CN223722500U - Personnel and material lifting channel for medium-sized wind driven generator - Google Patents

Personnel and material lifting channel for medium-sized wind driven generator

Info

Publication number
CN223722500U
CN223722500U CN202520610791.3U CN202520610791U CN223722500U CN 223722500 U CN223722500 U CN 223722500U CN 202520610791 U CN202520610791 U CN 202520610791U CN 223722500 U CN223722500 U CN 223722500U
Authority
CN
China
Prior art keywords
personnel
medium
hole
rope
winch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202520610791.3U
Other languages
Chinese (zh)
Inventor
耿彪
郝光伟
潘浩
邱莎
郝思杰
王树林
陈京英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengfeng Energy Taiyuan Co ltd
Original Assignee
Chengfeng Energy Taiyuan Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengfeng Energy Taiyuan Co ltd filed Critical Chengfeng Energy Taiyuan Co ltd
Priority to CN202520610791.3U priority Critical patent/CN223722500U/en
Application granted granted Critical
Publication of CN223722500U publication Critical patent/CN223722500U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00—Energy generation through renewable energy sources
    • Y02E10/70—Wind energy
    • Y02E10/72—Wind turbines with rotation axis in wind direction

Landscapes

  • Wind Motors (AREA)

Abstract

The utility model relates to the technical field of wind driven generators, and aims to solve the technical problem that a nacelle cannot be accessed from a tower. In order to solve the technical problems, the utility model provides a personnel and material lifting channel for a medium-sized wind driven generator. The utility model comprises a tower, a cabin, a first winch, an openable access door, a first through hole and a second through hole, wherein the cabin is connected to the top of the tower, the first winch is arranged in the tail end of the cabin, the bottom of the cabin is provided with the openable access door, the first through hole and the second through hole, a steel wire rope of the first winch passes through the first through hole and vertically downwards, a hoisting piece is connected to the end part of the steel wire rope, the hoisting piece is used for hoisting personnel or materials and wearing safety belts, a life wire rope is arranged parallel to the steel wire rope, one end of the life wire rope is connected with the top end of the cabin, the other end of the life wire rope passes through the second through hole and is connected with the ground, and the safety belt is connected with the life wire rope. The utility model is convenient for personnel and large materials to enter the cabin, and improves the safety performance.

Description

Personnel and material lifting channel for medium-sized wind driven generator
Technical Field
The utility model relates to the technical field of wind driven generators, in particular to a personnel and material lifting channel for a medium-sized wind driven generator.
Background
The wind driven generator is an electric power device which converts wind energy into mechanical work and drives a rotor to rotate and finally outputs alternating current. The wind driven generator drives the windmill blades to rotate by utilizing wind power, and the rotating speed is increased through a speed increaser so as to promote the generator to generate electricity. According to the current wind power generator technology, the generation of electricity can be started at a breeze speed (breeze degree) of about three meters per second.
When the prior art needs to be maintained and overhauled, the material mainly enters the engine room through the tower, but the maintenance and overhauling materials of the medium-sized wind driven generator are relatively large, so that the material cannot enter the engine room from the tower. Therefore, a lifting channel is required to be designed so that transportation personnel and materials can be maintained and overhauled.
Disclosure of utility model
The technical problem to be solved by the present utility model is to overcome the above problems in the prior art.
In order to solve the technical problems, the utility model provides a personnel and material lifting channel for a medium-sized wind driven generator, which comprises the following components:
A tower;
The device comprises a tower, a cabin, a first winch, a second winch, a first through hole and a second through hole, wherein the top of the tower is connected with the cabin;
The hoisting piece is connected to the end part of the steel wire rope and is used for hoisting personnel or materials, and the personnel wear safety belts;
The life line rope is arranged parallel to the steel wire rope, one end of the life line rope is connected with the top end of the cabin, and the other end of the life line rope penetrates through a second through hole to be connected with the ground;
Wherein the safety belt is connected with the life rope.
In one embodiment of the utility model, the utility model further comprises a mobile fall arrestor, through which the safety belt is connected to the lifeline cable.
In one embodiment of the utility model, the top end of the lifeline rope is connected with a second winch, the second winch is connected with the engine room, the lifeline rope is in a working state, and the lifeline rope is not wound on the second winch.
In one embodiment of the utility model, a limiting member is provided in the lower surface of the nacelle at a position close to the first through hole for limiting the lifting stroke of the lifting member.
In one embodiment of the utility model, a limiting member is also provided in the lower surface of the nacelle at a position close to the second through hole for limiting the ascending travel of the bottom end of the life rope.
In one embodiment of the utility model, the utility model further comprises a control part, wherein the control part is electrically connected with the first winch.
In one embodiment of the present utility model, the present utility model further comprises a remote control connected to the control section.
In one embodiment of the utility model, the lifting member is used for lifting personnel, through which the lifeline rope passes.
In one embodiment of the utility model, the access door is opened to the cabin interior.
In one embodiment of the utility model, the end part of the steel wire rope is provided with a lifting hook, the top of the lifting piece is provided with a lifting ring, and the lifting hook is hung on the lifting ring and is mutually locked.
In one embodiment of the utility model, the bottom end of the lifeline rope is secured to the ground by an earth anchor.
Compared with the prior art, the technical scheme of the utility model has the following advantages:
The personnel and material lifting channel for the medium-sized wind driven generator is provided with the first winch on the engine room, so that personnel and materials are lifted through the first winch, equipment in the engine room is convenient to maintain, and the life line rope is also arranged to protect when the personnel and the materials are lifted, so that the safety performance is improved.
Drawings
In order that the utility model may be more readily understood, a more particular description of the utility model will be rendered by reference to specific embodiments thereof which are illustrated in the appended drawings, in which:
FIG. 1 is a schematic view of a personnel and material lifting path for a medium-sized wind turbine according to a preferred embodiment of the present utility model;
FIG. 2 is an enlarged view of the personnel and material lift path A for the medium wind turbine of FIG. 1;
FIG. 3 is a top view of the interior of the nacelle in the personnel and materials lift path for the medium wind turbine of FIG. 1;
The reference numerals of the specification indicate 100, tower;
200. The engine room comprises a cabin, a first winch, 211, a steel wire rope, 220, an access door, 230, a first through hole, 240, a second through hole, 250, a second winch, 260, a limiting part, 270, a hinge, 280 and a lock;
300. a lifting member 310, a safety belt;
400. A lifeline cord;
500. an earth anchor;
600. a lifting hook;
700. A hanging ring;
800. and moving the falling protector.
Detailed Description
The present utility model will be further described with reference to the accompanying drawings and specific examples, which are not intended to be limiting, so that those skilled in the art will better understand the utility model and practice it.
Referring to fig. 1 to 3, an embodiment of the present utility model provides a personnel and material lifting channel for a medium-sized wind turbine, including:
A tower 100;
the nacelle 200 is connected to the top of the tower 100, a first winch 210 is arranged in the tail end of the nacelle 200, and an openable access door 220, a first through hole 230 and a second through hole 240 are arranged at the bottom of the nacelle 200, and a steel wire rope 211 of the first winch 210 passes through the first through hole 230 and vertically downwards;
The lifting device 300 is connected to the end of the steel wire rope 211, the lifting device 300 is used for lifting personnel or materials, the personnel wear safety belts 310, the lifting device 300 is a hanging basket when the personnel are lifted, and the lifting device 300 is a lifting rope when the materials are lifted.
The lifeline rope 400 is arranged parallel to the steel wire rope 211, one end of the lifeline rope 400 is connected with the top end of the nacelle 200, the other end of the lifeline rope 400 passes through a second through hole 240 to be connected with the ground, and the bottom end of the lifeline rope 400 is fixed on the ground through a ground anchor 500.
Wherein the harness is connected to the lifeline cable 400.
Specifically, the application is provided with the first winch 210 on the cabin, thereby lifting personnel and materials through the first winch 210, facilitating the personnel and large materials to enter the cabin, and in addition, the application is provided with the life line rope 400 for protecting when lifting the personnel and materials, thereby improving the safety performance.
The application has simple structure, high safety performance and low cost.
Further, the present application further includes a moving fall arrestor 800, and the safety belt is connected to the lifeline rope 400 through the moving fall arrestor 800. Specifically, the movable fall arrestor 800 can protect personnel or materials when the personnel or materials are lifted, so that safety is improved.
Further, a second hoist 250 is connected to the top end of the lifeline rope 400, the second hoist 250 is connected to the nacelle 200, the lifeline rope 400 is in a working state, and the lifeline rope 400 is not wound on the second hoist 250. Specifically, the second winding machine 250 provided in the present embodiment can wind the lifeline rope 400 when not in operation, saving space, and improving the service life. In addition, ensuring that the lifeline rope 400 is not wound on the second winch 250 in the operating state can prevent the second winch 250 from operating to affect safety due to a fault abnormality in the operating state.
Further, a stopper 260 for restricting the ascending stroke of the hoist 300 is provided at a position near the first through hole 230 in the lower surface of the nacelle 200. For example, the limiting member 260 may be a distance sensor. A part of the distance sensor is provided at the top of the hoist 300 and the other end is provided at the lower surface of the nacelle 200, so that the distance of the top of the hoist 300 from the lower surface of the nacelle 200 can be measured. When the distance measured by the distance sensor is smaller than the set distance, the first hoist 210 stops operating. As another example, the stop member 260 is a hook stop. The lifting hook limiter has the advantages that the lifting hook limiter can limit the lifting height, when the lifting hook is lifted to the upper limit position, the lifting mechanism is limited to stop running, the position avoiding device can automatically cut off the power supply, and the lifting hook is prevented from continuously lifting and breaking the steel wire rope to cause a falling accident. Limiting the descending depth, namely automatically cutting off the power supply by the limiter when the object taking device descends to the lowest position to stop the mechanism, ensuring that the steel wire rope has enough winding turns on the winding drum, and increasing the safety. The safety is improved, two sets of lifting limit position limiters are arranged for lifting hot metal or inflammable and explosive dangerous goods, and the lifting limit position limiters act sequentially, and different structure forms and different circuit breaking devices are controlled, so that the safety is improved. Specifically, the present embodiment can limit the lifting stroke of the lifting member 300, and avoid the collision of the over-stroke with the nacelle 200 when the lifting member 300 is lifted.
Further, a limiting member 260 is also provided in the lower surface of the nacelle 200 at a position close to the second through hole 240 for limiting the ascending stroke of the bottom end of the lifeline rope 400. Specifically, the limiting member 260 provided in the present embodiment can limit the ascending travel of the bottom end of the lifeline rope 400, and avoid the bottom end of the lifeline rope 400 from being retracted into the nacelle 200 for travel when the second winch 250 is retracted into the lifeline rope 400. After a period of time, there may be misalignment of the lifeline rope 400 with the second through hole 240, and the bottom end of the lifeline rope 400 may not pass through the second through hole 240 normally when the lifeline rope 400 is put down, resulting in failure of the lifeline rope 400 to be put down.
Further, the application also comprises a control part, wherein the control part is electrically connected with the first winch 210, the second winch 250, the heavy hammer and the limiting part 260. Specifically, the present embodiment can control the lifting of the lifting piece 300 by the control portion. The control unit can also control the retraction of the lifeline rope 400. In addition, the control part can control the first hoist 210 and the second hoist 250 to timely make feedback according to the signals collected by the weight and the limiting part 260, thereby realizing automatic control.
Further, the application also comprises a remote control, and the remote control is connected with the control part. In particular, the embodiment can be controlled remotely by a remote control, and is more convenient to use.
Further, in the case where the hoist 300 is used to hoist a person, the lifeline rope 400 passes through the hoist 300. Specifically, the lifeline rope 400 of the embodiment can perform a guiding function through the lifting member 300, thereby preventing the lifting member 300 from swinging left and right in the ascending and descending process, and ensuring the reliability and safety of operation.
Further, the access door 220 is opened to the interior of the nacelle 200. The access door 220 is connected with the bottom of the cabin 200 through a hinge 270, a lock 280 is arranged on the access door 220, and the lock 280 realizes locking of the access door 220 and the cabin 200.
Further, a hanging hook 600 is arranged at the end part of the steel wire rope 211, a hanging ring 700 is arranged at the top of the hanging piece 300, and the hanging hook 600 is hung on the hanging ring 700 and locked with each other. Specifically, the quick butt joint and the disassembly and assembly of the steel wire rope 211 and the lifting piece 300 can be realized quickly, and the locking of the lifting hook 600 and the lifting ring 700 can be realized through the lock 280 in the operation process, so that the safety accident caused by the separation of the lifting hook 600 and the lifting ring 700 when people and materials are lifted is avoided. Therefore, the application has the advantages of simple structure, rapid operation and high safety.
It is apparent that the above examples are given by way of illustration only and are not limiting of the embodiments. Other variations and modifications of the present utility model will be apparent to those of ordinary skill in the art in light of the foregoing description. It is not necessary here nor is it exhaustive of all embodiments. While still being apparent from variations or modifications that may be made by those skilled in the art are within the scope of the utility model.

Claims (10)

1.一种用于中型风力发电机的人员与物料升降通道,其特征在于:包括:1. A personnel and material lifting channel for a medium-sized wind turbine, characterized in that it comprises: 塔筒;Tower; 机舱,连接在所述塔筒的顶部;所述机舱尾端的内部设有第一卷扬机;所述机舱的底部设有可开启的检修门、第一通孔和第二通孔,所述第一卷扬机的钢丝绳穿过一所述第一通孔垂直向下;The nacelle is connected to the top of the tower; a first winch is provided inside the rear end of the nacelle; the bottom of the nacelle is provided with an openable maintenance door, a first through hole and a second through hole, and the wire rope of the first winch passes through the first through hole and hangs vertically downward. 吊装件,连接在所述钢丝绳的端部;所述吊装件用于起吊人员或物料,所述人员佩戴有安全带;A lifting device is attached to the end of the wire rope; the lifting device is used to lift personnel or materials, and the personnel are wearing safety belts; 生命线绳索,平行于所述钢丝绳设置;所述生命线绳索的一端与所述机舱的顶端连接、另一端穿过一所述第二通孔与地面连接;A lifeline rope is installed parallel to the steel wire rope; one end of the lifeline rope is connected to the top of the cabin, and the other end passes through a second through hole and is connected to the ground; 其中,所述安全带与所述生命线绳索连接。The safety belt is connected to the lifeline rope. 2.根据权利要求1所述的用于中型风力发电机的人员与物料升降通道,其特征在于:还包括移动止坠器,所述安全带与所述生命线绳索通过所述移动止坠器连接。2. The personnel and material lifting channel for a medium-sized wind turbine according to claim 1, characterized in that: it further includes a movable fall arrester, and the safety belt and the lifeline rope are connected through the movable fall arrester. 3.根据权利要求1所述的用于中型风力发电机的人员与物料升降通道,其特征在于:所述生命线绳索的顶端连接有第二卷扬机,所述第二卷扬机与所述机舱连接;所述生命线绳索处于工作状态,所述第二卷扬机上未绕设所述生命线绳索。3. The personnel and material lifting channel for a medium-sized wind turbine according to claim 1, characterized in that: a second winch is connected to the top end of the lifeline rope, and the second winch is connected to the nacelle; the lifeline rope is in working condition, and the lifeline rope is not wound on the second winch. 4.根据权利要求1所述的用于中型风力发电机的人员与物料升降通道,其特征在于:所述机舱的下表面中靠近所述第一通孔的位置处设有限位部件,用于限制所述吊装件的上升行程。4. The personnel and material lifting channel for a medium-sized wind turbine according to claim 1, characterized in that: a limiting component is provided on the lower surface of the nacelle near the first through hole to limit the upward stroke of the hoisting component. 5.根据权利要求1所述的用于中型风力发电机的人员与物料升降通道,其特征在于:所述机舱的下表面中靠近所述第二通孔的位置处也设有限位部件,用于限制所述生命线绳索底端的上升行程。5. The personnel and material lifting channel for a medium-sized wind turbine according to claim 1, characterized in that: a limiting component is also provided on the lower surface of the nacelle near the second through hole to limit the upward stroke of the bottom end of the lifeline rope. 6.根据权利要求1所述的用于中型风力发电机的人员与物料升降通道,其特征在于:还包括控制部;所述控制部与所述第一卷扬机电性连接。6. The personnel and material lifting channel for a medium-sized wind turbine according to claim 1, characterized in that: it further includes a control unit; the control unit is electrically connected to the first winch. 7.根据权利要求6所述的用于中型风力发电机的人员与物料升降通道,其特征在于:还包括遥控,所述遥控与所述控制部连接。7. The personnel and material lifting channel for a medium-sized wind turbine according to claim 6, characterized in that: it further includes a remote control, wherein the remote control is connected to the control unit. 8.根据权利要求6所述的用于中型风力发电机的人员与物料升降通道,其特征在于:所述吊装件用于起吊人员的情况下,所述生命线绳索穿过所述吊装件。8. The personnel and material lifting channel for a medium-sized wind turbine according to claim 6, characterized in that: when the hoisting component is used to lift personnel, the lifeline rope passes through the hoisting component. 9.根据权利要求1所述的用于中型风力发电机的人员与物料升降通道,其特征在于:所述检修门向所述机舱内部开启。9. The personnel and material lifting passage for a medium-sized wind turbine according to claim 1, characterized in that: the maintenance door opens into the nacelle. 10.根据权利要求1所述的用于中型风力发电机的人员与物料升降通道,其特征在于:所述钢丝绳的端部设有吊钩,所述吊装件的顶部设有吊环;所述吊钩挂设在所述吊环上且相互锁定。10. The personnel and material lifting channel for a medium-sized wind turbine according to claim 1, characterized in that: the end of the wire rope is provided with a hook, and the top of the lifting component is provided with a lifting ring; the hook is hung on the lifting ring and locked to each other.
CN202520610791.3U 2025-04-02 2025-04-02 Personnel and material lifting channel for medium-sized wind driven generator Active CN223722500U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202520610791.3U CN223722500U (en) 2025-04-02 2025-04-02 Personnel and material lifting channel for medium-sized wind driven generator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202520610791.3U CN223722500U (en) 2025-04-02 2025-04-02 Personnel and material lifting channel for medium-sized wind driven generator

Publications (1)

Publication Number Publication Date
CN223722500U true CN223722500U (en) 2025-12-26

Family

ID=98132981

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202520610791.3U Active CN223722500U (en) 2025-04-02 2025-04-02 Personnel and material lifting channel for medium-sized wind driven generator

Country Status (1)

Country Link
CN (1) CN223722500U (en)

Similar Documents

Publication Publication Date Title
CN108452451B (en) Mobile transmission line tower climbing personal safety protection method and device
EP2182202B1 (en) Method of removing an internal yaw drive in a wind turbine tower
CN112441532B (en) Position control system of blade repairing platform of wind generating set
CN101691197A (en) Self-propelled lifter
CN202625760U (en) Overhaul platform used for wind machine blades
CN201980831U (en) Lifting maintenance platform of wind generating set
KR100970393B1 (en) Wind power generator for ascent and descent elevator structure
CN118854875A (en) An offshore wind turbine foundation platform lifting system
EP3026263A1 (en) Arrangement to hoist a wind turbine component
CN209687398U (en) A kind of falling proof device for ladder
CN112796949B (en) Aerial power generation system
CN205838410U (en) Blower fan hoisting mechanism
KR101364614B1 (en) Maintenance of wind power equipment apparatus and method
CN215626034U (en) A retractable elevator system for lattice type large wind turbine support structure
CN101672101A (en) One-drive multi-hoisting-point hoisting system
CN207483225U (en) A kind of wind-proof tower crane of personnel's emergency escape easy to operation
CN220201231U (en) Offshore unmanned platform boarding device with heave compensation function
CN105858403A (en) Device for stabilizing ropes of man-carrying lifting cage in vertical shaft excavating period and application method
CN102344079A (en) Windmill service elevator
CN109969922B (en) Object lifting device, object lifting system and wind generating set
CN217458573U (en) High-safety rotary crane for offshore operation
CN218581149U (en) Building construction lift platform
CN221319206U (en) Lifting device and water turbine draft tube
CN206647074U (en) A kind of self-locking blowout preventer locking device hoistable platform
CN220929097U (en) Opening and closing device of cover plate of lifting opening

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant