CN223293357U - A construction platform installed on a load-bearing beam - Google Patents
A construction platform installed on a load-bearing beamInfo
- Publication number
- CN223293357U CN223293357U CN202422226062.6U CN202422226062U CN223293357U CN 223293357 U CN223293357 U CN 223293357U CN 202422226062 U CN202422226062 U CN 202422226062U CN 223293357 U CN223293357 U CN 223293357U
- Authority
- CN
- China
- Prior art keywords
- frame
- beam column
- motor
- bearing
- construction platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Building Environments (AREA)
Abstract
The utility model discloses a construction platform for installing a spandrel girder, which comprises a climbing device and a beam column outer frame, wherein the climbing device is arranged on the periphery of the beam column outer frame, the climbing device comprises a first frame and a second frame which are symmetrically arranged and are of a semi-surrounding opening structure, a first motor is fixedly arranged on one side of the inner wall of the first frame, a first bearing seat is arranged on the opposite side of the first motor, and a rotating rod is connected between the first motor and the first bearing seat.
Description
Technical Field
The utility model relates to the technical field of building construction, in particular to a construction platform for installing a spandrel girder.
Background
As is well known, building engineering refers to engineering entities formed by the construction of various house buildings and auxiliary facilities thereof and the installation activities of lines, pipelines and equipment matched with the house buildings, wherein the house buildings refer to engineering which has top covers, beam columns, walls and foundations and can form internal spaces so as to meet the production, living, study and public activities of people.
The construction platform is mostly temporarily built by using a tripod or is operated by using a hanging type combined small hanging frame platform in the prior use, so that the construction platform is inconvenient in the process of assembly, a great deal of manpower, material resources and time are required to be consumed, and the process of disassembling the platform after the subsequent completion is also very complicated
Disclosure of utility model
The utility model aims to overcome the defects of the prior art and provide a construction platform for installing a spandrel girder, which can save time and improve work efficiency.
In order to solve the technical problems, the utility model provides the following technical scheme:
The utility model relates to a construction platform for mounting a spandrel girder, which comprises a climbing device and a beam column outer wrapping frame, wherein the climbing device is arranged on the periphery of the beam column outer wrapping frame, the climbing device comprises a first frame and a second frame which are symmetrically arranged, the first frame and the second frame are both of a semi-surrounding opening structure, a first motor is fixedly arranged on one side of the inner wall of the first frame, a first bearing seat is arranged on the opposite side of the first motor, a rotating rod is connected between the first motor and the first bearing seat, the outer end of the rotating rod is fixedly connected with a first gear, both sides of the inner wall of the second frame are provided with a screw rod sliding table, the outer end of the screw rod sliding table is provided with a sliding seat, the sliding seats on both sides are respectively provided with a second motor and a second bearing seat, the outer ends of the rotating rod are fixedly connected with a second gear, the side edges of the sliding seats are connected with hydraulic rods, the top ends of the first frame and the second frame are respectively provided with a working table, the outer edge of a protective rail is respectively provided with a groove opening, the outer wrapping frame is provided with a hollow cavity, the outer wrapping frame is a beam column, the outer wrapping frame is provided with a hollow cavity, and the outer wrapping frame is formed by the outer wrapping the outer toothed column, and the outer wrapping frame is meshed with the outer toothed column, and the outer wrapping frame is arranged along the outer side of the outer wrapping frame.
As a preferable technical scheme of the utility model, the matching surfaces of the first frame and the second frame are provided with matched concave-convex openings, and the bottom ends of the first frame and the second frame are provided with rollers.
As a preferable technical scheme of the utility model, the outer surfaces of the first frame and the second frame are respectively provided with a plurality of reinforcing ribs, the inner corners of the first frame and the second frame are respectively provided with a triangular reinforcing plate, the adjacent parts of the outer surfaces of the first frame and the second frame are respectively provided with a plurality of thread seats, and the thread seats are in locking connection through screws.
As a preferable technical scheme of the utility model, a plurality of butt joint grooves are formed in the inner sides of one ends of the first outer wrapping frame and the second outer wrapping frame, and a plurality of butt joint inserting rods are arranged at the other ends of the first outer wrapping frame and the second outer wrapping frame.
As a preferable technical scheme of the utility model, a plurality of clamping frames are arranged on the outer side surfaces of the first frame and the second frame, limiting blocks are clamped and embedded in the clamping frames, bearing rods are arranged in the limiting blocks, the bottom ends of the bearing rods are connected with bearing columns, a plurality of connecting clamping seats are sleeved at the outer ends of the bearing rods, and a stabilizing rod is connected between the connecting clamping seats.
Compared with the prior art, the utility model has the following beneficial effects:
According to the utility model, the whole platform is more convenient in the installation process by modularized assembly and molding, the time for constructing the platform is greatly shortened, the subsequent disassembly is more convenient, the whole construction progress can be accelerated, meanwhile, the climbing device is stably maintained by meshing the gear with the insection on the surface of the long plate, the whole platform is more stable when being used by matching with a plurality of bearing rods on the periphery, the direct falling accident of the platform can not occur, and the safety is ensured.
Drawings
The accompanying drawings are included to provide a further understanding of the utility model and are incorporated in and constitute a part of this specification, illustrate the utility model and together with the embodiments of the utility model, serve to explain the utility model. In the drawings:
FIG. 1 is a front elevational view of the overall structure of the present utility model;
FIG. 2 is a view of the orientation A-A of FIG. 1 of the present utility model;
FIG. 3 is a B-B oriented view of FIG. 1 of the present utility model;
FIG. 4 is a schematic view of a work surface structure of the present utility model;
FIG. 5 is a schematic view of a beam column outer frame structure according to the present utility model;
FIG. 6 is a second schematic view of the beam column outer frame structure of the present utility model;
1, a climbing device; 2, a beam column outer frame, 3, a first frame, 4, a first motor, 5, a first bearing seat, 6, a first gear, 7, a screw rod sliding table, 8, a sliding seat, 9, a second motor, 10, a second bearing seat, 11, a second gear, 12, a push plate, 13, a hydraulic rod, 14, a working table surface, 15, a first outer frame, 16, a second outer frame, 17, a long plate, 18, a clamping frame, 19, a limiting block, 20, a bearing rod, 21, a bearing column, 22, a connecting clamping seat, 23, a stabilizing rod, 24, a second frame, 151, a butt joint groove, 152 and a butt joint inserting rod.
Detailed Description
The preferred embodiments of the present utility model will be described below with reference to the accompanying drawings, it being understood that the preferred embodiments described herein are for illustration and explanation of the present utility model only, and are not intended to limit the present utility model.
Wherein like reference numerals refer to like elements throughout.
Example 1
As shown in fig. 1-6, the utility model provides a construction platform for installing a bearing beam, which comprises a climbing device 1 and a beam column outer wrapping frame 2, wherein the climbing device 1 is arranged on the periphery of the beam column outer wrapping frame 2, the climbing device 1 comprises a first frame 3 and a second frame 24 which are symmetrically arranged and are of a semi-enclosed opening structure, a first motor 4 is fixedly arranged on one side of the inner wall of the first frame 3, a first bearing seat 5 is arranged on the opposite side of the first motor 4, a rotating rod is connected between the first motor 4 and the first bearing seat 5, the outer end of the rotating rod is fixedly connected with a first gear 6, screw rod sliding tables 7 are respectively arranged on two sides of the inner wall of the second frame 24, sliding seats 8 on two sides are respectively provided with a second motor 9 and a second bearing seat 10, a rotating rod is connected between the second motor 9 and the second bearing seat 10, the outer ends of the rotating rod are fixedly connected with a second gear 11, a push plate 12 is connected to one side of the push plate 12, the top ends of the first frame 3 and the second frame 24 are respectively provided with a first gear 6, the outer wrapping frame 14 is meshed with a second gear column 17, the outer wrapping frame 16 is arranged along the outer wrapping frame 16, the outer wrapping frame 2 is provided with a cavity surface of the second gear column 16, and the outer wrapping frame 16 is meshed with the first gear column 16, and the outer wrapping frame 2 is provided with a cavity surface of the second gear column 17, and the outer wrapping frame 16 is provided with a cavity plate 15, and the outer frame of the outer wrapping frame is a long-shaped gear frame 16.
Further, the mating surfaces of the first frame 3 and the second frame 24 are provided with matched concave-convex openings, and the bottom ends of the first frame 3 and the second frame 24 are provided with rollers.
The outer surfaces of the first frame 3 and the second frame 24 are provided with a plurality of reinforcing ribs, the inner corners of the first frame 3 and the second frame 24 are provided with triangular reinforcing plates, the adjacent parts of the outer surfaces of the first frame 3 and the second frame 24 are provided with a plurality of thread seats, and the thread seats are in locking connection through screws.
A plurality of docking slots 151 are formed inside one end of the first and second outer frames 15 and 16, and a plurality of docking pins 152 are provided at the other ends of the first and second outer frames 15 and 16.
The outside surface of first frame 3 and second frame 24 all is provided with a plurality of card frames 18, and the inside card of card frame 18 has inlayed stopper 19, and the inside of stopper 19 is provided with bearing rod 20, and the bottom of bearing rod 20 is connected with spanners 21, and the outer end cover of bearing rod 20 has connect a plurality of connection cassette 22, is connected with firm pole 23 between the connection cassette 22.
Specifically, during installation, the beam column outer frame 2 is firstly installed on the periphery of a heavy beam column, the first outer frame 15 and the second outer frame 16 are matched, the first outer frame and the second outer frame can be fixedly connected through screw rods or steel beams, the outer frames on the same side are subsequently butted upwards according to the height to be constructed, the butt joint of the upper part and the lower part is completed by vertically inserting the butt joint inserting rod 152 into the butt joint groove 151, and the outer frames which are assembled subsequently are sequentially and fixedly connected according to the previous operation until the height of the beam column outer frame 2 meets the construction height requirement; then the first frame 3 of the climbing device 1 is moved to one side of the second outer wrapping frame 16, the first gear 6 is pressed close to the long plate 17 to be meshed with the insection, meanwhile, the second frame 24 is moved to the other opposite side, after the second frame 24 is butted with the first frame 3, the external threaded seat is connected with the first frame 3 through a screw rod to enable the first frame 3 to be fixedly connected with the second frame 24, then the hydraulic rod 13 is driven, the push plate 12 is pushed to slide forwards on the screw rod sliding table 7 until the second gear 11 is meshed with the gear on the long plate 17, finally the working table 14 is assembled on the first frame 3 and the second frame 24, the stability of the whole structure of the climbing device 1 can be further improved due to the fact that the working table 14 is assembled with the first frame 3 and the second frame 24 in a staggered mode, finally the protective net around the working table 14 is installed, finally the limiting block 19 on the limiting block 20 is assembled with the clamping frame 18, the supporting column 21 at the bottom end of the clamping rod 20 is anchored, finally the stabilizing rod 23 is connected between the reconnecting clamping seat 22 to stabilize the whole motor, finally the first motor 4 and the second gear 9 drive the second gear 9 to roll along the long plate 17, and then drive climbing device to reciprocate, after reaching the construction position, carry out fixed welding or adopt the screw to connect stopper 19 and card frame 18, make climbing device 1 stable in the eminence can, lay connecting plate and protection ladder cage between the table surface 14 of adjacent beam column at last and can use.
It should be noted that the above-mentioned embodiments are merely preferred embodiments of the present utility model, and the present utility model is not limited thereto, but may be modified or substituted for some of the technical features thereof by those skilled in the art. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present utility model should be included in the protection scope of the present utility model.
Claims (5)
1. The utility model provides a construction platform on installation spandrel girder, its characterized in that includes climbing device (1) and beam column outsourcing frame (2), climbing device (1) set up in the periphery of beam column outsourcing frame (2), climbing device (1) are including symmetry are provided with first frame (3) and second frame (24), and are half-surrounding opening structure, the inner wall one side fixed mounting of first frame (3) has first motor (4), first bearing frame (5) are installed to the offside of first motor (4), be connected with the bull stick between first motor (4) and first bearing frame (5), and the outer end fixedly connected with first gear (6) of bull stick, lead screw slip table (7) are all installed to the inner wall both sides of second frame (24), the outer end of lead screw slip table (7) is provided with sliding seat (8), and second motor (9) and second bearing frame (10) are installed respectively to sliding seat (8) both sides, be connected with first bearing frame (12) between second motor (9) and second bearing frame (10), and outer end fixedly connected with bull stick (12) are connected with one side (12), the utility model discloses a beam column outer packing frame, including beam column outer packing frame (2), table surface (14), beam column outer packing frame (2), table surface (14)'s outer border all is provided with the rail guard, and open on the surface has the notch to supply beam column outer packing frame (2) to pass, beam column outer packing frame (2) are six prismatic just inside for cavity structure, beam column outer packing frame (2) are separated into first outer packing frame (15) and second outer packing frame (16) along the axial lead, the median plane of first outer packing frame (15) and second outer packing frame (16) is vertical to be provided with longeron (17), and the surface of longeron (17) is provided with the insection to mesh with first gear (6) and second gear (11).
2. The construction platform for installing the spandrel girder according to claim 1, wherein the opposite joint surfaces of the first frame (3) and the second frame (24) are provided with matched concave-convex openings, and the bottom ends of the first frame (3) and the second frame (24) are provided with rollers.
3. The construction platform for installing the spandrel girder according to claim 2, wherein a plurality of reinforcing ribs are arranged on the outer surfaces of the first frame (3) and the second frame (24), triangular reinforcing plates are arranged at the inner corners of the first frame (3) and the second frame (24), a plurality of thread seats are arranged on the adjacent positions of the outer surfaces of the first frame (3) and the second frame (24), and the thread seats are connected in a locking manner through screws.
4. The construction platform for installing the spandrel girder according to claim 2, wherein a plurality of docking slots (151) are formed inside one end of the first outer casing (15) and the second outer casing (16), and a plurality of docking inserting rods (152) are provided at the other end of the first outer casing (15) and the second outer casing (16).
5. The construction platform on the installation spandrel girder of claim 1, wherein, the outside surface of first frame (3) and second frame (24) all is provided with a plurality of card frame (18), the inside card of card frame (18) is inlayed and is had stopper (19), the inside of stopper (19) is provided with bearing rod (20), the bottom of bearing rod (20) is connected with spandrel post (21), the outer end of bearing rod (20) has cup jointed a plurality of connection cassette (22), be connected with firm pole (23) between connection cassette (22).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202422226062.6U CN223293357U (en) | 2024-09-11 | 2024-09-11 | A construction platform installed on a load-bearing beam |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202422226062.6U CN223293357U (en) | 2024-09-11 | 2024-09-11 | A construction platform installed on a load-bearing beam |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN223293357U true CN223293357U (en) | 2025-09-02 |
Family
ID=96864911
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202422226062.6U Active CN223293357U (en) | 2024-09-11 | 2024-09-11 | A construction platform installed on a load-bearing beam |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN223293357U (en) |
-
2024
- 2024-09-11 CN CN202422226062.6U patent/CN223293357U/en active Active
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN108894315B (en) | Modular building structure building system | |
| CN201809858U (en) | Combined house | |
| CN112681808A (en) | Quick construction honeycomb building suitable for earthquake relief work | |
| CN223293357U (en) | A construction platform installed on a load-bearing beam | |
| CN214884370U (en) | Aluminum alloy supporting beam for movable board house | |
| CN112814149B (en) | Precast concrete member | |
| CN218406477U (en) | Template trolley for integral pouring construction of constructional column and lintel | |
| CN215760665U (en) | Large-span building wavy line roof steel truss mounting structure | |
| CN214574922U (en) | Assembled wall structure | |
| CN111501838B (en) | Prefabricated octagonal cable well and construction method thereof | |
| CN210002544U (en) | A cantilever type aluminum alloy housing base | |
| CN210105358U (en) | Shingle nail with steel shotcrete reinforced structure | |
| CN219863294U (en) | Assembled building frame structure | |
| CN221481456U (en) | Assembled building structure | |
| JP3013244B2 (en) | Formwork cell and formwork apparatus using the same | |
| CN209817161U (en) | Steel construction wall body for light steel house | |
| CN113047439A (en) | Multilayer large-span assembled integral space steel grid building structure | |
| CN220954542U (en) | Can dismantle scalable elevator shaft operation platform structure | |
| CN223549009U (en) | Convenient zero carbon cabin that removes | |
| CN218970557U (en) | Building scaffold with breakage-proof brick structure that drops | |
| CN204001218U (en) | Assembly type beam column linkage | |
| CN222500981U (en) | Pre-installed scaffolding module and supporting scaffolding in building | |
| CN222295255U (en) | Main body structure of assembled purification operating room | |
| CN111155657A (en) | Beam-plate connecting node structure of fabricated framework plate building and connecting method thereof | |
| CN221523948U (en) | Floor board and shear wall corner steel structure for assembled building |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |