CN223176589U - Side cable steel anchor beam temporary positioning support of tower column on A-shaped bridge tower - Google Patents
Side cable steel anchor beam temporary positioning support of tower column on A-shaped bridge towerInfo
- Publication number
- CN223176589U CN223176589U CN202422430601.8U CN202422430601U CN223176589U CN 223176589 U CN223176589 U CN 223176589U CN 202422430601 U CN202422430601 U CN 202422430601U CN 223176589 U CN223176589 U CN 223176589U
- Authority
- CN
- China
- Prior art keywords
- steel anchor
- steel
- tower
- anchor beam
- tops
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The application discloses a side cable steel anchor beam temporary positioning bracket of an upper tower column of an A-shaped bridge tower, which comprises a base and a plurality of support components, wherein the base and the support components are arranged on the side of the top of a folding section, a plurality of upper section tower column concrete surfaces are arranged on tower limbs at the top of the folding section, steel anchor beams are arranged on the tops of the base and the support components, the support components and the steel anchor beams are obliquely arranged layer by layer, each support component comprises four second upright posts arranged on the tops of the steel anchor beams, supporting legs are arranged on the tops of the folding section, the supporting legs at the bottommost are arranged on the tops of the folding section, the rest supporting legs are arranged on the tops of the upper section tower column concrete surfaces of corresponding layers, second bearing beams are arranged on the tops of the four second upright posts and the supporting legs, and steel anchor beams are arranged on the tops of the second bearing beams, so that the heights of the base and the support components can be changed along with the actual needs through the first upright posts, the second upright posts and the supporting legs with optional lengths, and the steel anchor beams on each layer can be changed in height, and the installation is more convenient.
Description
Technical Field
The application relates to the field of bridge construction, in particular to a side cable steel anchor beam temporary positioning bracket of a tower column on an A-shaped bridge tower.
Background
The A-shaped bridge tower is a special bridge structural form and is characterized in that the bridge tower is in the shape of a letter A, the design is usually used for a cable-stayed bridge, the tower top is connected with a bridge deck through a plurality of stay cables to form a stable supporting system, the steel anchor beam is an important component of the A-shaped bridge tower and plays a role in transmitting the gravity of the main beam to the cable tower through the stay cables, and the steel anchor beam needs to be installed by using a temporary positioning bracket during hoisting.
However, in the process of implementing the related technical scheme, the technical problems that the steel anchor beam is divided into a middle cable, a side cable and the like according to the position of a tower column after reaching the site are found, and when the steel anchor beam of the side cable is installed, the temporary positioning brackets of the steel anchor beam are also installed obliquely layer by layer due to the inclined arrangement of the A-shaped bridge tower, and the temporary positioning brackets of the steel anchor beam have certain size, so that the position of the steel anchor beam cannot be changed according to the requirement when being installed, and the installation is inconvenient.
Disclosure of utility model
The application solves the problem that the height cannot be changed during the installation of the steel anchor beam of the side cable in the prior art by providing the side cable steel anchor beam temporary positioning bracket of the tower column on the A-shaped bridge tower, and realizes the effect of changing the height of the temporary positioning bracket according to the requirement so as to change the height position of the steel anchor beam.
The application provides a side cable steel anchor beam temporary positioning bracket of a tower column on an A-shaped bridge tower, which comprises a base and a plurality of support components, wherein the base is arranged on the side of the top of a folding section, a plurality of upper section tower column concrete surfaces are arranged on tower limbs at the top of the folding section, steel anchor beams are arranged at the tops of the base and the support components, the support components and the steel anchor beams are obliquely arranged layer by layer, each support component comprises four second upright posts, the support legs are arranged at the tops of the steel anchor beams, the support legs are arranged at the top of the folding section, the rest support legs are arranged at the tops of the upper section tower column concrete surfaces of corresponding layers, second bearing beams are arranged at the tops of the four second upright posts and the support legs, positioning grooves are formed in four corners of the tops of the steel anchor beams, and the positioning grooves are matched with the second upright posts in size.
Further, a second parallel connection is arranged on the two second upright posts and the supporting legs in the same plane.
Further, positioning grooves are formed in four corners of the top of the steel anchor beam, and the positioning grooves are matched with the second upright in size.
The base comprises four first upright posts, first parallel joints and first spandrel girders, wherein the four first upright posts are arranged on the side of the top of the folding section, the first parallel joints are arranged on the two first upright posts in the same plane, the first spandrel girders are arranged on the tops of the four first upright posts, and one of the steel anchor girders is arranged on the top of the first spandrel girders.
Further, the tops of the first spandrel girder and the plurality of second spandrel girders are respectively provided with a limiting component for installing the steel anchor beams, the limiting components comprise four steel fulcra, limiting steel plates and limiting steel plates, the four steel fulcra are arranged at the tops of the first spandrel girder and the second spandrel girder, the steel anchor beams are arranged at the tops of the four steel fulcra, the limiting steel plates are arranged at the tops of the steel fulcra, and the limiting steel plates are arranged at the outer sides of the steel anchor beams.
Further, two jacks are symmetrically arranged at the tops of the first spandrel girder and the plurality of second spandrel girders, and the tops of the two jacks are in contact connection with the steel anchor beams.
The technical scheme provided by the application has at least the following technical effects or advantages:
Install on folding the section through first stand and first spandrel girder, fix the steel anchor beam of bottommost, make other steel anchor beams can slope setting through the landing leg of second stand and horizontal setting, through first stand, second stand and the landing leg of optional length for the height of base and supporting component can change, make the steel anchor beam of every layer can change the height along with actual need, it is more convenient to install.
Drawings
FIG. 1 is a schematic view of a tower column on an A-shaped bridge tower according to an embodiment of the present application;
FIG. 2 is a schematic view of a base structure according to an embodiment of the present application;
FIG. 3 is a schematic view of a support assembly according to an embodiment of the present application;
FIG. 4 is a schematic structural view of a limiting assembly according to an embodiment of the present application;
The concrete surface of the upper section tower column is 10, the folding section is 20, the base is 30, the supporting component is 40, the steel anchor beam is 50, the locating groove is 60, the limiting component is 70, the limiting component is 31, the first upright post is 32, the first parallel connection is 33, the first spandrel girder is 41, the second upright post is 42, the supporting leg is 43, the second parallel connection is 44, the second spandrel girder is 71, the steel fulcrum is 72, the jack is 73 and the limiting steel plate.
Detailed Description
The embodiment of the application discloses a temporary positioning bracket for a side cable steel anchor beam of a tower column on an A-shaped bridge tower, which enables a steel anchor beam 50 to be obliquely arranged through a second upright column 41 and a transversely arranged supporting leg 42, and enables the length of a base 30 and a supporting component 40 to be changed through a first upright column 31, a second upright column 41 and the supporting leg 42 with optional lengths, and the height position of each layer of steel anchor beam 50 can be changed by jacking up the steel anchor beam 50 with a jack 72, so that the steel anchor beam 50 is convenient to install.
In order to better understand the above technical solutions, the following detailed description will refer to the accompanying drawings and specific embodiments.
Referring to fig. 1, fig. 2 and fig. 3, this embodiment provides a temporary positioning bracket for side cable steel anchor beams of a tower column on an a-shaped bridge tower, including a base 30 and a plurality of support assemblies 40 at the top side of a folding section 10, a plurality of upper segment tower column concrete surfaces 20 are arranged on the tower limb at the top of the folding section 10, steel anchor beams 50 are arranged at the tops of the base 30 and the plurality of support assemblies 40, the plurality of support assemblies 40 and the plurality of steel anchor beams 50 are obliquely arranged layer by layer, the base 30 comprises a first upright 31, a first parallel connection 32 and a first spandrel girder 33, four first upright 31 are arranged at the side of the top of the folding section 10, the first parallel connection 32 is arranged at the top of the four first upright 31 through bolts, one of the steel anchor beams 50 is arranged at the top of the first spandrel girder 33, the two first upright 31 are supported through the first parallel connection 32, the first parallel connection 32 and the first upright 31 are provided with fixed blocks, and the first upright 31 can be fixed in position, and the first spandrel girder 50 can be conveniently fixed, and the number of the first upright 31 can be changed, and the length of the first upright 31 can be conveniently fixed, and the first spandrel girder 50 can be fixed, and the top position can be conveniently changed, and the height can be fixed.
Referring to fig. 1, 2 and 3, the support assembly 40 includes a second upright 41, a supporting leg 42, a second parallel connection 43 and a second spandrel girder 44, four second uprights 41 are disposed at the top of the steel anchor girder 50, locating slots 60 are respectively formed at four corners of the top of the steel anchor girder 50, the locating slots 60 are matched with the second upright 41 in size, the bottom-most supporting leg 42 is disposed at the top of the folding section 10, the rest of the supporting legs 42 are disposed at the top of the upper-section tower column concrete surface 20 of the corresponding layer, the second parallel connection 43 is disposed on two second uprights 41 and supporting legs 42 in the same plane, the second spandrel girder 44 is disposed at the tops of the four second uprights 41 and the supporting legs 42, the tops of the second spandrel girder 44 are provided with steel anchor girders 50, the locating slots 60 are formed in the tops of the steel anchor girder 50 through the second uprights 41, the supporting legs 42 are transversely disposed at one side of the second uprights 41, the horizontal position of the second spandrel girder 44 is changed, the top of the second spandrel girder 44 is changed, and the top of the second spandrel girder 44 is matched with the second parallel connection girder 44 is matched with the supporting leg 42 in height, and the top of the second parallel connection girder 44 is matched with the second upright 41 in height, and the number of the second spandrel girder 42 is changed, and the number of the supporting girders can be changed along with the top of the second parallel connection 41 is matched with the top of the second upright 41.
Referring to fig. 1-4, the tops of the first spandrel girder 33 and the plurality of second spandrel girders 44 are provided with a limiting assembly 70 for installing the steel anchor beam 50, the limiting assembly 70 comprises steel fulcra 71, jacks 72 and limiting steel plates 73, four steel fulcra 71 are arranged at the tops of the first spandrel girder 33 and the second spandrel girder 44, the steel anchor beam 50 is arranged at the tops of the four steel fulcra 71, two jacks 72 are symmetrically arranged at the tops of the first spandrel girder 33 and the plurality of second spandrel girders 44, the tops of the two jacks 72 are in contact connection with the steel anchor beam 50, the limiting steel plates 73 are arranged at the tops of the steel fulcra 71, and the limiting steel plates 73 are arranged at the outer sides of the steel anchor beam 50, so that the steel anchor beam 50 can be lifted on the steel fulcra 71 through the two jacks 72 symmetrically arranged at the bottoms of the steel anchor beam 50, and the height of the steel anchor beam 50 can be accurately moved to a designated height, a inhaul cable can be conveniently carried out, and the limiting steel anchor beam 50 is prevented from moving at the tops of the steel anchor beam 50 through the limiting steel plates 73 at the tops of the steel fulcra 71.
The application can explain its functional principle by the following modes of operation:
During the use, select first stand 31 and the first parallel connection 32 of suitable number of suitable length, install first parallel connection 32 on first stand 31 through the bolt, the fixed block is installed between first parallel connection 32 and first stand 31, first spandrel girder 33 passes through the bolt to be installed at the top of first stand 31, steel fulcrum 71 passes through the bolt to be installed on steel fulcrum 71, the base 30 hoist and mount is at the top of foling section 10 avris, jack 72 sets up the top at first spandrel girder 33, install steel anchor beam 50 in the inboard of steel fulcrum 71 top spacing steel sheet 73, first spandrel girder 33 top jack 72 is with the steel anchor beam 50 of bottommost, according to the actual height that every layer of steel anchor beam 50 needs, select the second stand 41 and the landing leg 42 of suitable height, then select the number of second parallel connection 43 according to the length of second stand 41 and landing leg 42 at this moment, place second stand 41 in the constant head 60 at steel beam 50 top, the section of landing leg 42 is fixed on the top of corresponding layer of anchor beam 20, the steel anchor beam 50 is carried out to the actual height of second spandrel girder 50, the steel jack 50 is carried out to the actual height of each layer of steel anchor beam 50 is required to the second jack 50, the concrete is carried out to the second roof beam 50 of the actual height of jack 50 is adjusted to the required, every layer of the steel anchor beam is required to be moved, the actual height is required to the second spandrel girder 50.
It will be apparent to those skilled in the art that various modifications and variations can be made to the present application without departing from the spirit or scope of the application. Thus, it is intended that the present application also include such modifications and alterations insofar as they come within the scope of the appended claims or the equivalents thereof.
The foregoing is only a preferred embodiment of the present application, but the scope of the present application is not limited thereto, and any person skilled in the art should be able to apply equivalents and modifications according to the technical scheme and the concept of the present application within the scope of the present application.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202422430601.8U CN223176589U (en) | 2024-10-09 | 2024-10-09 | Side cable steel anchor beam temporary positioning support of tower column on A-shaped bridge tower |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202422430601.8U CN223176589U (en) | 2024-10-09 | 2024-10-09 | Side cable steel anchor beam temporary positioning support of tower column on A-shaped bridge tower |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN223176589U true CN223176589U (en) | 2025-08-01 |
Family
ID=96532628
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202422430601.8U Active CN223176589U (en) | 2024-10-09 | 2024-10-09 | Side cable steel anchor beam temporary positioning support of tower column on A-shaped bridge tower |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN223176589U (en) |
-
2024
- 2024-10-09 CN CN202422430601.8U patent/CN223176589U/en active Active
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN112609578A (en) | Method for mounting steel truss girder at top section of bridge pier of cable-stayed bridge | |
| CN116378466A (en) | Temporary fixing device for truss and construction method for steel structure space pipe truss | |
| CN113699887A (en) | Polygonal steel arch rib assembling and positioning device and using method thereof | |
| CN1736848A (en) | Large-scale structure integral hositing device and method | |
| CN115354688B (en) | Combined device for installing prefabricated platform structure and construction method | |
| CN206722428U (en) | A kind of building roof lighting Zhongting steel construction jacking apparatus | |
| CN214740171U (en) | Ancient building wall body hoist and mount migration device | |
| CN222758738U (en) | Cable-stayed bridge main tower bracket steel anchor beam construction structure | |
| CN103343626B (en) | The T-shaped support slide installation method of template Elements of Space Grid Truss and structure thereof | |
| CN117107584B (en) | Construction method of temporary construction channel based on shore-based high-pile wharf | |
| CN218714838U (en) | Self-lifting heavy-load construction platform | |
| CN219471494U (en) | Construction platform capable of lifting and horizontally moving | |
| JP3038154B2 (en) | Overhang work equipment | |
| CN112031370A (en) | Ceiling installation equipment and construction method thereof | |
| CN217710349U (en) | A jacking-slip system for bridge construction | |
| CN115929081A (en) | Temporary support and unloading device for steel truss column top | |
| CN107217669B (en) | Pile pulling equipment and its rapid movement method | |
| CN215166585U (en) | Quick connecting device without beam arch | |
| CN223176590U (en) | A temporary positioning bracket for the steel anchor beam of the upper tower column of an A-shaped bridge tower | |
| CN220167602U (en) | Supporting system for vertical assembly of roof herringbone box girder | |
| CN112681526A (en) | Jacking and installing system and method for large-span steel structure | |
| CN222084130U (en) | Steel construction inclined tube post returns top strutting arrangement | |
| CN222225825U (en) | Fixed jacking device of comprehensive building concrete spreader | |
| CN220100799U (en) | Support frame uninstallation device of large-span steel construction vestibule | |
| CN219973855U (en) | Climbing frame jump layer lifting device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |