CN223937634U CN202423078347.6U CN202423078347U CN223937634U CN 223937634 U CN223937634 U CN 223937634U CN 202423078347 U CN202423078347 U CN 202423078347U CN 223937634 U CN223937634 U CN 223937634U
Authority
CN
China
Prior art keywords
rod
post
pouring
die structure
beam post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202423078347.6U
Other languages
Chinese (zh)
Inventor
杨旭辉
张文斌
朱新普
胡伟
李涛
崔权
李肖斌
王深振
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Communications Investment Group Co ltd
China Railway Guangzhou Engineering Group Co Ltd CRECGZ
CRECGZ No 2 Engineering Co Ltd
Original Assignee
China Railway Communications Investment Group Co ltd
China Railway Guangzhou Engineering Group Co Ltd CRECGZ
CRECGZ No 2 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Communications Investment Group Co ltd, China Railway Guangzhou Engineering Group Co Ltd CRECGZ, CRECGZ No 2 Engineering Co Ltd filed Critical China Railway Communications Investment Group Co ltd
Priority to CN202423078347.6U priority Critical patent/CN223937634U/en
Application granted granted Critical
Publication of CN223937634U publication Critical patent/CN223937634U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

本申请公开了一种T梁后浇带挂模结构,涉及建筑施工技术领域,旨在解决对T梁后浇带挂模时,需要用螺栓固定挂模,这种方法费时费力,所带来施工效率低的问题,其技术方案要点是,当需要挂模时,首先在后浇带处搭设支墩、支撑板和立杆,根据挂模高度,调节立杆插入支撑板的长度,接着拉动手调杆,使穿孔杆依次穿过定位孔和调节孔,稳定在第一、二、三水平墩上并保持水平状态,让第一磁性件、第二磁性件与穿孔杆侧壁相吸,第三磁性件与第四磁性件相吸,以快速固定穿孔杆,实现有效提高挂模效率的效果。

This application discloses a formwork hanging structure for post-cast strips of T-beams, relating to the field of building construction technology. It aims to solve the problem of low construction efficiency caused by the time-consuming and labor-intensive method of fixing the formwork with bolts when hanging formwork for post-cast strips of T-beams. The key technical point is that when formwork hanging is required, firstly, supports, support plates, and uprights are erected at the post-cast strip. The length of the upright inserted into the support plate is adjusted according to the formwork hanging height. Then, the manual adjustment rod is pulled, causing the perforated rod to pass through the positioning hole and adjustment hole in sequence, stabilizing it on the first, second, and third horizontal supports and maintaining a horizontal state. The first and second magnetic components attract the sidewall of the perforated rod, and the third and fourth magnetic components attract each other, quickly fixing the perforated rod and effectively improving the efficiency of formwork hanging.

Description

T roof beam post-cast strip hangs mould structure
Technical Field
The application relates to the technical field of building construction, in particular to a T-beam post-pouring belt hanging die structure.
Background
The post-cast strip is used for preventing harmful cracks of cast-in-situ reinforced concrete structures due to uneven temperature and shrinkage in building construction, temporary construction joints are reserved at corresponding positions of foundation slabs, walls and beams according to design or construction specification requirements, the structures are temporarily divided into a plurality of parts, the structures are internally shrunk by members, concrete is poured and smashed at the construction joints after a plurality of times, the structures are connected into a whole, and the hanging die is a main die plate which is suspended in the air without lower support and can be fixed in various modes.
In the actual construction process, a plurality of construction units are not formed into an independent formwork system at the post-pouring zone, the construction units usually open holes in the supporting plate, one end of the steel pipe is connected with the formwork, the other end of the steel pipe penetrates through the supporting plate, the height is adjusted, the steel pipe and the supporting plate are fixed through bolting, and the bolts are required to be manually unscrewed when the steel pipe is dismounted.
However, when facing a large number of T-beam post-cast strip casting projects, it takes a great deal of time to screw bolts, both for installation and removal, affecting the construction efficiency, and therefore, needs to be improved.
Disclosure of utility model
The application aims to provide a T-beam post-pouring belt hanging die structure so as to solve the problem of low T-beam post-pouring belt hanging die efficiency.
In order to achieve the above purpose, the present utility model adopts the following technical scheme:
A T-beam post-pouring belt hanging die structure comprises two concrete plates, post-pouring gaps are formed between the two concrete plates, vertical rods are arranged in the post-pouring gaps along the up-down direction, sleeve rods are sleeved on the vertical rods, the upper ends of the vertical rods are connected with supporting plates, mounting holes for the vertical rods to be inserted are formed in the supporting plates in a penetrating mode, two ends of the supporting plates are located above the concrete plates, buttresses propped against the upper surfaces of the corresponding concrete plates are respectively arranged at two ends of the supporting plates, adjusting holes are formed in the vertical rods in a penetrating mode, templates for blocking the post-pouring gaps are arranged at the lower ends of the vertical rods, and perforating rods propped against the upper surfaces of the supporting plates are arranged in the adjusting holes in a penetrating mode.
Through adopting above-mentioned technical scheme, when needs carry out the hanging die to T roof beam post-cast strip, as long as set up buttress and backup pad, cup joint the sleeve pipe and connect the template in the pole setting lower extreme and with the inserted mounting hole of pole setting, adjust pole setting height, pass the regulation hole that corresponds the height with the perforating rod, just can reach the purpose of quick fixed pole setting to realize promoting the effect of T roof beam post-cast strip hanging die efficiency.
Further, one end of the perforating rod is provided with an operation box, and one end of the operation box, which is close to the vertical rod, is provided with a positioning hole for inserting the perforating rod into the operation box.
Through adopting above-mentioned technical scheme, the one end of perforating rod passes the locating hole, gets into in the operation box, and the operation box deposits the perforating rod as the container, makes its difficult emergence of in the use lost the condition.
Further, the upper surface of the operation box is provided with a square groove, and one end of the perforating rod inserted into the positioning hole is provided with a hand adjusting rod in the square groove.
Through adopting above-mentioned technical scheme, square groove is convenient for the operation personnel use the perforating rod in the operation box, and the hand pole links to each other with the perforating rod, and the operation personnel can be directly through removing the hand pole and control the perforating rod position.
Further, the hand adjusting rod is provided with a protective sleeve at one end far away from the connecting rod.
Through adopting above-mentioned technical scheme, when using the hand pole of adjusting, the lag can make things convenient for the operation personnel to hold, plays anti-skidding effect simultaneously.
Further, the inner side wall of the square groove is provided with a first magnetic piece, and the inner side wall of the square groove, which is close to one end of the positioning hole, is provided with a second magnetic piece.
Through adopting above-mentioned technical scheme, when using or idle perforating rod, the iron perforating rod in square inslot can inhale with the first magnetic part in the square inslot and second magnetic part mutually, plays the effect of fixed perforating rod, prevents that unexpected emergence from moving.
Further, the upper surface of the supporting plate is provided with a first horizontal pier and a second horizontal pier on two sides of the vertical rod respectively, and the lower surface of the inside of the operation box is provided with a third horizontal pier.
Through adopting above-mentioned technical scheme, after the adjustment has been done the perforating rod position, place the perforating rod on first, second and third horizontal mound, each horizontal mound upper surface height is the same, under the mutually supporting, makes the perforating rod keep the state of horizontal placement.
Further, the perforating rod is provided with a third magnetic part at one end far away from the manual adjusting rod, and a fourth magnetic part attracted with the third magnetic part is arranged on one side, far away from the operation box, of the vertical rod, on the upper surface of the supporting plate.
Through adopting above-mentioned technical scheme, when the perforation pole passed regulation hole and one end on first horizontal mound, the third magnetic part on the perforation pipe can attract each other with the fourth magnetic part in the backup pad, plays the effect of firm perforation pole.
Further, the fifth magnetic pieces are arranged at the two ends of the square groove in a protruding mode in the width direction, a box cover is arranged on the upper surface of the square groove, the lower surface of the box cover abuts against the upper surface of the fifth magnetic pieces, and a handle is arranged on the upper surface of the box cover.
Through adopting above-mentioned technical scheme, when working personnel make after the hanging die work or the perforating rod is retrieved in the operation box, can be with lid income square groove, iron lid and fifth magnetic part inhale mutually, play dustproof rainproof effect, the handle design makes things convenient for the operating personnel to take the lid.
In summary, the present application includes at least one of the following beneficial technical effects:
1. The height of the hanging die can be flexibly adjusted by moving the upright rod up and down through the adjusting holes on the upright rod, and the perforated rod penetrates through the adjusting holes, so that the quick fixing is realized, a plurality of groups of magnetic components are matched, the perforated rod is stabilized, and the deviation is avoided;
2. One end of the perforating rod is provided with an operation box, and the position of the perforating rod can be controlled by directly moving the manual adjusting rod in the operation box, so that the perforating rod is convenient for operators to use.
Drawings
Fig. 1 is a schematic structural view showing the connection relationship among a support plate, a vertical rod, a buttress, a perforated pipe and a template in the embodiment.
Fig. 2 is an enlarged view of a portion a in fig. 1.
Fig. 3 is a schematic structural view for embodying the connection relationship between the parts inside the operation box in the embodiment.
In the figure, 1, a supporting plate, 2, a vertical rod, 3, a buttress, 4, an adjusting hole, 5, a perforating rod, 6, an operation box, 7, a square groove, 8, a positioning hole, 9, a first horizontal pier, 10, a concrete slab, 11, a hand adjusting rod, 12, a template, 13, a protective sleeve, 14, a first magnetic piece, 15, a second magnetic piece, 16, a second horizontal pier, 17, a third magnetic piece, 18, a fourth magnetic piece, 19, a fifth magnetic piece, 20, a box cover, 21, a handle, 22, a third horizontal pier, 23, a post-pouring gap, 24, a sleeve rod, 25 and a mounting hole.
Detailed Description
The present application will be described in further detail with reference to the accompanying drawings.
Examples:
Referring to fig. 1, a T-beam post-pouring strip hanging die structure comprises two concrete plates 10, a post-pouring gap 23 is formed between the two concrete plates 10, a vertical rod 2 is arranged in the post-pouring gap 23 along the up-down direction, the vertical rod 2 is sleeved with a sleeve rod 24, the upper end of the vertical rod 2 is connected with a support plate 1, the support plate 1 is provided with mounting holes 25 for inserting the vertical rod 2 in a penetrating manner, two ends of the support plate 1 are positioned above the concrete plates 10, each support plate is provided with a buttress 3 propped against the upper surface of the corresponding concrete plate 10, the support plate 1 is connected with the buttress 3 in a bolt connection manner, the vertical rod 2 is provided with an adjusting hole 4 in a penetrating rod 5 propped against the upper surface of the support plate 1 in a penetrating manner, and the penetrating rod 5 is made of iron and steel materials capable of being adsorbed by magnets.
Referring to fig. 3, an operation box 6 is disposed at one end of the perforated rod 5, a positioning hole 8 for inserting the perforated rod 5 into the operation box 6 is disposed at one end of the operation box 6 close to the upright rod 2, and the perforated rod 5 is disposed in the operation box 6, so that the perforated rod 5 can be prevented from moving or losing during use.
Referring to fig. 1 and 3, the upper surface of the operation box 6 is provided with a square groove 7, one end of the perforated rod 5 inserted into the positioning hole 8 is provided with a hand adjusting rod 11 in the square groove 7, and the perforated rod 5 and the hand adjusting rod 11 are connected in a welding manner.
Referring to fig. 3, the hand adjusting rod 11 is provided with a protective sleeve 13 at one end far away from the perforated rod 5, and the protective sleeve 13 is made of rubber material and mainly plays a role in protection and skid resistance.
Referring to fig. 3, the inner side wall of the square groove 7 is provided with a first magnetic member 14, the inner side wall of the square groove 7 near one end of the positioning hole 8 is provided with a second magnetic member 15, and the first magnetic member 14 and the second magnetic member 15 are both magnets and can attract the perforated rod 5.
Referring to fig. 1, 2 and 3, the upper surface of the support plate 1 is provided with a first horizontal pier 9 and a second horizontal pier 16 at both sides of the upright 2, the lower surface inside the operation box 6 is provided with a third horizontal pier 22, the first horizontal pier 9, the second horizontal pier 16 and the third horizontal pier 22 are connected with the support plate 1 in a threaded connection mode, and the surfaces of the three are at the same height, so that when the perforated rod 5 is placed on the first horizontal pier 9, the second horizontal pier 16 and the third horizontal pier 22, the horizontal state is maintained.
Referring to fig. 1 and 2, the perforated rod 5 is provided with a third magnetic member 17 at one end far from the manual adjusting rod 11, a fourth magnetic member 18 attracted to the third magnetic member 17 is provided on the upper surface of the support plate 1 at the side of the upright rod 2 far from the operation box 6, the third magnetic member 17 and the fourth magnetic member 18 are magnets, and the third magnetic member 17 and the fourth magnetic member 18 are attracted to each other.
Referring to fig. 1 and 3, fifth magnetic members 19 are arranged at two ends of the square groove 7 in a protruding manner along the width direction, the fifth magnetic members 19 are magnets, a box cover 20 is arranged on the upper surface of the square groove 7, the box cover 20 is made of iron and steel materials which can be attracted by the magnets, a lifting handle 21 is arranged on the upper surface of the box cover 20 in a welding manner after the box cover 20 is covered, and the lower surface of the box cover 20 abuts against the upper surface of the fifth magnetic members 19.
The implementation principle of the embodiment of the application is as follows:
When the device is used, firstly, the supporting plate 1 and the buttress 3 are assembled, the upright rod 2 is sleeved with the sleeve rod 24 and is connected with the template 12, then the upright rod 2 passes through the mounting hole 25, the height of the upright rod 2 is adjusted, then the protective sleeve 13 of the hand adjusting rod 11 is held in the square groove 7, the perforated rod 5 sequentially passes through the positioning hole 8 and the adjusting hole 4 with the corresponding height, the perforated pipes are lapped on the first horizontal pier 9, the second horizontal pier 16 and the third horizontal pier 22, the first magnetic part 14 and the second magnetic part 15 are guaranteed to be attracted with part of the perforated rod 5 in the operation box 6, the third magnetic part 17 is guaranteed to be attracted with the fourth magnetic part 18, the perforated rod 5 is guaranteed to be horizontally fixed, and finally the box cover 20 is covered on the square groove 7, so that the next construction operation can be performed, and the die hanging efficiency is effectively improved through the rapid fixed design.
The embodiments of the present application are all preferred embodiments of the present application, and are not intended to limit the scope of the present application, wherein like reference numerals are used to refer to like elements throughout. Therefore, all equivalent changes according to the structure, shape and principle of the present application should be covered in the protection scope of the present application.

Claims (8)

1. A T-beam post-pouring belt hanging die structure comprises two concrete plates (10), wherein a post-pouring gap (23) is formed between the two concrete plates (10), the T-beam post-pouring belt hanging die structure is characterized in that vertical rods (2) are arranged in the post-pouring gap (23) along the up-down direction, loop bars (24) are sleeved on the vertical rods (2), the upper ends of the vertical rods (2) are connected with supporting plates (1), mounting holes (25) for inserting the vertical rods (2) are formed in the supporting plates (1) in a penetrating mode, two ends of the supporting plates (1) are located above the concrete plates (10), buttresses (3) propped against the upper surfaces of the corresponding concrete plates (10) are respectively arranged at two ends of the supporting plates (1), adjusting holes (4) are formed in the penetrating mode, the lower ends of the vertical rods (2) are provided with templates (12) for blocking the post-pouring gap (23), and through holes (5) propped against the upper surfaces of the supporting plates (1) are formed in the adjusting holes (4).
2. The T-beam post-pouring strip hanging die structure according to claim 1, wherein an operation box (6) is arranged at one end of the perforating rod (5), and a positioning hole (8) for inserting the perforating rod (5) into the operation box (6) is formed in one end, close to the vertical rod (2), of the operation box (6).
3. The T-beam post-pouring strip hanging die structure according to claim 2, wherein a square groove (7) is formed in the upper surface of the operation box (6), and a hand adjusting rod (11) is arranged in the square groove (7) at one end of the perforating rod (5) inserted into the positioning hole (8).
4. The T-beam post-pouring strip hanging die structure according to claim 3, wherein the hand adjusting rod (11) is provided with a protective sleeve (13) at one end far away from the perforating rod (5).
5. The T-beam post-pouring strip hanging die structure according to claim 3, wherein the inner side wall of the square groove (7) is provided with a first magnetic piece (14), and the inner side wall of the square groove (7) close to one end of the positioning hole (8) is provided with a second magnetic piece (15).
6. The T-beam post-pouring strip hanging die structure according to claim 2, wherein the upper surface of the supporting plate (1) is provided with a first horizontal pier (9) and a second horizontal pier (16) respectively on two sides of the vertical rod (2), and the lower surface of the inner part of the operating box (6) is provided with a third horizontal pier (22).
7. The T-beam post-pouring strip hanging die structure according to claim 4, wherein the perforated rod (5) is provided with a third magnetic piece (17) at one end far away from the hand adjusting rod (11), and a fourth magnetic piece (18) attracted with the third magnetic piece (17) is arranged on one side, far away from the operating box (6), of the upright rod (2) on the upper surface of the supporting plate (1).
8. The T beam post-pouring strip hanging die structure according to claim 3, wherein fifth magnetic pieces (19) are arranged at two ends of the square groove (7) in a protruding mode in the width direction, a box cover (20) is arranged on the upper surface of the square groove (7), the lower surface of the box cover (20) abuts against the upper surface of the fifth magnetic pieces (19), and a lifting handle (21) is arranged on the upper surface of the box cover (20).
CN202423078347.6U 2024-12-13 2024-12-13 T roof beam post-cast strip hangs mould structure Active CN223937634U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202423078347.6U CN223937634U (en) 2024-12-13 2024-12-13 T roof beam post-cast strip hangs mould structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202423078347.6U CN223937634U (en) 2024-12-13 2024-12-13 T roof beam post-cast strip hangs mould structure

Publications (1)

Publication Number Publication Date
CN223937634U true CN223937634U (en) 2026-02-24

Family

ID=98819203

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202423078347.6U Active CN223937634U (en) 2024-12-13 2024-12-13 T roof beam post-cast strip hangs mould structure

Country Status (1)

Country Link
CN (1) CN223937634U (en)

Similar Documents

Publication Publication Date Title
CN108505645B (en) CL composite concrete shear wall cast-in-place construction method
CN114482529A (en) Back-jacking construction method for post-cast strip galvanized steel pipe support frame
CN111113628B (en) Construction method of spray prefabricated T beam
JP2000320142A (en) Rebar assembling apparatus and its rebar assembling method in building construction
CN210396134U (en) Reinforcing tool for controlling horizontal joint quality of shear wall
CN111663770B (en) Quick and easy combination and shaping mold for post-cast strip of cast-in-place slab and construction method of quick and easy combination and shaping mold
CN109797969B (en) Construction method of post-cast strip tool type advanced formwork lifting system
CN110424722B (en) Integral assembly of large formwork narrow space wall and construction method
CN210636798U (en) Climbing formwork applied to vertical walls and frame columns in corner sections of wind tunnels
CN104878926A (en) Suspended template system construction method and turnover brackets
CN114561873A (en) Bridge high pier construction method
CN220285305U (en) Adjustable seam unilateral template reinforcing system
JP5437876B2 (en) Method of dismantling and removing support members in the construction process of RC RC ramen structure viaduct
CN218255748U (en) Hogging moment stretch-draw working hole template for precast box girder top plate
CN216276900U (en) Expansion joint steel formwork capable of being constructed on same floor
CN110284716A (en) The construction method of the lifter plate node structure of steel bar truss floor support plate
CN213806724U (en) A beam enlargement and reinforcement device for reconstruction projects
CN211736387U (en) Expansion joint formwork supporting tool
CN115681620A (en) Method for installing bearing embedded part of comprehensive support
CN114673174A (en) Formwork supporting device for anchor beam pouring construction and construction method
CN112962960B (en) Early formwork stripping support system of coincide floor rigid coupling independent stay
CN222667263U (en) Mounting structure of full-assembled floor and beam
CN222350240U (en) A splicable quick-detachable formwork support structure
CN112523534A (en) Beam enlarging and reinforcing device for reconstruction engineering
CN111809866A (en) Suspended correction fixing formwork supporting method for large steel formwork of concrete shear wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant