CN223951716U - Ecological water release structure during diversion tunnel closure period - Google Patents

Ecological water release structure during diversion tunnel closure period

Info

Publication number
CN223951716U
CN223951716U CN202520368807.4U CN202520368807U CN223951716U CN 223951716 U CN223951716 U CN 223951716U CN 202520368807 U CN202520368807 U CN 202520368807U CN 223951716 U CN223951716 U CN 223951716U
Authority
CN
China
Prior art keywords
gate
diversion tunnel
ecological
plugging
drain pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202520368807.4U
Other languages
Chinese (zh)
Inventor
张文剑
郝晋彩
郝莹莹
吴蕾
胡允楚
方海挺
杜巧丰
余建平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Water Resources And Hydropower Survey And Design Institute Co ltd
Original Assignee
Zhejiang Water Resources And Hydropower Survey And Design Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Water Resources And Hydropower Survey And Design Institute Co ltd filed Critical Zhejiang Water Resources And Hydropower Survey And Design Institute Co ltd
Priority to CN202520368807.4U priority Critical patent/CN223951716U/en
Application granted granted Critical
Publication of CN223951716U publication Critical patent/CN223951716U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00—Energy generation through renewable energy sources
    • Y02E10/20—Hydro energy

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses an ecological drainage structure in a diversion tunnel plugging period, which comprises a diversion tunnel inlet structure, an ecological drainage pipe, a diversion tunnel plugging gate opening and closing system and an ecological drainage pipe plugging gate opening and closing system, wherein the ecological drainage pipe is buried in a reinforced concrete gate pier at one side of the diversion tunnel inlet structure, a gate slot of the diversion tunnel plugging gate opening and closing system is positioned in the diversion tunnel inlet structure, a gate hoist is positioned at the top of a bent frame of the diversion tunnel inlet structure, a gate slot of the ecological drainage pipe plugging gate opening and closing system is positioned in a diversion tunnel reinforced concrete gate pier at the same side as the ecological drainage pipe, and the gate hoist is positioned at the top of the diversion tunnel reinforced concrete gate pier at the same side as the ecological drainage pipe. The utility model combines ecological protection with hydraulic engineering, has simple structure, embeds the ecological water drain pipe in the inlet structure of the diversion tunnel, seals the gate to stop water during the plugging of the diversion tunnel, and discharges ecological flow through the ecological water drain pipe to realize the combination of hydraulic engineering and ecological protection.

Description

Ecological drainage structure for diversion tunnel plugging period
Technical Field
The utility model relates to a hydraulic engineering and ecological protection technology, in particular to an ecological water discharging structure in a diversion tunnel plugging period.
Background
In order to solve the diversion problem in the construction process of the water conservancy diversion junction, dry land construction is realized, the upstream water of a river channel is usually diverted to the downstream through constructing a diversion tunnel, ecological flow is discharged from the diversion tunnel during construction, but in the process that the diversion tunnel is blocked by a lower gate until the water level of a dam rises to the inlet bottom elevation of a power generation diversion tunnel, no path is adopted to discharge the ecological flow.
The ecological flow is the minimum water flow for maintaining the survival and ecological balance of downstream organisms, and under the background of the growing importance of ecological protection, the ecological protection and the hydraulic engineering construction are combined, so that the ecological flow during the blocking of the diversion tunnel is ensured to be leaked, and the ecological flow is the problem to be solved in the current hydraulic junction construction process.
Disclosure of utility model
The utility model provides an ecological water drainage structure in a diversion tunnel plugging period aiming at the problems encountered in actual engineering, so as to solve the problem of ecological flow leakage in the diversion tunnel plugging period, ensure the continuous flow of ecological flow in the whole engineering construction period and realize the integration of hydraulic engineering and ecological protection.
The utility model adopts the technical scheme that:
The ecological water drainage structure in the diversion tunnel plugging period comprises a diversion tunnel inlet structure, an ecological water drainage pipe, a diversion tunnel plugging gate opening and closing system and an ecological water drainage pipe plugging gate opening and closing system;
The diversion tunnel inlet structure comprises two side gate piers, a bottom plate, a top plate and a bent frame, wherein the bottom plate, the two side gate piers, the top plate and the bent frame are sequentially arranged from bottom to top;
the ecological water drain pipe is buried in a gate pier at one side of the diversion tunnel inlet structure;
the opening and closing system of the diversion tunnel plugging gate comprises a diversion tunnel plugging gate, an opening and closing machine, a steel rope and a gate groove, wherein the opening and closing machine of the diversion tunnel plugging gate is positioned at the top of a bent frame of the diversion tunnel inlet structure, and the gate groove of the diversion tunnel plugging gate is positioned in the diversion tunnel inlet structure;
The opening and closing system of the ecological drain pipe plugging gate comprises an ecological drain pipe plugging gate, an opening and closing machine, a pull rod and a gate groove, wherein the opening and closing machine of the ecological drain pipe plugging gate is positioned at the top of a top plate of the diversion tunnel inlet structure, the gate groove of the ecological drain pipe plugging gate is positioned in a diversion tunnel reinforced concrete gate pier on the same side of the ecological drain pipe, the lower part of the opening and closing machine of the ecological drain pipe plugging gate is connected with the pull rod, the lower part of the pull rod is connected with the ecological drain pipe plugging gate, and the ecological drain pipe plugging gate is placed into the gate groove of the ecological drain pipe plugging gate through the opening and closing machine of the ecological drain pipe plugging gate to realize plugging of the ecological drain pipe.
Further, the gate piers, the bottom plate, the top plate and the upper bent frame at the two sides of the diversion tunnel inlet structure are all of reinforced concrete structures and are connected into a whole through reinforced concrete.
Further, stainless steel rails are arranged around the top of the bent frame.
The beneficial effects of the utility model are as follows:
The utility model can be used for ecological water discharge during diversion tunnel plugging, solves the problem of ecological flow leakage interruption during diversion tunnel plugging, has the characteristics of simple structure, convenient operation, low engineering cost and the like, and has higher popularization and application values in the field of reservoir junction engineering.
Drawings
FIG. 1 is a schematic view of a longitudinal cross-sectional structure of the present utility model;
FIG. 2 is a schematic view of the cross-sectional structure A-A of FIG. 1;
FIG. 3 is a schematic view of the cross-sectional B-B structure of FIG. 2;
FIG. 4 is a schematic view of the cross-sectional C-C structure of FIG. 2;
FIG. 5 is a layout diagram of a diversion tunnel plugging gate opening and closing system of the utility model;
fig. 6 is a layout diagram of the opening and closing system of the blocking gate of the ecological water drain pipe.
In the figure, a 1-diversion tunnel inlet structure, a 2-ecological water discharge pipe, a 11-gate pier, a 12-bottom plate, a 13-top plate, a 14-bent frame, a 15-stainless steel railing, a 3-diversion tunnel plugging gate opening and closing system, a 31-diversion tunnel plugging gate opening and closing machine, a 32-diversion tunnel plugging gate, a 33-diversion tunnel plugging gate slot, a 34-steel rope, a 4-ecological water discharge pipe plugging gate opening and closing system, a 41-ecological water discharge pipe plugging gate opening and closing machine, a 42-ecological water discharge pipe plugging gate, a 43-ecological water discharge pipe plugging gate slot and a 44-pull rod are arranged.
Detailed Description
The utility model is further described below with reference to the accompanying drawings.
As shown in fig. 1-6, the ecological water drainage structure in the diversion tunnel plugging period comprises a diversion tunnel inlet structure 1, an ecological water drain pipe 2, a diversion tunnel plugging gate opening and closing system 3 and an ecological water drain pipe plugging gate opening and closing system 4, wherein the diversion tunnel inlet structure 1 comprises two gate piers 11, a bottom plate 12, a top plate 13, a bent frame 14 and a stainless steel railing 15. The ecological water discharge pipe 2 is buried in the gate pier 11 at one side of the diversion tunnel inlet structure 1 in advance. The gate slot 33 of the diversion tunnel plugging gate opening and closing system 3 is positioned in the diversion tunnel inlet structure 1, the opening and closing machine 31 is positioned at the top of the diversion tunnel inlet structure bent frame 14, the gate slot 43 of the ecological water drain plugging gate opening and closing system 4 is positioned in the diversion tunnel reinforced concrete gate pier 11 at the same side as the ecological water drain 2, and the opening and closing machine 41 is positioned at the top of the diversion tunnel reinforced concrete gate pier 11 at the same side as the ecological water drain 2.
The two sides gate piers 11, the bottom plate 12, the top plate 13 and the bent frame 14 of the diversion tunnel inlet structure 1 are all of reinforced concrete structures, are connected into a whole through reinforced concrete, and are sequentially the bottom plate 12, the two sides gate piers 11, the top plate 13, the bent frame 14 and the stainless steel rail 15 from bottom to top, and the stainless steel rail 15 is positioned on the empty face around the top of the bent frame 14.
As shown in fig. 5, the diversion tunnel plugging gate opening and closing system 3 includes a diversion tunnel plugging gate opening and closing machine 31, a diversion tunnel plugging gate 32, a diversion tunnel plugging gate slot 33 and a steel cable 34. The diversion tunnel plugging gate hoist 31 is placed at the top of the upper bent frame 14 of the diversion tunnel inlet structure, the diversion tunnel plugging gate slot 33 is located in the diversion tunnel inlet structure 1, the lower part of the diversion tunnel plugging gate hoist 31 is connected with the steel cable 34, the lower part of the steel cable 34 is connected with the diversion tunnel plugging gate 32, and the diversion tunnel plugging gate 32 is placed into the diversion tunnel plugging gate slot 33 through the diversion tunnel plugging gate hoist 31 to realize the gate plugging of the diversion tunnel.
As shown in fig. 6, the ecological drain pipe blocking gate opening and closing system 4 includes an ecological drain pipe blocking gate opening and closing machine 41, an ecological drain pipe blocking gate 42, an ecological drain pipe blocking gate slot 43, and a tie rod 44. The ecological drain pipe shutoff gate hoist 41 is placed at the top of the diversion tunnel inlet structure top plate 13, the ecological drain pipe shutoff gate slot 43 is located in the diversion tunnel reinforced concrete gate pier 11 on the same side of the ecological drain pipe, the lower part of the ecological drain pipe shutoff gate hoist 41 is connected with the pull rod 44, the lower part of the pull rod 44 is connected with the ecological drain pipe shutoff gate 42, and the ecological drain pipe shutoff gate 42 is placed into the ecological drain pipe shutoff gate slot 43 through the ecological drain pipe shutoff gate hoist 41 to realize the shutoff of the ecological drain pipe 2.
The construction and use steps of the utility model are as follows:
s1, calculating and determining the pipe diameter of the ecological water discharge pipe 2 according to the ecological flow which is discharged as required.
S2, finishing the diversion tunnel inlet structure 1 and the embedded ecological water discharge pipe 2 before river closure and diversion tunnel water passage, and installing the diversion tunnel plugging gate opening and closing system 3 and the ecological water discharge pipe plugging gate opening and closing system 4.
S3, when the main structure of the reservoir junction engineering is finished and water storage is needed, the diversion tunnel is subjected to gate-down blocking by using the diversion tunnel blocking gate opening and closing system 3.
S4, after the diversion tunnel is blocked, the ecological drainage pipe 2 is used for discharging ecological flow, the upstream water level continuously rises along with upstream water, when the upstream water level exceeds the elevation of the inlet bottom of the power generation diversion tunnel, the power generation diversion tunnel can be used for discharging ecological flow, at the moment, the ecological drainage pipe 2 is blocked by the ecological drainage pipe blocking gate opening and closing system 4, and the diversion tunnel is blocked by concrete.
The above embodiments are described in connection with the accompanying drawings, but are not to be construed as limiting the scope of the utility model, and it should be noted that the technical solutions obtained by equivalent substitution or equivalent transformation to those skilled in the art without departing from the concept of the utility model are all within the scope of the utility model.

Claims (3)

1. The ecological drainage structure in the diversion tunnel plugging period is characterized by comprising a diversion tunnel inlet structure, an ecological drainage pipe, a diversion tunnel plugging gate opening and closing system and an ecological drainage pipe plugging gate opening and closing system;
The diversion tunnel inlet structure comprises two side gate piers, a bottom plate, a top plate and a bent frame, wherein the bottom plate, the two side gate piers, the top plate and the bent frame are sequentially arranged from bottom to top;
the ecological water drain pipe is buried in a gate pier at one side of the diversion tunnel inlet structure;
the opening and closing system of the diversion tunnel plugging gate comprises a diversion tunnel plugging gate, an opening and closing machine, a steel rope and a gate groove, wherein the opening and closing machine of the diversion tunnel plugging gate is positioned at the top of a bent frame of the diversion tunnel inlet structure, and the gate groove of the diversion tunnel plugging gate is positioned in the diversion tunnel inlet structure;
The opening and closing system of the ecological drain pipe plugging gate comprises an ecological drain pipe plugging gate, an opening and closing machine, a pull rod and a gate groove, wherein the opening and closing machine of the ecological drain pipe plugging gate is positioned at the top of a top plate of the diversion tunnel inlet structure, the gate groove of the ecological drain pipe plugging gate is positioned in a diversion tunnel reinforced concrete gate pier on the same side of the ecological drain pipe, the lower part of the opening and closing machine of the ecological drain pipe plugging gate is connected with the pull rod, the lower part of the pull rod is connected with the ecological drain pipe plugging gate, and the ecological drain pipe plugging gate is placed into the gate groove of the ecological drain pipe plugging gate through the opening and closing machine of the ecological drain pipe plugging gate to realize plugging of the ecological drain pipe.
2. The ecological drainage structure in the diversion tunnel plugging period according to claim 1, wherein the gate piers, the bottom plate, the top plate and the upper bent frame on two sides of the diversion tunnel inlet structure are all of reinforced concrete structures and are connected into a whole through reinforced concrete.
3. The ecological drainage structure in the diversion tunnel plugging period according to claim 1 or 2, wherein stainless steel rails are arranged around the top of the bent frame.
CN202520368807.4U 2025-03-05 2025-03-05 Ecological water release structure during diversion tunnel closure period Active CN223951716U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202520368807.4U CN223951716U (en) 2025-03-05 2025-03-05 Ecological water release structure during diversion tunnel closure period

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202520368807.4U CN223951716U (en) 2025-03-05 2025-03-05 Ecological water release structure during diversion tunnel closure period

Publications (1)

Publication Number Publication Date
CN223951716U true CN223951716U (en) 2026-02-27

Family

ID=98862055

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202520368807.4U Active CN223951716U (en) 2025-03-05 2025-03-05 Ecological water release structure during diversion tunnel closure period

Country Status (1)

Country Link
CN (1) CN223951716U (en)

Similar Documents

Publication Publication Date Title
CN101545251B (en) A method for blocking and storing water in a natural river course and taking water
CN103410130B (en) Multi-purpose tunnel arrangement structure
CN107288104A (en) A kind of cradle-type checkdam structure
CN104358240B (en) A kind of gate sill leakage plugging device and constructional method thereof
CN106968227B (en) Maintenance arrangement structure and maintenance method of permanent plugs of diversion tunnel of high arch dam
CN112502092A (en) Water gate and pump station double-layer integrated structure and operation method thereof
CN109267549A (en) Diversion tunnel structure
CN111305172A (en) A two-way pressure tunnel for water diversion and drainage
CN207032177U (en) Cradle-type checkdam structure
CN106381843A (en) Canal lining fastland repair foundation pit drainage structure and method without interruption of water transfer
CN202440787U (en) Riverway diversion device
CN112982319A (en) Structure and method for conducting diversion, emptying and water taking through dam foundation culvert
CN220888567U (en) Energy dissipation flow control structure
CN103614986B (en) It a kind of is applicable to the pressure free current inlet method that Tailings Dam drains off floodwaters
CN212714848U (en) Initial diversion tunnel plugging gate
CN119980960A (en) An ecological water release structure for diversion tunnel plugging period
CN211948317U (en) An ecological flow discharge facility for an existing diversion channel type rural hydropower station
CN217839924U (en) Permanent drainage structures in water conservancy diversion tail water tunnel reconstruction end cap upper reaches
CN206143723U (en) Canal lining restores bypass pipe water delivery and formula foundation ditch is cuted in cofferdam
CN215888150U (en) Blocking device for concrete block head drain pipe of diversion tunnel
CN117051760A (en) An ecological flow discharge facility with fish passage and construction method thereof
CN205604193U (en) A high dam reservoir emptying device
CN210216332U (en) Retaining dam structure for overhauling whole tunnel section of hydroelectric engineering diversion tunnel in canyon region
CN209194485U (en) Diversion tunnel structure
CN212052645U (en) Water diversion and drainage bidirectional pressure tunnel

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant