292Y/en
Application granted granted Critical
Publication of CN2389292Y publication Critical patent/CN2389292Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E20/00Combustion technologies with mitigation potential
    • Y02E20/12Heat utilisation in combustion or incineration of waste

Abstract

The utility model relates to an electricity generating device composed of the butting of a refuse incineration boiler and an old electricity generating device, which is mainly provided with a boiler, a steam turbine and a plurality of auxiliary devices; the utility model is also provided with a refuse incinerator; the incinerator is integrally connected with the boiler, forming the refuse incineration boiler, the refuse incineration boiler can replace a coal burning boiler of the old electricity generating device and be connected with the steam turbine arranged at the back of the boiler through a pipeline. The electricity generating device can utilize the refuse incineration boiler for replacing the original coal burning boiler on the basis of most of obsolete original devices in a small thermal power plant; because heat energy generated by the incineration of refuse is utilized for generating electricity, an original small thermal power plant can continuously work, and the investment for incinerating refuse is reduced; the utility model is suitable for power plants with at most fifty thousand KW.

Description

Power generation device with butt joint of waste incineration boiler and old power generation equipment
The utility model relates to a power generation facility, especially one kind with the coal fired boiler who eliminates the disuse in the old power plant demolish the back, have waste incinerator's boiler in the installation to carry out the device that generates electricity after docking with the steam turbine.
With the increase of population, economic development, industrial development and more factories, the living standard of people is increasingly improved and living consumer goods are increased. Domestic garbage and industrial garbage are increasing day by day. About 100 million tons of various industrial and domestic wastes are generated globally every year. By 1998, various types of garbage in China reach 12-15 hundred million tons, wherein the urban garbage is about 3 hundred million tons, and the collection and transportation amount reaches about 1.3 hundred million tons. The garbage becomes a huge pollution source on the earth, and the dumping and stacking of the garbage pollute the environment.
However, as the components of the domestic garbage are complex and are limited by factors such as social development, economic and technical levels, natural geographic conditions, domestic energy structures, traditional habits and the like, the domestic garbage treatment of various countries generally varies with the national conditions, and different treatment methods can be adopted in various regions in the same country, so that a unified mode is difficult to exist.
The steam and power generation by urban garbage incineration has been used for hundreds of years abroad, and the first solid waste power generation plant is built in German hamburger in 1895. The largest waste incineration power plant in the world today is the Munich power plant in Germany, with a scale of 125 MW. Incineration treatment is one of the important means for harmlesstreatment of household garbage, and compared with landfill and compost treatment, the incineration treatment has the following characteristics: the method has the advantages of mature treatment technology, small occupied area, easy selection of fields, short treatment time, remarkable reduction, thorough harmlessness, capability of recovering waste heat from waste incineration and the like, and is widely applied in developed countries;
the power generation and three-waste treatment processes of various garbage power generation processes are basically the same and different, and mainly comprise three types:
a full-scale incineration device (usually the incineration treatment capacity is 250-&lt3000T/&gt) for incinerating the mixed garbage; and the other type of Refuse Derived Fuel (RDF) is prepared by sorting the mixed refuse and preparing the Refuse Derived Fuel (RDF) with a certain size specification, wherein the prepared RDF has better uniformity than the mixed refuse and can be mixed and combusted with other fuels such as coal, wood chips and the like. Modular incinerators are typically manufactured at the manufacturing plant and installed on site in a modular manner, and these types of incinerators are relatively low throughput (10-300T/day). In addition, less treatment processes such as fluidized bed incinerators, pyrolysis, etc. are used.
Technological process chart of garbage power generation by incineration method
Figure Y9924836000051
The attached table 1 shows the statistics of investment and operation cost of the United states refuse burning plant. Attached table 1: statistics of investment and operating costs of U.S. waste incineration plants
Incinerator Type (B) Waste heat benefit Use method Formula (II) Investment per unit treatment (ten thousand dollars/ton @ Day) Operating costs (USD @ Ton) Backup note
Full-volume incinerator Burning device Power generation 3-21, average 10.6 9-48, ping Are all 26.5 Statistical data of 68 plants, size 750-3000 tons/day), 1991 Price
Generating electricity and supply of steam Lower than the single power generation 20-30% And hair alone Electric equivalent Statistical data of 20 plants, size 750-3000 tons/day), 1991 Price
Combined type Incineration device Device for placing Generating electricity and supply of steam Average 9.5 21-42 ping Are all 32 11 triple statistics, average size 243 ton/day, 1991 price
Supply of steam Mean ratio of single hair The electricity is reduced by about 20 percent And hair alone Electric equivalent 34 plant statistics, 1991 Price
Garbage can Raw fuel 7.5-10.2, ping Are all 9.8 13-67, Ping All 36 are Statistical data of 15 plants, 1991 And (4) the price.
The current various types of garbage power generation methods in the world mainly differ in the hearth structure and the combustion action mode adopted in the incineration process. The main categories of applications are among others: a roller grate arrangement of dusaltov; a muffle furnace (reciprocating grate); a fluidized bed; a rotary kiln; multi-chamber incinerators, and the like.
For China, a newly built garbage power plant has large construction investment and high requirements on management and treatment technical levels, is an important factor for restricting wide application of China, and creates conditions for further development of garbage incineration treatment along with economic development and domestic incineration technical progress of China. In large and medium cities, the incineration demand of household garbage is gradually increased, particularly in eastern coastal areas with developed economy, the population is large, the arable land area is small, the population distribution is relatively concentrated, land resources are precious, the urban gas popularization rate is increased, garbage is classified and collected in different regions, and the proportion of the household garbage suitable for incineration treatment is gradually increased.
At present, the investment of incineration treatment equipment for introducing recycled energy in China is about 40-70 ten thousand yuan/ton/day, the investment is too large, the economic bearing capacity of most cities is exceeded, and the incineration treatment equipment can only be built by using foreign preferential loans. In order to further develop the waste incineration treatment, the domestic technology and equipment need to be developed and utilized to reduce the unit treatment investment. If the unit treatment investment is reduced to 10-25 ten thousand yuan/ton/day, the method is suitable for the economic development level of most cities in China at present and can start the development and development of the household garbage incineration treatment market.
The attached table II shows the scale and investment schedule of garbage disposal plants in recent years
And B, attaching a table II: chinese recent garbage disposal plant scale and investment schedule
Location of a site Build up Time of day Scale of Fund coming Source Total investment (all ten thousand) Element) Total cost of Remarks for note
1. Shenzhen waste incineration Plant (S.A.) 1998 2×150 Ton/day Domestic 4700 Running cost 23 yuan/ton (1990) Measuring and calculating) Day of introduction The equipment
1996 1×150 Ton/day Domestic Part of the country Productive chemical
2. Waste of northern sea of Guangxi Incineration plant 1×150 Ton/day By using an accelerator Administration of Canada Loan in house About 6600 About 130 Yuan- Ton of Under construction
3. Mansion door refuse incineration Plant (S.A.) 400 ton/ml Day(s) Method of use National government Loan Earlier stage worker Making
4. Shanghai Pudong garbage Incineration plant About 1000 Ton/day Method of use National government Loan About 7.0 Hundred million (hundred million) About 150 Yuan- Ton of Under construction
5. Shanghai Pumi West refuse Incineration plant About 1000 Ton/day Using west Executive's political affairs Loan in house About 7.0 Hundred million (hundred million) About 150 Yuan- Ton of Under construction
6. High in Beijing Chaoyang district Antun refuse incineration plant About 1000 Ton/day Using west Executive's political affairs Loan in house About 7.0 Hundred million (hundred million) About 150 Yuan- Ton of Earlier stage worker Making
7. Guangzhou city refuse incinerator Combustion power plant 900 ton- Day(s) 5-7 hundred million Earlier stage worker Making
8. Tunica city of Beijing Refuse incineration plant About 1000 Ton/day About 7.0 Hundred million (hundred million) Plan for
9. Ningbo city refuse incinerator Burning plant About 1000 Ton/day Domestic About 3.5 Hundred million (hundred million) Earlier stage worker Making
10. Shenzhen dragon sentry garbage Incineration plant 300 ton/ml Day(s) Under construction
In addition, the refuse incineration plants in more than 20 cities, such as Guangdong Zhuhai, Shunde, Jiangsu Changzhou, Yixing, Xiangyang, Liaoning Panjin, Beijing Changping, Fujian Zhangzhou, Sichuan and the like, are built and established, wherein the differences of investment scale, technical types and treatment effects are large, and detailed statistics is not carried out.
At present,some small coal-fired power plants in China still run continuously, and the total amount of units below 5 thousands KW (including 5 thousands KW) in the whole country is about 3000 thousands KW through preliminary statistics, and the small units are incompatible with the large trend of the development of the current coal-fired power plants to large-capacity and high-parameter units, and face the result of production halt. The small power plant mainly has the following defects:
① use original fossil fuel (coal and oil, natural gas) as main fuel, and has carbon dioxide pollution to air space, and the fuel is non-renewable resource.
② the coal consumption rate is high, the economy is poor, and the precious non-renewable energy of the country is wasted.
③, low automation level, incomplete automatic protection device, low safety, and high maintenance and overhaul cost.
④ because of the imperfect waste gas treatment, the pollution discharge is often out of standard, which seriously affects the surrounding environment and does not meet the requirement of environmental protection.
After the small unit power plants are eliminated, the equipment cannot be reused, so that a great deal of domestic assets are wasted, and personnel arrangement becomes a big problem of local government headache.
To sum up, ① due to ecological reasons, the treatment of civil and commercial garbage and similar industrial and commercial garbage cannot be continued in a conventional manner, the capacity of the existing garbage collection and distribution sites is saturated quickly, the new establishment of large-scale garbage collection and distribution sites is difficult to accept due to the requirement of environmental protection, ② is oriented to the transition of garbage treatment modes beneficial to ecological protection, and the actual economic capability cannot be considered, the investment of the project for burning garbage introduced in China is too large to exceed the economic bearing capacity of most cities, so that the local government bears heavy burden, ③ is considered from both economic and environmental aspects, the existing small power plants must be eliminated, 5 thousands KW and the following conventional coal (fuel) fired units are basically shut down before 2003, and the small thermal power units in the acid rain control area and the sulfur dioxide pollution control area must burn fuel with the sulfur content of less than 1% or adopt other measures for reducing the emission of sulfur dioxide before shutting down.
The utility model aims to provide a: the utility model provides a power generation facility by butt joint of msw incineration boiler and old power generation facility, make it can utilize msw incineration to generate electricity, reduce the unit investment of msw incineration factory, can make the little thermal power plant who is eliminated simultaneously carry out the transformation of a small amount of equipment on the basis of most existing equipment to utilize the heat energy of msw incineration to generate electricity again, coil the small power plant.
Realize the utility model discloses the technical scheme of purpose as follows: a power generation equipment is composed of boiler, steam turbine and several auxiliary units, and features that the garbage incinerator is connected to boiler to form a garbage incinerating boiler, which is used to replace the coal-burning boiler in old power generation equipment and is connected via pipeline to steam turbine installed behind boiler. The utility model discloses still have the interfacing apparatus of the various equipment that remain in boiler and the old power plant among the power generation facility.
By adopting the technical scheme, the waste incineration boiler is used for replacing the original coal-fired boiler and is in butt joint with the water inlet equipment, the steam turbine, the flue gas treatment equipment and the automation equipment of the original power plant, so that most of equipment of the original power plant can be applied, personnel of the original power plant are partially arranged, the waste is treated by the waste incineration boiler, the generated heat is transferred to water to generate steam, the steam is converted into heat energy or electricity through the turbine for use, the waste is utilized, the investment of a waste incineration unit is reduced, the power generation is carried out again through the eliminated small power plant, and the small thermal power plant is activated.
The technical scheme of the utility model, compromise the requirement in ecology and economics two sides, both considered the economic strength in the present most cities of china, complied with ever-changing social condition again. The advanced technology meets the urgent need of the current society and does not need huge investment. The system is almost suitable for all small power plants with the power of less than 5 thousands KW (including 5 thousands KW), and the waste incineration boiler replaces a coal-fired boiler to generate steam, so that the small coal-fired (oil-fired) power plant with low efficiency and high pollution becomes a low-pollution environment-friendly power plant. The important point to be explained here is that the investment for applying this technology is 50% to 60% of the investment of a waste incineration plant with considerable treatment capacity, and the construction period is shortened by half.
The present invention will be further explained with reference to the drawings and the embodiments.
Description of the drawings:
FIG. 1 is a schematic structural diagram of a power generation device according to an embodiment of the present invention
FIG. 2 is a schematic view of the operation process of the present invention
FIG. 3 is a schematic view of a power plant equipped with the power generation device of the present invention
FIG. 4 is a schematic view of the garbage incinerator of the present invention
In the figure: 1. a boiler; 2. a superheater; 3. a coal economizer; 4. a bag-type dust collector; 5. a main steam line; 6. a condenser; 7. a steam turbine; 8. a high pressure regenerative heater; 9. a drain cooler; 10. a deaerator; 11. a low pressure heater; 12. a generator; 13. a roller bottom grate; 14. a parallel flow hearth; 15. a primary air port for combustion air; 16. a secondary air port for combustion air; 17. a post-combustion zone; 18. a garbage incinerator.
Example (b):
fig. 1 shows the structure schematic diagram of an embodiment of the power generation device of the present invention, in this embodiment, the power generation device includes a boiler 1, a main steam pipeline 5, a steam turbine 7, a condenser 6 and a bag-type dust collector 4. The boiler 1 and the steam turbine 7 are connected by a main steam pipeline 5. The boiler 1 further comprises a waste incinerator 18, a superheater 2 and an economizer 3. The waste incinerator 18 is integrated with the boiler 1 to form a waste incineration boiler. The condenser 6 is connected with the steam turbine 7 and the garbage incinerator 18 is connected with the bag-type dust collector 4 through pipelines.
The whole operation flow of the power plant with the power generation device of the utility model is shown in figure 2. The specific situation can be properly deviated according to the actual site and the assembly plan, and the part in the broken line frame of the power plant after modification is the same as that of the old power plant and can be fully utilized. The reconstruction part mainly comprises a garbage collecting and distributing center, a feeding device, a garbage incineration boiler and part of treatment equipment.
The equipment of the power plant with the power generation device of the utility model is shown in figure 3. The system mainly comprises a boiler 1, a high-pressure regenerative heater 8, a drain cooler 9, a deaerator 10, a low-pressure heater 11, a condenser 6 and a steam turbine 7. The devices are connected through pipelines. In the power plant there is also a generator 12, which is coupled to the steam turbine 7 by a coupling.
Fig. 4 shows the structure of the garbage incinerator of the present invention, which mainly comprises a roller bottom grate 13, a parallel flow furnace chamber 14, an air primary air port 15 and a secondary air port 16. In operation, garbage is fed to the roller bottom grate 13 through the feeding hopper, air is supplied through the primary air port 15 and the secondary air port 16 in sequence, the garbage is combusted in the parallel flow hearth 14, unburned gas is continuously combusted in the post-combustion zone 17, and flue gas enters a flue.
The utility model discloses still have the butt joint of the various equipment and the device that the boiler remained in the device and the old power plant, now with the utility model discloses the butt joint of technique and 5 ten thousand KW thermal power plant's former equipment is illustrated as follows for the example:
1. to ensure the water path circulation, the utility model discloses the realization of the butt joint of the economizer inlet header of the boiler and the feed pipe of the old power plant
Demolish the back with old power plant's boiler, the condensate water that comes out from old power plant's condenser 6 gets into the water supply pipe, gets into behind backheat heater 11, 8 the utility model discloses boiler economizer 3's import header.
The design of the economizer 3 is to perform reasonable structural dimension calculation and thermodynamic calculation according to the outlet water temperature of the regenerative heater of the old power plant, so that the purposes of reducing the exhaust gas temperature and improving the utilization rate of fuel and the boiler efficiency are achieved.
2. For guaranteeing the steam supply, the utility model discloses the realization of the main steam pipeline 5 that the 2 export headers of over heater of boiler draw forth and 7 steam inlets butt joints of steam turbine
And (4) after the old power plant boiler is dismantled, newly building a waste incineration boiler at the original site. The heat generated by the incineration of the incinerator heats the feed water to generate steam, and the steam is heated by the superheater to generate superheated steam. And a main steam pipeline 5 is led out from the superheater outlet header and is butted with the steam inlet of the original steam turbine. The steam generated by the newly-built boiler can be maintained to be normally operated as long as the steam can meet the steam inlet parameters of the original steam turbine. The steam inlet parameters which the steam at the outlet of the boiler needs to meet are as follows: steam temperature t, steam pressure p and steam flow D.
The utility model discloses the factor that should consider in the aspect of the boiler design has:
① boiler evaporation capacity, feedwater pressure and temperature, andmain pre-gate superheat steam pressure and temperature.
② flow rate of saturated steam extracted from the boiler drum.
③, such as low calorific value, soot properties, etc.
④ continuous blowdown.
⑤ ambient temperature.
⑥ the boiler is arranged integrally.
Through the parameter design, the special boiler suitable for waste incineration is formed.
3. Realization of butt joint of boiler smoke exhaust outlet and reserved smoke treatment equipment
This part is docked and is in following the utility model discloses boiler flue export is drawn pipeline and old power plant's dust remover butt joint, should consider following factor again when the butt joint to the technical scheme of decision butt joint:
① calorific value of refuse fuel
② flue gas flux determined by the smoke yield per unit mass of fuel is compared with the throughput capacity of the flue gas treatment device of the old power plant
③ comparing the smoke components of coal-fired boiler, the smoke mainly contains dust and CO2、NOX、SO2(ii) a The main components of the flue gas of the garbage incineration boiler are as follows: dust, CO2SOX, NOx and HCL. Since the new component adds HCL, the addition of HCL removal equipment should be considered. The utility model discloses well rubbish burns boiler exhaust flue gas's each composition concentration and whether matches with original flue gas treatment facility. If the concentration of some components is too high and exceeds the processing capacity of the original equipment, the processing effect of the original equipment can be affected, the national environmental protection requirements cannot be met, and more capacity or new advanced equipment should be selected and installed, such as: HCL-washing tower, SO 2-washing tower, activated carbon reactor and NOx removal reactor.
④ since most small coal-fired power plants are not equipped with electric dust-removing equipment, if the original dust-removing equipment can not meet the working requirement, the electric dust-removing equipment should be selected and installed.
⑤ if the power station does not have the smoke and dust sulphur removing facility, the discharge of sulphur dioxide can be reduced by 80% by dry adsorption method, the dry adsorption method is not used as the internal component of the new technology of the refuse burning device to replace the coal burning device, and can be provided as the matching technology.
4. Realize the utility model discloses well boiler automatic control equipment and old power plant's linking in the aspect of the operation regulation and control equipment, should link up in old power generation facility steam turbine controlling means with the utility model discloses the controlling means of power generation facility's boiler matches, adopts the fuel quantity controlling means who matches with boiler controlling means
The utility model discloses as long as the state parameter and the steam volume of boiler export steam guarantee with former boiler the same, the operation of steam turbine just can not receive any influence, so the original relatively independent controlling means of steam turbine still can adopt to the controlling means of old power plant's generator also can remain. Now considered is the control of the boiler section. The boiler control device includes: a steam temperature control device, a drum pressure and drum water supply control device, a boiler combustion control device and a boiler heat load adjusting device. In principle, the original control equipment is fully utilized. The principle and the function of the boiler drum water supply control device are the same, so that the boiler drum water supply control device can be reserved. The design process of the garbage incinerator is different from that of a coal-fired boiler, and the characteristics of fuel are also different, so that the combustion control device of a garbage power plant is matched with a new boiler for use. Of course, the fan used to regulate the furnace pressure and some other auxiliary machinery may be retained. In addition, the coal-fired boiler and the waste incineration boiler are greatly different in the fuel feeding process, so that the fuel quantity control device also needs to be readjusted, and a new fuel quantity adjusting control device is adopted. The running speed of the fire grate is controlled, so that the steam generation amount and the set value thereof are matched with the original steam turbine, fluctuation is realized in a close range, and the stable combustion is ensured. The newly added feeding device is correspondingly added with a weighing device, a loading vehicle control platform and a garbage hoisting start control device.
The following description of the related art to the present invention is as follows:
1. garbage collection and pre-treatment
It is envisaged that a set of equipment will process 30 million tons of waste per year, the waste to be processed being provided by one or more waste distribution centres from which it is transported directly to a power plant, either in containers or in bales by extrusion.
Before a specific project is designed, local garbage sources, garbage collection, transportation, storage and the like must be carefully investigated, and whether industrial garbage is used or not, the possibility of waste and other problems need to be clarified in advance.
The extrusion container is a recognized effective tool after long-distance transportation and railway and highway combined transportation verification, and the density of garbage extruded in the container can reach 600 kilograms per cubic meter.
The specific weight specification of the screened garbage extruded and packed is about 900 kg/cubic meter, which creates conditions for sealed storage. The storage bag should be kept dry, for example, it may be covered with a plastic film or the like.
2. Transport of refuse
Generally, domestic waste that cannot be disposed of by decay cannot be transported directly from a residential area to a power plant. It is envisaged that the refuse vehicle will periodically transport the combustible refuse to a fixed distribution centre where it will be extruded for packing and the like in preparation for further transport.
Rubbish is transported to the power plant, general accessible road or railway transportation, according to the utility model discloses technical scheme's design ability, every work daily needs transport about 1000 tons of combustible refuse to the power plant. If a 20 ton truck is used, the heavy load on the highway section traffic around the plant area is 50 cars per day and the transport truck should be fully enclosed.
If container transport is selected, at least the power plant should be provided with crane equipment. In addition, an extrusion device is required to ensure the smooth unloading of the container and the smooth feeding of the storage bin. If the supplied materials are garbage bags which are pressed and bundled, a cutting device for opening the bags is required to be configured.
The following description is based on a container rail transport mode.
3. Garbage incinerator
① garbage weighing device and garbage storage device
The garbage truck is weighed by the weighbridge and then discharges the garbage into the garbage pool. The weighing signal of the weighbridge is sent to a central control room. The number of discharge positions depends on the waste throughput. Discharge door distributor or hydraulic actuator. If necessary, a rotary large-piece crusher is arranged at one of the discharge locations. The capacity of the garbage pool is at least 5 days for operation, so as to ensure the insufficient transportation of the garbage and the short-term parking and storage requirements. In order to prevent dust and odor from diffusing into the surrounding environment, primary combustion air is extracted from the unloading plant through the garbage pool.
② garbage feeding device
Two independent mobile grab cranes are arranged at the upper part of the garbage pool. Each can be fed with garbage separately and mixed in a garbage pool. The entire waste receptacle can be conveniently viewed from the crane cab.
③ Combustion Process
The new principle of combining the parallel flow combustion device with the roller bottom grate is an ideal choice for garbage incineration and can completely meet the strict requirements related to high-temperature combustion. The process of quantitatively placing the garbage on the incineration grate is completed by a push type feeder. The transfer and conveying of the roller bottom fire grate distributes garbage and ensures that the burning is supplied in time. The combustion air is supplied from below through the roller bottom grate according to the district. Complete combustion of the flue gases is ensured by top overfire air fed into the furnace. The intense flame radiation from the furnace chamber promotes and enhances the drying process and the effective ignition of the waste on the front grate area. In the rear grate part, the hot flue gas is burnt out before the slag passes through a rear combustion area and then flows into a first hearth flue.
Temperature measures are also shown here, which will be used to monitor whether the parameters relating to residence time and flue gas temperature, which is reduced to about 200 ℃ during the subsequent boiler pass up to the furnace outlet, meet the prescribed minimum requirements, the energy contained therein being utilized for the production of steam.
The disposal measures associated with this combustion process are: reducing excess air, increasing furnace temperature, reducing specific mechanical loads on the grate.
The measures described above make it possible to reduce the following substances in the flue gas, carbon monoxide, organic carbon, dust, nitrogen oxides, harmful oxides and furans, also to achieve the greatest possible burnout of the residues and fly ash.
④ ignition and combustion-supporting burner
In order to start the garbage incinerator for ignition and balance the combustion quality, two high-quality gas burners are oppositely arranged in furnace walls on two sides of a hearth, the combustion power of the two high-quality gas burners reaches 60% of the thermal power of the whole garbage incinerator, and the garbage incinerator can be started by ignition smoothly within a short time.
⑤ slag and ash removing equipment
After the waste is burned by the garbage furnace, most (about 90 percent) of the residual inert substances are formed into blocky slag when reaching the bottom end of the roller bottom grate. And the other small part of the fine furnace ash falls to the bottom of the furnace through the roller bottom furnace, and the fine furnace ash can be generally sent to a slag cleaning machine together with other slag for treatment.
At the end of the grate at the bottom of the roller, the residue after combustion enters a ramming type wet-process slag remover connected with the grate through a totally-closed sliding channel and is cooled by a cleaning pool of the sealed slag remover. The water level of the cleaning pool is kept constant, so that gas leakage in the slag discharge channel is avoided.
The slag discharged from the slag remover is conveyed into a buffer grinder through a conveyor belt. The ground and crushed slag can be transported to a large slag pile of a power plant for unified treatment, and can be directly used for highway construction and the like. And hanging a magnet above the conveyor belts in front of and behind the grinding machine respectively to suck the large and small iron metal blocks in the slag.
The fine furnace ash falling into the furnace bottom is collected onto a chute conveyor belt through ash discharge chutes arranged below each roller bottom grate section, and then is directly conveyed to a slag cleaning machine. Because the chute conveyer belt is the operation under water, arrange grey groove fill and also directly soak in water and send the stove ash to the conveyer belt, consequently guaranteed the atmoseal. In fact, the fine furnace ash at the bottom of the furnace can be directly conveyed to a large slag pile of a power plant without any consideration, which is an alternative scheme.
Only a very small part (about 1-3 g/cubic meter) of fly ash particles enter the main boiler along with the flue gas and are removed together with the boiler ash; wherein a small part of the fly ash directly falls to the bottom of the boiler, and most of the fly ash is absorbed by an electric filter of the boiler.
⑥ boiler equipment (hearth)
The combustion chamber is of a steel plate and support profile steel structure and is lined with high-quality refractory materials. The combustion chamber is specially designed and manufactured for burning garbage, and is structurally characterized in that central concentrated combustion can be formed, the combustion chamber is relatively spacious, the maximum heat energy release of fuel is guaranteed, and the thermal stress generated on the chamber wall of the combustion chamber is small, so that the high-temperature furnace stagnation time of the fuel can be relatively prolonged, the thorough combustion of carbide is guaranteed, and the discharge of solid micro-materials is reduced.
In the horizontal section, the flue gas flows through a protection evaporator, a final superheater, a superheater, an evaporator and an economizer in sequence. The first convective heat exchange surface on the flue gas side is the screen evaporator (evaporators 1 and 2), which ensures a thorough mixing and separation of the flue gases. The temperature of the flue gas before the final superheater is kept below 650 ℃, so that scaling caused by overhigh temperature of the pipe wall is avoided, and corrosion is reduced. The final superheater is the first superheater tube bank in which the steam flow direction is in parallel with the flue gas flow direction. The economizer is the last heat exchange surface that cools the flue gas to no more than 200 degrees celsius. Due to the bypass on the water side, the economizer is able to maintain the flue gas temperature at 200 degrees celsius throughout the useful life of the boiler. The lateral spacing of the heat exchange surfaces is selected to be large; gradually decreasing from the evaporator to the boiler outlet. The flue gas flow rate is lower at all tube bundles to prevent erosion. Enough space is left between the tube bundles, so that the tube bundles are convenient to clean and maintain. An ash bucket is arranged below the tube bundle and used for discharging the boiler fly ash.
⑦ flue gas purifying device
The utility model discloses the flue gas purification device who takes should can be good, and the high-usage can satisfy the environmental protection requirement again.
The flue gas components generated by burning the garbage are increased by HCL compared with the flue gas components generated by burning coal. The apparatus should be augmented with a HCL-scrubber. The HCL-washing tower adopts a semi-dry absorption method of curing stones to absorb acid gases in the flue gas. In the HCL-scrubber, most of the HCL and SO2Can be adsorbed, and then absorbs dioxin and evaporated mercury by a dry method.
HCL and SO2The principle of adsorption is as follows:
the solid particles finally formed by the reaction are finally collected by a high-performance fabric dust collector or an electric dust collector, and are discharged by a dry method or a wet method and then are transported away. The flue gas after purification can reach the strictest standard when leaving the flue gas purification device.
Activated carbon injection: the activated carbon is injected to absorb heavy metals and dioxin in the flue gas. The activated carbon is injected into the flue gas flow through the injection device under the action of centrifugal force and is uniformly mixed with the whole flue gas flow. The effect of this effect is very important, since the amount of activated carbon is small compared to the total mass flow. The injection points are arranged in a compact reactor where the flue gases are turbulently formed in order to achieve uniform mixing. The reactor with a compact structure is arranged at the inlet of the bag-type dust collector.
And (3) draining treatment: due to the high organic content of the leachate, the most suitable treatment method is biochemical treatment. Due to the high content of organic matter, complete aerobic biochemical treatment requires a large amount of oxygen and the power consumption is high. Anaerobic biochemical treatment is more suitable.
In a word, the waste incineration device replaces a coal burning device and is in butt joint with related equipment of an old power plant, so that most of the equipment of the old power plant can be continuously used, and the obvious economic benefit is ensured.
It is particularly worth mentioning that the utility model has the following four obvious advantages: 1. the existing plant equipment, infrastructure and the like are fully utilized, and low investment is ensured; 2. the development and utilization efficiency of potential energy of garbage is improved as much as possible; 3. conventional fuels (coal, petroleum and natural gas) are replaced, so that the expenditure is saved; 4. the construction period is saved by more than half.
① Low input:
the savings in capital investment can be illustrated by a waste incineration plant processing 1000 tons a day:
2.5-4 hundred million RMB (16 years old) investment for replacing coal burning device for garbage burning device
Average capital investment of 25-40 million Yuan RMB/ton/day for each ton/day of garbage
The average capital investment of each ton of garbage is 54 yuan to 86 RMB yuan.
Investment for garbage incineration plants of the same scale 7.0 hundred million RMB (depreciation in 16 years)
Capital investment of 70 ten thousand yuan RMB/ton/day of garbage per ton/day
The average capital investment per ton of waste is 150 dollars in folk dollars.
It should be noted that the above investment calculation is based on the German import equipment price standard, considering that the cost and investment are lower if domestic equipment is adopted. The operating management costs are no longer used as a comparison here, since the expenditure of management personnel and maintenance equipment is almost insignificant compared to the capital investment and energy savings.
② energy saving
The enthalpy of 30 ten thousand tons of refuse (with a calorific value of 1100 kcal/kg) is equal to the enthalpy of 5 ten thousand tons of standard coal (with a calorific value of 7000 kcal/kg). If calculated according to 200 RMB per ton of coal, 1000 ten thousand RMB can be saved.
③ -year garbage disposal cost saving
The disposal of the waste is facilitated by government financial subsidies. According to the cost of saving 64-96 RMB per ton of garbage processed, 30 ten thousand tons of garbage can save 1920-2880 RMB for investment in other aspects.
The utility model is suitable for a transformation of old power plant of 5 ten thousand KW and below.

Claims (6)

1. The utility model provides a power generation facility of msw incineration boiler and butt joint of old power generation facility, mainly has boiler, steam turbine and a plurality of auxiliary assembly, its characterized in that: and the garbage incinerator (18) is connected with the boiler (1) into a whole to form a garbage incineration boiler so as to replace a coal-fired boiler in old power generation equipment, and is connected with a steam turbine (7) arranged behind the boiler (1) through a pipeline.
2. The power generation apparatus in which a waste incineration boiler is docked with old power generation equipment according to claim 1, characterized in that: in order to ensure waterway circulation, an economizer inlet header in a boiler (1) of the power generation device is butted with a water supply pipe of old power generation equipment, so that condensed water from an old gas condenser (6) with the coal-fired boiler removed enters a water supply pipeline, passes through regenerative heaters (11 and 8) and then enters an inlet header of a boiler economizer (3) of the power generation device.
3. The power generation apparatus in which a waste incineration boiler is docked with old power generation equipment according to claim 1, characterized in that: in order to ensure the steam supply, a main steam pipeline (5) led out from an outlet header of a superheater (2) of a boiler in the power generation device is butted with a steam inlet of a steam turbine (7).
4. The power generation apparatus in which a waste incineration boiler is docked with old power generation equipment according to claim 1, characterized in that: the smoke outlet of the boiler in the power generation device is in butt joint with the smoke treatment equipment of the old power generation equipment, and the part of the butt joint is that a pipeline led out from the flue outlet of the boiler (1) of the power generation device is in butt joint with the dust remover of the old smoke treatment equipment.
5. The power generation apparatus in which a waste incineration boiler is docked with old power generation equipment according to claim 1, characterized in that: the automatic control equipment of the boiler (1) of the power generation device is connected with the operation regulation and control equipment of the old power generation device, the connection is that a turbine control device in the old power generation device is matched with a control device of the boiler (1) of the power generation device, a fuel quantity regulation and control device matched with the boiler control device is adopted, and meanwhile, a weighing device, a loading vehicle control platform and a hoisting start control device are correspondingly added in a feeding device.
6. The power generation device with the butt joint of the waste incineration boiler and the old power generation equipment as claimed in claims 1-5, is characterized in that: the structure of the waste incineration boiler is a device which is suitable for waste incineration and is designed according to corresponding parameters of a butt joint object.
CN99248360U 1999-10-12 1999-10-12 Electricity generating apparatus composed of butt joined refuse incinerator and old generating equipment Expired - Fee Related CN2389292Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN99248360U CN2389292Y (en) 1999-10-12 1999-10-12 Electricity generating apparatus composed of butt joined refuse incinerator and old generating equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN99248360U CN2389292Y (en) 1999-10-12 1999-10-12 Electricity generating apparatus composed of butt joined refuse incinerator and old generating equipment

Publications (1)

Publication Number Publication Date
CN2389292Y true CN2389292Y (en) 2000-07-26

Family

ID=34033565

Family Applications (1)

Application Number Title Priority Date Filing Date
CN99248360U Expired - Fee Related CN2389292Y (en) 1999-10-12 1999-10-12 Electricity generating apparatus composed of butt joined refuse incinerator and old generating equipment

Country Status (1)

Country Link
CN (1) CN2389292Y (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107702107A (en) * 2017-09-30 2018-02-16 哈尔滨锅炉厂有限责任公司 A kind of waste incinerator and Large-scale fire-electricity unit fume side coupled system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107702107A (en) * 2017-09-30 2018-02-16 哈尔滨锅炉厂有限责任公司 A kind of waste incinerator and Large-scale fire-electricity unit fume side coupled system

Similar Documents

Publication Publication Date Title
CN101570388B (en) Harmless recycling treatment process for urban sludge
CN100572917C (en) The double-loop double-pyrogenation incinerator and the using method thereof that are used for rubbish processing to be harmless
CN203791331U (en) System for synergistic treatment of municipal domestic waste in cement kiln
CN105032884B (en) Cement rotary kiln collaboration processes house refuse and energy comprehensive utilization system and method
CN103934254B (en) A kind of system and method for cement kiln associated treatment domestic waste
CN1270988C (en) Sludge burning treatment method and system
CN204544958U (en) Cement rotary kiln associated treatment house refuse and energy comprehensive utilization system
CN101294708A (en) City life rubbish fluidized bed gasification combustion processing method
CN104501171B (en) Garbage derivatived fuel (RDF) pyrolysis gasification system
CN101476729A (en) Drying pretreatment method and device for urban domestic garbage
CN107062241A (en) A kind of domestic garbage pyrolysis stove
CN105066135A (en) Small garbage catalytic gasification pyrolysis technology method and equipment thereof
CN205402733U (en) Domestic waste and/or industrial waste's processing production line
CN216844701U (en) Sludge incineration treatment system
CN201310895Y (en) Municipal domestic refuse drying pretreatment device
CN202253665U (en) Solid waste incineration and high-temperature gasification combined system
CN206637622U (en) A kind of domestic garbage pyrolysis stove
CN111333298A (en) Sludge drying machine with transportation function and working method thereof
CN107674691A (en) A kind of system and method for domestic garbage resource
CN103939912A (en) Bypass power generation process and system of dry-process rotary kiln cooperative processing of wet garbage
CN102344259A (en) Environmental-protection and energy-saving garbage incineration and waste gas utilization device
CN203771420U (en) Bypass generating system for co-processing wet garbage by dry method rotary kiln
CN201327040Y (en) Domestic waste gasification and power generation system
CN106322387A (en) Rubbish disposal method
CN1259637A (en) Garbage burning boiler instead of coal burning boiler to proceed electricity generation

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee